In the Matter of HARRIS COUNTY, TEXAS
Agency decision
Ask Donna
What actually matters in this document.
Text
December 15, 2020
CBCA 6909-FEMA
In the Matter of HARRIS COUNTY, TEXAS
Wendy Huff Ellard of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,
Jackson, MS; Michelle Zaltsberg of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,
Orlando, FL; Jordan Corbitt of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,
Houston, TX; and Randall Smidt, Vince Ryan, and Robert Soard of the Office of the Harris
County Attorney, Houston, TX, counsel for Applicant.
W. Nim Kidd and Suzannah Jones, Texas Division of Emergency Management,
Austin, TX; and Julie A. Masek, Texas A&M University System, College Sation, TX,
appearing for Grantee.
Christiana C. Cooley and Ramoncito J. deBorja, Office of Chief Counsel, Federal
Emergency Management Agency, Department of Homeland Security, Washington, DC; and
John Dimos, Office of Chief Counsel, Federal Emergency Management Agency, Department
of Homeland Security, Baton Rouge, LA, counsel for Federal Emergency Management
Agency.
Before the Arbitration Panel consisting of Board Judges ZISCHKAU, LESTER, and
CHADWICK.
In late 2017, Harris County incurred more than $45 million in debris removal costs
after Hurricane Harvey, a category four storm, caused massive flooding in Harris County and
other nearby areas in Texas. The Federal Emergency Management Agency (FEMA) granted
Harris County’s request for public assistance (PA) under the Robert T. Stafford Disaster
Relief and Emergency Assistance Act (Stafford Act), 42 U.S.C. § 5189a (2018), reimbursing
all but $15 million of the claimed costs. Harris County sought arbitration under 42 U.S.C.
CBCA 6909-FEMA
2
§ 5189a(d) of FEMA’s denial of that $15 million. We grant Harris County’s application in
part.
Background
The massive flooding that Hurricane Harvey caused in Harris County occurred over
the course of several days beginning August 25, 2017. Thousands of residential and
commercial structures were flooded, with varying degrees of inundation and damage. For
Harris County, 70% of which was eventually covered in water, that flooding required that
unprecedented amounts of debris be removed and disposed of in an expedited manner for
public health and safety reasons. The President declared a major disaster for the State of
Texas on August 25, 2017, and authorized PA funding for both emergency and permanent
work for Harris County.
Prior to Hurricane Harvey, Harris County had agreements in place with two different
vendors—one designated as the “primary” vendor and the other, DRC Emergency Services,
LLC (DRC), designated as the “secondary” vendor—to provide emergency debris removal
services for Harris County if and when they were necessary. The two vendors were selected
from six that responded to a request for bids that Harris County issued in 2015 in anticipation
of possible future emergencies. The agreement with each vendor provided that “work shall
consist of clearing and removing any and all ‘eligible’ debris as defined by FEMA
Publication 325, all applicable State and Federal Disaster Specific Guidance and policies,
and/or as directed by the County.” Applicant Exhibit 21 at 23. Nevertheless, neither
agreement imposed any limitations on the amount of time that debris removal services might
take, something that DRC’s president testified is standard in the industry because the
imposition of such deadlines is considered too risky for contractors that accept these types
of pre-positioned contracts. Each agreement provided that “[t]hese services will only be
utilized during emergency situations” and that “funds will not be encumbered until the
services are needed and the County activates the contract.” Id. Neither vendor could provide
any services “without a Harris County Purchase Order, signed by an authorized agent of the
Harris County Purchasing Department.” Id. at 19.
The relevant pricing terms for the debris removal services at issue in this arbitration
provided for a specific unit price per cubic yard for debris removed, a unit price for each
abandoned vehicle removed, a unit price for each tree or stump removed, and a unit price per
pound of asbestos removed, without regard to the number of labor hours that each task
required. The prices in each agreement were to “be all inclusive,” such that “[n]o price
changes, additions, or subsequently qualifications will be honored during the course of the
contract.” Applicant Exhibit 21 at 18. Further, unlike debris removal contracts in many
other jurisdictions, each per-cubic-yard unit price in Harris County’s contracts was a “cradle-
CBCA 6909-FEMA
3
to-grave” price, meaning that the contractor was responsible for every cost involved in the
debris removal, including but not limited to “tipping fees” (that is, the actual disposal costs
that the contractor would have to pay the disposal site permanently to take the debris).
Neither agreement contained a guarantee that any services would be ordered or a minimum
payment obligation. The award documents indicated that “[t]he secondary vendor will be
utilized when the primary vendor is unavailable or unable to fulfill the services required.”
Applicant Exhibit 21 at 1.
Early estimates of the amount of debris that would be generated by flooding in Harris
County, developed in part using calculations from the United States Army Corps of
Engineers, exceeded 2.25 million cubic yards, an unprecedented figure for Harris County,
before soon thereafter being revised upward to possibly in excess of 4.2 million cubic yards.
By September 5, 2017, Harris County’s models, consistent with FEMA 329 Debris
Estimating Field Guide (Sept. 2010), had been adjusted to estimate a likelihood of just over
3.1 million cubic yards of debris. As the flooding was occurring, public health officials
immediately began insisting that expedited action would be necessary to remove
construction, demolition, and vegetative debris as quickly as possible so as to minimize
development of public health hazards such as mold, mosquito breeding grounds (in light of
Zika virus concerns that were of particular issue at that time, as well as malaria concerns),
rodents, and tetanus.
As the storm began, Harris County immediately approached its primary vendor to
order debris removal services, but that vendor declined to perform in accordance with the
terms of its bid. Harris County’s secondary vendor, DRC, said that it would do its best to
perform with the thirty debris removal trucks that it had set aside, but that the high volume
of services that Harris County was realizing it would need in an expedited time frame would
overwhelm DRC’s existing capabilities. Normally, DRC represented, it might be able to add
additional freelance debris removal personnel and equipment to supplement its team through
short-term hires and rentals, but news of another category four hurricane, Hurricane Irma,
that was about to hit Florida (a hurricane that arrived on September 9, 2017) was causing a
significant migration of debris removal teams to Florida. Unlike Texas, where the bulk of
debris removal needs following hurricanes typically involves construction and demolition
debris, hurricanes in Florida typically leave much higher percentages of vegetative debris,
the removal and disposal of which is generally viewed within the industry as being easier and
faster and as ultimately providing higher pay. This migration created great concern about the
adequacy of debris removal resources that would remain in Texas, and specifically the Harris
County area, to deal with the massive debris removal needs in that community. The County
Engineer was estimating that, with the seemingly available resources, removal of all debris
could take twelve to eighteen months. Yet, Harris County had a regulatory deadline of six
months (or February 25, 2018) to complete debris removal operations, 44 CFR 206.204(c)
CBCA 6909-FEMA
4
(2017),1 and, to address concerns of public health experts, believed that it needed to complete
debris removal efforts by the end of the 2017 calendar year. FEMA has not contested the
reasonableness of that belief.
On or about September 4, 2017, DRC suggested a solution to address the lack of
existing available trained debris removal resources in the area: it could attempt to hire
individuals who normally use smaller self-owned trucks to deliver sand, gravel, and similar
materials in the area and train them to collect, haul, and dispose of construction and
demolition debris, a process very different from sand-and-gravel hauling. Individuals who
haul such materials, though, typically are paid more for their services on an hourly basis than
they would make from removing debris on a cubic yard basis, given the increased time that
it takes to collect different kinds of debris and haul it, sometimes for fairly long distances,
to the limited number of disposal sites that would be available to them and the need for them
to pay “tipping fees” to the owners of the disposal sites. DRC thought that an increased
payment amount might create enough of an incentive to attract a sufficient number of sandand-gravel haulers willing to be trained to perform debris removal on an emergency and
expedited basis.
Assuming, based upon Harris County’s projection at that time, that there would likely
be approximately three million cubic yards of construction and demolition debris, DRC’s
president suggested offering an incentive of an additional $5 per cubic yard, above DRC’s
existing contract unit prices, to attract a sufficient number of sand-and-gravel haulers to
remove all Harris County debris by the end of the 2017 calendar year. Some municipalities
in Florida were, in anticipation of Hurricane Irma, offering an increase of approximately $5
per cubic yard of debris removed, above standard industry prices, in an effort to attract debris
removal contractors. The City of Houston, too, had increased its per-cubic-yard rates to deal
with Hurricane Harvey, although the record does not clearly reflect the amount of that
increase.2 Nevertheless, the dollar figure for the Harris County incentive was a “back of the
envelope” number that DRC and Harris County representatives quickly worked out on an
informal basis, with the $5 figure being somewhat of a gut feeling on the part of DRC’s
president.
1
That deadline was later extended, but Harris County did not know in September
2017 of a potential extension.
2
The record suggests that the City of Houston possibly may have paid significantly
more per cubic yard than Harris County, but Harris County has limited knowledge of the
City’s payments, and the evidence on this point is less than fulsome. FEMA has declined to
identify the City of Houston’s numbers because they are not yet fully reconciled.
CBCA 6909-FEMA
5
Harris County immediately emailed FEMA to ask whether this incentive approach
would be acceptable for purposes of FEMA reimbursement. FEMA’s Emergency
Management (EM) Program Specialist for Region VI responded that he had not previously
seen a request to approve incentive pricing like this one, but recognized that “[r]esources are
going to be hard to get and with the other Hurricane [Irma] no one knows what is going to
happen.” Applicant Exhibit 44 at 1. The EM Program Specialist suggested pushing the
Office of Chief Counsel (OCC) and the Office of Inspector General (OIG) for an answer.
Harris County’s witness testified that Harris County received no responses to such inquiries.
Very quickly thereafter, on September 6, 2017, Harris County presented DRC with
a contract amendment creating a series of incentive payments that looked different from what
DRC had suggested. In the amendment, Harris County created a series of three one-time $5
million payments if DRC was incrementally able to provide a specific number of hauling
units by each of three specific target dates, the first of which was described as follows:
Mobilization and Use Incentive #1: Harris County will pay [$5,000,000] if
DRC provides at least 40 operational debris hauling units that have a capacity
of over 60 cubic yards and at least 30 additional operational debris hauling
units[] that have a capacity of any at least 30 cubic yards by 10:00 a.m. Friday,
September 8, 2017,[] and maintains 80% or greater average operational rate
of the sum of all required trucks stated above through all 3 passes until those
passes are deemed complete by Harris County.
A second $5,000,000 incentive payment would be made if, by September 14, 2017, DRC
increased those amounts to sixty operational debris hauling units with a capacity of over sixty
cubic yards and fifty units with a capacity of over thirty cubic yards. A third and final
$5,000,000 incentive payment would be made if DRC increased those numbers by September
20, 2017, to sixty-five units with a capacity of over sixty cubic yards and 100 units with a
capacity of over thirty cubic yards. By the end of the third incentive period, DRC was
expected to have established the capacity to remove 6163 cubic yards of debris per week.
Harris County presented no evidence in this arbitration—either testimonial or
documentary—establishing how, why, or when the idea for the three-payment incentive
agreement was generated. Looking at the numbers and applying the three-million-cubic-yard
debris estimate about which DRC’s president testified, it is easy to see that someone,
presumably within Harris County’s contracting office, multiplied the anticipated three million
cubic yards by $5 to come up with a total $15 million incentive. Nevertheless, no work
papers support either the calculation or the amount of the payment, and Harris County was
unable to explain it. Despite the absence of such support, Harris County, relying on
testimony from DRC’s president, argues that the incentive payment was a creative and
CBCA 6909-FEMA
6
ultimately successful means of obtaining services in an expedited manner that was absolutely
necessary to protect the health of its citizens.
On September 10, 2017, four days after Harris County executed the incentive
payments amendment, FEMA, through the FEMA Region VI Regional Administrator, issued
a memorandum acknowledging that exigent and emergency conditions existed in the State
of Texas that allowed both state and local governments in declared counties, including Harris
County, to procure contracts for goods and services on a noncompetitive basis through
October 10, 2017. Applicant Exhibit 33 at 1. In the memorandum, FEMA provided that,
“[b]ecause the exception is only available for the duration of the exigent and emergency
circumstances, applicants must start the process of competitively procuring goods and
services for long term recovery so that they can transition to the new competitively procured
contracts when these circumstances cease to exist.” Id. at 2.
Five days later, on September 15, 2017, the FEMA Region VI Regional Administrator
issued another memorandum acknowledging that multiple locations within Texas were
having problems getting debris removal contractors to perform work at the prices set under
pre-existing contracts. The Administrator recommended that, to the extent a locality had to
agree to a higher debris removal price, it would “be critical to include written documentation
that supports the current circumstances and need for the requested price increases.”
Applicant Exhibit 19 at 2. The Administrator indicated in the memorandum that
“[s]peculation and unsupported price quotes are not sufficient and could open the local
government to risk of loss of funding.” Id.
Ultimately, DRC used the incentive payments to attract and train a sufficient number
of sand-and-gravel haulers to meet the targets in the amendment, and all debris was removed
within Harris County even earlier than the year-end deadline that Harris County was hoping
to meet. However, DRC only ended up having to remove a total of 1,129,652.73 cubic yards
of debris, far less than the three million cubic yards originally anticipated.
After completing all Harvey-related debris removal activities, Harris County
submitted a claim for total actual costs of $45,865,635.40, inclusive of the $15 million
incentive payments, under the Stafford Act provision (42 U.S.C. § 5173) authorizing PA
funding for debris or wreckage removal following a major disaster. In October 2019, FEMA
approved payment of the entire amount requested except for the $15 million in incentives,
finding the incentive improper and unreasonable. Harris County filed a first administrative
appeal to FEMA Region IV in December 2019, and FEMA denied that appeal in April 2020.
Harris County submitted its request for arbitration to the Board on August 20, 2020, and the
panel conducted a hearing, virtually, over the course of three business days beginning
November 5, 2020.
CBCA 6909-FEMA
7
Discussion
Standard of Review
FEMA correctly acknowledges that, in arbitration matters, the Board reviews FEMA
eligibility determinations, including those on challenged PA grants, de novo. Monroe
County, Florida, CBCA 6716-FEMA, 20-1 BCA ¶ 37,688. Nevertheless, FEMA also argues
that, because cost reasonableness is a “question of fact,” the Board “will overturn [FEMA’s]
factual determinations only where [they are] clearly erroneous.” FEMA Response at 7 (citing
Kellogg Brown & Root Services, Inc. v. United States, 742 F.3d 967, 970 (Fed. Cir. 2019)).
FEMA’s proposed review standard is wrong. “As explained in the preamble to our
arbitration rulemaking, ‘because an arbitration decision replaces final action by FEMA’ and
a panel is not a reviewing court, ‘the arbitrators must find facts and interpret the law
independently on behalf of the Executive Branch.’” Livingston Parish Government, CBCA
6513-FEMA, 19-1 BCA ¶ 37,436 (quoting 84 Fed. Reg. 7861, 7862 (Mar. 5, 2019)
(emphasis added)). Our de novo review extends to every aspect of this arbitration, including
the resolution of disputed facts. Florida Keys Electric Cooperative, CBCA 6822-FEMA, slip
op. at 4 (Nov. 24, 2020); Monroe County, Florida. Just like in an appeal of a contracting
officer’s decision under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (2018), parties
that come to the Board for arbitration “start . . . before the board with a clean slate.” Wilner
v. United States, 24 F.3d 1397, 1402 (Fed. Cir. 1994) (en banc). In fact, given that the
applicant is entitled to submit new evidence in the arbitration that was not originally provided
to FEMA, 42 U.S.C. § 5189a(d)(2), the fact-finding deference that FEMA seeks is
unworkable. We provide no deference to FEMA’s fact-finding.
FEMA’s Arguments About DRC Contract Defects
Before we address the central issue in this matter, which is the reasonableness of
Harris County’s decision to agree to $15 million in incentive payments, we must dispose of
a multitude of side arguments that FEMA seemingly tossed into this matter, hoping that
something might stick. These arguments are so lacking in merit that we cannot understand
why FEMA decided to raise them.
First, FEMA argues that Harris County’s agreement to incentive pricing is
automatically unreasonable because “performance of the debris removal work was already
prescribed in the original DRC contract, and DRC had agreed [in its contract] to perform the
work in accordance with its bid.” FEMA Response at 28. The evidence presented in this
arbitration makes clear, however, that the primary vendor had declined to perform at the
prices in its contract when Harris County approached it and that DRC, although willing to
perform, could not do so at the levels that Harris County needed absent incentives to obtain
CBCA 6909-FEMA
8
debris removal services from unusual sources that DRC would need to train. The OIG
reports included in the record show that Harris County was not alone, as virtually all
jurisdictions in Texas and Florida responding to Harvey and Irma were experiencing the
same kind of vendor refusals to meet prices set forth in similar contracts. Although FEMA
asserts that Harris County should have sued its primary vendor and possibly the secondary
vendor for contract breach and forced them either to perform at the contract’s unit prices or
to pay damages, rather than agreeing to an incentive payment with the secondary vendor,
there is no basis for a breach claim in the circumstances here under Harris County’s contracts
as written. Although the terms of both vendors’ agreements called them “contracts,” their
agreements neither obligated Harris County to purchase all of its debris removal requirements
solely from these two vendors nor provided a guarantee that any minimum amount of
services would ever be ordered.
The benefit of these contracts is that they pre-position Harris County immediately to
be able to issue purchase orders to pre-approved contractors when an emergency arises,
without the need for further responsibility and capability reviews or the issuance of new
requests for proposals. Nevertheless, such contracts are illusory in nature in the sense that
they create no mutuality of obligation, rendering them essentially enforceable only to the
extent that, when a need arises, both parties are willing to meet the originally agreed upon
terms. See, e.g., Willard, Sutherland & Co. v. United States, 262 U.S. 489, 493 (1923);
Coyle’s Pest Control, Inc. v. Cuomo, 154 F.3d 1302, 1306 (Fed. Cir. 1998); Torncello v.
United States, 681 F.2d 756, 761-62 (Ct. Cl. 1982). As we recently recognized in similar
circumstances in another FEMA arbitration, where contracts like those at issue here
“established no [mandatory] performance or return promise” arising out of mutuality of
obligation, those alleged contracts are “nothing more than a prequalification of [the primary
and secondary vendors] to aid in the procurement of future requirements,” and the
pre-approved vendors are free to chose not to accept a purchase order if issued. Florida Keys
Electric Cooperative, slip op. at 4. The mere fact that the parties called the original vendor
agreements “contracts” does not make them so absent mutuality. Packer v. Social Security
Administration, CBCA 5038, 16-1 BCA ¶ 36,260.
The testimony in this arbitration indicated that it is standard practice for local
governments to pre-position debris removal contracts like the primary and secondary vendor
contracts here—contracts that do not obligate the local government to pay any money if
services are not needed or place limits on how much can be ordered—that pre-qualify
contractors to provide services and that the local government can immediately invoke without
having to engage in further competitive procurement activities. In the situation before us
now, Harris County would have had no basis for suing either the primary vendor or DRC for
failing to honor any price commitment in their otherwise unenforceable contracts. Though
both the primary vendor and DRC were pre-qualified to provide debris removal services to
CBCA 6909-FEMA
9
Harris County, neither was required to perform at whatever levels of performance Harris
County desired. Further, even if otherwise enforceable as a contract, the DRC agreement
contained no mandatory time line or limits by which debris removal had to be completed, a
practice standard in the industry, meaning that the contract provided Harris County no way
to require expedited removal services. FEMA’s arguments seeking to enforce the pricing
terms of the original “contracts” and suggesting that Harris County should sue its vendors
for breach of contract fail.
Second, FEMA claims that Harris County is ineligible for any additional cost recovery
because the County’s underlying agreement with DRC, the terms of which become
incorporated into any purchase order that Harris County issues, does not contain various
clauses that FEMA contends are required by the Office of Management and Budget Guidance
for Grants and Agreements regulations set forth at 2 CFR 200.317, 2 CFR 200.326, and
Appendix II to 2 CFR Part 200 (2017). As authority for its ineligibility argument, it relies
on a remedies provision that in 2017 was located at 2 CFR 200.338(b) (2017),3 which permits
the government to “[d]isallow . . . all or part of the cost of the activity or action not in
compliance.” Without deciding the extent to which section 200.338(b) would permit
disallowance of otherwise reasonable costs, we reject FEMA’s arguments that any necessary
clauses are missing:
1.
FEMA argues that paragraph (C) in Appendix II required the Harris
County/DRC contract to contain an Equal Employment Opportunity (EEO)
clause compliant with 41 CFR 60-1.4(b). That requirement applies only to
contracts that “meet the definition of ‘federally assisted construction contract’
in 41 CFR Part 60-1.3.” Appendix II, ¶ C. FEMA contends that the Harris
County contract, some of which involved debris removal from roads and
highways, is a construction contract because 41 CFR 60-1.3 includes the
“rehabilitation” of highways in its definition of “construction work.” Contrary
to FEMA’s unsupported assertion, debris removal is not rehabilitation work.
See 23 CFR 650.403(c) (roadway bridge rehabilitation involves major work to
restore structural integrity); Federal Highway Administration Publication
FHWA-RD-03-088 (Nov. 2003) (now superceded) (pavement rehabilitation
involves resurfacing, reconstruction, the addition of lanes, and/or pavement
structure alteration) (available at https://www.fhwa.dot.gov/publications/
research/infrastructure/pavements/ltpp/reports/03088/08.cfm). Even FEMA
3
Effective November 12, 2020, this provision has been redesignated as 2 CFR
200.339(b). See 85 Fed. Reg. 49,506, 49,559 (Aug. 13, 2020). In this decision, we cite to
the regulation as section 338(b), referring to its location at the time of the disaster at issue.
CBCA 6909-FEMA
expressly recognizes the distinction between debris removal and roadway
rehabilitation at page 101 of its September 2019 Procurement Disaster
Assistance Team Field Manual (2019 PDAT Field Manual) (available at
https://www.fema.gov/ sites/default/files/2020-07/fema_procurement-disasterassistance-PDAT_field- manual.pdf)—a document that Harris County brought
to our attention, but that FEMA neither addressed nor cited in its briefing.
2.
FEMA complains that the Harris County contract did not contain a
clause requiring certification consistent with the Byrd Anti-Lobbying
Amendment, 31 U.S.C. § 1352. Paragraph (I) of Appendix II, upon which
FEMA relies as the basis of its argument, does not require such a clause. It
only requires that contractors subject to the statute actually “file the required
certification,” which DRC did.
3.
FEMA complains that Harris County’s contract does not comply with
paragraph (B) of Appendix II, which requires that “[a]ll contracts in excess of
$10,000 must address termination for cause and for convenience by the
non-Federal entity including the manner by which it will be effected and the
basis for settlement.” The Harris County contract contains a clause permitting
immediate termination of any purchase order upon breach by the contractor
and permitting termination without cause on thirty days’ notice. Applicant
Exhibit 21 at 19-20. That satisfies OMB’s regulation. Although FEMA
complains that the termination-without-cause provision should be more like
the convenience termination provision in the Federal Acquisition Regulation
(FAR) and allow for immediate termination without prior notice, nothing in
OMB’s regulation requires that, as even FEMA’s witness on this topic
acknowledged during the hearing. See also On Time Postal Service, PSBCA
2528, 90-2 BCA ¶ 22,698 (enforcing convenience termination provision that
required sixty days’ written notice); Executive Airlines, Inc., PSBCA 1452,
87-1 BCA ¶ 19,594 (same for clause requiring twenty-eight days’ written
notice).
4.
FEMA complains that the Harris County contract violates paragraph
(A) of Appendix II, which requires the contract to “address administrative,
contractual, or legal remedies in instances where contractors violate or breach
contract terms, and provide for such sanctions and penalties as appropriate.”
Contrary to FEMA’s assertion, the purchase order provides remedies for
breach.
10
CBCA 6909-FEMA
11
Third, FEMA argues that the contract is an improper time-and-materials (T&M)
contract, in violation of 2 CFR 200.318, and that FEMA, again under the authority of 2 CFR
200.338(b), has the discretion to preclude or limit reimbursement for costs incurred under
such a contract. Neither the original contract, under its original terms, nor the contract as
amended is a T&M contract. At page 42 of its 2019 PDAT Field Manual, FEMA defines a
T&M contract as a contract whose cost to the non-federal entity is (1) the sum of the actual
cost of materials and (2) direct labor hours charged at fixed hourly rates that reflect wages,
general and administrative expenses, and profit, but in which (3) no fee or profit is allowed
except as part of the fixed billing rate for direct labor hours. Unlike that definition, the
pricing terms for debris removal at issue here provided for a specific unit price per cubic yard
for debris removed, a unit price for each abandoned vehicle removed, a unit price for each
tree or stump removed, and a unit price per pound of asbestos removed, without regard to the
number of labor hours that each task required. That is not T&M pricing, but is more in the
nature of an indefinite quantities agreement with fixed unit prices, albeit without any
minimum purchase guarantee.4 Further, even if the contract, either before or after the
incentive pricing amendment, could somehow be interpreted as a T&M contract, FEMA’s
2019 PDAT Field Manual states that there is no absolute bar to using a T&M contract “in the
immediate response to an incident to protect lives or protect public health and safety,” 2019
PDAT Field Manual at 43, the situation that existed here. FEMA has no basis for
withholding reimbursement based upon its T&M contract argument.
Fourth, FEMA argues that the contract amendment adding the incentive pricing
constituted a cardinal change to the original contract, a type of noncompetitive procurement
that, under 2 CFR 200.320, is appropriate only in limited circumstances, such as when “[t]he
public exigency or emergency for the requirement will not permit a delay resulting from
competitive solicitation.” Id. 200.320(f)(2) (2017) (relocated, effective November 12, 2020,
to 2 CFR 200.320(c)(2)). We need not decide whether the amendment actually constituted
a cardinal change because FEMA’s argument that Harris County should have competed its
additional debris removal needs and looked for other sources in the circumstances here, and
that no public exigency or emergency existed when the amendment was executed, is
ridiculous. FEMA issued a memorandum on September 10, 2017, expressly finding that
“exigent and emergency circumstances exist” and “concur[ring], for debris removal and
emergency protective measures, with the use of non competitively procured contracts through
October 10, 2017, in all declared counties,” including Harris County. FEMA argues that the
4
To the extent that another part of DRC’s agreement contained pricing at a
combined hourly rate for equipment and operating labor, Harris County did not issue any
purchase orders invoking that part of the agreement. It only purchased services that were
priced by the number of cubic yards removed.
CBCA 6909-FEMA
12
memorandum does not apply here because the contract amendment at issue was executed on
September 6, 2017, four days before FEMA issued its memorandum finding exigent and
emergency circumstances, but it is the flooding caused by Hurricane Harvey in late August
2017 that created the need for expedited action. Those circumstances did not suddenly
appear on September 10, 2017, but had been mounting since the flooding began in late
August 2017. Harris County could not wait to take action until FEMA issued a written
acknowledgment that circumstances were dire and that time was of the essence. FEMA’s
contemporaneous acknowledgment of exigent circumstances in Harris County wholly
undermines FEMA’s argument that Harris County should have re-competed its increased
debris removal requirements.
Fifth, FEMA, presenting an analysis from its first administrative review comparing
Harris County’s per-cubic-yard removal costs with the per-cubic-yard costs in other parts of
Texas during the Harvey clean-up, asserts that removal costs elsewhere were cheaper than
what Harris County paid and, therefore, suggests that Harris County, through the incentives
amendment, overpaid. FEMA’s own witness, however, testified that the analysis was
comparing apples to oranges and was essentially worthless because of the differences in the
localities and nature of the necessary work in those other areas. We find FEMA’s
cost-comparison analysis of no value.
Sixth, FEMA added documents to the record just before the arbitration hearing
containing arguments not set forth in FEMA’s original response to Harris County’s
arbitration request, and it is unclear the extent to which FEMA purports to rely on any of
those new arguments in this arbitration. Harris County has filed a motion seeking to preclude
FEMA from relying on the new arguments raised in those documents and to exclude some
documents from the record, but we deny that motion as moot because, even if admitted, they
would not affect the result here. FEMA asserted in one of the newly presented documents
that, consistent with 2 CFR 200.318(h), Harris County should have documented DRC’s
integrity, compliance with public policy, record of past performance, and financial and
technical resource in making a responsibility determination and that DRC was not debarred
or suspended on www.SAM.gov; Harris County undertook that activity when it awarded the
DRC contract in 2015. The new documents also contain an analysis indicating that DRC did
not satisfy the cubic yard pick-up targets necessary for payment of two of the three $5 million
incentives, FEMA Exhibit 11 at 3; that analysis misinterprets the cumulative nature of the
targets over the course of three weeks and is simply wrong. FEMA’s new documents also
include a report from FEMA’s OIG criticizing Harris County’s emergency contract
procurements during Hurricane Harvey for non-debris removal services for which Harris
County apparently had no pre-positioned contracts and finding them to have insufficient
procurement safeguards; despite FEMA’s attempt to argue that we should infer that the lack
of safeguards there apply to the DRC contract, the OIG report did not involve the DRC
CBCA 6909-FEMA
13
contract and gives us no evidentiary basis for evaluating the incentive payment
reasonableness.
FEMA’s Cost Reasonableness Challenge
Having disposed of these side issues, we address the central issue in this arbitration:
the reasonableness of Harris County’s incentive payments. A cost is considered reasonable
if, in its nature and amount, it does not exceed that which would be incurred by a prudent
person under the circumstances prevailing at the time the decision to incur the costs was
made. Monroe County, Florida; 2 CFR 200.404. Although exigent circumstances like those
at issue here may allow an applicant to use noncompetitive methods to obtain services, the
applicant is still “not relieve[d] . . . from ensuring that costs are reasonable.” Florida Keys
Electric Cooperative, slip op. at 5 (quoting FEMA Fact Sheet, Public Assistance:
Procurement Conducted Under Exigent or Emergency Circumstances (Jan. 19, 2018)). The
applicant bears the burden of establishing cost reasonableness. St. Tammany Parish
Government, CBCA 3872-FEMA, 16-1 BCA ¶ 36,420.
It was plainly reasonable for Harris County to adopt some kind of incentive payment
in the circumstances here. FEMA implicitly recognized that fact in its memorandum dated
September 15, 2017, when acknowledging that Texas localities were losing debris removal
vendors to Florida and were fairly consistently unable to get contractors with pre-positioned
debris removal contracts to honor their contract pricing. FEMA’s EM Program Specialist
for Region VI testified at the hearing that he had seen situations in which it was tough to get
trucks, but nothing to the extent of Hurricane Harvey. FEMA argues that, in its September
10 and 15 memoranda, it only acknowledged the need for noncompetitive procurements and
price increases through October 10, 2017, at which point localities would have to have made
arrangements for more competitively awarded removal work, but all of the incentives to
which Harris County agreed were earned before that October 10 deadline. Further, Harris
County was having to work out how it would deal with its disaster needs before FEMA
provided that guidance and, in fact, before FEMA provided any guidance at all. FEMA has
no viable basis for faulting Harris County’s decision to provide an incentive when FEMA
was not providing timely and necessary guidance on how to deal with the lack of available
resources in the immediate disaster.
Further, we understand the logic of the specific incentive arrangement to which Harris
County agreed. Assuming a need to remove three million cubic yards of debris, and
assuming that a $5-per-cubic-yard increase to DRC’s existing contract unit prices was a
workable incentive, Harris County front-loaded the entirety of that $5-per-cubic-yard add-on
into the first three weeks of debris removal work, rather than spreading it out over time, to
provide a stronger incentive to the necessary sand-and-gravel haulers to get on the job
CBCA 6909-FEMA
14
immediately, instead of stretching things out with haulers slowly joining in over the course
of several months. Even FEMA’s EM Program Specialist for Region VI agreed during his
testimony that offering an extra $5-per-cubic-yard, at least for the first thirty days of the
debris removal process, was reasonable. Had Harris County’s three-million-cubic-yard total
estimate been correct, there would be little question as to the ultimate reasonableness of the
payment.
Nevertheless, the three-million-cubic-yard estimate turned out to be wildly off. In the
end, DRC only removed 1,129,652.73 cubic yards of debris—still a significant amount, but
far less than the number that Harris County had originally anticipated and upon which it
based the $15 million payment. Harris County has not made it easy to decide reasonableness
in light of that discrepancy. It has presented nothing—no documents, and no testimony—
showing how or why the incentive payment scheme came to be or why Harris County did not
adopt DRC’s original suggestion of simply adding a $5-per-cubic-yard bonus to DRC’s cubic
yard unit price contract amount. Had it adopted DRC’s original suggestion, Harris County
ultimately would have paid only an additional $5.648 million (1,129,652.73 x $5), rather than
the $15 million it actually paid. Would a $5 addition to each unit price have been a sufficient
incentive to get workers on site immediately? We cannot know, in part because Harris
County presented no contemporaneous analysis evaluating that approach. Harris County
does not even know who within its contracting office (or elsewhere) came up with the idea
for the $15 million incentive payment scheme, leaving us to guess at why someone thought
the approach adopted was necessary or believed DRC’s original suggestion would not work.
In light of the paucity of evidence about how DRC’s unit price increase suggestion
morphed into a $15 million upfront incentive payment, we cannot find that Harris County has
established that the entire $15 million payment is reasonable. We understand that, in early
September 2017, Harris County felt confident that its three-million-cubic-yard debris
estimate was not only reasonable, but was probably low. In some ways, we are engaging in
a type of Monday-morning quarterbacking by criticizing Harris County for not originally
considering the possibility that its estimate might be too high. In the end, though, it is the
absence of evidence about any alternatives that Harris County considered, which might have
tied payments to the actual quantity of debris ultimately found rather than a predetermined
three million cubic yard figure, and the reasons that Harris County discounted or rejected
those alternatives that preclude us from finding the entire $15 million incentive payment
reasonable. FEMA’s memorandum dated September 15, 2017, warned localities to ensure
that, if they paid increased prices above the amounts set forth in their pre-positioned
contracts, they needed to make sure carefully to document those increases. Although that
memorandum post-dated Harris County’s contract amendment by nine days, it was close
enough in time to place Harris County on notice of FEMA’s expectations. Harris County’s
CBCA 6909-FEMA
15
failure to document its decision-making process when it still could have precludes a finding
that it has proven the reasonableness of the entirety of its $15 million incentive payment.
Decision
Harris County has established that $5.648 million of its $15 million incentive payment
was reasonable. Accordingly, we grant Harris County’s application in part, allowing
recovery of $5.648 million beyond the debris removal costs that FEMA has previously
reimbursed. Harris County’s application is otherwise denied. Harris County’s motion to
limit consideration of and/or strike FEMA’s late-filed documents is denied as moot.
Harold D. Lester, Jr.
HAROLD D. LESTER, JR.
Board Judge
Jonathan D. Zischkau
JONATHAN ZISCHKAU
Board Judge
I agree with the majority’s careful description of the issue in dispute but would decide
it against the applicant. I comment briefly, mainly for the benefit of parties in future
arbitrations in which I am a panel member.
In my view, both parties steered this dispute off the rails by focusing on the price per
cubic yard of debris. The September 6, 2017, contract amendment established three fixed
incentives of $5 million each. It did not state an increase in the price per cubic yard hauled.
Had the applicant wished only to promise to pay an extra $5 per cubic yard, in arrears, as a
“sweetener” each time the vendor met one of the three milestones, the agreement could have
said that, and we might have faced a different issue. Instead, the parties converted a notional
increase in the price per cubic yard to three fixed payments, using an estimate of the total
amount of debris, which everyone knew would be either too high or too low, as estimates
always are. Several witnesses recited the arithmetic underlying this conversion, but no one
explained why it was reasonable to switch from a per-cubic-yard methodology to a riskier
fixed-price methodology to begin with. Moreover, I find no support in the record for the
CBCA 6909-FEMA
16
figure of $5 per cubic yard other than that the vendor suggested it, which may be a starting
point but cannot end a price reasonableness analysis.
I also take this opportunity to exhort future parties to take Board Rule 612 seriously
by “[o]mitting duplicative and immaterial evidence and arguments.” 48 CFR 6106.612(e)
(2020). Here, three judges—21% of our Board—sat through two full days of virtual hearing,
very little of which bore on the eligibility issue we were asked to resolve.
Kyle Chadwick
KYLE CHADWICK
Board Judge
This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.