Federal Register / Vol. 71, No. 17 / Thursday, January 26, 2006 / Notices

Agency decision

Ask Donna

What actually matters in this document.

Text

Federal Register / Vol. 71, No. 17 / Thursday, January 26, 2006 / Notices

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. EL05–107–000]

Oklahoma Gas and Electric Company;

OGE Energy Resources, Inc.; Notice of

Institution of Proceeding and Refund

Effective Date

January 20, 2006.

On June 7, 2005, the Commission

issued an order that instituted a

proceeding in Docket No. EL05–107–

000, pursuant to section 206 of the

Federal Power Act (FPA), 15 U.S.C.

824e, concerning the justness and

reasonableness of the OGE Companies

market-based rates in the OG&E control

area.1

The refund effective date in Docket

No. EL05–107–000, established

pursuant to section 2069(b) of the FPA,

will be 60 days from the date of

publication of this notice in the Federal

Register.

Magalie R. Salas,

Secretary.

[FR Doc. E6–986 Filed 1–25–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. ER06–407–000]

PJM Interconnection, L.L.C.; Notice of

Filing

rwilkins on PROD1PC63 with NOTICES

January 4, 2006.

Take notice that on December 28,

2005, PJM Interconnection, L.L.C. (PJM)

submitted for filing an unexecuted

interconnection service agreement (ISA)

among PJM; GSG, LLC; and

Commonwealth Edison Company,

designated as Original Service

Agreement No. 1407. PJM requests a

waiver of the Commission’s 60-day

notice requirement to permit a

December 23, 2005 effective date for the

ISA, and asks the Commission for

expedited action and a shortened

comment period.

PJM states that copies of this filing

were served upon the parties to the ISA

and the state regulatory commissions

within the PJM region.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

1 Oklahoma Gas and Electric Company and OGE

Resources, Inc., 111 FERC § 61,368 (2005). The OGE

Companies are Oklahoma Gas and Electric

Company and OGE Energy Resources.

VerDate Aug<31>2005

16:10 Jan 25, 2006

Jkt 205001

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211, 385.214).

Protests will be considered by the

Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed on or before the

comment date. On or before the

comment date, it is not necessary to

serve motions to intervene or protests

on persons other than the Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Comment Date: 5 p.m. Eastern Time

on January 9, 2006.

Magalie R. Salas,

Secretary.

[FR Doc. E6–954 Filed 1–25–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 1893]

Public Service Company of New

Hampshire; Notice of Authorization for

Continued Project Operation

January 19, 2006.

On December 29, 2003, the Public

Service Company of New Hampshire,

licensee for the Merrimack River

Hydroelectric Project No. 1893, filed an

application for a new or subsequent

license pursuant to the Federal Power

Act (FPA) and the Commission’s

regulations there under. Project No.

1893 is located on the Merrimack River

PO 00000

Frm 00014

Fmt 4703

Sfmt 4703

4359

in Hillsborough and Merrimack

Counties, New Hampshire.

The license for Project No. 1893 was

issued for a period ending December 31,

2005. Section 15(a)(1) of the FPA, 16

U.S.C. 808(a)(1), requires the

Commission, at the expiration of a

license term, to issue from year to year

an annual license to the then licensee

under the terms and conditions of the

prior license until a new license is

issued, or the project is otherwise

disposed of as provided in section 15 or

any other applicable section of the FPA.

If the project’s prior license waived the

applicability of section 15 of the FPA,

then, based on section 9(b) of the

Administrative Procedure Act, 5 U.S.C.

558(c), and as set forth at 18 CFR

16.21(a), if the licensee of such project

has filed an application for a subsequent

license, the licensee may continue to

operate the project in accordance with

the terms and conditions of the license

after the minor or minor part license

expires, until the Commission acts on

its application. If the licensee of such a

project has not filed an application for

a subsequent license, then it may be

required, pursuant to 18 CFR 16.21(b),

to continue project operations until the

Commission issues someone else a

license for the project or otherwise

orders disposition of the project.

If the project is subject to section 15

of the FPA, notice is hereby given that

an annual license for Project No. 1893

is issued to the Public Service Company

of New Hampshire for a period effective

January 1, 2006 through December 31,

2006, or until the issuance of a new

license for the project or other

disposition under the FPA, whichever

comes first. If issuance of a new license

(or other disposition) does not take

place on or before December 1, 2006,

notice is hereby given that, pursuant to

18 CFR 16.18(c), an annual license

under section 15(a)(1) of the FPA is

renewed automatically without further

order or notice by the Commission,

unless the Commission orders

otherwise.

If the project is not subject to section

15 of the FPA, notice is hereby given

that the Public Service Company of New

Hampshire is authorized to continue

operation of the Merrimack River

Hydroelectric Project No. 1893 until

such time as the Commission acts on its

application for subsequent license.

Magalie R. Salas,

Secretary.

[FR Doc. E6–952 Filed 1–25–06; 8:45 am]

BILLING CODE 6717–01–P

E:\FR\FM\26JAN1.SGM

26JAN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.