CBCA 6149 GRANTED IN PART; CBCA 7071 AND CBCA 7597 DENIED:
Agency decision
Ask Donna
What actually matters in this document.
Text
CBCA 6149 GRANTED IN PART; CBCA 7071 AND CBCA 7597 DENIED:
March 21, 2025
CBCA 6149, 7071, 7597
ALARES CONSTRUCTION, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Douglas L. Patin and Lee-Ann C. Brown of Bradley Arant Boult Cummings LLP,
Washington, DC, counsel for Appellant.
Jennifer L. Hedge, Office of General Counsel, Department of Veterans Affairs,
Pittsburgh, PA; and Kathleen E. Ramos, Office of General Counsel, Department of Veterans
Affairs, Arlington, TX, counsel for Respondent.
Before Board Judges LESTER, RUSSELL, and ZISCHKAU.
LESTER, Board Judge.
These appeals are before us following a five-day hearing that was conducted in March
2023 before Judge Jerome M. Drummond. During post-hearing briefing, Judge Drummond
unexpectedly passed away. After a new presiding judge was assigned to the appeals, the
parties elected to rely on the transcripts of the March 2023 hearing rather than again to
present witnesses for live testimony before the new presiding judge. The parties also
provided extensive and helpful closing arguments to the new presiding judge.
CBCA 6149, 7071, 7597
2
In CBCA 6149, appellant, Alares Construction, Inc. (Alares), seeks to recover
damages of $1,691,701.85 (a figure that has been revised several times during the course of
litigation) for delays and changes on a construction project at a Department of Veterans
Affairs (VA) medical center but with a reduction to its claimed general conditions costs to
account for its settlement and release of some of its earlier claims under this contract. With
the reduction, Alares tells us, the claim is approximately $1.5 million. Closing Argument
Transcript (Oct. 18, 2023) at 66. Alares asserts that the VA caused all 765 days of delay on
this project, but it seeks to recover extended general conditions for only 653 of those days.
Appellant’s Corrected Pre-Hearing Brief (Mar. 7, 2023) at 5.
Following a thorough review of the record, we find that, although there were some
defects in the specifications for the project that had to be addressed and corrected, which cost
Alares time and money and for which the VA is responsible, the project design was not, as
Alares alleges, “riddled with fundamental design errors.” Appellant’s Corrected Pre-Hearing
Brief at 1. To the contrary, much of the delay on this project was the result of Alares’
difficulty in managing and coordinating the work of its subcontractors. We reject Alares’
contention that the VA’s issuance of cure notices and a show cause notice, as well as the
VA’s purported refusal to acknowledge its alleged responsibility for changes in a timely
manner, were motivated by fears about not having sufficient appropriations to fund the
contract or as retaliation for Alares’ submission of claims. We find that, in CBCA 6149, the
VA is responsible for 218 days of delay to the critical path of performance on this project but
that Alares bears responsibility for the remaining delays.
In CBCA 7071, Alares seeks to recover direct costs associated with alleged extra work
to the patient lift supports in several rooms of the building, and, in CBCA 7597, Alares
asserts entitlement to the same damages that it seeks in CBCA 6149 on the basis of the VA’s
alleged breach of the implied duty of good faith and fair dealing. We deny both of those
appeals.
Findings of Fact
I.
The Contract
On April 28, 2016, the VA awarded a firm-fixed-price construction contract (contract
VA241-16-C-0037 (the contract)) to Alares1 for the replacement/relocation of the deficient
1
The contract was originally awarded to Alares LLC, see Appeal File, Exhibit
1 at 2, but, on May 25, 2016, was novated through contract modification P00001 to identify
Alares Construction, Inc., as the contractor. Appeal File, Exhibit 14 at 1-31.
CBCA 6149, 7071, 7597
3
Intensive Care Unit (ICU) at the Providence VA Medical Center in Providence, Rhode
Island, for a lump-sum price of $7,753,880.20. Appeal File, Exhibit 1 at 1-2.2 The project
required the construction of a two-story addition to an existing building. See Exhibit 12.
Alares was to connect the addition to the existing building through an elevated hallway,
which would run between the second floor of the addition and a second-floor opening in the
existing building. See id. Contract duration was to be 425 calendar days from the date that
the VA issued the Notice to Proceed (NTP). Exhibit 1 at 3.
Under the contract, Alares was required to coordinate all aspects of the construction
work in a manner that would avoid delays and ill-timed work:
GENERAL PROJECT COORDINATION
A.
The Contractor shall be responsible to uncover work completed in order
to install ill-timed work, at no additional cost to the Owner.
B.
Where space is limited, coordinate installation of different components
to assure maximum accessibility for maintenance, service and repair.
C.
Coordinate space requirements and installation of mechanical and
electrical work which are indicated diagrammatically on Drawings.
Follow routing shown for pipes, ducts, and conduit, as closely as
practicable; place runs parallel with line of building. Utilize spaces
efficiently to maximize accessibility for other installations, for
maintenance, and for repairs.
D.
Verify that utility requirement characteristics of operating equipment
are compatible with building utilities. Coordinate work of various
Sections having interdependent responsibilities for installing,
connecting to, and placing in service such equipment.
.....
2
All exhibits referenced in this decision are found in the appeal file, unless
otherwise noted.
CBCA 6149, 7071, 7597
UTILITIES, MECHANICAL AND ELECTRICAL COORDINATION
A.
Coordinate all Work of this Project. Provide full and complete
coordination for utilities, mechanical and electrical work in Divisions
11, 13, and 21 through 28, with Work of other Divisions.
B.
Give all advance notice to public utility companies as required by law,
and provide proper disposition, subject to the Owner’s Project Manager
and the Architect’s approval of all existing pipe lines, conduits, sewers,
drains, poles, wiring, and other utilities that in any way interfere with
the Work, whether or not they are specifically shown on the Drawings.
C.
Coordination regarding existing utilities:
1.
Notify Owner and appropriate authorities when coming across
an unknown utility line(s), and await decision as to how to
dispose of same.
2.
When an existing utility line must be cut and plugged or capped,
moved, or relocated, or has become damaged, notify the Owner
and Utility company involved, and assure the protection,
support, or moving of utilities to adjust them to the new work.
3.
The Contractor shall be responsible for all damage caused to
existing, active utilities located within the limits of this Contract,
whether or not such utilities are shown on the Drawings,
including resultant damages or injuries to persons or properties.
D.
General coordination of piping, ductwork, conduits and equipment:
1.
The Contract Drawings are diagrammatic only intending to
show general runs and general locations of piping, ductwork,
equipment and sprinkler heads. Determine exact routing and
location of individual systems prior to fabrication of
components or installation. . . .
2.
Adjust locations of piping, ductwork, conduits and equipment as
required to accommodate new work with interferences
anticipated and as encountered during installation. . . .
3.
Provide all offsets, transitions and changes of direction for all
systems, as may be required to maintain proper clearances for
headroom, and as may be required for coordination with other
“fixed-in-place” building components (such as structural
systems). . . .
4
CBCA 6149, 7071, 7597
4.
5.
5
Provide openings in the work for penetration of mechanical and
electrical work.
Coordinate final locations of ceiling mounted devices (including
air distribution devices, thermostats, heaters, control devices,
sprinkler heads and similar work) with reflected ceiling plans.
Review locations with the Owner’s Project Manager and the
Architect and obtain approval of all devices prior to installation.
Exhibit 6 at 46-48.
The contract specifications required Alares to develop a critical path method (CPM)
plan for scheduling work on the construction project and to utilize and routinely update it as
the project work progressed:
The Contractor shall develop a [CPM] plan and schedule demonstrating
fulfillment of the contract requirements (Project Schedule), and shall keep the
Project Schedule up-to-date in accordance with the requirements of this section
and shall utilize the plan for scheduling, coordinating and monitoring work
under this contract (including all activities of subcontractors, equipment
vendors and suppliers). Conventional [CPM] technique shall be utilized to
satisfy both time and cost applications.
Exhibit 6 at 53. The project schedule had to “reflect the Contractor’s approach to scheduling
the complete project and . . . describe the activities to be accomplished and their
interdependencies,” with “[t]he work for each major trade . . . represented by at least one
summary activity, so that the work cumulatively show[ed] the entire project schedule.” Id.
at 54. The schedule had to show “the sequence of work activities/events required for
complete performance of all items of work.” Id. “Each activity/event on the schedule [was
required to] contain,” at a minimum, identification and a description of each activity/event,
duration, budget amount, early start date, early finish date, late finish date, and total float.
Id.
Under the contract’s terms, the project schedule had to be submitted to the VA
monthly to reflect any activity/event changes resulting from delays in completion of any
activity/event, delays in submittals that made rescheduling of work necessary, and/or
inaccuracies in how the project was actually progressing:
With each monthly submission of the updated project schedule, the Contractor
shall submit a list of any activity/event changes for any of the following
reasons:
CBCA 6149, 7071, 7597
1.
2.
3.
4.
6
Delay in completion of any activity/event or group of activities/events,
which may be involved with contract changes, strikes, unusual weather,
and other delays will not relieve the Contractor from the requirements
specified unless the conditions are shown on the CPM as the direct
cause for delaying the project beyond the acceptable limits.
Delays in submittals, or deliveries, or work stoppage are encountered
which make rescheduling of the work necessary.
The schedule does not represent the actual prosecution and progress of
the project.
When there is, or has been, a substantial revision to the activity/event
costs regardless of the cause for these revisions.
Exhibit 6 at 58. In addition to monthly schedule updates, Alares’ project manager was
required to meet weekly with the VA contracting officer’s representative (COR) “(or as
otherwise mutually agreed to) . . . for the purpose of jointly reviewing the actual progress of
the project as compared to the as planned progress and to review planned activities for the
upcoming two weeks.” Id. at 57.
The contract also incorporated a clause titled “Subcontracts and Work Coordination
(APR 1984)” from Veterans Affairs Acquisition Regulation (VAAR) 852.236-80 (48 CFR
852.236-80 (2016)), which placed full responsibility on Alares for its subcontractors and for
coordinating their work:
The contractor shall be responsible to the Government for acts and omissions
of his/her own employees, and of the subcontractors and their employees. The
contractor shall also be responsible for coordination of the work of the trades,
subcontractors, and material suppliers.
Exhibit 1 at 17 (VAAR 852.236-80(b)).
Alares’ cost proposal for the project, which was incorporated into the contract,
identified an overhead rate of 10%, calculated by applying 10% to the entire project, and a
profit rate of 7%. Exhibit 1 at 4. The contract incorporated the “Contract
Changes—Supplement (JUL 2002)” clause from VAAR 852.236-88, which included the
following provision about overhead and profit rates applicable to changes of $500,000 or less
that might be made during performance:
Allowances not to exceed 10 percent each for overhead and profit for the party
performing the work will be based on the value of labor, material, and use of
construction equipment required to accomplish the change. As the value of the
CBCA 6149, 7071, 7597
7
change increases, a declining scale will be used in negotiating the percentage
of overhead and profit. Allowable percentages on changes will not exceed the
following: 10 percent overhead and 10 percent profit on the first $20,000;
7-1/2 percent overhead and 7-1/2 percent profit on the next $30,000; 5 percent
overhead and 5 percent profit on balance over $50,000. Profit shall be
computed by multiplying the profit percentage by the sum of the direct costs
and computed overhead costs.
Id. at 20-21.
The contract incorporated by reference the clause at Federal Acquisition Regulation
(FAR) 52.242-14, Suspension of Work (APR 1984) (48 CFR 52.242-14 (2016)), see Exhibit
1 at 28, which includes the following provision:
If the performance of all or any part of the work is, for an unreasonable period
of time, suspended, delayed, or interrupted (1) by an act of the Contracting
Officer in the administration of this contract, or (2) by the Contracting
Officer’s failure to act within the time specified in this contract (or within a
reasonable time if not specified), an adjustment shall be made for any increase
in the cost of performance of this contract (excluding profit) necessarily
caused by the unreasonable suspension, delay, or interruption, and the contract
modified in writing accordingly. However, no adjustment shall be made under
this clause for any suspension, delay, or interruption to the extent that
performance would have been so suspended, delayed, or interrupted by any
other cause, including the fault or negligence of the Contractor, or for which
an equitable adjustment is provided for or excluded under any other term or
condition of this contract.
FAR 52.242-14(b).
The contract also incorporated by reference the clauses in FAR 52.243-4, “Changes
(JUN 2007)”; FAR 52.233-1, “Disputes (MAY 2014)”; FAR 52.236-2, “Differing Site
Conditions (APR 1984)”; and FAR 52.236-3, “Site Investigation and Conditions Affecting
the Work (APR 1984).” Exhibit 1 at 26-28.
The VA issued the Notice to Proceed on June 3, 2016, with an expected completion
date within 425 calendar days (or August 2, 2017). Exhibit 16.
CBCA 6149, 7071, 7597
II.
8
Performance Under the Contract
A.
Period 1 (June 3, 2016, to January 13, 2017)
1.
The Original Schedule Logic for Period 1
Period 1 covers the 212-day period of time running from June 3, 2016, through
January 13, 2017. Exhibits 3644 at 5, RS-0593 (Expert Report) at 7. At this time, Nick
Budris was Alares’ project manager. Hearing Transcript, Vol. 3, at 35.
Alares’ Chief Executive Officer (CEO), Donald Maggioli, developed the original
construction schedule for the project with the assistance of one of Alares’ construction
managers. Hearing Transcript, Vol. 1, at 43; see Exhibits 3644 at 4999, 5023-24. As set
forth in its original baseline schedule for the project, dated June 3, 2016, Alares planned to
complete pre-construction development drawings and submissions, to mobilize and prepare
the site, and to complete concrete placement and structural steel erection work during this
period. Exhibit 3644 at 5023. Alares identified various dates from June 3 through July 25,
2016, as its early start dates for the submission to the VA of general requirements and site
development plans, structural steel shop drawings, concrete submissions, and building
envelope submissions. Id. It planned to mobilize to the project site on August 22, 2016, id.,
after which, following installation of erosion control measures and other site protection work,
it would perform certain site and foundation development work (inclusive of excavating for
new footings, relocating existing utilities; installing new drainage, and pouring concrete
footings and columns) with an early start date of October 19 and an early finish date of
December 14, 2016; place structural steel columns, erect structural steel, and plumb and
detail structural steel, with an early start date of December 21, 2016, and an early finish date
of January 24, 2017; and cast the concrete column slab on the deck from January 25 to 31,
2017. Id. It would begin demolition of the existing building’s second floor hallway and
open an entryway, perform exterior sheathing and vapor barrier work, insulate and place
PVC roofing, and install interior wall framing from November 30, 2016, to January 12, 2017.
Exhibit 18 at 23.
Soon thereafter, though, Alares changed the logic behind some of its activities and
moved several activities earlier in time, significantly altering many “early start” dates from
what it had originally planned.3 Specifically, in updated schedules dated July 25 and
3
Up until January 2017, Mr. Maggioli prepared Alares’ monthly updates to the
construction schedule, utilizing Primavera scheduling software. Hearing Transcript, Vol. 1,
at 44-45. Alares then hired Project Controls, Inc. (PCI), to serve as its scheduling consultant,
CBCA 6149, 7071, 7597
9
September 26, 2016, Alares indicated that it would perform its site and foundation
development work beginning August 25 and ending October 27, 2016 (rather than a start of
October 19 and finish of December 14, 2016); place structural steel columns, erect structural
steel, and plumb and detail structural steel beginning October 28 and ending November 25,
2016 (rather than December 21, 2016, and January 24, 2017); and cast the concrete column
slab on the deck on November 28 and 29, 2016. Exhibit 18 at 3, 23. This logic restructuring
would allow Alares to progress earlier than previously planned to other activities that could
not reasonably be performed until the concrete deck was cast. Alares now planned to be in
a position to install mechanical, electrical, and plumbing (MEP) rough-in work in a portion
of the building beginning January 13, 2017. See id.
2.
Actual Performance in Period 1
Alares’ June 3, 2016, baseline schedule projected substantial completion of the project
by August 2, 2017. Tab A to Exhibit 3644; Tab B to Exhibit RS-0593. By the time that
Alares issued another schedule update (no. 4) on January 13, 2017, the projected substantial
completion date had moved to September 5, 2017, see Exhibit 3644 at 5; Tab B to RS-0593,
reflecting a critical path delay to the project during Period 1 of thirty-four days. Exhibits
3644 at 8, RS-0593 (Expert Report) at 7.4
The critical path of performance initially, and logically, focused on Alares’ set-up of
the construction site and its initial performance activities. The parties agree that, during the
initial months of the project, there were no critical path delays.
By October 2016, the critical path had turned towards the need to complete
foundational work, which was necessary to allow Alares to begin erecting structural steel.
The parties agree, or at least the VA does not contest, that the VA is responsible for at least
four critical delay days relating to completion of the foundation. Hearing Transcript, Vol. 4,
and, beginning in January 2017, Scott Danzer, a PCI employee, took over responsibility for
the monthly updates (with input from Mr. Maggioli). Id. at 45-46; Hearing Transcript,
Vol. 2, at 32.
4
In his report and testimony, Mr. Maggioli asserted that there were thirty-three,
rather than thirty-four, days of critical delay during Period 1—four days resulting from
unforeseen underground piping that affected foundation work and twenty-nine days resulting
from coordination issues for which the VA is allegedly responsible. See Exhibit 3644 at 8;
Hearing Transcript, Vol. 1, at 62. Given that the delay in the anticipated substantial
completion date from August 2 to September 5, 2017, was thirty-four days, we adopt that
figure.
CBCA 6149, 7071, 7597
10
at 14-15. Specifically, Alares commenced excavation work on August 22, 2016, see Exhibit
RS-0593 (Expert Report) at 7; had planned on completing foundation work on October 27,
2016, Exhibit 18 at 23; but did not do so until November 1, 2016, four days later than
planned. Tab B to Exhibit RS-0593; Hearing Transcript, Vol. 4, at 15. Alares asserts that
this four-day delay was caused by the discovery of unforeseen underground piping that was
not shown on the contract drawings. Exhibits 3343 at 76, 3644 at 5002; Hearing Transcript,
Vol. 1, at 61. In response to Alares’ submission of request for information (RFI) 002 about
this discovery, the VA provided Alares with a new sewer route location. Exhibit 22 at 1.
This discovery delayed excavation of the water main and sewer line. Exhibit 3343 at 76.
Because installation of both was a precursor to excavation and the placement of three
footings, the discovery delayed the footings work. Id. Neither the VA’s expert, Robert M.
D’Onofrio, nor the VA, contests the VA’s responsibility for this delay or that, because Alares
had to finish the foundation work before it could begin erecting steel, it caused a four-day
delay to the critical path. Exhibit RS-0593 (Expert Report) at 7-8; Tab B to Exhibit
RS-0593.
Under standard practice, the footings that Alares placed would need to cure for
twenty-eight days before Alares could begin placing steel. Exhibit 22 at 1. Under an early
schedule, Alares had planned to erect steel beginning no earlier than December 21, 2016,
Exhibit 3644 at 5023, but, by the time of an updated schedule dated September 26, 2016, had
moved its planned steel erection start date to October 28, 2016. Exhibits 18 at 23, 22 at 1.
Although it is unclear how Alares had planned to satisfy the twenty-eight-day cure
requirement under its original schedules, the delays associated with rerouting the sewer lines
affected Alares’ ability to move forward with the project. At that point, the VA provided
Alares with a way to speed its performance. The VA indicated, in a progress meeting on
November 3, 2016, that it would waive the requirement for twenty-eight days of curing and
allow steel erection to begin early if the results of a test of strength were acceptable. Exhibit
22 at 2, 144. The VA received a positive test result on November 7, 2016, and Alares began
steel erection on November 9, 2016. Id. at 2, 147-49. The VA’s waiver of the twenty-eightday cure requirement minimized and mitigated what otherwise would have been a longer
critical delay before steel erection could commence.
Alares asserts that the remaining thirty days of critical delay during this period
resulted, in large part, from coordination issues in resolving conflicts in the specifications
relating to MEP work, including fire protection and medical gas systems, for which Alares
asserts the VA is responsible. Hearing Transcript, Vol. 1, at 61. MEP coordination is a
normal part of a construction project where the parties try to determine the best routes for
mechanical, electrical, and plumbing in a new building under construction. Closing
Argument Transcript at 98. Alares submitted RFI 005 on October 20, 2016, with preliminary
questions about requirements for the coordination drawings that its subcontractor, Delta
CBCA 6149, 7071, 7597
11
Mechanical Contractors (Delta Mechanical or Delta), was preparing. Exhibit 83A at 243-50.
The VA responded to the RFI the next day, indicating that it would have the
architect/engineer (A/E) for the building revise plans as needed to reflect new toilet chase
and enclosure dimensions and ceiling tile elevation revisions, the latter of which would allow
for dropped ceiling tiles where needed to accommodate piping. Id. at 245. The VA indicated
in its response, however, that “[t]hese changes will not affect structural steel fabrication,” id.,
such that these MEP coordination issues should not have affected, and did not affect, Alares’
ability to move forward with steel fabrication.
Alares’ subcontractor, Delta, met with the A/E and the VA on November 10, 2016,
and the A/E and the VA indicated that they would consider Alares’ request to drop the
ceilings on an as-needed and room-by-room basis once Alares submitted final coordination
drawings. Exhibit 19 at 163. Alares submitted the initial Delta-created coordination
drawings to the VA on December 20, 2016, while indicating that Delta still needed the A/E’s
revised plans as discussed in the VA’s original response to RFI 005. Exhibit 83k at 287-93.
Alares submitted a revision to RFI 005 on December 22, 2016, Exhibit 19 at 131, 163, and,
when the VA provided an answer about toilet chase sizes on January 26, 2017, told the VA
that it would “need[] an answer on this RFI and revisions to floor plans within the next week
to keep project on schedule.” Id. at 163. On February 10, 2017, Alares submitted its second
revision to RFI 005. Exhibit RS-0593 (Expert Report) at 7. After resolving what it called
“[i]ssues with submission,” Exhibit 19 at 152, and participating in a conference call with
Delta and the VA, id. at 195, the A/E, on or before February 23, 2017, issued Bulletin 3 and
its response to the second revision of RFI 005, resolving the MEP coordination conflicts, id.
at 206, which was immediately forwarded to Alares and Delta. Id.
Although it is clear that there was a delay associated with MEP coordination, that
delay did not affect the critical path during Period 1. Mr. Maggioli testified that coordination
of the MEP drawings for the new building had to be complete “before [Alares] could begin
mechanical rough.” Hearing Transcript, Vol. 1, at 62. Yet, under both Alares’ original
baseline schedule and its subsequent schedule updates, MEP rough-ins were never scheduled
to begin until after the end of Period 1, see Exhibit 18 at 23; Tab B to Exhibit RS-0593,5 and
any MEP coordination issues were not the cause of the additional thirty-day critical path
delay during Period 1. Any delay caused by MEP coordination issues would not, under
5
Under Alares’ original baseline schedule, dated June 2, 2016, MEP rough-ins
were listed as having a planned early start date of March 7, 2017. Exhibit 3644 at 5024.
Subsequently, by the time that it issued revised schedules on July 25, September 26, and
December 8, 2016, Alares had moved the early start date to January 13, 2017. Exhibit 18 at
3, 23; Exhibit 3345 at 109.
CBCA 6149, 7071, 7597
12
Alares’ contemporaneous scheduling plans, have impacted critical path items until, at the
earliest, Period 2. Even with that, meeting minutes from Alares’ weekly project meetings
with the VA reflect that, despite the MEP coordination issues that it alleges, Alares had
commenced some initial MEP rough-in work in December 2017, earlier than its projected
early start date. Exhibit 19 at 105-06, 129. Alares acknowledged on January 26, 2017, after
Period 1 had ended, that it would need the A/E’s complete response to RFI 005 “within the
next week” to preclude schedule impacts, indicating that these MEP coordination issues had
not yet impacted the critical path at that time. Id. at 163. We find insufficient
contemporaneous evidence in the record to show that MEP coordination issues impacted
necessary activities on the critical path during Period 1.
Alares also asserted that, beyond the four days of delay previously discussed for which
the VA assumes responsibility, additional critical delays in Period 1 were caused by the
continuing effects of unforeseen underground steam lines, unforeseen underground steel
piping, and defective design drawings. Yet, the parties dealt with these issues before Alares
completed its foundation work on November 1, 2016. Alares issued RFI 002 on
September 1, 2016, seeking instruction from the VA by September 8, 2016, regarding the
discovery of the steam lines impacting the foundation work. Exhibits 2 & 8 to Exhibit
RS-0593. The VA provided an initial response on September 8, 2016, and provided a new
route location on September 19, 2016. Id., Exhibits 3, 4; Exhibit RS-0593 (Expert Report)
at 8. Alares then submitted a change order proposal (COP) on September 23, 2016. Id.;
Exhibit 6 to Exhibit RS-0593 (Expert Report). The COR asked for clarifications and
revisions of the COP twice, but the parties could not agree on the change, and the contracting
officer issued unilateral modification P00002 on October 11, 2016, directing Alares to
complete the work in accordance with the VA’s initial response to RFI 002. Exhibit 24; see
Exhibit RS-0593 (Expert Report) at 8-9; Exhibits 7 & 8 to Exhibit RS-0593. The VA
contracting officer’s resolution of how Alares should proceed predated Alares’ completion
of the foundation, and there is nothing in the record that shows how, once the foundation was
completed, these issues affected subsequent work during this period.
Instead, the record reflects that any critical path delays (beyond the four-day period
associated with laying the foundation) related to Alares’ slow progress on steel erection,
decking, welding, and detailing. Under Alares’ as-planned schedule, steel erection was
supposed to start immediately after the foundation was completed, Exhibit 18 at 23; Tab B
to Exhibit RS-0593, although it is unclear from the record whether that schedule properly
accounted for the contract’s twenty-eight-day concrete cure requirements. Nevertheless, to
expedite the project, the VA, as described above, authorized a shorter cure period (seven days
if the foundation passed a test of strength, which it did) than the contract required. After the
foundation was completed on November 1, 2016, Alares began steel erection on November
9, 2016, eight days later than originally planned (but earlier than would have been realistic
CBCA 6149, 7071, 7597
13
had the original schedule accounted for the twenty-eight-day cure requirement), but it did not
finish that work until November 30, 2016, taking longer than planned under the baseline
schedule. Exhibit RS-0593 (Expert Report) at 8. Steel decking, welding, and detailing
commenced on November 29, 2016, and was not completed until January 4, 2017, with the
welding and detailing taking longer than scheduled. Id. Alares has identified no viable
defects in drawings or with VA coordination and assistance that would have slowed Alares’
steel work once it began.
Further, under the construction schedule (as revised in the July and September 2016
schedules), concrete slab on deck pours were supposed to have occurred the day after
completion of steel erection, which, as noted above, was finished on November 30, 2016.
Exhibit RS-0593 (Expert Report) at 8. Applying that sequence of events, Alares should have
started casting the concrete slab on December 1, 2016. By schedule update no. 3, dated
December 8, 2016, in which Alares acknowledged that casting the slab remained a critical
path item, Exhibit 3345 at 107, 110, that date had moved to December 19, 2016. Id. at 109.
Yet, in its next schedule update (no. 4) on January 13, 2017, which was the first one prepared
by Alares’ new scheduling consultant (Project Controls, Inc. (PCI)) rather than by
Mr. Maggioli himself, Alares had delayed the start of cast-in-place concrete deck work until
January 30, 2017. Exhibits 31 at 1, 3346 at 126. Although Alares suggested in schedule
update no. 4 that it had a new logic which made MEP coordination issues the only critical
path item (and removed the concrete slab from the critical path), see Exhibit 3346 at 119,
suggesting that its unexplained delays in casting the concrete slab had no impact on the
project, that explanation and Alares’ sudden revision of logic make no sense and ignore or
sugarcoat the impact of delays for which Alares is responsible.6 By January 26, 2017, Alares
had again delayed the start of casting the concrete slab, telling the VA that it was not
planning to do that work until early February. Exhibit 19 at 164. For reasons that Alares did
not explain at the hearing, it ultimately did not start the pour stops and subsequent deck pours
until February 16, 2017, and did not complete them until February 21, 2017. Id. at 196.
Casting the concrete slab on deck was necessary before Alares could begin to construct
exterior light gauge metal framing, which (in schedule update no. 3) Alares had previously
6
In schedule update no. 4, dated January 13, 2017, Alares added weeks of MEP
cost negotiations to the critical path, with staggered dates beginning December 22 (after the
A/E was to issue revised MEP layouts) that extended out for several weeks to allow the
general contractor to review costs, the owner to review costs, and the parties to negotiate
costs. Exhibit 3346 at 123. The logic behind the inclusion of this extensive cost review and
negotiation period, particularly when adding them as a critical path item leading to MEP
rough-in work without regard to the need first to cast the concrete slab, is unsupported and
does not provide a basis for imposing critical path delays on the VA during Period 1.
CBCA 6149, 7071, 7597
14
identified as critical path work, see Exhibit 3345 at 107, or complete MEP rough-ins.
Exhibits 18 at 1, 3345 at 110; see Hearing Transcript, Vol. 3, at 36-37 (“Casting the concrete
deck was one of the key items in order to allow the project to move forward.”).
Throughout Period 1 and into Period 2, the VA was complaining that the schedule was
slipping for reasons that the VA did not understand. See, e.g., Exhibits 30 at 1, 31 at 1. On
January 9, 2017, Mr. Boyle, the VA COR, complained that “[a]fter reviewing [the] latest
schedule, dated 12/8/2016, this morning I have to reiterate my concern that the schedule is
sliding on the ICU project. . . . While I realize Alares is bringing a scheduling consultant
onboard per our last weekly meeting, there appears to be a significant loss of time when I
look at the schedule.” Exhibit 30 at 1. Based on the Board’s review of the record, it appears
clear that Alares was not keeping up with its planned schedule for reasons not caused by the
VA.
3.
Summary of Critical Delays in Period 1
Of the thirty-four days of critical path delay in Period 1, four days of that delay were
caused by issues surrounding completion of the building foundation for which the VA is
responsible. The remaining thirty days were caused by Alares’ slow progress, first on steel
erection and then on the cast-in-place concrete slab.
B.
Period 2 (January 13 to July 14, 2017)7
1.
MEP Coordination Issues
Period 2 covers the 183-day period of time running from January 13 to July 14, 2017.
In its January 13, 2017, schedule update, Alares projected substantial completion on
September 5, 2017, Exhibit 3346 at 118, but, in its July 25, 2017, schedule update (which had
7
In their reports, both Mr. Maggioli and Mr. D’Onofrio select January 13, 2017,
as the start date for Period 2. Nevertheless, their end dates differ. Although Mr. D’Onofrio
picked July 14, 2017, as the end date, Mr. Maggioli selected July 25, 2017, which is the date
that Alares submitted schedule update no. 10 to the VA. See Exhibit 3352 at 182. As Mr.
D’Onofrio correctly notes, however, even though schedule update no. 10 was submitted on
July 25, the data within that update and upon which the update relies was run on July 14,
2017. See id. at 190; Exhibit RS-0592 (Expert Rebuttal Report) at 6-7. Like Mr. D’Onofrio,
we end Period 2 on the date of the July 14, 2017, data run. Given that the parties agree on
the number of days of delay during Period 2, the differences in the parties’ selection of a
Period 2 end date is ultimately of no consequence.
CBCA 6149, 7071, 7597
15
a run date of July 14, 2017), see Exhibit 3352 at 190, the substantial completion date had
slipped to December 27, 2017. Id. at 183-84. The parties agree that the project was delayed
a total of 113 days during Period 2.
As addressed above in our discussion of Period 1, Alares, as set forth in its schedule
updates dated July 25 and September 26, 2016, had planned to commence MEP rough-ins
by January 13, 2017. See Exhibit 18 at 3, 23; Tab B to Exhibit RS-0593. By the time that
Alares submitted schedule update no. 3 on December 8, 2016, that start date had slipped to
January 13, 2017, Exhibit 3345 at 116, and, in Alares’ schedule update (no. 5) on January 13,
2017, had further slipped to March 13, 2017. Exhibit 3346 at 126-27. Although it is difficult
from the record to decipher some of the logic ties applicable to Alares’ work during this
period, the VA’s expert witness, for reasons that we do not understand, acknowledged in a
rebuttal report that the critical path for activities between January 13 and February 17, 2017,
was driven by “Activity D190,” which involved the VA’s issuance of a response to RFI 005
and the A/E’s issuance of new layouts for MEP, steps needed to allow Delta to revise and
prepare final coordination drawings. Exhibits 18 at 44, 48; see Exhibit RS-0592 (Expert
Rebuttal Report) at 7. Although, in Alares’ updated schedule dated January 13, 2017,
Activity D190 had a projected finish date of January 27, 2017, see Exhibit 18 at 44, 48, the
A/E did not (as previously noted) issue the new layouts until sometime on or before February
23, 2017, Exhibit 19 at 206, delaying resolution of the MEP layout. Nevertheless, as Alares
acknowledged on January 26, 2017, Alares would not have needed the A/E’s complete
response to RFI 005 until early February 2017 to preclude schedule impacts to the critical
path. Exhibit 19 at 163. Putting these pieces together, the VA’s expert conceded a critical
delay of twenty-two days from the delay in Activity D190, for which he determined the VA
is responsible. Hearing Transcript, Vol. 4, at 16; Exhibit RS-0592 (Expert Rebuttal Report)
at 7-8. For reasons that we will explain in our later discussion of delay responsibility for
Period 1, the Board is unable to understand the basis of this concession or the logic for
asserting that MEP coordination issues, rather than the cast-in-place concrete work, was the
critical path item at this point in time.
Responsibility for MEP coordination change delays shifted after the A/E issued new
layouts on or about February 23, 2017. Delta took several weeks to prepare new
coordination drawings based on the A/E’s new layouts, before submitting them to Alares on
March 17, 2017. Exhibit 83N at 318-20. For reasons that Alares does not explain in the
record, Alares waited forty-six days after receipt before, on May 2, 2017, it forwarded
Delta’s coordination drawings to the VA. Exhibits 83N at 316, 83O at 321; Closing
Argument Transcript at 102. The VA approved the coordination drawings sixteen days later.
Exhibit 83O at 321; Closing Argument Transcript at 102. Although Alares complains about
the VA’s delays in approving Delta’s coordination drawings and attributes delays between
February 23 and May 18, 2023, to the VA based on MEP coordination issues, see Exhibit
CBCA 6149, 7071, 7597
16
3644 at 5005, there was nothing for the VA to approve between February 23 and May 2
because Alares had not provided the coordination drawings to the VA.
Alares also claims that continuing MEP design errors for the locations of tie-ins and
routes for water, electrical, fire sprinkler, and medical gases caused continued delays during
Period 2, until at least June 2, 2017, if not later. See Exhibit 3644 at 5005-06. There were
changes made in tie-ins during this period that were eventually resolved through modification
P00008. See Exhibit 48. Nevertheless, contrary to the suggestion in Mr. Maggioli’s report,
these changes did not affect the critical path of contract performance. Exhibit RS-0593
(Expert Report) at 12-13.
2.
Cast-in-Place Concrete Slab
Other activities in which Alares planned to engage during Period 2 (as reflected in
schedule update no. 4) included casting the concrete slab that it had originally planned to
complete during Period 1, completing superstructure erection, completing enclosure work,
meeting a weathertight milestone, and installing the Air Handling Unit (AHU). Exhibits
3346 at 123, 125-26; RS-0593 (Expert Report) at 11, 14. With regard to the concrete slab,
the VA COR complained early in Period 2 about the continuing slide in the schedule for that
work and the accompanying delays in other activities (like installation of exterior light gauge
metal framing) that depended on completion of the concrete slab casting work. By email
dated February 8, 2017, the COR informed Alares that, “[a]fter further reviewing your latest
schedule this morning, dated 1/13/2017, the previous schedule dated 12/8/2016, and the look
ahead provided with the meeting minutes received yesterday, I have to again reiterate my
concern that the schedule is sliding on the ICU project.” Exhibit 31 at 1. Focusing on the
cast-in-place concrete work, he noted that, under the latest schedule, it “was to be placed on
1/30-31/2017,” but that, under the weekly “look ahead,” it was “currently scheduled for . . .
2/15-16/2017, and there is little to no progress being made by Alares on any one item in
particular.” Id. “This,” the COR asserted, “represents a 9 week slide in the placement of the
deck from the 12/8 schedule and a 3+ week slide from the latest schedule.” Id. He also
made the following more general observation:
There appears to be an ongoing loss of time and a general lack of progress
when I review project status and schedules. Although the schedule appears to
be well thought out and I only have a few minor comments on the schedule
narrative . . . , my primary concern is that I don’t see a comprehensive course
of action or plan in the narrative that will stop the loss of time and bring the
project back in line with contractual end date.
CBCA 6149, 7071, 7597
17
Id. He noted that, although Alares identified in its schedule updates ways that Alares
believed the VA had slowed performance and actions that the VA could take to speed Alares’
performance, “nothing is mentioned” in those updates “about the avenues available to Alares
to correct the situation.” Id. at 2. The COR informed Alares that the VA did not intend to
“modify[] the contract to extend the end date” and that Alares should “investigate
adjustments to means and methods to keep the project moving forward and correct the delay
in project completion.” Id. at 1.
As noted in our discussion of Period 1, for reasons that Alares did not explain at the
hearing, Alares ultimately did not start the pour stops and subsequent cast-in-place concrete
deck pours until February 16, 2017, and did not complete them until February 21, 2017.
Exhibit 19 at 196, 198, 207, 209. Although Alares could have immediately commenced
exterior light gauge metal framing at that point, it delayed commencement of that activity
until mid-March 2017, see Exhibit 3349 at 158, for reasons that, again, are not explained in
the record.
3.
Weathertight Milestone and AHU Delays
Aside from the cast-in-place concrete slab work, Alares was, under the schedule that
it had in place at the start of Period 2, supposed to satisfy the contract’s weathertight
milestone by March 10, 2017. Exhibit 3346 at 118. “Achieving weathertightness is
generally an important milestone in the construction of a building as it allows the
construction of aspects of the interior that might be damaged by exposure to the weather,
such as finishes, electrical equipment and so on.” https://www.designingbuildings.co.uk/
wiki/Weathertight (last visited March 21, 2025). By the time that Alares submitted schedule
update no. 6 on March 10, 2017, the deadline for achieving weathertightness had slipped
from March 22 to May 1, 2017. Exhibit 3348 at 141. Weathertightness controlled the
critical path at that point in time, and Alares’ inability to achieve it had caused sixty-two days
of delay to the critical path. Exhibit RS-0593 (Expert Report) at 11.
The initial delays in achieving weathertightness were the result of Alares’ lack of
progress on the superstructure erection. Exhibit RS-0593 (Expert Report) at 11. That is,
Alares could not make the building weathertight until the superstructure was erected. The
weathertight milestone deadline continued slipping to May 22, 2017 (in schedule update
no. 7, dated April 14, 2017), see Exhibit 3349 at 152; then to June 2, 2017 (in schedule
update no. 8, dated May 12, 2017), see Exhibit 3350 at 161; and then to August 15, 2017 (in
schedule update no. 9, dated June 9, 2017). See Exhibit 3351 at 171. There was no
explanation for much of this continual slippage.
CBCA 6149, 7071, 7597
18
Once the superstructure erection was sufficiently in place, Alares’ ability to meet the
weathertight milestone was affected by delays in roofing activities for the building envelope,
specifically “Roof Railing Assemblies & Closure Plates” and “Roof Blocking - Perimeter &
AHU Deck.” Exhibit RS-0592 (Expert Rebuttal Report) at 8. These delays were the result
of Alares’ lack of progress on the building envelope and a new logic tie that required “Spray
Fireproofing (Roof Deck & Interior Steel)” to commence immediately after the critical
building envelope work was completed. Id. at 8 & n.14. There were also delays, as noted
above, in Alares’ commencement of exterior light gauge metal framing, which, even though
Alares could have begun that work immediately after completing the cast-in-place concrete
slab on February 21, 2017, did not begin until late March and was not completed in the
scheduled time. See Exhibits 3350 at 168, RS-0592 (Expert Rebuttal Report) at 8.
Alares also delayed the start of procurement for the fabrication and delivery of the
AHU and curb. The design of the AHU penthouse building, which was to sit atop the
building, originally contained two AHUs and related equipment. The curb is “a structural
support for the [AHU].” Hearing Transcript, Vol. 3, at 101. In its early schedules, Alares
had planned on commencing procurement of the AHU and curb in January 2017. Exhibit
RS-0592 (Expert Rebuttal Report) at 9. It appears that Alares actually began that work in
January 2017 but that its subcontractor made a mistake by planning on a smaller footprint for
the AHU than the design documents required and failed to coordinate the decreased AHU
footprint with the roofing subcontractor, Exhibit RS-0053 at 7, which essentially required
Alares to start over with planning for the AHU work once the error was discovered.
Accordingly, in its Period 2 schedules, Alares changed its original January start dates to
reflect that work had actually commenced in March 2017, with revised completion dates.
Exhibit RS-0592 (Expert Rebuttal Report) at 9. Nevertheless, Alares also made logic
changes to its schedule to tie fabrication and delivery of the AHU to the completion of
roofing, which reduced the amount of delay originally tied to the AHU and curb schedule.
Id.
Once it recommenced AHU procurement with the appropriate sizing, Alares
discovered a defect in the A/E’s original design for the AHU. On March 9, 2017, Alares
submitted RFI 26, notifying the VA that the manufacturer of the steam generator that was
part of the AHU system, DriSteem, had informed it that the design required two steam
generators, rather than the single steam generator that the A/E had identified. Exhibit 3670
at 5241. Alares asked the VA to have the A/E review the matter and issue appropriate
drawings, sketches, narratives, and a revised equipment schedule, as needed. Id. at 5241,
5243. The A/E did so on March 15 with drawings that the VA forwarded to Alares on March
16, 2017. Id. at 5242. Alares’ subcontractors provided Alares with cost quotations for the
added work on March 30 and April 10, 2017, see Exhibit 33 at 18, 21, and Alares submitted
a change order cost proposal to the VA on April 11, 2017, which the VA rejected three days
CBCA 6149, 7071, 7597
19
later as too high. Exhibit 50 at 3-4. Alares eventually, on May 12, 2017, submitted a revised
cost proposal through COP 0012-R2. Exhibit 33 at 15.
Eleven days later, on May 23, 2017, the parties entered into bilateral modification
P00005 to add to the contract the work identified in COP 0012R2—specifically, addition of
a second steam generator to the AHU “in accordance with RFI #26 and #31 in the amount
of $42,398.86,” plus associated necessary plumbing. Exhibit 33 at 1. In the modification,
the parties agreed that the “contract completion date remains 08/02/2017” and that the
modification was “the adjustment for the contractor’s proposal and for the contractor’s rights
to submit claims for unresolved issues which are not covered by this change.” Id. at 2. The
modification further provided that “[e]xcept as provided herein, all terms and conditions of
the document referenced in Item 10A of this document, (VA241-16-C-0037) with any/all
modifications as heretofore changed by this modification, remain unchanged and in full force
and effect.” Id. Incorporated into the modification were RFIs 26 and 31 themselves, which
indicated that the increase of $42,398.86 was “only [for] the direct costs of the change” and
that Alares “reserves its rights to additional costs for impact of this change, alone or in
combination with other changes, on unchanged work; for additional time, due to impacts, if
any, on the schedule; and for time-related extended time of performance costs, all of which
will be evaluated separately.” Id. at 15.
When the parties executed modification P00005, Alares anticipated a lead time for the
second generator of four to six weeks, which would result in delivery by early July 2017.
Exhibit RS-0593 (Expert Report) at 13. In the schedule update near in time to the
modification, Alares projected that the AHU work would be complete by July 19, see Exhibit
3350 at 168, but, by June 9, 2017, that date had slipped, without explanation, to August 4,
2017. Exhibit 3351 at 177. Further, by the time of the June 9, 2017, schedule update, the
AHU become the focus of the critical path. Id. at 172. Similarly, the curb associated with
the AHU, though set in the May 12 schedule update to finish on the same day as the update
(May 12), Exhibit 3350 at 168, was delayed to a finish date of August 4 in the June 9 update.
Exhibit 3351 at 177. Nevertheless, delivery of the second generator was delayed until
August 7, 2017. Exhibit RS-0593 (Expert Report) at 13-14. It is not clear from the record
when Alares (or its subcontractor) actually submitted the order to DriSteem for the second
generator.
Despite the length of time that it took to resolve the AHU second steam generator
issue, the controlling critical path delay in Period 2, at least up until June 9, 2017, was the
lack of progress in enclosing the building, coupled with the lack of progress on interior MEP
rough-in work that, despite the lack of a weathertight seal of the building, Alares had already
begun. Exhibit RS-0593 (Expert Report) at 13. Without enclosure, Alares could not create
a weathertight building. Nevertheless, in schedule update no. 9 (dated June 9, 2017), Alares
CBCA 6149, 7071, 7597
20
shifted the critical path to the rooftop mechanical AHU and curb work (specifically, the
“Fab[ricate] & Deliver – AHU” and “Fab[ricate] & Deliver Curb” line items). Id.; Exhibit
3351 at 172. Despite the shift in the critical path, Alares did not explain why, in its June 9
schedule update, it added more than two weeks of time than had previously been identified
in its prior May 12 schedule update for completing the AHU and added almost twelve weeks
of time for completing the curb.
4.
Alares’ Staffing and Submittal Issues
At various times during Period 2, the VA expressed concern about the continued slide
of the schedule, as well as about schedule updates that, in the VA’s mind, compressed
activities to maintain a particular completion date projection but did not appear logical, as
seen in this email from the VA’s COR to Alares’ project management team from May 26,
2017:
After reviewing the latest schedule update (no. 8), updates 6 and 7, the
narrative and the three week look ahead provided with the meeting minutes
received yesterday, I have to reiterate the VA’s concern that the schedule is
sliding on the ICU project. While the latest updated schedule maintained the
previous finish date, it did not bring the end date back in line with, or move it
closer to, the contractual end date. It appears as though several individual
items were compressed to keep the end date shown in previous schedule
updates. Per my previous e-mails, there appears to be an ongoing loss of time
and lack of progress related to bringing the end date back in line with the
contractual end date. My primary concern is that I don’t see a comprehensive
course of action or plan in the narrative that will stop the loss of time and bring
the project back in line with contractual end date, such as the [overtime] and
[w]eekend work that was discussed in our progress meeting. . . . Please
investigate adjustments to means and methods to keep the project moving
forward and correct the delay in project completion.
Exhibit 35 at 1; see Hearing Transcript, Vol. 3, at 41-43.
The VA’s concerns were reinforced by an email that Alares received from its
fireproofing subcontractor in late April 2017, complaining about Alares’ failure to move the
project along appropriately and performing work out of logical sequence:
I was just informed by my field ops that the second floor at the ICU project has
been completely studded. This is not how we figured this project. We have
been waiting for the roof to on [sic] for months now and then you decide to
CBCA 6149, 7071, 7597
21
stud the entire floor? Why? This will definitely impede my production. The
studs will have to come down because I will need access with a rolling
scaffold to perform my work. It clearly states in the qualifications . . . that the
floors will have clear access for the efficient use of a rolling scaffold.
Studding the entire floor is not clear access. . . . Please advise what will be
done about this so we can perform our work in an efficient manner.
Exhibit RS-0069 at 59719.
By March 6, 2017, Alares was on its second project manager (Josh Abrams, replacing
Nick Budris). Hearing Transcript, Vol. 3, at 38-39; see Exhibits 19 at 221, RT07. By
April 10, the VA had still not received 50% of the submittals that were required to construct
the project. Hearing Transcript, Vol. 3, at 40. Alares could not perform work on each aspect
of the project until it had provided the VA with a submittal showing how it would
accomplish the work and the VA had approved it, which means that there were many areas
of work that Alares could not yet commence. Id.
5.
Safety Violation Shutdown
On June 16, 2017, the entire construction site was shut down under the authority of
FAR 52.242-14 when one of Alares’ subcontractors, People Ready, created an on-site safety
incident. Exhibit 37 at 1; see Exhibit 096.1 (photograph of safety violation); Hearing
Transcript, Vol. 2, at 168-69. Alares was informed that the suspension would remain in
effect “until an adequate site safety monitoring plan is put into place, or until further
direction is given to you.” Exhibit 37 at 2. Ultimately, the shutdown lasted two weeks, with
the shutdown notice being lifted on June 30, 2017. Exhibit 107. Alares was not allowed to,
and did not, perform any work at the project site during the period of suspension. See id.;
see also Exhibit 17 at 569-82. Alares’ current safety manager, who was not employed by
Alares when this incident occurred, see Hearing Transcript, Vol. 2, at 176-78, acknowledged
at the hearing that the safety incident underlying the shutdown was a “serious concern,” id.
at 172, but he believes that the two-week shutdown was unnecessary and that what he calls
the VA’s zero-tolerance policy for safety infractions after this suspension was too much. Id.
at 163-64. Alares’ safety manager has misstated the requirements that the VA imposed for
restarting on-site operations, which did not impose a zero-tolerance policy, see Exhibit 102;
Hearing Transcript, Vol. 2, at 179-80; id., Vol. 3, at 85-86, and we find the VA’s response
to the safety infraction, including what became a two-week suspension, reasonable. See
Hearing Transcript, Vol. 3, at 82-83 (discussing safety issues). The shutdown occurred
during the procurement of the roof top mechanical AHU and curb, which was not affected
by the shutdown. Appellant’s Post-Hearing Reply Brief (Sept. 14, 2023) at 10; see Exhibit
3352 at 184.
CBCA 6149, 7071, 7597
22
Although the shutdown was lifted on June 30, Alares did not restart operations on the
job site until July 5, 2017. See Exhibit 17 at 583-87. For the first few days after it resumed
performance (that is, from July 5 through 9, 2017), Alares utilized lower-than-average
manpower at the site (a total of only 104 man-hours during those five days), see Exhibits 17
at 587-94, RS-0592 (Expert Rebuttal Report) at 10, before resuming staffing levels closer to
normal but still less than desirable from July 10 to 17, 2017 (with 59.5, 86.1, 76, 76, and 64
man-hours, respectively). Exhibit 17 at 595-604. Progress was slow between July 5 and 14,
2017.
We find no evidence of any improper motives or nefarious conduct by the VA in the
issuance or duration of the safety shutdown. Although the VA raises the safety shutdown in
its briefing, see Respondent’s Post-Hearing Brief (June 16, 2023) at 33, the VA’s expert
witness did not identify this issue in his expert report as creating any delay to the critical
path.
6.
Summary of Critical Path Delays in Period 2
At the start of Period 2 through February 21, 2017, the critical path of performance
was delayed by Alares’ unexplained delay in the casting of the concrete slab, after which
Alares’ delays in enclosing the building, which precluded Alares from reaching the
weathertight milestone, controlled the critical path, up until June 6, 2017. At that point in
time, delays in being able to complete the AHUs caused by redesign and rework necessitated
by the required addition of a second steam generator (an issue covered in modification
P00005) controlled the remainder of Period 2, although Alares’ progress was unnecessarily
slow.
Of the 113 days of delay during Period 2, Alares is responsible for delays to the
critical path relating to the cast-in-place concrete slab and building enclosure, which cover
the period from January 13 through June 6, 2017. With regard to the remaining thirty-eight
days of delay in Period 2 (from June 7 to July 14, 2017), the VA provided the original
drawings that omitted the need for the second AHU steam generator and is responsible for
extra work and delays associated with the necessary redesign. The VA argues that, by
executing bilateral modification P00005, Alares assumed responsibility for that extra work
and those delays. We will address that argument later in this decision.
CBCA 6149, 7071, 7597
C.
23
Period 3 (July 14, 2017, to May 18, 2018)8
1.
Weathertight Milestone and AHU Delays
Period 3 covers the 309-day period of time running from July 14, 2017, to May 18,
2018. Exhibit RS-0593 (Expert Report) at 15. At the start of Period 3, Alares’ anticipated
substantial completion date was December 27, 2017, Exhibits 3352 at 183, RS-0593 (Expert
Report) at 10, although the VA was pushing for completion by no later than December 1.
Exhibit 41 at 1. By the end of Period 3, Alares was projecting a substantial completion date
of September 4, 2018, which represented a critical path delay during Period 3 of 251 days.
Exhibit RS-0593 (Expert Report) at 15. Delays during this period were caused by continued
building enclosure delays, Alares’ failure timely to advance the interior rough and finish
work, and, eventually, issues involving receipt of permanent power. Id.
Early in Period 3, Alares changed the performance schedule to compress exterior
enclosure work to allow it to achieve weathertightness for the building. Exhibit RS-0593
(Expert Report) at 15. By the time of its September 2017 schedule update, Alares had
extended the deadline for making the building weathertight until September 29, 2017, but the
VA complained that it seemed unlikely that Alares could meet that date. Exhibits 18 at 83,
45 at 1. Alares blamed delays in its ability to achieve weathertightness on the VA’s own
alleged delays in resolving an AHU curb issue and a separate infill issue. Exhibit 45 at 3.
Yet, those delays were not the VA’s responsibility. The AHU curbing was installed between
August 21 and 23, 2017, and the AHU sections were installed on August 24 and 25, 2017.
Exhibit RS-108 at 21512. In mid-September, one of the VA’s CORs, Scott DaRosa, was on
the roof of the ICU building and discovered two problems: (1) that the eastern edge of the
AHU was overhanging the curb, creating a gap between the AHU frame and the curb, and
(2) that the western curb was damaged during installation, apparently by winches when one
of the AHU sections was being installed that caught the leading edge of the curb and bent it
inward. Hearing Transcript, Vol. 3, at 100-01. This caused springs along the sides of the
curb to protrude outward and caused a structural issue in the supports for the AHUs,
affecting their ability to support the weight of the AHUs. Id. at 101-06. The VA reported
these issues to Alares by email dated September 18, 2017, with suggested corrective
measures. Exhibit RS-108 at 21512-14. Alares took time to resolve these issues, Exhibit 45
at 3, which were not caused by the VA.
8
We adopt the start and end dates for Period 3 that the VA’s expert,
Mr. D’Onofrio selected, as they have a more logical basis than the start and end dates that
Mr. Maggioli, in his delay report, selected.
CBCA 6149, 7071, 7597
24
By October 5, 2017, Alares had still not reached the weathertight milestone, evidenced
by a photograph of the exterior of the project from that date showing numerous items
necessary for a weathertight structure—in addition to the AHU curb issue and the infill
issue—that were still far from complete. Exhibit 45 at 4; see Exhibit 17 at 746; Hearing
Transcript, Vol. 3, at 52. The building had to be weathertight before Alares could complete
interior work. Hearing Transcript, Vol. 3, at 50. These delays in enclosing the building were
caused by Alares’ subcontractor workmanship and Alares’ delays in addressing its
subcontractor issues. See Exhibit 45 at 3-4; Hearing Transcript, Vol. 3, at 51-52. Issues
surrounding the AHUs and making the building weathertight at this time were not caused by
the VA.
By its October 27, 2017, schedule update (no. 14), weathertightness had dropped off
of Alares’ written schedule and out of its schedule narrative, and Alares indicated that it was
planning to begin interior drywall work on October 30, 2017. Exhibit 3356 at 216, 218; see
Tab J to Exhibit RS-0593. That, though, does not mean that Alares had achieved the
weathertight milestone. It appears that Alares changed its schedule logic to remove
weathertightness completely from the schedule, which is evident from the listing of other
activities that were precursors to weathertightness which still needed to be completed,
including an AHU and curb corrective plan and roof flashing. Exhibit 3356 at 218.
Although no longer referencing “weathertightness,” Alares indicated that roofing and
exterior framing/sheathing, necessary for building enclosure and weathertightness, were
“nearly complete,” id. at 215, and set to be finished by December 6, 2017. Id. at 218. By the
time of its December 22, 2017, schedule update, the roofing and exterior framing/sheathing
building enclosure were still identified as “nearly,” though not quite, “complete,” Exhibit
3359 at 239, but now with a January 17, 2018, finish date. Id. at 241-42. By the time of its
January 24, 2018, schedule update, Alares had dropped any references to the status of the
roofing and the exterior framing/sheathing but indicated that it was still working on the AHU
and curb corrective plan and roof flashing needed to allow for enclosure, see Exhibit 3360
at 248, which, in a later schedule update, Alares reported completing sometime between June
20 and 22, 2018. Exhibit 3365 at 284. Alares’ schedule updates provided no reason for the
constant and ultimately lengthy delays in completing this work.
2.
Staffing, Scheduling, and Subcontractor Issues, and Two Cure Notices
Early in this period, the VA again recognized and expressed concern about what it
viewed as Alares’ lack of appropriate attention to this project, with inadequate staffing being
assigned to it, as reflected in this email from the VA COR to numerous Alares
representatives on July 25, 2017:
CBCA 6149, 7071, 7597
25
After numerous understaffed days on the project both last week and this week,
the VA wants to alert you again of our concern regarding the project schedule.
Given the current staffing levels being provided[,] we are concerned that the
project will not be completed in accordance with the latest schedule. (run date
6/13/2017). The VA has previously expressed concerns related to project
progress. . . . Alares should be implementing measures to complete the project
in a timely manner. However given the current staffing levels, the VA is
concerned [that the] completion date will continue to slide. Please provide an
updated schedule prior to the weekly progress meeting so we may review and
discuss it with you during the meeting.
Exhibit 39 at 1; see Exhibit 17 at 619-30 (daily logs showing, from July 24 through 30, 2017,
Alares and its subcontractors worked a total of ninety-six man-hours on the project (spending
thirty-four man-hours on July 24, followed by eighteen, eighteen, eighteen, eight, zero, and
zero man-hours over the next six days); Hearing Transcript, Vol. 3, at 45 (Alares and
subcontractor staffing levels were low at this time). The VA COR expanded on these
concerns in another email just two days later, complaining that, in a new schedule update that
Alares had just submitted (no. 10), Alares had ignored work areas that were causing schedule
slippages but that, seemingly because they were controlled by and the responsibility of Alares
or its subcontractors, Alares excluded from its narratives, including the effect of continual
personnel turnover, a lack of coordination among the various trades and subcontractors, and
inadequate staffing:
Prior to the meeting, seeing [as] how this is Alares’ narrative on the impacts
to the schedule, I am requesting that the narrative be revised to include impacts
to the schedule related to the following:
Alares’ Personnel turnover
Lack of coordination
Delayed responses to VA requests (such as 21 days to provide
information related to the steam generator COP which was
insufficiently documented)
Inadequate staffing
Lack of subcontractor control
Time lost due to 2 week shut down related to continued safety
violations
Etc.
Exhibit 40 at 1. The VA COR raised a concern that “[i]t appears as though the narrative is
carefully written to place the onus for delays squarely on the VA, and does not address a
single item that has impacted the schedule due to Alares.” Id.
CBCA 6149, 7071, 7597
26
On August 2, 2017, after meeting with Alares on August 1, 2017, the VA contracting
officer issued a cure notice declaring that Alares was in default on the contract for failing to
meet the contractual completion deadline of August 2, 2017. Exhibit 41 at 1. While
reserving “all contractual rights and remedies under the subject contract,” the contracting
officer indicated that “if Alares . . . will pursue all aspects of work required under an
extended schedule to ensure the successful completion of the contract and submit to the
Providence VAMC a recovery plan and schedule indicating major milestones and associated
dates of delivery or completion with 10 calendar days” of the cure notice, the VA would
“modify the contract and extend the completion date to December 1, 2017.” Id. We find no
evidence of any improper motives or nefarious conduct by the VA in the issuance of this cure
notice.
Alares responded on August 11, 2017, with an updated schedule identifying an
anticipated substantial completion date of December 1, 2017. Exhibit 42 at 1. It proposed
deadlines for the completion of remaining tasks on the project, including completion of AHU
installation by August 28; making the building weathertight by August 29; breaking through
to the second floor by August 31; and having the exterior wall complete by October 27, the
envelope complete by October 31, the interior work complete by November 22, and the final
site work complete by November 27. Id. Nevertheless, Alares highlighted its concerns about
a lack of permanent power for the building with its proposed solution involving a contract
modification allowing for the use of temporary power:
Please note that, due to the differing/unforeseen site condition involving the
location of the required electrical panel and the necessity of a contract
modification to correct this problem, permanent power cannot be completed
by the December 1, 2017 deadline. The permanent power connection issue is
still outstanding. Alares Construction requested the VA determine an alternate
permanent power tie-in due to differing site conditions as early as February
2017. This is an issue over which Alares has no control. The change
modification still requires negotiation and, because of the long-lead-time
equipment that must be ordered to correct the problem, the modification must
be finalized by August 22, 2017 in order to have permanent power by January
3, 2018.
Since the earliest permanent power can be completed is January 3rd, temporary
power will be required to condition the interior spaces for the installation of
the finishes to achieve the December 1st completion date. Temporary power
must be installed by September 29, 2017 and will require a change
modification.
CBCA 6149, 7071, 7597
27
Exhibit 42 at 1. Alares also represented that, as part of what it called a “Recovery Plan,” it
“has additional manpower commitments from the subcontractors” with a “recovery plan
consist[ing] of working double shifts, night work, and weekend work.” Id. at 2. It reported
that, once the VA approved its new schedule, “each subcontractor will develop a micro
schedule to achieve each of the task deadlines and develop manpower projections as well as
dates for double shifts or weekend work,” and “delivery of materials will be expedited to
ensure the labor efforts are not impeded.” Id. Alares also “reserve[d] all rights for an
equitable adjustment and modification to the contract . . . for the above-mentioned
conditions.” Id.
Despite saying that it would adopt a recovery plan, Alares continued to have difficulty
with staffing and with its subcontractors, even though it began significantly to increase daily
staffing and the number of man-hours on the project. See Exhibit 17 at 657-714. It began
complaining to its subcontractors about their insufficient staffing of the project and blaming
them for delays, see, e.g., Exhibits RT-20 at 29-31, RT-33 at 1, RS-0258 at 33888, RS-0279
at 32823, RS-0322 at 34058, RS-0370 at 150241, RS-0439 at 152835-36, even though at
least some subcontractors were complaining that Alares was not willing to pay for increased
manpower. See, e.g., Exhibit RS-0259 at 32295. For example, by letter dated September 8,
2017, Alares complained to one of its subcontractors, Delta, about its “failure to perform in
accordance with the contract requirements, which had “caused significant, unreasonable and
costly delays on the Project.” Exhibit RS-0099 at 1761. It claimed that “Delta has failed to
provide an Air Handler Building and Chiller in accordance with the contract documents” and
“has also failed to install certain materials in accordance with the contract documents such
as hanging pipe and ductwork from the structural steel instead of the metal deck.” Id. It
further pursued its complaints against Delta by letter dated February 28, 2018, warning Delta
that Alares would be filing a claim against Delta’s performance bond because of “Delta’s
failure to perform which caused significant, unreasonable and costly delays on the Project
and caused significant harm to Alares Construction’s reputation.” Exhibit RS-0352 at 44415.
Alares listed the following “major failures” by Delta and represented that Delta was
responsible for 254 days of delay to the project:
1.
2.
3.
4.
5.
6.
Delta did not provide Air handler unit (AHU) building drawings in a
timely manner causing the overall project schedule to delay.
Delta did not properly coordinate the AHU building curb with the steel
contractor causing significant repair costs.
Delta failed to deliver the AHU as originally scheduled.
Delta failed to provide the specified AHU building and equipment.
Delta failed to properly install the AHU building on the roof causing
major rework and delays.
Delta did not provide the proper hangers for ductwork or piping.
CBCA 6149, 7071, 7597
7.
8.
28
Delta failed to coordinate ductwork and piping in patient room causing
major rework.
Delta did not provide the proper supports for roof exhaust fans.
Alares Construction relied on Delta’s mechanical expertise as Rhode Island’s
premier mechanical contractor to provide a quality mechanical installation on
time and on budget. Instead Alares Construction suffered numerous delays
and sub-par quality installation of materials and equipment by Delta. Alares
Construction’s reputation was permanent[ly] impaired as a result of Delta’s
poor workmanship and schedule delays.
These and other failures have resulted in other subcontractors working out of
sequences, losses of productivity, losses of efficiency, and significant project
delays. Alares will be seeking reimbursement from Delta Mechanical for
damages that of Alares Construction and other subcontractors have incurred.
Alares Construction will be seeking damages of $867,884 for the project
delays. Delta caused the project to be delayed 254 days.
Id. In the appeals now before the Board, Alares has represented that, after sending this letter
to Delta, it eventually changed its mind about Delta’s fault and concluded that none of
Delta’s delays impacted the critical path. Hearing Transcript, Vol. 2, at 8.
Alares was also submitting schedule updates to the VA during Period 2 that failed
accurately to update or include all activities that Alares had to complete. By email dated
October 4, 2017, the VA COR complained that “[i]tems that appeared to be overlooked
during the [most recent schedule] update, and items that are likely going to miss the
scheduled early completion date, include,” among other things, “Milestone: New
Addition—Weather Tight (9/29/2017),” mechanical insulation, setting exhaust fans, interior
framing for stairs, and electrical rough-ins. Exhibit 45 at 1; see Exhibit RS-0439 at
152835-36 (Alares’ complaints about a glass subcontractor’s defective work with soffit
panels).
On May 7, 2018, the VA issued another cure notice, this time because Alares had
failed “to install smoke tight partitions in accordance with Fire Stopping Specification
Section 07 84 00 paragraph 1.1B and Regulatory Requirements Specification Section 01 41
00 paragraphs 1.3-A.1 and 1.3-A.12, a condition that is endangering the performance of the
contract.” Exhibit 54 at 1. Alares responded on May 14, 2018, acknowledging that it was
“aware of the smoke barrier requirements and [that] the drawings provide details of the
smoke barrier wall” but asserting that it felt that it still needed additional guidance. Exhibit
CBCA 6149, 7071, 7597
29
55 at 1. Through a series of communications between the parties between May 16 and
June 2, 2018, Alares eventually agreed to a remediation plan through which it performed the
identified work. Exhibits 56 at 1-2, 57 at 1-3, 58 at 1. We find no evidence of any improper
motives or nefarious conduct by the VA in the issuance of this cure notice.
Throughout Period 3, Alares was still trying to find subcontractors for work on the
project at prices that Alares found acceptable. See, e.g., Exhibit RT-22 at 258. In September
2017, Alares named its third project manager (George Archambeault, replacing Josh
Abrams). Exhibit 19 at 473, 483.
3.
Permanent and Temporary Power Issues
Contract drawing E2.0 provided detailed conduit routes from the electrical point of
connection in Building 1 to the new ICU addition. Exhibits 12 at 96, RS-0527 at 2. As early
as February 2017, Alares had raised concerns about the installation of electrical conduits for
the new building that would tie-in to the existing Building 1 electrical system, as the routes
identified on the drawings were, according to Alares, not feasible. Exhibits 19 at 218, 3673
at 5268-71, RS-0593 (Expert Report) at 11. The electric panel through which the ICU would
receive permanent electrical power was not in the location as shown on the drawing. Exhibit
RS-0527 at 2. Further, according to Alares, the ceiling through which the electrical conduits
were supposed to be routed was blocked with existing AHU ductwork and piping, leaving
insufficient room for additional conduits. Id. During March 2017, the VA worked with
Alares to identify a solution, looking for alternate routes, Exhibits 19 at 241, 3663 at 5169,
3665 at 5202, but, in response to a change order request from Alares on March 31, 2017, the
COR responded that “the utilities should be installed as shown on the plans” and that Alares
should “[p]roceed with the installation of the interior utilities as needed to maintain project
progress/schedule.” Exhibit 25 to Exhibit RS-0593. The COR cited section 1.4 (Utilities,
Mechanical and Electrical Coordination) of contract specification 01 31 00 to indicate that
the contract drawings were only diagrammatic and that the contractor was obligated to
configure exact runs as conditions permitted:
The Contract Drawings are diagrammatic only intending to show general runs
and general locations of piping, ductwork, equipment and sprinkler heads.
[Contractor should] [d]etermine exact routing and location of individual
systems prior to fabrication of components or installation.
.....
CBCA 6149, 7071, 7597
30
Adjust locations of piping, ductwork, conduits and equipment as required to
accommodate new work with interferences anticipated and as encountered
during installation.
Id. (quoting Exhibit 6 at 47).
On April 6, 2017, Alares submitted RFI 35, seeking direction from the VA for
alternate routing for the electrical tie-ins, given “that the engineer’s original planned route
did not take in account the obstructions and existing conditions.” Exhibit 3666 at 5210. The
VA COR immediately responded that, because “[t]he routes shown on the plans are
diagrammatic” and “[t]he specifications clearly indicate that the investigation and inspection
to determine final routes . . . is the responsibility of the Contractor,” the VA would “no
longer work to identify an alternate route as this may be cause for a delay and is the
responsibility of the Contractor.” Id. at 5211. In a revision to RFI 35 submitted on May 5,
2017, Alares proposed new routes for electrical services and other MEP tie-ins while noting
that such engineering work was not within the scope of its contract. Exhibit 3668 at 5228.
Further, the original contract drawings only called for one automatic transfer switch (ATS),
which did not comply with the requirements of the National Electrical Code (NEC). The
NEC requires separation of power into three branches, each of which must be supported by
stand-alone power feeders and dedicated transfer switches: (1) life-safety (such as egress
lighting and alarms); (2) critical (patient area lighting and outlets); and (3) equipment (such
as AHUs and elevators). Exhibit 4305 at 10559.
Although the VA COR issued a partial response to the RFI 35 revision on June 2,
2017, Exhibit 3668, that response did not provide a complete remedy to the tie-in issues. The
A/E attempted to remedy remaining defects on July 12, 2017, by issuing Bulletin #8, which
identified the need for three ATSs (instead of one) and new panels and transformers that
were not in the original design and that showed alternate MEP routes and tie-in locations in
a somewhat different manner from the COR’s June 2 response. Exhibits 63, RS-0593
(Expert Report) at 13. Bulletin #8 also called for a larger electrical closet to house the
increased number of ATSs and also moved the electrical closet eight feet—from the existing
building to the ICU—to avoid disrupting the pharmacy below. Exhibit 63.9 On August 1,
2017, Alares submitted COP 15 providing a preliminary cost estimate for the changes, which
Alares updated on August 15 and 31, 2017. Exhibits 3391, 3392, 3393.
9
As we will discuss later in this decision, the bulletin incorrectly only provided
for one control wire from the generator control panel to each ATS when, to comply with the
NEC, it needed more. Exhibit 63 at 9 (note 6).
CBCA 6149, 7071, 7597
31
As discussed above, the VA issued a cure notice on August 2, 2017, attempting to get
the project on track. Exhibit 41 at 1. When Alares responded to that cure notice on
August 11, 2017, it recognized that it would not be able to complete permanent power
connections by the then-proposed substantial completion date of December 1, 2017. In the
“Recovery Plan” that it provided to the VA, Alares proposed that “[s]ince the earliest
permanent power can be completed is January 3rd, temporary power will be required to
condition the interior spaces for the installation of the finishes to achieve the [then-proposed]
December 1st completion date. Temporary power must be installed by September 29, 2017
and will require a change modification.” Exhibit 42 at 1. In its August 4, 2017, schedule
update, Alares added temporary power activities, proposing to have temporary power in place
by September 29, 2017, Exhibit 18 at 78, although it did not meet that deadline. On October
9, 2017, Alares submitted a change order proposal to “[p]rovide temporary power for the
ICU addition for use until the permanent power tie in is completed,” which would “operate
the AHU and chiller,” with a proposed price of $5914.79. Exhibit 116A at 1133. This
temporary power tie-in would have “allow[ed] the HVAC system to be operated” and “to
control the climate in the space.” Hearing Transcript, Vol. 3, at 96. The contracting officer
agreed to the request, and Alares reported that it was having one of its subcontractors proceed
with installation while the change order was being processed. Exhibit 19 at 507. Yet, on the
day that Alares’ subcontractor, Collard Enterprises Inc. (Collard), was to run the temporary
power cable to the existing panel, Alares told Collard to stop and to abort the work. Exhibit
RS-0246 at 150998. Alares informed the VA on October 30, 2017, that, in the course of a
month, it had lost two months of time on the schedule because of its “review, analysis and
cost feasibility on supplying a temporary power source to start the building HVAC
equipment” and that “[t]he review yielded a cost which was not acceptable to the project
team, therefore, the plan for startup now requires the building permanent power.” Exhibit
3356 at 216. Yet, if price was the concern, Alares never attempted to submit an upward price
revision to its COP proposing temporary power or ask the VA whether it would fund a larger
dollar figure to install temporary power. Alares reported during a November 16, 2017,
meeting that it had decided not to perform the temporary power tie-in and effectively
withdrew its change order request. Exhibit 19 at 556-57.
Alares argues that, although it initially proposed the use of temporary power and
provided a price quote for it, it later determined that temporary power would not have
mitigated delay because the temporary power used to commission the equipment did not have
sufficient capacity. Appellant’s Closing Argument Presentation PowerPoint (Oct. 18, 2023)
at 54, 56-57; Closing Argument Transcript at 36-37. We find a lack of support in the record
for this assertion. When telling the VA that it was abandoning the concept of using
temporary power, which would have allowed Alares to pursue interior work, Alares did not
mention any capacity issue with temporary power. Further, on January 22, 2018, only two
months after withdrawing its request for funding to install temporary power, Alares’ project
CBCA 6149, 7071, 7597
32
manager, when complaining to its subcontractor, Delta, about delays to the ceiling
mechanical and AHU that Alares was then saying were Delta’s fault, represented that
“[t]emp power can be provided at any time to facilitate start-up,” Exhibit RS-0323 at 35944,
an assertion that is inconsistent with Alares’ position before the Board. Neither the VA’s
internal electrical engineer nor the A/E saw any issues with using temporary power for startup and operation of the AHUs. Hearing Transcript, Vol. 3, at 95. Although it is unclear
from the record exactly why Alares ultimately decided to abandon the use of temporary
power to mitigate the delay in being able to tie in permanent power, it was not because
temporary power would have been insufficient to provide Alares with the ability to perform
interior rough and finish work or other activities.
Eventually, the permanent power issue was resolved through modification P00007,
which the VA issued on December 6, 2017, increasing Alares’ contract price by $208,982.90
in exchange for the tie-in work and ATS and transformer installations identified in Alares’
change order request. Exhibit RS-0268 at 42721-73. The parties executed the bilateral
modification on December 13, 2017. Exhibit 46 at 1. The agreement expressly reserved
Alares’ right “to submit claims for additional time and costs associated with any time
extension required to perform the work under this modification.” Id. at 2.
Despite the delays in resolving the electrical tie-in issues for obtaining permanent
power in the new building, Alares’ monthly schedule updates never identified permanent
power as a critical path item until October 30, 2017, when, in schedule update no. 14, Alares
indicated that the “critical path for this update has changed . . . [to] run[] thr[ough] the
on-going change management associated with the establishment of permanent power.”
Exhibit 3356 at 214; see Exhibit 19 at 506, 515, 525-26, 536, 546, 556 (comments about
critical nature of permanent power at October and November 2017 meetings). This change
was based upon a change in logic to Alares’ planned schedule to make permanent power a
predecessor to HVAC startup and commissioning, which was a change from the logic in
Alares’ earlier schedules. Exhibit RS-0593 (Expert Report) at 17.
After the parties executed modification P00007, Alares’ next several schedule updates
continued to maintain a logic showing the critical path continuing to run through permanent
power. Exhibit RS-0593 (Expert Report) at 18. The prior delays in obtaining permanent
power had delayed Alares’ submittal for approval of electrical equipment required under
modifications P00006 and P00007. Id. The VA received Alares’ submittal for electrical
equipment on January 25, 2018, and approved it on January 30, 2018. Id. Yet, even though
the VA approved that submittal on January 30, Alares inexplicably did not place its order for
the electrical equipment until April 2, 2018, sixty-two days after the VA’s approval. Exhibits
45 at 207, RS-0593 (Expert Report) at 18.
CBCA 6149, 7071, 7597
33
The VA’s expert, Mr. D’Onofrio, determined that, although some delay in obtaining
permanent power constituted a critical delay for which there was no corresponding
concurrent delay, there were critical delays in the interior rough and finish work, along with
HVAC work, that were the cause of critical delays during Period 3 or were at least concurrent
with delays for which the VA was responsible:
While waiting on permanent power, Alares would have been independently
responsible for critical path delays due to its delayed enclosure and the lack of
progress on the interior build out of the building unrelated to the permanent
power issue. Upon recognizing the added scope associated with the permanent
power issue, much of the delay in the ability to proceed with the added work
was attributable to Alares’ deficient [change order proposal] that underwent
4 revisions, the late execution of Modification P00006, extended/late
submittals and the delay in ordering the required equipment. Independent of
Alares’ declining the VA’s offer to mitigate the permanent power, it still
would have been delayed by its own late progress on HVAC work. Alares
would not have completed its other predecessor work to HVAC startup,
testing, and commissioning for the enclosure, roof, and exterior sheeting on
June 13, 2018, and would not have required temporary or permanent power
through planned tie in of permanent power on July 17, 2018. Even if it did not
exercise the temporary power mitigation that the VA offered to pay for, the
delay that would have been solely due to permanent power would have been
the period between June 13, 2018 and July 17, 2018, meaning Alares would
be owed compensable time for only that portion of delay—34 days.
Exhibit RS-0593 (Expert Report) at 18-19. We agree with Mr. D’Onofrio’s factual analysis.
4.
Interior Rough and Finish Work
In response to the VA’s August 2 cure notice, Alares significantly revised the project
schedule and indicated that it would complete interior work no later than November 22,
2017. See Exhibit 34 to Exhibit RS-0593 at 1-7. Yet, despite the schedule revisions and
promises of a heightened aggressive approach to staffing and to weekend and overtime work,
Alares failed to make any significant progress on the interior rough and finish work. By the
time that it submitted schedule update no. 13 on September 22, 2017, Alares was projecting
that it would not complete interior finishes until January 22, 2018. Exhibit 18 at 85; see
Exhibit RS-0592 (Expert Rebuttal Report) at 11-12 (finding that Alares’ September 22
update showed no significant progress towards interior rough and finish work). When Alares
submitted its next schedule update (no. 14) on October 30, 2017, that completion date had
slipped to April 11, 2018. Exhibit 18 at 85. In fact, in its October 30 report, Alares indicated
CBCA 6149, 7071, 7597
34
that it had not even begun interior drywall work and had instead been focused on completing
remaining sitework and other activities. Exhibit 3356 at 216. The VA noted during each of
its August, September, October, and November 2017 meetings with Alares that “[t]he
breakthrough and work inside the hospital is a critical path issue, and needs to be done as
soon as possible to meet the December 1st deadline” (even though, by November, it was
clear that Alares would not meet that December 1 deadline). Exhibit 19 at 413, 475, 485,
495, 514, 524, 535, 545, 555. Although Alares completed the breakthrough work, it
continued to work slowly on interior work. By May 18, 2018 (the end of Period 3), Alares
was not projecting to finish interior work until August 7, 2018, a significant delay from its
earlier schedules. Exhibit RS-0593 (Expert Report) at 18. Nevertheless, at this point in time,
the delays in performing interior finish work were not causing any delay to the critical path.
Id.
5.
Summary of Critical Path Delays in Period 3
The initial critical path delays during this period were caused by Alares’ delays in
enclosing the building and failing to advance interior rough and finish work. Alares’
schedules do not show the necessity of obtaining permanent power to have become the
critical path issue until October 30, 2017. By that time, Alares had proposed a mitigation
plan involving the installation of temporary power that, for reasons that the Board has not
been able to identify, Alares suddenly abandoned. The VA’s expert has opined that the VA
is responsible for thirty-four days of critical path delay because of permanent power. Exhibit
RS-0593 (Expert Report) at 17. Although he finds that there were an additional
seventy-eight days of critical delay associated with permanent power between the
November 17, 2017, and May 18, 2018, schedule updates, id. at 17-18, he opines that Alares’
concurrent delays in the building enclosure and interior build-out, unrelated to the permanent
power issue, render those seventy-eight days of delay non-compensable:
While waiting on permanent power, Alares would have been independently
responsible for critical path delays due to its delayed enclosure and the lack of
progress on the interior build out of the building unrelated to the permanent
power issue. Upon recognizing the added scope associated with the permanent
power issue, much of the delay in the ability to proceed with the added work
was attributable to Alares’ deficient COP that underwent 4 revisions, the late
execution of Modification P00006, extended/late submittals and the delay in
ordering the required equipment. Independent of Alares’ declining the VA’s
offer to mitigate the permanent power, it still would have been delayed by its
own late progress on HVAC work. Alares would not have completed its other
predecessor work to HVAC startup, testing, and commissioning for the
enclosure, roof, and exterior sheeting on June 13, 2018, and would not have
CBCA 6149, 7071, 7597
35
required temporary or permanent power through planned tie in of permanent
power on July 17, 2018. Even if it did not exercise the temporary power
mitigation that the VA offered to pay for, the delay that would have been
solely due to permanent power would have been the period between June 13,
2018 and July 17, 2018, meaning Alares would be owed compensable time for
only that portion of delay—34 days.
Id. at 18-19.10 Alares has not presented a viable critical path analysis to rebut the VA
expert’s findings.
D.
Period 4 (May 18, 2018, to April 12, 2019)11
1.
The Critical Path in Period 4
Period 4 covers the 330-day period running from May 18, 2018, to April 12, 2019.
RS-0593 (Expert Report) at 24. In its May 18, 2018, schedule update, Alares projected
substantial completion on September 4, 2018, Exhibit 3364 at 272-73, but, in its April 12,
2019, schedule update, the substantial completion date had slipped to June 6, 2019. Exhibit
3370 at 323. This change represents a critical path delay in Period 4 of 275 days. Exhibit
RS-0593 (Expert Report) at 19.
Alares’ contemporaneous construction schedule updates identify the critical path
delays during this period as being caused by (1) the completion of ceilings, doors, and
hardware necessary to proceed with HVAC startup, test/balance, and commissioning;
(2) establishing permanent power to proceed with HVAC startup, test/balance, and
commissioning; (3) alleged delay resulting from added ATS and Building Management
System (BMS) interface work; and (4) alleged delay from an added security camera scope.
Exhibit RS-0593 (Expert Report) at 20. In his report, however, Mr. Maggioli attributes all
critical path delays in this period to a design change for the generator switch gear control
panel, Exhibit 3644 at 5011, and a deficient control sequence design for the HVAC system.
Id. at 5013. The VA’s expert attributes these delays to four activities, some of which he finds
compensable: (1) additional activities needed to satisfy revised medical gas requirements
10
It is not completely clear to the Board why Mr. D’Onofrio selected June 13,
2018, rather than a slightly later date within Period 3, as the start date for the VA’s sole
responsibility for critical path delay during this period, but we will accept his concession that
sole responsibility transferred to the VA by June 13, 2018.
11
We rely in this discussion on the start and end dates for Period 4 that the VA’s
expert selected.
CBCA 6149, 7071, 7597
36
(compensable); (2) Alares’ slow progress in installing cable for permanent power
(non-compensable); (3) Alares’ unexplained increased planned duration for HVAC startup,
testing/balancing, and commissioning (non-compensable); (4) change associated with the
ATS and BMS interface (compensable); and (5) Alares’ unexplained delays in getting around
to performing certain activities in a manner consistent with its planned schedule
(non-compensable). Exhibit RS-0593 (Expert Report) at 24. The VA’s expert believes that
Alares is entitled to a total of 131 compensable days of critical path delay in Period 4 but that
Alares is responsible for the remaining 144 days of critical path delay during this period.
At the beginning of this period, Alares submitted a schedule update (no. 22) showing
that the critical path was shifting from permanent power to the work leading to HVAC
startup, test/balance, and commissioning. Exhibits 3364 at 273, RS-0593 (Expert Report)
at 20. By its next schedule update (no. 23), the change was complete: the path now ran
through the change management associated with medical gas requirements on medical boom
assemblies that the VA had revised, which caused a delay in the critical path, Exhibits 3365
at 280, RS-0593 (Expert Report) at 20, because that work had to be completed before Alares
could perform ceiling tiling, flooring, and door and hardware installation, which, in turn,
delayed commissioning. Exhibit RS-0593 (Expert Report) at 20; Tab O to Exhibit RS-0593.
Installation of the medical gas was scheduled to last forty-five work days. Exhibits 3365 at
280, RS-0593 (Expert Report) at 20. This added scope originally resulted in a sixty-four-day
slippage in the schedule, although two days of that delay were subsequently recaptured.
Exhibit RS-0593 (Expert Report) at 20. The VA, which required the extra work necessitated
by its revisions, bears responsibility for this delay. Id.
The critical path then shifted back to permanent power (followed by HVAC startup,
test/balance, and commissioning) because of an expansion of the amount of time that Alares
now anticipated it would take to obtain permanent power. Exhibit RS-0593 (Expert Report)
at 20. Alares was slow in installing cabling for the permanent power, which contributed to
delaying the anticipated connection to permanent power. Id. at 21. Alares did not obtain
permanent power until September 25, 2018. Exhibit 3369-D at 321. The schedule continued
to slip, as seen in Alares’ September 21 schedule update (no. 26), in which Alares added an
additional twenty-one days to the planned duration of the project to allow for HVAC startup,
test/balance, and commissioning without providing any justifiable explanation of the reason
for the addition of time. Exhibits 3368 at 301-02, RS-0593 (Expert Report) at 22.
Subsequently, at a September 25, 2018, meeting, the VA indicated that additional
wires, not shown on the drawings, would be required from each ATS to the building’s
switchgear. Exhibits 3686 at 5359, 3688 at 5364. At this point, the critical path shifted to
this new ATS work. Exhibit RS-0593 (Expert Report) at 22-23. Alares submitted RFI 159
on September 26, 2018, formally requesting direction for the control wiring, including a
CBCA 6149, 7071, 7597
37
detailed diagram for connecting it. Exhibit 3687 at 5361. The VA responded on September
28, 2018, directing Alares to install thirty-three #14 American wire gauge (AWG) control
wires from each ATS to the control panels. Id. at 5362; Exhibit 3688 at 5365. Although the
VA initially viewed this direction as something within the scope of the existing drawings
based on a note on a drawing directing Alares to provide necessary wiring, Exhibit 3687 at
5362, it eventually acknowledged that the direction was a change and, on November 5, 2018,
requested a change order proposal. Exhibit 3689 at 5369. On November 30, 2018, Alares
provided the VA a COP for the work, id. at 5371-74, addressing the VA’s requirement that
Alares run the thirty-three #14 AWG wires through one-inch electrical metallic tubing (EMT)
that already existed in the building. Because the one-inch EMT conduit was too small to
accommodate thirty-three regular AWG wires, Alares’ subcontractor, Collard, would have
to order special pre-manufactured thin wiring that would allow all of the wires to run through
the one-inch conduit, with a delivery lead time of three to four weeks. Exhibit RS-0527 at
4. The VA provided authorization to proceed with the ATS wiring on December 6, 2018.
Exhibit 3689 at 5369. The ATS wiring and testing was completed on January 22, 2019.
Exhibit RS-0527 at 4. The additional RFI 159 interface work created a sixty-nine-day delay
for which the VA is responsible.
Alares submitted a schedule update (no. 29) on December 14, 2018, reflecting an
anticipated substantial completion date of February 14, 2019. Exhibit 3369-D at 318. At that
point, Alares indicated that the critical path was running through resolution of the interface
requirements between ATS and BMS. Id. at 319. Alares did not submit schedule updates
in January, February, or March 2019. Its next schedule update was not submitted until
April 12, 2019. Exhibit RS-0593 (Expert Report) at 23. By that point, Alares had shifted
the substantial completion date to June 6, 2019, Exhibit 3370 at 323, but provided no
explanation for this delay. See id. There are no daily logs or time records that explain the
work that Alares performed between December 14, 2018, and April 12, 2019. By the time
that the April 12 schedule update was submitted, the critical path, according to Alares, had
shifted to management of security cameras. Exhibit RS-0593 (Expert Report) at 23. Yet, we
do not see that work identified on its schedules.
2.
Alares’ Performance Problems During Period 4
On July 16, 2018, the VA issued a show cause notice to Alares, stating that, “[s]ince
you have failed to perform [the contract] within the time required by its terms and cure the
conditions endangering performance as described to you in the Government’s letter of 02
[August] 2017; the Government is considering terminating the contract under the provisions
for default of this contract.” Exhibit 4139 at 9075. We find no evidence of any improper
motives or nefarious conduct by the VA in the issuance of this show cause notice.
CBCA 6149, 7071, 7597
38
Alares responded to the show cause notice on July 26, 2018, asserting that “[s]everal
significant causes beyond Alares Constructions control and without fault or negligence on
Alares Construction’s part delayed the project and prevented project completion by the
original contract completion date of August 2, 2017 and the extended completion date of
December 1, 2017 deadline” and explaining the reasons that it believed continued
performance of the contract was in the Government’s best interests:
We believe that it is in the best interest of the Government for Alares
Construction to continue working to complete the project. The project is
currently 92% complete (as shown on the May 2018 invoice and VA’s
agreement of the % complete) and activities are on-going to substantially
complete the finishes in 6-8 weeks. The remaining work after the finishes will
only involve the completion of the permanent power installation and follow-on
related tasks, which were delayed due to VA design omissions. We anticipate
completing the permanent power installation and related tasks by November
15, 2018. In addition, there is low risk to the Government because of Alares
Construction’s detailed knowledge of the project and momentum as we near
completion, and any break to that work would only serve to create additional
delays. Simply put, a work stoppage would be less efficient and more
expensive to the government.
Exhibit 129 at 1334. Alares identified the following actions that it had taken “to ensure the
project remains on track”:
1.
2.
3.
4.
5.
6.
Supplemented labor to the drywall contractor
Removed and replaced the panel subcontractor for non-performance
Continued pressure on subcontractors to complete their work
Provided timely response to Government requests
Improved communication with subcontractors
Hiring of additional personnel as space and activities permit
Id. at 1335. Nevertheless, Alares acknowledged the problems that it had been having with
obtaining sufficient manpower to perform:
One issue that was beyond Alares Construction’s control is the availability of
capable and available trades. It is universally accepted that the construction
industry is experiencing a considerable labor shortage. We have continually
requested additional manpower from the subcontractors to accelerate the
schedule.
CBCA 6149, 7071, 7597
39
Id. At that point, it anticipated substantial completion of the project by November 6, 2018.
Id. at 1342.
As Alares reported to the VA, it was having trouble getting its subcontractors to
provide sufficient manpower for the project and was having to correct work that its
subcontractors had performed incorrectly. For example, on June 5, 2018, Alares notified its
glass subcontractor, which had been on the project since May 2017, that it was being
terminated for default because “[i]t has come to a point where your actions have been
detrimental to the project causing significant financial harm to Alares Construction and
unacceptable project schedule delays.” Exhibit RS-0443 at 151157. Alares reported that the
subcontractor had “demonstrated a lack of experience with the installation of [the] Insulated
Panel System” and had “installed [it] improperly per the manufacturer’s instructions,”
“proceed[ing] with the installation of the exterior panels without the proper insulation
installation.” Id. It complained that the subcontractor had “demonstrated the inability to
properly measure for installation [of] the individual panels as the initial panel order was
manufactured improperly and had to be discarded,” with “[t]he panel reorder caus[ing] more
schedule delays.” Id. It further complained that the subcontractor’s improper removal of
soffit panels had “resulted in a two to three month delay to finish the panel system as new
panels will need to be manufactured, shipped and installed,” id. at 151157-58, and that it had
“failed to achieve the schedule as provided [by Alares] at the beginning of the project,” as
explained below:
[The subcontractor] started the exterior panel project in September 2017 which
was scheduled to take one month. [It] still has not finished the exterior panels.
You are nine (9) months behind schedule. The exterior panels system requires
rework and the soffit panels were not installed correctly.
Id. at 151158.
Similarly, on September 4, 2018, Alares terminated its framing and drywall
subcontractor, which had worked the project since November 2016, because the
subcontractor had “failed to properly provide sufficient manpower to complete the project.”
Exhibit RS-0480 at 151050. Alares said that it had “sent dozens of emails . . . requesting
additional manpower because the project schedule was delayed” but that the subcontractor
“did not send the manpower.” Id. Alares also complained about the subcontractor’s
“fail[ure] to install framing and drywall in accordance with the contract documents[,] causing
Alares . . . to retain additional resources to correct [the subcontractor’s] mistakes,” at
“significant costs to Alares.” Id. In terminating the subcontract, Alares represented that the
subcontractor’s “actions have been detrimental to the project causing significant financial
harm to Alares Construction and unacceptable project schedule delays.” Id.
CBCA 6149, 7071, 7597
40
At the same time, Alares’ subcontractors were complaining about Alares’ lack of job
management for this project. One subcontractor contacted the other subcontractors through
a group email on July 23, 2018, to express frustrations with Alares’ project management
failures:
To my fellow owners and/or subcontractors,
I can’t speak for each of your companies, however our experience at the above
named project is something I’ve never experienced in my 27 years of owning
my company; whether it’s payments, lack of schedule, lack of job meetings,
change orders, or being treated fairly[.] We have dealt with approximately 6
[project managers] on this job, and I ran out of fingers counting supers.
I’d like to suggest meeting at my office to discuss a possible team effort in
dealing with Alares. Please feel free to bring your counsel or check with them
as I believe there is power and strength in numbers in getting us compensated
for the delays that their combined lack of management on this project created.
Exhibit RT-0042 at 1.
The VA contracting officer ultimately did not terminate the contract for default and
allowed contract performance to continue. Nevertheless, Alares did not meet the November
2018 substantial completion deadline that it set for itself in its show cause response.
3.
Summary of Critical Path Delays in Period 4
The VA is responsible for a total of sixty-two days of critical path delay early in this
period that resulted from the VA’s revision of medical gas requirements in the contract.
The VA is also responsible for sixty-nine days of critical path delay that resulted from the
change management of the ATS and BMS interface and associated added work, which was
a contract change.13
12
12
The VA’s expert showed that, originally, there were sixty-four days of critical
delay from the revision to the medical gas requirements but that Alares was able to recapture
two of those days and decrease the duration of the delay. See Exhibit RS-0593 (Expert
Report) at 20-21, 24.
13
The direct costs associated with the VA’s changes to the medical gas
requirements and the ATS/BMS interface are not before us in these appeals. They appear
to have been resolved through Alares’ October 29, 2019, “Final Release of Claims,” Exhibit
CBCA 6149, 7071, 7597
41
The VA’s expert identifies eleven days of critical path delay between the July 20 and
August 17, 2018, schedule updates, which were the result of Alares falling behind in its
cabling installation. Exhibit RS-0593 (Expert Report) at 21. Although the VA’s expert finds
this delay to be Alares’ responsibility, id., Alares met its burden of showing that the VA’s
vendor was the cause of this delay. The email exchanges between the VA’s COR and
Alares’ project manager, George Archambeault, sufficiently support Alares’ position because
the COR acknowledged that the VA’s other contractor had to resubmit a junction box,
causing a delay, and Mr. Archambeault explained to the COR how the junction box rather
than the conduits caused the delay because the junction box “isn’t in place and [he has] no
cut sheets on it after multiple requests.” Exhibit 4150 at 9184; see Hearing Transcript,
Vol. 5, at 5-8.
Remaining days of delay in Period 4 are Alares’ responsibility. Delays in HVAC
startup, testing and balancing, and commissioning resulted from Alares’ slow discussions
with its vendor and the historical timing for inspections and follow up on the project. And,
during the last 112 days in Period 4, Alares was inexplicably deferring performance of a part
of the contract (the security camera scope). Even if the security camera scope was not the
cause of delay here and, as Alares argues, the delay was instead because of a delay in the
performance of one of its subcontractors, Stryker, Alares cannot impose liability on the VA
for deficiencies of Alares’ subcontractor.
E.
Period 5 (April 12 to September 6, 2019)
Period 5 covers the 148-day period of time running from April 12 to September 6,
2019, the latter date being when the VA accepted the project “as is.” Exhibit RS-0593
(Expert Report) at 24-25. In its April 12, 2019, schedule update at the start of this period,
Alares projected substantial completion by June 6, 2019. Exhibit 3370 at 323. The VA’s
expert opines that there were ninety-two days of delay to the critical path during this period,
none of which he believes are compensable, running from the projected June 6 substantial
completion date through the VA’s “as is” acceptance of the work on September 6, 2019, see
Exhibit RS-0593 (Expert Report) at 24-25, while Alares asserts that every day between
April 12 and September 6—147 days in total—constitutes a critical path delay for which the
VA is responsible.14 Strangely, in addressing delay days, neither party addresses the fact that
RS-0533 at 3116, which is discussed below.
14
Mr. Maggioli used a different period of time—February 14 to September 6,
2019—than Mr. D’Onofrio as Period 5. For that period, Mr. Maggioli found that every
single day during that period—205 days—were compensable delay days. Exhibit 3644 at
5013-15, 5018. Although we are using April 12, 2019, as the start date for Period 5, it is
CBCA 6149, 7071, 7597
42
most of the alleged delays to the critical path occurred long after the substantial completion
date of the project.
Specifically, on May 15, 2019, Alares provided the VA COR with what it called the
“updated punch list from the final walkthrough.” Exhibit 3920-29-00 at 7546. Although
Alares still had to complete commissioning, install some seismic bracing, and adjust some
doors, Alares told the VA that it had achieved substantial completion of the project:
Based on the work completed to date we are substantially complete in
accordance with the contract documents and the VA can take possession of the
space.
Id. Alares repeated its representation that the project was substantially complete, “except for
a few punchlist and warranty items,” and was ready for beneficial occupancy at a weekly
meeting on May 16, 2019. Exhibit 82 at 242. Alares continues to believe that the project
was substantially complete on May 15, 2019, see Hearing Transcript, Vol. 1, at 154-55; id.,
Vol. 2, at 34, and the VA essentially agrees. Exhibits 4310 at 11063, 4311 at 11125.15 We
agree that substantial completion occurred on May 15, 2019.
Two weeks later, by email dated June 5, 2019, Mr. Maggioli reiterated that the project
was substantially complete when he informed the VA contracting officer that “[s]ince the
project is substantially complete the weekly meetings are no longer needed,” that “going
forward the Thursday morning meetings are canceled,” and that Alares would “provide the
VA updates of the punchlist items, warranty issues and the change order work as they get
completed.” Exhibit 144 at 1522. Although the VA contracting officer suggested that
continued weekly meetings would be beneficial “until all remaining items are complete,” id.
at 1521, Mr. Maggioli responded that Alares would “require a change modification to attend
clear from his delay report that Mr. Maggioli believes that every single day from April 12
through September 6, 2019, constitutes a compensable delay day.
15
The VA presented Mr. Boyle to testify for the VA in response to a deposition
notice under Rule 30(b)(6) of the Federal Rules of Civil Procedures in which the VA was
asked to identify the date that it believes the project was substantially complete. See Exhibit
4310. Mr. Boyle responded that substantial completion would have been the date of
“transmittal of the final consolidated punch list,” which he identified as “early June 2019.”
Id. at 11063; see Exhibit 4311 at 11125. Because the punch list that we located in the record
that resulted from the parties’ final walkthrough was provided on May 15, 2019, see Exhibit
3920-29-00 at 7546, we interpret Mr. Boyle’s testimony as acknowledging May 15 as the
date of substantial completion.
CBCA 6149, 7071, 7597
43
these meetings” and that Alares could “keep everyone updated on the progress via email
which is more than adequate considering where we are in the project.” Id. The weekly
meetings stopped.
After Alares submitted its April 12, 2019, schedule update (no. 30), it never again
submitted a schedule update. Exhibit RS-0593 (Expert Report) at 25; Hearing Transcript,
Vol. 2, at 32-33. Beginning May 24, 2019, it also stopped creating daily activity reports of
on-site work. Exhibits 3635 at 4143, RS-0593 (Expert Report) at 25. It did not create
minutes for any meetings and, in fact, had no meetings with the VA after May 16, 2019.
Exhibit 82 at 239-41.16 Alares has provided virtually no contemporaneous evidence of what
work, if any, it performed after May 24, 2019. Although it maintained sign-in sheets for the
project site through June 14, 2019, the only notations on them indicate work that is more
indicative of punch list work than continuing construction work. See, e.g., Exhibit 3643 at
4996 (note to Alares from a subcontractor on June 14, 2019, sign-in sheet: “There were 2
Broken Light Jars and one light fixture that is corroded and needs replaced! I drained all the
water out of the others. Water getting inside which caused glass to break.”).
After declaring substantial completion, Alares still had to complete the commissioning
process for the building. As defined in the contract specifications, commissioning under this
contract was “a systematic process of verifying that the building systems perform
interactively according to the construction documents and the VA’s operational needs.”
Exhibit 6 at 233. “The commissioning process [was to] encompass and coordinate the
system documentation, equipment startup, control system calibration, testing and balancing,
performance testing and training.” Id. The specifications anticipated that there would be
“[c]ommissioning during the construction and post-occupancy phases.” Id.
On July 8, 2019, EBI Consulting (EBI) issued the “Final Commissioning Report” for
the building. Exhibit 4234. As part of its report, EBI identified several “Major Issues
Outstanding,” including low flow frequency in the chiller, negative pressure volume issues
in the anteroom, balance issues involving an exhaust tie-in in the soiled utility room, and the
humidifiers’ return air humidity levels. Id. at 9468.
On July 26, 2019, Alares submitted RFI 179 to the VA, seeking direction for the
control sequences (for controlling the heating and cooling of the space, as well as two
16
Although the VA’s expert represented in his report that the last meeting
minutes were issued on May 23, 2019, Exhibit RS-0593 (Expert Report) at 25, we have been
unable to find minutes from that May 23 meeting in the record.
CBCA 6149, 7071, 7597
44
isolation rooms that have negative pressure for infectious control). Hearing Transcript,
Vol. 1, at 147. In that RFI, Alares complained as follows:
Delta and the VA’s proprietary vendor JCI has retested all the sequences to try
to resolve the two issues noted by the [commissioning] agent. Also VA noted
an alarm issue with the isolation rooms. According to Delta, the sequences
have been programmed according to the contract documents.
As you know, we have conducted retesting on several occasions over the last
month to try to resolve the chilled water flow and humidifier issues identified
by the [commissioning] agent. In testing the sequences and programming for
the chilled water flow and humidifier, we identified more issues that are design
related. We brought back the balancer on one of the site visits to verify
whether there were balancing issues and found that there were not any that
would interfere with the operation of the facility.
At this point we have exhausted our options to resolve the identified issues and
will need the engineer of record to resolve the noted issues. We believe the
chilled water flow issue was resolved by changing the control sequences.
However, we need engineer of record approval of the changes. Also the
humidifier issue remains unresolved and we believe it is due to design issues.
Exhibit 3692 at 5382. Alares listed several issues that it wanted the VA to address, all of
which it claimed were design defects. Id. at 5382-86. Alares requested a response by
August 5, 2019. Id. at 5382.
The VA did not respond to the RFI. Instead, in an email dated September 6, 2019, the
VA contracting officer notified Alares that the VA would not respond to RFI 179 and that,
instead, the VA was immediately “taking over full occupancy of the space and acceptance
of any/all remaining outstanding items” on the project. Exhibits 145 at 1526, 3691 at 5379.
She asked that Alares “forward a release of claims and notate any items Alares is not
providing full release for.” Exhibit 3691 at 5379. A few days later, by email dated
September 12, 2019, the VA contracting officer made clear that the VA had accepted the
building “as is” and that Alares’ work was done:
The VA has taken full ownership of this space as indicated to you on 9/6. If
you or any subs need to access this space, it needs to be fully coordinated and
approved by the VA at least one week in advance. You informed the VA on
9/10 at 2:05pm your sub would be onsite, without fully disclosing the
reason/need for their visit, to which Scott [DeRosa] responded on 9/11 at
CBCA 6149, 7071, 7597
45
11:47am informing you it would be a conflict. This email was delivered and
read by you yet the sub still came on site on 9/12. Any unauthorized visits
made to this site will be considered as trespassing.
Exhibit 145 at 1523. Between July 26, when Alares submitted RFI 179, and September 6,
2019, Alares was on the project site a total of no more than four days. Hearing Transcript,
Vol. 4, at 24. One of the VA’s employees testified that the VA had to hire other contractors
to complete the project work, including electrical work, medical gas tie-ins to the Stryker
boom, work on exhaust fans, and velocity nozzle installation. Exhibit 4309 at 11048
(Deposition Testimony of Michael LeBeau (June 7, 2022)); see Exhibits 4243, 4244, 4246,
4247 (evidencing the VA’s hiring of other contractors to perform additional work after
September 6); Closing Argument Transcript at 93-94.
On October 29, 2019, Alares signed and provided the VA with the following “Final
Release of Claims” on this contract, excepting REAs 1 through 29, to obtain final payment:
KNOW ALL MEN BY THESE PRESENTS: In consideration of the premise
and sum of $8,243,391.89 (Eight Million two hundred forty three thousand
three hundred ninety one and eighty nine cents) lawful money of the United
States of America (hereinafter called the “Government”) of which of
$8,207,391.89 (Eight Million two hundred seven thousand three hundred
ninety one and eighty nine cents) of the total amount has been paid, and a
balance due of $36,000 (thirty six thousand) which is to be paid by the
Government under the above noted contract, the undersigned contractor does
remise, release and forever discharge the Government, its officers, agents and
employees of and from all liabilities, obligations and claims whatsoever in law
and equity under, arising out of or by virtue of said contract, except specified
claims [REAs 1 through 29] in stated amounts, or in estimated amounts when
the amounts are not susceptible of exact [sic] by the contractor [as identified
in the release itself].
Exhibit RS-0533 at 3116. The excepted REAs included REA 17 (Repair Patient Lift
System), REA 20 (Extended General Conditions), REA 25 (Attorney Fees), and REA 26
(Delta Mechanical Issues). Id.
In these appeals, Alares asserts that every day between April 12 and September 6,
2019, including days after substantial completion of the building, constitutes a compensable
delay to the critical path of contract performance, alleging that these delays were caused by
defects in the “control sequences design.” Hearing Transcript, Vol. 1, at 147; see Appellant’s
Closing Argument Presentation PowerPoint at 71. Mr. Maggioli testified at the hearing that
CBCA 6149, 7071, 7597
46
“[w]e could not complete commissioning, which was a critical task, until the control
sequences were redesigned, and we couldn’t turn the space over to the Government until all
those control sequences were properly working.” Hearing Transcript, Vol. 1, at 147. Alares
also argues that the VA’s lack of a response to Alares’s RFI 179 led to Alares being unable
to complete the HVAC commissioning and thus project completion. Appellant’s Closing
Argument Presentation PowerPoint at 74; Exhibit 3692.
III.
Alares’ Claims and Proceedings Before the Board
A.
CBCA 6149
On March 1, 2018, long before completing work on this project, Alares submitted a
request for an equitable adjustment (REA) to the VA contracting officer, seeking (1) payment
of $1,039,693 for extended general conditions allegedly resulting from government-caused
schedule delays and differing site conditions, and (2) a time extension for completion of the
project from August 2, 2017, to August 3, 2018. Exhibit 50 at 1. Alares alleged that the
major issues causing scheduling delays at that time included differing site conditions relating
to permanent power (259 days), differing underground site conditions (forty-nine days), and
the need for an additional steam generator (thirty-eight days). Id. at 3-4. Alares asserted that
“[t]here were other delays due to differing site conditions but these tasks were not on the
project schedule critical path.” Id. at 1. In the REA, Alares included the claim certification
language required by the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101–7109. Exhibit
50 at 4.
On April 2, 2018, Alares converted its REA into a certified claim. Exhibit 4274.17
On June 5, 2018, after the deadline for the contracting officer to issue a decision on the claim
had passed, Alares filed a notice of appeal with the Board of the contracting officer’s
“deemed denial” of the claim, which the Clerk of the Board docketed as CBCA 6149.
The parties, on September 6, 2018, requested that the Chair of the Board assign a
mediator to assist them in settlement efforts, a request that the Chair granted. At a certain
point in time, the parties ended the mediation but continued to engage in settlement efforts
for several months. This appeal essentially remained stayed while the parties engaged in
mediation efforts.
17
Alares filed an updated certification for the April 2, 2018, claim with the Board
on March 31, 2021.
CBCA 6149, 7071, 7597
47
On May 29, 2019, while the parties were still engaged in mediation, Alares submitted
REA 20 to the VA contracting officer, essentially updating its April 2, 2018, claim.
See Exhibit RS-0527 at 1-7. It requested an equitable adjustment of $1,903,257.01 “for
extended general conditions due to government schedule delays and differing site conditions
. . . caused by the government.” Id. at 1, 7. It asserted that the VA was responsible for 682
calendar days of delay at that point in time, which it claimed were caused by “[d]iffering site
conditions relating to permanent power due to design errors,” “[d]iffering [u]nderground
[s]ite conditions while doing site work,” “[a]dditional steam generator due to design errors,”
and “ATS rewiring due to design errors.” Id. at 1.
On February 10, 2020, again while the parties were continuing their settlement efforts,
Alares submitted another revised version of its April 2, 2018, certified delay claim to the VA
contracting officer, increasing the amount of its claim for “extended general conditions due
to government schedule delays and differing site conditions” to $1,941,801 and alleging 764
days of critical path delay. RS-0535 at 1, 28. Alares alleged that the critical path delays for
which the VA was responsible were caused by the need to redesign the AHU equipment to
accommodate a second steam engine, design errors relating to the new electric service,
design errors relating to back-up emergency power, and a delay, and failure to coordinate
requirements for installing the Stryker Boom equipment in the building. Id. at 2-7. It also
alleged that the VA was responsible for numerous other delays that were not on the critical
path, id. at 7-26, including various weather delays between November 2016 and May 2017
that it asserted “equate[d] to a critical path delay of 25 working days.” Id. at 9.
On August 10, 2020, Alares submitted yet another revised version of its delay claim
to the VA contracting officer, asserting that it was modifying its claim “due to recent REA
#20 review comments by the VA,” reducing its monetary demand to $1,535,552, and
reducing its total claimed compensable time to 653 days. RS-0537 at 1, 30. It explained the
basis of its updated claim as follows:
The government reached beneficial occupancy of the Project on May 10, 2019
when the VA took possession of the ICU space. However, the contracting
officer notified Alares Construction on September 6, 2019 stating the VA will
be taking over full occupancy of the space and acceptance of any/all remaining
outstanding items. The September 6, 2019 date was 764 days beyond the
Contract completion date of August 2, 2017. Alares Construction is seeking
total compensable time of 653 days.
CBCA 6149, 7071, 7597
48
Id. at 1.18
Proceedings in CBCA 6149 and other Alares appeals that the Board had previously
consolidated with CBCA 6149, all of which arose out of the same contract, remained stayed
until April 13, 2021, when the Board granted the parties’ joint request to lift the stay of
proceedings. On June 28, 2021, the VA filed a motion to dismiss the appeal for lack of
jurisdiction, alleging that Alares’ name in these appeals differs from the name on the contract
at issue and that, therefore, Alares lacked privity of contract to pursue the appeal. The Board
denied the VA’s motion by decision dated August 11, 2021. Alares Construction, Inc. v.
Department of Veterans Affairs, CBCA 6149, et al., 21-1 BCA ¶ 37,906, at 184,099-100.
Subsequently, the parties engaged in discovery. The VA engaged Mr. D’Onofrio to
serve as its expert witness to analyze the delays on this project using a CPM analysis, and he
prepared a report of his findings, which the VA shared with Alares. Alares’ president,
Mr. Maggioli, prepared a delay analysis for his company, and Alares shared his report with
the VA.
Alares also requested dismissal with prejudice of six appeals—CBCA 7069, 7070,
7072, 7074, 7075, and 7086—that the Board had previously consolidated with CBCA 6149,
representing that the parties had settled the claims at issue in those appeals. Modification
P00015, executed November 16, 2021, resolved Alares’ direct labor cost claims for smoke
seal installation, scraping fireproofing, control joint installation, raising patient boom
supports, reimbursement for egress maintenance, and metal roof repairs. Exhibit 3301 at 12.
In those six claims, taken together, Alares had sought damages totaling $167,756, but it
agreed to resolve those claims in exchange for payment by the VA of $88,000 and provided
the following release:
RELEASE. In exchange for the relief enumerated [in this contract
modification], Alares agrees that such relief constitutes full and complete
settlement and satisfaction of the Claims including but not limited to all costs,
18
On May 28, 2021, Alares filed in CBCA 6149 and the appeals with which
CBCA 6149 was then consolidated what it titled “Amended Notice of Appeal,” which
purported to amend the notice of appeal in CBCA 6149. Alares asserted in its amended
notice that the VA contracting officer never issued a final decision on its August 10, 2020,
claim; that it therefore was “deemed denied”; and that Alares was adding that deemed denial
to CBCA 6149. The Clerk of the Board did not docket the “Amended Notice of Appeal” as
a new appeal but allowed it to remain filed as part of CBCA 6149.
CBCA 6149, 7071, 7597
49
direct and indirect, interest, and attorney fees including those recoverable
under the Equal Access to Justice Act (EAJA).
Exhibit 3301 at 13.
On November 22, 2022, as part of its responses to written discovery requests that the
VA had served, Alares again changed the amount of damages that it was claiming. Although
Alares indicated in its written discovery responses that it had recalculated its damages to
remove attorney fees related to claim preparation and prosecution, see Exhibit 3891 at 7078,
its claimed damages actually increased from $1,535,552 to $1,691,701.85. Exhibit 3901 at 1.
No explanation for the basis of the increase was provided.
B.
CBCA 7071
On February 10, 2020, Alares submitted REA 17 (revision 1) to the VA contracting
officer, seeking payment of $7344.70 for being required to remove and then reinstall patient
lift (LIKO) system supports that it had installed above the ceiling in Rooms 208, 209, 211,
and 213 to allow duct and pipe work to be completed. Exhibit 66T at 756-59. It asserted that
this work was caused by conflicts in the detailed layouts for the LIKO system that the VA
had provided. Id. at 756. The VA contracting officer denied the REA, which it considered
to be a claim, by decision dated January 4, 2021, finding that the only reason that Alares had
to remove the supports was because one of its subcontractors had installed them before a
different subcontractor had installed piping that needed to be installed before the supports
were put into place. Exhibit 66V at 799-800. The contracting officer represented that “[t]he
lack of coordination by the Contractor is the only reason this additional work was required.”
Id. at 800. The decision provided Alares notice of its appeal rights. Id. at 802.
Alares filed a notice of appeal with the Board on March 17, 2021, which the Clerk of
the Board docketed as CBCA 7071. By order dated April 2, 2021, the Board consolidated
CBCA 7071 (and other Alares appeals that were then pending) with CBCA 6149.
C.
CBCA 7597
On July 27, 2022, Alares filed with the Board in CBCA 6149 what it called a “second
addendum to its claim for general conditions at the [CBCA].” Exhibit 4273. In that
“addendum,” it attempted to add a claim for the VA’s alleged breach of good faith and fair
dealing to its existing appeals, asserting that VA officials took actions to deny change order
requests and REAs because of funding limitations that would have caused the VA, if it
approved the requests, to exceed the available appropriation for Alares’ contract. See id.
The VA argued to the Board that the second addendum was in reality a new claim over which
CBCA 6149, 7071, 7597
50
the Board lacked jurisdiction because it had never been submitted to the VA contracting
officer for a decision. By decision dated November 9, 2022, the Board denied Alares’
request to add its “second addendum” and its supporting documents to the record, finding
that the Board lacked jurisdiction to consider the addendum. Alares Construction, Inc. v.
Department of Veterans Affairs, CBCA 6149, et al., 22-1 BCA ¶ 38,225, at 185,649.
While awaiting the Board’s decision on whether the Board possessed jurisdiction to
consider its “second addendum,” Alares converted its “second addendum” into a new CDA
claim through which it sought payment of $1,679,495.60 and, on September 22, 2022,
submitted it to the VA contracting officer, along with a claim certification from
Mr. Maggioli. Exhibit 4278. By decision dated November 28, 2022, the VA contracting
officer denied that claim. Exhibit 4279. On November 30, 2022, the Clerk of the Board
docketed Alares’ appeal of that decision as CBCA 7597.
The VA filed a motion seeking to dismiss CBCA 7597 for lack of jurisdiction,
alleging that the new claim failed clearly to identify the sum certain to which Alares believed
itself entitled and, in the alternative, seeking summary judgment, alleging that the “Final
Release of Claims” that Alares executed on October 29, 2019, discharged the VA from all
liabilities under the contract except for those expressly listed therein. The Board denied the
VA’s motion by decision dated March 3, 2023. Alares Construction, Inc. v. Department of
Veterans Affairs, CBCA 7597, 23-1 BCA ¶ 38,296, at 185,927-28. By order dated March 6,
2023, the Board consolidated CBCA 7597 with CBCA 6149 and 7071 and indicated that it
would be included as a part of the hearing that was scheduled to begin on March 8, 2023.
D.
The Consolidated Hearing and Post-Hearing Proceedings
Beginning Wednesday, March 8, 2023, the parties presented five days of witness
testimony before Judge Drummond at a consolidated hearing covering CBCA 6149, 7071,
and 7597 that concluded on Tuesday, March 14, 2023. The hearing was conducted virtually
using the ZoomGov platform. During the hearing, Judge Drummond denied Alares’ request
to qualify Mr. Maggioli as an expert in scheduling and delay analysis, determining that
Alares had not established his qualifications. Hearing Transcript, Vol. 1, at 39-42.
Nevertheless, Judge Drummond allowed Mr. Maggioli to testify about his views on the
project’s critical path of performance as a lay witness, id. at 42, and the VA did not request
that his report be removed from the appeal file. Judge Drummond indicated that he would
give Mr. Maggioli’s report “the appropriate weight” but would not “refer[] to it as an expert
report.” Id. at 42. At the VA’s request, Judge Drummond qualified Mr. D’Onofrio, without
objection from Alares, as an expert in CPM scheduling, schedule delay analysis, time impact
analysis, disruption and inefficiency analysis, and construction. Hearing Transcript, Vol. 4,
at 10-11.
CBCA 6149, 7071, 7597
51
In an order issued following the conclusion of the hearing, Judge Drummond directed
the parties to file post-hearing briefs no later than May 18, 2023. See Post-Hearing Order
(Mar. 14, 2023) at 1. By May 16, 2023, when the parties requested an enlargement of time
for filing those briefs, Judge Drummond had unexpectedly become unable to continue work
on these appeals. On May 19, 2023, the Clerk of the Board assigned Judge Harold D. Lester,
Jr., to take Judge Drummond’s place as the presiding judge in these appeals. Judge
Drummond passed away in June 2023.
After being assigned to these appeals, the new presiding judge immediately requested
a status conference with the parties to discuss the situation and to “obtain the parties’ views
regarding the extent to which any modifications to the existing schedule of post-hearing
activities may be necessary” because of the reassignment of the appeals to a judge other than
the one who had heard the witnesses testify at the hearing, “including a discussion of whether
either party will want to present any live witness testimony for a second time.” Order (May
19, 2023) at 2. During the conference, both parties indicated that they did not wish to ask
for a new hearing or to recall witnesses to testify except to the extent that the new presiding
judge would find it helpful. Conference Memorandum (May 25, 2023) at 2. The new
presiding judge indicated that, after the parties had completed post-hearing briefing, he
would schedule a closing oral argument to help ensure that he fully understood the issues and
evidence in the appeals. Id. at 3.
The parties submitted their post-hearing briefs on June 16, 2023, and reply briefs on
September 14, 2023. They provided their positions to the Board through detailed
presentations at the closing oral argument on October 18, 2023.
Discussion
I.
Evidentiary Issues
A.
Requirements When an Appeal is Reassigned After the Hearing
Neither the Board’s Rules nor due process mandate that the judge who presided over
the taking of testimony at a hearing be one of the judges who ultimately decides the case.
See, e.g., Tri-Cor, Inc. v. United States, 458 F.2d 112, 116-17 (Ct. Cl. 1972); Blake
Construction Co., GSBCA 2196, 70-1 BCA ¶ 8166, at 37,941-42. Rule 63 of the Federal
Rules of Civil Procedure (FRCP), to which the Board looks for guidance, see Board
Rule 1(c), provides that, “[i]f a judge conducting a hearing or trial is unable to proceed, any
other judge may proceed upon certifying familiarity with the record and determining that the
case may be completed without prejudice to the parties.” Judge Drummond’s successor in
these appeals studied the appeal record thoroughly, went through the voluminous number of
CBCA 6149, 7071, 7597
52
exhibits contained in the appeal file, digested and analyzed the competing reports from the
VA’s expert witness and Alares’ president, and repeatedly reviewed the hearing transcripts
of the witnesses’ live testimony. In addition, at the successor judge’s request, the parties
presented detailed closing arguments on October 18, 2023, after post-hearing briefing was
complete, to walk the successor judge through the factual evidence supporting their positions
in the appeals as well as their legal theories for or against recovery, an effort that the
successor presiding judge found to be very helpful. To the extent that FRCP 63 requires the
successor presiding judge formally to certify his familiarity with the record and that these
appeals may proceed without prejudice to the contractors, he does so here.
Even with that certification, FRCP 63 requires that, “[i]n a hearing or a nonjury trial,
the successor judge must, at a party’s request, recall any witness whose testimony is material
and disputed and who is available to testify again without due burden.” “Courts . . . have
read into Rule 63 the negative inference that if the presiding judge in a civil case has yet to
issue his findings of fact and conclusions of law, a successor judge must retry the case”
unless “all parties . . . consent to allow the successor judge to make findings of fact and
conclusions of law based on the trial transcript.” Emerson Electric Co. v. General Electric
Co., 846 F.2d 1324, 1325-26 (11th Cir. 1988); see Townsend v. Gray Line Bus Co., 767 F.2d
11, 17-18 (1st Cir. 1985) (“An exception to the rule mandating a retrial is normally made
only if all parties agree to allow the successor judge . . . to make findings of fact and
conclusions of law based on a prior, or stipulated, record.”). Here, we expressly offered the
parties the opportunity to re-present witness testimony before the successor judge, but the
parties declined that opportunity in favor of extensive post-hearing briefing and the ability
to walk the successor judge through their positions in detail at a closing argument.
FRCP 63 also permits the successor judge, sua sponte, to “recall any other witness”
from whom the judge might like to hear. We elected not to require the parties to go to the
expense of presenting witness testimony a second time.
B.
Alares’ Request to Disregard Certain Appeal File Documents
In its post-hearing reply brief, the VA has cited to several appeal file documents that
were not discussed during the hearing (Exhibits 17, RS-0103, RS-0222, and RS-0589),
including the deposition transcript of Alares’ finance manager (Exhibit RS-0058), who
provided testimony about the preparation of financial documents upon which Alares’ cost
claims are based. Alares asks that we disregard those exhibits, stating that it is unfair for the
VA to use them to attempt “to impeach Mr. Maggioli when those documents were never
raised to Mr. Maggioli during cross-examination” at the hearing and “he was never given an
opportunity to explain/address them.” Appellant’s Post-Hearing Reply Brief at 36.
CBCA 6149, 7071, 7597
53
Under Board Rule 9(a) (48 CFR 6101.9(a) (2024)), “‘[t]he record on which the Board
will decide a case includes,’ among other things, ‘Rule 4 appeal file exhibits other than those
to which an objection is sustained,’ other documents or parts thereof admitted as evidence
at a hearing, and transcripts of testimony before the Board.” SRM Group, Inc. v. Department
of Homeland Security, CBCA 5194-R, et al., 21-1 BCA ¶ 37,869, at 183,886 (quoting Rule
9(a)), aff’d, No. 2021-2104, 2022 WL 1089228 (Fed. Cir. Apr. 12, 2022). “Accordingly, in
reaching a decision in an appeal following a hearing, the Board is not limited to the testimony
presented and exhibits introduced at the hearing but may also ‘rely upon any evidence
contained within the appeal file.’” Id. (quoting Springcar Co. v. General Services
Administration, CBCA 1310-R, et al., 10-2 BCA ¶ 34,534, at 170,333). Under Board
Rule 4(g), “[t]he Board considers appeal file exhibits part of the record for decision under
Rule 9(a) unless a party objects to an exhibit within the time set by the Board and the Board
sustains the objection.”19
Alares has no basis for waiting until its post-hearing reply brief was due to request
exclusion of this evidence. Here, the VA added Exhibit 17 to the appeal file on July 9, 2018,
almost five years before the hearing in these appeals, and added the other exhibits on
February 3, 2023, more than a month before the hearing. By order dated January 17, 2023,
Judge Drummond adopted the VA’s unopposed proposed revised schedule (filed on
December 29, 2022) that identified a deadline of February 10, 2023, for submitting
objections to appeal file documents and a deadline of February 17, 2023, for objecting to
exhibits. Alares filed a list of appeal file exhibits to which it objected by the February 10
deadline, but none of the exhibits that Alares now asks the Board to disregard was listed
there. Neither party filed objections to exhibits.
Even if we might be willing for good cause to consider a late-filed objection in some
instances, Alares has identified no good cause here. Further, Judge Drummond, at the
conclusion of the hearing on March 14, 2023, closed the evidentiary record in these appeals,
“except for submission to the clerk’s office and the briefs that will be coming in.” Hearing
19
Although Board judges, under their authority to “alter these procedures . . . to
promote the just, informal, expeditious, and inexpensive resolution of a case,” Board Rule
1(a), have the authority to limit the documents that they will consider in deciding an appeal
to those that the parties discuss with a witness or reference at a hearing, see Lebolo-Watts
Constructors 01 JV, LLC, ASBCA 59740, et al., 21-1 BCA ¶ 37,789, at 183,426 (2020)
(discussing another board’s analogous authority), aff’d, No. 21-1749, 2022 WL 499850 (Fed.
Cir. Feb. 18, 2022), Judge Drummond did not announce any such limitation in this case,
meaning that Alares has no right to insist upon such a limitation here. In this instance, we
will apply the standard rule set forth in Rules 4(g) and 9(a).
CBCA 6149, 7071, 7597
54
Transcript, Vol. 5, at 91; see Order (Mar. 14, 2023) at 1 (“The record will close at the end
of March 14, 2023, except for evidence that was already admitted and the filing of posthearing and reply briefs.”). Alares’ objections, first raised four months after the record
closed, are clearly too late. Its objections are considered waived.
C.
Alares’ Failure to Qualify its Scheduling Witness as an Expert
During discovery, Alares identified its CEO, Mr. Maggioli, as its expert witness in
scheduling and delay analysis, and Mr. Maggioli prepared a “Schedule Delay Analysis
Report” in which he constructed what he identified as “an ‘as-built’ critical path” schedule
for the project (Exhibit 3644 at 3) purporting to assess critical delays on the project, to
identify causes of and assess responsibility for those delays, and to establish a basis for a
damages award of more than $1.5 million resulting from those delays. Id. at 2-22. At the
hearing, Alares presented Mr. Maggioli and, over the VA’s objection, asked that, pursuant
to Rule 702 of the Federal Rules of Evidence (FRE), he be qualified as an expert in
construction scheduling and delay analysis. As part of its objection, the VA noted that,
although Alares did not mention it in its request to qualify him as an expert, Mr. Maggioli
purported to provide extensive damages analyses in his report as part of his critical path delay
opinions. Hearing Transcript, Vol. 1, at 40. After providing Alares an opportunity to
establish Mr. Maggioli’s background and areas of expertise, Judge Drummond declined to
qualify Mr. Maggioli as an expert witness. Id. at 39-42. Nevertheless, Judge Drummond,
without objection by the VA, allowed Mr. Maggioli to present his analysis as lay opinion
testimony under FRE 701. Id.
The panel agrees with Judge Drummond’s determination that Alares did not establish
Mr. Maggioli’s qualifications to testify as an expert under FRE 702. Only “[a] witness who
is qualified as an expert by knowledge, skill, experience, training, or education may testify
in the form of an opinion or otherwise” as an expert at a hearing. FRE 702. The proponent
of expert testimony bears the burden of establishing by a preponderance of the evidence that
the proposed witness qualifies as a expert. Sykes v. Napolitano, No. 07-42, 2009 WL
10696622, at *1 (D.D.C. Aug. 21, 2009); Chung v. World Corp., No. CV-04-0001, 2005 WL
8155795, at *2 (D.N. Mar. Is. Oct. 24, 2005). “Whether a witness is qualified as an expert
can only be determined by comparing the area in which the witness has superior knowledge,
skill, experience, or education with the subject matter of the witness’s testimony.” Carroll
v. Otis Elevator Co., 896 F.2d 210, 212 (7th Cir. 1990).
At the hearing, Alares’ basis for presenting Mr. Maggioli as an expert in scheduling
and delay analysis was his status as a professional engineer, Hearing Transcript, Vol. 1, at 25,
and “his 35 years of preparing schedules for projects, updating schedules for projects, and
. . . advising the VA on scheduling.” Id. at 39. Although Judge Drummond recognized that
CBCA 6149, 7071, 7597
55
Mr. Maggioli might have extensive experience in forward-looking construction project
scheduling, id. at 39-40, the report that Mr. Maggioli prepared did not involve forwardlooking scheduling but instead purported to reconstruct prior project timelines, assess past
time impacts, assign responsibility for delays on the completed project through what
Mr. Maggioli described as a critical path analysis, and quantify more than $1.5 million in
alleged damages. See Exhibit 3644 at 2-22. Mr. Maggioli had never previously prepared a
schedule delay analysis report, Hearing Transcript, Vol. 1, at 42, and Alares presented no
evidence that Mr. Maggioli had ever previously conducted a critical path delay analysis or
damages quantification. In such circumstances, Judge Drummond properly found that Alares
did not meet its burden of establishing Mr. Maggioli’s qualifications to testify as an expert
under FRE 702 on scheduling, delay, and damages analysis. See The Sherman R. Smoot Co.,
ASBCA 52261, 03-1 BCA ¶ 32,197, at 159,151 (excluding testimony of proposed expert in
construction CPM schedule analysis for lack of qualifications).
Ultimately, however, Alares suffered no prejudice from that ruling. Despite the lack
of evidence supporting Mr. Maggioli’s expertise in delay and damages analysis, Judge
Drummond, without objection by the VA (Hearing Transcript, Vol. 1, at 41-42), allowed
Mr. Maggioli to present his analysis as lay opinion testimony, eliminating any possible
prejudice to Alares from his exclusion as a FRE 702 expert witness, and the entirety of his
report was included in the Rule 4 appeal file. FRE 701 provides that, “[i]f a witness is not
testifying as an expert, testimony in the form of an opinion is limited to one that is:
(a) rationally based on the witness’s perception; (b) helpful to clearly understanding the
witness’s testimony or to determining a fact in issue; and (c) not based on scientific,
technical, or other specialized knowledge within the scope of Rule 702.” To the extent that
Mr. Maggioli’s testimony went beyond that which a lay opinion witness might ordinarily be
allowed to provide,20 the VA represented at the hearing that it had “no objection to him
testifying as a fact witness based on his personal experience on this project,” Hearing
Transcript, Vol. 1, at 41, and it did not otherwise object at any time during the hearing to any
of the testimony that he provided about his schedule delay analysis report. In such
circumstances, the VA waived any objection to the Board’s acceptance of his testimony.
Fruin-Colnon Corp. v. United States, 912 F.2d 1426, 1429 (Fed. Cir. 1990); see Constant v.
20
The type of critical path schedule analysis that Mr. Maggioli purported to
provide, inclusive of a quantification of damages based on that analysis, typically would be
viewed as “based upon ‘scientific, technical or other specialized knowledge’ and therefore
[would] fall outside the ambit of Federal Rule of Evidence (FRE) 701.” Regency
Construction, Inc. v. Department of Agriculture, CBCA 3246, et al., 17-1 BCA ¶ 36,884, at
179,774 (2016).
CBCA 6149, 7071, 7597
56
Advanced Micro-Devices, Inc., 848 F.2d 1560, 1566 (Fed. Cir. 1988) (“Failure to object in
a timely fashion constitutes a waiver.”).
D.
Alares’ Request for an Adverse Inference
Although the VA indicated on its witness list that Karla Rotondo, the contracting
officer for this project, would testify at the hearing, and although Ms. Rotondo attended the
hearing, the VA ultimately did not have her testify.21 Focusing on its implied duty of good
faith and fair dealing breach claim, Alares asks that we draw an adverse inference against the
VA and find that, had Ms. Rotondo testified, her testimony on issues such as the VA’s
funding limitations, the VA’s motives in issuing show cause and cure notices, the VA’s
recognition of delay caused by defective designs, and the VA’s ultimate breach of the duty
of good faith and fair dealing would not have been helpful to the VA. Appellant’s
Post-Hearing Brief (June 16, 2023) at 37. The VA responds that, in light of the documentary
evidence in the record and the fact that Peter Boyle, the COR, testified, Ms. Rotondo’s
testimony was unnecessary and would have been duplicative of Mr. Boyle’s, making an
adverse inference unwarranted. Respondent’s Post-Hearing Reply Brief (Sept. 14, 2023) at
12-13.
“When it would be natural under the circumstances for a party to call a particular
witness . . . and the party fails to do so, tradition has allowed the adversary to use this failure
as the basis for invoking an adverse inference.” 2 Kenneth S. Broun, McCormick on
Evidence § 264, at 220 (6th ed. 2006); see Graves v. United States, 150 U.S. 118, 121 (1893)
(“[I]f a party has it peculiarly within his power to produce witnesses whose testimony would
elucidate the transaction, the fact that he does not do it creates the presumption that the
testimony, if produced, would be unfavorable.”). Yet, “a party’s failure to call a witness does
not necessarily imply that the witness’s testimony would have been unfavorable to that
party.” United States v. Busic, 587 F.2d 577, 586 (3d Cir. 1978), rev’d on other grounds, 446
U.S. 398 (1980). “Every experienced trial lawyer knows that the decision to call a witness
often turns on factors which have little to do with the actual content of his [or her]
testimony.” Id. The adverse inference is potentially available only if the missing witness
“could have given material non-cumulative evidence.” LaMarca v. United States, 31 F.
Supp. 2d 110, 128 (E.D.N.Y. 1998). “If the testimony of the witness would be merely
cumulative, the inference is unavailable.” 2 Kenneth S. Broun, supra, § 264, at 222. Further,
even when all of the elements supporting an adverse inference are met, the tribunal may
21
Alares also listed Ms. Rotondo on its own witness list but then elected not to
call her to testify. See Appellant’s Witness List (Feb. 13, 2023) at 2; Closing Argument
Transcript at 69-70.
CBCA 6149, 7071, 7597
57
“exercise [its] discretion and decide not to grant a request for an adverse inference.”
BancorpSouth Bank v. Herter, 643 F. Supp. 2d 1041, 1061 (W.D. Tenn. 2009) (quoting
Kounelis v. Sherrer, 529 F. Supp. 2d 503, 521 (D.N.J. 2008)).
We deny Alares’ request for an adverse inference for several reasons:
First, “the availability of modern discovery and other disclosure procedures serves to
diminish both [the] justification [of an adverse inference] and the need for the inference.”
2 Kenneth S. Broun, supra, § 264, at 223. Other tribunals have held that “the fact that [the
party seeking an adverse inference] had [the missing witness’s] testimony available in
deposition form” weighs heavily against allowing an adverse inference against an employer
who did not call the witness to testify. Labit v. Santa Fe Marine, Inc., 526 F.2d 961, 962-63
(5th Cir. 1976). During the discovery period, Alares deposed Ms. Rotondo. Closing
Argument Transcript at 68-69; Respondent’s Response to Board’s Order (Jan. 20, 2025) at 1.
Although Alares included deposition transcripts from two VA witnesses in its appeal file
supplements, see Exhibits 4309, 4310, 4311, it did not submit Ms. Rotondo’s. We can only
presume from Alares’ decision not to introduce the deposition transcript that it does not
contain the types of admissions that Alares would have us now infer. See Bent Glass Design,
Inc. v. Brandt Manufacturing Systems, Inc., Civ. No. 89-4748, 1991 WL 60595, at *4 (E.D.
Pa. Apr. 10, 1991) (“[P]laintiff had the opportunity to introduce all or part of the [missing
witness’s] deposition and having declined to do so, dispelled any possible inference that [the
witness’s] testimony would have been adverse to defendant’s interest.”).
Second, the VA presented the live testimony of the COR and project manager,
Mr. Boyle, see Hearing Transcript, Vol. 3, at 9-10, and there is nothing in the record to
suggest that Ms. Rotondo’s testimony would be anything but duplicative of, yet potentially
less fulsome than, Mr. Boyle’s. Mr. Boyle testified that he and Scott DaRosa, another COR
on the project, took the lead in much if not most of the cost estimating for change orders, id.
at 11, and he would likely have had more routine contact with Alares and contemporaneous
insight into on-site work, see id. at 33-34, and the VA’s internal evaluations than the
contracting officer, who would have been located somewhere other than the job site. Alares
offers nothing to suggest that Ms. Rotondo disagreed with Mr. Boyle, and neither
Mr. Boyle’s testimony nor the documentary record in this case suggests it. To the contrary,
counsel for Alares represented during closing arguments that, during her deposition,
Ms. Rotondo repeatedly indicated that she did not remember the specifics of this project.
Closing Argument Transcript at 69-70. Because “the documentary evidence amply explains
the parties’ intents and there is no reason to believe that [the missing witness’s] testimony
would be materially any different than [Mr. Boyle’s,] [t]he government’s failure to call a
witness that the appellant believes would be helpful to appellant’s case, without more, does
not justify an adverse inference.” Aegis Defense Services, LLC, ASBCA 59082, et al., 17-1
CBCA 6149, 7071, 7597
58
BCA ¶ 36,915, at 179,859 n.10; see Del E. Webb Corp., ASBCA 22386, 79-2 BCA ¶ 14,140,
at 69,597 (“The contracting officer’s final decision is part of the record of this appeal. It
speaks for itself. No good purpose would have been served by calling the contracting officer
to testify as to what [is] already in the record.”), aff’d, 652 F.2d 69 (Ct. Cl. 1981).
Third, Alares listed Ms. Rotondo on its own witness list. Ms. Rotondo was available
at the hearing, and Alares could have called her to testify. It chose not to do so. We see no
basis for an adverse inference when Alares decided not to call a witness from its own list.
Fourth, because “[f]ailure to anticipate that the inference may be invoked entails
substantial possibilities of surprise, . . . courts often require early notice from a party
expecting to make a missing witness argument or intending to request [an adverse inference]
instruction.” 2 Kenneth S. Broun, supra, § 264, at 223 (citing cases). Nothing in the record
suggests that, prior to filing its post-hearing brief, Alares ever informed the VA that it viewed
the VA’s failure to call Ms. Rotondo to testify as something warranting an adverse inference
This text is long and has been trimmed here. Open the source document for the complete record.
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.