In the Matter of HOUSING AUTHORITY OF THE CITY OF LUMBERTON,

Agency decision

Ask Donna

What actually matters in this document.

Text

February 20, 2024

CBCA 7904-FEMA

In the Matter of HOUSING AUTHORITY OF THE CITY OF LUMBERTON,

NORTH CAROLINA

Danielle M. Aymond of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,

Baton Rouge, LA, counsel for Applicant.

Will Polk and Pamela M. Thombs, Office of the General Counsel, North Carolina

Department of Public Safety, Raleigh, NC, counsel for Grantee.

Shahnam Thompson and Rebecca J. Otey, Office of Chief Counsel, Federal

Emergency Management Agency, Department of Homeland Security, Washington, DC,

counsel for Federal Emergency Management Agency.

Before the Arbitration Panel consisting of Board Judges BEARDSLEY (Chair),

SULLIVAN, and KANG.

KANG, Board Judge, writing for the Panel.

Applicant, the Housing Authority of the City of Lumberton, North Carolina (HACL),

sought arbitration under 42 U.S.C. § 5189a(d) (2018) of a dispute with the Federal

Emergency Management Agency (FEMA) as to eligibility for public assistance (PA) funding

in connection with Hurricane Matthew. FEMA previously granted part of HACL’s request

for PA funding to repair thirty-three buildings, comprising sixty-eight housing units, but

denied applicant’s request to fully replace them. We find the buildings are not eligible for

replacement.

CBCA 7904-FEMA

2

Background

HACL owns and operates the Lumbee Homes Public Housing Community (Lumbee

Homes) in Robeson County, North Carolina. The buildings at issue here include standalone

and duplex one-, two-, three-, and four-bedroom units. In October 2016, Hurricane Matthew

struck the eastern coast of the United States, including Robeson County. The Lumbee

Homes buildings experienced flooding from the storm’s rainwater, followed by additional

flooding from a levee failure. On October 10, 2016, the President issued a major disaster

declaration (FEMA-4285-DR-NC) for Hurricane Matthew.

In December 2016, FEMA approved emergency work for repairs to certain Lumbee

Homes buildings, including asbestos testing and remediation, which was conducted from

February through August 2017. In July 2017, FEMA prepared permanent work project

worksheets (PWs) for repairs at Lumbee homes: PW 1368, which had an initial project cost

of $524,743, and PW 1370, which had an initial project cost of $515,242.

In June 2019, Anderson Consulting, a consultant retained by HACL, prepared an

estimate of repair and replacement costs.1 Based on this estimate, applicant requested that

FEMA add repair costs to PWs 1368 and 1370 and find the buildings eligible for replacement

because the added costs increased the overall value of the repairs to more than fifty percent

of the estimated costs of replacement. In July and August 2020, Anderson Consulting

provided FEMA itemized estimates for the repair of the buildings. In late August 2020,

FEMA issued amendments to PWs 1368 and 1370 based on the Anderson Consulting

estimates. These PW amendments found that the eligible repair costs were more than fifty

percent of the estimated costs of replacement.

In February 2022, FEMA issued determination memorandums (DMs) for PWs 1368

and 1370 that denied the majority of the repair costs requested by applicant. The DMs found

that some of the costs in the Anderson Consulting estimates were duplicative of costs

approved for the emergency work and that other costs were either not eligible or

unsupported. Based on FEMA’s revised costs in the DMs, FEMA found that the eligible

repair costs were less than fifty percent of applicant’s estimated costs of replacement and

were therefore not eligible for replacement.

Applicant filed first-level appeals of the DMs in April 2022 and June 2022, seeking

increased repair costs that HACL contended justified full replacement of the buildings.

FEMA’s August 2023 decision on the first-level appeals adjusted certain of applicant’s

1

Applicant does not state when Anderson Consulting inspected the Lumbee

Homes buildings for this report, but FEMA states that this occurred in June 2019.

CBCA 7904-FEMA

3

requested repair costs, concluding that some had been improperly excluded or found not

eligible, while others had been improperly found eligible. Relevant here, the costs that

FEMA found eligible included replacement of heating, ventilation, and air conditioning

(HVAC) systems, replacement of exterior wall insulation, and replacement and repair of

parts of the flooring.

Overall, FEMA found applicant eligible for $1,726,309 in repair costs under PW 1368

and $850,843 in repair costs under PW 1370. Because the eligible repair costs were less than

fifty percent of applicant’s estimated replacement values of the buildings ($8,591,270 for PW

1368 and $9,813,993 for PW 1370), FEMA found that the buildings were still not eligible

for replacement.

Applicant requested arbitration on October 2, 2023. The parties elected to conduct

the arbitration on the basis of the record submitted to the panel.

Discussion

The Robert T. Stafford Disaster Relief and Emergency Assistance Act (Stafford Act),

42 U.S.C. §§ 5121-5207 (2018), provides the statutory authority for FEMA’s federal disaster

response activities. Congress enacted the Stafford Act to provide “assistance by the Federal

Government to State and local governments in carrying out their responsibilities to alleviate

the suffering and damage which result from [major] disasters.” 42 U.S.C. § 5121(b). The

Stafford Act is “designed to assist the efforts of [states affected by major disasters] in

expediting the rendering of aid, assistance, and emergency services, and the reconstruction

and rehabilitation of devastated areas.” Id. § 5121(a).

An applicant has the burden to demonstrate that damage was directly caused by a

declared disaster. FEMA’s Public Assistance Program and Policy Guide (PAPPG)

(Jan. 2016) at 9, 19.2 To be eligible, costs must be directly tied to the performance of eligible

work and adequately documented. Id. at 21. Moreover, PA funding is intended to restore

damaged facilities to their prior function in accordance with applicable codes and standards,

and an applicant must demonstrate that the repair costs are for damage directly caused by the

disaster rather than by pre-existing damage or by a failure to reasonably mitigate damages.

Id. at 19, 81-82.

When evaluating whether a damaged facility is eligible for replacement, rather than

repair, “FEMA compares the repair cost with the replacement cost and evaluates the

2

The January 2016 PAPPG applies to declared disasters from January 1, 2016,

through March 31, 2017.

CBCA 7904-FEMA

4

feasibility of repairing the facility.” PAPPG at 96. “A facility is considered repairable when

disaster damages do not exceed 50 percent of the cost of replacing a facility to its predisaster

condition, and it is feasible to repair the facility so that it can perform the function for which

it was being used as well as it did immediately prior to the disaster.” 44 CFR 206.226(f)(1)

(2016).

Applicant seeks replacement of thirty-three buildings, comprising sixty-eight housing

units, at Lumbee Homes. HACL’s request for arbitration (RFA) initially asked “only [that]

the Panel determine whether or not the units are eligible for replacement.” RFA at 2.

Applicant raises two primary arguments in support of its position that the costs to repair the

buildings exceed fifty percent of the costs of replacing them. First, applicant contends that

the panel should accept the estimates prepared by HACL’s consultant that were presented

in the first appeal and that the estimates reflect repair costs in excess of fifty percent of the

costs of replacement.3 Second, in the event the panel does not accept the consultant’s

original estimates, applicant submits new estimates that identify three additional categories

of costs that were not raised in connection with the first appeal and that increase the repair

costs for the buildings above the fifty-percent threshold.

Notwithstanding the limited scope of the request set forth in the RFA, applicant’s

reply to FEMA’s response added new alternative requests in the event the panel does not find

the buildings eligible for replacement. These alternative requests ask that we either direct

FEMA to work with applicant to conduct a more detailed inspection of the buildings and

develop mutually-agreeable repair costs or remand the matter of repair costs for

reconsideration by FEMA. We therefore address applicant’s primary arguments in support

of its position that the costs to repair the buildings exceed fifty percent of the costs of

replacing them as well as applicant’s new alternative requests.

I.

Estimates from Applicant’s Consultant

Applicant argues that FEMA is obligated under its policies to accept as dispositive the

cost estimates prepared by HACL’s consultant, Anderson Consulting. Applicant contends

3

Applicant also contends that FEMA improperly reversed the findings in its

August 2020 amendments to PW 1368 and 1370, which found eligibility for repair costs in

excess of fifty percent of the estimated replacement costs. FEMA is not prohibited from

reconsidering or changing an initial determination, and an applicant cannot demonstrate

eligibility for PA funding based solely on the fact that FEMA had initially made a more

favorable finding. See Montgomery County Secondary Roads, CBCA 7480-FEMA, 22-1

BCA ¶ 38,230, at 185,659-60.

CBCA 7904-FEMA

5

that these estimates demonstrate that the costs of repairing the buildings exceed fifty percent

of the costs of replacement. We find no merit to these arguments.

The PAPPG states that FEMA will use an applicant’s cost estimate to determine PA

eligibility where it:

•

Is prepared by a licensed Professional Engineer or other estimating

professional, such as a licensed architect or certified professional cost

estimator who certifies that the estimate was prepared in accordance

with industry standards;

•

Includes certification that the estimated cost directly corresponds to the

repair of the agreed upon damage;

•

Is based on unit costs for each component of the SOW and not a lump

sum amount;

•

Contains a level of detail sufficient for FEMA to validate that all

components correspond with the agreed-upon SOW; and

•

Is reasonable.

PAPPG at 132.

To the extent applicant contends that the mere submission of certified estimates by

a licensed professional establishes cost eligibility, we disagree, as the adequacy of an

estimate’s details and its overall reasonableness must be considered.

FEMA does not dispute that the Anderson Consulting estimates were prepared by a

licensed professional engineer. FEMA argues, however, that the estimates do not contain

adequate detail, are not reasonable, and do not establish eligibility of repair costs that exceed

the fifty-percent threshold. FEMA notes that the estimates were based on inspections that

took place more than three years after Hurricane Matthew. Based on the passage of time,

FEMA contends that applicant cannot demonstrate that Hurricane Matthew was the direct

cause of the damage to the buildings, as opposed to delays in remediating the damage from

that storm or intervening events such as the flooding experienced in the buildings caused by

Hurricane Florence in September 2018.4

4

We do not agree with FEMA’s assertion that an assessment conducted three

years after a disaster is “blanketly unreliable.” FEMA Response at 13. However, we agree

CBCA 7904-FEMA

6

The 2019 and 2020 Anderson Consulting estimates consist solely of costs and do not

directly address why the claimed damages were eligible for reimbursement. Applicant

submitted an affidavit from Larry Anderson, president of Anderson Consulting, to support

the estimates, but the assertions therein do not adequately explain why inspections three

years later are reliable.5 In light of the passage of time and lack of adequate explanations,

the estimates do not contain details sufficient to validate that all of the repair costs are within

the scope of work or are otherwise reasonable. In sum, applicant does not establish that

FEMA policy requires deference to the estimates prepared by applicant’s consultant.

II.

Additional Repair Costs

We next address three categories of costs that applicant contends should be added to

the FEMA-approved repair costs: HVAC replacement, wall insulation replacement, and

flooring repair and replacement. Applicant contends that the addition of these costs increases

the repair costs above the fifty-percent threshold, thereby qualifying the buildings for

replacement. We find no merit to these arguments.

A.

HVAC Replacement Costs

FEMA granted $4554.54 to replace the HVAC systems at each of the thirty-three

affected buildings. FEMA’s Exhibit 26, Declaration of Jack Marlowe (Nov. 16, 2023) ¶ 18;

Applicant’s Exhibit 1, First Appeal Decision Analysis at 15; Cost Estimating Formula Sheets

(CEFs) at 1-78. This amount consists of $2777.16 for a condenser, evaporator, air handler,

and ductwork, plus $1777.38 for soft costs. Id. Applicant contends, based on the opinion

of Anderson Consulting and cost survey data, that the costs of replacing the HVAC systems

that the passage of time generally increases the burden on an applicant to demonstrate that

the claimed damage was directly caused by the disaster and not by alternative causes. See

City of Hattiesburg, Mississippi, CBCA 7228-FEMA, 22-1 BCA ¶ 38,029, at 184,684.

5

Applicant also argues that failure to promptly assess damage is due to FEMA’s

failure to conduct inspections of the buildings, as contemplated by the PAPPG. The PAPPG

provides that, during project formulation, “FEMA and the Recipient conduct site inspections

with the Applicant to validate, quantify, and document the cause, location, and details of the

reported damage and debris impacts and identify [environmental and historic preservation

(EHP)] issues and hazard mitigation opportunities . . . .” PAPPG at 128. In June 2017,

FEMA inspected two of applicant’s buildings for damage to assess EHP issues. Even if the

inspections were not the joint inspections anticipated by the PAPPG (a matter we need not

resolve), applicant does not establish that a failure to conduct inspections requires FEMA to

accept applicant’s estimates or otherwise excuses applicant from the requirement to establish

its entitlement to PA funding.

CBCA 7904-FEMA

7

should be higher, ranging from $11,432.82 for one-bedroom duplex units to $21,137.03 for

four-bedroom duplex units.

FEMA’s first appeal decision approved full replacement of HVAC systems for the

buildings, including replacement of existing 2.5-ton capacity units.6 Applicant’s consultant

states that the approved costs are inadequate, in part, because they do not include costs for

the larger three- to four-ton units. Applicant’s Exhibit 17, Affidavit of Larry W. Anderson

(Dec. 5, 2023) ¶ 11. The PWs for the buildings all provide for 2.5-ton capacity replacement

units, stating that they are “equivalent in size” to the existing units. Applicant’s Exhibit 6

at 7. While applicant appears to argue that the buildings require units larger than 2.5 tons,

applicant does not demonstrate that the existing units had this capacity. Thus, even if

upgrades to larger units were appropriate in light of previously undersized units at Lumbee

Homes, applicant is eligible only for restoration to the prior function of the units and not for

improvements or upgrades.7 On this record, applicant does not demonstrate that it is eligible

for replacement of the larger units.8

In addition, applicant’s RFA included a chart titled “NEW HVAC SYSTEM COST,”

citing cost survey data from the Homeguide.com website.9 Applicant contends that this data

shows significantly higher costs for HVAC replacements. The data, however, does not

address the size of the HVAC systems replaced or the locality of the work. Thus, nothing

6

Confusingly, FEMA’s response to the RFA stated that only the outdoor parts

of the HVAC systems were eligible for replacement, as there was no evidence of damage to

the interior parts of the system. The same response, however, stated that the outdoor

condenser, indoor component costs were eligible as well. Moreover, the first appeal decision

stated that the buildings were eligible for HVAC replacement, and the CEFs identified costs

for both the indoor and outdoor components. Applicant’s Exhibit 1, First Appeal Decision

Analysis at 15, 23-129 CEFs at 1-78. Thus, despite applicant’s contention that FEMA only

granted costs for the interior parts of the HVAC systems, the record shows that FEMA

granted costs for the indoor and outdoor components.

7

A building is eligible for upgrades required by applicable codes and standards.

PAPPG at 81-82; City of Hattiesburg, Mississippi, CBCA 7017-FEMA, 22-1 BCA ¶ 37,986,

at 184,457-58 (2021). Applicant, however, does not contend that upgrades to the size of the

HVAC units are required based on codes or standards.

8

Applicant does not explain whether its request for larger units applies to some

or all of the buildings, leaving the panel unable to assess the reasonableness of the costs.

9

Homeguide.com describes itself as a website that provides information services

homeowners and contractors. See https://homeguide.com/about (last visited Feb. 16, 2024).

CBCA 7904-FEMA

8

about this information establishes applicant’s costs as reasonable. On this record, applicant

is not eligible for costs for HVAC replacement in excess of that granted by FEMA.

B.

Exterior Walls Insulation Replacement

FEMA approved replacement of exterior wall insulation. Applicant contends that

additional repair costs are required for the related work of removing an exterior brick wrap

to access the insulation. Applicant also contends that fiberboard sheathing between the

exterior wall and the brick wrap must be sanitized and that this sheathing can only be

accessed by removing the brick wrap.

FEMA states that the exterior wall insulation may be accessed without removal of the

exterior brick wrap, making those costs not eligible for reimbursement. FEMA’s response

included photos and detailed rebuttals of applicant’s arguments regarding the design of the

buildings and the accessibility of the insulation from the interior of the building. FEMA also

states that photos of the units show plywood sheathing that does not require sanitizing, rather

than fiberboard sheathing, as claimed by applicant.

Applicant does not meaningfully explain why the insulation is inaccessible and

requires removal of the brick sheathing. Photos provided by applicant, which are cited by

both parties, appear to show that the insulation is accessible from the inside of the building

units. Further, while applicant represents that buildings of the type at Lumbee Homes

“typically” have fiberboard sheathing that requires replacement after flooding, applicant does

not directly address FEMA’s finding that the buildings do not have damaged fiberboard

sheathing. On this record, applicant is not eligible for costs for exterior wall insulation in

excess of that granted by FEMA.

C.

Floor Repair and Replacement

The floors at the Lumbee Homes buildings consist of two layers of vinyl floor

composite (VTC) tile and mastic adhesive paste over concrete floors. The parties agree that

the lower layer of VTC tiles and mastic contains asbestos. The parties also agree that the

upper layer of VTC tiles and mastic does not contain asbestos and was installed to

encapsulate the asbestos-containing lower layer, thereby preventing the release of asbestos

fibers.

FEMA’s first appeal decision found evidence of damage to some areas of the flooring,

including places that required removal and replacement of the upper layer of VTC and places

that required removal and replacement of both layers. FEMA noted, however, that applicant

did not provide specific dimensions or quantities for damaged tiles. FEMA therefore granted

costs to replace up to twenty-five percent of the lower layer of VTC tiles and mastic,

CBCA 7904-FEMA

9

including removal and disposal of materials containing asbestos, as well as up to 100% of

the upper layer of VTC tiles.

Applicant does not specifically dispute that the asbestos in the lower layer of VTC

tiles and mastic are encapsulated by the upper layer. Applicant also does not specifically

dispute that the upper layer of VTC tiles can be replaced without disturbing the asbestos in

the lower layer of VTC tiles and mastic. Instead, applicant’s consultant states that the flood

water that entered the buildings was “black water,” or “Category 3 water,” which the

consultant characterizes as “toxic.” Anderson Affidavit ¶ 7. Based on the assumption that

the water was toxic, applicant contends that both layers of the flooring require replacement,

as well as additional remediation and monitoring to address asbestos, and that the concrete

subfloor requires decontamination.

As FEMA notes, category 3 water is “grossly contaminated” and includes “water

originating from seawater, ground water, surface water, rising rivers and streams, and winddriven rain from hurricanes and tropical storms.” FEMA’s Exhibit 30 at 9.10 Such water is

not necessarily toxic but is rather “heavily contaminated and can contain pathogens or

toxins.” Id. at 19 (emphasis added). Additionally, guidance cited by applicant, issued by

FEMA in connection with Hurricane Katrina, states that, while vinyl tiles placed over wood

floors should be removed following flooding, vinyl tiles placed over concrete floors should

be removed if damaged, i.e., curled. See FEMA’s Exhibits 31 at 2, 32 (pt. 5) at 8-18.

Applicant assumes, but does not demonstrate, that toxins requiring decontamination

are present in the flooring. Apart from its argument that toxins require replacement of both

layers of all flooring, applicant does not demonstrate that FEMA’s estimate that twenty-five

percent of the lower layer of flooring is damaged and requires replacement is incorrect. On

this record, applicant is not eligible for costs for floor replacement in excess of that granted

by FEMA.

10

FEMA’s Exhibit 30 is a document titled “Report to [the Environmental

Protection Agency (EPA)] on Guidance Documents to Safely Clean, Decontaminate, and

Reoccupy Flood-Damaged Houses,” which appears to be a report provided by consultants

to the EPA. This document cites the S500 Standard and Reference Guide for Professional

Water Damage Restoration, published by the Institute of Inspection, Cleaning, and

Restoration Certification, which categorizes water by level of contamination in categories

1 through 3.

CBCA 7904-FEMA

III.

10

Alternative Requests

As alternatives to finding that the Lumbee Homes buildings are eligible for

replacement, applicant makes two additional requests. First, applicant requests that we direct

HACL and FEMA to “work together (to include a building-by-building joint site inspection,

if necessary) to submit to the Panel a mutually agreeable final repair CEF for each of the four

representative unit types in accordance with FEMA Policy.” Applicant’s Reply to FEMA

Response at 5. As a second alternative, applicant requests that “the Panel order FEMA to

remand this matter for genuine reconsideration of the repair values.” Id. at 17. We find no

basis to grant either of these alternative requests.

The applicable regulation states that “[a]n eligible applicant may request arbitration

to dispute the eligibility for assistance or repayment of assistance.” 44 CFR 206.206(b)

(2022). The regulation does not anticipate that the panel will direct FEMA to assist an

applicant with identifying information to support its application nor does the regulation

anticipate that the panel will order FEMA to conduct a general reconsideration of an

application, absent any specific errors. For these reasons, we deny applicant’s alternative

requests for relief.

Decision

The buildings at issue are not eligible for replacement costs, as the costs for repairs

do not exceed fifty percent of the costs to replace the units. No other relief is granted.

Jonathan L. Kang

JONATHAN L. KANG

Board Judge

Erica S. Beardsley

ERICA S. BEARDSLEY

Board Judge

Marian E. Sullivan

MARIAN E. SULLIVAN

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.