In the Matter of MONROE COUNTY, FLORIDA
Agency decision
Ask Donna
What actually matters in this document.
Text
September 11, 2020
CBCA 6716-FEMA
In the Matter of MONROE COUNTY, FLORIDA
Robert B. Shillinger and Christine Limbert-Barrows of Monroe County Attorney’s
Office, Key West, FL; Ernest B. Abbott of Baker, Donelson, Bearman, Caldwell &
Berkowitz, PC, Washington, DC; Wendy Huff Ellard of Baker, Donelson, Bearman,
Caldwell & Berkowitz, PC, Jackson, MS; and Danielle Aymond of Baker, Donelson,
Bearman, Caldwell & Berkowitz, PC, Baton Rouge, LA, counsel for Applicant.
Sherin Joseph, Appeals Officer, Allison McLeary, Compliance, Appeals and Special
Projects Manager, and Amanda Campen, Florida Division of Emergency Management,
Recovery Bureau Chief, Tallahassee, FL, appearing for Grantee.
Maureen Dimino, Office of Chief Counsel, Federal Emergency Management Agency,
Department of Homeland Security, Washington, DC; and Frank Bruscato, Office of Chief
Counsel, Federal Emergency Management Agency, Department of Homeland Security, Baton
Rouge, LA, counsel for Federal Emergency Management Agency.
Before the Arbitration Panel consisting of Board Judges VERGILIO, LESTER, and
O’ROURKE.
Applicant sought reimbursement for base camp support costs to accommodate
personnel providing disaster relief in response to Hurricane Irma. FEMA determined that
partial funding was warranted in this case. After reviewing the record (including witness
testimony presented during the arbitration hearing) and considering the arguments by both
parties, we grant the applicant’s request in part.
CBCA 6716-FEMA
2
Background
On September 10, 2017, Hurricane Irma, a category four hurricane, made landfall in
Monroe County, Florida, a 3737 square mile area which includes the Florida Keys, the
Everglades, and Big Cypress National Preserve. In the days leading up to the hurricane,
Monroe County officials began preparing for emergency response operations, including
establishing base camps to accommodate personnel participating in recovery efforts. Base
camps provide lodging, meal services, sanitation and laundry facilities, generators,
emergency healthcare, refueling, and other services to local, state, and federal emergency
responders rendering aid to the impacted area. Monroe County estimated that one thousand
emergency response personnel would require base camp support. This estimate was based
on early weather and damage forecasts, communications from emergency response groups,
guidance from state and federal agencies, and the training and experience of Monroe County
emergency management officials.
The President issued a disaster declaration the same day that Hurricane Irma made
landfall in Florida. Decisions related to the establishment of base camps were made in the
days immediately following the hurricane. The County engaged Ashbritt, Inc., its
comprehensive disaster response contractor, to construct the camps. Six months earlier,
Monroe County had issued a request for proposals (RFP) for disaster response and recovery
services. Although the primary focus of the RFP was debris collection and disposal services,
the scope of work also required “Logistical and Recovery Operations Services,” including
services related to the establishment of base camps. Ashbritt’s proposal included those
services, but offered them as “additional services,” rather than as part of its basic services.
Ashbritt’s proposal also included a price schedule for “Disaster Response Man
Camps/Comfort Services,” which consisted of three pages of detailed pricing information,
broken out by service category, and further divided by camp capacity (500-, 250-, and 100person man camps), mobilization and demobilization costs, labor, equipment units, per
person/per day costs, and weekly operations costs. Ashbritt’s cost summary supplied the
required attestation that “to the best of [its] knowledge all proposed prices were reasonable
and customary for the services listed.”
Monroe County awarded the contract to Ashbritt on June 21, 2017. The signed
contract, however, did not contain Ashbritt’s proposed pricing schedule for the man camps.
Instead, Article III of the contract stated that any additional services would be provided by
the contractor for an additional fee:
If Additional Services are required, such as those listed above, the COUNTY
shall issue a letter requesting and describing the requested services to the
CONTRACTOR. The CONTRACTOR shall respond with a fee proposal to
perform the requested services. Only after receiving an amendment to the
CBCA 6716-FEMA
3
Agreement and a notice to proceed from the COUNTY, shall the
CONTRACTOR proceed with the Additional Services.
Shortly after Hurricane Irma, County officials asked Ashbritt to establish two base
camps: one at Marathon Airport for 250 people and the other at Sugarloaf School for 100
people. The parties did not follow the precise procedure outlined above, but the record
contains several contemporaneous email messages that documented agreements made
immediately after the hurricane. In particular, an email, dated September 14, 2017, from
Ashbritt to the County acknowledged “acceptance of the original notice to proceed for the
250 person base camp conditioned on the county’s acceptance that the rates would be in
alignment with what the state of Florida rates would have been (approximately $250-$275
per person, per day) had they provided the county with these services.” The email further
confirmed “the notice to proceed with a 100 person base camp under the same rate
conditions.” The County responded to Ashbritt by email the next day, stating “Monroe
County acknowledges and agrees to the rate conditions stipulated below and accepts these
same rate conditions for the additional 100 person base camp, which is to be set up at the
Sugarloaf School.” Mobilization and demobilization fees were not addressed in the emails,
nor were the periods of performance for either camp.
The Marathon Airport camp was fully operational by September 15, 2017. Two days
later, the County requested a surge in the camp’s capacity: from 250 to 1000 people. Just
weeks before Irma, Hurricane Harvey devastated parts of Texas. As FEMA wound down
relief operations in Texas, Monroe County expected that it would quickly ramp up in Florida.
The Sugarloaf School base camp was substantially complete on September 20, 2017. That
same day, Hurricane Maria hit Puerto Rico and the U.S. Virgin Islands. Plans quickly
shifted, and demand for base camp services drastically decreased. Many personnel were
diverted to support response operations in areas impacted by Hurricane Maria, and FEMA
and Florida State emergency agencies decided to establish their own base camps. Monroe
County ended up with excess capacity in both of its base camps. Just five days after the
County sought to quadruple its capacity at Marathon Airport, the County asked the contractor
to halt the surge and maintain support operations at its current level of 600 personnel.
On September 29, 2017, County officials, Ashbritt representatives, and the base camp
subcontractor (Mike Holm of OK’s Cascade) discussed the costs related to the base camps.
According to a documented summary of that conversation, Mr. Holm advised that the
standard Florida contract has an initial minimum billing time of 30 days, and charges would
be as follows for the two base camps:
Marathon Airport (30 days)
Unit Cost
Extended Cost
Mobilization (250 capacity)
$170,000
$170,000
CBCA 6716-FEMA
4
Demobilization (250 capacity)
$145,000
$145,000
Mobilization (expansion to 1000)
$119,000
$119,000
Demobilization (expansion to 1000)
$145,000
$145,000
PP/PD Charges (250 x 8 days)
$205
$410,000
PP/PD Charges (1000 x 22 days)
$205
$4,510,000
Total
$5,499,000
The base camp subcontractor agreed to reduce the Sugarloaf School billing to fourteen
days, as follows:
Sugarloaf School (14 days)
Unit Cost
Extended Cost
Mobilization (100 capacity)
$170,000
$170,000
Demobilization
$145,000
$145,000
PP/PD Charges (100 x 14)
$235
$329,000
Total
$644,000
Both camps were demobilized by October 3, 2019. The contract did not contain a
termination for convenience clause, and the County accepted without question the statement
of Ashbritt’s subcontractor that a thirty-day minimum was standard in Florida, despite
evidence in the record that other contractors who bid on the County contract proposed
periods of performance for as little as seven days.
In November 2017, Ashbritt invoiced Monroe County for base camp services in the
amount of $6,470,410. The County attempted to verify the fees charged by Ashbritt as being
consistent with rates paid by the State of Florida for similar services. State officials provided
the County with sample invoices from their base camp contractors and a print-out from “My
Florida Marketplace” reflecting the rates that other base camp vendors had charged State
agencies, to include separate fees for mobilization and demobilization. The County followed
up with Ashbritt to discuss the invoice, which Ashbritt asserted “reflects the exact amount
charged to Ashbritt by an outside contractor plus a reasonable administrative fee as agreed
to by the County and Ashbritt.” The record contains no contemporaneous evidence of that
fee. Nonetheless, Ashbritt agreed to reduce its fee from 20% to 9%, the latter rate being
consistent with a previous Florida project. The County paid Ashbritt and then sought
reimbursement from FEMA under Project Worksheet 16035. FEMA denied the base camp
costs, and the County submitted a request for arbitration to the Board.
CBCA 6716-FEMA
5
An arbitration hearing convened by telephone on June 2, 2020, during which FEMA
determined that approximately $2.4 million was appropriate for disaster assistance funding.
FEMA stated that the remaining costs were ineligible for reimbursement due to flaws in the
contracting process and a lack of sufficient documentation for the costs. The County argued
that it could have procured the services non-competitively, using emergency procedures, and
urged FEMA to be guided by whether the costs were reasonable and necessary at the time
they were incurred, rather than analyzed after the fact on an “actual use” basis.
Discussion
The Board is authorized by Section 423 of the Robert T. Stafford Disaster Relief and
Emergency Assistance Act (Stafford Act), 42 U.S.C.A. § 5189a(d) (2019), to arbitrate
disputes between applicants and FEMA as to eligibility for public assistance for a disaster
that occurred after January 1, 2016, when the disputed amount exceeds $500,000. With $6.5
million in dispute, the Board’s jurisdictional minimum is satisfied in this case. A Presidential
disaster declaration under the Stafford Act enables state and local governments to access
critical disaster relief assistance and funding. However, the assistance must meet the Act’s
eligibility requirements and comply with federal regulations and FEMA policies. Monroe
County is an eligible applicant consistent with the Stafford Act’s requirements, which limit
funding to federal, state, local, and tribal government entities. In addition to applicant
eligibility, there are also three general eligibility requirements for the type of work for which
an applicant seeks public assistance funding. The work must: (1) be required as a result of
the declared incident, (2) be located within the designated area, with the exception of
sheltering and evacuation activities, and (3) be the legal responsibility of an eligible
applicant. FEMA did not challenge these requirements, and we find that based on the
information in the record, these requirements were met. The President issued a disaster
declaration for Hurricane Irma, base camp services were required to facilitate disaster
recovery operations, they were established in the designated area, and Monroe County had
jurisdiction over disaster operations in this area.
The final component of public assistance eligibility is cost. Not all costs incurred as
a result of a disaster are eligible for funding. To be eligible, FEMA regulations require that
costs be: (1) directly tied to the performance of eligible work; (2) adequately documented;
(3) reduced by applicable credits (such as insurance and salvage); (4) authorized and not
prohibited by federal, state, and local laws; (5) consistent with applicant’s policies,
regulations, and procedures; and (6) necessary and reasonable to accomplish the work
properly and efficiently. It is this final component upon which the parties disagree.
During the arbitration process, FEMA determined that some aspects of the County’s
contracting process were inconsistent with federal procurement law and that there was a lack
of documentation to support base camp costs. For these reasons, FEMA supported only
CBCA 6716-FEMA
6
partial funding of the base camps in the amount of $2,497,719.70. This amount represented
the documented reasonable and necessary costs “directly tied” to eligible work in compliance
with federal regulations and FEMA policy. 2 CFR 200.403(a), (g), 200.404 (2018); FEMA
Public Assistance Program Policy Guide, FP-104-009-2, at 21-22. Specifically, FEMA
identified the following costs as eligible for public assistance funding:
(1) mobilization and demobilization costs for Sugarloaf School base camp
totaling $315,000.00;
(2) the original mobilization cost of $170,000.00, the second expanded
capacity mobilization cost of $119,000.00, and a single demobilization cost of
$145,000.00, for Marathon Airport base camp, totaling $434,000;
(3) Marathon base camp: $406,679.00 for daily, per person costs ($223.45
pp/pd x 250 people x 8 days = $446,900.00) (with a 9% deduction =
$406,679.00).
(4) Marathon base camp: $1,342,040.70 for daily, per person costs ($223.45
pp/pd x 600 people x 11 days = $1,474,770.00) (with a 9% deduction =
$1,342,040.70).
Although FEMA determined that partial funding was appropriate in this case, under
the Stafford Act the Board reviews the evidence de novo and is not bound by FEMA’s
determination. City of New Orleans, CBCA 5684-FEMA, 18-1 BCA ¶ 37,005.
Nevertheless, after reviewing the record, including testimonial evidence provided during the
arbitration hearing, we agree with FEMA’s determination that partial funding is warranted
in this case. The County’s procurement was conducted using full and open competition
procedures. Eight proposals were submitted in response to the RFP issued in March 2017.
The RFP identified the scope of work, required offerors to submit pricing schedules, and
sought past performance information. Evaluation and scoring sheets reflected the reviews
of each proposal by four experienced evaluators. A final tally worksheet showed that all four
evaluators identified Ashbritt’s proposal as being the best value offer but varied on the
rankings of other offerors. In light of the fact that the RFP required base camp support
services, we do not find that such services represented a cardinal change to the contract, as
represented in FEMA’s initial determination memo. On the contrary, part two of the RFP
contained the scope of work. Paragraph F of that scope included “Logistical and Recovery
Operations Services.” Nine line items were listed under that section, to include the base
camp support functions performed by Ashbritt. All offerors were on notice that the scope
of work required this capability, and, indeed, several contractors included such services in
their offers. Although Ashbritt proposed base camp support services as an additional service,
rather than as part of its basic services, we find that the base camp support work was within
CBCA 6716-FEMA
7
the scope of the RFP and that the resulting contract provided a mechanism to request
additional services and pay for them.
The fact that Ashbritt’s price schedule for man camps was not part of the final
contract prevented the County from relying on those rates when the services became
necessary. Indeed, the benefit of having disaster recovery contracts pre-positioned is to avoid
having to negotiate terms and conditions during or immediately following a disaster. With
that opportunity lost, the County relied, in good faith, on its discussions with Ashbritt that
the County would be charged the same prices for base camp services that Ashbritt’s
subcontractor (OK’s Cascade) charged the state of Florida under a competitively procured
contract for these services. In an email message to a County official prior to establishing the
base camps, Ashbritt stated that “the rates would be in alignment with what the State of
Florida rates would have been (approximately $250 to $275 per person, per day) had they
provided the county with the services.” The email did not address the full scope of charges
for similar state contracts—only the per person, per day rate for services. The County did
not press Ashbritt on this figure and later learned that there was no standard rate.
Also, the County did not use the market research already available to it from other
contract proposals to challenge the contractor’s assertion that a thirty-day minimum billing
period was standard, and it did not attempt to negotiate for inclusion of a termination for
convenience provision that could have allowed it to significantly mitigate its costs. Applying
the requirements for reimbursements set forth at 2 CFR 200.326 and Appendix II to 2 CFR
Pt. 200, FEMA requires that the County include such provisions, or at least make efforts to
negotiate for the inclusion of such provisions, in its contracts to minimize the potential of
wasted expenditures, and we agree that FEMA may take their absence into account in
considering cost reasonableness and reimbursability.
Despite the procurement irregularities noted above, we agree with FEMA’s
determination that the type of work at issue here was eligible for funding. With regard to the
reasonableness of costs, FEMA regulations state that “[a] cost is reasonable if, in its nature
and amount, it does not exceed that which would be incurred by a prudent person under the
circumstances prevailing at the time the applicant makes the decision to incur the cost.” The
regulations further evaluate reasonableness of costs by determining if the cost is generally
recognized as ordinary and necessary for the type of work, is comparable to the current
market price for similar goods and services, based on historic documentation, average cost
in the area, and published unit costs from national databases. 2 CFR 200.403, 200.404;
FEMA Public Assistance Program Policy Guide FP-104-009-2 at 21-22. Based on this
guidance, we find that the all-inclusive, single rate of $205 per person, per day, for base
camp services was reasonable. We reach this conclusion by taking the individual rates for
each category of service in Ashbritt’s proposed price schedule and adding the cost of three
meals, beds, and other charges, such as power and communications, which results in a price
CBCA 6716-FEMA
8
range of $140 to $170 per person, per day, without the 9% fee. When considering the
remoteness of the location and the simultaneous demand for these services by multiple
organizations, we find that the additional costs were reasonable.
With regard to mobilization and demobilization fees, we find these costs to be both
necessary and reasonable. Mobilization and demobilization costs were included in Ashbritt’s
proposal, as well as in other vendor proposals. They were also reflected in the market
research provided by State officials, including one of the State’s actual invoices for similar
work by the same subcontractor: OK’s Cascade. Thus, these costs appear to be standard in
the provision of base camp services, and as such we find that they were necessary costs.
With regard to the amounts charged to the County for mobilization and demobilization costs,
we note that they were higher than what the State paid, but we also recognize that the County
established its camps first, when the road and bridge conditions along the single highway that
connects the Florida Keys were extremely poor. For these reasons, we find that the
mobilization and demobilization rates charged by Ashbritt were reasonable, with the
exception of the first demobilization fee of $145,000 for the Marathon Airport base camp.
When that camp expanded its capacity from 250 to 1000 personnel, we found nothing in the
record that supported a full demobilization charge as necessary. On the other hand, we find
a partial mobilization fee to achieve the expanded capacity to be necessary.
Finally, despite the County’s efforts to predict the demand for base camp capacity,
other disasters and the establishment of base camps at the State and Federal levels quickly
rendered the County’s camps superfluous. Although the camps were not fully utilized,
FEMA acknowledged that their establishment was necessary and found the costs reasonable
for the days that Marathon Airport base camp was actually open since there was
documentation associated with those costs.
FEMA did not support any daily costs for Sugarloaf School due to a lack of
documented costs. The County argued that actual use is an improper standard to measure the
reasonableness of the charges. It contends that the capacity for Sugarloaf School was based
on predicted use. We disagree. The fact that the camp was barely used is not the issue.
Rather, FEMA requires that costs be documented. The County’s contract with Ashbritt
required Ashbritt to comply with the documentation requirements articulated in the
regulations that FEMA applies. Any costs incurred by Ashbritt in operating that camp should
have been documented and provided to the County, and, in turn, to FEMA to support the
public assistance claim. While we understand the County’s position that it is better to have
capacity and not use it than to need capacity and not have it, FEMA need not waive its
requirement for documentation of those costs. During the hearing, the County explained that
documentation of costs usually improves as capabilities, such as base camps, are established
and operating. That may be so, but we nonetheless find that Ashbritt’s invoice, without
more, does not satisfy the requirement of adequate documentation.
CBCA 6716-FEMA
9
Decision
We grant the application in part. FEMA shall pay Monroe County $2,497,719.70.
Kathleen J. O’Rourke
KATHLEEN J. O’ROURKE
Board Judge
Harold D. Lester, Jr.
HAROLD D. LESTER, JR.
Board Judge
I write separately from the majority of the panel, because I conclude that the applicant
should receive zero reimbursement. Having considered the entire record, I make a decision
I believe FEMA itself should have made upon fairly and impartially applying applicable law
and FEMA policies to the evidence in the arbitration record. Here I provide a rationale, as
is appropriate in an arbitration matter.
For the additional work (related to the base camps), the applicant’s (that is, the
county’s) contract initially did not price the additional services. However, “If Additional
Services are required, such as those listed above, the COUNTY shall issue a letter requesting
and describing the requested services to the CONTRACTOR. The CONTRACTOR shall
respond with a fee proposal to perform the requested services. Only after receiving an
amendment to the Agreement and a notice to proceed from the COUNTY, shall the
CONTRACTOR proceed with the Additional Services.” Further, “Rates shall be inclusive
of all reimbursable expenses.”
As evidenced by emails, additional services were added to the contract. The
applicant’s contract to obtain base camps specifies that the applicant would pay rates similar
to those that the State of Florida would have charged, approximated as a rate per person per
day. There is no written agreement for the applicant to pay anything more than such rates,
which were stated as reflecting the contractor’s total charges for the ordered services, and
no agreement that the applicant would provide compensation for management or other
charges in excess of such rates. That contract determines the maximum amount that FEMA
CBCA 6716-FEMA
10
should reimburse the applicant for the base camps. The contract referenced by the applicant
and panel did not have base camps as an element of the competition. The pricing found in
an exhibit to the contract is less than what the applicant actually paid; e.g., the exhibit
identifies pricing which increases with camp size for mobilization and demobilization efforts.
The record does not provide a basis for me to conclude either that the
mobilization/demobilization costs were properly paid under the agreement or that the
amounts were reasonable, given that the payments were approximately three and seven times
the fees identified in the exhibit to the underlying contract.
The parties have paid scant attention to the actual language of the agreement. The
payments made by the applicant and its contractor are not necessarily indicative of
appropriate charges. The arbitration record does not contain reliable, credible evidence on
what rates would have been paid by the State of Florida, the entity referenced in the
applicants’ agreement. Moreover, the applicant did not utilize the grantee (a party to this
proceeding), which should have such information, nor did the grantee provide support for
what rates the State of Florida would have charged.
FEMA’s initial denial of reimbursement was appropriate, given the lack of support
provided by the applicant. The applicant should have provided support with its application
or first appeal. The additional information provided during the arbitration proceeding does
not justify payment by FEMA. At best, the record reveals an entitlement to a per person, per
day charge for use of one of the camps, at the rate the State of Florida would have paid. The
record does not support a rate. The anecdotal range presented by the applicant and its
contractor is not convincing that even a suggested fee of $180 per person would be
appropriate for the average daily usage by 4820 persons at the one camp actually utilized.
Although the product of the rate per person and number of persons ($180 x 4820) is
$867,600, payment is not appropriate because the rate is not adequately supported by the
record. The applicant and grantee had the opportunity to supplement the record with specific
proof; they failed to do so. The additional compensation the applicant seeks for
mobilization, demobilization, and other charges is not consistent with its contract. I would
not obligate FEMA to reimburse any such costs.
_Joseph A. Vergilio
JOSEPH A. VERGILIO
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.