GRANTED: March 17, 2011
Agency decision
Ask Donna
What actually matters in this document.
Text
GRANTED: March 17, 2011
CBCA 1966
SINGLETON ENTERPRISES-GMT MECHANICAL
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Wayne Singleton, Joint Venture Partner of Singleton Enterprises-GMT Mechanical,
Luthersville, GA, appearing for Appellant.
Lisa M. Clark, Office of the Regional Counsel, Department of Veterans Affairs,
Brecksville, OH, counsel for Respondent.
Before Board Judges BORWICK and POLLACK.
POLLACK, Board Judge.
This appeal arises out of contract no. VA541-C-0089, between Singleton EnterprisesGMT Mechanical, a Joint Venture (JV or appellant), and the Department of Veterans Affairs
(VA) for replacement of approximately 36,000 square feet of polyisobutylene (PIB) roof on
the second floor of a building at the VA Medical Center, Wade Park, Ohio, along with new
underlying insulation, associated masonry, carpentry, and other items. Supplemental Appeal
File , Exhibit 1; Transcript at 83, 117, 119. This case centers on contract provisions dealing
with the placement of new insulation on the roof deck (using asphalt), and how that related
to the contract’s requirement for a twenty-year manufacturer warranty on the PIB roof being
installed.
CBCA 1966
2
A hearing on this appeal was held on November 9, 2010, in Cleveland, Ohio. Each
party provided testimony from various witnesses. Appellant, however, provided only one
affirmative witness, Mr. Wayne Singleton, and thus when testimony of appellant is
referenced below, it refers to his testimony. The VA appeal file was divided into sections;
however, it was not otherwise tabbed or numbered. Appellant provided a tabbed
supplemental appeal file, which included most of the documents in the VA file. Because the
supplemental appeal file has been numbered, we use it as the primary citation source in this
decision. Additionally, the parties provided limited documents at the hearing. The Board
here issues a two-judge decision, as appellant elected the Board’s accelerated procedure.
Rule 53 (48 CFR 6101.53 (2010)).
Facts
The contract called for appellant to place layers of insulation on the roof deck and to
attach to that insulation a new PIB roof (PIB membrane). The roofing membrane was to be
attached to the insulation by means of specified proprietary adhesives manufactured by
Republic Powdered Metals, Inc. (RPM). Supplemental Appeal File, Exhibit 1; Appeal File,
sec. 4. While not stated in the specifications, the testimony of various VA witnesses makes
it clear that the VA wrote the PIB roofing specification for this contract around RPM’s PIB
product. Supplemental Appeal File, Exhibit 1; Transcript at 9, 119, 225, 246, 327. There
was no evidence, however, that the insulation provisions of the contract were written around
any particular manufacturer’s product.
Appellant submitted a bid of $777,020. The VA opened bids on September 28, 2007,
and awarded the contract on October 12, 2007. The contract initially called for five months
to complete from the date of award. That was later changed at the time of notice to proceed
(NTP) to 180 days. Supplemental Appeal File, Exhibit 1, 3; Transcript at 42.
Section 07220, Roof and Deck Insulation (eight pages) set out the requirements for
providing and installing new insulation on the project. It clearly addressed using asphalt for
adhering insulation to the existing concrete roof deck. It detailed the type (grade) of asphalt
to be used, as well as included details such as heating temperatures and coverage rates for
application of the material. Nothing in the section made reference to the use of adhesive as
the means for adhering insulation to the roof and deck. Supplemental Appeal File,
Exhibit 20.
Section 07531, Elastomeric Sheet Roofing Polyisobutylene Tear Off And
Replacement, which ran eighteen pages and contained parts of two separate roofing
specifications, addressed the tearing off of the existing roof and replacement with a new PIB
membrane which was to be attached to the new insulation by means of RPM adhesives.
CBCA 1966
3
Portions of section 07531 were confusing and could only be explained as a mistake. Appeal
File, sec. 4; Transcript at 206-08, 231. For example, as set out below, the roofing
specification had two warranty paragraphs, rather than one. While there were differences in
the two warranty specifications, each called for a twenty-year warranty and thus the
duplication does not materially affect our analysis in this appeal. The following provisions
from section 07531 are relevant to the claim. We list the warranty provisions in the order
they appeared in the specification.
1.10 WARRANTY
A. Provide manufacturers standard twenty (20) year warranty covering
materials and labor. Must be 100 mil. Polyisobutylene membrane adhered
with GEOTAC or GEOBOND Adhesive.
1.6 WARRANTY
Roofing work subject to the terms of the Article “Warranty of Construction”
of Section, General Conditions, except extend the warranty period to twenty
years.
3.03 ROOF INSULATION.
A. Apply insulation neatly fitted to penetrations, projections, and nailers.
Install tapered or feathered insulation around roof drains in such a way as to
provide proper slope (maximum 3: 12 pitch) for drainage.
B.
Adhere insulation with Manufacturers Insulation Adhesive, or
mechanically fasten per manufacturers recommendations.
Paragraph 3.03, above, although in the roofing specification, addressed the placement
of insulation. It was clear from the testimony of various VA witnesses that the VA wanted
insulation attached by adhesive (as set out in Paragraph 3.03) and the VA had not meant to
include asphalt as either the preferred method or an option. Transcript at 183-93, 222, 327.
However, nothing in the specifications conveyed that intention or even suggested that
asphalt could not be used. The VA’s best explanation as to how the two methods were to be
treated was from Mr. Edward Hazel, current chief of construction at the VAMC. He
described asphalt and adhesive as alternatives and also said that while asphalt was provided
in the specification, the Government did not intend or imply that appellant had to use asphalt.
Transcript at 117, 120, 180-81.
CBCA 1966
4
There is no dispute between the parties as to appellant’s responsibility for providing
a twenty-year roof warranty. However, as addressed below, the central dispute in this case
turns on how the use of asphalt meshed with appellant’s ability to secure that warranty.
Although the VA did not name a roof membrane supplier, the VA wrote the PIB
roofing specification around use of the RPM PIB roof. The VA did specify the RPM
adhesive in section 07531. Further, although RPM was not specified as the sole source for
the roof membrane, the VA wanted that product on this project. As noted by Mr. Brian Rice,
the contracting officer’s technical representative (COTR), had a contractor on this project
come in with a different roof (non-RPM), the VA would have probably disapproved it.
Transcript at 225, 246, 327. The VA had used RPM roofs at this facility for ten to fifteen
years and had approximately fourteen roofing areas with the RPM PIB roofing product.
Supplemental Appeal File, Exhibit 10-11; Transcript at 222-23. Mr. Rice explained the VA
had a policy at the facility to standardize, so it would not have to deal with ten different
roofing companies or ten different processes. Transcript at 327.
The VA held a pre-bid conference. Appellant did not attend; however, Gire Roofing
Construction (Gire), the firm appellant used for the roofing work, attended, as did another
potential subcontractor, Warren Roofing & Insulation Co. (Warren). Warren was a local
contractor with prior experience at the site. Gire was from Illinois, and there was no
evidence it had previously worked on the facility. Supplemental Appeal File, Exhibit 10-12;
Transcript at 196. Mr. Nick Carrozza, a VA engineer, and Mr. Rice represented the VA.
Supplemental Appeal File, Exhibit 22; Transcript at 94-95, 254, 323-26. Neither VA
official, however, addressed specifics as to roofing at the meeting. Instead, that was handled
by Tom Dornbrook, sales representative for RPM. On roofing matters, it appeared that the
VA had essentially turned its program over to Mr. Dornbrook. In a 2008 memo, where the
VA was seeking some advice on this claim from the Corps of Engineers, Mr. Hazel referred
the recipient to Mr. Dornbrook for details and described Mr. Dornbrook as “the VA’s main
contact for the roofing materials system in use for the entire hospital.” Supplemental Appeal
File, Exhibit 34. Under questioning from the VA counsel, Mr. Dornbrook confirmed that on
this project, he assisted as a consultant to the VA. Transcript at 236.
Mr. Dornbrook testified as to what he said at the pre-bid conference. He confirmed
that his presentation essentially focused on the RPM product and its requirements. He did
not address the use of asphalt during the meeting, and stated that at the time of the pre-bid
conference, he was in fact unaware that the VA even had provided an asphalt specification
in its contract. He acknowledged he did not say anything involving the operation of the RPM
warranty and use of asphalt, nor did he say that the use of asphalt would void the warranty.
At the close of the meeting he provided the attendees with an RPM material sheet. The sheet
CBCA 1966
5
was not later distributed by the VA to other potential bidders. Transcript at 236, 245, 255-56,
262, 265-66.
Appellant received three to four bids on roofing, including bids from Gire and
Warren. Gire provided a single price, based on seating the insulation in asphalt. Transcript
at 11-12. Warren provided two prices. The first was a primary price of $645,000 (based on
providing adhesive to attach insulation). The second specified a $50,000 deduct to the first
price if asphalt was used. Warren appended the following note to its bid: “For Asphalt as the
insulation adhesive, DEDUCT: $50,000. Asphalt is specified as the insulation adhesive but
in (sic) not compatible with warranty requirements.” Supplemental Appeal File, Exhibit 9.
Warren’s bid was based on using the RPM roof, and its comments as to the warranty
referred to that product. Supplemental Appeal File, Exhibit 9. After appellant received
Warren’s bid, it attempted to contact the VA for clarification, but was unsuccessful. It then
proceeded to provide its bid, relying on its understanding that the specifications clearly
provided for the use of asphalt and relying upon Gire’s pricing, which was based on asphalt.
Transcript at 12, 42, 333. Because appellant had utilized RPM’s price for the roof
membrane, appellant planned on using the RPM roof on top of the new insulation. While
RPM was local, there were other manufacturers that could furnish a PIB roof. Insulation was
not being provided by RPM. Transcript at 17, 26. The firm, quoting asphalt to appellant,
verbally agreed to keep its price firm for ninety days from bid. Supplemental Appeal File,
Exhibit 12; Transcript at 18-19, 45.
When asked to explain how it reconciled bidding with the note in Warren’s bid as to
the warranty, appellant stated it relied on the fact that the specifications called for the use of
asphalt and further that it saw nothing in the specifications that led it to believe that RPM
would not accept asphalt for attaching insulation, or that asphalt would void an RPM
warranty. Essentially, appellant was stating that because the specifications were explicit as
to the suitability of asphalt, there was no reason to assume a connection between how the
insulation was being connected and the roofing membrane warranty. At the time of bid,
appellant believed that the warranty could be issued. Appellant also pointed out that
Warren’s letter related solely to RPM and that Gire’s bid contained no similar qualification
or concern as to the use of asphalt. Supplemental Appeal File, Exhibit 24; Transcript at 331
37.
After award, appellant proceeded with gathering information for submittals from
RPM. During that process, appellant was advised, either directly by Mr. Dornbrook or
through Gire, that RPM would not provide a twenty-year warranty unless insulation was laid
with adhesive. Appellant testified that this was the first it knew of the problem; however,
as noted above, Warren had warned of a possible problem in its bid. Transcript at 13-14.
CBCA 1966
6
Based on what it had learned from RPM as to the warranty, appellant provided a letter, dated
November 27, 2007, to the VA along with an asphalt submission. The letter advised the VA
that RPM had said that the use of asphalt was not compatible with the RPM warranty and
appellant would have to use adhesive. Appellant advised that adhesive would be more costly.
Supplemental Appeal File, Exhibit 21; Transcript at 14.
The VA did not respond, so on December 28, 2007, appellant sent a letter seeking a
decision on the submittal. Appeal File, sec. 3. At this time, appellant was in contact with
Mr. Dornbrook as to the roofing materials. From those contacts and conversations it became
obvious to appellant that it was going to have to use adhesive for the insulation and do that
regardless of whether the Government issued a formal change order or not. Appellant
testified that after several discussions with Mr. Dornbrook, it was evident that the PIB roof
was to be supplied using RPM materials and Mr. Dornbrook “was calling the shots.”
Appellant characterized the use of RPM for the roofing material as essentially cast in
concrete. With that in mind, appellant, even without a change order, took steps to secure
adhesive so as to protect the price. Accordingly, Gire ordered 200 pails of insulation
adhesive from Dornbrook Marketing LTD on January 11, 2008. Notice to proceed (NTP)
was finally issued by the VA on January 14, 2008. Supplemental Appeal File, Exhibit 13;
Transcript at 15, 18, 55, 276.
The COTR explained the VA’s failure to respond, saying that the VA could not reject
a submittal until there was a NTP. Transcript at 100. The VA, however, did begin an
internal analysis. In his January 4, 2008, memo to engineering, the contracting officer (CO)
stated, “The specifications called for asphalt as the adhesive for insulation, but the
manufacturer may not honor the warranty using asphalt, according to the contractor.”
Supplemental Appeal File, Exhibit 5; Transcript at 14, 42.
On February 12, 2008, the VA rejected appellant’s submittal and provided under
Remarks, “Revise and resubmit in accordance with design bulletin No. 1.” Three days later,
the VA issued Bulletin No. 1, which provided: “The adhesive to be used to secure the roofing
insulation shall be RPM Insulation Primer and RPM Insulation Adhesive as manufactured
by Republic Metals, Inc. Asphalt shall not be used to secure insulation to the roof deck.”
Supplemental Appeal File, Exhibit 23. Mr. Hazel described the bulletin as a clarification and
not a contract modification. He said it addressed an ambiguity in the specifications.
Transcript at 181-82. Pursuant to the direction, appellant provided a new submittal noting
that the use of adhesive was based on the Government’s direction. Supplemental Appeal
File, Exhibit 24.
On March 13, 2008, the VA asked appellant for a proposal to delete a segment of
construction services in the southwest corner of the roofing project. This is relevant to the
CBCA 1966
7
claim, in that it reduced the square footage to be replaced. After negotiation, the parties
agreed that appellant would provide a credit for the deleted work. The VA has asserted that
the claim must be adjusted for the reduced area. Appellant has contended otherwise, pointing
out that in the modification, appellant gave the VA a credit based on the use of adhesive
instead of asphalt as planned. Supplemental Appeal File, Exhibit 28-32; Transcript at 103.
Appellant in this claim seeks to recoup the difference between what it provided in the credit
for adhesive and what that credit would have been if it had been based on asphalt.
On April 22, 2008, appellant submitted what it designated as its claim and change
order proposal, seeking $56,004 for changing the originally specified asphalt to RPM
insulation adhesive. The claim included a breakdown for subcontractor costs (Gire) of
$47,774. The remainder of the claim sought markups for the prime of 7.5% for overhead,
7.5% for profit, and 1.44% for bond. The subcontractor costs were broken down as follows:
Delete Asphalt
Delete Asphalt Labor
5-Gallon Pails Adhesive
Labor for Pails of Adhesive
7.5% overhead
1.5%(sic) profit
Total
14 Ton @ $500
14 Ton @ $ 90
200 EA @ $216
200 EA @ $ 32
($ 7,000)
( 1,260)
43,200
6,400
41,340
3,101
44,441
3,333
47,774
The 1.5% for subcontractor profit was intended to be 7.5%. Supplemental Appeal File,
Exhibit 6.
Although not provided to the VA in April 2008, appellant provided at the hearing a
further breakdown from Gire, dated April 25, 2008. It includes comparative labor prices for
asphalt and adhesive and shows 1344.75 manhours @ $46.55 per manhour for a total of
$62,598 for installing insulation with adhesive; and 1207.25 manhours @ $46.55 per manhour
for a total of $56,198 for installing insulation with asphalt. Supplemental Appeal File,
Exhibits 12, 29; Transcript at 58-59, 103, 106-07.
On May 7, 2008, Mr. Rice authored an estimate comparing the costs for using asphalt
versus adhesive based on 844.70 squares of roof insulation (versus 899 squares used by
appellant). His estimate provided no breakdown as to labor or material, but rather set out an
estimated combined cost of $56.67 per square for labor and material for laying insulation in
CBCA 1966
8
asphalt, and $43.22 per square for laying it with adhesive. He concluded the VA was entitled
to a net credit of $11,905.92. Supplemental Appeal File, Exhibit 36; Transcript at 65-66. The
numbers he used in the estimate were figures he secured from Mr. Dornbrook, who in turn had
secured the information from contractors he had contacted. Supplemental Appeal File,
Exhibit 36-37; Transcript at 87-88. There was no background information as to what
information was provided to the sources, and Mr. Rice under questioning stated that he did
not have any work papers with him. It appeared he had not reviewed any work papers prior
to the hearing. Transcript at 207-08. At some point, the VA tweaked its numbers and in a
June 12, 2009, memo increased the cost of the asphalt work to $57.87 per square. The change
was never addressed nor explained. Supplemental Appeal File, Exhibit 41.
On May 27, 2008, the VA and appellant spoke by telephone regarding appellant’s
costs, with VA advising that it needed more justification for appellant’s numbers. Transcript
at 296. On the same date, appellant wrote two letters to the contracting officer (CO). The
first, referencing the earlier conversation as to costs, addressed seven cost issues. Among
those were explanations as to how appellant arrived at square footage, appellant’s labor cost
differences, and how appellant arrived at the asphalt credit. In the letter, appellant stated that
by that point, asphalt cost was approaching $700 a ton, as compared to the $484 a ton it had
bid. Supplemental Appeal File, Exhibit 17. In the second letter, appellant stated the
following, “Unless directed otherwise in writing from the Contracting Officer, we are going
to proceed with changing the application material from asphalt to adhesive and consider it to
be a constructive change order coming from the Contracting Officer.” Supplemental Appeal
File at 18. As of May 27, work had not yet begun on the roof. Roofing commenced some
time in June or July.
The VA provided no response to either of the two letters. It did continue to review the
claim, focusing on pricing and still contending that using adhesive was cheaper. On
November 6, 2008, Mr. David Sabel, chief of engineering, provided a memorandum to the
acting CO. The memo affirmed confidence in Mr. Rice’s estimate, stating that it had been
provided to the VA from the roofing supplier (RPM), and further addressing alleged flaws in
appellant’s cost breakdown. Mr. Sabel claimed (1) appellant used the wrong size for the roof
(896 squares versus 844 squares), (2) used too low a cost per ton ($487) for asphalt, since it
based its figure on a September 2007 date (before asphalt increases in the summer of 2008),
and (3) asserted that appellant failed to include costs such as transport, maintenance, and
delivery of hot asphalt to the roof in its comparison of costs. In his memo, Mr. Sabel provided
no dollar figure for any of the purported omitted items; he similarly provided no figures at
trial. Finally, the memo said engineering had confirmed its costing through a contact person
with the Corps of Engineers (who got her information through a subconsultant) and that the
Corps concluded that there should be little difference in price between the two processes, with
any cost increase for adhesive being be offset by reduced labor costs in placing adhesive in
lieu of asphalt. Supplemental Appeal File, Exhibit 39.
CBCA 1966
9
On February 1, 2009, appellant asked for a final CO decision. Again it received no
reply. On June 12, 2009, Mr. Sabel authored another internal memorandum that in general
tracked the prior one. Supplemental Appeal File, Exhibit 41. Still having received no reply,
appellant filed its appeal with the Board on a deemed denial basis. Transcript at 32-33.
In order to resolve this dispute we must determine (1) whether a twenty-year PIB roof
was available from a manufacturer other than RPM and (2) whether a twenty-year warranty
could be secured if insulation was placed in asphalt. Mr. Dornbrook said he knew of at least
two RPM competitors that could have bid the project to provide the roof membrane. He
additionally confirmed that in some instances RPM had allowed use of asphalt and honored
warranties with asphalt. Transcript at 247-52. Mr. Sabel testified that he understood that
RPM installed material with asphalt and he further acknowledged that the use of asphalt was
an accepted method in certain situations. Transcript at 224. He also confirmed that there
were “a few manufacturers that provided” a PIB system. He also testified that he assumed
that there was another manufacturer that could have provided the roof with a warranty, stating,
“My assumption is that if it’s a method that’s accepted, that there is a warranty available to
install appropriately.” Transcript at 225-27. Finally, he testified that it was his understanding
that if a contractor installed insulation with asphalt, and installed the appropriate security
devices around it, “that would have a warranty to it.” Transcript at 224-25.
As noted earlier, Mr. Rice’s estimate provided that the combined labor and material
costs for adhesive should be $43.22 per square. When that figure is multiplied by 844
squares, claimed by the VA, the result is $36,477.68. Adhesive comes in five gallon pails,
which on this project cost $216 a pail. Each square requires a gallon of adhesive.
Accordingly, using the VA number of 844 squares, one would need 169 pails. When 169
pails are multiplied by the cost per pail, the total comes to $36,504 for material only. If we
use what was purchased on the project (200 pails), the number increases to $43,200. In each
instance, the cost of materials alone exceeds Mr. Rice’s price for materials as well as labor.
Multiplying the VA cost of $56.67 a square for asphalt by 844 squares, the result is $47,830
for both labor and material to lay insulation in asphalt. Even if we were to assume the cost
of asphalt at $1000 a ton (a number we do not find valid, but use for ease of calculation), the
difference (between $47,830 less $14,000 (for 14 tons)) would leave $33,830 for labor costs
to place insulation in asphalt. Obviously, the comparisons make no sense. Mr. Rice’s
calculation (once one accounts for material) yields no labor costs for adhesive, but labor of
$33,830 for asphalt. Additionally, since the VA provided no breakdown for Mr. Rice’s
numbers, his estimate is impossible to analyze. Finally, Gire’s labor breakdown shows total
labor costs of $56,000 for asphalt and $62,500 for adhesive. Supplemental Appeal File,
Exhibit 12, 36-37.
At the hearing, appellant provided further confirmation as to its costs. It could not
provide a written quote for asphalt on this job, because it had proceeded on a verbal quote.
CBCA 1966
10
It did, however, provide an August 2007 pricing proposal on another project, where prices
ranged from $415 to $450 a ton. Supplemental Appeal File, Exhibit 7; Transcript at 45.
Appellant also provided an excerpt from R.S. Means Building Construction Cost Data (65 th
ed. 2007) (Means). The excerpt showed comparative costs for using asphalt and adhesive
with roofing (it had no insulation listing). The comparisons showed labor of $44.50 per
square for adhesive, versus $33 for asphalt, an approximate 35% difference. Supplemental
Appeal File, Exhibit 42; Transcript at 211-14. That compares to an 11% difference in Gire’s
labor estimate. Supplemental Appeal File, Exhibit 12; Transcript at 211-12 . Finally, and a
further buttress to appellant’s labor claim, Mr. Sabel in his testimony referred to “Means”
several times as a valid industry source. Transcript at 206-08. His attempts to backtrack on
that were unconvincing.
As a final point, one of the VA bases for claiming that the credit for asphalt material
was understated by appellant, is that the appellant should have used the prices in effect for the
summer of 2008 and further (particularly of concern to Mr. Hazel), that the appellant was not
comparing like periods, since appellant was using a September 2007 date for asphalt and an
April 2008 date for adhesive. Transcript at 139-40, 145-46. The record shows, however, that
adhesive at $216 a pail was ordered in early January 2008, and the September 2007 price
(while quoted at that time) was firm until late December. Thus, appellant compared prices
for similar time frames. Supplemental Appeal File, Exhibit 13; Transcript at 18-19.
After the hearing, each party filed a brief. The VA brief consisted of two pages and
listed four conclusory positions with two record cites and no legal analysis. The VA points
were that appellant’s claim was overstated, that appellant knew at bid time that adhesive was
required, that appellant failed to properly seek clarification, and finally, that appellant did not
follow proper procedures in submitting its claim. As an aid to the Board in assessing the
procedural defense, the VA provided, as one of its record cites, pages 31 to 78 of the contract.
Discussion
When all is said and done, this case turns on the fact that in February 2008, the VA
changed appellant’s method of performance by first rejecting appellant’s submittal calling for
the use of asphalt to secure insulation to the existing roof; and then coupled that with issuing
what the VA called a design bulletin. That design bulletin required appellant to use an RPM
adhesive product to secure insulation to the roof, instead of asphalt, as appellant had bid.
The contract clearly specified that asphalt could be used to attach new insulation to the
existing roof deck. In fact, asphalt was the only material mentioned in the section of the
contract specifically addressing insulation. While we recognize that the contract’s PIB
roofing specification also contained limited provisions that addressed using adhesive to attach
insulation to the roof deck, that limited treatment, at best, permitted an alternative means of
CBCA 1966
11
performance to the asphalt. The roofing provision’s limited inclusion of directions for use of
adhesive (to attach insulation) in no way negated appellant’s right to set its insulation in
asphalt, as set forth in the insulation specification. There was no patent ambiguity in the
contract created by the two performance methods. The methods could be harmonized.
Accordingly, in forbidding appellant from using asphalt and in directing it to use adhesive,
the VA imposed a method of performance that appellant was not contractually required to
provide.
However, to resolve this dispute, we need to address additional facts. In addition to
identifying means of adhering the insulation to the roof deck, the contract also required that
the contractor provide the VA with a twenty-year manufacturer’s warranty for the PIB roof
it would install on top of the insulation. At least on this particular contract, RPM (the
manufacturer around whose products the VA wrote the roofing specifications) would not
provide a twenty-year warranty with its roofing product, unless adhesive was used to secure
the insulation below (which RPM was not providing). It would not provide the warranty if
insulation was set in an asphalt base. That was the case, even though the VA did not appear
to know at the time it prepared the specifications, or at the time of contract award, that RPM
would impose such a condition on its warranty.
In pricing this project, the record shows that appellant anticipated using asphalt for
securing the insulation and anticipated using the PIB roofing membrane as manufactured by
RPM. RPM had been providing roofs at the facility, and that fact was highlighted at the prebid conference, well established on the facility, and a logical choice for contractors to bid.
It was implicit that the VA wanted and was familiar with an RPM roof, and logical that VA
specifications would reflect that familiarity and not conflict with RPM requirements.
Additionally, we find that despite the fact that RPM was not specified as a sole source, it was
highly likely that it’s the only roofing product the VA would have accepted for this project.
Further, while the VA included asphalt as a means of attaching insulation, the VA clearly did
not want that product and likely would never have allowed it. That said, the VA not only
included, but also highlighted asphalt in its specifications as the means for setting insulation.
Mr. Singleton testified that by the time appellant provided its asphalt submittal to the
VA, it had learned from RPM that RPM was not willing to provide a twenty-year warranty,
absent the use of its adhesive. Appellant had also concluded from conversations that the VA
was going to require the use of the RPM roof. Given those circumstances, appellant appended
a letter to its asphalt submittal, advising the VA of a potential RPM warranty problem. In the
letter, appellant did not contest its obligation to provide the specified warranty, nor did it give
up its intention to use asphalt. Instead, the letter was advising the VA of a potential problem.
The VA did not respond to the submittal until February 12, 2008, when it returned the
submittal and marked asphalt as rejected. The VA followed that with the design bulletin,
CBCA 1966
12
which explicitly provided appellant could not use asphalt to secure the insulation and directed
appellant to use a specific RPM adhesive product in order to adhere the insulation.
Once the VA received the asphalt submission in November 2007, it could have entered
into a dialogue with appellant as to possible solutions. Alternatively, it could have simply sent
the submittal back to appellant with a note specifying its concerns as to the warranty and the
use of asphalt, and directed appellant to advise the VA as to how (with using asphalt)
appellant intended to provide the warranty. Had appellant been unable to provide assurance
as to the warranty, then the VA may have had a basis to issue a direction. However, the VA
first was obligated to give appellant an opportunity to meet the contract specifications. The
VA action, in issuing the bulletin and directing how appellant was to perform, took matters
out of appellant’s hands. Once the VA issued the bulletin, setting out directions, appellant
no longer had control of its performance. It no longer had the opportunity to pursue the option
of finding its own way of complying with the contract. The VA action in denying appellant
that opportunity constituted a change. Moreover, thereafter, appellant made its disagreement
with the VA position clear, but the VA did nothing to change its position.
In finding the VA action to be a change, we are mindful of the argument that appellant
had a duty to inquire because of the “note” in the Warren letter. However, it is critical to our
decision that Warren’s statement as to a possible conflict only involved one potential supplier,
RPM. That is particularly significant, because testimony of government witnesses has led us
to conclude that there were likely other manufacturers who could have provided a conforming
PIB roof and it was likely that those manufacturers would have been willing to provide a
warranty that would not have been voided due to setting insulation in asphalt.
The fact that appellant’s bid had contemplated using the RPM roof does not change our
view. A contractor is not obligated to stay with its intended bid, if after bidding it learns that
due to mistake, improvident analysis, or changed conditions it needs to move to an alternate
(but contract compliant) means of performance in order to comply with the contract. As long
as the contractor performs in compliance with the specifications, it has the right to proceed
as it finds best, even where that varies from how it bid. That is particularly the case where,
as here, appellant appeared to have other options.
In Shirley Construction Corp., ASBCA 46670, 94-2 BCA ¶ 26,868, at 133,690, the
Armed Services Board of Contract Appeals addressed the relationship between a claimed
conflict and a contractor’s right to perform. There, the Government asserted that there was
a conflict between the contractor’s reading of the specifications and a clear specification
requirement as to a required wind resistance warranty. Specifically, the Government claimed
that the contract required a warranty that covered damage from sustained winds up to seventyfive miles an hour, and such a warranty was only available from the manufacturer specified
in the contract if the contractor employed a combined system of roof application. The
CBCA 1966
13
Government contended that appellant’s reading, which was otherwise reasonable, did not
result in the needed combined system, and therefore, the appellant’s reading created a patent
conflict with the warranty. In addressing the matter, the board said the following:
We cannot conclude the requirement of the 75 mph warranty created an obvious
conflict. Indeed we believe the 75 mph warranty was a clear and unambiguous
contract requirement the successful bidder was obligated to supply under any
interpretation of the installation specifications. Whether it was attainable under
appellant’s interpretation from a manufacturer other than JPS is not discernable
from this record. However, respondent’s directions to appellant effectively
precluded appellant from pursuing its own interpretation and attempting to
provide a 75 mile per hour sustained wind warranty. In this regard, we note
respondent’s directions to appellant were focused on the method with the
warranty to be complied with “in addition” as part of the combined system
installation required under respondent’s interpretation.
In Shirley, the board ruled in favor of the appellant, even though it could not discern from the
record whether the appellant would have been able to secure the disputed warranty and
thereby proceed as it planned.
In summary, while we recognize that on the disputed contract, appellant initially
intended to use the RPM roof, and that the combination of that roof and the use of asphalt was
incompatible (at least on this facility), the fact remains that the contract permitted appellant
to pursue finding an alternate roofing manufacturer (even contrary to how it bid). Had it had
that option, it is likely that it could have provided asphalt and otherwise fully complied with
the contract. We find the VA’s actions in directing the use of adhesive, instead of asphalt, to
be a change.
Appellant has claimed $56,004.76. In reviewing the evidence on quantum, the primary
disputes involve the comparative costs of adhesive versus asphalt and the comparative labor
costs for placing the insulation with one product versus the other. On both material and labor,
we find appellant’s evidence to be significantly more convincing. The bulk of appellant’s
claim is the material cost differential between the $43,200 paid for adhesive versus the $7000
expected to have been expended for asphalt. As to the cost of adhesive, there was no real
dispute that it cost $216 per pail. While the VA challenges appellant’s pricing of asphalt, the
VA provides no credible evidence of a substitute number. In fact, the only credible
contemporaneous information as to the price of asphalt was provided by appellant. It showed
the cost in late December to be approximately $475 and in May to be as high as $700. In
evaluating this claim, we accept the price for asphalt of $500 a ton, as claimed by appellant.
We find that price is in line with the firm price it had up until the end of December 2007 and
further find that given an October award, that firm price should have held. Finally, the
CBCA 1966
14
adhesive price used in the claim is the early January 2008 price and therefore, by using a late
December date for asphalt pricing, we are using comparable time frames. As to labor, we find
the VA evidence as to labor costs to be second hand, on its face unreasonable, and the VA
estimate based on it to be incapable of logical analysis. In contrast, appellant’s numbers for
adhesive and asphalt, particularly in comparison to each other, appear generally reasonable.
Additionally, appellant provided sufficient data to allow a critical analysis of its labor costs.
As to the VA’s contention that because of the modification deleting part of the roof,
we must reduce appellant’s claim, we again find in favor of appellant. While some roofing
was deleted, the fact is that in pricing the deletion, appellant gave the VA a credit based on
laying the insulation with adhesive. Now that we have found that the requirement for
adhesive was a change, appellant is entitled to recoup the difference between the credit it gave
the VA for adhesive and the credit it would have given if it had been priced on the basis of
using asphalt.
Finally, we find that interest should start on April 22, 2008, the date on which appellant
first identified the dispute as a claim.
Decision
Based on the foregoing, we GRANT the appeal in the amount of $56,004 plus interest
under the Contract Disputes Act, 41 U.S.C. § 7109 (as amended by Pub. L. No. 111-350, 124
Stat. 3677, 3825-26 (2011).
_____________________________
HOWARD A. POLLACK
Board Judge
CBCA 1966
I concur:
___________________________
ANTHONY S. BORWICK
Board Judge
15
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.