Federal Register / Vol. 71, No. 175 / Monday, September 11, 2006 / Notices

Agency decision

Ask Donna

What actually matters in this document.

Text

Federal Register / Vol. 71, No. 175 / Monday, September 11, 2006 / Notices

are also available for review in the

Commission’s Public Reference Room in

Washington, DC.

There is an eSubscription link on the

Web site that enables subscribers to

receive e-mail notification when a

document is added to a subscribed

docket(s). For assistance with any FERC

Online service, please e-mail

FERCOnlineSupport@ferc.gov. or call

(866) 208–3676 (toll free). For TTY, call

(202) 502–8659.

Magalie R. Salas,

Secretary.

[FR Doc. E6–14951 Filed 9–8–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Project No. 11945–001—Oregon]

Dorena Lake Dam Hydroelectric

Project; Notice of Availability of Draft

Environmental Assessment

rwilkins on PROD1PC61 with NOTICES

September 1, 2006.

In accordance with the National

Environmental Policy Act of 1969 and

the Federal Energy Regulatory

Commission’s (Commission’s)

regulations, 18 CFR part 380 (Order No.

486, 52 FR 47897), the Office of Energy

Projects has reviewed Symbiotics, LLC’s

application for license for the proposed

Dorena Lake Dam Project (or project),

located on the Row River near the city

of Cottage Grove, Lane County, Oregon,

and has prepared a Draft Environmental

Assessment (Draft EA) for the project.

The proposed project would occupy less

than 0.13 acre (5,655 square feet) of

federal land administered by the U.S.

Army Corps of Engineers and the U.S.

Bureau of Land Management.

The Draft EA contains the staff’s

analysis of the potential future

environmental effects of the project, and

staff has concluded that licensing the

project, with appropriate environmental

protective measures, would not

constitute a major federal action that

would significantly affect the quality of

the human environment.

A copy of the Draft EA is available for

review at the Commission in the Public

Reference Room or may be viewed on

the Commission’s Web site at http://

www.ferc.gov using the ‘‘eLibrary’’ link.

Enter the docket number excluding the

last three digits in the docket number

field to access the document. For

assistance, contact FERC Online

Support at

FERCOnlineSupport@ferc.gov or toll-

VerDate Aug<31>2005

18:03 Sep 08, 2006

Jkt 208001

free at 1–866–208–3676, or for TTY,

202–502–8659.

You may also register online at

http://www.ferc.gov/docs-filing/

esubscription.asp to be notified via email of new filings and issuances

related to this or other pending projects.

For assistance, contact FERC Online

Support.

Any comments (an original and 8

copies) should be filed within 30 days

from the date of this notice and should

be addressed to Magalie R. Salas,

Secretary, Federal Energy Regulatory

Commission, 888 First Street, NE.,

Washington, DC 20426. Please affix

‘‘Dorena Lake Dam Project No. 11945–

001’’ to all comments. Comments may

be filed electronically via the Internet in

lieu of paper. See 18 CFR

385.2001(a)(1)(iii) and the instructions

on the Commission’s Web site at

http://www.ferc.gov under the ‘‘e-filing’’

link. The Commission strongly

encourages electronic filings.

For further information, contact

Michael Henry by telephone at 503–

552–2762 or by e-mail at

mike.henry@ferc.gov.

Magalie R. Salas,

Secretary.

[FR Doc. E6–14959 Filed 9–8–06; 8:45 am]

BILLING CODE 6717–01–P

DEPARTMENT OF ENERGY

Federal Energy Regulatory

Commission

[Docket No. CP05–357–003]

Cheniere Creole Trail Pipeline, L.P.;

Notice of Intent To Prepare an

Environmental Assessment for the

Proposed Creole Trail Segment I

Amendment Project and Request for

Comments on Environmental Issues

September 5, 2006.

The staff of the Federal Energy

Regulatory Commission (FERC or

Commission) will prepare an

environmental assessment (EA) that

discusses the environmental impacts of

Cheniere Creole Trail Pipeline, L.P.

(Cheniere) proposed Creole Trail

Segment I Amendment or Project)

which involves extension of Creole Trail

Pipeline by adding about 18.1 miles of

42-inch-diameter Pipeline (Segment I) to

be located in Cameron Parish,

Louisiana. The Creole Trail LNG and

Pipeline Project was authorized on June

15, 2006.1

1 On June 15, 2006, the Commission approved the

Creole Trail LNG and Pipeline Project in Docket

Nos. CP05–360–000, CP05–357–000, CP05–358–

000, and CP05–359–000. The Creole Trail LNG

PO 00000

Frm 00078

Fmt 4703

Sfmt 4703

53439

This notice announces the opening of

the scoping period that will be used to

gather environmental input from the

public and interested agencies on the

Project. Please note that the scoping

period will close on October 5, 2006.

Details on how to submit comments are

provided in the Public Participation

section of this notice.

This notice is being sent to potentially

affected landowners along the Project

route; Federal, State, and local

government agencies; elected officials;

environmental and public interest

groups; Native American tribes; and

local libraries and newspapers.

With this notice, we 2 are asking

Federal, State, and local agencies with

jurisdiction and/or special expertise

with respect to environmental issues to

cooperate with us in the preparation of

the EA. These agencies may choose to

participate once they have evaluated the

proposal relative to their

responsibilities. Agencies which would

like to request cooperating status should

follow the instructions for filing

comments described later in this notice.

We encourage government

representatives to notify their

constituents of this planned Project and

encourage them to comment on their

areas of concern.

Some affected landowners may be

contacted by a Project representative

about the acquisition of an easement to

construct, operate, and maintain the

proposed pipeline. If so, the company

should seek to negotiate a mutually

acceptable agreement. In the event that

the Project is certificated by the

Commission, that approval conveys the

right of eminent domain for securing

easements for the pipeline. Therefore, if

easement negotiations fail to produce an

agreement, the company could initiate

condemnation proceedings in

accordance with State law.

A fact sheet prepared by the FERC

entitled ‘‘An Interstate Natural Gas

Facility On My Land? What Do I Need

To Know?’’ addresses a number of

typically asked questions, including the

use of eminent domain and how to

participate in the Commission’s

proceedings. It is available for viewing

on the FERC Internet Web site (http://

www.ferc.gov).

A map illustrating the proposed

Project is provided in Appendix 1.3

Terminal and Pipeline Project included a liquefied

natural gas (LNG) terminal and associated LNG

facilities, 116.8 miles of dual 42-inch-diameter

mainline pipeline, and associated pipeline

facilities.

2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the

environmental staff of the Office of Energy Projects.

3 The appendices referenced in this notice are not

being printed in the Federal Register. Copies are

E:\FR\FM\11SEN1.SGM

Continued

11SEN1