GRANTED IN PART: March 10, 2022

Agency decision

Ask Donna

What actually matters in this document.

Text

GRANTED IN PART: March 10, 2022

CBCA 7233

CI-POND SOLUTIONS JV, LLC,

Appellant,

v.

DEPARTMENT OF JUSTICE,

Respondent.

Kevin H. Hudson and Alexander J. Bell of Hudson Lambert Parrott Walker, LLC,

Atlanta, GA, counsel for Appellant.

Marc E. Mandel, Office of General Counsel, Federal Bureau of Investigation,

Department of Justice, Washington, DC; and Kelli Beene, Office of General Counsel,

Federal Bureau of Investigation, Department of Justice, Redstone Arsenal, AL, counsel for

Respondent.

SHERIDAN, Board Judge.

Appellant, CI-Pond Solutions JV, LLC (CPS), was awarded task order

15F067-20-F-0000515 for the construction of the Federal Bureau of Investigation (FBI)

Hazardous Devices School Fuselage Training Facility (FTF), located in Huntsville, Alabama.

The contract was a firm-fixed-price, design-build type with a value of $1,251,599.

CPS is a small business concern, and the amount in controversy is $149,551.33. It

elected to pursue the appeal under the Board’s small claims procedure, as permitted by

section 7106(b) of the Contract Disputes Act (CDA) (41 U.S.C. § 7106(b) (2018)) and

implemented through Board Rule 52 (48 CFR 6101.52 (2020)). A decision issued under that

procedure is final and unappealable except for fraud.

CBCA 7233

2

Background

The contract’s scope of work included all management, labor, equipment, and material

necessary for design and construction of a fully operational FTF. Appeal File, Exhibit 5 at

391.1 The contractor was also responsible for site preparation, excavation, and soil

investigation. Id. Due to the restrictive nature of the facility, offerors were only permitted

a visual inspection of the site and were not allowed to take additional photographs or soil

samples. Appellant’s Reply at 4. Offerors did not receive a geotechnical report or

topographical survey. Id. The statement of work (SOW) provided a brief description of the

existing conditions at the site, including the following description of the soil: “The local

overburden is predominantly residual red clays, with some shallow loam or gravel lenses and

deeper cherty rubble occurring above the bedrock surface.” Exhibit 5 at 395.

CPS requested, but was denied, a follow-up site visit. Complaint at 2. Offerors,

including CPS, submitted hundreds of requests for information (RFIs). See generally

Exhibit 9 at 475-515. The Government, through responses to the RFIs, informed offerors

that the soil bearing conditions, electrical requirements, and other information would be

determined during design. Id. To assist offerors in developing their proposals for building

the FTF, the Government provided reference drawings of what it considered to be a

comparable building at the site. On January 18, 2020, CPS submitted a proposal based on

these conditions.

On May 20, 2020, the parties executed the contract for design and construction of the

FTF in the amount of $1,251,599. The contract incorporated CPS’s proposal, which

indicated that it planned to use a pre-engineered building for the FTF.

The contract incorporated Federal Acquisition Regulation (FAR) clauses 52.236-2,

Differing Site Conditions, and 52.243-4, Changes (48 CFR 52.236-2, .243-4). Exhibit 2 at

36, 37. The contract also included clauses appropriate for design-build contracts:

2.1 Project Description: The intent of this project is to provide all

management, labor, equipment and material necessary for design and

construction for a new Fuselage Training Facility. The government will

entertain pre-fabricated buildings. This project includes all related site

preparation and grading, utility relocation, placement, and connections,

installation of government-furnished fuselage, architectural,

telecommunications, electrical, mechanical, plumbing and fire protection

building components and system installations.

1

All exhibits are found in the appeal file, unless otherwise noted.

CBCA 7233

3

Exhibit 5 at 392.

H.14 Design Errors or Deficiencies, Inspection of Existing Work

The Contractor shall be responsible for the professional quality, technical

accuracy, and coordination of all services required under this contract. As

such, it shall be the responsibility of the Contractor to inspect the existing

facility identified in any Task Order and inspect and investigate the “as built

condition” for the preparation of construction documents.

Exhibit 2 at 13.

H.23.2 Schematic Design and Construction Documents

The Contractor shall submit schematic design and construction documents to

the FBI for review and comment at the following levels: 35%, 50%, 90% and

final for comment. The FBI shall have a minimum (14) fourteen calendar-day

period in which to provide comments to the Contractor during each of the

review periods, however, each review period shall not exceed (30) thirty

calendar-days.

Exhibit 2 at 17.

H.31 Responsibility of the Contractor For Design:

(a) The contractor shall be responsible for the professional quality, technical

accuracy, and the coordination of all designs, drawings, specifications, and

other on-construction [sic] services furnished by the Contractor under this

contract. The Contractor shall, without additional compensation, correct or

revise any errors or deficiency in its designs, drawings, specifications, and

other non-construction services and perform any necessary rework or

modifications, including any damage to real or personal property, resulting

from the design error or omission.

Exhibit 2 at 18.

On June 2, 2020, a kick-off meeting was held between the parties. CPS received the

geotechnical study from Building and Earth (its geotechnical subcontractor) on June 25,

2020. Exhibit 9 at 538. CPS tracked what it considered to be design changes and only noted

“TBD” (to be determined) for proposed design or construction changes. Exhibit 41 at 150.

By the fifty-percent design review meeting, the Government had directed several changes,

CBCA 7233

4

including changing the plane fuselage to be housed to the larger Boeing 757. Id. at 123;

Appellant’s Reply at 15. On July 17, 2020, CPS submitted its final design analysis, which

included the proposed work for constructing the FTF, completing all related site preparation

and grading, building the asphalt access road with parking lot, and installing the utility

connections for the building. Exhibit 41 at 76. The Government issued the notice to proceed

with construction on August 31, 2020. Exhibit 30 at 107. On September 3, 2020, CPS

submitted a document seeking an additional $499,545.13 and an extension of forty-five days

for changes in scope and pricing that differed from its proposal. Exhibits 31, 32.

The civil work required by the contract included, but was not limited to, asphalt

paving of the existing gravel road, an asphalt parking lot, a storm drainage system with a bioretention pond, landscaping, and utilities, including power. Exhibit 41 at 76-78. Civil

engineering work began on September 21, 2020. On October 26, 2020 (over a month after

it began work and over three months after it received the geotechnical study), CPS informed

the Government that unsuitable soil conditions were found under the asphalt road that would

result in a change to the contract. Exhibit 8. CPS requested $49,894.79 to complete the road

compaction work recommended by its geotechnical subcontractor. Id. at 450.

On December 3, 2020, CPS presented change order six “in response to changes in

design requirements, scope changes from bid, and overall reconciliation from bid to project

execution,” in the amount of $363,425.54. Exhibit 9 at 461. On December 22, 2020, under

pressure to pay its subcontractors, CPS split change order six into two requests for equitable

adjustment (REAs)—one addressing the civil portion of the proposed extra work (civil work

REA) and the other addressing the heating, ventilating, and air conditioning (HVAC) and the

electrical portion (HVAC/Electrical REA). Exhibits 10, 36. CPS asked the Government to

address the civil work REA first. Exhibit 10.

The civil work REA amounted to $216,953.68. Under the civil work REA, CPS

sought compensation for additional costs for sitework, existing conditions, and changes to

the concrete footings and slab for the foundations as well as costs for overhead, insurance,

and related fees. Exhibit 10 at 689.

On January 26, 2021, the Government presented a proposed modification for the civil

work, offering $151,511 in additional cost and stating that the offer “represents an equitable

amount of risk allocation.” Exhibit 37. On January 29, 2021, CPS responded, elaborating

on the basis for the civil work REA and requesting the full amount of $216,953.68.

Exhibit 35 at 515-16. The Government unilaterally executed modification eight in the

amount of $151,511 on February 10, 2021, stating that this was an “equitable transfer of cost

risk to assist with price increases due to COVID.” Exhibits 11 at 742, 12 at 743.

CBCA 7233

5

Paragraph 4.1.6.2 of the SOW required CPS to “design, provide, and commission a

complete and operable heating, ventilating, and air conditioning (HVAC) system.” Exhibit 5

at 407. The SOW required that the electrical system comply with applicable regulations

cited in the contract and that the system achieve the maximum level of energy efficiency that

was life-cycle cost effective. Id. at 411, 420-21. CPS submitted several RFIs to the

Government to determine the electrical and mechanical requirements of the project but did

not receive responses sufficient to determine what those requirements were. Exhibit 9.

For the HVAC system, CPS proposed the use of one ten-ton unit system. Exhibit 9

at 529. After conducting the life-cycle cost analysis and learning the actual power supply

requirement, CPS realized that its proposed HVAC design was impracticable and altered the

design to include two five-ton HVAC systems. Exhibit 41 at 87. After award, CPS was

informed by the utility company that CPS’s proposed pad-mounted electrical system would

be unacceptable and a pole-mounted transformer was necessary because the power line at the

site was single phase rather than the anticipated three phase. Exhibits 9 at 533, 39.

As previously mentioned, the original REA was spilt into two REAs. For the

HVAC/Electrical REA, CPS requested $185,643.37 for additional costs resulting from

purported HVAC and electrical changes, additional metals associated with the fuselage

cradle, and changes to the general conditions. Exhibit 36. Additional metals were part of

this REA because changes to the fuselage size mandated a larger sized cradle. Exhibit 9 at

467. On February 11, 2021, the Government partially approved the HVAC/Electrical REA

and offered an equitable transfer of cost risk in the amount of $50,342.20 “to assist with price

increases due to COVID” but also noted that this would be offset by the removal of certain

items within CPS’s scope of work and would result in a “zero-sum change.” Exhibit 13. In

the HVAC/Electrical proposed modification, the Government agreed to pay CPS the

requested $13,610.84 for additional metals, $10,957.12 of the requested $33,484 for the

HVAC work, and $25,774.34 of the requested $103,726 for the electrical work. Id.

On February 16, 2021, CPS responded by modifying its HVAC/Electrical REA to

$143,372.73 through reduction of its prices and markups. Exhibit 14 at 759. The

Government denied CPS’s modified REA and then unilaterally issued a modification for the

changes to the HVAC/Electrical work in the amount of $50,342.20 on February 25, 2021.2

Exhibit 15.

CPS submitted a certified claim to the contracting officer on May 12, 2021, seeking

$200,743.85, which is the difference between the amount requested by CPS in the civil work

2

The record does not include the actual modification issued for the

HVAC/Electrical work.

CBCA 7233

6

REA and the HVAC/Electrical REA ($402,597.05) and the amount paid by the Government

through the two unilateral modifications ($201,853.30). Exhibit 38. The contracting officer

responded with a final decision on September 23, 2021, denying CPS’s claim for additional

compensation. Exhibit 1. CPS timely appealed the contracting officer’s final decision on

October 21, 2021.

CPS claims entitlement to compensation for site work completed pursuant to differing

site conditions under FAR 52.236-2 and compensation for constructive changes under FAR

52.243-4. Complaint at 5-6. CPS’s claim is for $149,551.33 and consists of the following:

(1) $65,442.68 for unapproved costs of soil removal and changed conditions; (2) $73,227.38

(voluntarily reduced from the initial amount sought) for electrical and HVAC changes;

(3) $2371.64 for unapproved markups on additional metals; and (4) $8509.63 for unapproved

general conditions changes connected to electrical and HVAC changes. Id. at 4-5.

The Government filed an answer requesting the Board deny CPS’s claim and asserting

that it overpaid CPS. Answer at 8. The Government asked the Board to determine the

amount of the overpayment, making clear it contested both entitlement and quantum, even

though it made partial payment on the REAs that serve as the bases of CPS’s claim. In

response to a Board order, CPS filed its schedule of costs, providing a breakdown of the costs

it sought totaling $149,551.33. The Government filed its response to appellant’s schedule

of costs and brief, again requesting that the Board deny CPS’s claim and order CPS to repay

$173,542.98. Respondent’s Rule 19 Brief at 23. CPS filed its prehearing brief and a reply

to the Government’s brief. The Board held a hearing and ordered post-hearing briefs.

Regarding the Government’s allegations of overpayment, the contracting officer, until

just a few days before the hearing, had not issued a final decision in accordance with section

7103 of the CDA, 41 U.S.C. § 7103 (2018), asserting an affirmative Government claim

demanding the return of money. Prior to the hearing, though, the contracting officer issued

an “addendum” to his earlier September 23, 2021, decision and attempted to assert an

affirmative claim taking back the $201,853.30 previously granted in two unilateral

modifications. Although the “addendum” notified CI Pond of its appeal rights, CI Pond has

not yet appealed that decision to the Board, and it is therefore not properly before the Board.

See id. § 7104 (entitling the contractor, not the Government, to decide whether and where to

appeal a contracting officer’s decision). In fact, appellant affirmatively objected to the

addendum being a part of this appeal, and the Board refused to rule on the allowability of an

addendum at that late stage in these proceedings. As a result, we do not have an affirmative

Government claim before us in this appeal. We leave it to the parties to determine how to

pursue any claim contained in the “addendum,” if appropriate, outside the context of this

appeal.

CBCA 7233

7

Discussion

A.

The De Novo Standard

As we stated in BES Design/Build, LLC v. Department of Veterans Affairs, CBCA

5640, 17-1 BCA ¶ 36,840:

The CDA provides that “(e)ach claim by a contractor against the

[Government] relating to a contract shall be submitted to the contracting

officer for a decision.” 41 U.S.C. § 7103(a)(1) (2012); CompuCraft, Inc. v.

General Services Administration, CBCA 5516, 17- 1 BCA ¶ 36,662, at

178,538. The contracting officer’s final decision need not include specific

findings of fact, but “[i]f made, specific findings are not binding in any

subsequent proceeding.” 41 U.S.C. § 7103(e). On appeal, the Board proceeds

to conduct a de novo review. Id. § 7104(b)(4). “[O]nce an action is brought

following a contracting officer’s final decision, the parties start in court or

before the board with a clean slate.” Wilner v. United States, 24 F.3d 1397,

1402 (Fed. Cir. 1994) (en banc); Regency Construction, Inc. v. Department of

Agriculture, CBCA 3246, et al., 16-1 BCA ¶ 36,468, at 177,706.

Because of the de novo nature of proceedings under the CDA, “the contracting

officer’s [decision] is not to be treated [as] the unappealed determination of a

lower tribunal which is owed special deference or acceptance on appeal.”

Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987).

Accordingly, the fact that the contracting officer made specific findings,

including quantifying costs owed to [contractor], does not bind the agency

once appellant has appealed the final decision.

B.

Design-Build Contracts

We note that this is a design-build contract, which impacts somewhat the risks held

by the design-build contractor, CPS, and the owner, FBI. In a traditional design-bid-build

project, the owner hires the design team, and the contractor builds the design provided to it

by the owner. Under longstanding case law, design-bid-build construction contracts include

an implied warranty by the owner that the plans are accurate and suitable for the owner’s

intended purposes. Spearin v. United States, 248 U.S. 132, 136-37 (1918). Thus, if the plans

and specifications are not accurate or suitable, the owner cannot recover from the general

contractor for damages related to building performance deficiencies. Id. Moreover, an

owner who breaches the Spearin warranty may be liable to the contractor for damages,

including actual costs and delays incurred in rectifying deficiencies so that the building may

be built. Id.

CBCA 7233

8

Under design-build contracts, the design-builder assumes the responsibility of design,

thereby relieving the owner of liability that it would normally have under Spearin. A

properly written and administered design-build contract transfers the risk of design

insufficiency from the owner to the design-builder. The owner is shielded when the design

results in cost overruns or does not work. M.A. Mortenson Co., ASBCA 39978, 93-3 BCA

¶ 26,189. However, if the owner supplies design-related information that is to be

incorporated into the design or used in the bidding process, the owner may be held to have

established an implied warranty regarding that information. Donahue Electric, Inc., VABCA

6618, 03-1 BCA ¶ 32,129 (2002). Here, the Government provided only minimal information

pre-proposal, leaving it up to CPS to design the project within the cost it proposed. While,

as noted in the RFIs, a lack of information may drive the price of a proposal up, it may later

save costs on differing site condition and changes claims.

That this contract was a design-build type adds a twist that places greater liability on

CPS for its proposal. The fact that there were many RFIs in the contract, which the

Government answered with “TBD during design” or simply “TBD,” does not shift the design

responsibility and liability onto the Government. Of course, CPS is entitled to recover

increased costs due to differing site conditions and Government changes but to do that it

bears the burden of proof. See BCPeabody Construction Services, Inc. v. Department of

Veterans Affairs, CBCA 5410, 18-1 BCA ¶ 37,013 (finding that the contractor bears the

burden of proving a differing site condition in a firm-fixed price design-build task order).

CPS costed its proposal fully understanding that it had to design this project within the price

it proposed. If the proposal was faulty, or only provided for ideal conditions, the

responsibility for extra costs does not fall on the Government.

In the contract, the Government was responsible for providing the airplane fuselage

to be housed within the FTF. Exhibit 5 at 391. Under the scope of work defined in the

SOW, CPS was responsible for the design and construction of a fully operational FTF. Id.

Section 3.1 of the SOW, titled “existing conditions,” required the contractor to “verify all

existing conditions prior to any design or construction activities commencing.” Id. at 393.

The SOW placed the responsibility on CPS to provide, among other tasks, all geotechnical

services, including developing and providing an initial boring plan and an initial geophysical

investigation plan, to design and construct all water and sewer improvements, and to

“develop a structural design on accurate, site specific geotechnical information, and

anticipated loads for the building type and geographic location.” Id. at 396, 398, 401.

C.

Differing Site Conditions Claim

It is well known that the purpose of the Differing Site Conditions clause is to

encourage contractors not to inflate their bids to account for issues that may or may not arise.

Tucci & Sons, Inc. v. Department of Transportation, CBCA 4779, 17-1 BCA ¶ 36,599

CBCA 7233

9

(2016). Differing site conditions can arise either as a type I condition, in which the

contractor encounters physical conditions that differ materially from those indicated in the

contract, or as a type II condition, in which the physical condition is unknown, unusual, and

differs materially from those ordinarily encountered. Id.; FAR 52.236-2.

CPS alleges that the geotechnical report and topographical survey results revealed

lower soil bearing capacities than expected and other unanticipated subbase conditions which

added more work to balance the site, resize the storm drain, compact the subbase of the road,

and increase the foundation size for the FTF. CPS argues that it is entitled to recover costs

for a type I differing site condition because (1) the contract implied that contractors would

be entitled to a price adjustment if the information obtained during the surveys conflicted

with their proposal, and (2) the reference building provided by the Government indicated that

the bearing capacity would be sufficient for the use of the same size footing in the new FTF.

Appellant’s Prehearing Brief at 6-8. Alternatively, CPS argues that it is entitled to recover

under a type II differing site condition because the conditions were (1) unknown, as the

Government neither provided any geotechnical or survey information nor allowed contractors

to investigate the site beforehand, and (2) unusual, as the soil conditions differed from the

known conditions at other projects at the site. Id. at 9-10.

The Government argues that CPS is not entitled to compensation under the Differing

Site Conditions clause because (1) CPS cannot meet the burden to show that clay was an

unknown, unanticipated, or unusual condition, and (2) CPS did not properly notify the

Government of the differing site condition before proceeding with the work. Respondent’s

Rule 19 Brief at 25.

The contractor bears the burden to prove a differing site condition by a preponderance

of the evidence. Stuyvesant Dredging Co. v. United States, 834 F.2d 1576, 1581 (Fed. Cir.

1987). To prove a type I differing site condition, the contractor must show that:

(1) “the conditions ‘indicated’ in the contract differ materially from those it

encounter[ed] during performance,” (2) “[t]he conditions encountered must

have been reasonably unforeseeable based on all the information available to

the contractor at the time of bidding,” (3) “it reasonably relied upon its

interpretation of the contract and contract-related documents,” and (4) “it was

damaged as a result of the material variation between the expected and the

encountered conditions.” Regency Construction, Inc. v. Department of

Agriculture, CBCA 3246, et al., 16-1 BCA ¶ 36,468 (quoting Stuyvesant

Dredging Co. v. United States, 834 F.2d 1576, 1581 (Fed. Cir. 1987) (citations

omitted)).

CBCA 7233

10

Ahtna Construction & Primary Products Co. v. Department of Agriculture, CBCA 6892,

21-1 BCA ¶ 37,777 (finding that the contractor did not meet the burden of proving a type I

differing site condition claim when the contract made no representations as to the subsurface

conditions of the site).

To prove a type II differing site condition, the contractor must show that the unknown

physical condition was “one that could not be reasonably anticipated by the contractor from

his study of the contract documents, his inspection of the site, and his general experience[,]

if any, as a contractor in the area.” Randa/Madison Joint Venture III v. Dahlberg, 239 F.3d

1264, 1276 (Fed. Cir. 2001) (quoting Perini Corp. v. United States, 381 F.2d 403, 410 (Ct.

Cl. 1967)).

Item one: Site earthwork and grading access road to create a balanced site

CPS seeks $20,737.50 for additional work to balance and haul off soil and $2489.50

to strip and stockpile soil. Appellant’s Schedule of Costs at 3; Appellant’s Reply at 2. CPS

fails to establish a type I or type II differing site condition with respect to the soil grading and

haul-off work. CPS argues that, at the time of its proposal, there was no topographical

survey or information to know the exact grades of the site and no opportunity to perform a

takeoff analysis to determine if the site was balanced. Appellant’s Post-Hearing Brief at 12;

Appellant’s Reply at 11. After receiving the results from the topographic survey, CPS had

to move more soil than it expected and haul it off to balance the site. Appellant’s Schedule

of Costs at 3. The contract does not provide any indicators as to the topography of the site.

Instead, as part of the design-build nature of the agreement, the contract directed the

contractor to perform a topographic study to determine the conditions of the site.

Furthermore, CPS has not shown how the different topography is an unusual or unknown

condition. CPS’s claim for additional costs to balance the site and haul off soil is denied.

Item two: Storm drain system

CPS seeks $13,248.10 for additional work for the storm drain system when the size

of the bio-retention pond increased and the topographic survey revealed a steeper site than

CPS anticipated. Appellant’s Schedule of Costs at 2. CPS asserts that a survey and

measurements were unavailable to predict the quantities of soil at the site or account for the

quantities of storm water flowing onto the site. Appellant’s Reply at 11. Similar to the

reasoning for the site earthwork claim, the Board finds that CPS has not shown how there

were changes in what CPS anticipated for the topography that amounted to a type I or type

II differing site condition, and this portion of the claim is denied.

CBCA 7233

11

Item three: Asphalt paving for the road

CPS seeks $62,530.20 for additional costs to compact and pave the asphalt road. CPS

fails to prove that the road’s subbase either differed from what the contract indicated or was

an unknown physical condition. Appellant’s Schedule of Costs at 1. CPS argues that the

Government’s acceptance of its proposal to add a 1.5-inch asphalt topper to the existing

gravel road was a representation that the road was properly compacted. Appellant’s Closing

Brief at 8. CPS failed to show, by a preponderance of the evidence, that the condition could

not be reasonably anticipated by CPS from its study of the contract documents, inspection

of the site, and its general experience as a contractor. At the hearing, CPS’s witness

unconvincingly testified that CPS assumed the road’s subbase was properly compacted

because it was within a Government facility and appeared to be built to some standard.

CPS’s claim for asphalt paving is denied.

Item four: Footing and slabs, including anchor bolts

CPS relied upon the information provided by the Government about a comparable

structure at the site to determine the design for the FTF footings. Appellant’s Closing Brief

at 9-10. The geotechnical report revealed that the lower soil bearing capacity and changes

to the size of the building necessitated wider footings. Id. at 10. The Board is not convinced

that the soil bearing capacities encountered at the site were unusual or differed from the

contractor’s general experience. Instead, the Board finds that the need for wider footings was

largely a result of the constructive change to the size and weight of the building rather than

a differing site condition represented by the drawings. Therefore, the Board will analyze the

claim for footings, slab, and anchor bolts as a claim for a constructive change.

Item five: Bollards

The Government conceded that CPS is entitled to $1545 for the cost for bollards, as

those were additional items requested by the Government. Respondent’s Response to

Schedule of Costs at 3.

Item six: Silt fence, site fencing, stripping, and the use of an out-of-town crew

CPS requests entitlement for additional costs incurred in the amount of $57,446.59

for a silt fence, site fencing, stripping, and use of an out-of-town crew. Appellant’s Schedule

of Costs at 3. CPS has not proven entitlement for the additional costs incurred for the silt

fence, site fencing, stripping of topsoil, or out-of-town crew. The Board denies these costs

and finds that they were to be borne by the contractor as part of the fixed-price contract.

CBCA 7233

D.

12

Constructive Change Claim

CPS claims entitlement to additional costs incurred when the FBI changed the

parameters of the project by increasing the size of the fuselage to be placed in the building.

Appellant’s Prehearing Brief at 13. CPS argues that its proposal met the contract

requirements, the changes were for items in excess of the minimum contract requirements,

and added additional requirements than what was anticipated by CPS in its proposal. Id. The

Government asserts that, under the contract, CPS is responsible for designing and

constructing a complete HVAC and electrical system for the fuselage facility. Respondent’s

Rule 19 Brief at 20-21. The Government alleges that any changes to the design were within

the scope of the contract and CPS’s purview. Id. at 22.

“A constructive change occurs where a contractor performs work beyond the

contract requirements without a formal order, either by an informal order or

due to the fault of the Government.” International Data Products Corp. v.

United States, 492 F.3d 1317, 1325 (Fed. Cir. 2007). To recover on a

constructive change claim, a contractor must show that (1) it performed work

beyond the contract requirements and (2) the Government ordered—expressly

or implicitly—the contractor to perform the additional work. Bell/Heery v.

United States, 106 Fed. Cl. 300, 313 (2012), aff’d, 739 F.3d 1324 (Fed. Cir.

2014); IAP World Services, Inc. [v. Department of the Treasury, CBCA 2633,

12-2 BCA ¶ 35,119]. A contractor cannot invoke a claim for constructive

change against the Government unless the Government “effect[s] an alteration

in the work to be performed.” Bell/Heery, 739 F.3d at 1335.

Pernix Serka Joint Venture v. Department of State, CBCA 5683, 20-1 BCA ¶ 37,589.

Item one: Additional metals

CPS based its design for the fuselage cradle and the overall size and weight of the

building on the Government’s direction that the FTF would house a fuselage the size of a

Boeing 737. Exhibit 9 at 475; Appellant’s Prehearing Brief at 16. During design, the

Government changed the size of the fuselage to be housed to the larger Boeing 757.

Exhibit 41 at 123; Appellant’s Prehearing Brief at 16. CPS used more metal than anticipated

to build an adequate cradle for the larger fuselage. Appellant’s Prehearing Brief at 16. The

Government agreed that this was a constructive change and conceded the metal costs for the

fuselage cradle in the amount of $13,610.84. Respondent’s Response to Appellant’s

Schedule of Costs at 4.

CBCA 7233

13

Item two: Footing and slabs, including anchor bolts

While CPS alleges that the changes to the footing and slab were due to a differing site

condition, the Board instead finds that the changes were largely a result of the increase in

building height and weight caused by the change in fuselage size. The Board is convinced

by CPS’s testimony that the increased height and weight of the building had an effect on the

bearing capacity of the soil. While it is unclear if the soil bearing capacity was a differing

site condition, it is reasonable to find that the heavier building would affect the foundation

and stability of the building. Therefore, the Board finds that CPS is entitled to the incurred

costs of increasing the size of the building’s footings, including the costs for the anchor bolts.

CPS’s claim for $23,720.50 for the footings and slab and $880.50 for the anchor bolts is

granted.

Item three: HVAC system

CPS asserts that its proposal to use a ten-ton unit HVAC system for the fuselage was

within the contract requirements. Government-ordered changes to the size of the fuselage

increased the height of the building, which changed multiple engineering calculations

including the volume of air to be handled by the HVAC system. In addition, after conducting

a life cycle cost analysis and learning of the correct incoming power supply, CPS had to

change from the ten-ton unit to two five-ton units. Appellant’s Schedule of Costs at 6;

Appellant’s Prehearing Brief at 16-18. CPS, in its closing brief, adjusted the total HVAC

claim to $13,885. Appellant’s Closing Brief at 16. The Board finds that CPS is entitled to

the total HVAC claim as a result of constructive changes caused by changes to the building

height and the power supply. CPS’s claim for $13,885 is granted.

Item four: Electrical, including transformer in lieu of service panel

At the time of the contract, CPS did not know what power was available at the site and

assumed, based on CPS’s general knowledge of commercial buildings, that the building had

a three-phase power supply. Appellant’s Reply at 17. Based on that assumption, CPS

determined that a pad-mounted transformer would be sufficient to power the building and

comply with the electrical design standards. Id.; see Appellant’s Prehearing Brief at 18;

Appellant’s Post-Hearing Brief at 17. CPS alleges that, after award, the utility company

provided the power requirements for the building, which was a single-phase power supply

and required a pole-mounted transformer. Appellant’s Prehearing Brief at 18; Appellant’s

Reply at 17. CPS also argues that the Government requested additional outlets for the

fuselage building, which, combined with the changes in the HVAC system, necessitated

additional power distribution. Appellant’s Schedule of Costs at 7. The Board agrees with

CPS that these changes were a result of the Government ordering CPS to house a larger

CBCA 7233

14

fuselage as well as its request for additional power outlets. CPS is entitled to its full

electrical claim of $70,420.

Item five: Security lighting

The Government agreed with CPS’s claim for $9342 for security lighting requested

by the Government after award. Respondent’s Response to Appellant’s Schedule of Costs

at 6.

E.

Claim for General Conditions, Overhead, Fee, Insurance, and Bond Premium

The Government agreed to pay CPS $115.88 for overhead and $124.57 for insurance

and bond premiums for the civil claim. Respondent’s Response to Appellant’s Schedule of

Costs at 4. For overhead, fee, insurance, and bond claims for the fuselage support, the

Government agreed to pay a total of $2118.18. Id. at 4-5. As a result of increased work

under the electrical and security lighting claim, the Government agreed to pay $700.65 for

incurred overhead and fee and $753.20 for increased insurance and bond premium. Id. at 7.

The remaining portion of CPS’s claim for general conditions, additional overhead, fee,

insurance, and bond premium is denied.

Decision

The appeal is GRANTED IN PART. The Board finds that CPS is entitled to

$108,906 for the additional costs associated with the transformer, HVAC, footings, slab, and

anchor bolts. In addition, the Government conceded $28,310.32 which includes $1545 for

the bollards, $13,610.84 for the fuselage support, $9342 for the security lighting, and

$3812.48 for related overhead, fees, insurance, and bond premiums. In total, CPS is entitled

to $137,216.32.

Patricia J. Sheridan

PATRICIA J. SHERIDAN

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.