56510

Federal Register / Vol. 71, No. 187 / Wednesday, September 27, 2006 / Notices

ADDRESSES: Lowe’s L’Enfant Plaza

FOR FURTHER INFORMATION CONTACT: Rick

Klimkos, Designated Federal Officer,

Office of Federal Energy Management

Programs, U.S. Department of Energy,

1000 Independence Avenue, SW.,

Washington, DC 20585; (202) 586–8287.

SUPPLEMENTARY INFORMATION:

rwilkins on PROD1PC63 with NOTICES

Purpose of the Meeting: To seek input

and feedback from interested parties on

working group recommendations to

meet mandated Federal energy

management goals.

Tentative Agenda: Agenda will

include discussions on the following

topics:

Æ Update on FEMAC working group

activities;

Æ Discussion on FEMAC priorities;

Æ Open public discussion.

Public Participation: In keeping with

procedures, members of the public are

welcome to observe the business of the

Federal Energy Management Advisory

Committee. If you would like to file a

written statement with the committee,

you may do so either before or after the

meeting. If you would like to make oral

statements regarding any of these items

on the agenda, you should contact Rick

Klimkos at (202) 586–8287 or

rick.klimkos@ee.doe.gov (e-mail). You

must make your request for an oral

statement at least 5 business days before

the meeting. Members of the public will

be heard in the order in which they sign

up at the beginning of the meeting.

Reasonable provision will be made to

include the scheduled oral statements

on the agenda. The chair of the

committee will make every effort to hear

the views of all interested parties. The

chair will conduct the meeting to

facilitate the orderly conduct of

business.

Minutes: The minutes of the meeting

will be available for public review and

copying within 60 days at the Freedom

of Information Public Reading Room;

Room 1E–190; Forrestal Building; 1000

Independence Avenue, SW.,

Washington, DC, between 9 a.m. and 4

p.m., Monday through Friday, except

Federal holidays.

Issued at Washington, DC on September

21, 2006.

Rachel Samuel,

Deputy Committee Management Officer.

[FR Doc. E6–15830 Filed 9–26–06; 8:45 am]

BILLING CODE 6450–01–P

VerDate Aug<31>2005

16:48 Sep 26, 2006

Jkt 208001

Comment Date: 5 p.m. Eastern Time

on October 5, 2006.

DEPARTMENT OF ENERGY

Hotel, 480 L’Enfant Plaza, SW.,

Lafayette Room, Washington, DC 20024.

Federal Energy Regulatory

Commission

Magalie R. Salas,

Secretary.

[FR Doc. E6–15806 Filed 9–26–06; 8:45 am]

[Docket Nos. EL05–74–003]

American Electric Power Service

Corporation, Behalf of: Appalachian

Power Company, Columbus Southern

Power Company, Indiana Michigan

Power Company, Kentucky Power

Company, Kingsport Power Company,

Ohio Power Company, Wheeling Power

Company, Commonwealth Edison

Company, and Commonwealth Edison

Company of Indiana, Inc., Dayton

Power and Light Company; Notice of

Compliance Filing

September 20, 2006.

Take notice on September 14, 2006,

PJM Interconnection filed a refund

report, showing refunds that were

implemented in its June billings to its

members and settled on July 20, 2006,

pursuant to the Commission’s order

issued May 30, 2006.

Any person desiring to intervene or to

protest this filing must file in

accordance with Rules 211 and 214 of

the Commission’s Rules of Practice and

Procedure (18 CFR 385.211, 385.214).

Protests will be considered by the

Commission in determining the

appropriate action to be taken, but will

not serve to make protestants parties to

the proceeding. Any person wishing to

become a party must file a notice of

intervention or motion to intervene, as

appropriate. Such notices, motions, or

protests must be filed on or before the

comment date. Anyone filing a motion

to intervene or protest must serve a copy

of that document on the Applicant and

all the parties in this proceeding.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper using the

‘‘eFiling’’ link at http://www.ferc.gov.

Persons unable to file electronically

should submit an original and 14 copies

of the protest or intervention to the

Federal Energy Regulatory Commission,

888 First Street, NE., Washington, DC

20426.

This filing is accessible on-line at

http://www.ferc.gov, using the

‘‘eLibrary’’ link and is available for

review in the Commission’s Public

Reference Room in Washington, DC.

There is an ‘‘eSubscription’’ link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov, or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

PO 00000

Frm 00043

Fmt 4703

Sfmt 4703

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. EF06–2011–000]

United States Department of Energy—

Bonneville Power Administration;

Order Approving Rates on an Interim

Basis and Providing Opportunity for

Additional Comments

Issued September 21, 2006.

Before Commissioners: Joseph T. Kelliher,

Chairman; Suedeen G. Kelly, Marc Spitzer,

Philip D. Moeller, and Jon Wellinghoff.

1. In this order, we approve the

Bonneville Power Administration’s

(Bonneville) proposed wholesale power

rates 1 on an interim basis, pending our

full review for final approval. We also

provide an additional period of time for

parties to file comments. The proposed

wholesale power rates are intended to

allow Bonneville to recover its costs and

repay the Federal investment in the

Federal Columbia River Power System.

Background

2. On July 28, 2006, Bonneville filed

a request for interim and final approval

of its wholesale power rates in

accordance with the Pacific Northwest

Electric Power Planning and

Conservation Act (Northwest Power

Act) 2 and subpart B of part 300 of the

Commission’s regulations.3

Interventions and Comments

3. Notice of Bonneville’s July 28, 2006

wholesale power rates filing was

published in the Federal Register, 71 FR

45,801 (2006), with protests or

interventions due on or before August

28, 2006. Avista Corporation, Portland

General Electric Company, Idaho Power

Company, PacifiCorp, Puget Sound

Energy, Inc., Northwest Requirements

1 The proposed wholesale power rates for which

Bonneville seeks approval for the period October 1,

2006 through September 30, 2009, include: PF–07

Priority Firm Power Rate, NR–07 New Resource

Firm Power Rate, IP–07 Industrial Firm Power Rate,

FPS–07 Firm Power Products and Services Energy

Rate, and GTA General Transfer Agreement

Delivery Charge in addition to related General Rates

Schedule Provisions (GRSPs).

2 16 U.S.C. 839e(a)(2), 839e(i)(6) (2000).

3 18 CFR part 300 (2006).

E:\FR\FM\27SEN1.SGM

27SEN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.