APPELLANT’S MOTION TO DISMISS DENIED: March 10, 2020
CBCA 6563, 6564
SRA INTERNATIONAL, INC.,
Appellant,
v.
DEPARTMENT OF STATE,
Respondent.
D. Joe Smith, Umer M. Chaudhry, and Eric K. Herendeen of Jenner & Block LLP,
Washington, DC, counsel for Appellant.
Dennis J. Gallagher, Office of the Legal Adviser, Buildings and Acquisitions,
Department of State, Washington, DC, counsel for Respondent.
Before Board Judges SOMERS (Chair), SHERIDAN, and LESTER.
LESTER, Board Judge.
In response to the complaints that respondent, the Department of State (DOS), filed
in these now-consolidated appeals, appellant, SRA International, Inc. (SRA), filed a motion
to dismiss the appeals with prejudice for lack of jurisdiction or, in the alternative, for failure
to state a claim. Previously, the Board had directed DOS to file the initial complaints in these
appeals, which involve two separate DOS contracting officer decisions asserting government
claims, for efficiency purposes. In response to DOS’s designation of the contracting officers’
decisions as its complaints, SRA contends that the complaints are deficient and that these
CBCA 6563, 6564
2
appeals should be dismissed with prejudice. For the reasons set forth below, we deny SRA’s
motion.
Background
I.
DOS’s Factual Allegations
The following facts are taken from the allegations in the contracting officers’ final
decisions at issue in these appeals, which DOS has designated as its complaints, and
documents referenced and/or incorporated into the decisions:
A.
The Contracts At Issue
On December 13, 2011, DOS awarded SRA task order no. SAQMMA12F0156 (task
order 0156), through which SRA was to provide services related to the enhancement and
maintenance of the Worldwide Refugee Admissions Processing System (WRAPS).
Subsequently, on August 17, 2012, DOS awarded contract no. SAQMMA12C0204 (contract
0204) to SRA for cyber security operations support services that SRA was to perform for the
Bureau of Diplomatic Services. Both the task order and the contract are subject to incurred
cost audits under the clause at Federal Acquisition Regulation (FAR) 52.215-2 (48 CFR
62.215-2 (2012)), titled “Audits and Records–Negotiation.”
B.
The Audit
On April 6, 2018, following a November 7, 2017, audit entrance conference, SRA
received a formal notice from the Defense Contract Audit Agency (DCAA) about DCAA’s
plan to examine SRA’s incurred cost proposals under both task order 0156 and contract 0204
for fiscal years 2012, 2013, 2014, and 2015. The formal notice indicated that DCAA
expected to start its audit on April 20, 2018, and to issue a report on “approximately August
18, 2018.”
DCAA issued its audit report on August 29, 2018. In that report, DCAA represented
that “SRA was unable to provide sufficient appropriate evidence to support the claimed costs
with regards to time and material (T&M) labor, direct material, subcontracts, other direct
costs (ODCs) and indirect costs in accordance with FAR 31.201-2(d), “Determining
Allowability.” DCAA indicated that SRA, though having been given adequate time, “did not
provide the requested documentation to support the audit procedures.” DCAA also reported
that it was “unable to complete the procedures for testing [SRA’s] compliance with FAR
52.216-7(b)(1), Allowable Cost and Payment,” because SRA was able to provide payment
support only for ODCs and direct material transactions for FY 2014 and 2015. DCAA,
CBCA 6563, 6564
3
“[b]ased on the limited procedures performed,” then “identified . . . noncompliances” for FY
2012, 2013, 2014, and 2015 “which warrant the attention of those charged with governance,”
including unsupported and/or FAR-noncompliant charges for T&M labor, direct materials,
subcontracts, and ODCs, as well as an inability to reconcile particular costs claimed and
billed in the fiscal years in question with amounts identified in project status reports for those
years. DCAA calculated and identified the amount of questioned charges in each category
for each of the fiscal years at issue, ultimately questioning a total of $29,184,741.62 in costs
under task order 0156 and contract 0204.
C.
The Contracting Officers’ Final Decisions
On June 28, 2019, DOS, through two different contracting officers, issued final
decisions asserting government claims against SRA seeking repayment of a total of
$29,184,741.62 in disallowed costs, one decision under task order 0156 for $6,209,475.97
and one decision under contract 0204 for $22,975.267.66. In the decision relating to contract
0204, which essentially mirrors the decision relating to task order 0156 except for the dollar
amounts being sought, the contracting officer identified the following facts:
The [DCAA] completed a multi-year incurred cost audit of [SRA’s] 2012-15
fiscal years on August 29, 2018 and issued Audit Report Numbers
09811-2012G10100001, 09811-2013G10100001, 09811-2014G10100001, and
0981-2015G10100001 in which DCAA identified $29,184,741.62 of [DOS]
direct cost to be noncompliant with Federal Acquisition Regulation (FAR)
31.201-2(d) (See attached Audit Report).
Of that total amount,
$22,975,265.66 specifically pertains to [DOS] contract SAQMMA12C0204.
The noncompliant cost[s] are the result of SRA failing to provide DCAA
supporting documentation required to substantiate that claimed cost for
subcontracts and other direct cost (ODCs) in SRA’s incurred cost proposal
were reasonable, allocable, and allowable. The lack of supporting
documentation was so egregious that DCAA, after numerous requests for
information (timeline detailed below), were forced to disclaim an audit
opinion. Note, of the total $29,184,741.62 noncompliant cost detailed in
DCAA’s report, over 99.5% pertain to subcontractor cost with less than
$140,000 pertaining to ODCs. Therefore, the following timeline and record
retention guidelines pertain specifically to subcontractor cost. Similar
retention guidelines and timeline apply to the ODCs but, for the sake of
brevity, only the subcontract details are espoused upon further review.
CBCA 6563, 6564
4
Timeline of Information Requests by DCAA for Subcontract Support:
•
•
•
•
•
•
•
•
October 17, 2017 – DCAA provides audit notification to SRA.
November 7, 2017 – DCAA and SRA hold audit entrance conference.
April 2, 2018 – Initial document request sent with a due date of April
23, 2018. No support provided.
April 24, 2018 – DCAA follows up and SRA states they need more
time to locate files and will try to provide by May 8, 2018. DCAA
provides extension to May 8, 2018.
May 8, 2018 – No support provided. DCAA agrees to one last
extension until May 21, 2018.
May 21, 2018 – No support provided. DCAA supervisor provides
additional final extension until July 20, 2018.
July 20, 2018 – No support was provided.
August 29, 2018 – DCAA issues audit report with disclaimed opinion.
Appeal File Exhibit 9 at 1-2.
In the decision, the contracting officer discussed an in-person negotiation that DOS
had conducted with representatives of SRA on June 28, 2019, after DCAA had provided
DOS with the audit report, and acknowledged that, “[d]uring the negotiation meeting, SRA
attempted to provide what it claimed to be the required supporting documentation it
otherwise never submitted to DCAA.” Exhibit 9 at 3. Nevertheless, the contracting officer
opined that SRA’s “action and the response copied above fail to comply with the [FAR],”
going so far as to identify and highlight various sections of the FAR dealing with record
retention that the contracting officer believed SRA had failed to satisfy. Id. at 3-4.
In addition, as indicated above, a copy of DCAA’s August 29, 2018, audit report was
referenced in and attached to each of the two contracting officers’ final decisions.
II.
Activity Before the Board
On July 18, 2019, SRA filed notices of appeal from the two contracting officers’
decisions, which the Board docketed as CBCA 6563 and 6564.
In orders issued on July 29, 2019, the Board directed DOS to file the initial complaint
on the government claims and, in each complaint, to “identify[] the bases for its repayment
demand.” Consistent with the Board’s rules, though, the Board also indicated that DOS
could designate the contracting officers’ decisions or other documents as the complaint. On
CBCA 6563, 6564
5
August 23, 2019, DOS designated the June 28, 2019, contracting officers’ decisions as its
complaints, and the Board subsequently consolidated CBCA 6563 and 6564.
On September 20, 2019, SRA, in lieu of filing an answer, filed a motion seeking “to
dismiss the Government’s claims with prejudice for lack of jurisdiction and failure to state
a claim upon which relief can be granted.” Motion at 1. In its motion, to which SRA
attached numerous emails as evidentiary exhibits, SRA asserted that, contrary to the
representations in the contracting officers’ decisions, SRA actually responded to DCAA’s
document requests between April and July 2018 and “communicated with DCAA regarding
SRA’s inability to provide certain requested documents, specifically because these
documents were stored at an off site location,” such that “SRA did not have immediate
access to them.” Motion at 3. SRA also alleged that, in August 2018, a DCAA supervisory
auditor told SRA that DCAA was no longer accepting supporting documentation from SRA,
but that, if SRA held its documentation, DCAA would accept it when SRA met with the DOS
contracting officers for negotiation purposes. SRA alleges that it then attempted to provide
supporting documentation to DOS at a June 25, 2019, negotiation, but that DOS refused to
take it.
The parties have fully briefed SRA’s motion.
Discussion
SRA’s Jurisdictional Motion
SRA argues that the Board lacks subject matter jurisdiction to entertain the two
government claims at issue in these appeals because the contracting officers’ decisions fail
to provide adequate notice as to the basis and amounts of DOS’s claims.1
The Board derives its jurisdiction to consider contract disputes from the Contract
Disputes Act (CDA), 41 U.S.C. §§ 7101-7109 (2012). Pursuant to the CDA, we possess
jurisdiction to consider a dispute over a government claim only if a contracting officer issues
a final decision asserting the government claim and the contractor timely appeals it. National
1
SRA asserts that, if we dismiss these appeals for lack of jurisdiction, we should
dismiss them with prejudice. This we could not do. “A dismissal with prejudice effectively
renders an adjudication on the merits.” Scott Aviation v. United States, 953 F.2d 1377, 1378
(Fed. Cir. 1992). Without jurisdiction, we lack the ability to render a merits determination
and therefore “cannot presume to dismiss the complaint,” or the appeal, “with prejudice.”
Id. Any dismissal for lack of jurisdiction is, by necessity, without prejudice.
CBCA 6563, 6564
6
Fruit Product Co. v. Department of Agriculture, CBCA 2445, 12-1 BCA ¶ 34,979, at
171,932; see 41 U.S.C. § 7103(a)(3)-(4) (under the CDA, “[e]ach claim by the Federal
Government against a contractor relating to a contract shall be the subject of a written
decision by the contracting officer” and “submitted within 6 years after the accrual of the
claim”). Although the CDA does not define the term “claim,” we look for guidance to the
CDA’s implementing regulation, the FAR, see Magwood Services, Inc., CBCA 4975, 16-1
BCA ¶ 36,520, at 177,908 (2015), which defines a monetary “claim” as “a written demand
or written assertion by one of the contracting parties seeking, as a matter of right, the
payment of money in a sum certain.” FAR 2.101 (48 CFR 2.101 (2019)). On its face, each
of the two contracting officers’ decisions at issue here satisfies the FAR’s definition of a
“claim: each is in writing, identifies a specific amount of money that the contracting officer
asserts SRA owes DOS, and demands that SRA pay DOS that amount.
SRA argues that more is required and that, to be valid, the decision asserting the
government claim must also contain a “clear and unequivocal statement that gives . . .
adequate notice of the basis and amount of the claim.” Motion at 8 (quoting Contract
Cleaning Maintenance, Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987)). Although
most decisions discussing this “adequate notice” requirement address contractor claims
submitted to the contracting officer, several tribunals have applied the same “adequate
notice” requirement to government claims set forth in contracting officers’ final decisions.
See, e.g., Raytheon Co. v. United States, 105 Fed. Cl. 236, 298 (2012) (applying “adequate
notice” requirement to a government claim); Johnson Controls World Services, Inc. v. United
States, 43 Fed. Cl. 589, 592 (1999) (same); Volmar Construction, Inc. v. United States, 32
Fed. Cl. 746, 752 (1995) (same); L-3 Communications Integrated Systems, L.P., ASBCA
60713, et al., 17-1 BCA ¶ 36,865, at 179,625 (same); Keany Square Associates Limited
Partnership, VABCA 3228, 91-1 BCA ¶ 23,371, at 117,252 (1990) (same). We agree that
the “adequate notice” requirement applies equally to both contractor and government claims.
Nevertheless, SRA is seeking to impose an “adequate notice” standard upon
government claims that is significantly higher and more burdensome than that typically
applied to contractor claims. Here, SRA complains that each of the two contracting officers’
decisions “essentially has one generic reference to the amount demanded, with no additional
information regarding the Government’s basis for the demand or a breakdown of the
disallowed costs,” which SRA views as insufficient to support a claim. Motion at 9.
Contrary to SRA’s description, though, both of the final decisions clearly indicate that
DCAA conducted an incurred cost audit covering specific fiscal years, that SRA did not
provide supporting documentation to justify its costs during the audit, and that the
Government finds the amount of the unsupported and/or FAR-noncompliant costs that SRA
must reimburse DOS to be $6,209,475.97 under task order 0156 and $22,975.267.66 under
contract 0204.
CBCA 6563, 6564
7
For a contractor claim, “[t]he minimal amount of information sufficient to provide
adequate notice is quite low.” L-3 Communications, 17-1 BCA at 179,626. A valid
contractor claim “need not include a detailed breakdown of costs” or “account[] for each cost
component.” H.L. Smith, Inc. v. Dalton, 49 F.3d 1563, 1565 (Fed. Cir. 1995). SRA has
identified no reason for imposing a more demanding notice standard upon government claims
than upon contractor claims or to demand cost breakdowns only in government claims.
SRA’s mere “desire for more information” is insufficient to strip the contracting officers’
decisions of their jurisdictional effectiveness. Id.
Further, even if the language contained in the final decisions, in and of itself, was less
than clear about the basis of DOS’s claims, that would not defeat the claims’ effectiveness
for jurisdictional purposes. In such circumstances, we would look to correspondence
surrounding and leading up to SRA’s receipt of the Government’s claims, coupled with the
actual language in the contracting officers’ decisions, to determine whether, in fact, SRA
understood or should have understood the basis of those claims. See, e.g., K-Con Building
Systems, Inc. v. United States, 107 Fed. Cl. 571, 588-89 (2012); Valco Construction Co.,
ASBCA 47909, et al., 96-2 BCA ¶ 28,344, at 141,552; C.F. Electronics, Inc., ASBCA
44282, 93-3 BCA ¶ 25,971, at 129,153-54; General Construction Co., ASBCA 39983, 91-1
BCA ¶ 23,314, at 116,917 (1990); Marshall Construction, Ltd., ASBCA 37014, et al., 90-1
BCA ¶ 22,597, at 113,390. That type of determination is made on a case-by-case basis,
depending on the specific situation at hand. B.L.I. Construction Co., ASBCA 40857, et al.,
92-2 BCA ¶ 24,963, at 124,394. Here, attached to, if not incorporated into, the two
contracting officers’ decisions was the DCAA audit report that formed the basis of the
Government’s claims. That audit report breaks down the total amount of questioned costs
into categories and subcategories for each of the four fiscal years at issue. Certainly, SRA
understands, or should understand, the basis of DOS’s claims. SRA’s argument that the audit
report “fails to provide any clarity” regarding that basis, Motion at 9, ignores the information
actually contained in the audit report.
Relying upon a decision of one of our sister boards, SRA further argues that the
statement of claim in a contracting officer’s decision must, but in this case fails to, “provide
a basis for meaningful dialogue between the parties aimed toward settlement or negotiated
resolution of the claim if possible, or for adequate identification of the issues to facilitate
litigation should that be necessary.” Motion at 10 (quoting Blake Construction Co., ASBCA
34480, et al., 88-2 BCA ¶ 20,552, at 103,890). Yet, in its reply brief, SRA specifically states
that it “is certainly aware of the costs questioned by DCAA and is ready to address these
issues on their merits.” Reply at 3 n.2. In such circumstances, we cannot understand SRA’s
position that the decisions here provide no basis for a meaningful dialogue. Further, the
Court of Appeals for the Federal Circuit, in reversing a lower court decision that had relied
in part upon Blake Construction in finding a lack of “adequate notice” in a claim, made clear
CBCA 6563, 6564
8
that a letter alleging a breach of specific contractual provisions and containing a demand for
a specific amount in damages provides enough information to meet any “dialogue”
requirements that the CDA and the FAR impose. See Northrop Grumman Computing
Systems, Inc. v. United States, 709 F.3d 1107, 1112-13 (Fed. Cir. 2013) (reversing 99 Fed.
Cl. 651 (2011)). To the extent that Blake Construction purports to impose higher or more
burdensome notice requirements, it would conflict with Federal Circuit precedent, and we
would not be bound by it.
SRA has no basis for contesting the jurisdictional validity of the two June 28, 2019,
contracting officers’ final decisions.2
SRA’s Motion for Failure to State a Claim
SRA alternatively argues that we must dismiss these appeals because the two
contracting officers’ final decisions at issue fail to state a claim upon which the Board can
grant relief.
DOS has elected to rely upon the final decisions as its complaints in these appeals.
In a complaint, a party “must allege facts ‘plausibly suggesting (not merely consistent with)’
a showing of entitlement to relief.” American Bankers Association v. United States, 932 F.3d
1375, 1380 (Fed. Cir. 2019) (quoting Acceptance Insurance Cos. v. United States, 583 F.3d
849, 853 (Fed. Cir. 2009) (quoting Bell Atlantic Corp. v Twombly, 550 U.S. 544, 557
(2007))). “A claim has facial plausibility when the plaintiff pleads factual content that allows
the [tribunal] to draw the reasonable inference that the defendant is liable for the misconduct
alleged.” Id. (quoting Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009)). In reviewing a motion
to dismiss for failure to state a claim, “we accept as true the complaint’s well-pled factual
allegations,” though not its “asserted legal conclusions.” Id.
2
SRA also asserts that the “sum certain” dollar amounts that the DOS contracting
officers identified in their decisions are slightly different than the total amounts that the
DCAA questioned. Although SRA argues that this slight variation defeats the Board’s
jurisdiction, the contracting officers’ decisions clearly demand payment in a “sum certain,”
satisfying the requirements of the CDA. 444 Brickell Partners, LLC v. General Services
Administration, CBCA 6199, et al., 19-1 BCA ¶ 37,271, at 181,363. We have found no court
or board decision dismissing an appeal based upon a slight mathematical variation in the
claim’s stated “sum certain” and dollar amounts identified in prior communications. Any
slight variations between the DCAA audit figure and the contracting officers’ demands can
be explored during discovery, but do not affect jurisdiction.
CBCA 6563, 6564
9
SRA interprets DOS’s claims as being based upon the fact “that SRA failed to make
certain documents available to DCAA during the audit period (approximately four months).”
Motion at 11. According to SRA, DOS is complaining that SRA “violated FAR 4.703 and
52.215-2 by failing to make documents available during the audit period to DCAA.” Motion
at 12-13. SRA asserts that the FAR provisions, although they mandate that the contractor
make its records available for audit, do not specify a length of time within which the
contractor must respond to an inspection or audit notice and that, as a matter of law, four
months’ notice is too short. Id. at 13. SRA, relying upon evidentiary documents that it has
attached to its motion, also alleges that, at the end of that four-month period, DCAA said that
it was too late at that point to deliver documents, but represented that SRA would be allowed
to do so when negotiations began. That representation, SRA says, turned out to be false.
We deny SRA’s motion to dismiss for failure to state a claim for several reasons:
First, SRA’s argument depends, in part, upon evidence (in the form of
contemporaneous email communications) that SRA attached to its motion. SRA argues that
the emails conflict with the DOS contracting officers’ representations that SRA did not
provide support for its incurred costs and reflect DCAA’s instruction to SRA in mid-2018
to hold, rather than submit, documents. We cannot consider the submitted material on a
motion to dismiss for failure to state a claim. “In general, a case can only be dismissed for
failure to state a claim upon which relief may be granted when that conclusion can be
reached by looking solely upon the pleadings.” A to Z Wholesale v. Department of Homeland
Security, CBCA 2110, 11-1 BCA ¶ 34,674, at 170,811. Although, in appropriate
circumstances, we might also consider materials attached to or essentially incorporated into
a complaint in considering such a motion, Systems Management & Research Technologies
Corp. v. Department of Energy, CBCA 4068, 15-1 BCA ¶ 35,976, at 175,789, other outside
materials, like the emails upon which SRA is relying, are not permissible. See A to Z, 11-1
BCA at 170,811. SRA cites nothing to support its representation that, because DOS has not
challenged the outside documents’ authenticity, they are admissible on a motion to dismiss
for failure to state a claim.
Second, we disagree with SRA’s interpretation of the timing requirements of the
applicable FAR provisions. The contract clause at FAR 52.215-2, titled “Audit and
Records–Negotiation,” provides that the contracting officer or an authorized representative
“shall have the right to examine and audit all records and other evidence sufficient to reflect
properly all costs claimed to have been incurred or anticipated to be incurred directly or
CBCA 6563, 6564
10
indirectly in the performance of this contract”3 and that the contractor shall make requested
documents “available at its office at all reasonable times.” 48 CFR 52.215-2(b), (f).
According to DOS’s complaints in these appeals, DCAA gave SRA four months to provide
access to documents supporting SRA’s incurred costs, but SRA did not provide any
documents during that time. Although SRA argues that it is entitled to judgment as a matter
of law because the FAR establishes no time limit within which a contractor must respond to
an audit request, the FAR clause plainly grants DOS a contractual right to access SRA’s
documents “at all reasonable times.” Accepting as true the factual allegations that DOS
makes in its complaints, as we must, we reject SRA’s assertion that DOS has not alleged “a
facially plausible claim” that SRA failed to support its incurred costs. The evidence that
SRA wishes to present challenging DOS’s factual allegations is not properly before us on the
type of motion that SRA has filed.
Third, even if we were to agree with SRA that the amount of time that DCAA and
DOS gave SRA to provide access to SRA’s cost support was unreasonable, that would not
mean that SRA would suddenly be entitled to judgment as a matter of law. Although the
contracting officers’ decisions identify various FAR provisions that required SRA to preserve
and make available documents to support SRA’s incurred costs, the crux of DOS’s
repayment claim is that DOS has seen no support for $29,184,741.62 in costs for which SRA
invoiced DOS and that DOS paid. DOS wants the unsupported and/or FAR-noncompliant
costs back. If we find the amount of time that SRA was given to provide cost support
unreasonable, and if SRA has actual support for questioned costs, SRA may attempt to
present that support as evidence in this litigation.4 Nevertheless, under its contracts, SRA is
subject to incurred cost audits, and it does not get to retain all $29 million in questioned costs
unless it provides appropriate cost support for them. To date, at least as alleged by DOS,
SRA has never provided DOS or DCAA with such support. A finding that the DCAA or
DOS should have given SRA more time to submit that support would mean only that SRA
is not barred from submitting it now.
3
Similarly, FAR 4.703 provides that “contractors shall make available records . . .
to satisfy contract negotiation, administration, and audit requirements of the contracting
agencies” and shall maintain those records for specific periods of time. 48 CFR 4.703(a).
4
We recognize that one of our predecessor boards held that “[a] litigant may not
freely withhold records during audit and then produce them during a Board trial to support
a claim for recompense.” TDC Management Corp., DOT BCA 1802, 91-2 BCA ¶ 23,815,
at 119,323, aff’d sub nom. Skinner v. TDC Management Corp., 975 F.2d 869 (Fed. Cir. 1992)
(table). We do not decide here the extent to which, if SRA’s failure to provide cost support
access during the four-month DCAA audit period was not reasonable, SRA would still be
entitled to provide that support as part of this litigation.
CBCA 6563, 6564
11
Fourth, SRA argues that the DOS decisions are internally contradictory and, as a
result, fail to state a viable claim. In their decisions, the DOS contracting officers
acknowledged that, during negotiations in June 2019, SRA attempted to provide what SRA
claimed was at least some of the missing cost support documentation, but that DOS would
not accept it. DOS asserts in its response that, because the CDA’s statute of limitations was
about to expire on its right to reclaim at least some of DOS’s unsupported costs, DOS could
no longer accept new material from SRA or recommence the audit.5 Regardless of DOS’s
reasons for rejecting material presented in June 2019, the cited statements in the final
decisions do not necessarily defeat DOS’s claim. SRA cannot establish at this point in the
litigation that the documents which it allegedly wanted to provide DOS in June 2019 actually
provide full support for the questioned costs. Further proceedings will be necessary to
determine the extent to which SRA has such support.
Decision
For the foregoing reasons, SRA’s motion to dismiss is DENIED. SRA shall file its
answers to DOS’s complaints no later than March 24, 2020.
Harold D. Lester, Jr.
HAROLD D. LESTER, JR.
Board Judge
We concur:
Jeri Kaylene Somers
JERI KAYLENE SOMERS
Board Judge
5
Patricia J. Sheridan
PATRICIA J. SHERIDAN
Board Judge
SRA complains that, if DOS “had actually been concerned about the CDA’s statute
of limitations, it could have asked [SRA] to enter into a tolling agreement.” Reply at 6. SRA
neither suggests that SRA ever brought up the idea of a tolling agreement before filing its
reply brief nor identifies any authority requiring agencies to offer CDA tolling agreements
to contractors. In any event, SRA’s argument is irrelevant to its dispositive motion.