In the Matter of HARRIS COUNTY, TEXAS

Agency decision

Ask Donna

What actually matters in this document.

Text

December 15, 2020

CBCA 6909-FEMA

In the Matter of HARRIS COUNTY, TEXAS

Wendy Huff Ellard of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,

Jackson, MS; Michelle Zaltsberg of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,

Orlando, FL; Jordan Corbitt of Baker, Donelson, Bearman, Caldwell & Berkowitz, PC,

Houston, TX; and Randall Smidt, Vince Ryan, and Robert Soard of the Office of the Harris

County Attorney, Houston, TX, counsel for Applicant.

W. Nim Kidd and Suzannah Jones, Texas Division of Emergency Management,

Austin, TX; and Julie A. Masek, Texas A&M University System, College Sation, TX,

appearing for Grantee.

Christiana C. Cooley and Ramoncito J. deBorja, Office of Chief Counsel, Federal

Emergency Management Agency, Department of Homeland Security, Washington, DC; and

John Dimos, Office of Chief Counsel, Federal Emergency Management Agency, Department

of Homeland Security, Baton Rouge, LA, counsel for Federal Emergency Management

Agency.

Before the Arbitration Panel consisting of Board Judges ZISCHKAU, LESTER, and

CHADWICK.

In late 2017, Harris County incurred more than $45 million in debris removal costs

after Hurricane Harvey, a category four storm, caused massive flooding in Harris County and

other nearby areas in Texas. The Federal Emergency Management Agency (FEMA) granted

Harris County’s request for public assistance (PA) under the Robert T. Stafford Disaster

Relief and Emergency Assistance Act (Stafford Act), 42 U.S.C. § 5189a (2018), reimbursing

all but $15 million of the claimed costs. Harris County sought arbitration under 42 U.S.C.

CBCA 6909-FEMA

2

§ 5189a(d) of FEMA’s denial of that $15 million. We grant Harris County’s application in

part.

Background

The massive flooding that Hurricane Harvey caused in Harris County occurred over

the course of several days beginning August 25, 2017. Thousands of residential and

commercial structures were flooded, with varying degrees of inundation and damage. For

Harris County, 70% of which was eventually covered in water, that flooding required that

unprecedented amounts of debris be removed and disposed of in an expedited manner for

public health and safety reasons. The President declared a major disaster for the State of

Texas on August 25, 2017, and authorized PA funding for both emergency and permanent

work for Harris County.

Prior to Hurricane Harvey, Harris County had agreements in place with two different

vendors—one designated as the “primary” vendor and the other, DRC Emergency Services,

LLC (DRC), designated as the “secondary” vendor—to provide emergency debris removal

services for Harris County if and when they were necessary. The two vendors were selected

from six that responded to a request for bids that Harris County issued in 2015 in anticipation

of possible future emergencies. The agreement with each vendor provided that “work shall

consist of clearing and removing any and all ‘eligible’ debris as defined by FEMA

Publication 325, all applicable State and Federal Disaster Specific Guidance and policies,

and/or as directed by the County.” Applicant Exhibit 21 at 23. Nevertheless, neither

agreement imposed any limitations on the amount of time that debris removal services might

take, something that DRC’s president testified is standard in the industry because the

imposition of such deadlines is considered too risky for contractors that accept these types

of pre-positioned contracts. Each agreement provided that “[t]hese services will only be

utilized during emergency situations” and that “funds will not be encumbered until the

services are needed and the County activates the contract.” Id. Neither vendor could provide

any services “without a Harris County Purchase Order, signed by an authorized agent of the

Harris County Purchasing Department.” Id. at 19.

The relevant pricing terms for the debris removal services at issue in this arbitration

provided for a specific unit price per cubic yard for debris removed, a unit price for each

abandoned vehicle removed, a unit price for each tree or stump removed, and a unit price per

pound of asbestos removed, without regard to the number of labor hours that each task

required. The prices in each agreement were to “be all inclusive,” such that “[n]o price

changes, additions, or subsequently qualifications will be honored during the course of the

contract.” Applicant Exhibit 21 at 18. Further, unlike debris removal contracts in many

other jurisdictions, each per-cubic-yard unit price in Harris County’s contracts was a “cradle-

CBCA 6909-FEMA

3

to-grave” price, meaning that the contractor was responsible for every cost involved in the

debris removal, including but not limited to “tipping fees” (that is, the actual disposal costs

that the contractor would have to pay the disposal site permanently to take the debris).

Neither agreement contained a guarantee that any services would be ordered or a minimum

payment obligation. The award documents indicated that “[t]he secondary vendor will be

utilized when the primary vendor is unavailable or unable to fulfill the services required.”

Applicant Exhibit 21 at 1.

Early estimates of the amount of debris that would be generated by flooding in Harris

County, developed in part using calculations from the United States Army Corps of

Engineers, exceeded 2.25 million cubic yards, an unprecedented figure for Harris County,

before soon thereafter being revised upward to possibly in excess of 4.2 million cubic yards.

By September 5, 2017, Harris County’s models, consistent with FEMA 329 Debris

Estimating Field Guide (Sept. 2010), had been adjusted to estimate a likelihood of just over

3.1 million cubic yards of debris. As the flooding was occurring, public health officials

immediately began insisting that expedited action would be necessary to remove

construction, demolition, and vegetative debris as quickly as possible so as to minimize

development of public health hazards such as mold, mosquito breeding grounds (in light of

Zika virus concerns that were of particular issue at that time, as well as malaria concerns),

rodents, and tetanus.

As the storm began, Harris County immediately approached its primary vendor to

order debris removal services, but that vendor declined to perform in accordance with the

terms of its bid. Harris County’s secondary vendor, DRC, said that it would do its best to

perform with the thirty debris removal trucks that it had set aside, but that the high volume

of services that Harris County was realizing it would need in an expedited time frame would

overwhelm DRC’s existing capabilities. Normally, DRC represented, it might be able to add

additional freelance debris removal personnel and equipment to supplement its team through

short-term hires and rentals, but news of another category four hurricane, Hurricane Irma,

that was about to hit Florida (a hurricane that arrived on September 9, 2017) was causing a

significant migration of debris removal teams to Florida. Unlike Texas, where the bulk of

debris removal needs following hurricanes typically involves construction and demolition

debris, hurricanes in Florida typically leave much higher percentages of vegetative debris,

the removal and disposal of which is generally viewed within the industry as being easier and

faster and as ultimately providing higher pay. This migration created great concern about the

adequacy of debris removal resources that would remain in Texas, and specifically the Harris

County area, to deal with the massive debris removal needs in that community. The County

Engineer was estimating that, with the seemingly available resources, removal of all debris

could take twelve to eighteen months. Yet, Harris County had a regulatory deadline of six

months (or February 25, 2018) to complete debris removal operations, 44 CFR 206.204(c)

CBCA 6909-FEMA

4

(2017),1 and, to address concerns of public health experts, believed that it needed to complete

debris removal efforts by the end of the 2017 calendar year. FEMA has not contested the

reasonableness of that belief.

On or about September 4, 2017, DRC suggested a solution to address the lack of

existing available trained debris removal resources in the area: it could attempt to hire

individuals who normally use smaller self-owned trucks to deliver sand, gravel, and similar

materials in the area and train them to collect, haul, and dispose of construction and

demolition debris, a process very different from sand-and-gravel hauling. Individuals who

haul such materials, though, typically are paid more for their services on an hourly basis than

they would make from removing debris on a cubic yard basis, given the increased time that

it takes to collect different kinds of debris and haul it, sometimes for fairly long distances,

to the limited number of disposal sites that would be available to them and the need for them

to pay “tipping fees” to the owners of the disposal sites. DRC thought that an increased

payment amount might create enough of an incentive to attract a sufficient number of sandand-gravel haulers willing to be trained to perform debris removal on an emergency and

expedited basis.

Assuming, based upon Harris County’s projection at that time, that there would likely

be approximately three million cubic yards of construction and demolition debris, DRC’s

president suggested offering an incentive of an additional $5 per cubic yard, above DRC’s

existing contract unit prices, to attract a sufficient number of sand-and-gravel haulers to

remove all Harris County debris by the end of the 2017 calendar year. Some municipalities

in Florida were, in anticipation of Hurricane Irma, offering an increase of approximately $5

per cubic yard of debris removed, above standard industry prices, in an effort to attract debris

removal contractors. The City of Houston, too, had increased its per-cubic-yard rates to deal

with Hurricane Harvey, although the record does not clearly reflect the amount of that

increase.2 Nevertheless, the dollar figure for the Harris County incentive was a “back of the

envelope” number that DRC and Harris County representatives quickly worked out on an

informal basis, with the $5 figure being somewhat of a gut feeling on the part of DRC’s

president.

1

That deadline was later extended, but Harris County did not know in September

2017 of a potential extension.

2

The record suggests that the City of Houston possibly may have paid significantly

more per cubic yard than Harris County, but Harris County has limited knowledge of the

City’s payments, and the evidence on this point is less than fulsome. FEMA has declined to

identify the City of Houston’s numbers because they are not yet fully reconciled.

CBCA 6909-FEMA

5

Harris County immediately emailed FEMA to ask whether this incentive approach

would be acceptable for purposes of FEMA reimbursement. FEMA’s Emergency

Management (EM) Program Specialist for Region VI responded that he had not previously

seen a request to approve incentive pricing like this one, but recognized that “[r]esources are

going to be hard to get and with the other Hurricane [Irma] no one knows what is going to

happen.” Applicant Exhibit 44 at 1. The EM Program Specialist suggested pushing the

Office of Chief Counsel (OCC) and the Office of Inspector General (OIG) for an answer.

Harris County’s witness testified that Harris County received no responses to such inquiries.

Very quickly thereafter, on September 6, 2017, Harris County presented DRC with

a contract amendment creating a series of incentive payments that looked different from what

DRC had suggested. In the amendment, Harris County created a series of three one-time $5

million payments if DRC was incrementally able to provide a specific number of hauling

units by each of three specific target dates, the first of which was described as follows:

Mobilization and Use Incentive #1: Harris County will pay [$5,000,000] if

DRC provides at least 40 operational debris hauling units that have a capacity

of over 60 cubic yards and at least 30 additional operational debris hauling

units[] that have a capacity of any at least 30 cubic yards by 10:00 a.m. Friday,

September 8, 2017,[] and maintains 80% or greater average operational rate

of the sum of all required trucks stated above through all 3 passes until those

passes are deemed complete by Harris County.

A second $5,000,000 incentive payment would be made if, by September 14, 2017, DRC

increased those amounts to sixty operational debris hauling units with a capacity of over sixty

cubic yards and fifty units with a capacity of over thirty cubic yards. A third and final

$5,000,000 incentive payment would be made if DRC increased those numbers by September

20, 2017, to sixty-five units with a capacity of over sixty cubic yards and 100 units with a

capacity of over thirty cubic yards. By the end of the third incentive period, DRC was

expected to have established the capacity to remove 6163 cubic yards of debris per week.

Harris County presented no evidence in this arbitration—either testimonial or

documentary—establishing how, why, or when the idea for the three-payment incentive

agreement was generated. Looking at the numbers and applying the three-million-cubic-yard

debris estimate about which DRC’s president testified, it is easy to see that someone,

presumably within Harris County’s contracting office, multiplied the anticipated three million

cubic yards by $5 to come up with a total $15 million incentive. Nevertheless, no work

papers support either the calculation or the amount of the payment, and Harris County was

unable to explain it. Despite the absence of such support, Harris County, relying on

testimony from DRC’s president, argues that the incentive payment was a creative and

CBCA 6909-FEMA

6

ultimately successful means of obtaining services in an expedited manner that was absolutely

necessary to protect the health of its citizens.

On September 10, 2017, four days after Harris County executed the incentive

payments amendment, FEMA, through the FEMA Region VI Regional Administrator, issued

a memorandum acknowledging that exigent and emergency conditions existed in the State

of Texas that allowed both state and local governments in declared counties, including Harris

County, to procure contracts for goods and services on a noncompetitive basis through

October 10, 2017. Applicant Exhibit 33 at 1. In the memorandum, FEMA provided that,

“[b]ecause the exception is only available for the duration of the exigent and emergency

circumstances, applicants must start the process of competitively procuring goods and

services for long term recovery so that they can transition to the new competitively procured

contracts when these circumstances cease to exist.” Id. at 2.

Five days later, on September 15, 2017, the FEMA Region VI Regional Administrator

issued another memorandum acknowledging that multiple locations within Texas were

having problems getting debris removal contractors to perform work at the prices set under

pre-existing contracts. The Administrator recommended that, to the extent a locality had to

agree to a higher debris removal price, it would “be critical to include written documentation

that supports the current circumstances and need for the requested price increases.”

Applicant Exhibit 19 at 2. The Administrator indicated in the memorandum that

“[s]peculation and unsupported price quotes are not sufficient and could open the local

government to risk of loss of funding.” Id.

Ultimately, DRC used the incentive payments to attract and train a sufficient number

of sand-and-gravel haulers to meet the targets in the amendment, and all debris was removed

within Harris County even earlier than the year-end deadline that Harris County was hoping

to meet. However, DRC only ended up having to remove a total of 1,129,652.73 cubic yards

of debris, far less than the three million cubic yards originally anticipated.

After completing all Harvey-related debris removal activities, Harris County

submitted a claim for total actual costs of $45,865,635.40, inclusive of the $15 million

incentive payments, under the Stafford Act provision (42 U.S.C. § 5173) authorizing PA

funding for debris or wreckage removal following a major disaster. In October 2019, FEMA

approved payment of the entire amount requested except for the $15 million in incentives,

finding the incentive improper and unreasonable. Harris County filed a first administrative

appeal to FEMA Region IV in December 2019, and FEMA denied that appeal in April 2020.

Harris County submitted its request for arbitration to the Board on August 20, 2020, and the

panel conducted a hearing, virtually, over the course of three business days beginning

November 5, 2020.

CBCA 6909-FEMA

7

Discussion

Standard of Review

FEMA correctly acknowledges that, in arbitration matters, the Board reviews FEMA

eligibility determinations, including those on challenged PA grants, de novo. Monroe

County, Florida, CBCA 6716-FEMA, 20-1 BCA ¶ 37,688. Nevertheless, FEMA also argues

that, because cost reasonableness is a “question of fact,” the Board “will overturn [FEMA’s]

factual determinations only where [they are] clearly erroneous.” FEMA Response at 7 (citing

Kellogg Brown & Root Services, Inc. v. United States, 742 F.3d 967, 970 (Fed. Cir. 2019)).

FEMA’s proposed review standard is wrong. “As explained in the preamble to our

arbitration rulemaking, ‘because an arbitration decision replaces final action by FEMA’ and

a panel is not a reviewing court, ‘the arbitrators must find facts and interpret the law

independently on behalf of the Executive Branch.’” Livingston Parish Government, CBCA

6513-FEMA, 19-1 BCA ¶ 37,436 (quoting 84 Fed. Reg. 7861, 7862 (Mar. 5, 2019)

(emphasis added)). Our de novo review extends to every aspect of this arbitration, including

the resolution of disputed facts. Florida Keys Electric Cooperative, CBCA 6822-FEMA, slip

op. at 4 (Nov. 24, 2020); Monroe County, Florida. Just like in an appeal of a contracting

officer’s decision under the Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (2018), parties

that come to the Board for arbitration “start . . . before the board with a clean slate.” Wilner

v. United States, 24 F.3d 1397, 1402 (Fed. Cir. 1994) (en banc). In fact, given that the

applicant is entitled to submit new evidence in the arbitration that was not originally provided

to FEMA, 42 U.S.C. § 5189a(d)(2), the fact-finding deference that FEMA seeks is

unworkable. We provide no deference to FEMA’s fact-finding.

FEMA’s Arguments About DRC Contract Defects

Before we address the central issue in this matter, which is the reasonableness of

Harris County’s decision to agree to $15 million in incentive payments, we must dispose of

a multitude of side arguments that FEMA seemingly tossed into this matter, hoping that

something might stick. These arguments are so lacking in merit that we cannot understand

why FEMA decided to raise them.

First, FEMA argues that Harris County’s agreement to incentive pricing is

automatically unreasonable because “performance of the debris removal work was already

prescribed in the original DRC contract, and DRC had agreed [in its contract] to perform the

work in accordance with its bid.” FEMA Response at 28. The evidence presented in this

arbitration makes clear, however, that the primary vendor had declined to perform at the

prices in its contract when Harris County approached it and that DRC, although willing to

perform, could not do so at the levels that Harris County needed absent incentives to obtain

CBCA 6909-FEMA

8

debris removal services from unusual sources that DRC would need to train. The OIG

reports included in the record show that Harris County was not alone, as virtually all

jurisdictions in Texas and Florida responding to Harvey and Irma were experiencing the

same kind of vendor refusals to meet prices set forth in similar contracts. Although FEMA

asserts that Harris County should have sued its primary vendor and possibly the secondary

vendor for contract breach and forced them either to perform at the contract’s unit prices or

to pay damages, rather than agreeing to an incentive payment with the secondary vendor,

there is no basis for a breach claim in the circumstances here under Harris County’s contracts

as written. Although the terms of both vendors’ agreements called them “contracts,” their

agreements neither obligated Harris County to purchase all of its debris removal requirements

solely from these two vendors nor provided a guarantee that any minimum amount of

services would ever be ordered.

The benefit of these contracts is that they pre-position Harris County immediately to

be able to issue purchase orders to pre-approved contractors when an emergency arises,

without the need for further responsibility and capability reviews or the issuance of new

requests for proposals. Nevertheless, such contracts are illusory in nature in the sense that

they create no mutuality of obligation, rendering them essentially enforceable only to the

extent that, when a need arises, both parties are willing to meet the originally agreed upon

terms. See, e.g., Willard, Sutherland & Co. v. United States, 262 U.S. 489, 493 (1923);

Coyle’s Pest Control, Inc. v. Cuomo, 154 F.3d 1302, 1306 (Fed. Cir. 1998); Torncello v.

United States, 681 F.2d 756, 761-62 (Ct. Cl. 1982). As we recently recognized in similar

circumstances in another FEMA arbitration, where contracts like those at issue here

“established no [mandatory] performance or return promise” arising out of mutuality of

obligation, those alleged contracts are “nothing more than a prequalification of [the primary

and secondary vendors] to aid in the procurement of future requirements,” and the

pre-approved vendors are free to chose not to accept a purchase order if issued. Florida Keys

Electric Cooperative, slip op. at 4. The mere fact that the parties called the original vendor

agreements “contracts” does not make them so absent mutuality. Packer v. Social Security

Administration, CBCA 5038, 16-1 BCA ¶ 36,260.

The testimony in this arbitration indicated that it is standard practice for local

governments to pre-position debris removal contracts like the primary and secondary vendor

contracts here—contracts that do not obligate the local government to pay any money if

services are not needed or place limits on how much can be ordered—that pre-qualify

contractors to provide services and that the local government can immediately invoke without

having to engage in further competitive procurement activities. In the situation before us

now, Harris County would have had no basis for suing either the primary vendor or DRC for

failing to honor any price commitment in their otherwise unenforceable contracts. Though

both the primary vendor and DRC were pre-qualified to provide debris removal services to

CBCA 6909-FEMA

9

Harris County, neither was required to perform at whatever levels of performance Harris

County desired. Further, even if otherwise enforceable as a contract, the DRC agreement

contained no mandatory time line or limits by which debris removal had to be completed, a

practice standard in the industry, meaning that the contract provided Harris County no way

to require expedited removal services. FEMA’s arguments seeking to enforce the pricing

terms of the original “contracts” and suggesting that Harris County should sue its vendors

for breach of contract fail.

Second, FEMA claims that Harris County is ineligible for any additional cost recovery

because the County’s underlying agreement with DRC, the terms of which become

incorporated into any purchase order that Harris County issues, does not contain various

clauses that FEMA contends are required by the Office of Management and Budget Guidance

for Grants and Agreements regulations set forth at 2 CFR 200.317, 2 CFR 200.326, and

Appendix II to 2 CFR Part 200 (2017). As authority for its ineligibility argument, it relies

on a remedies provision that in 2017 was located at 2 CFR 200.338(b) (2017),3 which permits

the government to “[d]isallow . . . all or part of the cost of the activity or action not in

compliance.” Without deciding the extent to which section 200.338(b) would permit

disallowance of otherwise reasonable costs, we reject FEMA’s arguments that any necessary

clauses are missing:

1.

FEMA argues that paragraph (C) in Appendix II required the Harris

County/DRC contract to contain an Equal Employment Opportunity (EEO)

clause compliant with 41 CFR 60-1.4(b). That requirement applies only to

contracts that “meet the definition of ‘federally assisted construction contract’

in 41 CFR Part 60-1.3.” Appendix II, ¶ C. FEMA contends that the Harris

County contract, some of which involved debris removal from roads and

highways, is a construction contract because 41 CFR 60-1.3 includes the

“rehabilitation” of highways in its definition of “construction work.” Contrary

to FEMA’s unsupported assertion, debris removal is not rehabilitation work.

See 23 CFR 650.403(c) (roadway bridge rehabilitation involves major work to

restore structural integrity); Federal Highway Administration Publication

FHWA-RD-03-088 (Nov. 2003) (now superceded) (pavement rehabilitation

involves resurfacing, reconstruction, the addition of lanes, and/or pavement

structure alteration) (available at https://www.fhwa.dot.gov/publications/

research/infrastructure/pavements/ltpp/reports/03088/08.cfm). Even FEMA

3

Effective November 12, 2020, this provision has been redesignated as 2 CFR

200.339(b). See 85 Fed. Reg. 49,506, 49,559 (Aug. 13, 2020). In this decision, we cite to

the regulation as section 338(b), referring to its location at the time of the disaster at issue.

CBCA 6909-FEMA

expressly recognizes the distinction between debris removal and roadway

rehabilitation at page 101 of its September 2019 Procurement Disaster

Assistance Team Field Manual (2019 PDAT Field Manual) (available at

https://www.fema.gov/ sites/default/files/2020-07/fema_procurement-disasterassistance-PDAT_field- manual.pdf)—a document that Harris County brought

to our attention, but that FEMA neither addressed nor cited in its briefing.

2.

FEMA complains that the Harris County contract did not contain a

clause requiring certification consistent with the Byrd Anti-Lobbying

Amendment, 31 U.S.C. § 1352. Paragraph (I) of Appendix II, upon which

FEMA relies as the basis of its argument, does not require such a clause. It

only requires that contractors subject to the statute actually “file the required

certification,” which DRC did.

3.

FEMA complains that Harris County’s contract does not comply with

paragraph (B) of Appendix II, which requires that “[a]ll contracts in excess of

$10,000 must address termination for cause and for convenience by the

non-Federal entity including the manner by which it will be effected and the

basis for settlement.” The Harris County contract contains a clause permitting

immediate termination of any purchase order upon breach by the contractor

and permitting termination without cause on thirty days’ notice. Applicant

Exhibit 21 at 19-20. That satisfies OMB’s regulation. Although FEMA

complains that the termination-without-cause provision should be more like

the convenience termination provision in the Federal Acquisition Regulation

(FAR) and allow for immediate termination without prior notice, nothing in

OMB’s regulation requires that, as even FEMA’s witness on this topic

acknowledged during the hearing. See also On Time Postal Service, PSBCA

2528, 90-2 BCA ¶ 22,698 (enforcing convenience termination provision that

required sixty days’ written notice); Executive Airlines, Inc., PSBCA 1452,

87-1 BCA ¶ 19,594 (same for clause requiring twenty-eight days’ written

notice).

4.

FEMA complains that the Harris County contract violates paragraph

(A) of Appendix II, which requires the contract to “address administrative,

contractual, or legal remedies in instances where contractors violate or breach

contract terms, and provide for such sanctions and penalties as appropriate.”

Contrary to FEMA’s assertion, the purchase order provides remedies for

breach.

10

CBCA 6909-FEMA

11

Third, FEMA argues that the contract is an improper time-and-materials (T&M)

contract, in violation of 2 CFR 200.318, and that FEMA, again under the authority of 2 CFR

200.338(b), has the discretion to preclude or limit reimbursement for costs incurred under

such a contract. Neither the original contract, under its original terms, nor the contract as

amended is a T&M contract. At page 42 of its 2019 PDAT Field Manual, FEMA defines a

T&M contract as a contract whose cost to the non-federal entity is (1) the sum of the actual

cost of materials and (2) direct labor hours charged at fixed hourly rates that reflect wages,

general and administrative expenses, and profit, but in which (3) no fee or profit is allowed

except as part of the fixed billing rate for direct labor hours. Unlike that definition, the

pricing terms for debris removal at issue here provided for a specific unit price per cubic yard

for debris removed, a unit price for each abandoned vehicle removed, a unit price for each

tree or stump removed, and a unit price per pound of asbestos removed, without regard to the

number of labor hours that each task required. That is not T&M pricing, but is more in the

nature of an indefinite quantities agreement with fixed unit prices, albeit without any

minimum purchase guarantee.4 Further, even if the contract, either before or after the

incentive pricing amendment, could somehow be interpreted as a T&M contract, FEMA’s

2019 PDAT Field Manual states that there is no absolute bar to using a T&M contract “in the

immediate response to an incident to protect lives or protect public health and safety,” 2019

PDAT Field Manual at 43, the situation that existed here. FEMA has no basis for

withholding reimbursement based upon its T&M contract argument.

Fourth, FEMA argues that the contract amendment adding the incentive pricing

constituted a cardinal change to the original contract, a type of noncompetitive procurement

that, under 2 CFR 200.320, is appropriate only in limited circumstances, such as when “[t]he

public exigency or emergency for the requirement will not permit a delay resulting from

competitive solicitation.” Id. 200.320(f)(2) (2017) (relocated, effective November 12, 2020,

to 2 CFR 200.320(c)(2)). We need not decide whether the amendment actually constituted

a cardinal change because FEMA’s argument that Harris County should have competed its

additional debris removal needs and looked for other sources in the circumstances here, and

that no public exigency or emergency existed when the amendment was executed, is

ridiculous. FEMA issued a memorandum on September 10, 2017, expressly finding that

“exigent and emergency circumstances exist” and “concur[ring], for debris removal and

emergency protective measures, with the use of non competitively procured contracts through

October 10, 2017, in all declared counties,” including Harris County. FEMA argues that the

4

To the extent that another part of DRC’s agreement contained pricing at a

combined hourly rate for equipment and operating labor, Harris County did not issue any

purchase orders invoking that part of the agreement. It only purchased services that were

priced by the number of cubic yards removed.

CBCA 6909-FEMA

12

memorandum does not apply here because the contract amendment at issue was executed on

September 6, 2017, four days before FEMA issued its memorandum finding exigent and

emergency circumstances, but it is the flooding caused by Hurricane Harvey in late August

2017 that created the need for expedited action. Those circumstances did not suddenly

appear on September 10, 2017, but had been mounting since the flooding began in late

August 2017. Harris County could not wait to take action until FEMA issued a written

acknowledgment that circumstances were dire and that time was of the essence. FEMA’s

contemporaneous acknowledgment of exigent circumstances in Harris County wholly

undermines FEMA’s argument that Harris County should have re-competed its increased

debris removal requirements.

Fifth, FEMA, presenting an analysis from its first administrative review comparing

Harris County’s per-cubic-yard removal costs with the per-cubic-yard costs in other parts of

Texas during the Harvey clean-up, asserts that removal costs elsewhere were cheaper than

what Harris County paid and, therefore, suggests that Harris County, through the incentives

amendment, overpaid. FEMA’s own witness, however, testified that the analysis was

comparing apples to oranges and was essentially worthless because of the differences in the

localities and nature of the necessary work in those other areas. We find FEMA’s

cost-comparison analysis of no value.

Sixth, FEMA added documents to the record just before the arbitration hearing

containing arguments not set forth in FEMA’s original response to Harris County’s

arbitration request, and it is unclear the extent to which FEMA purports to rely on any of

those new arguments in this arbitration. Harris County has filed a motion seeking to preclude

FEMA from relying on the new arguments raised in those documents and to exclude some

documents from the record, but we deny that motion as moot because, even if admitted, they

would not affect the result here. FEMA asserted in one of the newly presented documents

that, consistent with 2 CFR 200.318(h), Harris County should have documented DRC’s

integrity, compliance with public policy, record of past performance, and financial and

technical resource in making a responsibility determination and that DRC was not debarred

or suspended on www.SAM.gov; Harris County undertook that activity when it awarded the

DRC contract in 2015. The new documents also contain an analysis indicating that DRC did

not satisfy the cubic yard pick-up targets necessary for payment of two of the three $5 million

incentives, FEMA Exhibit 11 at 3; that analysis misinterprets the cumulative nature of the

targets over the course of three weeks and is simply wrong. FEMA’s new documents also

include a report from FEMA’s OIG criticizing Harris County’s emergency contract

procurements during Hurricane Harvey for non-debris removal services for which Harris

County apparently had no pre-positioned contracts and finding them to have insufficient

procurement safeguards; despite FEMA’s attempt to argue that we should infer that the lack

of safeguards there apply to the DRC contract, the OIG report did not involve the DRC

CBCA 6909-FEMA

13

contract and gives us no evidentiary basis for evaluating the incentive payment

reasonableness.

FEMA’s Cost Reasonableness Challenge

Having disposed of these side issues, we address the central issue in this arbitration:

the reasonableness of Harris County’s incentive payments. A cost is considered reasonable

if, in its nature and amount, it does not exceed that which would be incurred by a prudent

person under the circumstances prevailing at the time the decision to incur the costs was

made. Monroe County, Florida; 2 CFR 200.404. Although exigent circumstances like those

at issue here may allow an applicant to use noncompetitive methods to obtain services, the

applicant is still “not relieve[d] . . . from ensuring that costs are reasonable.” Florida Keys

Electric Cooperative, slip op. at 5 (quoting FEMA Fact Sheet, Public Assistance:

Procurement Conducted Under Exigent or Emergency Circumstances (Jan. 19, 2018)). The

applicant bears the burden of establishing cost reasonableness. St. Tammany Parish

Government, CBCA 3872-FEMA, 16-1 BCA ¶ 36,420.

It was plainly reasonable for Harris County to adopt some kind of incentive payment

in the circumstances here. FEMA implicitly recognized that fact in its memorandum dated

September 15, 2017, when acknowledging that Texas localities were losing debris removal

vendors to Florida and were fairly consistently unable to get contractors with pre-positioned

debris removal contracts to honor their contract pricing. FEMA’s EM Program Specialist

for Region VI testified at the hearing that he had seen situations in which it was tough to get

trucks, but nothing to the extent of Hurricane Harvey. FEMA argues that, in its September

10 and 15 memoranda, it only acknowledged the need for noncompetitive procurements and

price increases through October 10, 2017, at which point localities would have to have made

arrangements for more competitively awarded removal work, but all of the incentives to

which Harris County agreed were earned before that October 10 deadline. Further, Harris

County was having to work out how it would deal with its disaster needs before FEMA

provided that guidance and, in fact, before FEMA provided any guidance at all. FEMA has

no viable basis for faulting Harris County’s decision to provide an incentive when FEMA

was not providing timely and necessary guidance on how to deal with the lack of available

resources in the immediate disaster.

Further, we understand the logic of the specific incentive arrangement to which Harris

County agreed. Assuming a need to remove three million cubic yards of debris, and

assuming that a $5-per-cubic-yard increase to DRC’s existing contract unit prices was a

workable incentive, Harris County front-loaded the entirety of that $5-per-cubic-yard add-on

into the first three weeks of debris removal work, rather than spreading it out over time, to

provide a stronger incentive to the necessary sand-and-gravel haulers to get on the job

CBCA 6909-FEMA

14

immediately, instead of stretching things out with haulers slowly joining in over the course

of several months. Even FEMA’s EM Program Specialist for Region VI agreed during his

testimony that offering an extra $5-per-cubic-yard, at least for the first thirty days of the

debris removal process, was reasonable. Had Harris County’s three-million-cubic-yard total

estimate been correct, there would be little question as to the ultimate reasonableness of the

payment.

Nevertheless, the three-million-cubic-yard estimate turned out to be wildly off. In the

end, DRC only removed 1,129,652.73 cubic yards of debris—still a significant amount, but

far less than the number that Harris County had originally anticipated and upon which it

based the $15 million payment. Harris County has not made it easy to decide reasonableness

in light of that discrepancy. It has presented nothing—no documents, and no testimony—

showing how or why the incentive payment scheme came to be or why Harris County did not

adopt DRC’s original suggestion of simply adding a $5-per-cubic-yard bonus to DRC’s cubic

yard unit price contract amount. Had it adopted DRC’s original suggestion, Harris County

ultimately would have paid only an additional $5.648 million (1,129,652.73 x $5), rather than

the $15 million it actually paid. Would a $5 addition to each unit price have been a sufficient

incentive to get workers on site immediately? We cannot know, in part because Harris

County presented no contemporaneous analysis evaluating that approach. Harris County

does not even know who within its contracting office (or elsewhere) came up with the idea

for the $15 million incentive payment scheme, leaving us to guess at why someone thought

the approach adopted was necessary or believed DRC’s original suggestion would not work.

In light of the paucity of evidence about how DRC’s unit price increase suggestion

morphed into a $15 million upfront incentive payment, we cannot find that Harris County has

established that the entire $15 million payment is reasonable. We understand that, in early

September 2017, Harris County felt confident that its three-million-cubic-yard debris

estimate was not only reasonable, but was probably low. In some ways, we are engaging in

a type of Monday-morning quarterbacking by criticizing Harris County for not originally

considering the possibility that its estimate might be too high. In the end, though, it is the

absence of evidence about any alternatives that Harris County considered, which might have

tied payments to the actual quantity of debris ultimately found rather than a predetermined

three million cubic yard figure, and the reasons that Harris County discounted or rejected

those alternatives that preclude us from finding the entire $15 million incentive payment

reasonable. FEMA’s memorandum dated September 15, 2017, warned localities to ensure

that, if they paid increased prices above the amounts set forth in their pre-positioned

contracts, they needed to make sure carefully to document those increases. Although that

memorandum post-dated Harris County’s contract amendment by nine days, it was close

enough in time to place Harris County on notice of FEMA’s expectations. Harris County’s

CBCA 6909-FEMA

15

failure to document its decision-making process when it still could have precludes a finding

that it has proven the reasonableness of the entirety of its $15 million incentive payment.

Decision

Harris County has established that $5.648 million of its $15 million incentive payment

was reasonable. Accordingly, we grant Harris County’s application in part, allowing

recovery of $5.648 million beyond the debris removal costs that FEMA has previously

reimbursed. Harris County’s application is otherwise denied. Harris County’s motion to

limit consideration of and/or strike FEMA’s late-filed documents is denied as moot.

Harold D. Lester, Jr.

HAROLD D. LESTER, JR.

Board Judge

Jonathan D. Zischkau

JONATHAN ZISCHKAU

Board Judge

I agree with the majority’s careful description of the issue in dispute but would decide

it against the applicant. I comment briefly, mainly for the benefit of parties in future

arbitrations in which I am a panel member.

In my view, both parties steered this dispute off the rails by focusing on the price per

cubic yard of debris. The September 6, 2017, contract amendment established three fixed

incentives of $5 million each. It did not state an increase in the price per cubic yard hauled.

Had the applicant wished only to promise to pay an extra $5 per cubic yard, in arrears, as a

“sweetener” each time the vendor met one of the three milestones, the agreement could have

said that, and we might have faced a different issue. Instead, the parties converted a notional

increase in the price per cubic yard to three fixed payments, using an estimate of the total

amount of debris, which everyone knew would be either too high or too low, as estimates

always are. Several witnesses recited the arithmetic underlying this conversion, but no one

explained why it was reasonable to switch from a per-cubic-yard methodology to a riskier

fixed-price methodology to begin with. Moreover, I find no support in the record for the

CBCA 6909-FEMA

16

figure of $5 per cubic yard other than that the vendor suggested it, which may be a starting

point but cannot end a price reasonableness analysis.

I also take this opportunity to exhort future parties to take Board Rule 612 seriously

by “[o]mitting duplicative and immaterial evidence and arguments.” 48 CFR 6106.612(e)

(2020). Here, three judges—21% of our Board—sat through two full days of virtual hearing,

very little of which bore on the eligibility issue we were asked to resolve.

Kyle Chadwick

KYLE CHADWICK

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.