RESPONDENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT GRANTED;
Agency decision
Ask Donna
What actually matters in this document.
Text
RESPONDENT’S MOTION FOR PARTIAL SUMMARY JUDGMENT GRANTED;
APPELLANT’S MOTION FOR PARTIAL SUMMARY JUDGMENT DENIED:
August 29, 2025
CBCA 8034
ALL PHASE SERVICES, INC.,
Appellant,
v.
DEPARTMENT OF VETERANS AFFAIRS,
Respondent.
Lawrence J. Sklute of Sklute & Associates, Potomac, MD, counsel for Appellant.
Jennifer L. Hedge, Office of General Counsel, Department of Veterans Affairs,
Pittsburgh, PA, counsel for Respondent.
Before Board Judges BEARDSLEY (Chair), SHERIDAN, and SULLIVAN.
SULLIVAN, Board Judge.
All Phase Services, Inc. (APS) appealed the termination for default issued by the
contracting officer for the Department of Veterans Affairs (VA). The parties filed crossmotions for summary judgment on various aspects of their respective burdens of proof. VA
asks that we find that, based upon the undisputed facts, APS was in default when VA
terminated the contract. We find that the contracting officer properly reestablished the
contract completion date (CCD) and based his termination of the contract on APS’s failure
to make progress on the contract to meet that date. APS failed to establish that the CCD was
CBCA 8034
2
later in time or that VA failed to consider its request to use a different roofing product. On
the basis of these findings, we grant VA’s motion for partial summary judgment asking us
to find that it has established a prima facie case of default and deny APS’s motion. With the
prima facie case of default now established, APS’s evidence and arguments as to why its
failure to perform should be excused will be the focus of the hearing scheduled for October
2025.
Background
I.
Contract Award and Relevant Terms
In October 2020, VA awarded to APS a contract to replace fifty-five roofs at the VA
Medical Center located in Buffalo, New York. Exhibits 7 at 2074; Respondent’s Statement
of Undisputed Material Facts ¶ 16. The period of performance was 730 days measured from
the notice to proceed issued at the contract kick-off meeting. Exhibit 7 at 2074, 2105.1 The
parties convened the kick-off meeting on November 12, 2020, which made the CCD
November 12, 2022. Exhibit 9 at 2156. The parties later modified the contract and added
thirty days to the performance period of the contract, pushing the CCD to December 12,
2022. Exhibit 39 at 2655.2
The contract incorporated by reference two clauses relevant to the Board’s
consideration of the parties’ motions: (1) Default (APR 1984) clause, Federal Acquisition
Regulation (FAR) 52.249-10 (48 CFR 52.249-10), which provides, in part, “[i]f the
Contractor refuses or fails to prosecute the work or any separable part, with the diligence that
will insure its completion within the time specified in this contract including any extension
. . . the Government may, by written notice to the Contractor, terminate the right to proceed,”
Exhibit 7 at 2118; and (2) Permits and Responsibilities (NOV 1991) clause, FAR 52.236-7,
which provides, in part, that “[t]he Contractor shall be responsible for all materials delivered
and work performed until completion and acceptance of the entire work.” Id. The contract
did not include a provision allowing VA to assess liquidated damages.
1
“Exhibit XX at XXXX” refers to the exhibits in the appeal file and the bates
page numbers applied by the parties.
2
This exhibit incorrectly states that the CCD was November 12, 2022.
Respondent’s Statement of Undisputed Facts at 4 n.3. APS objects to this proposed finding,
but does not object to the finding that the original CCD was November 12, 2022.
Appellant’s Statement of Genuine Issues, ¶ 26. If one adds 30 days to the original CCD, the
new CCD would be December 12, 2022.
CBCA 8034
3
The contract contained two clauses which delegated contract administration functions
to the contracting officer’s representative (COR) but also limited the COR’s authority to
certain functions—Veterans Affairs Acquisition Regulation (VAAR) 852.242-70,
Government Construction Contract Administration (APR 2019) (Exhibit 7 at 2126), and
VAAR 852.270-1, Representatives of Contracting Officers (JAN 2008) (Exhibit 7 at 2129).
Pursuant to VAAR 852.270-1, the contracting officer issued a memorandum defining the
limits of the COR’s authority which included a limitation that the COR could not “encourage
the contractor by words, actions, or a failure to act to undertake new work or an extension
of existing work beyond the contract period.” Exhibit 8 at 2153. The memorandum further
advised that any unauthorized commitment made by a COR was not a binding commitment
on behalf of the Government. Id. The president of APS acknowledged receipt of this
memorandum in November 2020. Id. at 2155.
The contract contained specifications for the submittals requesting approval of
products to be used on the contract. Exhibits 2 at 178-81, 7 at 2084. These specifications
included the requirement for a transmittal form, and, if the transmittal was a request for a
deviation, the submittal was to include “a side by side comparison of [the] item being
proposed against [the] item specified.” Exhibit 2 at 180. The specification further advised
that incomplete submittals would be returned without review. Id. at 179. VA kept a log for
all submittals. Exhibits 7 at 2084, 104 at 4049.
II.
Extension of the CCD
The parties agree that VA did not enforce the CCD of December 2022, but dispute
what date was agreed to as the new CCD. APS asserts that the VA contracting officer
approved an extension to July or October 2025. VA maintains that the parties agreed that the
CCD would be October 2024. We set forth here the facts that underlie the parties’
contentions.
On September 22, 2022, APS submitted to the COR a proposed schedule showing
performance through June 2025. Exhibit 220 at 3127-31. On September 26, 2022, the COR
responded indicating that the schedule was approved. Id. at 3125. Similarly, on October 24,
2022, the COR approved another schedule update showing performance through June 2025.
Exhibit 222 at 3319-28. The contracting officer was included on both of the COR’s emails.
CBCA 8034
4
On October 28, 2022, APS submitted its request for a contract extension to July 3,
2025, to the contracting officer. Exhibit 75 at 3666.3 By email the same day, the VA
contracting officer responded and disagreed with APS’s explanations of the need for an
extension. Id. at 3665. He also suggested that APS revise its extension request. Id.
On January 5, 2023, APS submitted a request for a contract extension to October 3,
2025. Exhibit 143 at 4574, 4585-86. After a further exchange of emails regarding the status
of APS’s efforts to hire a new roofing subcontractor, on January 26, 2023, the contracting
officer stated that he was willing to allow the contact to proceed and requested that APS
submit a “request for contract extension since this [s]chedule extends into 2024 when the
original stated the project would be completed in 2022.”4 Exhibit 88 at 3795. The
contracting officer further stated that “[f]or the contract [period of performance (POP)]
extension request I will attach what was sent by [APS’s former project manager] and our
comments in response. I need this right away to develop a modification to the contract.
Complete this POP request ASAP and send to [COR] and I for review.” Id. To the email,
the contracting officer attached APS’s previous request for an extension to October 3, 2025,
with an accompanying schedule. Id. at 3810-12.5
By letter dated January 30, 2023, APS submitted to the contracting officer a POP
extension request, seeking an extension to October 10, 2025. Exhibit 147. On March 7,
2023, the contracting officer issued a cure notice pursuant to FAR 52.211-10,
Commencement, Prosecution and Completion of Work (APR 1994). Exhibit 92. The
contracting officer stated that the proposed schedule extension to October 10, 2025, was not
3
APS disputes that this letter was a request for an extension because the COR
had already approved the requested extension. Appellant’s Revised Statement of Genuine
Issues, ¶ 56. APS’s contention is contradicted by the text of the letter itself wherein APS
“requests an extension to July 3, 2025.” Exhibit 75 at 3666.
4
APS noted that the contracting officer’s email did not accord with their request.
In an email to the COR the following day the president of APS noted that the contracting
officer had said the schedule went to 2024, but their request was for 2025. Exhibit 146 at
4647.
5
Exhibit 145 contains the same email exchanges between the contracting officer
and APS and appends the schedule showing the proposed completion date of October 2025.
Exhibit 145 at 4640-41. But, this exhibit accords with the contracting officer’s note that he
was attaching the previous request for an extension through July 3, 2025, and VA’s previous
response. Id. at 4642-44.
CBCA 8034
5
acceptable to the VA. Id. at 3848. Instead, the contracting officer directed APS to submit
a revised schedule with a CCD of October 10, 2024. Id. at 3849.
By letter dated March 17, 2023, APS responded to the cure notice and submitted a
schedule showing final inspection in October 2024. Exhibit 93 at 3850-51, 3908-09. APS
described the construction schedule as part of its “plan of action” and did not object to the
contracting officer’s direction that it assemble the schedule based upon a CCD of October
10, 2024. Id. at 3851.
III.
Contracting Officer’s Termination Decision
On December 12, 2023, the contracting officer issued a decision terminating the
contract for default because APS had “failed to diligently pursue the remaining work on the
contract in order to ensure completion.” Exhibit 123 at 4252. The contracting officer
terminated the contract after issuing two cure notices in which the contracting officer sought
assurances of APS’s ability to perform. Exhibits 92, 109. At the point the contract was
terminated, APS had performed thirteen percent of the work on the contract. Respondent’s
Statement of Undisputed Material Facts ¶¶ 117, 123 (citing Exhibit 123 at 4259). At
termination, APS had not finalized a contract with a subcontractor to complete the roofing
work. Id. ¶ 124 (citing Exhibit 184 at 3404). At termination, APS had not completed the
punch list on the seven roofs on which it had worked. Id. ¶¶ 64, 125 (citing Exhibit 185
¶ 14). At termination, APS had not begun work on forty-eight of the roofs to be re-roofed
in performance of the contract. Id. ¶ 126 (citing Exhibit 185 ¶ 16). APS does not dispute any
of these proposed material facts. Appellant’s Statement of Genuine Issues ¶¶ 64, 117,
123-126.
IV.
Evidence of Workmanship Defects/Issues
VA asserts that the evidence of poor workmanship by APS on the roofs that it
completed provides another basis for the default termination. In support of this allegation,
VA cited to emails and contract reports that discuss damage to roofs thirty-six and forty.
Respondent’s Supplemental Statement of Undisputed Material Fact ¶¶ 35, 48, 50-54, 154;
Exhibits 68, 177-179. In response, APS provided a declaration of its project superintendent
explaining that the issues related to roofs thirty-six and forty were fixed by APS. Exhibit 296
at 6834.
V.
Request for Consideration of Use of Kemper Products
Because it was having difficulty obtaining a subcontractor that was certified to use the
already-approved Tremco roofing products, APS, in response to the second cure notice,
CBCA 8034
6
offered to switch to Kemper roofing products. Exhibit 164 at 4822. As part of its response,
APS offered a single sheet listing, for comparison purposes, the properties of both the
Tremco and Kemper roofing materials. APS indicated that the sheet was provided for the
contracting officer’s “review and approval.” Id. APS does not cite to any other
documentation that it provided for VA’s review and approval of its request to switch to
Kemper products. The submittal log does not list a submittal for use of the Kemper products.
Exhibit 104.
Discussion
Standards for Review
APS seeks to overturn the contracting officer’s termination of its contract for default.
Termination for default is a drastic sanction. J.D. Hedin Construction Co. v. United States,
408 F.2d 424, 431 (Ct. Cl. 1969). VA bears the burden of establishing a prima facie case
that the contractor was in default, and, if VA satisfies that burden, APS bears the burden of
establishing that its failure to perform should be excused. CDA, Inc. v. Social Security
Administration, CBCA 1558, 12-1 BCA ¶ 34,990, at 171,971 (citing Integrated Systems
Group, Inc. v. Social Security Administration, GSBCA 14054-SSA, 98-2 BCA ¶ 29,848, at
147,742).
“In deciding a motion for summary judgment, we initially determine if there are
material facts in dispute; we will not weigh the facts and evidence. Only when there are no
material facts in dispute do we look to whether the movant is entitled to judgment as a matter
of law.” Centex Bateson Construction Co., VABCA 5166, et al., 97-2 BCA ¶ 29,196, at
145,252. While “[a]ny doubt as to the existence of a disputed issue of material fact must be
resolved against the non-moving party,” Campos Construction Co., VABCA 3019, 90-3
BCA ¶ 23,108, at 116,012, the non-moving party “must present sufficient evidence, by
pointing to some part of the record or additional evidence, indicating that the facts differ
significantly from the way the non-movant has presented them.” Centex Bateson, 97-2 BCA
at 145,252.
The Contract Completion Date Was October 10, 2024
VA terminated the contract based upon APS’s failure to make progress and concern
that APS would not complete the contract on time. To decide this issue, we first need to
determine the CCD. See Omni Development Corp., AGBCA 97-203-1, et al., 05-2 BCA
¶ 32,982, at 163,433 (“Since the endangerment issue is tied to final completion and
occupancy, we need to determine how much time [the contractor] had remaining for
performance at the time of termination.”).
CBCA 8034
7
The parties do not dispute that VA did not enforce the original CCD. In January 2023,
more than a month past the December 2022 CCD, the contracting officer told APS that he
was willing to allow APS to continue with the contract. “Where the Government elects to
permit a delinquent contractor to continue performance past a due date, it surrenders its
alternative and inconsistent right under the Default clause to terminate, assuming the
contractor has not abandoned performance and a reasonable time has expired for a
termination notice to be given.” DeVito v. United States, 413 F.2d 1147, 1153 (Ct. Cl. 1969).
The parties disagree as to the date of the new CCD. APS urges the Board to find that
the new CCD was either in July or October 2025, based upon the contracting officer’s
purported approval of APS’s extension requests. For the July 2025 date, APS recites facts
regarding the COR’s efforts to help APS develop the schedule and then his communications
indicating that he approved the schedule submissions. Pursuant to the terms of the contract,
the COR did not have the authority to approve such a schedule extension. APS demonstrated
its understanding of this limitation when it submitted the July 2025 schedule extension
request to the contracting officer. Moreover, while the fact that the contracting officer was
included on the emails between the COR and APS regarding his “approval” of the schedule
extensions may constitute knowledge of the COR’s actions, APS cannot establish ratification
by the contracting officer because he rejected the subsequent schedule extension request. See
Winter v. Cath-dr/Balti Joint Venture, 497 F.3d 1339, 1347 (Fed. Cir. 2007) (“Ratification
requires knowledge of material facts involving the unauthorized act and approval of the
activity by one with authority.”).
For the October 2025 schedule extension request, APS relies upon the fact that the
contracting officer attached to his email the schedule showing performance through October
2025. But, this attachment does not comport with the text of the contracting officer’s email
which requested a schedule with a CCD in 2024. And, the contracting officer asked for a
proper extension request, which APS submitted based upon the October 2025 date, and the
contracting officer rejected the request. This record does not provide a basis for us to find
that the contracting officer is somehow bound to an October 2025 performance extension due
to an inadvertent attachment.
VA asserts that the contracting officer set the new CCD of October 2024 in the first
cure notice. VA further asserts that APS agreed to this date by submitting a schedule that
complied with the new CCD date. Bilateral agreement on a new schedule date has been
found when the contracting officer requests a new date from the contractor, the contractor
supplies a new date in a proposed schedule, and the contracting officer adopts the schedule
as the one for the contract. ASC Systems Corp., DOTCAB 73-37, et al., 78-1 BCA ¶ 13,119,
at 64,137.
CBCA 8034
8
APS challenges this assertion, claiming that APS only submitted the schedule based
on the October 2024 CCD under threat of termination, a form of economic duress. To
establish economic duress, APS has to establish that (1) it involuntarily accepted VA’s date,
(2) the circumstances permitted no alternative, and (3) the circumstances were the result of
VA’s coercive acts. Fortis Industries, LLC v. General Services Administration, CBCA 7967,
24-1 BCA ¶ 38,668, at 187,969. To establish that VA’s actions were coercive, APS would
have to show “a wrongful action by the Government that was illegal, a breach of an express
provision of the contract without a good-faith belief that the action was permissible under
the contract, or a breach of the implied covenant of good faith and fair dealing.” Id. The
contracting officer properly reset the CCD in a cure notice issued pursuant to the Default
clause. “The proper way thereafter for time to again become of the essence is for the
Government to issue a notice under the Default clause setting a reasonable but specific time
for performance.” DeVito, 413 F.2d at 1154; see also id. at 1155 (noting that the contracting
officer would have been well-advised to issue a cure notice setting a reasonable time for
performance). Asking APS for a schedule to reestablish the CCD on the contract did not
violate the terms of the contract or the implied covenant of good faith and fair dealing. APS
has failed to rebut VA’s showing that the CCD was established as October 10, 2024.
VA Has Established a Prima Facie Case That APS Was In Default
The contracting officer terminated the contract because APS had failed to make
sufficient progress on the contract to ensure timely completion. A termination for default for
failure to prosecute the work requires “a reasonable belief on the part of the contracting
officer that there was ‘no reasonable likelihood that the [contractor] could perform the entire
contract effort within the time remaining for contract performance.’” Lisbon Contractors,
Inc. v. United States, 828 F.2d 759, 765 (Fed. Cir. 1987) (quoting RFI Shield-Rooms,
ASBCA 17374, et al., 77-2 BCA ¶ 12,714, at 61,735). The agency is not required to prove
that performance was impossible. RFI Shield-Rooms, 77-2 BCA at 61,735. Instead, the
termination will be upheld where “a demonstrated lack of diligence indicates that [the
agency] could not be assured of timely completion.” Id.
At the time the contract was terminated, with one roofing season left to complete the
contract, APS had not started work on forty-eight of the fifty-five roofs that it was to
complete on the contract and had not completed the punch list on the seven roofs on which
it had worked. APS also did not have a subcontractor to perform the roofing work. Based
upon these undisputed material facts, VA has established that the contracting officer had a
reasonable belief that APS would be unable to complete the contract within the time
remaining.
CBCA 8034
9
“Once the Government establishes the existence of default,” as VA has done here,
“the burden shifts to the contractor to prove that there were excusable delays under the terms
of the default provision of the contract that render the termination inappropriate . . . or that
it was making sufficient progress on the contract such that timely contract completion was
not endangered.” 1-A Construction & Fire, LLP v. Department of Agriculture, CBCA 2693,
15-1 BCA ¶ 35,913, at 175,553. APS did not include in its motion any grounds for why its
failure to make progress should be excused. This issue will be the focus of the hearing
scheduled for October 2025.
VA Has Not Established That the Roof Leaks Provide an Alternate Basis for Termination
VA terminated APS’s contract based upon APS’s failure to make progress. Since the
appeal was filed, VA has offered an alternate basis for the termination—poor workmanship
by APS led to leaks in the roofs that APS worked on. “[I]t is well-settled that a default
termination can be sustained ‘if justified by circumstances at the time of termination,
regardless of whether the Government originally removed the contractor for another
reason.’” 1-A Construction, 15-1 BCA at 175,554 (quoting Kelso v. Kirk Brothers
Mechanical Contractors, Inc., 16 F.3d 1173, 1175 (Fed. Cir. 1994)). Poor workmanship can
be a proper basis for a default termination. M.C. & D. Capital Corp. v. United States, 948
F.2d 1251, 1256 (Fed. Cir. 1991).
As evidence of the poor workmanship, VA provides proposed findings based upon
emails detailing leaks in two roofs in the 2021 and 2022 timeframe. APS rebuts these
findings with evidence that states these leaks were repaired. On this record, applying the
standards for summary judgment, the Board is unable to find that the alleged workmanship
failures provided an alternate basis for termination.
APS Has Not Established That VA Failed to Consider a Proper Request to Use Kemper
Products
APS alleges that VA violated the duty of good faith and fair dealing not to interfere
in the performance of the contract by failing to investigate the use of Kemper roofing
products on the contract. VA responds that APS failed to make a proper submission for VA
to consider.
As noted above, the contract contains specific requirements regarding the submittal
of information for the approval by VA. As support for its contention that VA failed to
consider the Kemper product, APS points to its response to the second cure notice wherein
it stated that it was providing, for the contracting officer’s review and approval, a single sheet
that compared the properties of the Tremco and Kemper products. VA counters that this
CBCA 8034
10
single sheet does not comport with the contract requirements for submittals. APS has not
shown on the current record that it made a proper submission for VA to consider.
Decision
VA’s motion for partial summary judgment is GRANTED, and APS’s motion is
DENIED. The parties’ presentations at hearing in October 2025 will be limited to the
evidence and arguments regarding why APS’s failure to perform should be excused.
Marian E. Sullivan
MARIAN E. SULLIVAN
Board Judge
We concur:
Erica S. Beardsley
ERICA S. BEARDSLEY
Board Judge
Patricia J. Sheridan
PATRICIA J. SHERIDAN
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.