Federal Register / Vol. 72, No. 157 / Wednesday, August 15, 2007 / Notices

Description: PowerGrid Systems Inc

submits a petition for acceptance of its

FERC Electric Tariff, Original Volume 1.

Filed Date: 08/06/2007.

Accession Number: 20070807–0135.

Comment Date: 5 p.m. Eastern Time

on Monday, August 27, 2007.

Docket Numbers: ER07–1251–000.

Applicants: Northern Maine

Independent System Administrator, Inc.

Description: Northern Maine

Independent System Administration,

Inc submits revisions to the NMISA

FERC Electric Tariff, Original Volume 1.

Filed Date: 08/03/2007.

Accession Number: 20070807–0136.

Comment Date: 5 p.m. Eastern Time

on Friday, August 24, 2007.

Docket Numbers: ER07–1252–000.

Applicants: Entergy Services, Inc.

Description: Entergy Services, Inc

acting as agent for Entergy Operating

Companies submits unexecuted First

Revised Transmission Service

Agreement between Entergy & American

Electric Power Service Corp.

Filed Date: 08/06/2007.

Accession Number: 20070807–0209.

Comment Date: 5 p.m. Eastern Time

on Monday, August 27, 2007.

Docket Numbers: ER07–1253–000.

Applicants: Delaware Municipal

Electric Corporation.

Description: Delaware Municipal

Electric Corporation, Inc submits FERC

Electric Tariff, Original Volume 1 &

supporting cost data.

Filed Date: 08/06/2007.

Accession Number: 20070807–0208.

Comment Date: 5 p.m. Eastern Time

on Monday, August 27, 2007.

Docket Numbers: ER07–1254–000.

Applicants: Midwest Independent

Transmission System Operator, Inc.

Description: Midwest Independent

Transmission System Operator Inc

submits proposed revisions to Articles

two & five & Appendices A & F of the

agreement of transmission facilities

owners.

Filed Date: 08/06/2007.

Accession Number: 20070807–0210.

Comment Date: 5p.m. Eastern Time

on Monday, August 27, 2007.

Take notice that the Commission

received the following electric securities

filings:

Docket Numbers: ES07–50–000.

Applicants: Monongahela Power

Company.

Description: Monongahela Power

Company submits application for

authorization under Section 204(A) of

the Federal Power Act to Issue

Securities under ES07–50.

Filed Date: 07/27/2007.

Accession Number: 20070809–0138.

Comment Date: 5 p.m. Eastern Time

on Friday, August 17, 2007.

VerDate Aug<31>2005

15:00 Aug 14, 2007

Jkt 211001

Docket Numbers: ES07–55–000.

Applicants: Entergy Nuclear

Palisades, LLC.

Description: Application Requesting

Rescission of Certain Section 204

Authorization and Request for Blanket

Authorization Under Part 34 for Entergy

Nuclear Palisades, LLC.

Filed Date: 08/02/2007.

Accession Number: 20070802–5055.

Comment Date: 5 p.m. Eastern Time

on Thursday, August 23, 2007.

Take notice that the Commission

received the following open access

transmission tariff filings:

Docket Numbers: OA07–80–000.

Applicants: MidAmerican Energy

Company.

Description: MidAmerican Energy

Company submits supplements to their

7/13/07 filing and submits pro forma

Second Revised Sheet 137 and 140 of

the Open Access Transmission Tariff.

Filed Date: 08/01/2007.

Accession Number: 20070802–0023.

Comment Date: 5 p.m. Eastern Time

on Wednesday, August 22, 2007.

Take notice that the Commission

received the following electric

reliability filings:

Docket Numbers: RR06–1–010.

Applicants: North American Electric

Reliability Corp.

Description: Compliance Filing of the

North American Electric Reliability

Corporation in Response to June 7, 2007

Order.

Filed Date: 08/06/2007.

Accession Number: 20070806–5027.

Comment Date: 5 p.m. Eastern Time

on Monday, August 27, 2007.

Any person desiring to intervene or to

protest in any of the above proceedings

must file in accordance with Rules 211

and 214 of the Commission’s Rules of

Practice and Procedure (18 CFR 385.211

and 385.214) on or before 5 p.m. Eastern

time on the specified comment date. It

is not necessary to separately intervene

again in a subdocket related to a

compliance filing if you have previously

intervened in the same docket. Protests

will be considered by the Commission

in determining the appropriate action to

be taken, but will not serve to make

protestants parties to the proceeding.

Anyone filing a motion to intervene or

protest must serve a copy of that

document on the Applicant. In reference

to filings initiating a new proceeding,

interventions or protests submitted on

or before the comment deadline need

not be served on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper, using the

FERC Online links at http://

www.ferc.gov. To facilitate electronic

PO 00000

Frm 00082

Fmt 4703

Sfmt 4703

service, persons with Internet access

who will eFile a document and/or be

listed as a contact for an intervenor

must create and validate an

eRegistration account using the

eRegistration link. Select the eFiling

link to log on and submit the

intervention or protests.

Persons unable to file electronically

should submit an original and 14 copies

of the intervention or protest to the

Federal Energy Regulatory Commission,

888 First St., NE., Washington, DC

20426.

The filings in the above proceedings

are accessible in the Commission’s

eLibrary system by clicking on the

appropriate link in the above list. They

are also available for review in the

Commission’s Public Reference Room in

Washington, DC. There is an

eSubscription link on the Web site that

enables subscribers to receive e-mail

notification when a document is added

to a subscribed dockets(s). For

assistance with any FERC Online

service, please e-mail

FERCOnlineSupport@ferc.gov or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Nathaniel J. Davis, Sr.,

Acting Secretary.

[FR Doc. E7–15990 Filed 8–14–07; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 82–000]

Alabama Power Company; Notice of

Authorization for Continued Project

Operation

August 8, 2007.

On July 28, 2005, Alabama Power

Company, licensee for the Mitchell

Hydroelectric Project, filed an

application for a new or subsequent

license pursuant to the Federal Power

Act (FPA) and the Commission’s

regulations thereunder. The Mitchell

Project is located on the Coosa River in

the state of Alabama.

The license for Project No. 82 was

issued for a period ending July 31, 2007.

Section 15(a)(1) of the FPA, 16 U.S.C.

808(a)(1), requires the Commission, at

the expiration of a license term, to issue

from year-to-year an annual license to

the then licensee under the terms and

conditions of the prior license until a

new license is issued, or the project is

otherwise disposed of as provided in

section 15 or any other applicable

section of the FPA. If the project’s prior

E:\FR\FM\15AUN1.SGM

15AUN1

Federal Register / Vol. 72, No. 157 / Wednesday, August 15, 2007 / Notices

license waived the applicability of

section 15 of the FPA, then, based on

section 9(b) of the Administrative

Procedure Act, 5 U.S.C. 558(c), and as

set forth at 18 CFR 16.21(a), if the

licensee of such project has filed an

application for a subsequent license, the

licensee may continue to operate the

project in accordance with the terms

and conditions of the license after the

minor or minor part license expires,

until the Commission acts on its

application. If the licensee of such a

project has not filed an application for

a subsequent license, then it may be

required, pursuant to 18 CFR 16.21(b),

to continue project operations until the

Commission issues someone else a

license for the project or otherwise

orders disposition of the project.

If the project is subject to section 15

of the FPA, notice is hereby given that

an annual license for Project No. 82 is

issued to Alabama Power Company, for

a period effective August 1, 2007

through July 31, 2008, or until the

issuance of a new license for the project

or other disposition under the FPA,

whichever comes first. If issuance of a

new license (or other disposition) does

not take place on or before July 31,

2008, notice is hereby given that,

pursuant to 18 CFR 16.18(c), an annual

license under section 15(a)(1) of the

FPA is renewed automatically without

further order or notice by the

Commission, unless the Commission

orders otherwise. If the project is not

subject to section 15 of the FPA, notice

is hereby given that Alabama Power

Company is authorized to continue

operation of the Mitchell Project until

such time as the Commission acts on its

application for a subsequent license.

Kimberly D. Bose,

Secretary.

[FR Doc. E7–15904 Filed 8–14–07; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 2101–000]

Sacramento Municipal Utility District;

Notice of Authorization for Continued

Project Operation

ebenthall on PROD1PC69 with NOTICES

August 8, 2007.

On July 15, 2005, Sacramento

Municipal Utility District, licensee for

the Upper American River Hydroelectric

Project, filed an application for a new or

subsequent license pursuant to the

Federal Power Act (FPA) and the

Commission’s regulations. The Upper

VerDate Aug<31>2005

15:00 Aug 14, 2007

Jkt 211001

American River Hydroelectric Project is

located on the Rubicon River, Silver

Creek, and South Fork of the American

River near Placerville, California.

The license for Project No. 2101–000

was issued for a period ending July 31,

2007. Section 15(a)(1) of the FPA, 16

U.S.C. 808(a)(1), requires the

Commission, at the expiration of a

license term, to issue from year-to-year

an annual license to the then licensee

under the terms and conditions of the

prior license until a new license is

issued, or the project is otherwise

disposed of as provided in section 15 or

any other applicable section of the FPA.

If the project’s prior license waived the

applicability of section 15 of the FPA,

then, based on section 9(b) of the

Administrative Procedure Act, 5 U.S.C.

558(c), and as set forth at 18 CFR

16.21(a), if the licensee of such project

has filed an application for a subsequent

license, the licensee may continue to

operate the project in accordance with

the terms and conditions of the license

after the minor or minor part license

expires, until the Commission acts on

its application. If the licensee of such a

project has not filed an application for

a subsequent license, then it may be

required, pursuant to 18 CFR 16.21(b),

to continue project operations until the

Commission issues someone else a

license for the project or otherwise

orders disposition of the project.

If the project is subject to section 15

of the FPA, notice is hereby given that

an annual license for Project No. 2101

is issued to Sacramento Municipal

Utility District, for a period effective

August 1, 2007 through July 31, 2008, or

until the issuance of a new license for

the project or other disposition under

the FPA, whichever comes first. If

issuance of a new license (or other

disposition) does not take place on or

before July 31, 2008, notice is hereby

given that, pursuant to 18 CFR 16.18(c),

an annual license under section 15(a)(1)

of the FPA is renewed automatically

without further order or notice by the

Commission, unless the Commission

orders otherwise. If the project is not

subject to section 15 of the FPA, notice

is hereby given that Sacramento

Municipal Utility District, is authorized

to continue operation of the Upper

American River Hydroelectric Project

until such time as the Commission acts

on its application for a subsequent

license.

Kimberly D. Bose,

Secretary.

[FR Doc. E7–15906 Filed 8–14–07; 8:45 am]

BILLING CODE 6717–01–P

PO 00000

Frm 00083

Fmt 4703

Sfmt 4703

45805

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 2146–000]

Alabama Power Company; Notice of

Authorization for Continued Project

Operation

August 8, 2007.

On July 28, 2005, Alabama Power

Company, licensee for the Coosa River

Hydroelectric Project, filed an

application for a new or subsequent

license pursuant to the Federal Power

Act (FPA) and the Commission’s

regulations. The Coosa River Project is

located on the Coosa River in the states

of Alabama and Georgia.

The license for Project No. 2146 was

issued for a period ending July 31, 2007.

Section 15(a)(1) of the FPA, 16 U.S.C.

808(a)(1), requires the Commission, at

the expiration of a license term, to issue

from year-to-year an annual license to

the then licensee under the terms and

conditions of the prior license until a

new license is issued, or the project is

otherwise disposed of as provided in

section 15 or any other applicable

section of the FPA. If the project’s prior

license waived the applicability of

section 15 of the FPA, then, based on

section 9(b) of the Administrative

Procedure Act, 5 U.S.C. 558(c), and as

set forth at 18 CFR 16.21(a), if the

licensee of such project has filed an

application for a subsequent license, the

licensee may continue to operate the

project in accordance with the terms

and conditions of the license after the

minor or minor part license expires,

until the Commission acts on its

application. If the licensee of such a

project has not filed an application for

a subsequent license, then it may be

required, pursuant to 18 CFR 16.21(b),

to continue project operations until the

Commission issues someone else a

license for the project or otherwise

orders disposition of the project.

If the project is subject to section 15

of the FPA, notice is hereby given that

an annual license for Project No. 2146

is issued to Alabama Power Company,

for a period effective August 1, 2007

through July 31, 2008, or until the

issuance of a new license for the project

or other disposition under the FPA,

whichever comes first. If issuance of a

new license (or other disposition) does

not take place on or before July 31,

2008, notice is hereby given that,

pursuant to 18 CFR 16.18(c), an annual

license under section 15(a)(1) of the

FPA is renewed automatically without

further order or notice by the

Commission, unless the Commission

E:\FR\FM\15AUN1.SGM

15AUN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.