MOTION FOR SUMMARY RELIEF DENIED: September 28, 2012

Agency decision

Ask Donna

What actually matters in this document.

Text

MOTION FOR SUMMARY RELIEF DENIED: September 28, 2012

CBCA 2407

SHAW AREVA MOX SERVICES, LLC,

Appellant,

v.

DEPARTMENT OF ENERGY,

Respondent.

Mark J. Meagher and Joseph G. Martinez of McKenna Long & Aldridge, LLP,

Denver, CO, counsel for Appellant.

Timothy P. Fischer, Savannah River Site Office, National Nuclear Security

Administration, Department of Energy, Aiken, SC; and Keith R. Landolt, Office of the

General Counsel, National Nuclear Security Administration, Department of Energy,

Washington, DC, counsel for Respondent.

Before Board Judges DANIELS (Chairman), POLLACK, and McCANN.

DANIELS, Board Judge.

The Department of Energy (DOE), respondent, moves for summary relief in a case

regarding the reasonableness of costs which Shaw AREVA MOX Services, LLC (MOX

Services), appellant, incurred, and for which it was reimbursed by the agency, under a costtype contract. We deny the motion, for it is premised on an incorrect legal standard and

material facts are in dispute.

CBCA 2407

2

Background

The contract underlying this dispute is for the design, construction, and operation of

the Mixed Oxide Fuel Fabrication Facility, a nuclear processing facility that will take

plutonium which is surplus to the United States’ national security needs and blend it with

depleted uranium to make fuel to be irradiated in commercial power reactors. The facility

is being built at DOE’s Savannah River Site (SRS) near Aiken, South Carolina. The parties

characterize this contract as a cost reimbursement or cost-plus-fixed-fee contract.

The contract was awarded to Duke, COGEMA, Stone & Webster, LLC in March

1999. After a series of mergers and acquisitions, MOX Services assumed the contract in

mid-2006. MOX Services is owned by Shaw Environmental and Infrastructure, LLC and

AREVA NC.

Between 1999 and 2006, much of the design work under the contract was performed

at Charlotte, North Carolina, and other locations. Toward the end of 2006, as the project

neared the start of construction, MOX Services began to relocate operations to Aiken. At

this time, however, uncertainty existed as to when construction would actually begin.

According to MOX Services, the company encountered a number of difficulties in recruiting

and retaining qualified personnel1 to work at the SRS. These difficulties included hesitancy

by some personnel to permanently relocate to the Aiken area, a housing market in which

prices were declining, increased competition for personnel in the nuclear power industry,

uncertainty regarding funding for the contract, and the limited duration of performance by

certain trades or individuals with certain professional expertise.

To address these concerns, MOX Services says that its senior management considered

several alternatives, including increasing base compensation for personnel who would

relocate to Aiken, tasking personnel from other sites to the SRS on business travel, and

developing a policy to address the circumstances. The company ultimately determined that

the last option was preferable. It established a Long Term Temporary Assignment (LTTA)

policy in February 2007. Under this policy, personnel who maintained a permanent residence

more than fifty miles from Aiken and were deemed by company management to fill a critical

role would be reimbursed for a portion of the expenses they incurred for maintaining a

second residence in the Aiken area. Individuals receiving LTTA payments would receive

1

MOX Services says that it “is an unpopulated limited liability company” and

that any references to “personnel” or “employees” are to “personnel employed by either of

MOX Services’ members and assigned to work on the Contract.”

CBCA 2407

3

a monthly lump-sum payment equal to seventy percent of the per diem allowance established

by the General Services Administration for government employees traveling to Aiken.

MOX Services kept the DOE contracting officer informed about its development of

the LTTA program. The company and the contracting officer engaged in many discussions

about the program and its application. The contracting officer expressed concerns that the

information the company provided was not adequate to support the costs claimed. By letter

dated March 7, 2008, the contracting officer proposed that $1,483,023.23 would be

disallowed unless documentation was presented to support these costs.

In August 2008, the contracting officer approved MOX Services’ fourth iteration of

LTTA (now called Jobsite Living Allowance (JLE).) This iteration included at least two

revisions which had been made at the contracting officer’s request. The company capped

reimbursements to an employee at the amount equal to the cost of relocating that employee

to Aiken, but excluding the costs of later relocating him following completion of his work

on the contract. The company also limited the duration of LTTA/JLE benefits to twenty-four

months.

DOE continued to review LTTA/JLE costs. In October 2010, the contracting officer

sent to the company a second notice of intent to disallow costs, identifying $2,172,670 as

unallowable. After discussions with the company, the contracting officer reduced this

amount to $2,097,993.15. The company continued to maintain that these costs are allowable.

On February 1, 2011, the contracting officer sent to MOX Services a decision which held that

the company must make payment to DOE in the amount of $2,097,993.15 “for the . . .

personnel who received inappropriate monetary benefits which were previously invoiced and

paid by the Government.” MOX Services has appealed this decision.

The amount at issue involves payments to approximately half of the sixty-eight

(according to the contracting officer) or sixty-nine (according to MOX Services) personnel

who received LTTA/JLE benefits.

The contracting officer says that some of the employees had agreed to accept

permanent positions in Aiken with lump-sum relocation benefits, and that the LTTA/JLE

payments granted to those individuals were considerably more than the lump-sum benefits

would have been. She also maintains that the company’s documentation shows that some

employees received LTTA/JLE benefits for periods of time which were not temporary –

some lasting as long as five years – in violation of program requirements. She explained,

“The jobs were not temporary in nature. MOX Services took no steps to find replacements

for the individuals filling the positions temporarily, and many of the employees stated that

they intended to stay on the project long term.” Thus, the contracting officer concluded that

CBCA 2407

4

the costs at issue were not reasonable, as that term is understood in Federal Acquisition

Regulation 31.201-3.

MOX Services, on the other hand, says that it “made a determination that payment of

LTTA was appropriate to address: (1) individuals who intended to relocate to Aiken, South

Carolina, but were unable to do so as anticipated because of the housing downturn in 2007

and 2008; and (2) individuals who were offered relocation, but nevertheless indicated they

were not willing to relocate to Aiken.” The company also states that it encouraged personnel

to relocate permanently to Aiken and worked to recruit personnel who were willing to

relocate permanently. MOX Services also notes that the contracting officer did not cite any

justification other than lack of reasonableness for demanding repayment of the funds at issue.

Discussion

Resolving a dispute on a motion for summary relief is appropriate when the moving

party is entitled to judgment as a matter of law, based on undisputed material facts. The

moving party bears the burden of demonstrating the absence of genuine issues of material

fact. All justifiable inferences must be drawn in favor of the nonmovant. Celotex Corp. v.

Catrett, 477 U.S. 317 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242 (1986).

The parties agree that whether the costs in question are reasonable is to be determined

by application of Federal Acquisition Regulation 31.201-3, “Determining reasonableness.”

This provision states:

(a)

A cost is reasonable if, in its nature and amount, it does not

exceed that which would be incurred by a prudent person in the conduct of

competitive business. Reasonableness of specific costs must be examined with

particular care in connection with firms or their separate divisions that may not

be subject to effective competitive restraints.

No presumption of

reasonableness shall be attached to the incurrence of costs by a contractor. If

an initial review of the facts results in a challenge of a specific cost by the

contracting officer or the contracting officer’s representative, the burden of

proof shall be upon the contractor to establish that such cost is reasonable.

(b)

What is reasonable depends upon a variety of considerations and

circumstances, including –

(1)

Whether it is the type of cost generally recognized as

ordinary and necessary for the conduct of the contractor’s business or

the contract performance;

CBCA 2407

5

(2)

Generally accepted sound business practices, arm’s length

bargaining, and Federal and State laws and regulations;

(3)

The contractor’s responsibilities to the Government, other

customers, the owners of the business, employees, and the public at

large; and

(4)

Any significant deviations from the contractor’s

established practices.

48 CFR 31.201-3 (2011).2

According to DOE, because the contracting officer made a thoughtful determination

that the costs in question are not allowable, the Board must deny MOX Services’ appeal of

what the agency characterizes as a discretionary act. In support of this position, DOE cites

the following paragraph from Planning Research Corp. Systems Service Co., NASA BCA

680-11, 81-2 BCA ¶ 15,179, at 75,121-22:

In the absence of an express contract provision or established practice between

the parties controlling the allocability of the costs in question, this Board will

not substitute its judgment for that of the Contracting Officer in the reasonable

exercise of his discretionary authority. Appellant assumed the risk and

responsibility of being wrong when it substituted its judgment for the

Contracting Officer’s.

As MOX Services points out, if this formulation of the law was ever correct, it has not

been so since enactment of the Contract Disputes Act in 1978. This Act states that if a

contracting officer makes specific findings in his decision, they “are not binding in any

subsequent proceeding.” 41 U.S.C. § 7103(e) (Supp. IV 2011) (restating language previously

found at 41 U.S.C. § 605(a)). The Court of Appeals for the Federal Circuit has held, “[T]he

Disputes Act itself suggests that, where an appeal is taken to a board [of contract appeals]

or court, the contracting officer’s award is not to be treated as if it were the unappealed

determination of a lower tribunal which is owed special deference or acceptance on appeal.”

Wilner v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994) (en banc) (quoting Assurance

Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987)). Further, as explained by the

Court, “[D]e novo review precludes reliance upon the presumed correctness of the decision.

2

This provision has been in effect since May 1987, and thus, throughout the life

of the contract in question.

CBCA 2407

6

. . . [O]nce an action is brought following a contracting officer’s decision, the parties start

in court or before the board with a clean slate.” Id. at 1401-02; see also Bay Shipbuilding

Co. v. Department of Homeland Security, CBCA 54, et al., 07-2 BCA ¶ 33,678, at 166,743.

Thus, now that the contracting officer’s decision has been appealed, it is the

prerogative of the Board, writing on a clean slate, to determine whether the costs which DOE

reimbursed and now believes were not allowable, are allowable or not. DOE acknowledges

that “there could be differing opinions on the reasonableness of the disallowed costs.” This

concession, which we find corroborated by conflicting conclusions of the contracting

officer’s decision and a Shaw Environmental and Infrastructure vice president’s affidavit,

demonstrates that material facts are in dispute and therefore precludes summary relief. The

appeal file submitted by DOE contains documentary evidence which may bear on this issue,

as to each of the employees to whom payment of LTTA/JLE benefits is considered

unreasonable by DOE and reasonable by MOX Services. We have scheduled a hearing at

which we will receive testimony which may elucidate the documentary evidence and the

justification for the conclusions reached by the parties. We will then decide, based on a

preponderance of the evidence, how much of the costs, if any, were reasonably incurred by

the company. See Commercial Contractors, Inc. v. United States, 154 F.3d 1357, 1362 (Fed.

Cir. 1998); Kelly Martinez, IBCA 3140, et al., 97-2 BCA ¶ 29,243, at 145,458; Conner

Brothers Construction Co., VABCA 2519, et al., 95-1 BCA ¶ 27,409, at 136,643 (1994);

Griffin Services, Inc., GSBCA 11171, 92-1 BCA ¶ 24,556, at 122,534.

Decision

DOE’s motion for summary relief is DENIED.

_________________________

STEPHEN M. DANIELS

Board Judge

We concur:

_________________________

HOWARD A. POLLACK

Board Judge

_________________________

R. ANTHONY McCANN

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.