GRANTED: June 20, 2013
Agency decision
Ask Donna
What actually matters in this document.
Text
GRANTED: June 20, 2013
CBCA 2709
IAP WORLD SERVICES, INC.,
Appellant,
v.
DEPARTMENT OF THE TREASURY,
Respondent.
David J. Craig of IAP World Services, Inc., Cape Canaveral, FL, counsel for
Appellant.
Marianna Lvovsky, Office of Chief Counsel, Internal Revenue Service, Department
of the Treasury, Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), SHERIDAN, and STEEL.
DANIELS, Board Judge.
The Internal Revenue Service (IRS), an entity within the Department of the Treasury,
awarded a firm, fixed-price contract to IAP World Services, Inc.1 (IAP) for “all management,
1
The contract was awarded to IAP World Services, Inc. The company is also
referred to, in some filings with the Board, by the name of its parent company, IAP
Worldwide Services, Inc. See, as to the relationship between the two firms,
<<http://investing.businessweek.com/research/stocks/private/snapshot.asp?privcapId=
(continued...)
CBCA 2709
2
supervision, labor, materials, supplies, and equipment necessary for operation and
maintenance of building equipment at [six] IRS facilities.” IAP has filed two claims for
reimbursement of costs it incurred, in addition to those it expected, in performing fixed-price
portions of the contract. The contracting officer denied both of the claims, and IAP
appealed. Last year, we denied the appeal of one of those claims, for removal of snow from
the facility in Ogden, Utah. IAP World Services, Inc. v. Department of the Treasury, CBCA
2633, 12-2 BCA ¶ 35,119. We now consider the appeal of the other claim, for performance
of service calls at the facility in Philadelphia, Pennsylvania.
The IRS maintains that this claim is much like the snow removal matter and should
be denied for like reasons. IAP contends that this one is quite different from the other. We
agree with the contractor and grant this appeal.
Findings of Fact
The IRS awarded the contract to IAP on August 31, 2005. The contract covered a
phase-in period, which per amendment 1 ran until March 13, 2006, and five option periods,
each one year in duration, with the first beginning on March 14, 2006. The IRS exercised
all of the options and later extended the contract through May 8, 2011.
The contract required IAP to provide “basic services,” including facility operation and
performance of service calls and repairs required by the Government, for a fixed price in
each contract period. (Some work could be ordered at additional cost, but the parties agree
that it is not relevant to this appeal.) A “service call” was defined by the contract to be a
demand by the Government to remedy unscheduled building-related problems. Examples
given were “taking measures to respond to and correct building related deficiencies such as
malfunctioning HVAC [heating, ventilation, and air conditioning] systems resulting in
hot/cold complaints, miscellaneous electrical, plumbing, architectural, carpentry, and
structural system repairs.” The contract’s fixed price included the first $2500 of labor,
materials, and subcontract costs of work under each service call.
The IRS included in the request for proposals (RFP) which led to this contract
technical exhibits which showed service call history, equipment to be maintained, and
government furnished items at the various facilities. Among the technical exhibits was
number TE-3-PA, which was entitled “Philadelphia Service Call Analysis FY [fiscal year]
03.” This exhibit shows that during January, February, and March of 2003, there were 472
1
(...continued)
4235284>> (last visited June 19, 2013).
CBCA 2709
3
service calls at the Philadelphia facility and that the service call labor hours there were
distributed in the following way:
Duration
Equal to or less than 1 hour
More than 1 hour to equal to or less than 4 hours
More than 4 hours to equal to or less than 8 hours
More than 8 hours to equal to or less than 12 hours
More than 12 hours to equal to or less than 32 hours
More than 32 hours
Percentage
88.1%
11.4%
0.4%
0.0%
0.0%
0.0%
Questions posed by prospective offerors, and responses to those questions, were
published by the IRS in amendments to the RFP. The interchange demonstrated that
prospective offerors were concerned that the data provided by the agency did not give them
enough information to price the contract work. One company asked the agency to consider
an alternative pricing arrangement. This request was refused. Another company asked for
data covering longer periods of time for several locations, including Philadelphia. The
agency said that it had already provided all available historical data, notwithstanding the fact
that the IRS had been performing all relevant work itself at the Philadelphia site for the
previous five years.
The matter was also raised in this comment by a prospective offeror:
Sub-Factor 2. Service Calls has . . . requirements[] which are difficult to
estimate based upon the uncorrelated data provided by the government . . . , the
limited on-site time available for an examination (with no questions answered
and no documents provided when requested per the CO’s [contracting
officer’s] guidance), and incomplete historical information related to service
calls generated. . . . Additionally, this contract is a firm-fixed price contract,
and as such it is up to the contractor to determine what equipment and supplies
are required to perform the work and to have those available to accomplish the
task. To estimate requirements without having any parameters related to the
work is both risky and foolish.
The IRS responded with the following statement:
Sufficient information on building requirements and equipment is contained
in the Technical Exhibits. When used in conjunction with the offeror’s
experience, it provides a reasonable basis to determine materials and
CBCA 2709
4
equipment required to support service call work under $2,500 and service call
materials that should be stocked on-site.
IAP states, and the IRS does not contest, that the contractor proposed its price for
service calls at the Philadelphia facility in reliance on the data provided by the agency in the
RFP. IAP has not provided documentation explaining how it constructed that price, but
because the IRS does not assert that the price was unreasonable, we have no basis for finding
it to be other than reasonable.
In performing the contract, IAP found that it was spending considerably more time
per service call in Philadelphia than had been noted in RFP exhibit TE-3-PA. The contractor
said that its actual labor hour distribution was as follows:
Duration
Percentage
Equal to or less than 1 hour
More than 1 hour to equal to or less than 4 hours
More than 4 hours to equal to or less than 8 hours
More than 8 hours to equal to or less than 12 hours
More than 12 hours to equal to or less than 32 hours
More than 32 hours
72.3%
24.4%
2.4%
0.7%
0.2%
0.0%
The contractor said that for the period between March 2006 and September 2008, its
proposed price for basic service calls in Philadelphia was $279,797.83 and its actual costs
were $759,963 – $480,165.17 more than proposed. It claimed, however, only $308,879.57,
after reducing its number in response to the IRS’s concern that IAP may have been spending
so much time because the skill level of its employees was substandard. The certified claim
was dated August 9, 2011.
The contracting officer denied the claim on the ground that the contract “was awarded
as a firm fixed-price contract and is not subject to any adjustment on the basis of the
contractor’s actual cost experience in performing the contract.” IAP appealed from this
decision.
Discussion
As we explained in our decision on the snow removal claim –
The Federal Acquisition Regulation explains that “[a] firm-fixed-price contract
provides for a price that is not subject to any adjustment on the basis of the
CBCA 2709
5
contractor’s cost experience in performing the contract. This contract type
places upon the contractor maximum risk and full responsibility for all costs
and resulting profit or loss.” 48 CFR 16.202-1. “It is well-established that
absent a special adjustment clause, a contractor with a fixed price contract
assumes the risk of increased costs not attributable to the Government.”
Southwestern Security Services, Inc. v. Department of Homeland Security,
CBCA 1264, 09-2 BCA ¶ 34,139, at 168,777 (citing Gulf Shores, LLC v.
Department of Homeland Security, CBCA 802, 09-1 BCA ¶ 34,024, at
168,305 (2008)).
12-2 BCA at 172,445.
The IRS would have us believe that these statements resolve the Philadelphia service
call claim as well. They do not. As to this matter, the agency specifically told prospective
offerors that the information contained in the RFP’s technical exhibits, including the exhibit
for the Philadelphia facility, should be a basis for determining costs. IAP followed this
instruction and based its offer on that information. We held in Admiral Elevator v. Social
Security Administration, CBCA 470, 07-2 BCA ¶ 33,676, that when an agency directs
offerors to base their contract prices on material, incorrect representations, and the contractor
does so to its detriment, the agency is responsible for the losses which the contractor
consequently suffers. This principle clearly applies to the case now before us. While there
may not have been a “special adjustment clause” explicitly written into the contract, the
agency’s direction as to pricing serves the same purpose as such a clause. The IRS, having
told IAP to base its costs on certain data, must bear the risk that that data did not accurately
represent conditions that the contractor found on the job.
Having disposed of the case in this way, we have no need to make determinations with
regard to various issues raised by IAP -- whether the inaccuracy of the data was caused by
negligence, whether the agency did not disclose superior knowledge about service call
requirements, or whether the increased workload made performance commercially
impracticable. Very simply, we conclude that because the data on which the agency told the
contractor to rely in pricing the contract was faulty, the contractor relied on that data, and the
contractor had to perform work beyond the agency’s representations, the resulting additional
work constituted a constructive change, and the agency must pay for the consequences of that
change. The situation is markedly different from that in the snow removal claim, where the
agency simply provided historical data to prospective offerors and did not direct them to
price their proposals in reliance on that data.
The IRS has made no comment on IAP’s cost calculations, so we accept the
contractor’s claimed amount as reasonable.
CBCA 2709
6
Decision
The appeal is GRANTED. The Internal Revenue Service shall pay to IAP World
Services, Inc. the amount of the August 9, 2011, claim, $308,879.57, plus interest on that
sum from the date the contracting officer received the claim until the date of payment. 41
U.S.C. § 7109 (Supp. IV 2011).
_________________________
STEPHEN M. DANIELS
Board Judge
We concur:
________________________
PATRICIA J. SHERIDAN
Board Judge
_________________________
CANDIDA S. STEEL
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.