DENIED: June 15, 2021
Agency decision
Ask Donna
What actually matters in this document.
Text
DENIED: June 15, 2021
CBCA 6906
MERIDIAN GLOBAL CONSULTING, LLC,
Appellant,
v.
DEPARTMENT OF HOMELAND SECURITY,
Respondent.
Ryan C. Bradel and Stephen G. Darby of Ward & Berry, PLLC, Washington, DC,
counsel for Appellant.
Keri Borzilleri and Matthew Lane, Office of Chief Counsel, Federal Emergency
Management Agency, Department of Homeland Security, Washington, DC, counsel for
Respondent.
Before Board Judges LESTER (presiding), VERGILIO, and CHADWICK.
Opinion for the Board by Board Judge CHADWICK. Board Judge LESTER concurs.
CHADWICK, Board Judge.
The appellant, Meridian Global Consulting, LLC (MGC), seeks compensation from
the respondent, Department of Homeland Security (DHS), for a course of events in which
the Federal Emergency Management Agency (FEMA) ordered fewer hours of security guard
services than the number of hours that FEMA had set forth as the estimates in a labor-hour
contract. Following discovery, both parties seek summary judgment. We grant DHS’s
motion, deny MGC’s, and deny the appeal.
CBCA 6906
2
Background
Except as noted, the material facts supported by the record are undisputed. FEMA
and MGC executed the contract in December 2018. The standard form 1449 described the
contract as “a labor hour contract with fixed hourly labor rates (fully burdened) as set forth
in the contract line item numbers (CLINs),” for Department of Labor (DOL) level II armed
security guard services at three “FEMA sites in Louisiana.” (We alter the contract’s
capitalization for readability.) The contract’s schedule of services contained one CLIN for
the base period of performance, from February 1 to March 31, 2019, and one CLIN for each
of seven, three-month option periods, potentially ending on December 31, 2020. A final
CLIN provided for a one-month option period in January 2021. The base CLIN stated an
“estimated number of hours” of 10,572. Each option CLIN except the last one stated an
“estimated number of hours” of 15,120. In each CLIN, the total estimated value of the
CLIN—the estimated hours times the hourly rate—was identified as “the not to exceed
amount” of that CLIN. Every CLIN stated, “contractor shall invoice based on actual hours.”
We do not know how FEMA developed its estimates of labor hours. Neither party
placed such evidence in the record. Nor can we say whether, or to what extent, MGC relied
on FEMA’s estimates in developing its price of $24.40 per labor hour (which FEMA
increased during performance to $26.24 based on a subsequent DOL wage determination).
MGC’s statement of facts in support of its motion starts with a paragraph purporting to
describe how MGC “determined” the overhead and profit rates for its bid, but the paragraph
is entirely conclusory, citing no “appeal file exhibits, admissions in pleadings,” or “evidence
filed with the motion,” as required by Board Rule 8(f)(1) (48 CFR 6101.8(f)(1) (2019)).
FEMA ultimately exercised, and MGC performed, all eight options, through January
2021. MGC invoiced for 61,856.96 hours of contract services, as compared to an estimated
total of 121,452 hours that had been set forth in the awarded contract for the base period plus
eight option periods.1 During performance, however, MGC signed without objection seven
bilateral modifications exercising options, which cumulatively reduced the total, estimated
number of labor hours to 77,040.2 The 61,856.96 hours billed by MGC are 51% of the
1
Apparently in reliance on the solicitation, MGC states that the total number of
estimated hours was originally 126,000. DHS denies that MGC states the correct estimate
for the base period. The sum of the estimates in the awarded CLINs is in fact 121,452 hours.
2
The bilateral modifications that reduced the estimated hours were
modifications P00004, P00005, P00006, P00007, P00008, and P00009. Bilateral
modification P00003 increased the estimated hours. FEMA issued a unilateral modification
further reducing the estimated hours for the last option period. Given the contract language
specifying payment for actual hours, these modifications do not affect our decision.
CBCA 6906
3
originally estimated labor hours and 80% of the estimated labor hours taking into account the
seven bilateral modifications.
In February 2020, during the fourth option period, MGC sent the contracting officer
a certified claim seeking $96,672.12 for services already provided plus an increase in its
hourly rate to $27.28 for future work. MGC asserted that FEMA had ordered only 8850 of
the estimated hours for the base period and that, by exercising options including lower
estimated hours than had been stated in the contract, FEMA had impaired MGC’s ability to
recover its overhead. MGC characterized the differences between the originally estimated
and the ordered or currently estimated numbers of labor hours as, alternatively, a partial
termination for convenience, a constructive change, a breach of FEMA’s duty to disclose
superior knowledge, and/or as the provision of negligent estimates. The contracting officer
denied the claim in July 2020, writing that the contract estimates “were based on the best
information available to FEMA at the time.” MGC filed this appeal in August 2020.
The parties conducted discovery until January 2021 and filed cross-motions for
summary judgment in February 2021. The motions are fully briefed.
Discussion
We apply the familiar summary judgment standard. E.g., Mingus Constructors, Inc.
v. United States, 812 F.2d 1387, 1390–91 (Fed. Cir. 1987); Mission Support Alliance, LLC
v. Department of Energy, CBCA 6477, 20-1 BCA ¶ 37,657. MGC advances four theories
of relief: (1) the bilateral modifications reducing the estimated labor hours constituted partial
terminations for convenience; (2) FEMA constructively changed the contract by eliminating
locations and reducing the number of guard positions, thereby reducing the number of labor
hours it ordered; (3) FEMA negligently prepared the contract estimates; and (4) FEMA
committed a breach by not disclosing its “superior knowledge” that it might not require all
of the estimated services.3 We address these arguments using the usual rules of contract
interpretation, which “are well settled and without need of elaborate reiteration.” ITT Arctic
Services, Inc. v. United States, 524 F.2d 680, 684 (Ct. Cl. 1975). In particular, where a
contract “is unambiguous, we follow the plain meaning without considering extrinsic
evidence or related arguments.” P.K. Management Group, Inc. v. Secretary of Housing &
Urban Development, 987 F.3d. 1030, 1033 (Fed. Cir. 2021).
3
To the extent that MGC raises other arguments, such as that FEMA breached
the duty of good faith and fair dealing in administering the security clearance process, we
lack jurisdiction to entertain such arguments, as neither they nor their operative facts were
presented in a certified claim. See Lee’s Ford Dock, Inc. v. Secretary of the Army, 865 F.3d
1361, 1369 (Fed. Cir. 2017).
CBCA 6906
4
MGC’s first and second arguments fail because the contract contained no guarantee
that FEMA would order a fixed quantity of services. The parties formed a commercial-item,
labor-hour contract. See 48 CFR 12.207(b)(2)(ii) (2018) (authorizing use of a labor-hour
contract only if the agency cannot “accurately estimate [at award] the extent or duration of
the work or . . . anticipate costs with any reasonable degree of confidence”). The contract
plainly stated that FEMA would pay the agreed rate for such services as it ordered and that
MGC must invoice only for actual hours. The estimated CLIN values were identified as
maximum, “not to exceed” amounts, not as floors. The estimates of labor hours served
purposes related to funding the contract and to placing ceilings on FEMA’s orders, but such
amounts plainly labeled as “estimates” cannot be read as “guarantees or warranties of
quantity.” Shader Contractors, Inc. v. United States, 276 F.2d 1, 7 (Ct. Cl. 1960); accord
Seaboard Lumber Co. v. United States, 308 F.3d 1283, 1302 (Fed. Cir. 2002). Because the
contract clearly did not obligate FEMA to use every available labor hour, MGC cannot
demonstrate either a “termination” of any obligations or a constructive change.4
Turning to MGC’s third argument, we need not and do not decide whether a
contractor could, in principle, recover for faulty estimates under a contract with these terms.5
We need not reach that unsettled issue because MGC proffers no evidence that could satisfy
its burden to “demonstrate that the approach actually selected by the [FEMA] estimator was
an unreasonable one.” Contract Automotive Repair & Management v. General Services
Administration, GSBCA 13627, et al., 99-2 BCA ¶ 30,530 (citing Medart, 967 F.2d at
581–82), aff’d, 243 F.3d 563 (Fed. Cir. 2000) (table); see also Walker v. Department of
Agriculture, CBCA 2131, et al., 18-1 BCA ¶ 36,921 (the contractor “did not present evidence
4
We note that it is not immediately clear that this contract contained the
minimum quantity guarantee which typically makes such an open-ended agreement
enforceable. See Coyle’s Pest Control, Inc. v. Cuomo, 154 F.3d 1302, 1304 (Fed. Cir. 1998);
Maxima Corp. v. United States, 847 F.2d 1549, 1557 (Fed. Cir. 1988); ASW Associates, Inc.
v. Environmental Protection Agency, CBCA 2326, 17-1 BCA ¶ 36,699. We need not explore
the possible ramifications of this observation, however, as MGC’s claim and arguments focus
on the expressly stated “estimates,” not on the presence or absence of a stated minimum
quantity, and the contract is enforceable to the extent performed. ASW.
5
Our appellate authority has addressed the viability of negligent estimate claims
under indefinite quantity contracts, Travel Centre v. Barram, 236 F.3d 1316, 1319 (Fed. Cir.
2001) (explaining that the contractor “could not have had a reasonable expectation” of
revenue exceeding the minimum guarantee “[r]egardless of the accuracy of the estimates”),
and under requirements contracts. E.g., Medart, Inc. v. Austin, 967 F.2d 579, 581 (Fed. Cir.
1992). We lack such definitive precedent applicable to this labor-hour contract with
commercial terms. Cf. John Cibinic, Jr., Ralph C. Nash, Jr., & Christopher R. Yukins,
Formation of Government Contracts 1323 (4th ed. 2011).
CBCA 6906
5
of a negligent estimate”). The mere fact that the estimates did not pan out does not imply
that they were unreasonable when made. MGC cannot avoid summary judgment on this
theory by relying on mere “allegations without evidence, which fail to set forth specific facts
showing that there is a genuine issue of material fact.” Microtechnologies LLC
v. Department of Justice, CBCA 6772 (Mar. 31, 2021); see GAF Corp. v. United States, 932
F.2d 947, 949 (Fed. Cir. 1991) (a claimant must “produce specific evidence” for the claim
elements when opposing summary judgment).
MGC’s superior knowledge theory fails for essentially the same reasons. MGC’s
argument here has two parts. First, MGC complains that the contract start date and the
duration of the base period differed from the dates that FEMA had used in the solicitation.
MGC waived or forfeited any such reliance on the solicitation when it accepted the dates in
the awarded contract. See Brawley v. United States, 96 U.S. 168, 173 (1877) (an executed
contract “merge[s] all previous negotiations, and is presumed, in law, to express the final
understanding of the parties”); SCM Corp. v. United States, 595 F.2d 595, 598 (Ct. Cl. 1979)
(“When legal obligations between the parties will be deferred until the time when a written
document is executed, there will not be a contract until that time.”). Second, MGC maintains
that FEMA knew or should have known before award that its need for the guard services
would decline during the two years covered by the contract. Again, however, we see no
evidence that could support a triable claim that FEMA had advance knowledge or notice that
the contract estimates would eventually turn out to be too high. MGC’s assertions that
FEMA must have had such awareness by virtue of its agency mission are conclusory.
The respondent is entitled to summary judgment in all respects. Accordingly, we
grant DHS’s motion and deny MGC’s motion.
Decision
We DENY the appeal.
Kyle Chadwick
KYLE CHADWICK
Board Judge
I concur:
Joseph A. Vergilio
JOSEPH A. VERGILIO
Board Judge
CBCA 6906
6
LESTER, Board Judge, concurring.
I concur with the result in this appeal. I agree with the majority’s determination that,
because the contract did not guarantee that the Federal Emergency Management Agency
(FEMA) would order all of the contract’s estimated labor hours, appellant, Meridian Global
Consulting (MGC), cannot prevail on its arguments that FEMA either partially terminated
or constructively changed the contract merely because FEMA ultimately ordered less than
all of the estimated hours. I also agree with the majority that MGC has failed to identify any
evidence that FEMA’s labor hours estimates were negligently prepared or that FEMA
withheld any superior knowledge that it was required, but failed, to disclose prior to contract
award, entitling the Government to summary judgment on those issues.
I write separately because of my view that, as I explain below, the majority decision
does not adequately address or resolve an issue that I believe must be decided to resolve this
appeal fully.
Supplemental Undisputed Facts
The contract at issue here, which the parties executed on December 21, 2018, required
MGC to provide armed security guard services at disaster-related sites and facilities in Baton
Rouge, Louisiana. As the majority notes, it was a commercial-item labor-hour contract. It
provided that services would be needed at three specific sites – a group site that was then
housing disaster survivors in mobile housing units (MHUs) until the survivors’ homes were
repaired and habitable; a storage site housing empty MHUs until needed in the field; and an
office building being used by FEMA employees – and that FEMA could order guard services
at other, then-unidentified sites during the term of the contract. Appeal File, Exhibit 2 at 38.6
For the base period of performance (CLIN 0001), which ran from February 1 through
March 31, 2019, FEMA estimated that it would order 10,572 labor hours; for each of seven
option periods, each of which contemplated ninety-day additional periods of performance
(CLINs 1001 through 7001), FEMA estimated 15,120 labor hours per period; and, for a final
option for a thirty-day performance period (CLIN 8001), FEMA estimated 5040 labor hours.
Exhibit 1 at 2-6; Exhibit 2 at 38; Exhibit 5 at 81; Exhibit 22.7
6
Except where otherwise noted, all exhibits referenced in the concurrence are
found in the appeal file.
7
MGC complains that the solicitation on which it bid contemplated a longer
base period – from January 1 through March 31, 2019 – with a 15,120 labor hours estimate
but that delays in the contract award reduced that period by thirty-one days with a resulting
reduction in the estimated labor hours. MGC executed the contract, with its reduced base
period, without objection, and I agree with the majority that MGC cannot complain now
CBCA 6906
7
When FEMA exercised the first ninety-day performance option under the contract,
it increased the estimated labor hours for that option period from 15,120 to 15,444, and MGC
executed a bilateral modification accepting that option exercise without objection.
Subsequently, however, FEMA issued a task order reducing guard coverage at one of its sites
and, on April 10, 2019, issued a bilateral modification, which MGC executed (again without
objection), reducing the estimated labor hours for the previously executed first option period
by 2160 to 13,284 hours. Exhibit 10 at 127-28.
FEMA subsequently continued exercising the contract’s performance options but, as
the group housing site and later the storage site were closed, reduced the estimated labor
hours in each of its option exercises below that which the contract identified. In its exercise
of the second performance option, extending contract performance through the end of
September 2019, FEMA identified an estimated number of 11,208 labor hours, a reduction
of 3912 hours from the 15,120 estimate in the contract for that option period. The third
option exercise, extending performance through December 31, 2019, was for 7896 estimated
labor hours, a reduction of 7224 hours from the contract’s 15,120 labor-hour estimate. In
response to both option exercises, however, MGC executed bilateral modifications, dated
June 26 and September 25, 2019, accepting the option exercises without objection. See
Exhibit 11 at 129-30; Exhibit 12 at 131-32.
By email dated December 2, 2019, MGC complained to the FEMA contracting officer
about what it described as a significant reduction in the number of hours anticipated. The
contracting officer responded that the labor hours identified in the contract were only
estimates, not guarantees, and presented MGC with a draft bilateral modification (P00007)
to exercise the fourth option period (extending contract performance through March 31,
2020), but with estimated labor hours of only 4719. Exhibit 13 at 133-34. On December 31,
2019, MGC submitted a request for equitable adjustment (REA), asserting that the reduction
of estimated labor hours from 15,120 to 4719 in exercising the fourth option (through
modification P00007) would reduce the original scope of work set forth in the contract by
nearly 70% and, in MGC’s opinion, constituted a constructive partial termination for
convenience. As a remedy, MGC asked that FEMA formally increase the fully-burdened
contractual labor-hour rate to a rate of $33.67 per hour. Exhibit 17. The next day, MGC’s
president executed bilateral modification P00007 without further comment. Exhibit 13 at
133-34.
about a “change” that occurred prior to, and is incorporated within, the contract as executed.
See, e.g., K-W Construction, Inc. v. United States, 671 F.2d 481, 484 (Ct. Cl. 1982); SCM
Corp. v. United States, 595 F.2d 595, 598 (Ct. Cl. 1979).
CBCA 6906
8
The FEMA contracting officer denied the REA on January 29, 2020. Exhibit 18.
Subsequently, on February 20, 2020, MGC submitted a certified claim to the contracting
officer seeking $96,672.12 in “back pay” for work already performed and an increase in its
hourly rate to $27.28 going forward for any further work to be performed under the contract.
Exhibit 19 at 6. MGC asserted that, based upon the estimates in the solicitation and resulting
contract, it needed to hire forty-two guards to perform the estimated work, as well as a
full-time project manager to manage the project, costs that it had factored into the hourly rate
of $24.40 (later increased to $26.24 as a result of new DOL wage determinations) that it had
included in its bid, along with allocations for time that other company executives would
dedicate to the project and general and administrative expenses. It complained that FEMA
had only given it 8850 hours of performance during the contract’s base period, rather than
the 15,120 hours identified in the original solicitation, and that, in exercising the second,
third, and fourth options with much lower estimated hours than set forth in the contract,
FEMA had negatively impacted MGC’s ability to recover its overhead. As the legal basis
for its right to recover, MGC argued that the reduction in estimated labor hours resulted in
a partial termination for convenience, a constructive change, a breach of FEMA’s duty to
disclose superior knowledge, and/or a breach of FEMA’s duty not to provide negligent
estimates.
On March 26, 2020, while MGC’s claim was pending before the FEMA contracting
officer, the parties executed bilateral modification P00008 through which FEMA exercised
the fifth option period, extending contract performance through June 30, 2020. In the
modification, FEMA capped the estimated labor hours for the fifth option period at 4719
hours, rather than the 15,120 hours identified in the contract. Exhibit 14 at 135-36. Through
bilateral modification P00009, executed June 30, 2020, FEMA exercised the sixth option
period, extending contract performance through September 30, 2020, with estimated labor
hours of 4782, rather than the 15,120 hours identified for that option period in the contract.
Exhibit 15 at 137-38.
By decision dated July 17, 2020, the FEMA contracting officer denied MGC’s
February 20 claim, asserting that the labor-hour estimates identified in the solicitation “were
based on the best information available to FEMA at the time.” Exhibit 20 at 4. On
August 25, 2020, MGC filed this appeal of that decision with the Board. Both parties
subsequently filed cross-motions for summary judgment.
While this appeal was pending, FEMA issued unilateral modifications P00010 and
P00011, exercising the seventh option period to extend the contract performance period
through December 30, 2020, with an estimated number of labor hours of 4782 (rather
than 15,120) to be provided solely at the office building housing FEMA employees.
Appellant’s Summary Judgment Motion (Feb. 1, 2021), Exhibit 3.
CBCA 6906
9
From the start of the contract through February 1, 2021, the date on which MGC filed
its summary judgment motion, MGC expended 61,856.96 hours on the contract, a figure
below the 126,000 estimated labor hours (assuming exercise of all options) identified in the
contract’s solicitation. Appellant’s Summary Judgment Motion, Exhibit 5.
Discussion
There are two issues that I believe are raised by the claim underlying this appeal and
the pleadings that, in my opinion, the majority decision does not fully address. First, the
Government has questioned the extent to which a contractor could ever pursue a negligent
estimates claim under the type of commercial-item labor-hour contract at issue in this appeal,
assuming that the contract at issue here does not guarantee the contractor any work beyond
what the Government actually orders. Second, if we assume that a negligent estimates theory
could potentially be viable here because the contract entitles the contractor to something
more than a minimum guaranteed quantity of work, we would have to consider whether
FEMA effected a constructive change when it exercised option periods under this contract,
but changed the ceilings on the number of labor hours that FEMA could order during that
option period from those identified in the contract. In my mind, resolution of the first issue
in FEMA’s favor moots and negates the need to resolve the second issue, but the majority
has decided neither.
The majority held that, because MGC had presented no factual evidence to support
a negligent estimates argument, it was unnecessary to resolve whether the contract was
amenable to a negligent estimates argument. The majority did not address whether FEMA
effected a constructive change by exercising options using different labor hour ceilings than
those identified in the contract, indicating only that options were exercised through bilateral
modifications that presumably bar MGC from complaining about defects in the option
exercises. In the factual circumstances of this case, I do not believe that MGC’s execution
of bilateral modifications bars complaints about some of those option exercises because,
when MGC signed several of the modifications, FEMA was well aware that MGC was
simultaneously objecting to FEMA’s reduction in the labor hour ceilings under the options.
The need for us to resolve the option exercise defect issue is negated only because, under the
type of contract at issue here, FEMA did not guarantee that it would order anything more
than the minimum quantity (if any) set forth in the contract, making (for reasons I explain
below) any defect in the option exercise irrelevant. Without a finding that the contract did
not provide any other guarantee, the option exercise defect issue is not moot. Accordingly,
for the reasons explained below, I would resolve this appeal in the Government’s favor
because MGC’s contract is not comparable to a requirements contract and did not obligate
FEMA to order anything more than what FEMA actually ordered.
CBCA 6906
10
Negligent Estimates Claims Under Labor-Hour Contracts
In its summary judgment briefing, the Government argues not only that its estimates
were not negligently prepared, but that the type of commercial-item labor-hour contract at
issue here precludes a negligent estimates claim. The nature of this contract, the Government
asserts, entitles the contractor to nothing more than what the agency in the contract actually
guarantees will be ordered.
Under the United States Court of Appeals for the Federal Circuit’s precedent, whether
a contractor can pursue a negligent estimates claim appears heavily dependent on the type
of indefinite-delivery contract at issue and the extent of the promises that the Government
has made through that contract. The Federal Acquisition Regulation (FAR) states that
“[t]here are three types of indefinite-delivery contracts: Definite-quantity contracts,
requirements contracts, and indefinite-quantity [(IDIQ)] contracts.” 48 CFR 16.501-2(a)
(2018) (FAR 16.501-2(a)). Only two of those, requirements contracts and IDIQ contracts,
require the Government to estimate its future needs and provide that the specific quantity of
supplies or services that the Government will order will ultimately be defined by future
events and circumstances. FAR 16.503(a)(1), 16.504(a)(1). It is under those two latter types
of contracts that the Federal Circuit has addressed the viability of “negligent estimates”
damages claims.
A requirements contract “is formed when the seller has the exclusive right and legal
obligation to fill all of the buyer’s needs for the goods or services described in the contract,”
Modern Systems Technology Corp. v. United States, 979 F.2d 200, 205 (Fed. Cir. 1992)
(emphasis added), even though “[t]he exact requirements are usually not known.” DOT
Systems, Inc., IBCA 1197-6-78, et al., 80-2 BCA ¶ 14,694 (quoting Radionics, Inc., ASBCA
20796, 77-1 BCA ¶ 12,448), aff’d, 231 Ct. Cl. 765 (1982). For reasons that it explained in
Rumsfeld v. Applied Cos., 325 F.3d 1328 (Fed. Cir. 2003), the Federal Circuit has affirmed
that negligent estimates claims can be viable under requirements contracts, holding that, if
“a contractor can show by preponderant evidence that estimates were ‘inadequately or
negligently prepared, not in good faith, or grossly or unreasonably inadequate at the time the
estimate was made’” before executing a requirements contract, the Government can be liable
for damages. Id. at 1335 (quoting Medart, Inc. v. Austin, 967 F.2d 579, 581 (Fed. Cir.
1992)); see Agility Defense & Government Services, Inc., 847 F.3d 1345, 1350 (Fed. Cir.
2017); Crown Laundry & Dry Cleaners, Inc., ASBCA 39982, 90-3 BCA ¶ 22,993; DOT
Systems, Inc.
The Federal Circuit has taken a different view of negligent estimates claims under
IDIQ contracts. In such contracts, the Government does not promise to satisfy all of its
requirements for a particular type of service or supply from the contractor but leaves open
the possibility that “the Government could procure additional quantities of such supplies and
CBCA 6906
11
services from other sources” while guaranteeing a minimum quantity of purchases from or
payment to the contractor. DOT Systems, Inc. (quoting Radionics, Inc.). The Federal Circuit
has held that, as a matter of law, IDIQ contractors cannot maintain negligent estimates claims
since the only promise that the Government makes regarding quantity in such contracts is
that it will order the guaranteed minimum. Travel Centre v. Barram, 236 F.3d 1316, 1319-20
(Fed. Cir. 2001); see Future Forest, LLC v. Secretary of Agriculture, No. 2020-2039, 2021
WL 1422742, at *4-*5 (Fed. Cir. Apr. 15, 2021); Mason v. United States, 615 F.2d 1343,
1350 (Ct. Cl. 1980); DOT Systems, Inc. v. United States, 231 Ct. Cl. 765, 769 (1982). Once
the Government meets its obligation to order that minimum, any “allegation that the
estimates were negligently prepared, even if true, [becomes] immaterial.” C.F.S. Air Cargo,
Inc., ASBCA 40694, 91-2 BCA ¶ 23,985; see RocJoi Medical Imaging, LLC v. Department
of Veterans Affairs, CBCA 6885, 20-1 BCA ¶ 37,746.
If an IDIQ contract fails to identify any mandatory minimum purchase guarantee at
all, the contractor still remains unable to seek a remedy for negligently estimated quantities
because, without a minimum guarantee, the entire contract becomes illusory and
unenforceable for lack of consideration and mutuality beyond the work actually performed,
with payment under the terms of the contract. Coyle’s Pest Control, Inc. v. Cuomo, 154 F.3d
1302, 1306 (Fed. Cir. 1998) (citing Willard, Sutherland, 262 U.S. at 493); Mason, 615 F.2d
at 1346 n.5; DOT Systems, Inc., 80-2 BCA ¶ 14,694. In such circumstances, the IDIQ
contractor is entitled only to retain whatever money it was paid for its prior performance
under the terms of the otherwise unenforceable contract, Coyle’s Pest Control, 154 F.3d at
1306; Flink/Vulcan v. United States, 63 Fed. Cl. 292, 301 (2004), aff’d, 163 F. App’x 890
(Fed. Cir. 2006), even if the work was performed under protest. Federal Electric Corp. v.
United States, 486 F.2d 1377, 1381-82 (Ct. Cl. 1973). Conversely, the absence of a
minimum mandatory quantity in a requirements contract does not affect that contract’s
enforceability because “the seller’s promise to satisfy the buyer’s requirements and the
buyer’s promise to purchase all its requirements from the seller ensure mutuality of
obligation.” Mason, 615 F.2d at 1349.
The contract at issue here is not labeled a requirements contract or an IDIQ contract
but instead is identified as a labor-hour contract, which is essentially a time-and-materials
contract for services without the delivery of materials. FAR 16.602. Where does a
labor-hour contract fit within the context of the Federal Circuit’s recent directions about the
viability of “negligent estimates” claims? It is somewhat difficult to decipher.
The FAR directs that “[t]ime-and-materials contracts and labor-hour contracts are not
fixed-price contracts,” FAR 16.600, but does not otherwise expressly address where such
contracts fit within the three kinds of indefinite-delivery contracts identified in FAR
16.501-2(a). At least one commentator has noted that neither the FAR nor statutes “yield a
definitive answer to the question of how to classify time-and-materials and labor-hour
CBCA 6906
12
contracts.” Ralph C. Nash, Time-and-Materials and Labor-Hour Contracts: Fixed-Price or
Cost Contracts?, 12 Rep. ¶ 1 (Jan. 1998). They have been described as “indefinite-quantity,
indefinite-delivery contract[s] under which payment is based on specified fixed hourly rates
for labor and on a cost-reimbursable basis for materials,” Systems Research & Applications
Corp., B-225574, et al., 87-1 CPD ¶ 540 (May 26, 1987); as “essentially . . .
cost-reimbursement contract[s], where the labor provided is at a fixed hourly rate which
includes overhead and profit,” Wolf, Block, Schorr & Solis-Cohen, B-221363, et al., 86-1
CPD ¶ 491 (May 28, 1986); as fixed-price and cost-reimbursement hybrids where “the only
fixed-price aspect is the burdened labor rates,” Ralph C. Nash, supra, 12 Nash & Cibinic
Rep. ¶ 1; and, on some occasions, as requirements-type contracts. E.I.L. Instruments, Inc.,
GSBCA 4459, 76-1 BCA ¶ 11,909; Katmai Information Technologies, LLC, B-406885, 2012
CPD ¶ 277 (Sept. 20, 2012); Temps & Co., 65 Comp. Gen. 640, 640 (June 9, 1986).
According to the commentator, “[t]he coverage of time-and-materials and labor-hour
contracts [in the FAR] appears to indicate that the FAR drafters did not know what to do with
them.” Ralph C. Nash, supra, 12 Nash & Cibinic Rep. ¶ 1.
A lack of consistency in classifying time-and-materials and labor-hour contracts is
evident in the differing results in prior decisions analyzing negligent estimate arguments
under such contracts. In H.L. Yoh Co. v. United States, 288 F.2d 493 (Ct. Cl. 1961), the
Court of Claims permitted recovery under a time-and-materials contract when the quantity
of drawings and parts lists that the contractor was asked to convert was less than what the
contractor should have been provided under the contract terms. The Court described the
time-and-materials contract at issue in that case as structured in a manner similar to a
requirements contract, finding that the contract provided for conversion of “all drawings and
parts lists at the Detroit Arsenal relating to automotive equipment.” Id. at 494; see New
Orleans Stevedoring Co., ASBCA 7483, 1962 BCA ¶ 3382 (indicating that the Court in H.L.
Yoh had considered the time-and-materials contract in that case to mirror a requirements
contract). Conversely, in a recent, non-precedential small claims procedure decision in
Dream Management, Inc. v. Department of Homeland Security, CBCA 5517, 17-1 BCA
¶ 36,716, the Board rejected the contractor’s attempt to pursue a negligent estimates claim
under a time-and-materials contract, holding that, even though the agency had acknowledged
making a significant error in identifying estimated quantities in the solicitation and resulting
contract, “[t]he concept of a negligent estimate in a time and materials contract is antithetical
to the contract vehicle.” In that case, the contract, though titled a time-and-materials
contract, was structured in a manner that mirrored the structure of an IDIQ contract.
In my view, the fact that a contract is titled a time-and-materials contract or a
labor-hour contract does not, in and of itself, define the extent to which a negligent estimates
claim may be considered. “Determination of the type of contract is a matter of law – not
controlled by a label in the contract.” Maintenance Engineers v. United States, 749 F.2d 724,
726 n.3 (Fed. Cir. 1984). The FAR indicates that, in both IDIQ and requirements contracts,
CBCA 6906
13
the Government can adopt pricing arrangements like those that are found in time-andmaterials and labor-hour contracts, FAR 16.501-2(c), and, as seen in the previously cited
cases, time-and-materials and labor-hour contracts can similarly be written in a manner that
makes them resemble requirements contracts or IDIQ contracts. No matter how
characterized, any contract, to be enforceable, must provide for mutuality of obligation,
Ridge Runner Forestry v. Veneman, 287 F.3d 1058, 1061 (Fed. Cir. 2002), and, to provide
a basis for a negligent estimate claim, contain terms that make the reasonableness of the
original quantity estimate relevant to a damages award. Rather than relying upon the label
placed upon a contract, we must look to the contract’s language and structure to determine
how properly to categorize it.
Looking at MGC’s contract, it does not contain terms that would make it a
requirements-type contract. “[A]n essential element of a requirements contract is the
promise by the buyer to purchase the subject matter of the contract exclusively from the
seller.” Modern Systems Technology, 979 F.2d at 205 (emphasis added). Although the
contract here indicates that guard services “will be required” at no less than three particular
sites identified in the contract, Exhibit 2 at 38, it does not contain any language precluding
FEMA from bringing in additional resources at those sites from other sources or
guaranteeing exclusivity to MGC for guard services that FEMA might ultimately need at
other possible sites in Louisiana. As the Federal Circuit recognized, even if some language
in a contract might “suggest exclusivity,” a contract ultimately “falls short of the exclusivity
language necessary for a requirements contract” where, like here, it fails to require the
agency to assign all work of that type to the contractor. Coyle’s Pest Control, 154 F.3d at
1305-06.
This particular labor-hour contract is instead set up more like an IDIQ contract for
services. The manner in which services are ordered in MGC’s contract mirrors the set-up of
one of the IDIQ contracts in Art Anderson Associates, ASBCA 27807, 84-1 BCA ¶ 17,225,
which identified a labor category of “Chief Design,” an estimate of 650 hours, an hourly
labor rate (and a parallel overtime rate), a holiday hourly labor rate, and a “Not to Exceed”
amount for the contract. Because MGC’s labor-hour contract is “used as the basis for pricing
tasks to be specified after award,” it should be “subject to the limitations imposed on [IDIQ]
‘task order contracts.’” John Cibinic, Jr., Ralph C. Nash, Jr., & Christopher R. Yukins,
Formation of Government Contracts 1323 (4th ed. 2011). Accordingly, I would apply the
negligent estimate rules applicable to IDIQ contracts to the labor-hour contract at issue here.
In MGC’s contract, it is questionable whether there is any minimum quantity
guarantee sufficient to provide mutuality. The only possible minimum guarantee that I can
see comes through the contract’s representation that MGC “will be required” to provide
guard services at three specific sites, albeit without specifying a minimum dollar payment
or time frame for those required services. Both parties have indicated that, unlike the FAR
CBCA 6906
14
provisions for IDIQ contracts, the FAR provisions applicable to labor-hour contracts do not
identify any requirement for a minimum quantity guarantee, see FAR 12.207, 16.601,
16.602, which is true, but any contract, no matter its type, has to create mutuality to be
enforceable, Ridge Runner Forestry, 287 F.3d at 1061, and neither party has identified how,
absent a minimum quantity obligation, that mutuality would be established in this nonrequirements contract. Nevertheless, the mutuality issue need not be resolved because,
regardless of its outcome, MGC’s negligent estimates claim is not viable as a matter of law.
If the contract here is unenforceable for lack of mutuality, MGC is not entitled to prevail on
its negligent estimates claim, as its recovery is limited to what it has already been paid. See
Coyle’s Pest Control, 154 F.3d at 1305-06; Flink/Vulcan, 63 Fed. Cl. at 301. If the contract
is enforceable, MGC cannot succeed on a negligent estimate claim for the same reasons that
such claims are not viable under IDIQ contracts. See Travel Centre, 236 F.3d at 1319-20.
I would find that DHS is entitled to summary judgment on MGC’s inability to maintain a
negligent estimate argument.
Why We Must Resolve The Agency’s Negligent Estimates Argument
A constructive change issue in this appeal related to the one addressed by the majority
involves potential defects in FEMA’s option exercises. If the labor-hour contract at issue
here were written in a manner that entitled MGC to something more than a minimum
labor-hour guarantee, we would have to decide that issue. Only because MGC’s contract
provides no such right is that constructive change issue moot.
When FEMA exercised each of the first seven options under this contract, it did not
identify the 15,120 labor hours estimate set forth in the contract for each option period.
Instead, it modified the labor hours number to reflect what it then thought it actually would
order during that period – in the first option exercise, it increased the labor hours estimate
above the 15,120 figure, but, in every other exercise, it reduced (sometimes significantly) the
estimate below the 15,120 figure. Given that the labor hours estimate in a labor-hour
contract creates a ceiling on the number of labor hours that the agency can order and the
contractor can perform during the relevant period, FAR 12.207(b)(1)(ii)(B), FEMA’s
exercise of options using a modified ceiling begs the question of whether the exercises were
valid.
It is a general rule that, if the Government “attempts to alter the conditions of the
contractor’s obligation” when it exercises an option, “the purported option exercise normally
becomes ineffective” and entitles the contractor “to an equitable adjustment for a
constructive contract change under the Changes clause.” Safeguard Maintenance Corp.,
IBCA 3379-E, 95-1 BCA ¶ 27,383 (1994). Did FEMA change the terms of the option when
it purported to exercise them in a manner that could constitute a constructive change?
CBCA 6906
15
In its decision, the majority references the fact that FEMA exercised the options
through bilateral modifications. Given that such a modification can create a “substituted
contract” that discharges any complaint about the nature of the Government’s action,
Kokosing Construction Co., EBCA 439-2-90, 91-1 BCA ¶ 23,508 (1990), the bilateral nature
of the modifications might be viewed as rendering any concern about the manner of the
option exercises irrelevant. Nevertheless, whether a “substituted contract” results from a
bilateral modification depends upon the intention of the parties. Transworld Systems Inc. v.
Department of Education, CBCA 6049 (Aug. 13, 2020). Because MGC executed bilateral
modifications accepting the first three option exercises without comment or complaint, it
most likely has no basis upon which to object to them. Nevertheless, before executing the
modification exercising the fourth option, MGC not only complained to the contracting
officer about the constant reduction in labor hours but submitted an REA seeking an
equitable adjustment as a result of what it called a constructive change. FEMA was well
aware of MGC’s complaints when executing modifications regarding the fourth, fifth, and
sixth option periods, and FEMA exercised the seventh option through a unilateral, not
bilateral, modification. In such circumstances, I cannot see how the mere fact that MGC
signed bilateral modifications involving options necessarily bars objections to them, either
in form or content. See Daniels Co. of Southern Pines, ASBCA 18920, 74-1 BCA ¶ 10,608
(contracting officer’s knowledge at time of bilateral modification execution that contractor
did not consider it a resolution of the contractor’s dispute precluded accord and satisfaction).
Nevertheless, if, under the terms of its contract, FEMA had no obligation to order
anything more than the minimum number of labor hours guaranteed by the contract, or if the
contract was illusory because it provided no minimum guarantee at all and was not a
requirements contract, MGC could not, for reasons that I discussed above, seek damages for
negligent estimates or for any quantity of missed labor hours beyond the minimum guarantee.
Its only right under a contract guaranteeing purchase of a minimum number of labor hours
is payment for that minimum. Future Forest, 2021 WL 1422742, at *4-*5; Travel Centre,
236 F.3d at 1319-20. Its remedy under an illusory contract is to retain whatever money it
was paid for its prior performance under the terms of the otherwise unenforceable contract.
Coyle’s Pest Control, 154 F.3d at 1306. In either circumstance, any defect in the exercise
of option periods would provide no basis for an increased monetary recovery.
Because of my view of the nature of MGC’s contract, I do not believe it necessary to
resolve any questions about the validity of FEMA’s option exercises. Nevertheless, I believe
that, to come to the conclusion that an invalid option exercise would not provide MGC with
any monetary rights for a constructive change, the Board must first identify the nature of the
contract and decide the extent to which the contractor may maintain a negligent estimates
claim under it. I concur in the result that the majority reached in this appeal, but I disagree
with its belief that a decision about the nature of and rights created by the underlying contract
is unnecessary to reach that result.
CBCA 6906
16
For the foregoing reasons, I concur in the decision to deny MGC’s appeal.
Harold D. Lester, Jr.
HAROLD D. LESTER, JR.
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.