Federal Register / Vol. 72, No. 54 / Wednesday, March 21, 2007 / Notices

Agency decision

Ask Donna

What actually matters in this document.

Text

13270

Federal Register / Vol. 72, No. 54 / Wednesday, March 21, 2007 / Notices

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed in accordance

with the provisions of Section 154.210

of the Commission’s regulations (18 CFR

154.210). Anyone filing an intervention

or protest must serve a copy of that

document on the Applicant. Anyone

filing an intervention or protest on or

before the intervention or protest date

need not serve motions to intervene or

protests on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Philis J. Posey,

Acting Secretary.

[FR Doc. E7–5126 Filed 3–20–07; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. ER07–522–000]

Old Trail Wind Farm, LLC; Notice of

Issuance of Order

jlentini on PROD1PC65 with NOTICES

March 15, 2007.

Old Trail Wind Farm, LLC (Old Trail)

filed an application for market-based

rate authority, with an accompanying

rate schedule. The proposed marketbased rate schedule provides for the sale

of energy, capacity and ancillary

services at market-based rates. Old Trail

also requested waivers of various

Commission regulations. In particular,

Old Trail requested that the

Commission grant blanket approval

under 18 CFR part 34 of all future

VerDate Aug<31>2005

17:08 Mar 20, 2007

Jkt 211001

issuances of securities and assumptions

of liability by Old Trail.

On March 15, 2007, pursuant to

delegated authority, the Director,

Division of Tariffs and Market

Development—West, granted the

requests for blanket approval under Part

34. The Director’s order also stated that

the Commission would publish a

separate notice in the Federal Register

establishing a period of time for the

filing of protests. Accordingly, any

person desiring to be heard or to protest

the blanket approvals of issuances of

securities or assumptions of liability by

Old Trail should file a motion to

intervene or protest with the Federal

Energy Regulatory Commission, 888

First Street, NE., Washington, DC 20426,

in accordance with Rules 211 and 214

of the Commission’s Rules of Practice

and Procedure. 18 CFR 385.211, 385.214

(2004).

Notice is hereby given that the

deadline for filing motions to intervene

or protest is April 16, 2007.

Absent a request to be heard in

opposition by the deadline above, Old

Trail is authorized to issue securities

and assume obligations or liabilities as

a guarantor, indorser, surety, or

otherwise in respect of any security of

another person; provided that such

issuance or assumption is for some

lawful object within the corporate

purposes of Old Trail, compatible with

the public interest, and is reasonably

necessary or appropriate for such

purposes.

The Commission reserves the right to

require a further showing that neither

public nor private interests will be

adversely affected by continued

approvals of Old Trail’s issuance of

securities or assumptions of liability.

Copies of the full text of the Director’s

Order are available from the

Commission’s Public Reference Room,

888 First Street, NE., Washington, DC

20426. The Order may also be viewed

on the Commission’s Web site at

http://www.ferc.gov, using the eLibrary

link. Enter the docket number excluding

the last three digits in the docket

number filed to access the document.

Comments, protests, and interventions

may be filed electronically via the

internet in lieu of paper. See, 18 CFR

385.2001(a)(1)(iii) and the instructions

on the Commission’s Web site under the

‘‘e-Filing’’ link. The Commission

strongly encourages electronic filings.

Philis J. Posey,

Acting Secretary.

[FR Doc. E7–5124 Filed 3–20–07; 8:45 am]

BILLING CODE 6717–01–P

PO 00000

Frm 00035

Fmt 4703

Sfmt 4703

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. CP07–99–000]

Southern Star Central Gas Pipeline,

Inc.; Notice of Request Under Blanket

Authorization

March 15, 2007.

Take notice that on March 9, 2007,

Southern Star Central Gas Pipeline, Inc.

(Southern Star), 4700 Highway 56,

Owensboro, Kentucky 42301, filed in

Docket No. CP07–99–000, an

application pursuant to Sections

157.205 and 157.208 of the

Commission’s Regulations under the

Natural Gas Act (NGA) as amended, to

construct and operate approximately

14.5 miles of 20-inch diameter pipeline

in Woods County, Oklahoma, under

Southern Star’s blanket certificate

issued in Docket No. CP82–479–000, all

as more fully set forth in the application

which is on file with the Commission

and open to the public for inspection.

Southern Star’s proposed pipeline

would serve as a new natural gas supply

lateral (Waynoka Gas Supply Lateral) for

Southern Star and its customers. The

Waynoka Gas Supply Lateral would

enable Southern Star to deliver

processed gas originating from

Anadarko Petroleum Corporation’s

(Anadarko) Waynoka Gas Processing

Plant to an interconnection to be built

on Southern Star’s 26-inch diameter

Straight Blackwell mainline in Woods

County. Southern Star estimates that it

would cost $11,200,000 to construct the

proposed Waynoka Gas Supply Lateral.

Any questions concerning this

application may be directed to David N.

Roberts, Manager of Regulatory Affairs,

Southern Star Central Gas Pipeline, Inc.,

P.O. Box 20010, Owensboro, Kentucky

42304, or telephone 270–852–4654.

This filing is available for review at

the Commission or may be viewed on

the Commission’s Web site at http://

www.ferc.gov, using the ‘‘eLibrary’’ link.

Enter the docket number excluding the

last three digits in the docket number

filed to access the document. For

assistance, please contact FERC Online

Support at FERC

OnlineSupport@ferc.gov or call toll-free

at (866) 206–3676, or, for TTY, contact

(202) 502–8659. Comments, protests and

interventions may be filed electronically

via the Internet in lieu of paper. See, 18

CFR 385.2001(a)(1)(iii) and the

instructions on the Commission’s Web

site under the ‘‘e-Filing’’ link. The

Commission strongly encourages

intervenors to file electronically.

E:\FR\FM\21MRN1.SGM

21MRN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.