Federal Register / Vol. 71, No. 65 / Wednesday, April 5, 2006 / Notices

Revised Sheet 500 and 501 to First

Electric Rate Schedule 23–33 pursuant

to Section 205 of the Federal Power Act

etc.

Filed Date: 03/22/2006.

Accession Number: 20060328–0081.

Comment Date: 5 p.m. Eastern Time

on Wednesday, April 12, 2006.

Docket Numbers: ER06–777–000.

Applicants: Connectiv Energy Supply,

Inc.

Description: Conectiv Energy Supply,

Inc. submits its request for authorization

to make wholesale power sales to its

affiliate, Delmarva Power & Light Co.

Filed Date: 03/22/2006.

Accession Number: 20060328–0086.

Comment Date: 5 p.m. Eastern Time

on Wednesday, April 12, 2006.

Docket Numbers: ER06–779–000.

Applicants: Carolina Power & Light

Company.

Description: Carolina Power & Light

Co. dba Progress Energy Carolinas, Inc.

submits a notice of termination of the

Standard Large Generator

Interconnection Agreement with North

Carolina Electric Membership Corp.

Filed Date: 03/23/2006.

Accession Number: 20060328–0075.

Comment Date: 5 p.m. Eastern Time

on Thursday, April 13, 2006.

Any person desiring to intervene or to

protest in any of the above proceedings

must file in accordance with Rules 211

and 214 of the Commission’s Rules of

Practice and Procedure (18 CFR 385.211

and 385.214) on or before 5 p.m. Eastern

time on the specified comment date. It

is not necessary to separately intervene

again in a subdocket related to a

compliance filing if you have previously

intervened in the same docket. Protests

will be considered by the Commission

in determining the appropriate action to

be taken, but will not serve to make

protestants parties to the proceeding.

Anyone filing a motion to intervene or

protest must serve a copy of that

document on the Applicant. In reference

to filings initiating a new proceeding,

interventions or protests submitted on

or before the comment deadline need

not be served on persons other than the

Applicant.

The Commission encourages

electronic submission of protests and

interventions in lieu of paper, using the

FERC Online links at http://

www.ferc.gov. To facilitate electronic

service, persons with Internet access

who will eFile a document and/or be

listed as a contact for an intervenor

must create and validate an

eRegistration account using the

eRegistration link. Select the eFiling

link to log on and submit the

intervention or protests.

VerDate Aug<31>2005

16:10 Apr 04, 2006

Jkt 208001

Persons unable to file electronically

should submit an original and 14 copies

of the intervention or protest to the

Federal Energy Regulatory Commission,

888 First St. NE., Washington, DC

20426.

The filings in the above proceedings

are accessible in the Commission’s

eLibrary system by clicking on the

appropriate link in the above list. They

are also available for review in the

Commission’s Public Reference Room in

Washington, DC. There is an

eSubscription link on the Web site that

enables subscribers to receive e-mail

notification when a document is added

to a subscribed dockets(s). For

assistance with any FERC Online

service, please e-mail

FERCOnlineSupport@ferc.gov or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–4878 Filed 4–4–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 2146–113]

Alabama Power Company; Notice of

Availability of Environmental

Assessment

March 29, 2006.

In accordance with the National

Environmental Policy Act of 1969 and

the Federal Energy Regulatory

Commission’s regulations, the Office of

Energy Projects has reviewed the

application requesting the

Commission’s authorization for nonproject use of project lands and waters

for a water withdrawal at the Logan

Martin development of the Coosa River

Project. The proposed withdrawal

would be located south of Ragland,

Alabama. An environmental assessment

(EA) has been prepared.

In the EA, the Commission’s staff

concludes that approval of the licensee’s

application would not produce any

significant adverse environmental

impacts, consequently the proposal

would not constitute a major federal

action significantly affecting the quality

of the human environment.

A copy of the EA is attached to the

Commission order titled ‘‘Approving

Non-Project use of Project Lands and

Waters, issued March 28, 2006, and is

available at the Commission’s Public

Reference Room. A copy of the EA may

also be viewed on the Commission’s

PO 00000

Frm 00019

Fmt 4703

Sfmt 4703

17089

Web site at http://www.ferc.gov using

the ‘‘elibrary’’ link. Enter the docket

numbers (P–2146) in the docket field to

access the document. For assistance,

call (202) 502–8222 or (202) 502–8659

(for TTY).

Magalie R. Salas,

Secretary.

[FR Doc. E6–4881 Filed 4–4–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. PF06–17–000]

Gulf South Pipeline Company; Notice

of Intent To Prepare an Environmental

Impact Statement for the Proposed

East Texas Expansion Project and

Request for Comments on

Environmental Issues

March 28, 2006.

The staff of the Federal Energy

Regulatory Commission (FERC or

Commission) will prepare an

environmental impact statement (EIS)

for the East Texas Expansion Project

proposed by the Gulf South Pipeline

Company (Gulf South). This notice

describes the proposed project, the EIS

process and how the public can

participate in our 1 analysis.

This notice is being sent to affected

landowners; Federal, state, and local

government agencies; elected officials;

environmental and public interest

groups; Native American tribes; other

interested parties; and local libraries

and newspapers. We encourage

government representatives to notify

their constituents of this proposed

project and encourage them to comment

on their areas of concern.

An effort is being made to send this

notice to all individuals, organizations

and government entities interested in

and/or potentially affected by the

proposed project. This includes all

landowners who are potential right-ofway grantors, whose property may be

used temporarily for project purposes or

who own homes within distances

defined in the Commission’s regulations

of certain aboveground facilities.

If you received this notice, you are on

the environmental mailing list for this

project. If you would like to remain on

our mailing list, please return the

Information Request (Appendix 2). If

you do not return the Information

Request, you will be removed from the

1 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the

environmental staff of the FERC’s Office of Energy

Projects.

E:\FR\FM\05APN1.SGM

05APN1

17090

Federal Register / Vol. 71, No. 65 / Wednesday, April 5, 2006 / Notices

Commission’s environmental mailing

list.

Summary of the Proposed Project

Gulf South proposes to construct,

operate and maintain approximately 146

miles of natural gas pipeline in Desoto,

Red River, Bienville, Jackson, Ouachita

and Richland Parishes, Louisiana. This

pipeline would have the capacity to

deliver approximately 1.5 billion cubic

feet (BCF) of natural gas per day and

would interconnect with three existing

interstate natural gas pipeline facilities.

Gulf South is also proposing to expand

its existing natural gas compressor

station in Panola County, Texas; and

construct a new natural gas compressor

station in Ouachita Parish, Louisiana.

According to Gulf South, the purpose

of this project is to transport natural gas

from production fields in east Texas and

northern Louisiana to markets in the

Gulf Coast, Midwestern, Northeastern

and Southeastern United States. Gulf

South has also stated that the East Texas

Expansion Project will satisfy the

growing demand for natural gas in the

United States.

Specifically, Gulf South is proposing

to construct, operate and maintain:

• 146.3 miles of 42-inch-diameter

pipeline beginning near Keatchie,

Louisiana and extending easterly

through Desoto, Red River, Bienville,

Jackson, Ouachita and Richland

Parishes until connecting with existing

pipeline facilities near Delhi, Louisiana.

• An additional 40,000 horsepower

(HP) of compression at the existing

Carthage Junction Compressor Station in

Panola County, Texas.

• A new 26,830 HP compressor

station (Vixen Compressor Station) near

pipeline mile post 98.3 in Ouachita

Parish, Louisiana.

• Meter and regulation stations,

mainline block valves, and pigging

facilities.

A general location of the proposed

pipeline and compressor stations is

provided in Appendix 1.2

Land Requirements

wwhite on PROD1PC61 with NOTICES

Construction of the proposed 42-inchdiameter pipeline would generally

require the use of a 100 foot

2 The appendices referenced in this notice are not

being printed in the Federal Register. Copies of all

appendices, other than Appendix 1 (maps), are

available on the Commission’s Web site at the

‘‘eLibrary’’ link or from the Commission’s Public

Reference Room, 888 First Street, NE., Washington,

DC 20426, or call (202) 502–8371. For instructions

on connecting to eLibrary refer to the Public

Participation section of this notice. Copies of the

appendices were sent to all those receiving this

notice in the mail. Requests for detailed maps of the

proposed facilities should be made directly to Gulf

South.

VerDate Aug<31>2005

16:10 Apr 04, 2006

Jkt 208001

construction right-of-way (ROW). The

exact size of the construction ROW

would vary depending on land type and

construction method. Additional

temporary work spaces (ATWS), access

roads, pipe storage and contractor yards

would also be required during

construction of the 42-inch-diameter

pipeline. Expansion of the Carthage

Junction Compressor Station would be

conducted within the fenced boundaries

of the station. Construction of the

proposed Vixen Compressor Station

would require the purchase and

temporary disturbance of approximately

20 acres of land. Approximately 2,500

acres of land would be temporarily

affected by construction of the proposed

project.

Operation of the proposed 42-inchdiameter pipeline would require the use

of a 60 foot permanent ROW. Operation

of the expanded Carthage Junction

Compressor Station would not require

the use of additional lands. Operation of

the proposed Vixen Compressor Station

would require the use of approximately

10 acres of land. Approximately 950

acres of land would be permanently

affected by operation of the proposed

project.

If you are a landowner receiving this

notice, you may be contacted by a Gulf

South representative about the

acquisition of an easement to construct,

operate and maintain the proposed

project facilities. The pipeline company

would seek to negotiate a mutually

acceptable agreement. However, if the

project is approved by the FERC, that

approval conveys with it the right of

eminent domain. Therefore, if easement

negotiations fail to produce an

agreement, the pipeline company could

initiate condemnation proceedings in

accordance with state law.

The EIS Process

The National Environmental Policy

Act (NEPA) requires the Commission to

take into account the environmental

impacts that could result from the

approval of an interstate natural gas

pipeline. The FERC will use the EIS to

assess the environmental impact that

could result if the East Texas Expansion

Project is authorized under section 7 of

the Natural Gas Act.

NEPA also requires us to discover and

address concerns the public may have

about proposals under consideration by

the Commission. This process is

referred to as ‘‘scoping.’’ The main goal

of the scoping process is to focus the

analysis in the EIS on the important

environmental issues. With this Notice

of Intent, the Commission staff is

requesting public comments on the

scope of the issues to be addressed in

PO 00000

Frm 00020

Fmt 4703

Sfmt 4703

the EIS. All comments received will be

considered during preparation of the

EIS. Please note that the scoping period

will close on April 27, 2006.

In the EIS, we will discuss impacts

that could occur as a result of the

construction and operation of the

proposed project under these general

headings:

• Geology and soils;

• Water resources;

• Wetlands and vegetation;

• Fish and wildlife;

• Threatened and endangered

species;

• Land use, recreation and visual

resources;

• Air quality and noise;

• Cultural resources;

• Socioeconomics;

• Reliability and safety; and

• Cumulative impacts.

In the EIS, we will also evaluate

possible alternatives to the proposed

project or portions of the project and

make recommendations on how to

lessen or avoid impacts on affected

resources.

Our independent analysis of the

issues will be included in a draft EIS.

The draft EIS will be mailed to Federal,

state and local government agencies;

elected officials; environmental and

public interest groups; Native American

tribes; affected landowners;

commentors; other interested parties;

local libraries and newspapers; and the

FERC’s official service list for this

proceeding. A 45-day comment period

will be allotted for review of the draft

EIS. We will consider all comments on

the draft EIS and revise the document,

as necessary, before issuing a final EIS.

We will consider all comments on the

final EIS before we make our

recommendations to the Commission.

To ensure that your comments are

considered, please follow the

instructions in the Public Participation

section of this notice.

Although no formal application has

been filed, the FERC staff has already

initiated its NEPA review under its Prefiling Process. The purpose of the Prefiling Process is to encourage the early

involvement of interested stakeholders

and to identify and resolve issues before

an application is filed.

With this notice, we are also asking

federal, state and local governmental

agencies with jurisdiction and/or

special expertise with respect to

environmental issues to express their

interest in becoming cooperating

agencies for the preparation of the EIS.

These agencies may choose to

participate once they have evaluated the

proposal relative to their

responsibilities. Agencies that would

E:\FR\FM\05APN1.SGM

05APN1

Federal Register / Vol. 71, No. 65 / Wednesday, April 5, 2006 / Notices

like to request cooperating status should

send a letter expressing that interest and

expected level of involvement to the

Secretary of the Commission at the

address provided in the public

participation section of this notice.

wwhite on PROD1PC61 with NOTICES

Currently Identified Environmental

Issues

The EIS will discuss impacts that

could occur as a result of the

construction, operation and

maintenance of the proposed project.

We have already identified several

issues that we think deserve attention

based on a preliminary review of the

project site, interaction with the public

during the pre-filing process and

information provided by Gulf South.

This preliminary list of issues may be

changed based on your comments and

our analysis.

• The minimization of construction

rights-of-way and associated

construction impacts.

• Potential effects on prime farmland

and soils with a high potential for

compaction.

• Potential impacts to existing land

uses, including residences, suburban

housing developments, agricultural and

managed forested lands.

• Potential increases in noise

resulting from the construction of

pipeline compression.

• Potential impacts to perennial and

intermittent waterbodies, including

waterbodies with federal and/or state

designations.

• Evaluation of temporary and

permanent impacts on wetlands and

development of appropriate mitigation.

• Potential impacts to fish and

wildlife habitat, including potential

impacts to federally and state-listed

threatened and endangered species.

• Potential impacts to wildlife

management areas.

• Potential impacts and benefits of

construction workforce on local

housing, infrastructure, public services

and economy.

• Public safety and potential hazards

associated with the transport of natural

gas.

• Alternative alignments for the

pipeline route.

• Assessment of the effect of the

proposed project when combined with

other past, present, or reasonably

foreseeable future actions in the project

area.

Public Participation

You can make a difference by

providing us with your specific

comments or concerns about the

proposed project. By becoming a

commentor, your concerns will be

VerDate Aug<31>2005

16:10 Apr 04, 2006

Jkt 208001

addressed in the EIS and considered by

the Commission. Your comments

should focus on the potential

environmental effects, reasonable

alternatives (including alternative

facility sites and pipeline routes), and

measures to avoid or lessen

environmental impacts. The more

specific your comments, the more useful

they will be. To ensure that your

comments are timely and properly

recorded, please carefully follow these

instructions:

• Send an original and two copies of

your letter to: Magalie R. Salas,

Secretary, Federal Energy Regulatory

Commission, 888 First St., NE., Room

1A, Washington, DC 20426.

• Label one copy of your comments

for the attention of Gas Branch 2, DG2E.

• Reference Docket No. PF06–17–000

on the original and both copies.

• Mail your comments so that they

will be received in Washington, DC on

or before April 27, 2006.

Please note that we are continuing to

experience delays in mail deliveries

from the U.S. Postal Service. As a result,

we will include all comments that we

receive within a reasonable time frame

in our environmental analysis of this

project. The Commission strongly

encourages electronic filing of any

comments in response to this Notice of

Intent. For information on electronically

filing comments, please see the

instructions on the Commission’s Web

site at http://www.ferc.gov; before you

can submit comments you will need to

create a free account.

Public scoping meetings are designed

to provide another opportunity to offer

comments on the proposed project. The

FERC will announce plans for public

scoping meetings in the vicinity of the

proposed project once Gulf South has

filed additional information with the

Commission. Interested groups and

individuals are encouraged to attend

these meetings and to present comments

on the environmental issues they

believe should be addressed in the EIS.

A transcript of each meeting will be

generated so that comments are

accurately recorded.

Once Gulf South formally files its

application with the Commission, you

may want to become an official party to

the proceeding known as an

‘‘intervenor.’’ Intervenors play a more

formal role in the process and are able

to file briefs, appear at hearings and be

heard by the courts if they choose to

appeal the Commission’s final ruling.

An intervenor formally participates in a

Commission proceeding by filing a

request to intervene. Instructions for

becoming an intervenor are included in

the User’s Guide under the ‘‘e-filing’’

PO 00000

Frm 00021

Fmt 4703

Sfmt 4703

17091

link on the Commission’s Web site.

Please note that you may not request

intervenor status at this time. You must

wait until a formal application is filed

with the Commission.

Availability of Additional Information

Gulf South has established an Internet

Web site for this project at http://

www.gulfsouthpl.com. This Web site

includes a description of the project, a

map of the proposed pipeline route and

answers to frequently asked questions.

You can also request additional

information or provide comments

directly to Gulf South at 1–877–972–

8533 or by e-mail at

easttexasexpansionproject

@gulfsouthpl.com.

Additional information about this

project can also be obtained by

contacting the Commission’s Office of

External Affairs, at 1–866–208—FERC

(3372). Additional information is also

available on the Internet at http://

www.ferc.gov. The ‘‘eLibrary link’’ on

the FERC Web site provides access to

documents submitted to and issued by

the Commission, such as comments,

orders, notices and rulemakings. Once

on the FERC website, click on the

‘‘eLibrary link,’’ select ‘‘General Search’’

and in the ‘‘Docket Number’’ field enter

the project docket number excluding the

last three digits (PF06–17). When

researching information be sure to select

an appropriate date range. In addition,

the FERC now offers a free email service

called eSubscription that allows you to

keep track of all formal issuances and

submittals in specific dockets. This can

reduce the amount of time you spend

researching proceedings by

automatically providing you with

notification of these filings, document

summaries and direct links to the

documents. To register for this service,

go to http://www.ferc.gov/

esubscribenow.htm.

Public meetings or site visits will be

posted on the Commission’s calendar

located at http://www.ferc.gov/

EventCalendar/EventsList.aspx along

with other related information.

For assistance with the FERC Web site

or with eSubscription, please contact

FERC Online Support at

FERCOnlineSupport@ferc.gov or toll

free at 1–866–208–3676, or TTY, contact

(202) 502–8659.

Magalie R. Salas,

Secretary.

Appendix 2—Information Request

[Docket No. PF06–17–000]

b Please keep my name on the mailing list

for the East Texas Expansion Project.

Name llllllllllllllllll

E:\FR\FM\05APN1.SGM

05APN1

17092

Federal Register / Vol. 71, No. 65 / Wednesday, April 5, 2006 / Notices

Agency lllllllllllllllll

Address

llllllllllllllll

City llllllllllllllllll

State llllllllllllllllll

Zip Code llllllllllllllll

b Please send me a paper copy of the

environmental document instead of an

electronic copy (compact disc).

From llllllllllllllllll

lllllllllllllllllllll

lllllllllllllllllllll

lllllllllllllllllllll

ATTN: OEP—Gas 2, PJ—11.2, Federal Energy

Regulatory Commission, 888 First Street,

NE., Washington, DC 20426.

(Docket No. PF06–17–000)

Staple or Tape Here

[FR Doc. E6–4873 Filed 4–4–06; 8:45 am]

BILLING CODE 6717–01–P

ENVIRONMENTAL PROTECTION

AGENCY

[EPA–HQ–OPPT–2003–0604; FRL–7774–6]

Access to Confidential Business

Information by Chemical Abstract

Services; Correction

AGENCY: Environmental Protection

Agency (EPA).

ACTION: Correction.

wwhite on PROD1PC61 with NOTICES

SUMMARY: EPA issued a notice in the

Federal Register of November 29, 2005,

concerning the authorization of EPA’s

contractor Chemical Abstract Services,

of Columbus, Ohio, to access

information which has been submitted

to EPA under sections 5 and 8 of the

Toxic Substances Control Act (TSCA).

This document is being issued to correct

errors in that notice.

FOR FURTHER INFORMATION CONTACT: For

general information contact: Colby

Lintner, Regulatory Coordinator,

Environmental Assistance Division

(7408M), Office of Pollution Prevention

and Toxics, Environmental Protection

Agency, 1200 Pennsylvania Ave., NW.,

Washington, DC 20460; telephone

number: (202) 554–1404; e-mail address:

TSCA-Hotline@epa.gov.

For technical information contact:

Scott M. Sherlock, TSCA Security Staff,

Environmental Assistance Division

(7408M), Office of Pollution Prevention

and Toxics, Environmental Protection

Agency, 1200 Pennsylvania Ave., NW.,

Washington, DC 20460; telephone

number: (202)564–8257; e-mail address:

sherlock.scott@epa.gov

SUPPLEMENTARY INFORMATION:

I. General Information

A. Does this Notice Apply to Me?

This action is directed to the public

in general. This action may, however, be

of interest to those persons who are or

VerDate Aug<31>2005

18:34 Apr 04, 2006

Jkt 208001

may be required to conduct testing of

chemical substances under TSCA. Since

other entities may also be interested, the

Agency has not attempted to describe all

the specific entities that may be affected

by this action. If you have any questions

regarding the applicability of this action

to a particular entity, consult the

technical person listed under FOR

FURTHER INFORMATION CONTACT.

B. How Can I Get Copies of this

Document and Other Related

Documents?

1. Docket. EPA has established a

docket for this action under docket

identification (ID) number EPA–HQ–

OPPT–2003–0004. Publicly available

docket materials are available

electronically athttp://

www.regulations.gov or in hard copy at

the OPPT Docket, EPA Docket Center,

EPA West, Rm. B102, 1301 Constitution

Ave., NW., Washington, DC. The EPA

Docket Center Public Reading Room is

open from 8:30 a.m. to 4:30 p.m.,

Monday through Friday, excluding legal

holidays. The telephone number for the

Public Reading Room is (202) 566–1744,

and the telephone number for the OPPT

Docket is (202) 566–0280.

2. Electronic access. You may access

this Federal Register document

electronically through the EPA Internet

under the ‘‘Federal Register’’ listings

athttp://www.epa.gov/fedrgstr/.

II. What Does this Correction Do?

In FR Doc 05–23437 published in the

Federal Register of November 29, 2005

(70 FR 71500) (FRL–7751–6), EPA

issued a notice announcing the access of

information submitted to EPA under

sections 5 and 8 of TSCA to Chemical

Abstract Services. In that document the

access date and expiration date were

inadvertently listed. The document is

corrected as follows:

1. On page 71501, first column, the

date unit should have read:

‘‘DATES: Access to confidential data will

occur on March 1, 2006.’’

2. On page 71501, second column,

under Unit II., the fifth paragraph is

corrected to read:

‘‘Clearance for access to TSCA CBI

under Contract Number EP–W–06–011

may continue until December 31, 2012.

Access will occur on March 1, 2006.’’

List of Subjects

Environmental protection,

Confidential business information.

PO 00000

Frm 00022

Fmt 4703

Sfmt 4703

March 29, 2006.

Vicki Simons,

Acting Director, Information Management

Division, Office of PollutionPrevention and

Toxics.

[FR Doc. E6–4931 Filed 4–4–06; 8:45 am]

BILLING CODE 6560–50–S

ENVIRONMENTAL PROTECTION

AGENCY

[EPA–HQ–OPP–2006–0273; FRL–7771–6]

The Association of American Pesticide

Control Officials State FIFRA Issues

Research and Evaluation Group

Working Committee on Water Quality

and Pesticide Disposal Public Meeting

AGENCY: Environmental Protection

Agency (EPA).

ACTION: Notice.

SUMMARY: The Association of American

Pesticide Control Officials (AAPCO)/

State FIFRA Issues Research and

Evaluation Group (SFIREG) Working

Committee on Water Quality and

Pesticide Disposal (WC/WQ&PD) will

hold a 2–day meeting, beginning on

April 24, 2006 and ending April 25,

2006. This notice announces the

location and times for the meeting and

sets forth the tentative agenda topics.

DATES: The meeting will be held on

April 24, 2006 from 9 a.m. to 5 p.m. and

9 a.m. to 12 p.m. on April, 25, 2006.

ADDRESS: The meeting will be held at

Mayflower Park Hotel, 4th and Olive

Streets, Seattle, WA, 98101, telephone

number: (206) 623–8700.

FOR FURTHER INFORMATION CONTACT:

Georgia McDuffie, Field and External

Affairs Division (7506C), Office of

Pesticide Programs, Environmental

Protection Agency, 1200 Pennsylvania

Ave., NW., Washington, DC 20460–

0001; telephone number: (703) 605–

0195; fax number: (703) 308–1850; email address: mcduffie.georgia@epa.gov

or Philip H. Gray, SFIREG Executive

Secretary, P.O. Box 1249, Hardwick, VT

05843–1249; telephone number: (802)

472–6956; fax (802) 472–6957; e-mail

address: aapco@plainfield.bypass.com.

SUPPLEMENTARY INFORMATION:

I. General Information

A. Does this Action Apply to Me?

You may be potentially affected by

this action if you are interested in

SFIREG information exchange

relationship with EPA regarding

important issues related to human

health, environmental exposure to

pesticides, and insight into EPA’s

decision-making process are invited and

E:\FR\FM\05APN1.SGM

05APN1

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.