Federal Register / Vol. 71, No. 232 / Monday, December 4, 2006 / Notices

WGC is collectively owned by the towns

of Rainelle, Rupert, and Quinwood, and

its mission is to provide economic

development for the area through the

construction and operation of the

proposed facility.

The main focus of the WGC CoProduction Facility Project is the

construction and operation of the 98

MWe generating plant that utilizes the

technologies described in Section 2.3 of

the Draft Environmental Impact

Statement. However, there are several

unique and important aspects of the

project that extend beyond the

construction and operation of the power

plant. In addition to generating power

for the national grid and demonstrating

the inverted cyclone technology, the

proposed plant is intended to use coal

refuse as its primary fuel source, to

apply potential waste streams to

beneficial uses, and to serve as an

economic catalyst for the region by

providing an anchor tenant for a

planned industrial park (the ‘‘EcoPark’’)

to be located in Rainelle. As a result,

there are connected actions associated

with the excavation and reclamation of

the proposed coal refuse piles (e.g.,

beneficiation of the coal refuse by a

third party), the additional industrial

activities that may occur with the

project (e.g., potential production of

building products from the cement), and

potential future commercial and

industrial development that are

intended to occur as a result of the

plant. These additional project aspects

are not integral to the DOE decision on

whether to provide cost-shared funding

to demonstrate the clean coal

technologies of interest.

Under the No Action Alternative,

DOE would not provide cost-shared

funding to demonstrate the CoProduction Facility Project. Although

WGC could proceed to implement the

proposed project in spite of DOE’s No

Action Alternative, it is unlikely that

this project would be completed

successfully without DOE funding

support. The No Action alternative

would not involve new construction,

new discharges, or changes in land or

water uses in the planning area. Because

this alternative would not involve

introducing new emission sources, no

impact on the air quality, either locally

or regionally, is expected. Aesthetic and

scenic conditions, as well as surface and

ground water, would remain

unchanged. The No Action alternative

would not contribute to the goal of the

CCPI program, which is to accelerate

commercial deployment of advanced

technologies that provide the United

States with clean, reliable, and

affordable energy.

VerDate Aug<31>2005

11:51 Dec 01, 2006

Jkt 211001

Availability of the Draft EIS

Copies of this Draft EIS have been

distributed to Members of Congress,

Federal, State, and local officials, and

agencies, organizations and individuals

who may be interested or affected. This

Draft EIS will be available on the

Internet at: http://www.eh.doe.gov/

nepa/. Additional copies can also be

requested by telephone at: 304–285–

5460, or (800) 432–8330, x5460. Copies

of the Draft EIS are also available for

public review at the Greenbrier County

Public Library, 301 Courtney Drive,

Lewisburg, West Virginia, and at the

Rainelle Municipal Public Library, 312

7th Street, Rainelle, West Virginia.

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible online at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Comment Date: 5 p.m. Eastern Time

on December 11, 2006.

Issued in Washington, DC, on November

28, 2006.

Mark J. Matarrese,

Director, Office of Environment, Security,

Safety and Health, Office of Fossil Energy.

[FR Doc. E6–20435 Filed 12–1–06; 8:45 am]

Magalie R. Salas,

Secretary.

[FR Doc. E6–20469 Filed 12–1–06; 8:45 am]

BILLING CODE 6450–01–P

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

Federal Energy Regulatory

Commission

[Docket No. TX07–1–000]

[Docket No. RP07–74–000]

Brazos Electric Power Cooperative,

Inc.; Notice of Filing

Dauphin Island Gathering Partners;

Notice of Proposed Changes in FERC

Gas Tariff

November 27, 2006.

Take notice that on October 13, 2006

and amended on November 21, 2006,

Brazos Electric Power Cooperative, Inc.

filed an application for an order

directing a physical interconnection of

facilities and transmission services

under sections 210, 211 and 212 of the

Federal Power Act.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211, 385.214).

Protests will be considered by the

Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed on or before the

comment date. On or before the

comment date, it is not necessary to

serve motions to intervene or protests

on persons other than the Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

PO 00000

Frm 00013

Fmt 4703

Sfmt 4703

November 24, 2006.

Take notice that on November 20,

2006, Dauphin Island Gathering

Partners (Dauphin Island) tendered for

filing as part of its FERC Gas Tariff, First

Revised Volume No. 1, the revised tariff

sheets listed below to become effective

December 21, 2006:

First Revised Sheet No. 5

First Revised Sheet No. 33

Third Revised Sheet No. 50

First Revised Sheet No. 89

Third Revised Sheet No. 115

First Revised Sheet No. 284

Second Revised Sheet No. 286

Second Revised Sheet No. 315

First Revised Sheet No. 342

First Revised Sheet No. 344

First Revised Sheet No. 358

Dauphin Island states that these tariff

sheets reflect numerous housekeeping

changes to Dauphin Island’s tariff.

Dauphin Island states that copies of

the filing are being served

contemporaneously on its customers

and other interested parties.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211 and

385.214). Protests will be considered by

E:\FR\FM\04DEN1.SGM

04DEN1

Federal Register / Vol. 71, No. 232 / Monday, December 4, 2006 / Notices

the Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed in accordance

with the provisions of Section 154.210

of the Commission’s regulations (18 CFR

154.210). Anyone filing an intervention

or protest must serve a copy of that

document on the Applicant. Anyone

filing an intervention or protest on or

before the intervention or protest date

need not serve motions to intervene or

protests on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible online at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–20464 Filed 12–1–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. CP05–413–004]

East Tennessee Natural Gas, LLC;

Notice of Supplemental Filing

mstockstill on PROD1PC61 with NOTICES

November 24, 2006.

Take notice that on November 17,

2006, East Tennessee Natural Gas, LLC

(East Tennessee) tendered for filing as

part of its FERC Gas Tariff, Third

Revised Volume No. 1, Substitute

Original Sheet No. 21A to be effective

October 29, 2006.

East Tennessee states that it is

supplementing its filing approved by

the Commission on September 15, 2006,

VerDate Aug<31>2005

11:51 Dec 01, 2006

Jkt 211001

in the captioned docket with the revised

tariff sheet in order to reflect the

reduced 2006 ACA unit charge in its

rates for lateral service under Rate

Schedules FT–L and IT–L.

East Tennessee states that copies of its

filing have been mailed to all affected

customers and interested state

commissions, as well as all parties on

the Commission’s official service list in

this proceeding.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211 and

385.214). Protests will be considered by

the Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed in accordance

with the provisions of Section 154.210

of the Commission’s regulations (18 CFR

154.210). Anyone filing an intervention

or protest must serve a copy of that

document on the Applicant. Anyone

filing an intervention or protest on or

before the intervention or protest date

need not serve motions to intervene or

protests on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible online at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–20461 Filed 12–1–06; 8:45 am]

BILLING CODE 6717–01–P

PO 00000

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket Nos. CP05–413–003, RP97–13–027

and PA05–63–003]

East Tennessee Natural Gas, LLC;

Notice of Compliance Filing

November 24, 2006.

Take notice that on November 15,

2006, East Tennessee Natural Gas, LLC

(East Tennessee) tendered for filing as

part of its FERC Gas Tariff, Third

Revised Volume No. 1, the tariff sheets

listed on Appendix A to the filing,

which the effective date of the tariff

sheets is October 29, 2006.

East Tennessee states that the filing is

being made in compliance with the

Commission orders issued on

September 15, 2006 and October 4, 2006

in Docket Nos. CP05–413–001 and

RP97–13–025.

Any person desiring to protest this

filing must file in accordance with Rule

211 of the Commission’s Rules of

Practice and Procedure (18 CFR

385.211). Protests to this filing will be

considered by the Commission in

determining the appropriate action to be

taken, but will not serve to make

protestants parties to the proceeding.

Such protests must be filed on or before

the date as indicated below. Anyone

filing a protest must serve a copy of that

document on all the parties to the

proceeding.

The Commission encourages

electronic submission of protests in lieu

of paper using the ‘‘eFiling’’ link at

http://www.ferc.gov. Persons unable to

file electronically should submit an

original and 14 copies of the protest to

the Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426.

This filing is accessible online at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Protest Date: 5 p.m. Eastern Time on

December 8, 2006.

Magalie R. Salas,

Secretary.

[FR Doc. E6–20465 Filed 12–1–06; 8:45 am]

BILLING CODE 6717–01–P

Frm 00014

Fmt 4703

Sfmt 4703

70373

E:\FR\FM\04DEN1.SGM

04DEN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.