MOTIONS TO DISMISS DENIED: February 14, 2017
Agency decision
Ask Donna
What actually matters in this document.
Text
MOTIONS TO DISMISS DENIED: February 14, 2017
CBCA 5323
H.C. BECK, LTD.,
Appellant,
v.
GENERAL SERVICES ADMINISTRATION,
Respondent.
Timothy D. Matheny of Peckar & Abramson, P.C., Dallas, TX, counsel for Appellant.
John S. Tobey and Catherine Crow, Office of General Counsel, General Services
Administration, Washington, DC, counsel for Respondent.
Before Board Judges DANIELS (Chairman), DRUMMOND, and LESTER.
DANIELS, Board Judge.
The General Services Administration (GSA), respondent, moves to dismiss – for
failure to state a claim for which relief may be granted, and alternatively for lack of
jurisdiction – an appeal filed by H.C. Beck, Ltd. (Beck). We deny the motions.
Background
On July 24, 2009, GSA awarded to Beck a contract for the renovation of the San
Antonio Hipolito Garcia United States Post Office and Courthouse in San Antonio, Texas.
The contract was awarded at a firm fixed price of $34,040,575.
CBCA 5323
2
The project documents included information indicating the presence of a small
quantity of asbestos containing materials (ACM) in the building and required Beck to remove
those materials. As the contractor proceeded to perform its work, it identified significantly
more ACM than was shown in the project documents. To compensate Beck for additional
work required to remove this material, GSA agreed to sixty-three contract modifications,
with a total value of $16,672,848, thereby increasing the contract value to $50,713,423.
Beck completed the project by the required project completion date of March 28, 2012.1
1
Each of the modifications includes a statement regarding accord and
satisfaction. For example, modifications PS02, 03, 04, 05, 06, 08, 19, 20, and 23 include the
statement:
Acceptance of this modification by the contractor constitutes an accord and
satisfaction and represents payment in full for both time and money for any
and all costs, impact effect, and for delays and disruptions arising out of, or
incidental to, the work as herein revised.
Modifications PS21, 22, and 39 include:
Acceptance of this modification by the contractor constitutes an accord and
satisfaction and represents payment in full for money for any and all costs,
impact effect, and for delays and disruptions arising out of, or incidental to, the
work as herein revised.
Modifications PS24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 38, 42, 43, and 47 include:
CONTRACTOR[’]S STATEMENT OF RELEASE:
In consideration of the modification agreed to herein as complete equitable
adjustment, the contractor hereby releases the Government from any and all
liability under this contract for further equitable adjustments attributable to
such facts or circumstances giving rise to this modification. Acceptance of
this modification by the contractor constitutes an accord and satisfaction and
represents payment in full for both time and money for any and all costs,
impact effect, and for delays and disruptions arising out of, or incidental to, the
work as herein revised.
The Board directed the parties to address in further briefing whether these statements
in the contract modifications preclude recovery by the contractor on the claims at issue in the
(continued...)
CBCA 5323
3
By letter dated April 19, 2012, Beck submitted to the contracting officer a request for
equitable adjustment (REA) of the contract price in the amount of $2,271,073. In this letter,
Beck asserted:
As a direct result of the differing site conditions encountered, Beck was
required to engage in work beyond what was originally contemplated in the
Statement of Work (“SOW”) in the performance of the following tasks:
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Performing ACM assessments, reports, and recommendations for
abatement/remediation;
Confirming the accuracy of GSA’s licensed asbestos consultant’s (GEO
[International Management, LLC]) clearance and monitoring reports;
Maintaining, testing, and reporting air quality through the building;
Cleanup of the ACM’s in the disturbed second floor area;
Additional management, safety supervision, and scheduling due [to] the
increased scope of ACM abatement, remediation, and work stoppage;
Additional management and insurance costs due to the work stoppage;
Demobilization/remobilization activities due to the work stoppage;
Additional equipment storage, rescheduling, and relocation due to the
work stoppage and additional abatement; and
Providing temporary HVAC [heating, ventilation, and air conditioning]
for an extended duration due to the work stoppage and additional ACM
abatement.
Engage legal counsel to assist in dealing with the differing site
conditions and the potential of ACM exposure, as well as, assisting
with putting together the REA for the extra work.
In its REA, Beck said that it “is seeking a REA under the provisions of FAR [Federal
Acquisition Regulation] 52.235-1 – Differing Site Conditions and GSAR [General Services
1
(...continued)
case. In response, Beck maintains, with supporting affidavits and other documents, that at
least beginning with modification PS21, the modifications released only claims for the direct
costs of the asbestos removal itself; the modifications reserved to the contractor future claims
for ancillary costs. GSA says that it has concluded “that more evidence is necessary to
determine whether the statements in the specified contract modifications preclude recovery
entirely and GSA’s defense of accord and satisfaction is not amenable to disposition by
dismissal at this time.” Accordingly, we do not consider in this decision whether the quoted
portions of the modifications preclude recovery.
CBCA 5323
4
Acquisition Regulation] 552.243-71 – Request for Equitable Adjustments.” The contract
contains clauses entitled “FAR 52.236-2 – DIFFERING SITE CONDITIONS (APR 1984)”
and “GSAR 552.243-71 – EQUITABLE ADJUSTMENTS (APR 1984),” which the parties
agree are the ones Beck referenced (or meant to reference). In pertinent part, these
provisions read as follows:
FAR 52.236-2 – DIFFERING SITE CONDITIONS (APR 1984)
(a)
The Contractor shall promptly, and before the conditions are
disturbed, give a written notice to the Contracting Officer of (1) subsurface or
latent physical conditions at the site which differ materially from those
indicated in this contract . . . .
(b)
The Contracting Officer shall investigate the site conditions
promptly after receiving the notice. If the conditions do materially so differ
and cause an increase or decrease in the contractor’s cost of, or the time
required for, performing any part of the work under this contract, whether or
not changed as a result of the conditions, an equitable adjustment shall be
made under this clause and the contract modified in writing accordingly.
GSAR 552.243-71 – EQUITABLE ADJUSTMENTS (APR 1984)
(a)
The provisions of the “Changes” clause prescribed by FAR
52.243-4 are supplemented as follows:
(1)
Upon written request, the contractor shall submit a
proposal, in accordance with the requirements and limitations set forth in the
“Equitable Adjustments” clause, for work involving contemplated changes
covered by the request. . . .
....
(b)
The provisions of the “Differing Site Conditions” clause
prescribed by FAR 52.236-2 are supplemented as follows: The Contractor
shall submit all claims for equitable adjustment in accordance with, and
subject to the requirements and limitations set out in paragraph (a) of this
“Equitable Adjustments” clause.
By letter dated November 22, 2013 (received on November 25, 2013), Beck converted
this REA into a certified claim. GSA believed that the certification was deficient, and Beck
CBCA 5323
5
resubmitted the claim by letter dated January 8, 2014 (received on January 9). Beck
withdrew from settlement discussions and amended its claim to be in the amount of
$1,170,429 on August 31, 2015. By letter dated February 10, 2016, the contracting officer
denied the claim in its entirety. Beck appealed the contracting officer’s decision to the Board
on May 10, 2016.
Discussion
Motion to Dismiss for Failure to State a Claim
When considering a motion to dismiss for failure to state a claim upon which relief
can be granted, we “must accept as true the complaint’s undisputed factual allegations and
should construe them in a light most favorable to the plaintiff.” Cambridge v. United States,
558 F.3d 1331, 1335 (Fed. Cir. 2009) (citing Papasan v. Allain, 478 U.S. 265, 283 (1986)).
Even viewed in this advantageous light, however, the complaint “must plead factual
allegations that support a facially ‘plausible’ claim to relief in order to avoid dismissal.” Id.
(citing Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 557 (2007)). “A claim has facial
plausibility when the plaintiff pleads factual content that allows the [tribunal] to draw the
reasonable inference that the defendant is liable for the misconduct alleged. . . . The
plausibility standard is not akin to a ‘probability requirement,’ but it asks for more than a
sheer possibility that a defendant has acted unlawfully.” Ashcroft v. Iqbal, 556 U.S. 662, 678
(2009) (citing Twombly, 550 U.S. at 557). See Strawberry Hill, LLC v. General Services
Administration, CBCA 5149, 16-1 BCA ¶ 36,561, at 178,061.
GSA reasons as follows in urging us to dismiss this appeal for failure to state a claim
upon which relief may be granted: Beck seeks recovery under the contract’s Differing Site
Conditions clause. This clause “appl[ies] only to conditions existing when the contract was
executed.” Olympus Corp. v. United States, 98 F.3d 1314, 1318 (Fed. Cir. 1996). Beck’s
claim, however, pertains to ACM disturbances which occurred after the parties entered into
the contract. Therefore, “it is impossible for Beck to establish required elements for a claim
under this clause.” Furthermore, if Beck had submitted its claim under the contract’s
Changes or Suspension of Work clauses,2 the Board would have to consider a different set
2
FAR 52.243-4 – CHANGES (JUN 2007) provides, in part, that:
(a)
The Contracting Officer may, at any time, without notice to the
sureties, if any, by written order designated or indicated to be a change order,
make changes in the work within the general scope of the contract, including
(continued...)
CBCA 5323
6
of operative facts, so that would be a different claim from the one which was submitted to
the contracting officer. Finally, even if the claim could be considered under the Differing
Site Conditions clause, Beck cannot meet some of the “indispensable elements” of such a
claim set forth in Weeks Dredging & Contracting, Inc. v. United States, 13 Cl. Ct. 193, 218
(1987) – in particular, the contractor cannot prove that it reasonably relied on the indications
2
(...continued)
changes –
(1)
(2)
(3)
(4)
In the specifications (including drawings and designs);
In the method or manner of performance of the work;
In the Government-furnished property or services; or
Directing acceleration in the performance of the work.
***
(d)
If any change under this clause causes an increase or decrease
in the contractor’s cost of, or the time required for, the performance of any part
of the work under this contract, whether or not changed by any such order, the
Contracting Officer shall make an equitable adjustment and modify the
contract in writing.
FAR 52.242-14 – SUSPENSION OF WORK (APR 1984) provides, in part,
that:
(b)
If the performance of all or any part of the work is, for an
unreasonable period of time, suspended, delayed, or interrupted (1) by an act
of the Contracting Officer in the administration of this contract, or (2) by the
Contracting Officer’s failure to act within the time specified in this contract (or
within a reasonable time if not specified), an adjustment shall be made for any
increase in the cost of performance of this contract (excluding profit)
necessarily caused by the unreasonable suspension, delay, or interruption, and
the contract modified in writing accordingly. However, no adjustment shall
be made under this clause for any suspension, delay, or interruption to the
extent that performance would have been so suspended, delayed, or interrupted
by any other cause, including the fault or negligence of the Contractor, or for
which an equitable adjustment is provided for or excluded under any other
term or condition of this contract.
CBCA 5323
7
of subsurface conditions in the contract when preparing its bid, or that the claimed excess
costs were solely attributable to the materially different subsurface conditions.
These arguments are not convincing. The parties modified the contract to increase its
price by nearly fifty percent to compensate Beck for removing far greater amounts of ACM
than expected (more than thirty-one times as much as expected, according to Beck). This
demonstrates plainly that the subsurface conditions when the contract was executed were far
different from those which were actually encountered. Frank Lill & Son, Inc., ASBCA
35774, 88-3 BCA ¶ 20,880, at 105,584 (in appropriate circumstances, the unanticipated
discovery of ACM can constitute a differing site condition). Furthermore, Beck did not
submit its claim solely under the Differing Site Conditions clause of the contract; it
implicated also the Equitable Adjustments clause. GSA does not explain why we would have
to consider different operative facts if Beck had submitted its claim under the Changes clause
(which is supplemented by the Equitable Adjustments clause). If the claim had been founded
on the Suspension of Work clause, the only difference in consideration noted by the agency
is that we would have to review one less issue – the contractor’s profit on awarded costs. In
any event, merely asserting a different legal theory for recovery, based on the same operative
facts, does not change the nature of the claim. Scott Timber Co. v. United States, 333 F.3d
1358, 1365-66 (Fed. Cir. 2003); CB&I AREVA MOX Services, LLC v. Department of Energy,
CBCA 5395, 17-1 BCA ¶ 36,591, at 178,217 (2016); Sage Western Investments v. General
Services Administration, CBCA 1680, 09-2 BCA ¶ 34,297, at 169,418; but see K-Con
Building Systems, Inc. v. United States, 778 F.3d 1000, 1006 (Fed. Cir. 2015) (“presenting
a materially different . . . legal theory . . . does create a different claim” (emphasis added)).
Whatever the underlying clause, it is clear that Beck believes that the claimed costs
were all incurred because the project involved far more ACM than anyone expected. Whether
the claimed excess costs were solely attributable to the materially different subsurface
conditions is something Beck will have to prove to prevail on the merits, but at this stage of
the proceedings, it has presented sufficient factual allegations to survive a motion to dismiss
for failure to state a claim upon which relief may be granted. Those allegations support a
facially plausible claim – they allow us to draw the reasonable inference that GSA is liable
for the costs asserted. Strawberry Hill, LLC v. General Services Administration, CBCA
5149, 16-1 BCA ¶ 36,561, at 178,061 (citing Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009);
Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 556 (2007)).
Motion to Dismiss for Lack of Jurisdiction
A tribunal would normally consider a motion to dismiss for lack of jurisdiction before
any other motion, for if the tribunal does not have jurisdiction, it cannot proceed to other
matters placed before it. Steel Co. v. Citizens for a Better Environment, 523 U.S. 83, 94-95,
CBCA 5323
8
101-02 (1998). In this case, though, GSA has made its jurisdictional motion subordinate to
its other motion – and with good reason, for the agency’s arguments as to jurisdiction are
nothing more than a rehash of the arguments it made in far greater detail in pursuing
dismissal for failure to state a claim. The arguments fare no better in this iteration.
GSA summarizes the justification for its jurisdictional motion in the following
paragraph:
The basis for dismissal for lack of jurisdiction is that the services and work for
which Beck seeks to recover in this Appeal are only recoverable upon the
submission of claims under FAR 52.243-4 Changes and/or FAR 52.242-14 Suspension of Work[]. Here, Beck has not presented a claim under these
clauses to the Contracting Officer for a Final Decision. In turn, there has been
no appeal of a Final Decision for claims under the Changes Clause or the
Suspension of Work Clause. As such, the Board lacks jurisdiction over Beck’s
claim to $1,170,429.00 and must dismiss.
Beck says that GSA’s arguments “are simply nonsensical.” We hesitate to use such
pejorative language in evaluating a party’s position, but here, we must agree with the
appellant’s characterization. The Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (2012),
under which we consider this case, contains specific requirements regarding the jurisdiction
of a board of contract appeals. To place a matter before a contracting officer, a contractor
must submit a claim to such an officer for decision; the claim must be in writing; and, if it
is for more than $100,000 (as this one is), it must contain a specified certification. Id.
§ 7103(a)(1), (2), (b). After receiving a claim from a contractor, a contracting officer is to
issue a decision in writing. Id. § 7103(d). The contractor may appeal the decision to the
appropriate board within ninety days from the date of receipt. Id. § 7104(a). “The Civilian
Board [of Contract Appeals] has jurisdiction to decide any appeal from a decision of a
contracting officer of any executive agency (other than [named agencies of which GSA is not
one]) relative to a contract made by that agency.” Id. § 7105(e)(1)(B). All the required
events transpired with regard to this matter, and Beck appealed the contracting officer’s
decision to us within ninety days of the date on which it received the decision. That is all that
is necessary for us to have jurisdiction over the case.
CBCA 5323
9
Decision
GSA’s MOTIONS TO DISMISS for failure to state a claim upon which relief may
be granted and for lack of jurisdiction are both DENIED.
_________________________
STEPHEN M. DANIELS
Board Judge
We concur:
_________________________
JEROME M. DRUMMOND
Board Judge
_________________________
HAROLD D. LESTER, JR.
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.