63294

Federal Register / Vol. 71, No. 209 / Monday, October 30, 2006 / Notices

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket Nos. ER06–1419–000, ER06–1419–

001]

MeadWestvaco Virginia Corporation;

Notice of Issuance of Order

sroberts on PROD1PC70 with NOTICES

October 19, 2006.

MeadWestvaco Virginia Corporation

(MeadWestvaco Virginia) filed an

application for market-based rate

authority, with an accompanying rate

schedule. The proposed market-based

rate schedule provides for the sale of

energy and capacity at market-based

rates. MeadWestvaco Virginia also

requested waivers of various

Commission regulations. In particular,

MeadWestvaco Virginia requested that

the Commission grant blanket approval

under 18 CFR part 34 of all future

issuances of securities and assumptions

of liability by MeadWestvaco Virginia.

On October 18, 2006, pursuant to

delegated authority, the Director,

Division of Tariffs and Market

Development—West, granted the

requests for blanket approval under part

34. The Director’s order also stated that

the Commission would publish a

separate notice in the Federal Register

establishing a period of time for the

filing of protests. Accordingly, any

person desiring to be heard or to protest

the blanket approvals of issuances of

securities or assumptions of liability by

MeadWestvaco Virginia should file a

motion to intervene or protest with the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426, in accordance with Rules 211

and 214 of the Commission’s Rules of

Practice and Procedure. 18 CFR 385.211,

385.214 (2004).

Notice is hereby given that the

deadline for filing motions to intervene

or protest is November 17, 2006.

Absent a request to be heard in

opposition by the deadline above,

MeadWestvaco Virginia is authorized to

issue securities and assume obligations

or liabilities as a guarantor, indorser,

surety, or otherwise in respect of any

security of another person; provided

that such issuance or assumption is for

some lawful object within the corporate

purposes of MeadWestvaco Virginia,

compatible with the public interest, and

is reasonably necessary or appropriate

for such purposes.

The Commission reserves the right to

require a further showing that neither

public nor private interests will be

adversely affected by continued

approvals of MeadWestvaco Virginia’s

VerDate Aug<31>2005

02:16 Oct 28, 2006

Jkt 211001

issuance of securities or assumptions of

liability.

Copies of the full text of the Director’s

Order are available from the

Commission’s Public Reference Room,

888 First Street, NE., Washington, DC

20426. The Order may also be viewed

on the Commission’s Web site at http://

www.ferc.gov, using the eLibrary link.

Enter the docket number excluding the

last three digits in the docket number

filed to access the document.

Comments, protests, and interventions

may be filed electronically via the

Internet in lieu of paper. See 18 CFR

385.2001(a)(1)(iii) and the instructions

on the Commission’s Web site under the

‘‘e-Filing’’ link. The Commission

strongly encourages electronic filings.

Magalie R. Salas,

Secretary.

[FR Doc. E6–18111 Filed 10–27–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket Nos. CP07–4–000; CP07–5–000;

CP07–6–000]

Mississippi Hub, L.L.C.; Notice of

Application

October 20, 2006.

On October 10, 2006, in Docket Nos.

CP07–4–000, CP07–5–000 and CP07–6–

000, Mississippi Hub, L.L.C. (MS HUB),

pursuant to section 7(c) of the Natural

Gas Act, as amended, and part 157,

subparts A and F, and part 284, subpart

G of the Federal Energy Regulatory

Commission’s (Commission)

regulations, filed requests for:

authorization to construct, own, and

operate the MS HUB Storage Project; a

Subpart F construction, operation and

abandonment blanket certificate (CP07–

5–000); and, a Subpart G transportation

blanket certificate (CP07–6–000). MS

HUB also seeks: approval of its pro

forma tariff; authorization to charge

market-based rates for the proposed

storage services; and, waiver of certain

Commission regulations. Further, MS

HUB asks that the Commission issue

requested authorizations by February

15, 2007 so that: construction may start

in spring 2007; initial storage injections

can commence in spring and summer of

2008; and, withdrawals can begin by

December 31, 2008. Start-up in this

timeframe also would coincide with

proposed in-service dates of certain Gulf

Coast region liquefied natural gas

import terminals.

PO 00000

Frm 00016

Fmt 4703

Sfmt 4703

The new, high-deliverability storage

facility would be located in Simpson

and Jefferson Davis Counties,

Mississippi. The facility would have

initial interconnections with two

interstate (Southern Natural Gas Co. and

Gulf South Pipeline) and one intrastate

(CrossTex Energy) gas pipeline systems.

Due to the sequential construction

process associated with the solution

mining of the two proposed caverns, MS

HUB requests that the Commission

authorize construction over a five-year

period.

Questions concerning the application

should be directed to by calling (281)

242–2381 or J. Gordon Pennington,

Attorney at Law, 2707 N. Kensington

St., Arlington, Virginia 22207 or at 703–

533–7638 or pennington5@verizon.net.

There are two ways to become

involved in the Commission’s review of

this project. First, any person wishing to

obtain legal status by becoming a party

to the proceedings for this project

should, on or before the comment date,

file with the Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426, a motion to

intervene in accordance with the

requirements of the Commission’s Rules

of Practice and Procedure (18 CFR

385.214 or 385.211) and the Regulations

under the NGA (18 CFR 157.10). A

person obtaining party status will be

placed on the service list maintained by

the Secretary of the Commission and

will receive copies of all documents

filed by the applicant and by all other

parties. A party must submit 14 copies

of filings made with the Commission

and must mail a copy to the applicant

and to every other party in the

proceeding. Only parties to the

proceeding can ask for court review of

Commission orders in the proceeding.

However, a person does not have to

intervene in order to have comments

considered.

The second way to participate is by

filing with the Secretary of the

Commission, as soon as possible, an

original and two copies of comments in

support of or in opposition to this

project. The Commission will consider

these comments in determining the

appropriate action to be taken, but the

filing of a comment alone will not serve

to make the filer a party to the

proceeding. The Commission’s rules

require that persons filing comments in

opposition to the project provide copies

of their protests only to the party or

parties directly involved in the protest.

Comments, protests and interventions

may be filed electronically via the

Internet in lieu of paper. See 18 CFR

385.2001(a) (1) (iii) and the instructions

on the Commission’s web site under the

E:\FR\FM\30OCN1.SGM

30OCN1

Federal Register / Vol. 71, No. 209 / Monday, October 30, 2006 / Notices

‘‘e-Filing’’ link at http://www.ferc.gov.

The Commission strongly encourages

intervenors to file electronically.

The Commission may issue a

preliminary determination on nonenvironmental issues prior to the

completion of its review of the

environmental aspects of the Projects.

This preliminary determination

typically considers such issues as the

need for the Project and its economic

effect on other pipelines in the area and

on land and communities.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Comment Date: November 9, 2006.

Magalie R. Salas,

Secretary.

[FR Doc. E6–18128 Filed 10–27–06; 8:45 am]

filing a protest must serve a copy of that

document on all the parties to the

proceeding.

The Commission encourages

electronic submission of protests in lieu

of paper using the ‘‘eFiling’’ link at

http://www.ferc.gov. Persons unable to

file electronically should submit an

original and 14 copies of the protest to

the Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–18102 Filed 10–27–06; 8:45 am]

BILLING CODE 6717–01–P

63295

before the intervention or protest date

need not serve motions to intervene or

protests on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–18125 Filed 10–27–06; 8:45 am]

BILLING CODE 6717–01–P

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. RP07–25–000]

Federal Energy Regulatory

Commission

[Docket No. RP06–478–001]

Mojave Pipeline Company; Notice of

Tariff Filing

[Docket No. CP07–3–000]

Mojave Pipeline Company; Notice of

Filing

October 20, 2006.

Natural Gas Pipeline Company of

America; Notice of Application

sroberts on PROD1PC70 with NOTICES

October 18, 2006.

Take notice that on October 12, 2006,

Mojave Pipeline Company (Mojave)

tendered for filing as part of its FERC

Gas Tariff, Second Revised Volume No.

1, Sub Fifteenth Revised Sheet No. 11,

to become effective October 1, 2006.

Mojave states that the tariff sheet is

being filed to update the total and

subtotal columns on the Statement of

Rates after the decrease in the annual

charge adjustment.

Any person desiring to protest this

filing must file in accordance with Rule

211 of the Commission’s Rules of

Practice and Procedure (18 CFR

385.211). Protests to this filing will be

considered by the Commission in

determining the appropriate action to be

taken, but will not serve to make

protestants parties to the proceeding.

Such protests must be filed in

accordance with the provisions of

Section 154.210 of the Commission’s

regulations (18 CFR 154.210). Anyone

VerDate Aug<31>2005

02:16 Oct 28, 2006

Jkt 211001

Take notice that on October 17, 2006,

Mojave Pipeline Company (Mojave)

tendered for filing as part of its FERC

Gas Tariff, Second Revised Volume No.

1, First Revised Sheet No. 213, to

become effective November 17, 2006.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211 and

385.214). Protests will be considered by

the Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed in accordance

with the provisions of Section 154.210

of the Commission’s regulations (18 CFR

154.210). Anyone filing an intervention

or protest must serve a copy of that

document on the Applicant. Anyone

filing an intervention or protest on or

PO 00000

Frm 00017

Fmt 4703

Sfmt 4703

October 24, 2006.

Take notice that on October 10, 2006,

Natural Gas Pipeline Company of

America (Natural), 747 East 22nd Street,

Lombard, Illinois 60148, filed an

application under sections 7(c) and 7(b)

of the Natural Gas Act seeking authority

to: (i) Construct and operate 4.43 miles

of 36-inch diameter pipe that will

become part of Natural’s Louisiana Line

No. 2 Cameron Parish, Louisiana; (ii)

replace three 12-inch meter runs and

meters at the Sabine Henry Hub Plant in

Vermilion Parish, Louisiana with three

8-inch turbine meters; (iii) install one

10,000 hp electric compressor unit and

appurtenant equipment at Compressor

Station (CS) 302 in Montgomery County,

Texas; (iv) add one Solar Taurus 60 gas

turbine compressor unit and

appurtenant equipment, including

expanded platform space, and re-wheel

of one existing 4,200 hp gas compressor

unit at CS 342 in Cameron Parish,

Louisiana; (v) replace three gas fired

E:\FR\FM\30OCN1.SGM

30OCN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.