In the Matter of EVERETT L. BUTLER
Agency decision
Ask Donna
What actually matters in this document.
Text
April 26, 2010
CBCA 1882-RELO
In the Matter of EVERETT L. BUTLER
Renee Lias, Castro, TX, appearing for Claimant.
Rachael K. House, Associate Counsel, Space & Missile Systems Division, Defense
Contract Management Agency, Carson, CA, appearing for Department of Defense.
WALTERS, Board Judge.
Claimant, Everett L. Butler, has requested reimbursement of extended temporary
quarters subsistence expenses (TQSE) and extended household goods (HHG) storage fees,
plus attorney fees and costs, in the total amount of $35,000. For the reasons explained
below, we find the claim to have some merit, but return the matter to the agency to determine
the amount to be reimbursed.
Background
In June 2009, claimant, who had been employed at the Patuxent River Naval Air
Station, Maryland, assumed a new position for the Defense Contract Management Agency
(DCMA), Oakland, California. In connection with the permanent change of station (PCS)
travel orders issued to him for his move from Maryland to California, claimant was
authorized reimbursement for actual TQSE for a period of thirty days. (Claimant elected to
be reimbursed based on actual expenses rather than a fixed amount of TQSE.) Claimant was
also authorized shipment of his household goods (HHG) and storage of those goods for up
to sixty days. His orders envisioned the possibility of DCMA granting extensions of HHG
storage eligibility for additional periods of sixty days each, up to a total of 180 days, and
CBCA 1882-RELO
2
extensions of TQSE eligibility for additional periods of thirty days each, up to a total of 120
days. Any request for such an extensions had to include written justification and
endorsement of the employee’s supervisor, including a description of the employee’s efforts
to secure permanent quarters at the new duty station. Extensions could be approved by
DCMA headquarters.
Claimant made a house hunting trip (HHT) to Oakland from June 9 through 16, 2009,
and began incurring TQSE expenses on June 20, 2009. Within a month of entering
temporary quarters, claimant asked his supervisor for an extension of his period of eligibility
for TQSE. He noted in an e-mail message that he had been “looking for permanent quarters
very diligently and . . . have found adequate housing but it will not be available until the
end of September.” The supervisor endorsed his extension request and passed it on for
processing.
When claimant made written inquiry in early September, he was told that a written
request, justification, and supervisor’s approval had not been submitted to the proper
authority. Claimant so informed the supervisor, requesting that, in addition to extending his
TQSE eligibility for the full 120 day period permitted, the period of eligibility for
reimbursement of the costs of storing his HHG also be extended. He reported that he would
be “moving to a permanent residence on October 18.” On September 23, the supervisor again
conveyed his approval in writing, stating: “It has been difficult to locate adequate housing
in that geographic area [where claimant was assigned].”
The request was sent to DCMA headquarters, where a management analyst denied it.
He determined that, because the request was submitted after the initially-approved periods
of eligibility for TQSE and storage of HHG had expired, it arrived too late to be considered.
He also noted a “general policy” that TQSE should be denied when an employee has been
reimbursed for HHT costs prior to moving, as claimant had been.
At this point, a Navy captain intervened and asked a high-ranking DCMA human
resources official to reconsider the agency’s denial of the claim. This official told others in
the agency, “[I]f there’s a way to work this legally, let’s find it.” He was advised, however,
that, based on rulings by our predecessor, the General Services Board of Contract Appeals,
he was legally obligated to deny reconsideration. The official followed that advice.
Unfortunately, the advice was misguided. The cases cited, Alex L. Rowe, GSBCA
14479-RELO, 98-2 BCA ¶ 29,919, and Joel Williams, GSBCA 16437-RELO, 04-2 BCA
CBCA 1882-RELO
3
¶ 32,769, have no relevance to this one. Those cases describe restrictions on agencies’ ability
to modify travel orders retroactively. In Rowe, after citing a rule that orders may generally
not be modified after travel has been performed, the board actually permitted reimbursement
of storage costs. In Williams, the board applied the established rule that once an employee
elects TQSE under one method (actual expenses or fixed amount), his orders may not be
changed to the other method.
The preliminary determination of the management analyst as to the claim makes no
more sense than the advice furnished to the human resources official. We are unable to find
in the Joint Travel Regulations (JTR) any requirement that if an employee requests an
extension of the period of eligibility for TQSE or HHG storage, he must do so within the
period prescribed in his original travel orders. See JTR C5364, C5190. Even if such a
requirement exists, it would not affect detrimentally claimant’s request for an additional
period of TQSE, for that request was made within the prescribed period. We also note that
the general policy of the JTR as to the relationship between TQSE and HHT reimbursement
does not preclude authorization of TQSE when a HHT has been taken. The policy merely
says that if, after an employee has made a HHT, temporary lodging is justified, “only a
necessary TQSE period” should be permitted. JTR C5356-D.
Claimant’s supervisor determined that claimant was unable to locate suitable,
permanent housing in the area of his new duty station because of housing conditions there.
According to the JTR, this is an acceptable justification for extending the periods of
eligibility for both TQSE and storage of HHG. JTR C5364-B.2.a(3), C5190-B.2.b. The
record makes clear that the DCMA official who was asked to reconsider the agency’s denial
of claimant’s request would have granted the request on this ground, if not for the incorrect
advice he received. We conclude that the official’s desire to grant the request should be
honored.
It is not clear from the record, however, how much of the instant $35,000 claim
represents additional TQSE and HHG storage costs and how much represents attorney fees
and associated costs, for which there is no authority for either the Board or the agency to
provide relief. The Board’s authority under the Equal Access to Justice Act, 5 U.S.C. § 504
(2006), does not extend to cases involving travel and relocation such as this one. Also, if
more than thirty days of actual TQSE is authorized, as would be the case here, the regulations
call for the actual number of days for which HHT expenses were reimbursed to be subtracted
from the first thirty days of reimbursable TQSE. JTR C5372-A.1.
CBCA 1882-RELO
4
Decision
Accordingly, although we find the present claim to have merit, we return the matter
to the agency to determine the amount due, providing relief solely for claimant’s extended
actual TQSE and HHG storage costs.
___________________________
RICHARD C. WALTERS
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.