DISMISSED IN PART: October 18, 2016

Agency decision

Ask Donna

What actually matters in this document.

Text

DISMISSED IN PART: October 18, 2016

CBCA 5299

SYLVAN B. ORR,

Appellant,

v.

DEPARTMENT OF AGRICULTURE,

Respondent.

Sylvan B. Orr, pro se, Idaho Falls, ID.

Daniel B. Rosenbluth, Office of the General Counsel, Department of Agriculture,

Golden, CO, counsel for Respondent.

Before Board Judges GOODMAN, WALTERS, and LESTER.

LESTER, Board Judge.

On April 26, 2016, appellant, Sylvan B. Orr, filed an appeal of a contracting officer’s

decision dated March 18, 2016. In response to the complaint that Mr. Orr subsequently filed

with the Board on May 27, 2016, the United States Forest Service (an entity within the

Department of Agriculture, the respondent in this appeal) requested that we address several

“threshold issues” that it believed would allow this case to proceed expeditiously. On August

25, 2016, after two extensive telephonic conferences with the parties, the Board issued a

show cause order requesting that the parties address three issues the resolution of which

CBCA 5299

2

could be dispositive of this appeal. Both parties have responded to the show cause order, and

Mr. Orr has also submitted a response to the Board’s order of September 23, 2016, in which

we requested additional information. We have thoroughly considered the arguments that the

parties made during the telephonic conferences and in response to the show cause order, and

we have thoroughly reviewed all of the documents in the appeal file.

Factual Background

I.

The Solicitation and Award

The Forest Service issued a request for quotations (RFQ) seeking “to obtain Weed

Washing Units1 for use on a local, Regional and Nationwide basis” for fire suppression and

all-hazard incidents. Appeal File, Exhibit A at 27-28.2 The RFQ indicated that the agency

would award “a sufficient number of I-BPAs [Incident Blanket Purchase Agreements]

anticipated to meet incident resource needs resulting from this solicitation to responsible

quoters whose quotes conforming to the solicitation will be advantageous to the Government,

price and other factors considered.” Id. at 15 (clause B.3(a)). The RFQ further provided that

“[t]he number of I-BPAs awarded will be determined based upon historical usage and other

relevant data such as predictive services information, available personnel to administer

agreements, etc.” Id.

The RFQ made clear that, if a contractor received an I-BPA, there was no guarantee

that any orders would ever be placed under it and that, if the agency placed an order, the

contractor would be encouraged but not required to accept it:

This solicitation will result in multiple agreements. The dollar limitation for

any individual order is $150,000.00. Since the needs of the Government and

availability of Contractor’s resources during an emergency cannot be

determined in advance, it is mutually agreed that, upon request of the

Government, the Contractor shall furnish the resources listed herein to the

1

A weed washing unit includes all equipment (including, among other things,

portable commercial high-pressure power washers) necessary for washing fire engines, heavy

equipment, logging equipment, and other vehicles to remove soil, plant parts, and seeds from

them during a fire suppression or all-hazard incident; transportation of the weed washing

equipment to and from an incident site; set up and take down of that equipment; and at least

two skilled operators to perform operations. Exhibit A at 28-30.

2

All exhibits referenced in this decision are found in the appeal file, unless

otherwise noted.

CBCA 5299

3

extent the Contractor is willing and able at the time of order. Due to the

sporadic occurrence of incident activity, the placement of any orders IS NOT

GUARANTEED.

Exhibit A at 14 (clause B.2(a)) (emphasis added). The RFQ also made clear that the award

of I-BPAs “does not preclude the Government from using any Agency or Agency Cooperator

owned resources before equipment is mobilized under this Agreement.” Id. at 31 (clause

D.6(a)).

The RFQ provided that numerous individuals – dispatchers, buying team members,

finance section chiefs, procurement unit leaders, contracting officers, and purchasing agents,

see Exhibit A at 26 (clause C.4) – could place orders against an I-BPA, but that any such

orders, to be effective, had to “be placed in accordance with established ordering procedures

as specified in National and Regional mobilization guides.” Id. Orders were to “originate

from the host dispatch center.” Id. at 34 (clause D.6.9). The RFQ stated that “[e]ach host

dispatch center will give dispatch priority to the resource offering the greatest advantage” to

the Government “before all other private resources not under Agreement” except in certain

specifically identified circumstances. Id. at 31 (clause D.6.1(a)). It also provided that

“[r]esources on an awarded Agreement will be ranked on a dispatch priority list” by a host

dispatch zone, id. at 32 (clause D.6.2(a)); that “each host dispatch center will have an

established dispatch priority list showing [those] resources,” id. (clause D.6.3.1); and that the

Government “intends to dispatch contractor resources based on this priority ranking other

than for initial attack.” Id. The RFQ also identified the procedures that the agency would

use to place an order with a contractor (through the delivery of certain information, including

an incident order number, the date and time to report to the incident, and incident contact

information), id. at 32-33 (clause D.6.4.1(a)), and established the manner in which the

contractor would accept the order:

D.6.5 – DISPATCHING PROCEDURES

D.6.5.1 – When receiving the dispatch call, the Contractor shall confirm their

availability and ability to meet specified timeframes. If the Contractor cannot

be reached or is not able to meet the time and date needed, the dispatcher may

proceed with contacting the next resource on the dispatch priority list.

Contractor shall check in at the assignment at the time agreed upon when

dispatched.

Id. at 33. The RFQ expressly precluded dispatchers at the host dispatch center from

providing any contractor with pre-assignment information, “such as ‘when or if a Contractor

will be called for an assignment’ or ‘status of other contractors.’” Id. at 31 (clause D.6(b)).

CBCA 5299

4

The RFQ further provided that, for each order that the contractor performed, the

Forest Service would undertake a written performance evaluation, as follows:

D.20 – PERFORMANCE EVALUATIONS

Performance evaluations will be performed at the incident using the form in

Exhibit E. The evaluation will be completed at the incident by the government

representative supervising the work. This form is the preferred performance

evaluation to be accepted by the Contracting Officer. The evaluators [sic]

signature shall be legible and printed on the form. If the supervising

Government representative is released from the incident prior to the release of

the resource, the government representative will complete a performance

evaluation prior to demobilization, for work the resource performed under

their supervision. The Government representative will review the performance

evaluation with the Contractor, record Contractor comments, and obtain

Contractor signature acknowledging completion of the evaluation. The

Government evaluator will then give a copy of the evaluation form(s) to the

Contractor at the incident and submit a copy to the incident Finance Section

(for distribution to the Contracting Officer and the Host unit incident file).

Exhibit A at 38-39; see Exhibit C at 117. The parties originally indicated that this clause was

subsequently modified to include somewhat different language, see Complaint ¶ 5; Answer

¶ 5, but the Forest Service has since retreated from that position.3 We cannot find any

contract modification amending the original clause in the appeal file, but, reading the alleged

amendment’s language, any such amendment is not relevant for purposes of this appeal

because the substance of the requirements under clause D.20 remained the same regardless

of which version applies, although the amendment allegedly adds language indicating that

the contracting officer will use the performance evaluation in future procurements when

considering past performance and adds a requirement for a final inspection.

3

In our show cause order, we asked the parties to provide us with a copy of the

contract amendment substituting the alternate version of clause D.20 and to explain the

circumstances under which the substitution occurred, but neither party did so. Instead, the

Forest Service, contrary to the statement in its answer, represented that the version of clause

D.20 applicable to Mr. Orr’s agreement is the one found at page 38 of the appeal file, which

is quoted above. Because of the similarity in the two cited versions of clause D.20, it is

unnecessary for us to attempt to resolve the discrepancy in the Forest Service’s statements.

CBCA 5299

5

On April 9, 2013, the Forest Service awarded Mr. Orr an I-BPA for weed washing

units for Regions 2 and 4 (Rocky Mountain and Intermountain Regions), effective April 9,

2013, through April 9, 2016. Exhibit A at 1. Mr. Orr’s I-BPA incorporated the terms of the

RFQ.

II.

Orders Under the I-BPA

In August 2015, the Central Idaho Interagency Fire Center placed an order under Mr.

Orr’s I-BPA, numbered as resource order no. E-60, for a weed washing unit for the Bobcat

fire in Salmon, Idaho. Exhibit B at 79. According to the appeal file, there was a dispute

upon Mr. Orr’s arrival as to whether the equipment was set up in accordance with I-BPA

requirements, and Mr. Orr or his employee(s) may have been required to relocate the

equipment. Exhibit D at 140-44. In any event, Mr. Orr and/or his employee(s) performed

the work, and, on August 26, 2015, Mr. Orr signed an invoice (on Optional Form 286)

indicating that he had worked on the order from August 22 through 25, 2015, and seeking

payment of $5860. Exhibit D at 180. Above Mr. Orr’s signature on the invoice, which was

also signed by the government receiving officer, was the following pre-printed release

language:

Contract Release For And In Consideration Of Receipt Of Payment In The

Amount Shown On “Net Amount Due” Line 28 [$5860]. Contractor Hereby

Releases The Government From Any And All Claims Arising Under This

Agreement Except As Reserved In “Remarks” Block 22.

Id. In block 22, titled “Remarks,” was the pre-printed word “Final,” and Mr. Orr provided

an additional signature next to the handwritten words “No Damage No Claims” in block 22,

id., although he maintains that he signed the document under duress.

Mr. Orr has also alleged that he requested assignment to the Elevenmile fire incident

and that there was some indication from individuals associated with the Government that he

would obtain the assignment. Ultimately, though, his request was not honored, and he asserts

that he lost work which he “could have reasonably expected the Government” to provide

him. See Complaint at 2.

III.

The E-60 Bobcat Fire Performance Evaluation

On August 25, 2015, as Mr. Orr was completing the E-60 Bobcat fire work, the

government inspector on the site prepared a performance evaluation on the form identified

in the BPA. Exhibit D at 137-38. That evaluation contains comments about the preparedness

and responsiveness of Mr. Orr’s team with which Mr. Orr has informed us he disagrees. The

CBCA 5299

6

government inspector was called to another job and did not review the comments with Mr.

Orr at that time, provide Mr. Orr with the opportunity to comment upon the performance

evaluation, or obtain Mr. Orr’s signature on it, as required by clause D.20 of the BPA.

Nevertheless, the performance evaluation was provided to the contracting officer. Mr. Orr

was not aware that a performance evaluation had been written until some time after he had

executed the release on August 26, 2015.

The contracting officer has since recognized that the proper procedures for completing

the performance evaluation, which required an opportunity for Mr. Orr to comment, were not

followed. Exhibit D at 184. She has informed Mr. Orr that, because of that, she never acted

upon the performance evaluation and did not consider it in evaluating future awards or

performance ratings. Id. She has also notified the Board in a sworn declaration that the

evaluation is not included in the Contractor Performance Assessment Reporting System

(CPARS), that the document is wholly internal to her Forest Service office, that she has not

used it to date and will not use it in the future, and that it “will never be distributed, shared

or utilized by any successor contracting officers.” Declaration of Contracting Officer ¶ 8

(Sept. 26, 2016). She subsequently averred that it has been withdrawn from Mr. Orr’s

contract file and destroyed. Supplemental Declaration of Contracting Officer (Oct. 3, 2016).

IV.

Mr. Orr’s Claim

On September 25, 2015, Mr. Orr submitted what the Forest Service contracting officer

considered to be a claim. Exhibit C at 81-119. In that document, Mr. Orr made various

representations complaining about alleged errors in the performance evaluation and appears

to request that the contracting officer reexamine it:

To sum this up [there] are some remarkable discrepancies between . . .

evaluation ID-SCF-015187 and Facts that should be examined bearing in mind

some considerable time, and expenditures [were] put forth both personally as

well as cooperatively by [Contractor Orr] and employees [sic] individual

preparation and timing.

Id. at 90.

On the last page of the September 25, 2015, document, under the heading “Change

Order or Claim,” Mr. Orr requested $3691 for the E-60 weed washing unit work. Exhibit C

at 119. Of that amount, $1465 was for payment for an additional day of work on August 21,

2015, at Mr. Orr’s daily rate, apparently because of a dispute with the on-site inspector that

required him to relocate equipment, and $2226 (six days at $371 per day) because Mr. Orr

CBCA 5299

7

allegedly could not dispose of waste generated by the project until August 31, 2015. Mr. Orr

indicated on the page that “[t]his is a very condensed version of our claim.” Id.

Subsequently, the contracting officer asked Mr. Orr to clarify what he was requesting

through the September 25, 2015, submission. On January 20, 2016, Arlyn Orr, who is Sylvan

Orr’s son, responded to the contracting officer that the Orrs would provide her with an

invoice “that includes a qualified claim for the amount specific to the terms of the contract.”

Exhibit D at 154.

On or about January 21, 2016, the contracting officer received a supplement to Sylvan

Orr’s September 25, 2015, submission, which was in the form of an invoice titled “Estimate”

and that identified two claims, the Bobcat fire claim previously discussed and a second claim,

not previously identified, for the Elevenmile fire. Exhibit C at 120-23. As for the Bobcat

fire claim, Sylvan Orr provided what he described as an “estimate and time line of the issue,”

id. at 15, and increased the amount requested to $10,255 ($1465 for work on August 21,

2015, and $8790 for six days of pressure washing and trying to deliver solid waste from

August 26 to August 31, 2015). As for the new Elevenmile fire claim, Mr. Orr asserted that

this claim was “a result of extension of” the Bobcat fire claim “due to the Bobcat fire

evaluation.” Id. at 158. He stated that, because the government inspector for the Bobcat fire

work provided Mr. Orr with an unfair performance evaluation on that project and

“discriminated against” him, he did not receive an order for the Elevenmile fire work, work

that he thought he should have gotten. Because the Elevenmile fire lasted from August 28

to September 11, 2015, he felt that he should be paid his daily rate for that period “due to the

unfair treatment by [the government inspector] on the Bobcat fire” and requested payment

of $27,540. Id.

V.

The Contracting Officer’s Decision and the Appeal

On March 18, 2016, the Forest Service contracting officer issued a decision denying

Mr. Orr’s monetary claims. Exhibit E at 197-99. In the decision, she indicated that, with

regard to the E-60 Bobcat fire claim, Mr. Orr had signed a final invoice containing a release

indicating no damage and no claims. Id. at 199. She did not address Mr. Orr’s comments

about the performance evaluation for the E-60 Bobcat fire work. Subsequently, on March 28,

2016, the contracting officer, further addressing the Elevenmile fire claim, provided Mr. Orr

with a copy of the dispatch priority list from the host dispatch center, which showed that Mr.

Orr was fourth in line amongst I-BPA holders for a weed washing unit order, and indicated

that, with three contractors ahead of him in line, he could not have received the Elevenmile

fire work. Exhibit D at 181.

CBCA 5299

8

On April 26, 2016, Mr. Orr filed a notice of appeal, challenging the contracting

officer’s decision “[d]enying his Claim for – equitable adjustment in final pay – due to

[agency] Arbitrary & Capricious Abuse of the contract” and stating that the total amount in

dispute is $37,795. He also asserted in his notice of appeal that the Forest Service had

“failed to observe the mandatory [contract clause] D.20 PERFORMANCE EVALUATIONS,

as well as the FINAL INSPECTION,” in violation of “standard policy prior to

demobilization for work performed under [the inspector’s] supervision.”

VI.

Proceedings Before the Board

After filing his notice of appeal, Mr. Orr filed a complaint with the Board, and the

Government filed an answer. With its answer, the Forest Service requested a telephonic

conference with the Board to address specific “threshold issues” that the Forest Service

wanted the Board to resolve in an “expeditious” manner. The Board conducted an hour-long

telephonic conference with the parties on July 29, 2016, in which Arlyn Orr (upon behalf of

his father), counsel for the Forest Service, and the Forest Service contracting officer

participated. During that conference, the parties discussed in detail the various issues that

Sylvan Orr was raising, addressing their positions on the defects in the performance

evaluations and on the monetary claims. After the Board subsequently conducted a more indepth review of the appeal file, it held a longer telephonic conference with the parties on

August 22, 2016, in which both Sylvan and Arlyn Orr, as well as Mr. Orr’s son-in-law,

participated, along with counsel for the Forest Service and the Forest Service contracting

officer. During that conference, the parties presented their positions on the various issues

raised in the appeal.

Following that conference, the Board issued a show cause order, dated August 25,

2016, asking the parties to address three issues. First, we asked Sylvan Orr to show cause

as to why, in light of the Court of Appeals for the Federal Circuit’s decisions in Ridge

Runner Forestry v. Veneman, 287 F.3d 1058 (Fed. Cir. 2002), and Crewzers Fire Crew

Transport, Inc. v. United States, 741 F.3d 1380 (Fed. Cir. 2014), we should not dismiss his

Elevenmile fire claim for lack of jurisdiction because of the absence of any enforceable

contract for that work. Second, we asked Mr. Orr to address whether he had submitted a

valid claim for the Bobcat fire work and, if he had, whether a final release that he signed

barred recovery for his claim. Third, we asked the parties to address the extent to which we

possessed jurisdiction to entertain Mr. Orr’s complaints about the manner in which his

contractor performance evaluation was conducted and about the contents of that evaluation,

as well as whether those complaints had become moot. Both parties have responded to that

order; Mr. Orr has also responded to a subsequent order, dated September 23, 2016,

requesting additional information; and both parties later submitted additional information.

CBCA 5299

9

Discussion

I.

Mr. Orr’s Pro Se Status

“Generally, we give greater procedural latitude to appellants representing themselves

pro se than we give to parties represented by attorneys.” Brent Packer v. Social Security

Administration, CBCA 5038, et al., 16-1 BCA ¶ 36,260, at 176,896; see 1-A Construction

& Fire, LLP v. Department of Agriculture, CBCA 2693, 15-1 BCA ¶ 35,913, at 175,552,

appeal dismissed, No. 15-1623 (Fed. Cir. Jan. 28, 2016). “[T]his more lenient standard for

interpreting pleadings,” however, “does not change a pro se litigant’s burden of proof or our

weighing of the factual record.” 1-A Construction, 15-1 BCA at 175,552 (quoting House of

Joy Transitional Programs v. Social Security Administration, CBCA 2535, 12-1 BCA

¶ 34,991, at 171,975).

II.

The Elevenmile Fire Claim

Mr. Orr asserts that he should have been, but was not, offered an order for work on

the Elevenmile fire incident and that the Government’s failure to offer him this work cost

him an estimated $27,540. As the agency has correctly argued, we lack jurisdiction to

consider this claim because it arises out of an I-BPA that did not create mutual obligations.

The I-BPA at issue here expressly provided that there was no guarantee that the

Government would ever place any orders under it, Exhibit A at 14 (clause B.2(a)), and it

provided no minimum purchase guarantee. Further, Mr. Orr was not obligated to accept any

order that the Government placed, but was free to decline an order if he so chose. Id.

The Court of Appeals for the Federal Circuit addressed a similar “contract” with the

Forest Service in Ridge Runner Forestry v. Veneman, 287 F.3d 1058 (Fed. Cir. 2002), in

which a fire protection company complained that it had been “systematically excluded” from

providing firefighting services to the Government under tender agreements. Id. at 1060.

Like the I-BPA at issue in this appeal, the tender agreements in Ridge Runner did not

guarantee that the Forest Service would order any equipment and did not require the

contractor to accept any orders that were placed. The Federal Circuit held that such

agreements do not constitute binding and enforceable contracts because they create only

“illusory promises” without any mutuality of obligation:

The Tender Agreements here are nothing but illusory promises. By the phrase

illusory promise is meant words in promissory form that promise nothing; they

do not purport to put any limitation on the freedom of the alleged promisor, but

leave his future action subject to his own future will, just as it would have been

CBCA 5299

10

had he said no words at all. The government had the option of attempting to

obtain firefighting services from [the contractor] or any other source,

regardless of whether that source had signed a tender agreement. The

Agreements contained no clause limiting the government’s options for

firefighting services; the government merely “promised” to consider using [the

contractor] for firefighting services. Also, the Tender Agreement placed no

obligation upon [the contractor]. If the government came calling, [the

contractor] “promised” to provide the requested equipment only if it was

“willing and able.” It is axiomatic that a valid contract cannot be based upon

the illusory promise of one party, much less illusory promises of both parties.

Id. at 1061-62 (citations omitted).

Because “BPAs themselves are not contracts,” we lack jurisdiction under the Contract

Disputes Act (CDA), 41 U.S.C. §§ 7101-7109 (2012), to entertain claims arising out of them.

Zhengxing v. United States, 71 Fed. Cl. 732, 738, aff’d, 204 F. App’x 885 (Fed. Cir. 2006);

see Crewzers Fire Crew Transport, Inc. v. United States, 741 F.3d 1380, 1382-83 (Fed. Cir.

2014) (failure to make “nonfrivolous allegation” that a BPA created mutual obligations is a

jurisdictional defect); Brent Packer, 16-1 BCA at 176,897-98 (Board lacks jurisdiction to

entertain claim arising under a BPA that does not create mutual obligations); Bob Minor

Irrigation Parts & Service v. Department of Agriculture, CBCA 1096, 08-2 BCA ¶ 33,895,

at 167,766 (dismissing claim under similar type of agreement for weed washing units). The

fact that the I-BPA used words that sound contractual in nature or that purport to require the

Government to create priority listings of I-BPA holders does not somehow create mutual

contract obligations or transform the I-BPA into an enforceable contract. To the extent that

Mr. Orr is alleging that he was led to believe from discussions with various individuals that

he would or might receive the Elevenmile fire incident work, the I-BPA made clear that any

orders had to originate from the host resource center, Exhibit A at 34 (clause D.6.9), and, in

any event, Mr. Orr does not allege that any order was ever consummated. Until and unless

the host resource center issued an order that he accepted, he had no contractual rights in the

Elevenmile fire incident work.

We dismiss Mr. Orr’s Elevenmile fire claim for lack of jurisdiction.

III.

The Bobcat Fire Claim

A.

Jurisdiction

Once an order under a BPA is issued by the Government and accepted by the

contractor, a contract comes into being. Brent Packer, 16-1 BCA at 176,898; see

CBCA 5299

11

Cardiometrix, DOT BCA 2571, et al., 94-1 BCA ¶ 26,269, at 130,699 (“Separate contracts

came into being each time the [agency] ordered services [under a BPA] and [the contractor]

provided the requested services.”). Mr. Orr has claimed that he is entitled to recover $10,255

in additional costs under an order that the Government placed, and that he performed, for the

Bobcat fire incident. We possess jurisdiction to entertain this claim because it arises under

a contract that came into existence when Mr. Orr accepted the agency’s Bobcat fire order and

because, in addition, it is the subject of a written claim submission compliant with the

requirements of the CDA.4

B.

Mr. Orr’s Written Release

The agency has argued that Mr. Orr’s Bobcat fire claim is barred by a general release

that Mr. Orr signed to obtain final payment for work performed under the order. “It is well

settled that a contractor who executes a general release is thereafter barred from maintaining

a suit for damages or for additional compensation under the contract based upon events that

occurred prior to the execution of the release.” B.D. Click Co. v. United States, 614 F.2d

748, 756 (Ct. Cl. 1980). “A party who settles,” or provides a release, “may not avoid it by

proof that his claim was just,” as it “has long been held that a release for a lawful

consideration is binding though the contractor received only what was otherwise due him.”

Johnson, Drake & Piper, Inc. v. United States, 531 F.2d 1037, 1044 (Ct. Cl. 1976). “If

parties intend to leave some things open and unsettled, their intent so to do should be made

manifest” in the release itself. United States v. William Cramp & Sons Ship & Engine

Building Co., 206 U.S. 118, 128 (1907).

To determine the scope of a release, we look to its language. “Because a release is

contractual in nature, it is interpreted in the same manner as any other contract term or

provision.” Bell BCI Co. v. United States, 570 F.3d 1337, 1341 (Fed. Cir. 2009).

4

In our show cause order dated August 25, 2016, we asked the parties to address

whether the Bobcat fire claim that Mr. Orr submitted sufficiently identified the basis of Mr.

Orr’s claim, made a monetary request in a sum certain, and requested a contracting officer’s

final decision, as required by the CDA, 41 U.S.C. § 7103(a), and the Federal Acquisition

Regulation (FAR), 48 CFR 2.101 (2015). Although there is some language in Mr. Orr’s

claim and its supplement indicating that the amount claimed was stated as an estimate rather

than as a “sum certain,” see J.P. Donovan Construction, Inc. v. Mabus, 469 F. App’x 903,

908 (Fed. Cir. 2012) (use of qualifying language in identifying monetary amount owed, such

as use of word “approximately,” is not a sum certain), we are convinced after studying the

entirety of the documents that Mr. Orr intended his request for $10,255 to be the definitive

amount sought and that his communication otherwise satisfies the requirements of a claim.

CBCA 5299

12

Accordingly, “[i]f the provisions of a release are ‘clear and unambiguous, they must be given

their plain and ordinary meaning.’” Holland v. United States, 621 F.3d 1366, 1378 (Fed. Cir.

2010) (quoting Bell BCI, 570 F.3d at 1341). Here, the pre-printed release form that Mr. Orr

signed on August 26, 2015, provided a “Contract Release for and in Consideration of Receipt

of Payment in the Amount Shown on ‘Net Amount Due’ Line 28 [$5860]” and indicated that

“Contractor Hereby Releases the Government from Any and All Claims Arising under this

Agreement Except as Reserved in ‘Remarks’ Block 22.” Exhibit D at 180. In block 22 was

the typed word “Final” and the handwritten words “No Damage No Claims,” next to which

Mr. Orr provided a separate and additional signature. Id. As the Court of Claims, the

predecessor to the Federal Circuit, held in Bobbi’s Decorating & Renovation Co. v. United

States, 218 Ct. Cl. 653 (1978), this type of broad release encompasses and waives all claims

arising under a contract:

[P]laintiff signed a full release at about the same time it received the payment

it now calls partial. There was no exception to the release or any indication,

in the release itself or outside, that it did not mean precisely what it said

(plaintiff “hereby releases the Secretary [of the agency] from any and all

claims arising under or by virtue of said contract or any modification or change

thereof”). A full-scale release of that type ends all liability.

Id. at 654 (emphasis added); see Safe Haven Enterprises, LLC v. Department of State, CBCA

3871, et al., 16-1 BCA ¶ 36,444, at 177,624 (discussing effect of general release).

C.

Mr. Orr’s Claim of Duress

“[T]here are ‘special and limited situations’ in which a claim will survive the

execution of a general release.” Turner Construction Co. v. Smithsonian Institution, CBCA

2862, et al., 15-1 BCA ¶ 36,139, at 176,395 (quoting J.G. Watts Construction Co. v. United

States, 161 Ct. Cl. 801, 806 (1963)); see Ingham Regional Medical Center v. United States,

126 Fed. Cl. 1, 38 (2016) (“There are . . . circumstances when a party may bring a claim

despite the execution of an otherwise applicable release.”). “[W]here fraud or duress is

involved,” for example, “the release will not be held to bar the prosecution of the claim.”

J.G. Watts, 161 Ct. Cl. at 807. “Boards of contract appeals have consistently reviewed

assertions by contractors that notwithstanding unambiguous releases in contract

modifications, claims should be considered on their merits because the release language did

not represent the parties’ intentions.” Walsh/Davis Joint Venture v. General Services

Administration, CBCA 1460, 11-2 BCA ¶ 34,799, at 171,262.

In his response to the Board’s show cause order, Mr. Orr argues that his signature

beneath the final payment release “was obtained under duress” and that the entire release

CBCA 5299

13

document is “an unconscionable pretext.” Show Cause Response at 6. He further asserts

that a government employee, not he, added the “No Damage No Claims” language to the

final payment document that Mr. Orr had to sign and that the Government’s act of forcing

Mr. Orr to sign such a release to obtain final payment violated FAR 3.101-1, which provides

that “Government business shall be conducted in a manner above reproach and, except as

authorized by statute or regulation, with complete impartiality and with preferential treatment

for none.” 48 CFR 3.101-1.

The burden of proving that a release’s execution was procured through duress

sufficient to invalidate it is upon the party seeking relief. Klamath & Moadoc Tribes v.

United States, 81 Ct. Cl. 79, 99, aff’d, 296 U.S. 244 (1935); see Riennes Construction Co.,

IBCA 3572-96, et al., 98-2 BCA ¶ 29,821, at 147,658 (“Appellant has the burden to prove

duress” in executing release); Longmire Coal Corp., EBCA 156-2-81, 84-2 BCA ¶ 17,345,

at 86,429 (“Appellant has the burden of proving that what appears to be a binding . . .

agreement was entered into by [appellant] under duress imposed by [the agency].”). In

establishing any claim of economic duress or improper business compulsion in the execution

of a release, there are three common elements that the contractor must show existed at the

time that it was allegedly forced to execute its release: “(1) that one side involuntarily

accepted the terms of another; (2) that circumstances permitted no other alternative; and

(3) that said circumstances were the result of coercive acts of the opposite party.” Fruhauf

Southwest Garment Co. v. United States, 111 F. Supp. 945, 951 (Ct. Cl. 1953). The

contractor “must go beyond the mere showing of a reluctance to accept and of financial

embarrassment” to substantiate its allegation of economic duress or business compulsion.

Id. Instead, the contractor must show wrongful conduct on the Government’s part, not

merely that the Government made a hard bargain:

Economic pressure and “even the threat of considerable financial loss” are not

duress. International Tel. & Tel. Corp. v. United States, 206 Ct. Cl. 37, 52,

n.11, 509 F.2d 541, 549, n.11 (1975). “Economic duress may not be implied

merely from the making of a hard bargain.” Aircraft Associates & Mfg. Co.,

Inc. v. United States, 174 Ct. Cl. 886, 896, 357 F.2d 373, 378 (1966). The

mere stress of business conditions will not constitute duress where the

defendant was not responsible for the conditions. Fruhauf Southwest Garment

Co. v. United States, [126 Ct. Cl. 51, 62, 111 F. Supp. 945, 951 (1953)].

“Some wrongful conduct must be shown, to shift to defendant the

responsibility for bargains made by plaintiff under the stress of financial

necessity.” LaCrosse Garment Mfg. Co. v. United States, 193 Ct. Cl. 168, 177,

432 F.2d 1377, 1382 (1970).

CBCA 5299

14

Systems Technology Associates, Inc. v. United States, 699 F.2d 1383, 1387 (Fed. Cir. 1983)

(emphasis in original) (quoting Johnson, Drake & Piper, Inc., 531 F.2d at 1042-43); see Bish

Contracting Co., IBCA 951-1-72, 73-1 BCA ¶ 9896, at 46,270 (“Economic duress may not

be implied . . . merely from the fact that a hard bargain may have been made.”).

To meet this standard and “render an agreement voidable on grounds of duress it must

be shown that the party’s manifestation of assent was induced by an improper threat which

left the recipient with no reasonable alternative save to agree.” Systems Technology, 699

F.2d at 1387 (quoting David Nassif Associates v. United States, 644 F.2d 4, 12 (Ct. Cl.

1981)) (emphasis added); see Adler Construction Co. v. United States, 423 F.2d 1362, 1365

(Ct. Cl. 1970) (even a contractor’s “desperate financial condition” does not constitute the

type of duress sufficient to vitiate a release, absent improper coercion by the Government).

The types of threats that can render an agreement voidable include improper “threats that

would accomplish economic harm,” “threats that would breach a duty of good faith and fair

dealing under a contract,” and “threats which, though lawful in themselves, are enhanced in

their effectiveness in inducing assent to unfair terms because they exploit prior unfair dealing

on the part of the party making the threat.” Systems Technology, 699 F.2d at 1387 (quoting

David Nassif, 644 F.2d at 12). “A threat does not amount to duress unless it is so improper

as to amount to an abuse of [the bargaining] process.” Restatement (Second) of Contracts

§ 176 cmt. a (1981). In Nash Janitorial Service, Inc., GSBCA 6390, 84-1 BCA ¶ 17,135,

one of our predecessor boards, the General Services Board of Contract Appeals, looked to

the Restatement (Second) of Contracts to attempt to distinguish between the types of

“threats” during negotiations that would constitute duress and the types of conduct in the

bargaining process that would not rise that level:

When a Threat Is Improper

(1)

(2)

A threat is improper if

(a) what is threatened is a crime or a tort, or the threat itself would be

a crime or a tort if it resulted in obtaining property,

(b) what is threatened is a criminal prosecution,

(c) what is threatened is the use of civil process and the threat is made

in bad faith, or

(d) the threat is a breach of the duty of good faith and fair dealing under

a contract with the recipient.

A threat is improper if the resulting exchange is not on fair terms, and

(a) the threatened act would harm the recipient and would not

significantly benefit the party making the threat,

CBCA 5299

15

(b) the effectiveness of the threat in inducing the manifestation of

assent is significantly increased by prior unfair dealing by the party

making the threat, or

(c) what is threatened is otherwise a use of power for illegitimate ends.

Id. at 85,369.

Here, Mr. Orr has not identified any threat or coercion by an agency employee.

Instead, he has alleged that he “does not have unlimited operating capitol [sic] and could not

at the time [of signing the release] on short notice have easily covered the payroll and

expenses without making some type of financial sacrifice or seeking an operating loan, or

high Interest Pay day loan . . . of some sort.” Appellant’s Supplemental Response at 2 (Sept.

29, 2016). That type of financial situation does not constitute the type of government-created

coercion that would vitiate the finality of a release. It is, instead, a type of external economic

pressure that, while obviously causing hardship for a contractor, we cannot attribute to the

Government. International Telephone & Telegraph Corp., 509 F.2d at 549 n.11; Adler

Construction, 423 F.2d at 1364.

Mr. Orr also attempts to distance himself from the words “No Damage No Claims”

in block 22 of the form in which the release is contained, asserting that it was a Forest

Service employee (not he) who handwrote those words. Nevertheless, Mr. Orr acknowledges

that he signed the release after those words were written there. The written language on the

form clearly indicated that the signatory was releasing all claims under the contract other than

those specifically identified and reserved in block 22. Further, Mr. Orr has not alleged any

facts indicating that he was barred from listing specific claims in block 22 if he wanted to

exempt them from the scope of the release or that he otherwise could not have objected to

the full release before he signed it. “The time to have reserved such claims was upon the

execution of the release, and we cannot passively assume that their reservation in the release

would have caused the Government to deny him the final payment.” Adler Construction, 423

F.2d at 1364.

Mr. Orr also suggests that his burden of establishing duress should be reduced because

the agency failed to satisfy its obligations under FAR 3.101-1, which addresses the

Government’s obligation to conduct business “in a manner above reproach” and to expend

public funds with “the highest degree of public trust and an impeccable standard of conduct.”

That standard, he alleges, creates heightened obligations for Government actors that should

vitiate releases created in violation of that standard, and he alleges that the Government did

not meet that standard in its dealings with him. FAR 3.101-1 creates a general standard for

government behavior that is intended to protect “the integrity of the government procurement

process” and “the integrity of the system,” rather than to protect “a particular interest of the

CBCA 5299

16

contractor.” INSLAW, Inc. v. United States, 40 Fed. Cl. 843, 858-59 (1998). FAR 3.101-1

does not, in and of itself, create an actionable claim by a contractor for its violation during

performance of a contract, beyond and outside the context of a specific breach of a particular

contract provision or a specific violation of the duty of good faith and fair dealing under an

existing contract. See, e.g., Cannon v. University of Chicago, 441 U.S. 677, 690 n.13 (1979)

(“the Court has been especially reluctant to imply causes of action under statutes” or, here,

regulations “that create duties on the part of persons for the benefit of the public at large”);

Shero v. City of Grove, Oklahoma, No. 05-CV-0137, 2006 WL 3196270, at *9 (N.D. Okla.

Nov. 2, 2006) (law enacted for public benefit does not generally create private right of action

for monetary damages). Similarly, it provides no basis for somehow lessening a contractor’s

burden of excusing itself from the effect of a release that it voluntarily signed. In any event,

Mr. Orr has not alleged, much less provided any evidence showing, that his execution of the

release was the product of any type of coercion or threat by the Government.

Mr. Orr cannot avoid the release based upon a claim of duress.

D.

Mr. Orr’s Claim Based Upon Post-Release Actions

Although a portion of Mr. Orr’s Bobcat fire claim covers work that pre-dates and is

barred by Mr. Orr’s execution of the release on August 26, 2015, Mr. Orr asserts that the

release should not apply to that portion of his Bobcat fire claim relating to events that

occurred after his execution of the release. Under Mr. Orr’s I-BPA, at the conclusion of each

order that it placed, the Forest Service was to “[r]emove solid waste or designate an

appropriate disposal site” for it. Exhibit A at 28 (clause D.2.1(e)(3)). Correspondingly, Mr.

Orr was to “[c]apture, package and label solid waste in secure, easily transportable

containment packages/devices, approved by the government representative at the incident,

and place them at a location specified by the government.” Id. at 29 (clause D.2.1(f)(7)).

Mr. Orr asserts that the Forest Service employee directed him to dispose of solid waste, but

provided “no instruction as to where to dispose of it.” Exhibit C at 121. For the six days

beginning August 26 and ending August 31, 2015 (after he executed the release at issue

here), Mr. Orr alleges, he actively “made efforts to find out where [the Forest Service

employee] wanted the solid waste disposed of,” and the employee “was negligent,” after Mr.

Orr’s execution of the release, “in his duty to designate a proper disposal site.” Id.; see

Exhibit D at 152.5

5

The Forest Service has presented evidence disputing Mr. Orr’s version of what

happened after Mr. Orr executed the release on August 26, 2015. At this stage of

proceedings, we cannot resolve disputed facts about Mr. Orr’s claim. Resolution will require

further development of the record.

CBCA 5299

17

Absent special circumstances, a general release only serves to preclude those claims

“based upon events which occurred prior to the execution of the release.” H.L.C. &

Associates Construction Co. v. United States, 367 F.2d 586, 590 (Ct. Cl. 1966); see B.D.

Click Co., 614 F.2d at 756; Johnson, Drake & Piper, Inc., 531 F.2d at 1047. Although it is

conceivable that parties to a government contract could agree to release future claims

resulting from future government actions, such a release would require very clear and explicit

language to that effect. See, e.g., Augustine Medical, Inc. v. Progressive Dynamics, Inc., 194

F.3d 1367, 1372-74 (Fed. Cir. 1999); Vita-Herb Nutriceuticals Inc. v. Probiohealth LLC, No.

11-1463, 2012 WL 3903454, at *6 (C.D. Cal. Sept. 6, 2012); Matlock v. National Union Fire

Insurance Co. of Pittsburgh, 925 F. Supp. 468, 473 (E.D. Tex. 1996). We do not have such

clear and explicit language here. To the extent that Mr. Orr’s solid waste disposal claim is

based upon a Forest Service employee’s alleged actions, or inactions, after execution of the

release, the release, at least based upon the information currently in the record, does not bar

that claim.

Although Mr. Orr’s claim for monies associated with the August 21 work pre-dating

the release are dismissed, we will schedule further proceedings with regard to Mr. Orr’s

claim seeking monies associated with work from August 26 to 31, 2015.

IV.

Mr. Orr’s Performance Evaluation

A.

Procedural Challenges to the Performance Evaluation

Mr. Orr has challenged the performance evaluation that the Forest Service created at

the conclusion of the Bobcat fire order, disputing its conclusions and challenging the

procedures under which it was created. The Forest Service questions our authority to

consider Mr. Orr’s challenge.6

In Todd Construction, L.P. v. United States, 656 F.3d 1306 (Fed. Cir. 2011), the

Federal Circuit held that, under the CDA, a contract “claim” that is subject to review by the

Court of Federal Claims or a board of contract appeals may involve a challenge to certain

aspects of a performance evaluation. The Court recognized that, under the FAR, the

definition of “claim” includes not only requests for payment of money in a sum certain and

for the adjustment or interpretation of contract terms, but also requests for “other relief

arising under or relating to the contract.” Id. at 1311 (quoting 48 CFR 2.101). Finding that

6

In challenging Mr. Orr’s performance evaluation claim, the Forest Service argues

that the claim is barred by the August 25, 2015, release. Based upon our resolution of Mr.

Orr’s performance evaluation claim below, we need not address this argument.

CBCA 5299

18

the term “relating to” is one “of substantial breadth,” id. at 1312, the Court held that a

non-monetary dispute can be the subject of a claim if it has “some relationship to the terms

or performance of a government contract.” Id. (quoting Applied Cos. v. United States, 144

F.3d 1470, 1478 (Fed. Cir. 1998)). Although “unsatisfactory performance evaluations may

not relate to the terms of the contract itself,” the Court found, “they relate to [the

contractor’s] performance under the contract” and, therefore, are properly the subject of a

“claim.” Id. at 1313. Accordingly, a contractor’s challenge to a performance evaluation can

constitute a matter within the Board’s subject matter jurisdiction.

That being said, the Federal Circuit made clear that not every aspect of a performance

evaluation is subject to challenge as a contract “claim,” specifically excluding challenges

based upon “minor procedural violations.” Todd Construction, 656 F.3d at 1315. As the

Armed Services Board of Contract Appeals explained in Raytheon Co., Space & Airborne

Systems, ASBCA 57801, et al., 15-1 BCA ¶ 36,024, any defect in a performance evaluation

must have a prejudicial effect upon the contractor if a board is to exercise jurisdiction to

entertain a challenge to it:

[T]he Federal Circuit has required contractors to show a prejudicial violation

of a regulation in comparable circumstances. In Todd Construction, L.P. v.

United States, 656 F.3d 1306 (Fed. Cir. 2011), a contractor contended that the

contracting officer failed to follow the requirements of a pertinent regulation

while issuing a performance evaluation. The court of appeals found, however,

that the contractor had “alleged nothing to indicate that the outcome of the

performance evaluations would have been any different if the purported

procedural errors had not occurred.” Id. at 1316. The court of appeals held

that “[i]n general, standing requires that the plaintiff show an injury in fact, ‘a

casual connection between the injury and the conduct complained of,’ and that

his injury would likely be redressable by court action.” Id. at 1315 (quoting

Lujan v. Defenders of Wildlife, 504 U.S. 555, 560 (1992)). As a result, the

Federal Circuit held that the contractor lacked standing to sue with respect to

these procedural violations. See id.

Id. at 175,959; see GSC Construction, Inc., ASBCA 58747, 14-1 BCA ¶ 35,714, at 174,868

(agreeing with the Government’s argument that, “regardless of whether procedural violations

occurred [in preparing the performance evaluation], appellant has failed to offer any proof

that it was prejudiced as a result thereof”).

Mr. Orr asserts that the performance evaluation was improper because the government

inspector “did not review the performance evaluations with the contractor, record contractor

comments, and obtain contractor signature acknowledging completion of the evaluation in

CBCA 5299

19

observance of [contract clause] D.20.” Complaint ¶ 8. The Forest Service does not deny that

these procedures, which clause D.20 contemplates, were not followed. Yet, Mr. Orr

acknowledges that he received a copy of the performance evaluation on or about October 12,

2015, Complaint ¶ 7.C, and, to the extent that it prejudices him, he is free to comment upon

and dispute it now. The errors about which Mr. Orr complains are procedural missteps that

the Federal Circuit held in Todd Construction do not give rise to a cause of action under the

CDA.

Mr. Orr also complains that no final inspection was performed. See Complaint ¶ 9.

We have no jurisdiction to consider this argument because, as far as we can tell, it is not

mentioned in his claim, much less identified as a non-monetary dispute that the contracting

officer was required to decide. See Magwood Services, Inc. v. General Services

Administration, CBCA 4975, slip op. at 5 (Dec 3, 2015) (“The Board cannot exercise

jurisdiction over a claim that was never presented to the contracting officer for a final

decision.”). Further, the contracting officer has provided Mr. Orr with what she has told him

is the final inspection document. Exhibit D at 172, 177, 184. Although Mr. Orr complains

that he would like the document “officially formatted” in a different way, he has no basis

under his contract for demanding, or using the Board to obtain, such action. We must

dismiss this procedural challenge.

B.

Substantive Challenges to the Performance Evaluation

That leaves us with Mr. Orr’s challenge to the substance of each sentence in the Forest

Service’s performance evaluation. He essentially disputes the accuracy of everything in the

evaluation. The Federal Circuit has held that a contractor “clearly does have standing to sue

based on its substantive allegation that the government acted arbitrarily and capriciously in

assigning an inaccurate and unfair performance evaluation.” Todd Construction, 656 F.3d

at 1316; see MicroTechnologies, LLC, ASBCA 59911, et al., 16-1 BCA ¶ 36,354, at

177,235-36 (finding jurisdiction to consider challenge to allegedly flawed performance

evaluation); GSC Construction, 14-1 BCA at 174,868 (“GSC also alleges that the Navy’s

final performance evaluation is arbitrary and capricious because it is based on erroneous

factual conclusions regarding its performance under the contract, which necessarily requires

an examination of the details of GSC’s performance that underlie the Navy’s adverse

ratings.” (citation omitted)). Under the Federal Circuit’s decision in Todd Construction, we

normally would have jurisdiction to consider this aspect of Mr. Orr’s non-monetary claim.

In this case, though, the Forest Service contracting officer has made clear that Mr.

Orr’s challenge to the particular performance evaluation at issue here has become moot.

During two conference calls with the Board, she reported that, because Mr. Orr had not had

an opportunity to comment upon the performance evaluation before it was provided to her

CBCA 5299

20

and because she recognized that procedural defect, she never acted upon the performance

evaluation and never considered it when making future awards or developing performance

ratings, and she referred us to an April 2016 email message to Mr. Orr to that effect. Exhibit

D at 184. It is not included in the CPARS or any other database and is used only internally

within the Forest Service office involved here for consideration for future awards. The

contracting officer did not use the performance evaluation for any purpose, has now

withdrawn it from Mr. Orr’s contract performance file and destroyed it, and has attested that

it will not “be taken into consideration for any future awards or performance evaluations,”

and “it will never be distributed, shared or utilized by any successor contracting officers.”

Declaration of Contracting Officer ¶ 8 (Sept. 26, 2016).

A matter becomes “moot when the issues presented are no longer ‘live’ or the parties

lack a legally cognizable interest in the outcome.” NEC Corp. v. United States, 151 F.3d

1361, 1369 (Fed. Cir. 1998) (quoting Powell v. McCormack, 395 U.S. 486, 496 (1969)). To

the extent that an agency withdraws a negative performance evaluation such that it cannot

influence future evaluations of the contractor, that action, which eliminates the harm

resulting from the negative evaluation, can moot a challenge to it. See Gittens v. Department

of Homeland Security, 124 F. App’x 653, 654 (Fed. Cir. 2005) (case was properly dismissed

as moot where agency had rescinded its unsuitability determination, even though petitioner

“appears to dispute that the adverse action was rescinded”). If a matter becomes moot, “it

no longer presents a justiciable controversy over which a federal court may exercise

jurisdiction.” Humane Society of the United States v. Clinton, 236 F.3d 1320, 1331 (Fed. Cir.

2001) (quoting NEC Corp. v. United States, 151 F.3d 1361, 1369 (Fed. Cir. 1998)). That

same mootness doctrine applies to and limits the authority of the Board. See, e.g.,

AeroVironment, Inc., ASBCA 58598, et al., 16-1 BCA ¶ 36,337, at 177,180-81; Air, Inc.,

GSBCA 7687, et al., 1985 WL 17107 (Nov. 5, 1985).

Nevertheless, the agency’s rescission or cancellation of the challenged document

“must be complete in order for the appeal to be deemed moot and to relieve [a tribunal] of

its statutory obligation to decide the appeal.” Kagel v. Department of the Army, 126 F.3d

1455, 1458 (Fed. Cir. 1997) (citing Bruning v. Veterans Administration, 834 F.2d 1019, 1021

(Fed. Cir. 1987)). “The burden rests with [the respondent] to demonstrate that an action is

moot.” Harris Patriot Healthcare Solutions, LLC v. United States, 95 Fed. Cl. 585, 592

(2010).7

7

Mr. Orr has informed us that he recently sold his weed washing equipment and is

now out of that business. Because he conceivably could elect to purchase new equipment

and reenter that field, we cannot say, despite the agency’s suggestion to the contrary, that the

equipment sale is enough to render his performance evaluation challenge moot.

CBCA 5299

21

Because we can review challenges to performance evaluations only to the extent that

the contractor can show that the Government’s missteps prejudice the contractor, Todd

Construction, 656 F.3d at 1315, the Forest Service can meet its burden of proving mootness

by establishing that the disputed performance evaluation will never have any effect upon Mr.

Orr’s future consideration for awards. The Forest Service has satisfied that burden. Because

the current performance evaluation can have no effect upon Mr. Orr’s ability to obtain future

awards, there is no actual controversy affecting any legally cognizable interest for us to

review.

From the Board’s communications with Mr. Orr, it is clear that he is extremely upset

about his performance evaluation, does not like what it said, and disagrees with the views of

the Forest Service employee who drafted it. Although the mere fact that the negative

evaluation was written will likely continue to bother him, the Board is not a forum for

resolving every factual disagreement that a contractor may have with the Government,

regardless of its ultimate lack of effect upon the contractor’s rights. Even in the best of

circumstances, we can review a performance evaluation only to assess whether it was

arbitrary and capricious, but we cannot direct the Government to revise it in a particular way

through some form of injunctive relief. See, e.g., MicroTechnologies, LLC, ASBCA 59911,

et al., 15-1 BCA ¶ 36,125, at 176,350; Versar, Inc., ASBCA 56857, 10-1 BCA ¶ 34,437, at

169,959. Further, to the extent that we can review a contractor’s factual challenges to a

performance evaluation under the rationale of Todd Construction, there must be some

quantifiable prejudice to the contractor from the performance evaluation, meaning “[d]amage

or detriment to one’s legal rights or claims.” Black’s Law Dictionary 1370 (10th ed. 2014).

Mr. Orr’s bruised feelings, even if justified, are not enough to invoke the authority of the

Board. Any challenges to the only performance evaluation that is before us for review are

now moot.

If this appeal were pending in federal court, “[m]ootness [would be] a jurisdictional

question because [courts are] ‘not empowered to decide moot questions or abstract

propositions’” for which no case or controversy, as required by Article III of the United

States Constitution, exists. North Carolina v. Rice, 404 U.S. 244, 246 (1971) (quoting

United States v. Alaska Steamship Co., 253 U.S. 113, 116 (1920)). “[M]ootness is an

exception to ‘the long-standing rule in the Federal courts that jurisdiction is determined at

the time the suit is filed and, after vesting, cannot be ousted by subsequent events, including

action by the parties.’” CBY Design Builders v. United States, 105 Fed. Cl. 303, 329 (2012)

(quoting F. Alderete General Contractors, Inc. v. United States, 715 F.2d 1476, 1480 (Fed.

Cir. 1983)). “Traditionally,” however, “the boards of contract appeals, when dismissing

cases for mootness, have not linked such dismissals to a lack of jurisdiction,” Air, Inc., 1985

WL 17107, apparently, at least in part, because the Board’s jurisdiction arises under Article I

rather than Article III. Sperry Corp., GSBCA 8208-P, et al., 86-1 BCA ¶ 18,704, at 94,078;

CBCA 5299

22

Custodial Guidance Systems, Inc., GSBCA 6531, 83-1 BCA ¶ 16,278, at 80,886; see

Grammco Computer Sales, Inc., GSBCA 9612-P, 88-3 BCA ¶ 21,118, at 106,613

(dismissing protest with prejudice as moot); North American Automated Systems Co.,

GSBCA 9179-P, 88-1 BCA ¶ 20,258, at 102,516 (1987) (same). Although there is authority

for the proposition that an Article I tribunal (like the Board) subject to review by an Article

III appellate body should treat the case-or-controversy requirement as a jurisdictional

necessity, see CBY Design, 105 Fed. Cl. at 328 (“[w]hen a matter before [an Article I] court

is subject to review by the Federal Circuit, an Article III court, mootness is not merely a

matter of prudence” (citations omitted)), we are guided by the precedent of our predecessor

board, see Business Management Research Associates, Inc. v. General Services

Administration, CBCA 464, 07-1 BCA ¶ 33,486, at 165,989 (adopting decisions of

predecessor boards as precedent), and dismiss Mr. Orr’s challenge to the contents of his

performance evaluation for failure to state a claim.

Decision

For the foregoing reasons, we DISMISS Mr. Orr’s appeal IN PART. We dismiss his

monetary claim for unassigned Elevenmile fire incident work for lack of jurisdiction; dismiss

with prejudice his monetary claim arising out of work on August 21, 2015, under the Bobcat

fire incident order for failure to state a claim; dismiss his procedural challenges to the

agency’s performance evaluation for lack of jurisdiction; and dismiss his remaining

challenges to the performance evaluation as moot. By separate order, we will schedule

further proceedings on Mr. Orr’s monetary claim arising out of work from August 26 to 31,

2015, under the Bobcat fire incident order.

______________________________

HAROLD D. LESTER, JR.

Board Judge

We concur:

____________________________

ALLAN H. GOODMAN

Board Judge

_____________________________

RICHARD C. WALTERS

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.