DENIED: September 25, 2007

Agency decision

Ask Donna

What actually matters in this document.

Text

DENIED: September 25, 2007

CBCA 54, 84

BAY SHIPBUILDING COMPANY,

Appellant,

v.

DEPARTMENT OF HOMELAND SECURITY,

Respondent.

Daniel J. Borowski, Litigation Counsel, Bay Shipbuilding Co., Manitowoc, WI,

counsel for Appellant.

Isaac Johnson, Jr., Office of Procurement Law, United States Coast Guard,

Department of Homeland Security, Washington, DC, counsel for Respondent.

Before Board Judges STERN, FENNESSY, and SOMERS.

SOMERS, Board Judge.

Bay Shipbuilding Co. (BSC) appeals the denial of two claims by the contracting

officer for the United States Coast Guard, Department of Homeland Security (USCG or

Coast Guard). In CBCA 84, BSC asserts that the Government is not entitled to damages of

$17,275.36 arising from BSC’s alleged breach of the contract. In CBCA 54, BSC seeks

$23,125 for costs incurred when it encountered excessive underwater hull paint during the

course of contract performance.

The parties have elected to submit the case for resolution on the written record without

a hearing. The written record includes the appeal files, the pleadings, and the submission by

CBCA 54, 84

2

both parties of multiple briefs with supporting affidavits, declarations, and documentary

evidence.

I.

CBCA 84: Repair or Replacement of Heat Exchanger Gasket Kits

Findings of Fact

On August 5, 2005, the Coast Guard awarded a fixed price contract to BSC for dry

dock repairs of the USCG Cutter (USCGC) Hollyhock. The contract required BSC to

perform routine maintenance on the cutter and to repair items as appropriate. The contract

expressly stated that the contractor must “furnish all necessary labor, material, services,

equipment, supplies, power, accessories, facilities, and such other things and services as are

necessary, except as otherwise specified to perform dry dock repairs and alterations to the

vessel.” Appeal File, CBCA 84, Exhibit 4 at 2. Among other things, the contract required

BSC to clean, inspect, repair, and reassemble heat exchanger gasket kits for the main diesel

engine jacket water heat exchangers (MDE heat exchangers). Specifically, the contract

stated as follows:

3.4 Cleaning requirements. The Contractor shall clean all

interior and exterior heat transfer surfaces to a state free of all

debris, scale and surface contaminants in accordance with the

heat exchanger manufacturer’s recommendations, and in

compliance with all federal, state and local environmental

regulations.

....

3.6 Reassembly. After all authorized repairs, the Contractor

shall reassemble each heat exchanger. Renew all software

(seals, gaskets, O-rings) and isolation fittings/mounts in

accordance with the manufacturer’s specifications. Renew

fasteners, hoses, thermostats and anodes as applicable. Apply

silicone rubber sealant conforming to CID A-A-59588 around

all fasteners, nozzles or gaskets that penetrate the hull.

Id., Exhibit 5 at 23.

Paragraph 3.1 of the General Requirements section of the contract required the

contractor to “conform to all requirements specified in Std Spec 0000_STD [the Coast Guard

Maintenance and Logistics Command Atlantic (MLCA) Standard Specification 0000_STD,

CBCA 54, 84

3

2004 Edition].” Appeal File, CBCA 84, Exhibit 5 at 2. The paragraph emphasized in bold

type the following:

NOTICE!

The requirements of paragraph 3.1 (General) applies to all work

under the scope of this contract, whether explicitly stated in

work items or not, and also to all other work subsequently

authorized by changes, modifications, or extensions to the

contract.

Id. at 2-3.

Standard Specification 0000_STD listed and defined various terms used in the work

items. Appeal File, CBCA 84, Exhibit 6C at 28. The word “renew” is defined as follows:

Permanently remove an item and install, in its place, a new and

unused item which is identical in material, form, fit, and

function; the new item must:

•

Have the same shape, size, dimensions, and other

physical parameters.

•

Have the same ability as the old item, to physically

interface or interconnect with or become an integral part

of another item.

•

Perform the same action or actions that the original item

was designed to perform.

Id. at 30.

Todd Thayse, the Director of Contract Services for BSC, prepared BSC’s bid for this

work item, which included 560 hours in labor and $31,000 in materials for a total bid of

$60,000. This amount did not include the cost of replacing the MDE heat exchanger gaskets.

Appellant’s Submission, Declaration of Todd Thayse (May 18, 2006) ¶ 46.

The contract required BSC to provide a technical representative authorized by the

manufacturer of the MDE heat exchanger system, Alfa Laval, to provide advice about the

manufacturer’s proprietary information pertinent to the system, to ensure compliance with

CBCA 54, 84

4

the manufacturer’s procedures and standards during disassembly, inspection, and reassembly,

and to assist with the proper cleaning, inspecting, and testing of the heat exchanger. Appeal

File, CBCA 84, Exhibit 5 at 24. As the contract required, BSC provided Corey O’Conner,

who was the manufacturer’s field technical representative. Mr. O’Conner inspected the

gaskets in the MDE heat exchangers and opined that the gaskets could be reused. Thayse

Declaration ¶¶ 49, 50.

Relying upon Mr. O’Conner’s statement that the gaskets could be reused, BSC

advised the Coast Guard in a condition found report (CFR) dated October 11, 2005, that the

manufacturer’s technical representative had visually inspected the heat exchanger. BSC

informed the Coast Guard of Mr. O’Conner’s recommendation that BSC clean the plates by

hand and then reassemble them by using existing materials unless the materials were

damaged. BSC stated that it would submit a second CFR if it determined that replacing the

gaskets would be necessary. Appeal File, CBCA 84, Exhibit 8C. BSC suggested that if it

determined that the gaskets would need to be replaced, it would seek to obtain new gaskets

from the Government. Id. BSC’s suggestion ignored the fact that the gaskets do not appear

on the list of government furnished equipment identified in the contract. Id., Exhibit 5 at x­

xiii.

Chief Warrant Officer (CWO) Derrick Johnson responded to the CFR by telling BSC

that paragraph 3.6 of the contract required BSC to renew, i.e., replace the existing materials.

CWO Johnson noted that paragraph 5.1.23 on page 30 of the standard specifications defined

the term “renew” as to “permanently remove an item and install, in its place, a new and

unused item which is identical in material, form, fit and function.” Appeal File, CBCA 84,

Exhibit 10, Declaration of Kathryn Stark, Contracting Officer (May 1, 2006) ¶ 15.

Accordingly, CWO Johnson rejected BSC’s contention that the contract permitted reuse of

the materials under any conditions. Id.

Over the course of the next two days, the contracting officer exchanged email

messages with BSC’s contract administrator about the dispute. Appeal File, CBCA 84,

Exhibit 10 at ¶¶ 16, 17, 19. BSC and the Coast Guard tried to resolve the issue during a

conference call on October 10. Id. at ¶ 20. The Government stated that paragraph 3.6

required the contractor to renew all software. Id. The contractor responded that it was

following the manufacturer’s recommendations for gasket replacement and that the

manufacturer did not recommend replacing them. Id. After the telephone conference, BSC

stopped work on the item. On that same day, BSC’s contract administrator, Julie Koch, sent

an e-mail message to the contracting officer, stating:

Bay Shipbuilding understands the Coast Guard’s interpretation

of para 3.6 as to the renewal of software, however, we feel that

CBCA 54, 84

5

we are in following [sic] with the manufacturer’s

recommendations for gasket replacement as stated in para. 3.7.

Work has stopped on this job and we cannot move forward until

this matter is settled.

Id., Exhibit 8K. The contracting officer disagreed with BSC’s characterization, responding

that “[w]ork has stopped on this work item because you refuse to comply with the contractual

requirements to replace the gaskets.” Id., Exhibit 8L.

Mr. Thayse wrote in an e-mail message dated October 13, 2005, that “as stated many

times in the last few days the work has stopped because your crew has refused to allow BSC

to proceed with the work items. . . .” Appeal File, CBCA 84, Exhibit 8M. The Coast Guard

responded by letter dated October 13, 2005, which stated in pertinent part:

Bay Shipbuilding has refused to complete Work item 3 . . . .

Specifically, Bay Shipbuilding has refused to purchase the

gaskets needed to complete the work item in accordance with

the specification.

....

Bay Shipbuilding must proceed with the performance of this

contract pending final resolution of any dispute arising under it.

Bay Shipbuilding otherwise will be liable for default of this

contract. Any delay in completion of this work item is the

responsibility of Bay Shipbuilding. The Coast Guard will

purchase the gaskets specified to be replaced in work item 3 in

order to ensure that this work item is completed in accordance

with the specification. However, the Coast Guard also reserves

the right to deduct the cost of the gaskets from the total contract

price as a requirement of your contract as awarded.

Id., Exhibit 8N. The Coast Guard purchased the gaskets for a cost of $17,275.26. Id.,

Exhibit 8O.

On October 13, 2005, Jack Dafgek, Alfa Laval’s Technical Support Manager, sent

BSC a letter in which he reiterated Mr. O’Conner’s opinion that the gaskets could be reused.

Appellant’s Submission at 21; Appellant’s Initial Position Statement, Exhibit P. BSC

provided a copy of the letter to the Coast Guard. Thayes Declaration ¶ 53.

CBCA 54, 84

6

On October 13, 2005, CWO Johnson issued a contract deficiency report for BSC’s

failure to have timely ordered the proper gaskets for the main diesel engine coolers. Appeal

File, CBCA 84, Exhibit 8E. In the portion of the form entitled “Contractor’s Response,” Ms.

Koch contended that BSC would have ordered the replacement gaskets if necessary. Id. On

October 14, 2005, BSC installed the gaskets for the MDE heat exchangers under the direction

of the Alfa Laval technical representative. Id. at ¶ 55.

By final decision dated October 28, 2005, the contracting officer stated:

Concerning work item 3 Clean, Inspect and Test Heat

Exchangers, by Contract Deficiency Report 003 dated October

13, 2005, Bay Shipbuilding refused to perform the work item as

written that specifically required at paragraph 3.6 to “renew all

software (seals, gaskets, O-rings). . .” By definition RENEW

means “. . . Permanently remove an item and install, in its place,

a new and unused item which is identical in material, form, fit

and function . . .” This definition is located in MLCA STD

000_STD 2004 Edition, General Requirements. Your refusal to

perform places your company in breach of the contract. The US

Coast Guard purchased the necessary gaskets at a cost of

$17,275.36. This cost is being taken from your funds otherwise

due your company under this contract.

Appeal File, CBCA 84, Exhibit 8P. BSC appealed the final decision by letter dated

November 9, 2005. Id., Exhibit 3.

Discussion

The question presented in this appeal is whether the Coast Guard has established that

it is entitled to damages of $17,275.36 for BSC’s alleged breach of contract. As a matter of

law, the Coast Guard bears the burden of proof for its claim. Whitesell-Green, Inc., ASBCA

53938, et al., 06-2 BCA ¶ 33,323 at 165,257 (citing Southwest Welding & Manufacturing Co.

v. United States, 413 F.2d 1167, 1176 n.7 (Ct. Cl. 1969); Insulation Specialities, Inc.,

ASBCA 52090, 03-2 BCA ¶ 32,361, at 160,100-01). As the Government is claiming that it

is entitled to collect damages from appellant, it must prove that it is entitled to assess

damages in the amount claimed. Id. This means that the Government must prove each

element by a preponderance of the evidence. Id. (citing 9 Wigmore, Evidence § 2485

(Chadbourn rev. 1981)).

CBCA 54, 84

7

The Coast Guard states that the contract expressly required BSC to “renew all

software (seals, gaskets, O-rings) and isolation fittings in accordance with the manufacturer’s

specifications.” The contract defined “renew” as to “permanently remove an item and install,

in its place a new and unused item which is identical in material, form, fit and function.”

Accordingly, the Coast Guard contends that the only option presented by the contract

required BSC to replace all software, including the gaskets.

BSC challenges the Government’s claim, contending that the contract did not require

the gaskets to be replaced except in accordance with the manufacturer’s specifications. BSC

states that it intended to replace the gaskets if advised to do so by the technical representative

from Alfa Laval. In that event, BSC intended to submit a CFR for the cost of replacing the

gaskets. BSC asserts that the technical representative permitted re-use of the existing

gaskets, and, accordingly, BSC was not required to replace the gaskets.

This dispute requires contract interpretation. The Board will interpret a contract in

such a way as to give words their plain and ordinary meaning. Id. at 747-48 (citing Moran

v. Prather, 90 U.S. 492, 499 (1874); Forman v. United States, 329 F.3d 837, 842 (Fed. Cir.

2003); McAbee Construction, Inc. v. United States, 97 F.3d 1431, 1435 (Fed. Cir. 1996);

Elden v. United States, 617 F.2d 254, 260-61 (Ct. Cl. 1980)). A contract must be “interpreted

so as to harmonize and give meaning to all its provisions, and [thus] an interpretation which

gives a reasonable meaning to all parts is preferred to one which leaves a portion of it

useless, inexplicable, inoperative, void, insignificant, meaningless, superfluous, or achieves

a weird and whimsical result.” Arizona v. United States, 575 F2d 855, 863 (Ct. Cl. 1978);

see also, e.g., Gould, Inc. v. United States, 935 F.2d 1271, 1274 (Fed. Cir. 1991); United

States v. Johnson Controls, Inc., 713 F.2d 1541, 1555 (Fed. Cir. 1983).

Here, the contract required BSC to “renew all software (seals, gaskets, O-rings) and

isolation fittings/mounts in accordance with the manufacturer’s specification.” “Renew” is

defined by the contract to mean to “permanently remove an item and install, in its place a

new and unused item which is identical in material, form, fit and function. . . .” The

definition of “renew” did not include anything that could be interpreted as permitting an item

to be “reused.” Thus, the plain language of the contract called for the contractor to

permanently remove all software and install, in its place, new and unused items identical to

those items replaced.

BSC’s argument that it could reuse the gaskets ignores the plain meaning of the

contract definition of “renew.” Consistent with the definition contained in the contract,

“renew” means to replace the item, not to repair or reuse. Thus, the only reasonable

interpretation is that the contract required BSC to replace the gaskets. The contract refers

to the manufacturer’s specifications for the purpose of requiring the contractor to follow the

CBCA 54, 84

8

manufacturer’s procedures and standards for reassembly. This interpretation is consistent

with the contract requirement that the contractor obtain the services of a technical

representative who is authorized to “assist with the proper cleaning, inspecting, and testing

of the heat exchanger, inspection and reassembly of the system.” Even if the manufacturer’s

technical representative concluded that the gasket could be reused, that conclusion does not

supercede the contractual requirement to replace, i.e., to renew, the gaskets.

In any event, even if the contractor disputed the Government’s interpretation of the

contract requirements, both the Contract Disputes Act (CDA) and the Disputes clause 1 of the

Federal Acquisition Regulation (FAR) provide that pending a final decision of an appeal,

action, or final settlement, a contractor shall proceed diligently with performance of the

contract in accordance with the contracting officer’s decision. 41 U.S.C. § 605(b) (2000);

48 CFR 52.233-1 (2004). In this case, we find that because the contract did require BSC to

replace the gaskets and BSC failed to purchase the gaskets necessary to fulfill the contract

requirements, the Government is entitled to be reimbursed for costs arising from BSC’s

failure to act. The Government has presented uncontroverted evidence that it purchased the

new gaskets for a total cost of $17,275.36. Therefore, we find that the Government is

entitled to be reimbursed for the cost of the gaskets, i.e., $17,275.36.

II.

CBCA 54: Hull Paint Thickness Claim

Findings of Fact

In 2002, the Coast Guard contracted with Marinette Marine Corporation (MMC) in

Marinette, Wisconsin, to build the USCG Hollyhock. Lt. Loring A. Small, a Coast Guard

engineer assigned to the Coast Guard Project Resident Office at MMC, conducted

inspections during ship construction and assisted the contracting officer with basic contract

administration. During the construction of the Hollyhock, Lt. Small observed that the paint

thickness on the underwater body exceeded the paint thickness recommended by the

construction contract and by the paint manufacturer’s application guidelines. Appeal File,

CBCA 54, Exhibit 27 at 3.

During a subsequent inspection of the underwater hull prior to delivery of the

Hollyhock to the Coast Guard, a diver’s inspection revealed that paint had fallen off,

1

Although the contract documents do not appear to contain a Disputes clause,

the clause is incorporated as a matter of law into the contract pursuant to the Christian

doctrine. See G.L. Christian & Associates v. United States, 312 F.2d 418, 426 (Ct. Cl. 1963).

CBCA 54, 84

9

exposing bare steel in places. Accordingly, MMC subcontracted with BSC to correct the

defective paint.2 Appeal File, CBCA 54, Exhibit 27 at 3.

BSC blasted the hull to remove all loose paint and then repainted the hull. BSC’s

paint foreman, Jack Schmidt, supervised the paint operation. The Coast Guard accepted

delivery of the Hollyhock on October 24, 2004. Appeal File, CBCA 54, Exhibit 25 at 5.

On June 9, 2005, in response to the Government’s solicitation of bids for drydock

repairs of the USCGC Hollyhock, BSC submitted a bid of $53,800 for Work Item 2. Appeal

File, CBCA 54, Exhibit 26 at 2. Work Item 2 of the contract required BSC to remove and

reapply the underwater body hull paint system of the USCGC Hollyhock. BSC’s bid

included the cost of sandblasting paint from the underwater body hull. Appellant’s

Submission, Declaration of Todd Thayse (November 10, 2006) ¶ 17. However, the contract

did not provide BSC with any information about the thickness of the paint to be removed, nor

did BSC inquire about it. Id. at ¶ 20.

On August 3, 2005, the contracting officer sent an e-mail message to BSC,

questioning the amount of BSC’s bid for Work Item 2 because the bid was substantially

lower than the Government’s estimate. BSC responded to the contracting officer’s inquiry

at 12:38 p.m. on that same day, August 3, and asked to review the Government’s estimates.

Appeal File, CBCA 54, Exhibit 4. By e-mail message sent at 1:57 p.m., the contracting

officer agreed to check on the item. Id., Exhibit 5. The contracting officer contacted BSC

by e-mail message at 3:51 p.m and told BSC that she had not yet received the information

for the government estimate. Ms. Koch responded by e-mail message at 4:02 p.m., stating:

Kathy, Underwater body detail – if you get it, fine, but let’s keep

the ball moving. We are ready to stand by the pricing submitted.

Id., Exhibit 6; Position Paper of Bay Shipbuilding Company in Support of its Claim for the

Cost of Removing Excess Paint From the Underwater Body Hull of the Hollyhock

(Appellant’s Position Paper), Exhibit B, Declaration of Julie Koch (November 9, 2006) ¶ 12.

The contracting officer did not provide BSC with any additional information about the

government’s estimate for Work Item 2.

2

The Manitowoc Company, Inc., owns both MMC and BSC. See Thayse

Declaration ¶ 8.

CBCA 54, 84

10

The contract included a provision entitled Site Visit (APR 1984), 48 CFR 52.237-1,

which stated:

Offerors or quoters are urged and expected to inspect the site

where services are to be performed and to satisfy themselves

regarding all general and local conditions that may affect the

cost of contract performance, to the extent that the information

is reasonably obtainable. In no event shall failure to inspect the

site constitute grounds for a claim after contract award.

Appeal File, CBCA 54, Exhibit 5 at 11. There is no evidence that BSC took the opportunity

to perform a site visit,3 request access to the ship, review the paint logs included in the

documents of the hull history, or ask about the thickness of the underwater body paint prior

to submitting its bid. Id., Exhibit 25, Declaration of Vanessa A. Nemara (November 27,

2006) ¶ 19; Exhibit 26, Declaration of Kathryn E. Stark (December 4, 2006) ¶ 6.

Once BSC confirmed its bid on Work Item 2, the Coast Guard awarded the contract

on August 9, 2005. On September 7, 2005, BSC reported to the Coast Guard that BSC had

discovered higher than standard coating on the underwater hull of the vessel. Appeal File,

CBCA 54, Exhibit 10; Thayse Declaration ¶ 30, Exhibit F. BSC noted that “especially high

readings” were found in the sea chests (boxes inside the hull that take cooling water) and

thruster tunnels (tunnels which help maneuver the vessel in port), which were part of the

underwater body hull. Thayse Declaration ¶ 30, Exhibit F. BSC sought additional

compensation for the cost of removing the excess paint.

CWO Johnson denied BSC’s request for additional compensation on September 7,

2005. Thayse Declaration ¶ 31, Exhibit G. CWO Johnson stated:

Bay Ship [Building] Company has been the only contractor to do

any Underwater Body Paint repair on the Hollyhock. If the

paint system has been applied not IAW [sic] they had some part

in the process. For this work item BSC had more information

than any other bidder, due to there [sic] past work. . . . Thruster

tunnels and sea chests were not part of the paint repair in Oct 03.

This area may need to be addressed.

3

BSC argues that it was not reasonable for the contractor to incur the costs of

traveling to the site for a site investigation, nor would a site investigation have necessarily

revealed the thickness of the paint on the underwater hull.

CBCA 54, 84

11

Appeal File, CBCA 54, Exhibit 11; Thayse Declaration ¶ 31, Exhibit G. CWO Johnson told

BSC to prepare another CFR about the excess paint on the sea chests and thruster tunnels.

Thayse Declaration ¶ 32, Exhibit H. Upon receipt, the Coast Guard approved an equitable

adjustment of $4801 for the additional costs of removing the paint millage from the sea

chests and thruster tunnels. Thayse Declaration ¶ 33, Exhibits H-J.

On December 7, 2005, BSC submitted a formal request for an equitable adjustment

for $23,125, the costs incurred in removing the excess paint from the remainder of the

underwater body hull. Appeal File, CBCA 54, Exhibit 34; Koch Declaration ¶ 30, Exhibit

J. The contracting officer denied the request by decision dated January 30, 2006, asserting

that BSC had superior knowledge of the thickness of the underwater hull paint based upon

the fact that BSC had applied the paint in question during construction of the USCGC

Hollyhock. Appeal File, CBCA 54, Exhibit 35; Koch Declaration ¶ 33, Exhibit K. The

contracting officer stated:

It is the Contracting Officer’s determination that the U.S. Coast

Guard is not responsible for compensating Bay Shipbuilding for

the removal of the underwater body hull paint beyond what was

paid as part of this contract. You can not [sic] create the

situation under one contract [the construction contract] and

obtain additional compensation under another for a situation that

you alone created.

Appeal File, CBCA 54, Exhibit 35. BSC appealed the contracting officer’s decision.

Discussion

BSC contends that it encountered difficulties in removing the paint from the

underwater body hull because the existing coat exceeded the amount of paint that BSC had

anticipated when it bid the project. BSC argues that the Government possessed superior

knowledge about the condition of the hull based upon the fact that the Government initially

questioned BSC’s estimate as being too low. BSC states that the extra costs involved in

removing excessive paint accounted for the difference between BSC’s estimate and the

Government’s. BSC argues that it had no reason to suspect that the underwater hull had

excessive paint and, therefore, did not account for the excessive thickness when it prepared

its bid. BSC claims that it incurred actual additional labor and material costs of $23,125 to

remove the additional millage from the underwater body hull.

BSC can establish entitlement to an equitable adjustment only if it can prove that the

Government had misrepresented the amount of paint present on the underwater hull or

CBCA 54, 84

12

possessed superior knowledge about the paint thickness. See Walker Boat Yard, Inc.,

DOTBCA 4133, 03-2 BCA ¶ 32,397, at 160,324 (citing United States v. Spearin, 248 U.S.

132, 136 (1918); Marine Industries Northwest, Inc., ASBCA 51942, 01-1 BCA ¶ 31,201,

at 154,043. As there is no evidence suggesting that the Government misrepresented the

condition of the hull, BSC’s argument must focus upon its contention that the Government

possessed superior knowledge about the underwater hull.

BSC has the burden of establishing that the Government possessed superior knowledge

about the condition of the underwater hull paint. AT&T Communications, Inc. v. Perry, 296

F.3d 1307, 1312 (Fed. Cir. 2002); Hercules, Inc. v. United States, 24 F.3d 188, 196 (Fed. Cir.

1994). The superior knowledge doctrine imposes an implied affirmative duty upon a

contracting agency “to disclose to a contractor otherwise unavailable information regarding

some novel matter affecting the contract that is vital to its performance.” Giesler v. United

States, 232 F.3d 864, 876 (Fed. Cir. 2000). When analyzing a claim that the Government

breached its duty to disclose superior knowledge, the Board “must focus its inquiry on the

government’s knowledge at the time of contracting and its relationship to the contractor’s lack

of knowledge.” L.W. Matteson, Inc. v. United States, 61 Fed. Cl. 296, 316 (2004); accord

Max Jordan Bauunternehmung v. United States, 10 Cl. Ct. 672, 679 (1986) (“The

government’s liability for failure to provide information arises from a conscious omission to

share superior knowledge it possesses in circumstances where it permits a contractor to pursue

a course of action known to be defective.”). Appellant has not met this burden because it has

failed to establish that the Government possessed knowledge that the contractor did not.

BSC presents declarations from various witnesses to show that the Coast Guard knew,

but failed to disclose to BSC, that the paint on the hull was excessively thick. On this point,

the Government does not dispute the fact that it knew about the condition of the paint when

it accepted the ship in 2004. Rather, although the Government does not necessarily agree that

the paint on the hull was excessively thick, the Government has submitted uncontroverted

Declarations showing that the contractor had the same information as did the Government

about the condition of the hull based upon the fact that BSC had been hired as the painting

subcontractor in 2003 and painted the hull. Specifically, Lt. Small stated that he worked at

the Coast Guard Project Resident Office at Marinette Marine Corporation (MMC) in

Marinette, Wisconsin, from July 2002 until May 2004, as the contracting officer’s technical

representative. During that time period, Lt. Small conducted inspections during the

construction of the USCGC Hollyhock and discovered the application of excessive paint on

the underwater hull. He reported this to the prime contractor, MMC, which subcontracted

with BSC to repaint the hull. The same BSC personnel, specifically BSC paint foreman Jack

Schmidt and BSC’s Julie Koch, worked on BSC’s subcontract to repaint the underwater hull

in 2003 and on the current contract.

CBCA 54, 84

13

We conclude that appellant has failed to meet its burden of proving by a preponderance

of the evidence that the Government withheld superior knowledge. Both parties knew about

the thickness of the paint applied during the construction of the ship. Appellant has presented

no evidence to establish that the data available to each had changed based upon a subsequent

paint job or any other circumstance known only to the Government.

Moreover, the fact that the Government asked BSC to review its bid for the paint work

because it was substantially lower than the Government’s estimate should have put BSC on

notice that the its bid should be reexamined. However, when the Government did not respond

to BSC’s request for information regarding the Government’s estimate as quickly as BSC

wanted, BSC elected to confirm its bid without further investigation. This may have been

poor judgment by BSC, but it is not a ground for recovery. In any event, as stated above, BSC

knew or should have known the same information as the Government concerning the

underwater hull.

In addition to its argument that the Government possessed superior knowledge about

the condition of the paint, BSC contends that the Government’s arguments on appeal must be

rejected because they are different from the facts and conclusions set forth in the contracting

officer’s final decision quoted above. Appellant’s Reply Brief at 4 (“[T]he appeal should be

decided solely on the grounds set forth in the Contracting Officer’s final decision.”). BSC is

incorrect on this point. “[W]here an appeal is taken to a board or court, the contracting

officer’s award” of time or money “is not to be treated as if it were the unappealed

determination of a lower tribunal which is owed special deference or acceptance on appeal.”

Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987). Because the findings

of fact in the contracting officer’s final decision are not binding on the parties, the contractor

bears the burden of proving by preponderant evidence “the fundamental facts of liability and

damages de novo.” Wilner v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994)(en banc).

Further, “a contractor is not entitled to the benefit of any presumption arising from the

contracting officer’s decision. De novo review precludes reliance upon the presumed

correctness of the [prior] decision.” Id. (citing Renegotiation Board v. Bannercraft Clothing

Co., 415 U.S. 1, 23 (1974)). Therefore, the Board is not bound by the contracting officer’s

final decision in reaching its findings on appeal.

Decision

These appeals are DENIED. The Government’s claim for $17,275.36 in CBCA 84 is

granted. BSC’s claim for $23,125 in CBCA 54 is denied.

__________________________

JERI KAYLENE SOMERS

Board Judge

CBCA 54, 84

14

We concur:

____________________________

JAMES L. STERN

Board Judge

_______________________________

EILEEN P. FENNESSY

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.