GRANTED IN PART: April 6, 2016

Agency decision

Ask Donna

What actually matters in this document.

Text

GRANTED IN PART: April 6, 2016

CBCA 4068

SYSTEMS MANAGEMENT AND RESEARCH

TECHNOLOGIES CORPORATION,

Appellant,

v.

DEPARTMENT OF ENERGY,

Respondent.

Lorenzo F. Exposito, Washington, DC, counsel for Appellant.

James J. Jurich and Charmaine A. Howson, Office of the General Counsel,

Department of Energy, Washington, DC, counsel for Respondent.

Before Board Judges DANIELS (Chairman), KULLBERG, and LESTER.

LESTER, Board Judge.

Pending before us are the appellant’s motion for partial summary relief and the

Government’s cross-motion for summary relief.

Appellant, Systems Management and Research Technologies Corporation

(SMARTECH), argues in its motion that, under a proper interpretation of the contract at issue

here, it was entitled to be paid a sum certain “fixed fee” for the contract’s second base year

period and for each of four option periods. Respondent, the Department of Energy (DOE),

asks us to find that the “fixed fee” referenced in the contract was not a sum certain dollar

amount, but an eight-percent markup to SMARTECH’s hourly direct labor rate charges

(subject to a fee ceiling).

CBCA 4068

2

In addition, each party seeks summary relief upon SMARTECH’s requests for interest

under the Prompt Payment Act (PPA), 31 U.S.C. §§ 3101-3907 (2012). According to

SMARTECH, DOE failed timely to pay the fixed fee amounts that SMARTECH sought in

its 2010 request for equitable adjustment (REA) and, in addition, to release a retainage after

SMARTECH provided DOE with a final payment release.

DOE also requests that we grant summary relief in its favor upon SMARTECH’s

claim that DOE diverted work away from its contract in its final option year, which

SMARTECH asserts should entitle it to recover rental charges that it incurred for office

space that, because of the diversion, it did not need.

For the reasons explained below, we grant appellant’s motion for summary relief on

its “fixed fee” claim, but we grant the Government’s motion for summary relief on

SMARTECH’s PPA and diversion claims.

Background

I.

The Original Request for Proposals

On June 10, 2002, DOE issued a request for proposals (RFP), no. DE-RP0102SO20138, seeking specialized technical support to the Office of Classified and Controlled

Information Review (OCCIR) in reviewing classified and unclassified-but-sensitive

documents. Appellant’s Statement of Uncontested Facts (ASUF) ¶ 1; Appeal File, Exhibit

1 at 7, 13 (§§ B.1, C.1).1 In a cover letter to the RFP, DOE indicated that it contemplated

award of “[a] single, fixed rate, fixed fee, level of effort, task assignment, term type contract,

with performance incentives.” Exhibit 1 at 1; see id. at 88 (RFP § L.9: “The Government

contemplates award of a fixed rate, fixed fee, labor hour contract resulting from this

solicitation.”). Nevertheless, DOE also indicated that it “reserve[d] the right to award any

type of contract deemed appropriate.” Id. at 1; ASUF ¶ 1. The acquisition was set-aside for

small businesses. Exhibit 1 at 1, 89-90.

“Sections A through J of the RFP represent[ed] a draft contract [which was to] be the

basis for the contractual relationship between DOE and the selected offeror . . . .” ASUF ¶ 2

(quoting the RFP cover letter, Exhibit 1 at 1); see Exhibit 1 at 80 (RFP § L.2: “Any contract

1

All exhibits referenced in this decision are found in the appeal file, unless otherwise

noted. Further, to the extent that we cite to the ASUF or to Respondent’s Statement of

Uncontested Facts (RSUF) in this decision, the responding party admitted, or did not contest,

those proposed facts.

CBCA 4068

3

awarded as a result of the solicitation will contain PART I – The Schedule, PART II –

Contract Clauses, and PART III – List of Documents, Exhibits and Other Attachments.”).

Section B.3 of the RFP contained a clause titled “Direct Labor Rates” in which offerors were

to propose fixed hourly labor rates for various labor categories, as well as an “other direct

cost not-to-exceed” amount, a “fixed fee,” and a “ceiling price” for the base period, as

follows:

B.3 Direct Labor Rates (JUL 1991)

The Contractor shall provide [direct productive labor hours (DPLH)] from the

labor categories set forth as follows at the fixed hourly labor rates indicated:

** The following sample is to be used as a guide in completing ALL labor

categories

Year One

Regular Time

Hourly Rate

Program Manager

Prime: Key: (name)

$

Task Area Coordinator

Prime: Key: (name)

Sub 1: Key: (name)

Sub 2: Key: (name)

Document Reviewer

Prime:

$

Sub 1:

Sub 2:

Consultant:

Other Direct Cost

Not-To-Exceed

$ __________

Fixed Fee

$

CBCA 4068

CEILING PRICE – BASE PERIOD

4

$

*Overtime may only be authorized in writing by the Contracting Officer.

The rates indicated for each year of the contract shall apply to all DPLH

provided during that respective year of the contract.

Exhibit 1 at 7-8. In response to section B.6 of the RFP, the offeror was to provide labor,

“Other Direct Cost” (ODC) “Not-To-Exceed,” and “Fixed Fee” pricing in a similar manner

for each of three option years. See id. at 9-11.

The RFP indicated that “[p]ayment shall be made for DPLH provided in accordance

with” the contract clause titled “Payments under Time-and-Materials and Labor-Hour

Contracts” at Federal Acquisition Regulation (FAR) 52.232-7 (48 CFR 52.232-7 (2001)).

See Exhibit 1 at 42 (§ H.14(a)), 48. Pursuant to that FAR clause, the agency would pay the

“hourly rate” for “all labor performed on the contract that meets the labor qualifications

specified in the contract,” up to a ceiling price, 48 CFR 52.232-7(a)(3), (e), and that hourly

rate would “include wages, indirect costs, general and administrative expense, and profit.”

Id. 52.232-7(a)(4). The RFP also provided that subcontractors providing DPLH would be

paid the “fixed rate per DPLH specified in Section B, clause entitled ‘Direct Labor Rate.’”

Exhibit 1 at 42 (§ H.14(e)(2)).

Nevertheless, the RFP also indicated that the contract resulting from the solicitation

would incorporate by reference the contract clause titled “Fixed Fee (Mar 1997)” from FAR

52.216-8, which read as follows:

(a) The Government shall pay the Contractor for performing this contract the

fixed fee specified in the Schedule.

(b) Payment of the fixed fee shall be made as specified in the Schedule;

provided that after payment of 85 percent of the fixed fee, the Contracting

Officer may withhold further payment of fee until a reserve is set aside in an

amount that the Contracting Officer considers necessary to protect the

Government’s interest. This reserve shall not exceed 15 percent of the total

fixed fee or $100,000, whichever is less. The Contracting Officer shall release

75 percent of all fee withholds under this contract after receipt of the certified

final indirect cost rate proposal covering the year of physical completion of

this contract, provided the Contractor has satisfied all other contract terms and

conditions, including the submission of the final patent and royalty reports, and

is not delinquent in submitting final vouchers on prior years’ settlements. The

CBCA 4068

5

Contracting Officer may release up to 90 percent of the fee withholds under

this contract based on the Contractor’s past performance related to the

submission and settlement of final indirect cost rate proposals.

48 CFR 52.216-8 (2001); see Exhibit 1 at 47; ASUF ¶ 5.

In responding to questions about the RFP provision allowing subcontractors to be paid

the “fixed rate per DPLH,” DOE indicated that offerors were not to apply “fee” to ODCs and

noted that clause B.3 specifically segregates the fixed fee from the loaded hourly rates:

Question 10. 1. Item H.14 of page 39 of the subject RFP states that

“Subcontractors providing DPLH will be paid the fixed rate per DPLH

specified in Section B. . . .” Does this mean that prime contractor markup on

the subcontractor costs such as [general and administrative expense (G&A)]

and fee will not be allowed[?] Are G&A and fee markups allowed on any

ODCs including but not limited to Consultants, subcontractors, travel, etc?

Answer 10: Fee cannot be applied to any OCD’s. It is up to offerors to

determine whether or not to apply their G&A to consultants and subcontractor

rates. Note that Clause B.3 and the cost/price proposal preparation

instructions specifically segregate the fixed fee from the loaded hourly rates.

Exhibit 4 at 14 (emphasis added); see ASUF ¶ 6.

II.

Appellant’s Offer

On or about February 14, 2003, SMARTECH submitted a proposal in response to the

RFP, and it revised the proposal on or about August 21, 2003. See Exhibits 6, 7.2 In both

the original and the revised proposals, SMARTECH represented that it was proposing a

“fixed fee” of “approximately” eight percent of its total burdened labor costs, as follows:

2

In its briefing, SMARTECH indicates that it first submitted a proposal in response

to the RFP on July 25, 2002, with revisions submitted on January 31, February14, and

August 21, 2003. The appeal file that DOE submitted contains portions of SMARTECH’s

February 14 and August 21 cost proposals, but nothing from the July 25 or January 31

proposals. Because SMARTECH has not alleged that the July 25, 2002, and January 31,

2003, proposals were materially different from the August 21 proposal that immediately

preceded DOE’s letter contract award, which is discussed below, the specific date of the

proposal submissions is not material to the pending summary relief motions.

CBCA 4068

6

SMARTECH is proposing a fixed fee based on other rates which vary by labor

category. These rates are shown in Table B-1. The total fee, as computed, is

approximately 8% of burdened labor costs. The profit levels and application

are discussed in the description of Exhibits [sic] A.

Exhibit 6 at 11 (emphasis added); see Exhibit 7 at 12. The referenced Table B-1 identified

some of the economic assumptions underlying SMARTECH’s cost proposal, including a

profit rate of eight percent:

Table B-1: Economic Assumptions

Base Period

Year-1 Year-2

Year-3

SMARTECH

Fringe

31.47%

Overhead

6.23%

G&A

8.79%

Profit [Sub-Contractor] 0.00%

Profit

8.00%

31.47%

6.23%

8.79%

0.00%

8.00%

31.57%

6.26%

8.68%

0.00%

8.00%

Option Periods

Year-4

Year-5

32.61%

5.88%

8.69%

0.00%

8.00%

32.61%

5.88%

8.63%

0.00%

8.00%

Exhibit 6 at 15; Exhibit 7 at 16. SMARTECH indicated in its proposal that it was listing

profit “as a line item as specified in the RFP,” with “a flat profit rate of 8%,” and that the

“table formats in Section B of the RFP include a fixed fee”:

Note that the exhibits include profit as a line item as specified in the RFP.

SMARTECH’s profit is computed only on direct labor, fringe benefits,

overhead, and general and administrative expenses. No profit is computed on

ODC’s, sub-contractor costs[.] The profit in the exhibits is that included in the

price by the Prime Contractor. The subcontractor is including profit in its

prices to the Prime. The table formats in Section B of the RFP include a fixed

fee.

The current contract uses different profit levels for different labor categories

under the contract. The justification for this has been the different risks and

costs involved in finding, hiring and retaining different grades of acceptable

staff. SMARTECH proposes a flat profit rate of 8%, as noted earlier, for both

itself and [a subcontractor]. The profit rates are shown in Table B-1 . . . .

Exhibit 7 at 14.

CBCA 4068

7

The cost proposal also provided a breakdown of the costs required by sections B.3 and

B.6 of the RFP. SMARTECH represented that Table B-3, as “required by Section B-3 of the

RFP,” “contain[ed] prices for the two contract years of the Base Contract Period,” and Table

B-6, as “required by section B-6 of the RFP,” “contain[ed] the unit prices for the three option

periods.” Exhibit 6 at 9; Exhibit 7 at 10. “The two tables contain[ed] hourly fixed labor hour

prices for all staff members under the contract,” prices which were “fully burdened”

(including “all indirect costs”). Exhibit 6 at 9; Exhibit 7 at 10. At the end of Tables B-3 and

B-6, after listing the fixed hourly labor rates for a variety of specific labor categories for

“Base Year 1,” “Base Year 2,” and the three option years, SMARTECH identified a specific

dollar amount in the ODC “Not-To-Exceed” line, in the “Fixed Fee” line, and in the ceiling

price line for both base years and all three option years:

Section B.3 Fixed Hourly Labor Rates

Base Contract Period

Key

Base Year Two

Regular Time

Hourly Rate

(Price)

RFP

Labor Category

Prime or

SubCon

Program Manager

Technical Program

Manager

Training Coordinator

Prime

Key

Sub/Prime Key

[Named Employee]

[Named Employee]

$

$

77.71

85.99

$

$

80.43

86.86

Prime

[Named Employee]

$

78.88

$

81.64

Key

Name

Base Year One

Regular Time

Hourly Rate

(P rice)

....

Other Direct Costs

Not-To-Exceed

$50,000.00

$50,000.00

Fixed Fee*

$ 326,446

$

Ceiling Price

*Prime Only

$8,813,241

$ 9,113,531

382,480

Declaration of Bruce M. Jordan (Sept. 8, 2015), Attachment A.

On August 4, 2003, just before SMARTECH submitted its August 21, 2003, cost

proposal revision, the DOE contracting officer sent an email message to SMARTECH,

referencing a telephone conversation earlier that day. See Jordan Declaration Attachment B.

In the email message, the contracting officer referenced the “total fixed fee amount” from

sections B.3 and B.6 as follows:

CBCA 4068

8

Section B, Clause B.3 and B.6, include total fixed fee amount after Other

Direct Costs. Also add a footnote indicating that the base for G&A excludes

subcontractor and other direct costs.

Id.

III.

Award of an Undefinitized Letter Contract

On September 30, 2003, DOE awarded SMARTECH an undefinitized time-andmaterials (T&M) letter contract, no. DE-AC01-03S020138, for the technical support work.

Complaint ¶¶ 1, 7, 17; RSUF ¶ 5; Exhibit 8. As anticipated by the RFP, the contract

incorporated the “Fixed Fee” clause from FAR 52.216-8, which specified that “[t]he

Government shall pay the Contractor for performing this contract the fixed fee specified in

the Schedule.” Exhibit 8 at 46; ASUF ¶ 11. Nevertheless, the dollar amount lines in sections

B.3 and B.6 of the contract for DPLH, ODC, “Fixed Fee,” and “Ceiling Price” were blank,

and the terms of the letter contract remained undefinitized. Exhibit 8 at 4-8; Response to

ASUF ¶ 10.

IV.

The Definitized Contract

The contract was definitized by the parties on March 17, 2005 (after SMARTECH had

already completed performance of the first base year of the contract), pursuant to

modification no. A006. ASUF ¶ 12; Exhibit 21; Complaint ¶ 7. Consistent with the nature

of a T&M contract, DOE was to issue specific work/task orders, or “task assignments,” to

SMARTECH during the contract period identifying the specific tasks that SMARTECH was

to accomplish and for which it would be paid at an hourly labor rate. Exhibit 8 at 13, 32

(contract clauses C.4.0 and H.8); see 48 CFR 16.601(b) (2014) (discussing T&M contracts).

As definitized, the contract had a base period of twenty-four months, plus four option periods

totaling an additional thirty-six months. As set forth in modification no. A006, the first and

second option periods were for six months each, and the third and fourth option periods were

each for twelve months. Complaint ¶ 8; ASUF ¶ 12; Exhibit 21 at 2-10.

Modification no. A0006 specifically amended section B.3 to add direct labor rates and

“indirect cost ceilings,” as follows:

Part I, Section B, Clause B.3 Direct Labor Rates is hereby definitized and

incorporated below as negotiations[.] Base Year 1 lists base labor rates per

employee by name, in lieu of fully loaded labor rates by labor category.

Accordingly, indirect cost ceilings are also separately provided immediately

following the labor rates.

CBCA 4068

9

Exhibit 21 at 2. For Base Year 1 (September 30, 2003, through September 29, 2004), section

B.3 was amended to list a base hourly rate for numerous labor categories, id. at 2-6, a list that

was then followed by the language below:

Base Year 1 – Definitized

Direct Labor (DL)

Fringe Benefits (FB)

Overhead (OH)

Other Direct Costs (ODC’s)

General & Administrative (G&A)

Fixed Fee

Total Ceiling Price – Base Year 1

$2,766,174

$ 951,011

$ 342,724

$ 12,360

$ 541,998

$ 368,153

$4,982,420

Id. at 6. For Base Year 2 (September 30, 2004, through September 29, 2005), the

modification indicated that, “[b]eginning in Base Year 2, loaded fixed hourly rates are

utilized and identified per individual key personnel and non-key labor categories,” and “[t]he

base hourly rate is loaded with FB, OH, and G&A,” but not profit. Id. It then listed loaded

fixed hourly rates for a variety of labor categories, followed by the language below:

Direct Labor Costs (DL, FB, OH, & G&A)

Other Direct Costs

Fixed Fee

Total Ceiling Price – Base Year 2

$8,984,738

$ 50,000

$ 718,779

$9,753,517

Id. Through subsequent modifications, similar listings of labor categories and dollar amounts

were applied to the options, which resulted in a dollar amount of $231,596 next to the words

“Fixed Fee” applicable to the first six-month option period (Exhibit 31 at 3); $231,596 for

the second six-month option period (Exhibit 34 at 3); $366,019 for the first one-year option

period (Exhibit 39 at 3); and $367,422 for the last one-year option period (Exhibit 57 at 3).

DOE exercised all four of the options. ASUF ¶ 14. SMARTECH was notified of

DOE’s intent to exercise the fourth and final one-year option on August 28, 2007, Exhibit

80; Jordan Declaration ¶ 31, and DOE formally exercised the option through modification

no. A019 on September 27, 2007. Exhibit 57. After exercising the option, the DOE

contracting officer informed SMARTECH on or about March 6, 2008, that DOE had

awarded a separate contract “that will satisfy the Department’s document review

requirements” and that “SMARTECH should take all necessary steps to prepare for the

complete phase-out of this contract on March 31, 2008.” Exhibit 65 at 2. Nevertheless, the

contracting officer did not terminate SMARTECH’s contract, and the contract performance

period ended on September 29, 2008. ASUF ¶ 14.

CBCA 4068

V.

10

SMARTECH’s Billing Practices During Performance

During contract performance, SMARTECH requested payment of fee in its invoices

as an eight-percent markup to the DPLH charged. ASUF ¶ 15. It did not contemporaneously

invoice for all of the fixed fee amounts that it now claims are due under its contract, id., but

followed a DOE-provided sample form only because, SMARTECH alleges (and DOE

disputes), DOE instructed it to do so. Complaint ¶ 22; Answer ¶ 22; Exhibit 71 at 8-12. The

sample invoice form called for the invoicing of fee amounts as an eight-percent markup to

the DPLH charged under that invoice. Complaint ¶ 22; Exhibit 26 at 6-7; Exhibit 71 at 8-12.

SMARTECH first sought payment of the total unbilled “fixed fee” in an REA

submitted to the contracting officer on September 29, 2010. ASUF ¶ 20; Exhibit 69 at 4.

Accompanying that REA was a final release that reserved the claims now pending before the

Board. Exhibit 69 at 13. In the REA, SMARTECH also sought recovery of several other

costs, including rent on office space that it had leased in the fourth option year, and release

of a $50,000 retainage. Id. at 1-5. By letter dated May 18, 2011, the DOE contracting officer

indicated that, if SMARTECH submitted a final payment invoice requesting the retainage,

DOE would pay it, but denied the remainder of SMARTECH’s REA. Exhibit 70 at 1-6.

SMARTECH did not submit the requested invoice until June 19, 2013, more than two years

after the contracting officer’s request. Exhibit 71. DOE paid it within a few days.

VI.

The Appeal

On March 28, 2014, SMARTECH submitted a certified claim for $788,303.29,

alleging entitlement to additional payment under the contract as follows: (1) unpaid fixed

fees totaling $722,236.79; (2) reimbursement for private office space in the amount of

$8436.61; (3) interest on unpaid fixed fees of $54,602.94; and (4) interest on withheld

retainage of $3026.95. Exhibit 72. The contracting officer denied the claim on May 22,

2014. Exhibit 73. This appeal followed. After the Board denied DOE’s motion to dismiss

a portion of this appeal, see Systems Management & Research Technologies Corp. v.

Department of Energy, CBCA 4068, 15-1 BCA ¶ 35,796, the parties filed cross-motions for

summary relief, which are now pending before the Board.

Discussion

I.

The Standard of Review

Each party seeks summary relief in its favor regarding the proper interpretation of the

contract language. The standard that we must apply in reviewing motions for summary relief

is well-established:

CBCA 4068

11

“Summary relief is only appropriate where there is no genuine issue as to any

material fact and the moving party is entitled to relief as a matter of law.”

Butte Timberlands, LLC v. Department of Agriculture, CBCA 3232, 13 BCA

¶ 35,383, at 173,627 (quoting Greene v. Department of Homeland Security,

CBCA 49, 07-2 BCA ¶ 33,668, at 166,700). A material fact is one that will

affect the outcome of a case. Anderson v. Liberty Lobby, Inc., 477 U.S. 242,

247 (1986). “Any doubt on whether summary relief is appropriate is to be

resolved against the moving party.” Butte Timberlands, 13 BCA at 173,627

(quoting Greene, 07-2 BCA at 166,700).

McAllen Hospitals LP v. Department of Veterans Affairs, CBCA 2774, et al., 14-1 BCA

¶ 35,758, at 174,972.

“When both parties move for summary relief, each party’s motion must be evaluated

on its own merits and all reasonable inferences must be resolved against the party whose

motion is under consideration.” Government Marketing Group v. Department of Justice,

CBCA 964, 08-2 BCA ¶ 33,955, at 167,991. Nevertheless, “[c]ontract interpretation is a

question of law generally amenable” to summary relief, Varilease Technology Group, Inc.

v. United States, 289 F.3d 795, 798 (Fed. Cir. 2002), although “the question of interpretation

of language, the conduct, and the intent of the parties, i.e., the question of what is the

meaning that should be given by a court or board to the words of a contract, may sometimes

involve questions of material fact and not present a pure question of law.” DJM/Reza, A

Joint Venture, VABCA 6917, et al., 05-1 BCA ¶ 32,943, at 163,208.

II.

The “Fixed Fee” Claim

A.

Contract Interpretation Rules

The main claim at issue in this appeal is SMARTECH’s request for payment of those

portions of a fixed fee that, it asserts, were not paid during contract performance. The parties

raise conflicting interpretations of the contract: SMARTECH alleges that the contract

provided for a specific fixed fee that was to be added to any DPLH charges in the second

contract base year and in each option period, while DOE alleges that the words “fixed fee”

were used in such a way in this contract as to provide for an eight-percent “fee” markup on

allowable DPLH charges (instead of the addition of a fixed dollar amount in each contract

period).

“The primary objective of contract interpretation is to determine the intent of the

parties at the time an agreement is created.” 600 Second Street Holdings LLC v. Securities

CBCA 4068

12

& Exchange Commission, CBCA 3228, 13 BCA ¶ 35,396, at 173,666. In resolving a dispute

about that intent, “we turn to the ‘time-honored rules’ of contract interpretation”:

The starting point for contract interpretation is the language of the written

agreement. In interpreting the language of a contract, reasonable meaning

must be given all parts of the agreement so as to not render any portion

meaningless, or to interpret any provision so as to create a conflict with other

provisions of the contract. The nature of the contract is determined by an

objective reading of its language, not by one party’s characterization of the

instrument.

Jane Mobley Associates, Inc. v. General Services Administration, CBCA 2878, slip op. at 10

(Mar. 9, 2016) (quoting Champion Business Services v. General Services Administration,

CBCA 1735, et al., 10-2 BCA ¶ 34,539, at 170,345, modified on reconsideration, 10-2 BCA

¶ 34,598) (citations omitted).

B.

The Contract’s Plain Language

SMARTECH alleges that, “[u]nlike a typical T&M contract, which would call for the

capture of ‘fee’ as part of the burdened hourly rates, the Contract set out fixed and partially

burdened hourly rates for direct labor and separate and stand-alone ‘fixed fee’ terms by

contract/option period.” Complaint ¶ 9. Specifically, the contract, as definitized and

subsequently modified, set out a “fixed fee” in the first base year (a period running from

September 30, 2003, to September 29, 2004) of $368,153;3 in the second base year (running

from September 30, 2004, to September 29, 2005) of $718,779; in option period one (running

from September 30, 2005, to March 29, 2006) of $231,596; in option period two (March 30,

2006, to September 30, 2006) of $231,596; in option period three (October 1, 2006, to

September 30, 2007) of $366,019; and in option period four (October 1, 2007, to

September 29, 2008) of $367,422. Id. ¶¶ 12, 29. SMARTECH alleges that the fixed fee

provisions “were not in any way qualified and were clearly independent from the otherwise

burdened hourly labor rates and other elements of contractor compensation.” Id. ¶ 13. It

asserts that its entitlement to a stand-alone fixed fee, in addition to payment for labor at the

contractual hourly rates, is “consistent with DOE’s intent as expressed in its RFP.” Id. ¶ 10.

The plain language of the contract supports SMARTECH’s position. The original

solicitation for this contract indicated that DOE anticipated making “a fixed rate, fixed fee,

3

SMARTECH does not seek any additional fee for the first base year because, it

asserts, the contract was definitized after that year’s work was complete. Complaint ¶ 23.

CBCA 4068

13

labor hour contract, Exhibit 1 at 88 (emphasis added), and the subsequent letter contract

similarly indicated that, when the contract was definitized, DOE contemplated that it would

be a “fixed rate fixed fee labor hour definitive contract,” Exhibit 8 at 40 (emphasis added);4

the solicitation included a specific line for the dollar amount of the “fixed fee,” without

mention of any kind of percentage markup, id. at 8; and the ultimate contract that was

awarded contained not only that “fixed fee” line item but also the clause at FAR 52.216-8

titled “Fixed Fee.” Exhibit 8 at 4, 46. That FAR clause expressly directs that “[t]he

Government shall pay the Contractor the fixed fee specified in the Schedule.” 48 CFR

52.216-8(a). The FAR provides that the Government will utilize the “Fixed Fee” clause at

FAR 52.216-8 when contemplating a contract “that provides for payment to the contractor

of a negotiated fee that is fixed at the inception of the contract” and “does not vary with

actual cost.” Id. 16.306(a); see id. 16.307(b).5 In such contracts, “the fee represents the

contractor[’]s profit.” Fessel, Seigfriedt, & Moeller Advertising, HUDBCA 90-5360-DO,

06-1 BCA ¶ 33,128, at 164,182 (1991); see Sanders Associates, Inc., ASBCA 8481, 64 BCA

¶ 4091, at 19,985 (“The contractor’s basic obligation is to seek its profit in fixed fee, rather

than as part of reimbursable costs.”); 48 CFR 15.404-4 (equating profit with fee); John

Cibinic, Jr., Ralph C. Nash, Jr., & Christopher R. Yukins, Formation of Government

Contracts 1207 (4th ed. 2011) (in a cost-plus-fixed-fee contract, “profit will be stated

separately in the contract as a fixed fee”).

Although those factors support SMARTECH’s interpretation of this contract as calling

for payment of a specific fixed dollar amount fee (or profit) in each contract period, the

contract also contains the seemingly conflicting “Payments under Time-and-Materials and

Labor-Hour Contracts” contract clause (T&M Payments clause) from FAR 52.232-7. Exhibit

8 at 47. Under that clause, which the Government is to include “in solicitations and contracts

when a time-and-materials or labor-hour contract is contemplated,” 48 CFR 32.111(a)(7), the

Government agrees to pay the contractor, upon submission of vouchers and subject to a

4

To the extent that the reference to a “fixed rate fixed fee labor hour” contract could

be viewed as merging the fixed fee and a “fixed rate,” clause B.3 makes clear that the

contractor was to identify “fixed hourly labor rates” for specific labor tasks, separate from

the fixed fee. Exhibit 1 at 7-8; Exhibit 8 at 4-5. The “fixed rate” identified in this RFP and

contract phrase clearly refers to labor rates, not the fee.

5

The “Fixed Fee” clause is typically used when a cost-plus-fixed-fee contract is

contemplated. FAR 16.307(b). As we will discuss below, the contract here is not a costreimbursement contract. Nevertheless, given that this contract contains the FAR’s “Fixed

Fee” clause as well as a line item titled “Fixed Fee,” the regulations that govern the use of

the “Fixed Fee” clause are helpful in defining what the term “fixed fee” means.

CBCA 4068

14

ceiling price, agreed-upon hourly labor rates for work performed. Id. 52.232-7(a), (e).

Under this clause, the hourly rates must “include wages, indirect costs, [G&A] expense, and

profit.” Id. 52.232-7(a)(4) (emphasis added). Nevertheless, in the RFP, there was an express

direction that offerors “segregate the fixed fee from the loaded hourly rates,” Exhibit 4 at 14

– that is, offerors were expressly directed to remove profit from the hourly rates – providing

offerors with a more specific direction than the general one in the T&M Payments clause.

See Southcentral Foundation v. Department of Health & Human Services, CBCA 541-ISDA,

slip op. at 6 (Aug. 3, 2007) (“Under accepted rules of contract interpretation, the specific

takes precedence over the more general.”) (citing Hol-Gar Manufacturing Co. v. United

States, 351 F.2d 972, 980 (Ct. Cl. 1965)). Although, on its face, there is a facial disconnect

between the “Fixed Fee” clause requiring a separate line item for a fixed amount of profit in

each contract period and the T&M Payments clause requiring profit be included in the

contractor’s hourly rates, the RFP clarified that hourly labor rates were to be loaded with

indirect costs and G&A, but with profit segregated into a separate fixed fee.6

C.

DOE’s Extrinsic Evidence

In light of the conflict in the “Fixed Fee” and T&M Payments clauses, DOE asks us

to consider extrinsic evidence to define the meaning of the contract’s fixed fee provisions.

“If a contract provision appears ambiguous on its face, extrinsic evidence may assist in

discerning the parties’ intent and may show that language appearing on its face to be

ambiguous is not because, for example, the parties shared a mutual understanding as to its

meaning.” A-Son’s Construction, Inc. v. Department of Housing & Urban Development,

CBCA 3491, et al., 15-1 BCA ¶ 36,089, at 176,210 (citing Metropolitan Area Transit, Inc.

v. Nicholson, 463 F.3d 1256, 1260 (Fed. Cir. 2006)). Yet, the extrinsic evidence that DOE

wants us to consider does not address the conflict between the “Fixed Fee” and T&M

Payments clauses. That is, it does not address whether profit was supposed to be included

6

The language in modification no. A0006 does not affect this interpretation. In that

modification, DOE indicated that “indirect cost ceilings are also separately provided

immediately following the labor rates.” Exhibit 21 at 2. The modification then lists, after

the direct labor rates, dollar amounts for fringe benefits, overhead, other direct costs, G&A,

and “fixed fee.” Id. Although DOE suggests that the inclusion of “fixed fee” as part of the

list of indirect costs (that is, fringe benefits, overhead, and G&A) suggests that fee was

reimbursable at a percentage markup subject to a cost ceiling, profit is not an “indirect cost.”

It is, instead, an “element of the potential total remuneration that contractors may receive for

contract performance over and above allowable costs.” FAR 15.404-4(a)(1). Accordingly,

we cannot interpret the “indirect cost ceilings” language in the modification to apply to the

“fixed fee,” or profit, line item or to convert fixed fee to a percentage markup on labor rates.

CBCA 4068

15

in the hourly rates (which the T&M Payments clause would normally require, but that other

provisions of the contract make clear was excluded) or was, instead, segregated into the

“Fixed Fee” line item. Instead, DOE uses it to try to establish that the “Fixed Fee” clause and

the corresponding line items identifying the fixed fee for each contract period were intended

to provide for a fee or profit rate that would be added to the DPLH charges that SMARTECH

billed. As a result, according to DOE, instead of being entitled to a fixed fee payment of

$718,779 in the second contract base year, SMARTECH was entitled to an eight-percent

markup on the DPLH that it charged, up to a fee ceiling of $718,779.

As support for this interpretation, DOE first argues that, in negotiating the dollar

amount of the fixed fee, the parties assumed a profit rate of approximately eight percent. It

cites to SMARTECH’s cost and pricing proposals as evidence that the parties agreed to a

profit rate of eight percent. Yet, in its negotiation memorandum addressing the pricing

proposal, DOE recognized that SMARTECH was merely proposing a “total fee . . . reflective

of a rate of 8%” and that the negotiations “resulted in a total negotiated fee amounting [to]

$3,424,464,” without any mention of the fee actually being a ceiling for a percentage markup.

Exhibit 20 at 6 (emphasis added). More importantly, the language ultimately used in the

definitized contract does not reference a “fee rate” or “percentage,” but expressly identifies

a dollar amount for a specific “Fixed Fee.” Exhibit 21 at 6, 7; Exhibit 31 at 3; Exhibit 34 at

3; Exhibit 39 at 3; Exhibit 57 at 3. In such circumstances, the mere fact that the parties used

an eight-percent profit rate as a marker for negotiating the amount of the fixed fee does not

suggest, in light of the actual contract language, that the fixed fee was actually a markup to

hourly labor charges rather than a fixed fee.

More compelling is DOE’s evidence that, during performance of the contract,

SMARTECH never billed for the full amount of the fixed fee. Instead, in each invoice that

it submitted throughout contract performance, SMARTECH billed its fixed fee as an eightpercent markup to its DPLH charges. See, e.g., Exhibit 40 at 5; Exhibit 41 at 3; Exhibit 42

at 5. Until submitting its REA in September 2010, almost two years after contract

completion, SMARTECH never requested payment of the fixed fee other than as a

percentage markup to its direct costs. “It is well settled that the practical interpretation of a

contract, as shown by the conduct of the parties” during contract performance, “is of great

weight in interpreting the contract.” Dynamics Corp. of America v. United States, 389 F.2d

424, 430 (Ct. Cl. 1968). Although SMARTECH relies on evidence in the record to argue

that it was merely following the invoice format that the Government directed it to use, it does

not explain why it never objected to that format, and never attempted to bill for the full fixed

fee, throughout five years of contract performance.

Nevertheless, we cannot rely upon this evidence to create a genuine issue of material

fact for two reasons:

CBCA 4068

16

First, “[t]he parol evidence rule is a rule of substantive law that prohibits the use of

external evidence to add to or otherwise modify the terms of a written agreement ‘in

instances where the written agreement has been adopted by the parties as an expression of

their final understanding.’” Barron Bancshares, Inc. v. United States, 366 F.3d 1360, 1375

(Fed. Cir. 2004) (quoting David Nassif Associates v. United States, 557 F.2d 249, 256 (Ct.

Cl. 1977)). “The rule thus renders inadmissible evidence introduced to modify, supplement,

or interpret the terms of an integrated agreement,” and “[e]vidence of the parties’ course of

dealing constitutes this kind of parol evidence that is prohibited by the rule.” Id.; see Alves

v. United States, 133 F.3d 1454, 1459 (Fed. Cir. 1998) (“Alves’ attempt to vary the clear

meaning of the exchange-of-use agreement in accordance with the parties’ ‘course of

dealing’ is improper under the parol evidence rule.”). As a result, “[i]f the terms of a contract

are clear and unambiguous, they must be given their plain meaning – extrinsic evidence is

inadmissible to interpret them.” Barron Bancshares, 366 F.3d at 1375; see The Carrington

Group, Inc. v. Department of Veterans Affairs, CBCA 2091, 12-1 BCA ¶ 34,993, at 171,984

(“we may not resort to extrinsic evidence to interpret” clear and unambiguous contract

provisions (quoting Banknote Corp. of America v. United States, 365 F.3d 1345, 1353 (Fed.

Cir. 2004))).

As we have already discussed, the plain language of the agreement supports

SMARTECH’s interpretation of the contract’s “Fixed Fee” as being just that: a fixed fee.

The FAR very clearly defines what a “fixed fee” is – “a negotiated fee that is fixed at the

inception of the contract” and “does not vary with actual cost,” FAR16.306(a) – and there

is no language in the contract stating that any other definition of the term “Fixed Fee” is

intended or that it is really a percentage-of-billings markup. In the line item in which the

contractor’s fixed fee dollar amount is listed, there is no reference to a “Fixed Fee Ceiling”

or payment of a fixed fee at a particular percentage rate. To the contrary, the line item

expressly refers to the “Fixed Fee” and contains a specific dollar amount. The eight-percent

figure upon which DOE relies is not mentioned anywhere in the contract. Although DOE

has identified an ambiguity in the contract, that ambiguity is unrelated to whether the “Fixed

Fee” provision creates a fixed fee or, instead, a percentage markup with a fee ceiling. We

are aware of no exception to the parol evidence rule that would allow a party to introduce

extrinsic evidence regarding an unambiguous contract provision simply because, elsewhere

in the contract, there is an unrelated ambiguity. The actual language of the contract very

clearly indicates a fixed fee, not the percentage-of-DPLH fee markup that DOE advocates.

Second, even if DOE were to argue that the contract here is not fully integrated, it

could not use extrinsic evidence to explain or contradict the terms of the actual contract. To

establish that a contract is not fully integrated, a party may use parol evidence to supplement

the actual language of the contract with consistent terms, but not to change or contradict it:

CBCA 4068

17

Even if the contract were only partially integrated, [plaintiff] would be

permitted to introduce parol evidence only to supplement the “agreement by

consistent additional terms.” However, it wants parol evidence to interpret the

“necessary and incident” language of the contract. Consequently, whether the

contract was fully integrated is really of no moment to [plaintiff], for its

argument hinges upon whether the contract was ambiguous. Only then could

the court resort to extrinsic evidence to inform its interpretation of that

provision, regardless of whether the contract was fully integrated.

McAbee Construction, Inc. v. United States, 97 F.3d 1431, 1434 (Fed. Cir. 1996) (citations

omitted); see West Bend Mutual Insurance Co. v. Procaccio Painting & Drywall Co., 794

F.3d 666, 673 (7th Cir. 2015) (if contract is only partially integrated, “parol evidence may

not be used to explain the writing or to introduce terms that contradict the written

agreement”); Robb Evans & Associates, LLC v. Holibaugh, 609 F.3d 359, 365 (4th Cir. 2010)

(even if contract is only partially integrated, “we may not consider evidence that contradicts

its plain and unambiguous terms”); Goodfellow Brothers, Inc., AGBCA 80-189-3, 81-1 BCA

¶ 14,917, at 73,808 (“Since the evidence contradicts the lease provisions, it is generally

excludable under the rule regardless of whether the lease is fully or partially integrated.”).

Here, DOE is arguing that the term “Fixed Fee” does not mean what the FAR says it

means, but should instead be read to say “Fee Percentage Markup” or something to that

effect. Given that FAR expressly informs us what the term “Fixed Fee” means, we cannot

accept extrinsic evidence – even evidence showing a mutual course of dealing, see Barron

Bancshares, 366 F.3d at 1375 – to redefine that term in a manner that is wholly inconsistent

with and contrary to the FAR, particularly where, as here, the contract language itself

provides us with no basis for adopting that redefinition. See United States v. Wiltberger, 18

U.S. (5 Wheat.) 76, 95-96 (1820) (Marshall, C.J.) (“The case must be a strong one indeed,

which would justify a court in departing from the plain meaning of words . . . in search of an

intention which the words themselves did not suggest.”).7

7

In DOE’s reply to SMARTECH’s opposition to DOE’s cross-motion, DOE, for the

first time, argued that SMARTECH’s fixed fee claim should be barred by laches. See

Respondent’s Reply at 13. Laches is an affirmative defense that DOE was required to raise

in its answer. Systems Integration & Management, Inc. v. General Services Administration,

CBCA 1512, et al., 13 BCA ¶ 35,417, at 173,767; Fed. R. Civ. P. 8(c)(1). Further, tribunals

are not required to consider arguments raised for the first time in a reply brief. Bannum, Inc.

v. United States, 121 Fed. Cl. 543, 552 n.6 (2015) (citing United States v. Ford Motor Co.,

463 F.3d 1267, 1277 (Fed. Cir. 2006)). It is too late to raise this defense now. Even if we

considered the late-raised argument, a respondent seeking to establish laches must show

CBCA 4068

D.

18

The Legality of the Parties’ Interpretations

DOE argues that SMARTECH’s interpretation of the contract would render it illegal.

“[I]t is a rule of interpretation that, where a contract is fairly open to two constructions, by

one of which it would be lawful and the other unlawful, the former must be adopted.” Hobbs

v. McLean, 117 U.S. 567, 576 (1886), quoted in part in Northrop Grumman Computing

Systems, Inc. v. General Services Administration, GSBCA 16367, 06-2 BCA ¶ 33,324, at

165,266; see Truc v. United States, 212 Ct. Cl. 51, 64 n. 11 (1976) (“contract provisions

should be construed, if possible, to be lawful rather than unlawful”). By statute, except in

circumstances not applicable here, “the fee in a cost-plus-a-fixed-fee contract shall not

exceed 10 percent of the estimated cost of the contract, not including the fee, as determined

by the agency head at the time of entering into the contract.” 41 U.S.C. § 3905(b)(1). DOE

asserts that, under SMARTECH’s theory, SMARTECH would be entitled to recover a fixed

fee in excess of ten percent of the price for work actually ordered, in violation of the statute.

DOE’s argument fails for two reasons:

First, SMARTECH’s interpretation does not create a cost-reimbursement or cost-plusfixed-fee (CPFF) contract. DOE created a contract under which SMARTECH was to be paid

at fixed hourly rates that encompass wages, overhead, and G&A, but from which profit was

excluded and paid separately. But for the segregated profit issue, the contract is consistent

with a T&M contract:

When a contractor enters into a time and materials contract he agrees to furnish

the labor and equipment necessary to fulfill his obligations at a prescribed rate.

(1) unreasonable, unexcused delay by the claimant in bringing suit to remedy an alleged

wrong, and (2) either economic prejudice or “defense prejudice” (such as loss of records) to

the respondent. JANA, Inc. v. United States, 936 F.2d 1265, 1269-70 (Fed. Cir. 1991);

Systems Integration, 13 BCA at 173,767. DOE asserts that, had SMARTECH notified it of

its interpretation of the contract earlier, it might “have acted to renegotiate and modify the

contract or chose not to exercise any further options.” Respondent’s Reply at 13. Laches is

inapplicable because DOE is complaining about a lack of notice during performance, not a

delay in bringing suit. Further, DOE offers no evidence – through declaration or otherwise

– that it actually would have changed its conduct with notice. Conclusory assertions by

counsel unsupported by factual evidence are insufficient to defeat a motion for summary

relief. Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390-91 (Fed. Cir. 1987);

Levi Strauss & Co. v. Genesco, Inc., 742 F.2d 1401, 1404 (Fed. Cir. 1984); Barmag Barmer

Maschinenfabrik AG v. Murata Machinery, Ltd., 731 F.2d 831, 836 (Fed. Cir. 1984).

CBCA 4068

19

The rate to be charged for direct labor can be precisely predetermined at an

hourly rate or any acceptable measurement. However, the rate for

nonproduction personnel such as owners, officers, clerical workers, salesmen,

and others must of necessity be estimated. This rate is referred to as overhead

or burden rate.

H.L. Yoh Co. v. United States, 288 F.2d 493, 494 (Ct. Cl. 1961); see 48 CFR 16.601(b)(1)

(defining T&M contract). Unlike a cost-reimbursement contract, a contractor under a T&M

contract invoices according to the fixed labor rate negotiated at the start of the contract, even

if the contractor’s actual labor costs increase during performance:

To be a cost-reimbursement contract, the payments to the contractor would

have to be based on its incurred costs. Under a time-and-materials contract,

except for material costs, the contractor is not reimbursed for its incurred costs.

It is paid on the basis of fixed hourly rates. Absent a change, or other

Government action, the rate does not change with fluctuations of the

contractor’s costs.

Ralph C. Nash & John Cibinic, Time-and-Materials and Labor-Hour Contracts, 17 Nash &

Cibinic Report ¶ 9, at 24 (Feb. 2003); see id. at 25 (unlike a cost-reimbursement contract, the

contractor holding a T&M contract “takes the risk that the actual costs will be higher than

the amounts included for direct labor and indirect expense”). Because SMARTECH’s

contract did not base payment upon actual performance costs, but upon pre-negotiated DPHL

rates, it is technically not a cost-reimbursement contract to which the statutory limitations on

CPFF contracts at 41 U.S.C. § 3905(b)(1) would apply.

Second, even if the contract here were a CPFF contract, the fixed fee to which the

parties agreed was approximately eight percent of the estimated amount of work that DOE

originally anticipated ordering. That is within the ten-percent limit set forth at 41 U.S.C.

§ 3905(b)(1). That DOE did not order all of the work that it originally anticipated does not

render the negotiated fee in violation of the statutory limit.

To the extent that DOE is also claiming that SMARTECH’s contract is illegal because

it is a mixture of different contract types (a portion of a T&M contract and a portion of a

fixed fee contract), we disagree with DOE’s position. Contracts with the Government need

not fall uniformly into one specific category or another, but “may be of any type or

combination of types that will promote the Government’s interest,” except to the extent that

a particular contract type is barred by statute. 48 CFR 16.102(b) (emphasis added). “A

contract is not unenforceable merely because it does not fit neatly into a recognized

category.” Ace-Federal Reporters, Inc. v. Barram, 226 F.3d 1329, 1332 (Fed. Cir. 2000).

CBCA 4068

20

We can see nothing inherently illegal about the type of contract that SMARTECH alleges,

and that we find, was created here.8

Based upon the plain language of the contract, we grant summary relief to

SMARTECH on its fixed fee claim.

III.

Prompt Payment Act Interest

A.

Interest for Non-Payment of the Fixed Fee in the REA

SMARTECH submitted its REA seeking payment of its fixed fees on September 29,

2010. SMARTECH asserts that it is entitled to interest under the PPA because DOE did not

pay monies owed within thirty days of the REA’s submission.

Pursuant to the PPA, “where a contract does not specify a payment date, the

government is obliged to make payments ‘30 days after a proper invoice for the amount due

is received.’” Reddick & Sons of Gouverneur, Inc. v. United States, 31 Fed. Cl. 558, 559

(1994) (quoting 31 U.S.C. § 3903(a)(1)(B)). “[I]f payment is not made by the required

payment date after the Government’s receipt of a proper invoice,” the contractor is generally

“entitled to interest” under the PPA. MCI WORLDCOM Communications, Inc. v. Social

Security Administration, GSBCA 16169-SSA, 04-2 BCA ¶ 32,689, at 161,760, appeal

dismissed sub nom. Barnhart v. MCI WORLDCOM Commications, Inc., 120 F. App’x 321

(Fed. Cir. 2005); see Thunderhoof Ranch v. Department of the Interior, CBCA 1554, et al.,

10-2 BCA ¶ 34,477, at 170,046 (“If the agency does not make payment by the required

8

For its part, SMARTECH argues that DOE’s interpretation, if accepted, would

convert the contract into a cost-plus-percentage-of-cost (CPPC) contract, which, by statute,

is illegal. 41 U.S.C. § 3905(a). We cannot agree. One of the criteria that the Court of

Appeals for the Federal Circuit has accepted for evaluating whether a contract is a CPPC

contract is that “the predetermined percentage rate is applied to actual performance costs.”

Urban Data Systems, Inc. v. United States, 699 F.2d 1147, 1150 (Fed. Cir. 1983) (citing 55

Comp. Gen. 554, 562 (1975)). The percentage markup that DOE advocates is based upon

SMARTECH’s DPLH rates, not its actual costs. Accordingly, the statute barring CPPC

contracts is irrelevant in considering DOE’s interpretation. See United States v. Morgan

Management Systems, Inc., No. 84-3350 (D.D.C. May 13, 1985), summarized at 32 Contract

Cases Federal ¶ 73,561, at 78,521-22 (T&M contract with a six-percent fee was not a CPPC

contract because the fee was a percentage of the fixed hourly direct labor rate, rather than a

percentage of actual costs).

CBCA 4068

21

payment date, it must pay the contractor not only the principal amount due, but also an

interest penalty.”).

Nevertheless, the PPA interest provisions are intended typically to apply when

payments are “inadvertently late.” Inversa, S.A. v. United States, 73 Fed. Cl. 245, 247

(2006), aff’d, No. 2007-5110, 2007 WL 4467656 (Fed. Cir. Dec. 20, 2007). “Interest is not

mandated ‘on a payment that is not made because of a dispute between the head of an agency

and a business concern over the amount of payment or compliance with the contract.’” Delta

Air Lines, Inc. v. General Services Administration, CBCA 1306, 09-1 BCA ¶ 34,052, at

168,408 (quoting 31 U.S.C. § 3907(c)). For the Government to avoid paying PPA interest

because of a disagreement between the parties, “there must be, at the time payment of an

invoice is delayed, a ‘present basis for delaying payment which is related to an objective

discernible dispute.’” Ross & McDonald Contracting, GmbH, ASBCA 38154, et al., 94-1

BCA ¶ 26,316, at 130,894 (1993). “All that is required to raise a bona fide dispute

concerning contract compliance is that the government’s questions be raised in good faith.

That a contractor may ultimately prevail on the merits does not defeat an otherwise proper

payment withholding if there is such a good faith dispute.” Dick Pacific/GHEMM, JV,

ASBCA 55829, 08-2 BCA ¶ 33,937, at 167,942.

SMARTECH, citing to the Claims Court’s decision in Sterling Millwrights, Inc. v.

United States, 26 Cl. Ct. 49 (1992), argues that DOE’s refusal to pay “should not be deemed

a sufficiently reasonable ‘dispute’ for purposes of excusing DOE from [PPA] interest

liability.” Appellant’s Motion for Summary Relief at 8. In Sterling Millwrights, the Claims

Court asserted that, to defeat liability for PPA interest, any dispute that the Government

raises over a contractor’s right to payment would have to have “some reasonable basis” and

that “[m]erely alleging the existence of a dispute, or raising a frivolous dispute, [would be]

insufficient to deny the contractor its right to interest for late payments.” 26 Cl. Ct. at 90

n.15. In that case, though, the court had found that the contracting officer’s refusals to make

progress payments “were precipitate and arbitrary” because they were invoked solely to

create leverage in negotiations over an unrelated contract extension, meaning that there had

not been any actual dispute over entitlement to the progress payments. Id. at 90 & n.15.

There is no suggestion in the record of this appeal that DOE, in declining to pay

SMARTECH’s REA, did not hold a good faith belief that its interpretation of the contract

was correct, and SMARTECH has not even alleged, much less provided evidence, that DOE

somehow created a fake dispute as a pretext to DOE’s real objective of delaying payment.

In such circumstances, the concerns that the court raised in Sterling Millwrights do not exist.

See Oregon Woods, Inc. v. Department of the Interior, CBCA 1072, 09-1 BCA ¶ 34,014, at

168,204 (2008) (“Government officials are presumed to act in good faith. To overcome that

presumption, a contractor must prove, by clear and convincing evidence, that the officials

CBCA 4068

22

had specific intent to injure the company.”), motion for reconsideration denied, 09-1 BCA

¶ 34,063, aff’d sub nom. Oregon Woods, Inc. v. Salazar, 355 F. App’x 403 (Fed. Cir. 2009).

Accordingly, we have no basis for requiring the Government to pay PPA interest for

contesting the validity of SMARTECH’s REA submission.

B.

PPA Interest Upon a $50,000 Withholding

Clause H.14 of the definitized contract, in conjunction with FAR 52.232-7 (which was

incorporated into the contract), permitted the contracting officer to withhold five percent of

the amount otherwise due to SMARTECH for DPLH, up to a $50,000 maximum. Exhibit

8 at 35; see 48 CFR 52.232-7(a)(7). Pursuant to FAR 52-232.7(a)(7), “[t]he amounts

withheld [were to] be retained until the Contractor executes and delivers the release required

by paragraph (g) of this clause.” 48 CFR 52.232-7(a)(7). Paragraph (g) provided that the

contractor “shall execute and deliver, at the time of and as a condition precedent to final

payment under this contract, a release discharging the Government” from further liability

under the contract except to the extent that specific claims are reserved. Id. 52.232-7(g). In

response to invoice no. 19, which SMARTECH submitted in August 2005, DOE withheld

the $50,000 authorized by clause H.14.

On September 29, 2010, SMARTECH submitted an REA to DOE to which it attached

the final release contemplated by FAR 52.232-7(g). See Exhibit 69 at 13; Complaint ¶ 41.

In the REA, SMARTECH indicated that “[t]he [$50,000] withholding must now be released

to SMARTECH in accordance with the terms of the clause since SMARTECH is executing

the requested release,” and it “request[ed] payment of this amount.” Exhibit 69 at 2, 13. By

letter dated May 18, 2011, the DOE contracting officer indicated that SMARTECH had

“submitted the release forms without a final invoice” and that “DOE is prepared to authorize

the immediate release of the $50,000 withholding . . . upon submission of an invoice from

SMARTECH.” Exhibit 70 at 1. SMARTECH did not submit the requested invoice until

June 19, 2013, more than two years after the contracting officer requested it. See Exhibit 71

at 1-3. DOE paid the invoice within a few days after its receipt. Complaint ¶ 65.

SMARTECH alleges that it is entitled to PPA interest based upon DOE’s failure to

release the $50,000 withholding in response to SMARTECH’s September 29, 2010, REA

submission. Although it does not dispute that DOE was initially entitled to retain the

$50,000, SMARTECH asserted in its claim that DOE was required to release the withholding

“upon ‘execution and delivery of a release by the Contractor’ as provided in paragraph (f)

of [FAR 52.232-7],’” without further action by SMARTECH. Exhibit 72 at 5 (quoting FAR

52.232-7(a)(2)). Because DOE had no authority to insist upon a new invoice requesting

payment of the withholding, SMARTECH argues, it is entitled to PPA interest on the delayed

payment of the $50,000 withholding.

CBCA 4068

23

We agree with DOE that PPA interest did not accrue on DOE’s failure to pay in

response to the REA because the REA did not constitute a “proper invoice,” as defined by

the PPA and the FAR. By statute, a “proper invoice” for purposes of accruing PPA interest

is “an invoice containing or accompanied by substantiating documentation the Director of

the Office of Management and Budget [OMB] may require by regulation and the head of the

appropriate agency may require by regulation or contract.” 31 U.S.C. § 3901(a)(3). OMB

implemented that obligation by promulgating 5 CFR 1315.2(y) and 1315.9(b), which require

that a proper “invoice” contain specific information, including any “substantiating

documentation or information required by the contract.” 5 CFR 1315.9(b)(1)(x). The clause

at FAR 52.232-25, which is incorporated into SMARTECH’s contract, further refines

OMB’s definition as it applies to procurement contracts and requires that a “proper invoice”

must include “the items listed in paragraphs (a)(3)(i) through (a)(3)(x) of this clause,” such

as the name and address of the contractor, the invoice date, the contract number, a taxpayer

identification number, electronic funds transfer (EFT) information, and “[a]ny other

information or documentation required by the contract.” 48 CFR 52.232-25(a)(3).

SMARTECH’s REA did not contain all of the information required by FAR 52.232-25(a)(3).

Accordingly, it does not meet the definition of a “proper invoice” under the relevant FAR

clause and, therefore, does not provide a basis for the accrual of PPA interest.

SMARTECH argues that it had already billed DOE for the costs underlying the

$50,000 retainage through invoice no. 19 (which it had submitted to DOE back in August

2005). It does not dispute that, in light of the language of clause H.14 and FAR 52.232-7(g),

DOE was originally entitled to retain $50,000 from the requested payment. Nevertheless, it

asserts, quoting from FAR 52.232-7(a)(7), that the contracting officer is allowed to retain the

$50,000 only “until the Contractor executes and delivers the [final] release required by

paragraph (g)” of that clause. That FAR provision does not mean, though, that the agency

must pay interest under the PPA before a “proper invoice” is submitted. The August 2005

invoice, when first submitted, did not constitute a “proper invoice” under the PPA for

purposes of payment of the retainage because it was not accompanied by a final payment

release. Contrary to what SMARTECH appears to argue, invoice no. 19 did not somehow

ripen into a “proper invoice” for the retainage simply because SMARTECH, five years after

the invoice’s original submission, gave the contracting officer a final release: under the

FAR, the documentation necessary to support payment of the retainage – that is, the final

release – had to accompany the “proper invoice” when the invoice was submitted. 48 CFR

52.232-7(a)(3)(x). The submission of the release as part of the REA, five years later, did not

somehow retroactively convert invoice no. 19 into a “proper invoice” for the retainage under

the PPA. The FAR, in fact, contemplates that the contractor will submit a final payment

invoice, see id. 52.232-7(a)(4)(iii), which is exactly what the contracting officer requested

that SMARTECH do here. It is not the agency’s fault that SMARTECH inexplicably waited

two years to submit the final invoice after DOE asked for it, and SMARTECH is not entitled

CBCA 4068

24

to compensation for its own delay. See Zinger Construction Co., ASBCA 41690, 92-1 BCA

¶ 24,652, at 122,992 (1991) (PPA interest on delayed repayment of $1000 retainage did not

begin to accrue until contractor submitted invoice for retainage).

IV.

SMARTECH’s Diversion Claim

DOE seeks summary relief upon SMARTECH’s claim that, in the fourth option year,

DOE improperly diverted work away from this contract. In its certified claim, SMARTECH

alleged that “DOE cut off funding to the fourth and final option period under the contract on

March 31, 2008, six months into the 12-month option period,” which constituted a contract

breach “given DOE’s stated purpose to divert SMARTECH’s work to a new, successor

contractor.” Exhibit 72 at 3. SMARTECH complained that, although DOE did not terminate

SMARTECH’s contract for convenience, DOE failed to give SMARTECH any work under

the contract between March 31 and September 29, 2008, when the contract expired. Id.

SMARTECH’s diversion claim is wholly dependent upon whether its contract

constitutes a “requirements” contract. A requirements contract “provides for filling all actual

purchase requirements of designated Government activities for supplies or services during

a specified contract period (from one contractor), with deliveries or performance to be

scheduled by placing orders with the contractor.” 48 CFR 16.503(a). Only if SMARTECH

held a requirements contract could it complain if DOE diverted work to another contractor

after March 31, 2008. See Rumsfeld v. Applied Cos., 325 F.3d 1328, 1339 (Fed. Cir. 2003)

(“the government breaches a requirements contract when it has requirements for contract

items or services, but diverts business from the contractor and does not use the contractor to

satisfy those requirements”). Otherwise, SMARTECH was not guaranteed, and had no right

to demand, that work.

The contract at issue here is not labeled a requirements contract, and it does not

contain any of the contract clauses that the FAR mandates for requirements contracts. See

48 CFR 16.506(b), (d) (directing inclusion of FAR clauses 52.216-19 and 52.219-21 in

requirements contracts). Although “[d]etermination of the type of contract is a matter of law

– not controlled by a label in the contract,” Maintenance Engineers v. United States, 749 F.2d

724, 726 n.3 (Fed. Cir. 1984), the Federal Circuit in Coyle’s Pest Control, Inc. v. Cuomo, 154

F.3d 1302 (Fed. Cir. 1998), held (on review of a summary judgment decision) that a contract

which did not contain the typical FAR requirements contract clauses could not be interpreted

as a requirements contract, even if some clauses suggested some exclusivity, unless the

contract language actually required the agency to purchase all of its requirements from the

contractor under that contract:

CBCA 4068

25

The contract does include terms that suggest exclusivity. For instance, the

contract obligates Coyle “to furnish all labor, service, equipment,

transportation, materials and supplies to provide subterranean termite control

and related services on assigned properties by [HUD].” (emphasis added).

While the contract states that Coyle will provide all labor and services for a

given property, the clause does not require HUD to assign Coyle all properties

in the region. Thus, this contract language falls short of the exclusivity

language necessary for a requirements contract.

Id. at 1305-06. We have previously interpreted Coyle’s Pest to mean that, where “the

contract does not contain the FAR Requirements clause, to qualify as a requirements contract

it must contain ‘words of exclusivity’ that not merely suggest, but require that all of the work

be assigned to the contractor.” Environmental Quality Management, Inc. v. Environmental

Protection Agency, CBCA 3072, 13 BCA ¶ 35,300, at 171,283 (emphasis in original); see

The Ducke Group, LLC v. Department of Veterans Affairs, CBCA 3239, 13 BCA ¶ 35,337,

at 173,459 (rejecting argument that requirements contract exists where “[t]here is no

requirements clause or language to indicate that the agreement is such”); Marut Testing &

Inspection Services, Inc. v. General Services Administration, GSBCA 15412, 02-2 BCA

¶ 31,945, at 157,821 (“Although these [contract] provisions impose an obligation upon Marut

to perform and to provide the services contained in the contract’s statement of work, they do

not impose an obligation upon GSA to fulfill all of its requirements by utilizing only Marut’s

contract.”), appeal dismissed, 66 F. App’x 886 (Fed. Cir. 2003).

Here, the contract required SMARTECH to “furnish all personnel, facilities,

equipment, material, supplies, and services . . . and do all things necessary for, or incident

to,” providing “specialized technical support . . . in reviewing classified and unclassified[but-sensitive] documents.” Exhibit 8 at 4. The original solicitation indicated that DOE

anticipated making “[a] single” contract award for this work, and, “because services under

this contract [were] vital to the Government and must be continued without interruption,” the

contract required SMARTECH to be available to “furnish phase-in, phase-out services” and

work with a successor contractor “for up to 90 days after this contract expires.” Exhibit 8

at 60. Although this language suggests some exclusivity, there are no actual “words of

exclusivity” in the contract itself that expressly indicate that DOE is bound to order all of its

document review requirements from SMARTECH. Accordingly, we cannot find it to be a

requirements contract.9

9

SMARTECH cites to a declaration from its president in which he avers that he

understood that, until March 31, 2008, the OCCIR “ordered all of its requirements for

[non-appellate] classification and sensitive unclassified document review services” under

CBCA 4068

26

SMARTECH asserts that other tribunals have previously interpreted contracts to

constitute requirements contracts despite the absence of FAR clauses associated with such

contracts. See, e.g., Crown Laundry & Dry Cleaners, Inc. v. United States, 29 Fed. Cl. 506,

517-18 (1993); Rowe, Inc. v. General Services Administration, GSBCA 15217, 03-1 BCA

¶ 32,162, at 159,020; Centurion Electronics Service, ASBCA 51956, 03-1 BCA ¶ 32,097,

at 158,658 (2002). In those cases, though, the contracts were written as indefinite-quantities

contracts without any mandatory minimum orders, meaning that they would have been

unenforceable and void unless they were interpreted as requirements contracts. See Willard,

Sutherland & Co. v. United States, 262 U.S. 489, 493 (1923) (discussing indefinite-quantity

contracts with no minimum mandatory obligations). Here, the contract contains a minimum

payment obligation: the fixed fee to which SMARTECH is entitled in each contract period.

Further, the tribunals in those cases found language in the contracts providing for exclusivity.

The Federal Circuit’s decision in Coyle’s Pest and our decision in Environmental Quality

preclude us from adding language that does not exist to this contract, and we must find that

the contract is not a requirements contract. Accordingly, DOE’s diversion of work away

from this contract in the fourth option year, if that actually occurred, does not entitle

SMARTECH to damages.

As a companion to its diversion argument, SMARTECH asserts that DOE breached

the contract by exercising the fourth option period in bad faith, knowing at the time of the

option exercise that it did not intend to honor the full one-year period of the option. It cites

to the Federal Circuit’s decision in Salsbury Industries v. United States, 905 F.2d 1518 (Fed.

Cir. 1990), arguing that, “when the government contracts with a party knowing full well that

it will not honor the contract, it cannot avoid a breach claim.” Id. at 1521. In support of its

position, it asserts that, before DOE exercised the fourth year option, it was already working

on awarding a follow-on contract, and it asserts that discovery is necessary to determine

whether, when she exercised the option, the contracting officer actually intended to honor

the option’s one-year term. SMARTECH has not cited to any evidence of bad faith or

inappropriate intent. It had the opportunity to take discovery before responding to DOE’s

motion, but elected not to do so. Its entire defense to DOE’s motion is supposition and

speculation. That is insufficient to defeat a motion for summary relief. Mingus

Constructors, 812 F.2d at 1390-91; Barmag Barmer, 731 F.2d at 836.

SMARTECH’s contract. Jordan Declaration ¶ 28. The Federal Circuit in Coyle’s Pest

indicated that a similar declaration could not “override or contradict the plain language of the

contract, which does not require sufficient exclusivity for a requirements contract.” Coyle’s

Pest, 154 F.3d at 1306. It further found that such evidence is insufficient to show that both

parties shared the same contractual intent. Id. Accordingly, the declaration upon which

SMARTECH relies does not create a genuine issue of material fact.

CBCA 4068

27

We grant DOE’s motion for summary relief on SMARTECH’s diversion claim.

Decision

For the foregoing reasons, we grant appellant’s motion for summary relief, and deny

respondent’s cross-motion for summary relief, on the “fixed fee” claim. We grant

respondent’s cross-motion for summary relief, and deny appellant’s motion, on appellant’s

PPA claims. We grant summary relief to respondent on appellant’s diversion claim.

DOE does not contest the amount of the unpaid fees. See Answer ¶¶ 25, 46; Response

to ASUF ¶¶ 13 17, 18. Accordingly, we find that SMARTECH is entitled to payment of

$722,236.79 on its “fixed fee” claim, plus interest under the Contract Disputes Act (CDA),

41 U.S.C. § 7009, running from March 28, 2014, the date that SMARTECH submitted its

claim to the contracting officer, until the date of payment.

Accordingly, the appeal is GRANTED IN PART. DOE shall pay SMARTECH

$722,236.79, plus CDA interest running from March 28, 2014.

_____________________________

HAROLD D. LESTER, JR.

Board Judge

We concur:

____________________________

STEPHEN M. DANIELS

Board Judge

_____________________________

H. CHUCK KULLBERG

Board Judge