DENIED: December 5, 2008

Agency decision

Ask Donna

What actually matters in this document.

Text

DENIED: December 5, 2008

CBCA 802

GULF SHORES, LLC,

Appellant,

v.

DEPARTMENT OF HOMELAND SECURITY,

Respondent.

Michael J. Caywood of Dresser, Dresser, Haas & Caywood, P.C., Sturgis, MI, counsel

for Appellant.

Jean Hardin, Office of Chief Counsel, Federal Emergency Management Agency,

Department of Homeland Security, Washington, DC, counsel for Respondent.

Before Board Judges POLLACK, STEEL, and DRUMMOND.

DRUMMOND, Board Judge.

Gulf Shores, LLC (GS) alleges that the Department of Homeland Security, Federal

Emergency Management Agency (FEMA), owes it $146,632.50 under a purchase order for

the lease of mobile home pads in Port Charlotte, Florida.1

1

Appellant originally sought $191,029.50, which included, inter alia, $44,460

for attorney fees and costs relating to a dispute between appellant and a local utility authority

in Florida. At appellant’s request, by order dated April 23, 2008, the Board dismissed with

prejudice appellant’s claim for attorney fees and ordered that appellant’s claim be reduced

to $146,632.50.

CBCA 802

2

Respondent has filed a motion to dismiss, or in the alternative, a motion for summary

relief, arguing that GS’s claim should be dismissed or denied because appellant has failed

to state a claim upon which relief can be granted. GS opposes the motion.

Background 2

On September 7, 2004, FEMA issued purchase order (PO) number HSFEE-04-L-4097

to GS. The PO was for the lease of mobile home pads (pads) on which to place FEMA travel

trailers to be used for temporary housing in the aftermath of the devastation caused by

Hurricane Charlie. The pads were located at Vizcaya Lakes, a manufactured home

community owned and operated by GS, a Florida limited liability company, with its principal

place of business located in Michigan. Appeal File, Exhibits 1, 13; Supplemental Appeal

File, Exhibit 25; Complaint ¶ 3; Respondent’s Statement of Uncontested Facts (RSUF) ¶ 3.

The PO was signed only by FEMA and stated:

This is a firm fixed price purchase order for the lease of one hundred &

seventy five (175) . . . trailer pads. The lease price is $775.00 per month, per

pad including all utilities including electricity. The total amount of this order

is $813,750.00. The lease period for one hundred & forty-eight (148) pads is

from 25 August 2004 to 25 February 2005. The lease period for the remaining

twenty seven (27) pads is from 1 September 2004 to 1 March 2005.

Appeal File, Exhibit 1. The PO incorporated as an attachment a “Mobile Home Unit Pad

Lease” agreement dated August 25, 2004. Section 2 of the agreement stated:

The Lessor agrees to provide and maintain all water, sanitary, sewage,

electrical, [and] other utilities connections provided on the site at the time of

execution of this lease.

Id. Section 4 of the agreement stated that the monthly rental amount would remain at the

fixed rate “for a period not to exceed one (1) year from the date of the lease.” Id.

Neither the PO nor the agreement included any provision for adjustment of the fixed

rental rate prior to August 25, 2005. The PO also incorporated by reference Federal

Acquisition Regulation (FAR) clause 52.212-4, CONTRACT TERMS AND CONDITIONS

--COMMERCIAL ITEMS (2004), which states, in relevant part, that “the contract price

includes all applicable Federal, State, and local taxes and duties.” Appeal File, Exhibit 1.

2

The Board considers the following facts not to be in dispute.

CBCA 802

3

The PO was modified once to extend the leases for all 175 pads for three months at

$775 per month. The modification was signed by the parties and stated:

The lease for 148 units ended on 2/25/2005 and is extended through

5/25/2005. The lease for 27 additional units ended on 3/01/2005 and is

extended through 5/31/2005. The total amount of this modification is

increased from $813,750.00 to $1,220,625.00.

Appeal File, Exhibit 8. The modification did not include any provision for adjusting the

fixed rental rate. Id.

GS was authorized by the State of Florida to operate Vizcaya Lakes pursuant to an

approved prospectus. The cover letter for the prospectus, dated October 1, 1999, from the

Florida Department of Business and Professional Regulation, states, inter alia, that:

The park owner is obligated by law to furnish a copy of an approved

prospectus and all exhibits to each home owner. An approved prospectus must

be delivered by the park owner to each home owner . . . prior to increasing the

lot rental if no prospectus has been given.

Supplemental Appeal File, Exhibit 23. An attachment to that letter stated, inter alia, that

“upon delivery of the prospectus to a prospective lessee, the rental agreement is voidable by

the lessee for a period of 15 days.” Id. There is no evidence in the record that GS provided

a copy of the prospectus to FEMA or that FEMA agreed to be bound by the terms of the

prospectus.

The prospectus addressed generally fees and charges associated with water and sewer

services, including special assessments, hookup fees, and pass-through fees. No dollar

amounts were stated in the prospectus for any fees, charges, and assessments. Supplemental

Appeal File, Exhibit 23. There is no evidence in the record that FEMA agreed to pay any

fees in addition to the fixed monthly rental or that FEMA intended the PO to incorporate any

of the terms of the prospectus.

Water service was supplied to the pads by the El Jobean Water Association (EJWA)

through a system of underground pipes. GS had paid local and county impact fees for water

services prior to September 2004. Consequently, GS interpreted the PO as requiring it to pay

these fees in connection with providing and maintaining water services to the pads leased to

FEMA. GS has stated that the local water authority waived these fees in connection to it

providing water services to the pads leased to FEMA. Appellant’s Statement of Uncontested

CBCA 802

4

Facts (ASUF) ¶¶ 6, 7; Affidavit of Michael Sussex (Sept. 27, 2007) ¶¶ 9, 10; Supplemental

Appeal File, Exhibit 23.

Sewer services were provided to the pads by the Riverwood Community Development

District (RCDD) through a system of underground pipes. The RCDD, like the EJWA, was

a local utility authority in Florida. ASUF ¶ 8. A dispute arose between the RCDD and GS

concerning the payment of sewer impact fees. Several months before FEMA issued this PO,

the RCDD wrote to GS seeking payment of sewer impact fees for approximately seventeen

properties. Appeal File, Exhibit 13. There is no evidence in the record that GS received the

letter from the RCDD. GS claims that it was unaware that such fees were applicable to the

temporary FEMA disaster units installed at Vizcaya Lakes. GS has stated that it did not

anticipate paying any sewer impact fees under this PO. Complaint ¶ 15; ASUF ¶ 3; Appeal

File, Exhibit 11.

The total amount of the PO remained unchanged at $1,220,625. FEMA has paid GS

the full amount of the PO. Appeal File, Exhibit 9.

On June 23, 2006, GS sent to FEMA an invoice for increased costs. The increased

costs were for sewer impact fees paid to the RCDD for the period September 2004 to May

2005. The sewer impact fees totaled $146,632.50 and included: “Retroactive sewer fee

increase from $27.35 to $50.21 per month Sept. – May” totaling $36,004.50; “Sewer-hook

up fees” totaling $108,360; and “processing fees” totaling $2205. Appeal File, Exhibit 12.

GS has referred to the claimed fees collectively as sewer impact fees. Id., Exhibit 11.

GS submitted a certified claim to the contracting officer (CO) in the amount of

$146,632.50 on October 11, 2006, alleging, inter alia, breach of contract due to FEMA’s

refusal to reimburse GS for the sewer impact fees paid to the RCDD. GS stated that although

it had never before paid sewer impact fees, the RCDD had insisted that sewer impact fees

were owed for the “temporary housing units at Vizcaya Lakes constructed by GS as part of

the Hurricane Charlie effort.” Appeal File, Exhibit 14. GS asserted that the sewer impact

fees were not customary sewer fees but, rather, special assessments, and as such, were

FEMA’s obligation. Id., Exhibit 11.

The CO denied this claim, stating that the contract required GS “to provide and

maintain . . . sewer services . . . .” The CO noted that the PO was fixed-price and therefore

placed the risk of these fees on GS. The CO noted further that the contract lacked any

provision whereby GS could pass these fees to FEMA. Appellant filed a timely appeal with

the Board. Appeal File, Exhibits 13, 14.

CBCA 802

5

Discussion

The parties have submitted extensive briefs. We have considered all of their

arguments, whether or not we mention or discuss them. The Government claims that it is

entitled to summary relief since as a matter of law, based on the terms of the PO, appellant’s

claim must fail.

We are guided by the well-established rules applicable to summary relief motions.

Summary relief is appropriate where there is no genuine issue as to any material fact (a fact

that may affect the outcome of the litigation) and the moving party is entitled to relief as a

matter of law. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247 (1986). Any doubt on

whether summary relief is appropriate is to be resolved against the moving party. Celotex

Corp. v. Catrett, 477 U.S. 317, 325 (1986). The moving party shoulders the burden of

proving that no question of material fact exists. Adickes v. S.H. Kress & Co., 398 U.S. 144,

157 (1970).

However, under Rule 56(e) of the Federal Rules of Civil Procedure, which this Board

looks to for guidance, more than mere allegations are necessary to defeat a properly

supported motion for summary relief. Marine Metal, Inc. v. Department of Transportation,

CBCA 537, 07-1 BCA ¶ 33,554, at 166,175 (citing Fireman’s Insurance Co. of Newark, N.J.

v. DuFresne, 676 F.2d 965 (3d Cir. 1982); Tilden Financial Corp. v. Palo Tire Services, Inc.,

596 F.2d 604 (3d Cir. 1979); General Dynamics Corp., DOT CAB 1232, 83-1 BCA¶ 16,386,

at 81,459).

Respondent’s motion for summary relief restates the reasons the contracting officer

gave for denying appellant’s claim. Respondent maintains that appellant’s claim fails

because the contract required appellant to provide and maintain sewer services to the pads.

Respondent asserts that there is no provision in the contract to adjust the fixed price to

include these fees. Respondent also asserts that appellant could have negotiated a provision

to pass these fees to respondent, but neglected to do so.

Appellant responds that the Government breached the contract by refusing to

reimburse it for the sewer impact fees paid to the RCDD. Appellant asserts that impact fees

are special assessments and in the absence of a contract provision requiring it to pay these

fees, the Government is liable. Alternatively, appellant alleges that it is entitled to the

claimed amount based upon the doctrines of breach of duty of good faith and fair dealing and

unjust enrichment.

CBCA 802

6

Breach of Contract

In order to prevail on a breach of contract claim, appellant must establish that: (1) a

valid contract existed between it and the Government; (2) the contract gave rise to duties or

obligations; (3) the Government breached its duties or obligations; and (4) the breach resulted

in damages. See San Carlos Irrigation and Drainage District v. United States, 877 F.2d 957,

959 (Fed. Cir. 1989); Die Casters International, Inc. v. United States, 73 Fed. Cl. 174, 195

(2006).

At the outset, it must be emphasized that a purchase order is an offer to enter into a

unilateral contract, which can be accepted by a contractor when it performs pursuant to the

order’s terms. Reliable Disposal Co., ASBCA 40100, 91-2 BCA ¶ 23,895; L&D Industries,

Inc., ASBCA 38239, 91-2 BCA ¶ 23,718; Klass Engineering, Inc., ASBCA 22052, 78-2

BCA ¶ 13,236. It is undisputed that appellant accepted the PO by performing pursuant to its

terms. We find that a unilateral contract existed between the Government and appellant.

Appellant does not allege that the Government breached any express or implied

contractual duty. Rather, appellant alleges that the Government’s refusal to reimburse it for

the fees paid to the RCDD constitutes a breach. Appellant has offered no evidence which

supports this allegation. Rather, appellant asserts that in the absence of a provision requiring

it to pay these fees, the fees were the obligation of the Government. We are not persuaded.

Drawing all inferences in favor of appellant, it has failed to offer any evidence that

the Government breached any contractual duty by refusing to reimburse GS for the fees paid

to the RCDD. Since there is no express provision in the PO itself concerning the

Government’s liability for the claimed costs, appellant, to recover its claim, must prove that

the parties intended that the Government would be responsible for these costs beyond the

stated fixed amount. However, as shown in the factual summary, there is simply no evidence

of such intent.

It is undisputed that the contract was a fixed-price contract. It is further undisputed

that the contract required appellant to provide and maintain all utilities, including any

necessary connections, and to pay all applicable taxes at the fixed price, and contained no

clause shifting appellant’s risk of loss to the Government. Therefore the absence of a

provision specifically mentioning sewer impact fees or special assessments does not change

the nature of the contract, leaving it up to appellant to investigate its liability for sewer

impact fees as it did for the water impact and county impact fees.

CBCA 802

7

It is well settled that a contractor in a fixed-price contract assumes the risk of

unexpected costs. J. Filiberto Sanitation, Inc., VABCA 2696, 88-3 BCA ¶ 21,160, at

106,813 (citing ITT Arctic Services, Inc. v. United States, 524 F.2d 680, 691 (Ct. Cl. 1975);

McNamara Construction of Manitoba, Ltd. v United States, 509 F.2d 1166 (Ct. Cl. 1975);

Sperry Rand Corp. v. United States, 475 F.2d 1168 (Ct. Cl. 1973)). Performance rendered

more burdensome or costly by an unforseen cause is insufficient to entitle a contractor to

compensation beyond that provided for in the contract. Appellant has failed to produce any

evidence that the parties intended that the Government assume any risk if appellant incurred

unanticipated expenses. See ITT Arctic Services, 524 F.2d at 691. Since the contract did not

obligate the Government to pay sewer impact fees, we find that the Government did not

breach the contract by refusing to reimburse appellant for the fees paid to the RCDD.

We find that appellant has failed to offer evidence in response to the Government’s

motion that would meet its burden of proving the second and third elements of a breach

claim. We hold that, on the record before us for purposes of the Government’s motion, there

are no disputed material facts and undisputed facts fail to support appellant’s breach claim.

The Government is, therefore, entitled to judgment in its favor as a matter of law.

Ambiguity

In its claim, appellant alleges that the Government is liable to it for the sewer impact

fees because the contract is ambiguous. We are not persuaded.

Contract language must be read in accordance with its express terms and plain

meaning. C. Sanchez and Son, Inc. v. United States, 6 F.3d 1539, 1543 (Fed. Cir. 1993);

Hills Materials Co. v. Rice, 982 F.2d 514, 516 (Fed. Cir. 1992); Hol-Gar Manufacturing

Corp. v. United States, 351 F.2d 972, 976 (Ct. Cl. 1965). When a provision in a contract is

susceptible to more than one reasonable interpretation, it is ambiguous. Corners & Edges,

Inc. v. Department of Health and Human Services, CBCA 648-R, 08-1 BCA ¶ 33,741 (2007)

(citing Teg-Paradigm Environmental, Inc. v. United States, 465 F.3d 1329, 1338 (Fed. Cir.

2006)). If the ambiguity is “obvious, gross, [or] glaring,” then it is patent, and the contractor

has a duty to seek clarification of the ambiguity before entering the contract or suffer the

consequence of its own erroneous interpretation. H & M Moving, Inc. v. United States, 499

F.2d 660, 671 (Ct. Cl. 1974); see also Newsome v. United States, 230 Ct. Cl. 301 (1982). By

contrast, if the ambiguity is not glaring, substantial, or patently obvious, then it is latent and

the contractor must establish reliance on its interpretation. Grumman Data Systems Corp.

v. Dalton, 88 F.3d 990, 997 (Fed. Cir. 1996); Fruin-Colnon Corp. v. United States, 912 F.2d

1426, 1429 (Fed. Cir. 1990). In the event we determine that the ambiguity in the contract

was not patent, then “the contract is construed against its drafter if the interpretation

CBCA 802

8

advanced by the nondrafter is reasonable.” Fort Vancouver Plywood Co. v. United States,

860 F.2d 409, 414 (Fed. Cir. 1988).

For its part, respondent argues that the contract language is clear and appellant is not

entitled to the requested relief and accordingly, appellant is responsible for all costs

associated with providing and maintaining utilities and taxes. Respondent notes that the

contract includes no provision for adjusting the fixed price during the lease period.

Respondent argues further that the sewer impact fees constitute a tax which is appellant’s

responsibility.

Appellant contends that the wording in section 2 of the contract is ambiguous.

According to appellant, sewer impact fees are not customary sewer fees within the meaning

of section 2 of the contract, but instead special assessments which are the responsibility of

the Government. Appellant does not explain the difference between impact fees for water

and sewer, other than to say that it had never paid any impact fees for sewer services before

this contract. Appellant’s naked characterization that the fees assessed by the RCDD are

special assessments because they had never been assessed before is not per se evidence that

the contract is ambiguous, nor is it evidence that the fees are special assessments. Moreover,

appellant’s alleged interpretation of section 2 as excluding impact fees for sewer services is

not reasonable, given that appellant initially interpreted the contract as requiring it to pay

water impact fees and county impact fees for the pads leased to the Government. It is

undisputed that appellant did not make any inquiry and performed consistent with the stated

contract terms.

Drawing all interferences in favor of appellant, the contract, plainly read, sets a fixed

price for the pads, including all utilities and taxes, and does not provide for any adjustment

in the contract price due to the imposition of sewer impact fees or special assessments. The

absence of a provision addressing sewer impact fees or special assessments does not change

the nature of the contract. It leaves to appellant to investigate its liability for any sewer

impact fees or assessments, as it did for the water impact fees, and to include that in the

contract, if it expects compensation. Section 2, after all, says nothing about fees; it requires

appellant to provide and maintain utility connections, regardless of what those connections

might cost. We find that the undisputed record discloses nothing more than a unilateral error

of judgment by appellant in accepting the contract with FEMA.

Appellant also advances that the contract, through the Florida Mobile Home Act

(FMHA), incorporates the prospectus, thereby “providing numerous provisions clearly

placing the burden of impact fees squarely on the shoulders of the lessee, FEMA.” Appellant

argues that the FMHA makes it clear that a prospectus is deemed to be incorporated into the

rental agreement. Fla. Stat. § 723.031(10) (2004). Further, appellant alleges that it would

CBCA 802

9

be disingenuous for FEMA to now argue the FMHA does not apply, given that the

Government referred to it when distinguishing between a property tax and sewer utility fee

in its motion.

Respondent argues that no provision of the FMHA or prospectus affects the terms of

the firm fixed-price contract because the contract makes no reference to either the FMHA

or prospectus and they were not submitted to the agency during negotiations. The

Government alleges appellant’s argument is misplaced because the FAR governs the contract

between appellant and the Government. Further, respondent asserts that the earlier reference

to Florida law when distinguishing between a property tax and sewer utility fee was for

persuasive value only.

Appellant’s reliance upon Florida law is misplaced. Federal law controls the

interpretation of contracts, including leases, to which the Federal Government is a party.

Forman v. United States, 767 F.2d 875, 880 (Fed. Cir. 1985); 41 U.S.C. § 602 (2000).

Furthermore, the plain language of this contract contained no reference to the FMHA or

prospectus. There is no evidence that the parties intended the contract to incorporate either,

and significantly, at the time the contract was performed, appellant did not expect to charge

respondent the contested fees. The PO, even if the FMHA was incorporated, had nothing in

it to hold respondent to the claimed fee. We find that the terms of the contract between

appellant and respondent are restricted to the provisions stated or specifically incorporated

into the contract. G. L. Christian & Associates v. United States, 312 F.2d 418 (Ct. Cl. 1963).

Accordingly, the Board finds no merit in this argument.

We hold that, on the record before us for purposes of the Government’s motion, there

are no disputed material facts and the undisputed facts fail to support appellant’s allegation

that the contract is ambiguous. The Government is, therefore, entitled to judgment in its

favor as a matter of law.

Mistake

To be granted reformation on the basis of a mutual mistake of fact, a party must prove

that: (1) the parties to a contract were mistaken in their belief regarding an existing fact; (2)

the mistake constitutes a basic assumption underlying the contract; (3) the mistake had a

material effect on the bargain; and (4) the contract did not put risk of the mistake on the party

alleging mistake. Dairyland Power Cooperative v. United States, 16 F.3d 1197, 1202 (Fed.

Cir. 1994); Atlas Corp. v. United States, 895 F.2d 745, 750 (Fed. Cir. 1990). The purpose

and function of the reformation of a contract is to make it reflect the true agreement of the

parties on which there was a meeting of the minds. To establish a mutual mistake warranting

CBCA 802

10

reformation, appellant must first show that both parties to the contract were mistaken in their

belief regarding an existing fact.

Appellant asserts that it had never been assessed these fees before. Appellant’s

understanding and expectation concerning these fees after contract award is not a mistake as

to an existing fact as:

“A party’s prediction or judgment as to events to occur in the future, even if

erroneous, is not a ‘mistake’ as that word is defined [under the doctrine of

mutual mistake of fact].” Restatement (Second) of Contracts § 151 cmt. a

(1981); . . . United States v. Garland, 122 F.2d 118, 122 (4th Cir. [1941]) (“A

mutual mistake in prophecy or opinion may not be taken as a ground for

rescission where such mistake becomes evident through the passage of time.”).

. . . Indeed, there is uniformity among the circuit courts of appeals and the

commentators that mutual mistake of fact cannot lie against a future event.

Dairyland, 16 F.3d at 1203. Appellant’s mistaken belief about whether it would be required

to pay these fees in the future after contract award cannot form the basis for a mutual mistake

of fact. Furthermore, appellant has presented no evidence as to respondent’s belief if any as

to the fees at the time the purchase order was issued. It is therefore immaterial whether

appellant’s belief about the likelihood of these fees in the future was reasonable or not, and

we need not address that issue.

Drawing all inferences in favor of appellant, appellant has failed to offer evidence in

response to the Government’s motion that would meet the burden of proving the first element

of mutual mistake of fact. Absent proof of a mutual mistake regarding an existing fact,

whether the other elements might be sustained is immaterial. Alfair Development Co.,

ASBCA 53119, et al., 05-2 BCA ¶ 32,990, at 163,514, aff’d, 208 Fed. Appx. 840 (Fed. Cir.

2006).

We hold that, on the record before us in support of the motion, there are no disputed

material facts and the undisputed facts fail to support appellant’s theory of mutual mistake

of fact. The Government is, therefore, entitled to judgment in its favor as a matter of law.

In its opposition papers, appellant offers several other legal theories, such as unjust

enrichment and breach of duty of good faith and fair dealing to support its position. We have

considered them all, but are not persuaded that any of them – singly or in combination – can

defeat the Government’s motion on this record.

CBCA 802

11

Decision

Respondent’s motion for summary relief is granted. This appeal is DENIED.

JEROME M. DRUMMOND

Board Judge

We concur:

HOWARD A. POLLACK

Board Judge

CANDIDA S. STEEL

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.