sroberts on PROD1PC70 with NOTICES

Agency decision

Ask Donna

What actually matters in this document.

Text

sroberts on PROD1PC70 with NOTICES

Federal Register / Vol. 71, No. 127 / Monday, July 3, 2006 / Notices

any resource agency, Indian Tribe, or

person believes that an additional

scientific study should be conducted in

order to form an adequate factual basis

for a complete analysis of the

application on its merit, the resource

agency, Indian Tribe, or person must file

a request for a study with the

Commission not later than 60 days from

the date of filing of the application, and

serve a copy of the request on the

applicant.

l. Deadline for filing additional study

requests and requests for cooperating

agency status: August 11, 2006.

All documents (original and eight

copies) should be filed with: Magalie R.

Salas, Secretary, Federal Energy

Regulatory Commission, 888 First

Street, NE., Washington, DC 20426.

Additional study requests and

requests for cooperating agency status

may be filed electronically via the

Internet in lieu of paper. The

Commission strongly encourages

electronic filings. See 18 CFR

385.2001(a)(1)(iii) and the instructions

on the Commission’s Web site (http://

www.ferc.gov) under the ‘‘eFiling’’ link.

m. This application is not ready for

environmental analysis at this time.

n. The Cushaw Project consists of the

following features: (1) A 1,550-foot-long

and 27-foot-high reinforced concrete

dam extending diagonally across the

James River; (2) a 138-acre reservoir at

a surface elevation of 656 feet mean sea

level; (3) an integral powerhouse with

the dam containing five generating units

with a total installed capacity of 7,500

kilowatts; (4) a 2.3–kV cable connecting

the powerhouse to the Cushaw

substation; and (5) appurtenant

facilities. The project is operated in a

run-of-river mode, and the average

annual electrical generation is

approximately 16,971,000

kilowatthours.

o. A copy of the application is

available for review at the Commission

in the Public Reference Room or may be

viewed on the Commission’s website at

http://www.ferc.gov using the

‘‘eLibrary’’ link. Enter the docket

number excluding the last three digits in

the docket number field to access the

document. For assistance, contact FERC

Online Support at

FERCOnlineSupport@ferc.gov or tollfree at 1–866–208–3676, or for TTY,

(202) 502–8659. A copy is also available

for inspection and reproduction at the

address in item h above.

You may also register online at

http://www.ferc.gov/docs-filing/

esubscription.asp to be notified via

email of new filings and issuances

related to this or other pending projects.

VerDate Aug<31>2005

17:12 Jun 30, 2006

Jkt 208001

For assistance, contact FERC Online

Support.

p. With this notice, we are initiating

consultation with the Virginia State

Historic Preservation Officer (SHPO), as

required by Section 106 of the National

Historic Preservation Act, and the

regulations of the Advisory Council on

Historic Preservation, 36 CFR 800.4.

q. Procedural schedule and final

amendments: The application will be

processed according to the following

Hydro Licensing Schedule. Revisions to

the schedule will be made as

appropriate. The Commission staff

proposes to issue one environmental

assessment rather than issue a draft and

final EA. Comments, terms and

conditions, recommendations,

prescriptions, and reply comments, if

any, will be addressed in an EA. Staff

intents to give at least 30 days for

entities to comment on the EA, and will

take into consideration all comments

received on the EA before final action is

taken on the license application.

Issue Deficiency or Acceptance Letter:

July 2006.

Issue Scoping Document 1 for

comments: August 2006.

Notice of application is ready for

environmental analysis: October 2006.

Notice of the availability of the EA:

February 2007.

Ready for Commission’s decision on

the application: June 2007.

Final amendments to the application

must be filed with the Commission no

later than 30 days from the issuance

date of the notice of ready for

environmental analysis.

Magalie R. Salas,

Secretary.

[FR Doc. E6–10331 Filed 6–30–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

Combined Notice of Filings #1

June 26, 2006.

Take notice that the Commission

received the following electric rate

filings.

Docket Numbers: ER91–569–033.

Applicants: Entergy Services Inc.

Description: Entergy Services, Inc on

behalf of Entergy Arkansas, Inc et al.

submits a non-material change in status

pursuant to requirements of Order 652.

Filed Date: 6/20/2006.

Accession Number: 20060623–0049.

Comment Date: 5 p.m. Eastern Time

on Tuesday, July 11, 2006.

PO 00000

Frm 00045

Fmt 4703

Sfmt 4703

37931

Docket Numbers: ER96–496–015;

ER99–14–012; ER99–4463–006.

Applicants: Northeast Utilities

Service Company.

Description: Northeast Utilities

submits certain notifications to the

Commission to reflect the acquisition by

Hess Corp of the competitive retail

businesses operated by Northeast

Utilities Enterprise, Inc’s subsidiaries.

Filed Date: 6/20/2006.

Accession Number: 20060623–0039.

Comment Date: 5 p.m. Eastern Time

on Tuesday, July 11, 2006.

Docket Numbers: ER97–2153–015;

ER02–556–007; ER00–2181–003.

Applicants: Amerada Hess

Corporation; Select Energy New York,

Inc.; Hess Energy, Inc.

Description: Select Energy New York,

Inc et al. submits a notice of nonmaterial change in status.

Filed Date: 6/20/2006.

Accession Number: 20060623–0045.

Comment Date: 5 p.m. Eastern Time

on Tuesday, July 11, 2006.

Docket Numbers: ER05–1089–003.

Applicants: Wisconsin Public Service

Corporation.

Description: Wisconsin Public Service

Corp submits a settlement payment

report in compliance with the

Commission’s 6/2/06 order.

Filed Date: 6/19/2006.

Accession Number: 20060619–5023.

Comment Date: 5 p.m. Eastern Time

on Monday, July 10, 2006.

Docket Numbers: ER05–1508–002.

Applicants: Midwest Independent

Transmission System Operator, Inc.

Description: Midwest Independent

Transmission System Operator, Inc.

submits its Large Generator

Interconnection Agreement with Power

Partners Midwest, LLC and Interstate

Power and Light Company.

Filed Date: 6/21/2006.

Accession Number: 20060623–0056.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–255–003.

Applicants: Midwest Independent

Transmission System Operator, Inc.

Description: Midwest Independent

Transmission System Operator, Inc.

submits a Large Generator

Interconnection Agreement with

FirstEnergy Generation Corp and

American Transmission System, Inc.

Filed Date: 6/21/2006.

Accession Number: 20060623–0057.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–714–001.

Applicants: Midwest Independent

Transmission System.

Description: Midwest Independent

Transmission System Operator, Inc

E:\FR\FM\03JYN1.SGM

03JYN1

sroberts on PROD1PC70 with NOTICES

37932

Federal Register / Vol. 71, No. 127 / Monday, July 3, 2006 / Notices

submits its Large Generator

Interconnection Agreement with

FirstEnergy Nuclear Operating Company

and American Transmission System,

Inc.

Filed Date: 6/21/2006.

Accession Number: 20060623–0040.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–836–001.

Applicants: Pacific Gas & Electric

Company.

Description: Pacific Gas and Electric

Co submits a supplement to its 4/4/06

filing of Supplemental Balancing

Account Revisions.

Filed Date: 6/22/2006.

Accession Number: 20060623–0085.

Comment Date: 5 p.m. Eastern Time

on Thursday, July 13, 2006.

Docket Numbers: ER06–1046–002.

Applicants: Western Kentucky Energy

Corp.; LG&E Energy Marketing Inc.;

Louisville Gas & Electric Company;

Kentucky Utilities Company.

Description: LG&E Energy Marketing,

Inc et al. submit updated information to

inform FERC of certain recent

developments in a proceeding pending

before the Kentucky Public Service

Commission etc.

Filed Date: 6/21/2006.

Accession Number: 20060623–0051.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–1055–001.

Applicants: Newmont Nevada Energy

Investment, LLC.

Description: Newmont Nevada Energy

Investment LLC submits revised tariff

sheets to its Electric Tariff, Original

Volume 1.

Filed Date: 6/21/2006.

Accession Number: 20060623–0047.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–1098–001.

Applicants: JJR Power LLC.

Description: JJR Power LLC submits

an amended Petition of Acceptance of

Initial Tariff, Waiver and Blanket

Authority.

Filed Date: 6/21/2006.

Accession Number: 20060623–0041.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

Docket Numbers: ER06–1163–000.

Applicants: American Electric Power

Service Corporation.

Description: The American Electric

Power Service Corp, on behalf of Ohio

Power Co et al submits an

interconnection agreement with Duke

Energy.

Filed Date: 6/21/2006.

Accession Number: 20060623–0042.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 12, 2006.

VerDate Aug<31>2005

17:12 Jun 30, 2006

Jkt 208001

Docket Numbers: ER06–1164–000.

Applicants: New York State Electric &

Gas Corporation.

Description: New York State Electric

& Gas Corp submits a supplement to

Rate Schedule 200—Facilities

Agreement with New York Power

Authority.

Filed Date: 6/19/2006.

Accession Number: 20060623–0048.

Comment Date: 5 p.m. Eastern Time

on Monday, July 10, 2006.

Docket Numbers: ER06–1165–000.

Applicants: Southern Company

Services, Inc.

Description: Southern Company

Services, Inc on behalf Alabama Power

Co et al submits Revision 3 to the

Agreement for Network Integration

Transmission Service for Tennessee

Valley Authority.

Filed Date: 6/22/2006.

Accession Number: 20060623–0052.

Comment Date: 5 p.m. Eastern Time

on Thursday, July 13, 2006.

Docket Numbers: ER06–1166–000.

Applicants: Liberty Power Nevada

LLC.

Description: Liberty Power Nevada,

LLC submits its petition for acceptance

of initial rate schedule (FERC Electric

Rate Schedule No. 1), waivers and

blanket authority.

Filed Date: 6/22/2006.

Accession Number: 20060626–0163.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–1167–000.

Applicants: Liberty Power New

Hampshire LLC.

Description: Liberty Power New

Hampshire, LLC submits a petition for

acceptance of its initial rate schedule

(FERC Electric Rate Schedule No. 1),

waivers and blanket authority.

Filed Date: 6/22/2006.

Accession Number: 20060626–0161.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–1168–000.

Applicants: Liberty Power

Pennsylvania LLC.

Description: Liberty Power

Pennsylvania, LLC submits a petition of

its initial rate schedule (FERC Electric

Rate Schedule 1), waivers and blanket

authority.

Filed Date: 6/22/2006.

Accession Number: 20060626–0162.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–1169–000.

Applicants: Moses Lake Generating

LLC.

Description: Moses Lake Generating,

LLC submits a notice of cancellation of

its market-based rate tariff, FERC

Electric Tariff, Original Volume No. 1.

PO 00000

Frm 00046

Fmt 4703

Sfmt 4703

Filed Date: 6/23/2006.

Accession Number: 20060626–0149.

Comment Date: 5 p.m. Eastern Time

on Friday, July 14, 2006.

Docket Numbers: ER06–1170–000.

Applicants: Liberty Power Ohio LLC.

Description: Liberty Power Ohio, LLC

submits a petition for acceptance of its

initial rate schedule (FERC Electric Rate

Schedule 1) waivers and blanket

authority.

Filed Date: 6/22/2006.

Accession Number: 20060626–0150.

Comment Date: 5 p.m. Eastern Time

on Monday, July 3, 2006.

Docket Numbers: ER06–1171–000.

Applicants: Southern California

Edison Company.

Description: Southern California

Edison Co submits an Interconnection

Facilities Study Agreement with the

Nevada Hydro Co Inc.

Filed Date: 6/23/2006.

Accession Number: 20060626–0158.

Comment Date: 5 p.m. Eastern Time

on Friday, July 14, 2006.

Docket Numbers: ER06–1172–000.

Applicants: Liberty Power California

LLP.

Description: Liberty Power California,

LLP submits a petition for acceptance of

its initial rate schedule (FERC Electric

Rate Schedule 1), waivers and blanket

authority.

Filed Date: 6/23/2006.

Accession Number: 20060626–0160.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 5, 2006.

Docket Numbers: ER06–1173–000.

Applicants: Liberty Power

Connecticut LLP.

Description: Liberty Power

Connecticut, LLP submits a petition for

acceptance of its initial rate schedule

(FERC Electric Tariff 1), waivers and

blanket authority.

Filed Date: 6/23/2006.

Accession Number: 20060626–0159.

Comment Date: 5 p.m. Eastern Time

on Wednesday, July 5, 2006.

Docket Numbers: ER06–1174–000.

Applicants: New York Independent

System Operator, Inc.

Description: New York Independent

System Operator, Inc submits revised

tariff to reinstate inadvertently delete

language needed to determine sanctions

for failure to meet ICAP Bidding

requirements.

Filed Date: 6/23/2006.

Accession Number: 20060626–0146.

Comment Date: 5 p.m. Eastern Time

on Friday, July 14, 2006.

Any person desiring to intervene or to

protest in any of the above proceedings

must file in accordance with Rules 211

and 214 of the Commission’s Rules of

E:\FR\FM\03JYN1.SGM

03JYN1

Federal Register / Vol. 71, No. 127 / Monday, July 3, 2006 / Notices

Practice and Procedure (18 CFR 385.211

and 385.214) on or before 5 p.m. Eastern

time on the specified comment date. It

is not necessary to separately intervene

again in a subdocket related to a

compliance filing if you have previously

intervened in the same docket. Protests

will be considered by the Commission

in determining the appropriate action to

be taken, but will not serve to make

protestants parties to the proceeding.

Anyone filing a motion to intervene or

protest must serve a copy of that

document on the Applicant. In reference

to filings initiating a new proceeding,

interventions or protests submitted on

or before the comment deadline need

not be served on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper, using the

FERC Online links at http://

www.ferc.gov. To facilitate electronic

service, persons with Internet access

who will eFile a document and/or be

listed as a contact for an intervenor

must create and validate an

eRegistration account using the

eRegistration link. Select the eFiling

link to log on and submit the

intervention or protests.

Persons unable to file electronically

should submit an original and 14 copies

of the intervention or protest to the

Federal Energy Regulatory Commission,

888 First St. NE., Washington, DC

20426.

The filings in the above proceedings

are accessible in the Commission’s

eLibrary system by clicking on the

appropriate link in the above list. They

are also available for review in the

Commission’s Public Reference Room in

Washington, DC. There is an

eSubscription link on the Web site that

enables subscribers to receive e-mail

notification when a document is added

to a subscribed dockets(s). For

assistance with any FERC Online

service, please e-mail

FERCOnlineSupport@ferc.gov. or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–10328 Filed 6–30–06; 8:45 am]

sroberts on PROD1PC70 with NOTICES

BILLING CODE 6717–01–P

VerDate Aug<31>2005

17:12 Jun 30, 2006

Jkt 208001

ENVIRONMENTAL PROTECTION

AGENCY

[ER–FRL–6676–8]

Environmental Impact Statements and

Regulations; Availability of EPA

Comments

Availability of EPA comments

prepared pursuant to the Environmental

Review Process (ERP), under section

309 of the Clean Air Act and section

102(2)(c) of the National Environmental

Policy Act as amended. Requests for

copies of EPA comments can be directed

to the Office of Federal Activities at

202–564–7167. An explanation of the

ratings assigned to draft environmental

impact statements (EISs) was published

in FR dated April 7, 2006 (71 FR 17845).

Draft EISs

EIS No. 20050540, ERP No. D–FAA–

C51029–00, New York/New Jersey/

Philadelphia Metropolitan Area

Airspace Redesign Project, To

Increase the Efficiency and Reliability

of the Airspace Structure and Air

Traffic Control System, NY, NJ and

PA.

Summary: EPA expressed

environmental concern about

cumulative impacts. EPA also requested

information on outreach to

environmental justice communities

impacted by noise and mitigation/

minimization of noise exposure to those

communities. Rating EC2.

EIS No. 20060154, ERP No. D–NPS–

E65081–FL, Castillo de San Marcos

National Monument, General

Management Plan, Implementation,

City of St. Augustine, St. Johns

County, FL.

Summary: EPA does not object to the

proposed action. Rating LO.

EIS No. 20060170, ERP No. D–COE–

K39097–AZ, Rio Salado Oeste Project,

Ecosystem Restoration along the Salt

River, City of Phoenix, Maricopa

County, AZ.

Summary: EPA supports the

restoration project and requested more

information regarding adaptive

management plans. Rating LO.

EIS No. 20060050, ERP No. DR–COE–

E34031–FL, Central and Southern

Florida Project, Revised Draft

Integrated Project Implementation

Report, Comprehensive Restoration

Plan, Implementation, Everglades

Agricultural Area Storage Reservoirs,

Palm Beach County, FL.

Summary: While EPA fully supports

the construction and operation of the

proposed project, it expressed

environmental concerns about potential

PO 00000

Frm 00047

Fmt 4703

Sfmt 4703

37933

water quality impacts, and requested

that additional water quality

information be included in the Final

EIS. Rating EC1.

Final EISs

EIS No. 20060156, ERP No. F–COE–

J39034–MT, Upper Columbia

Alternative Flood Control and Fish

Operations, Implementation, Libby

and Hungry Horse Dams, Columbia

River Basin, MT.

Summary: EPA supports the basic

goal of operating Libby and Hungry

Horse Dams to simulate a more natural

hydro graph for aquatic ecosystem

benefits. EPA also supports the Flow

Implementation Protocol being

developed by the Corps and other

stakeholders. However, EPA expressed

environmental concerns about the

potential for the new Libby Dam to

result in increased total dissolved gas

levels in the Kootenai River that would

exceed the state of Montana’s Water

Quality Standards.

EIS No. 20060157, ERP No. F–IBR–

K39076–00, Navajo Reservoir

Operations, Proposed Operational

Changes to Navajo Dam and

Reservoir, Endangered Species Act

(ESA), Related Flow

Recommendations, Navajo Unit-San

Juan River, NM, CO and UT.

Summary: EPA supports the

modification of operation of Navajo

Dam to meet flow recommendations for

the sucker and pikeminnow, and

requested additional commitments to

mitigation and monitoring for water

quality impacts.

EIS No. 20060196, ERP No. F–COE–

E34031–FL, South Florida Water

Management District (SFWMD),

Proposes Construction and Operation

Everglades Agricultural Area

Reservoir A–1 Project, Lake

Okeechobee, Palm Beach County, FL.

Summary: EPA continues to support

this element of the original selected

alternative as having reasonable and

feasible objectives while providing

sufficient environmental restoration

benefits; therefore, EPA does not object

to the proposed action.

EIS No. 20060225, ERP No. F–BLM–

K65293–NV, Sheep Complex, Big

Springs and Owyhee Grazing

Allotments Sensitive Bird Species

Project, Determine Impacts of

Livestock Grazing, Elko County, NV.

Summary: Modifications to the

selected alternative, such as using

phased grazing levels and the

implementation of monitoring and

adaptive management measures that

rely on ecosystem goals have addressed

E:\FR\FM\03JYN1.SGM

03JYN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.