In the Matter of FORREST COUNTY BOARD OF SUPERVISORS

Agency decision

Ask Donna

What actually matters in this document.

Text

March 3, 2010

CBCA 1772-FEMA

In the Matter of FORREST COUNTY BOARD OF SUPERVISORS

David B. Miller, Forrest County Board of Supervisors, Hattiesburg, MS, counsel for

Applicant.

Thomas M. Womack, Executive Director, Mississippi Emergency Management

Agency, Pearl, MS, appearing for Grantee.

Janice Williams-Jones, Office of Chief Counsel, Federal Emergency Management

Agency, Department of Homeland Security, Washington, DC; and Linda D. Litke, Office of

Chief Counsel, Federal Emergency Management Agency, Department of Homeland Security,

Biloxi, MS, counsel for Federal Emergency Management Agency.

Before the Arbitration Panel consisting of Board Judges BORWICK, VERGILIO, and

KULLBERG.

This matter involves a dispute between the Forrest County Board of Supervisors

(BOS) and the Federal Emergency Management Agency (FEMA) concerning a request for

public assistance related to mold remediation for the Forrest County Courthouse (courthouse)

located in Hattiesburg, Mississippi. The BOS and the Mississippi Emergency Management

Agency (MEMA), which supports the BOS in its request for public assistance in this matter,

contend that the courthouse, a historic structure built in 1910, suffered damage from mold

growth due to high interior temperatures and humidity during the nine-day loss of electrical

power necessary to run the air conditioning system following Hurricane Katrina. FEMA

contends that no public assistance is warranted. This matter is before the panel under

CBCA 1772-FEMA

2

authority of section 601 of Public Law 111-5, the American Recovery and Reinvestment Act

of 2009, and section 206.209 of title 44 of the Code of Federal Regulations.

Hurricane Katrina struck Hattiesburg, Mississippi, on August 29, 2005. In preparation

for the hurricane, the doors to the courthouse were sandbagged. As a result of the

hurricane-force winds and rain, four windows on the second floor of the southeast corner of

the courthouse were broken, which resulted in water intrusion. Water intrusion on the first

floor resulted from the loss of flashing on the east side of the courthouse. The hurricane

caused the loss of electrical power throughout the surrounding area, and the courthouse was

without electrical power for nine days.

Immediately following the hurricane, several measures were taken to prevent further

damage to the courthouse. The broken windows were boarded up. A portable generator was

available at the courthouse to provide power for some fans and equipment for vacuuming up

water (wet vacs). The wet vacs were used to remove water from areas of the first and second

floors where rain had leaked into the building.

Due to the loss of electrical power, the air conditioning and ventilation system for the

courthouse was out of operation. No external generators of sufficient capacity were available

during that power outage to run the air conditioning in the courthouse because the Unified

Command Group for Mississippi determined that hospitals, nursing homes, and shelters had

priority for such generators. Temperatures in the Hattiesburg area during the nine-day power

outage ranged from 90 to 105 degrees with high humidity, and consequently, the interior of

the courthouse was extremely hot and humid. When electrical power to the courthouse was

finally restored, the air conditioning started automatically.

With electrical power restored, courthouse operations resumed. Approximately two

weeks after returning to work, an employee in the county clerk’s office, which was located

on the first floor of the east side of the building, complained about an odor in her office that

was causing sinus problems and headaches. As a result of the county clerk’s complaints and

the presence of a dark substance underneath some of the wallpaper in that office, the

maintenance supervisor for the BOS, Curtis Elliott, contacted a FEMA representative, who

advised him to have the courthouse inspected.

Dr. Michael Bonner of Bonner Analytical Testing Company was employed by the

BOS to investigate the air quality within the courthouse. Dr. Bonner’s investigation of the

courthouse took place on October 21 and 24, 2005, December 30, 2005, and

January 16, 2006. Dr. Bonner initially inspected three offices, and he later inspected the rest

of the building. Dr. Bonner’s written report noted that the courthouse had suffered water

intrusion as a result of wind-driven rain followed by a nine-day electrical power outage.

CBCA 1772-FEMA

3

Those conditions, according to Dr. Bonner’s report, would have resulted in “extensive

microbial amplification . . . within 48 hours.” The report further stated that such extensive

microbial amplification would have occurred “even if no pre-existing conditions contributed

to the contamination.” Based upon his professional experience, Dr. Bonner’s report, which

was issued in February of 2006, stated that the percentage of damage due to Hurricane

Katrina was the following:

1.

Air handling systems–Katrina damage 10%. These

systems were likely contaminated prior to Katrina. The

conditions were exacerbated by the storm.

2.

Tear-out and build back–Katrina damage 40%. Vinyl

wall covering is likely to have contributed to the contamination.

Tear-out should include all visible microbial amplification to

include drywall, insulation and damaged plaster.

3.

Clean, disinfect and HEPA [high efficiency particulate

absorbing] vacuum, pack out/move contents–Katrina damage

60%.

4.

Replace porous contents

individually–Katrina damage 60%.

or

clean

and

test

5.

Clean, disinfect and HEPA vacuum files–Katrina damage

60%.

6.

Clean, disinfect and HEPA vacuum computers–Katrina

damage 60%.

On June 7, 2006, representatives from FEMA and MEMA executed project worksheet

(PW) 8837, which estimated the cost of mold remediation at $506,108.30. The PW provided

a breakdown of the costs for cleaning certain parts of the building, including the air

conditioning system, and replacing porous surfaces such as upholstered furniture, wallpaper,

and carpeting. Also, the PW included the costs of relocation of courthouse personnel and

Dr. Bonner’s inspection and written report.

Beginning in the spring of 2006, courthouse personnel and offices were relocated

while mold remediation took place. The work was not completed until sometime in 2007.

Under two separate contracts, all contaminated furniture and porous surfaces in the building

were removed and replaced. The costs related to mold remediation that the BOS was able

CBCA 1772-FEMA

4

to document totaled $225,381.1 Additionally, the costs of employing Dr. Bonner totaled

$17,460. The BOS represented that additional amounts were expended for mold remediation,

but documentation of those costs was not presented.

On November 3, 2006, FEMA determined that no public assistance was warranted for

the mold remediation work shown on PW 8837. MEMA submitted on behalf of the BOS an

appeal to FEMA’s regional administrator, which was denied on January 17, 2008, and a

subsequent appeal to FEMA’s headquarters was denied on February 18, 2008, in which

FEMA determined that no public assistance was warranted in that the mold damage was not

due to Hurricane Katrina, but instead, was due to “deferred maintenance and post-storm

negligence.” Relying on Dr. Bonner’s report that determined that only a portion of the mold

damage was due to Hurricane Katrina, the BOS brought this matter for arbitration seeking

forty percent of the estimated cost for mold remediation shown on PW 8837.

This matter presents the issue whether FEMA properly determined that no award of

public assistance is warranted. Eligibility for public assistance requires a finding that such

repairs were “required as the result of the major disaster event.” 44 CFR 206.233(a)(1)

(2009). Public assistance will not be “provided to an applicant for damages caused by its

own negligence.” Id. 206.233(e).

The Bonner report established that the air quality within the courthouse was unsuitable

due to mold shortly after the power outage caused by Hurricane Katrina. Dr. Bonner

explained during the hearing that the conditions in southern Mississippi are such that prolific

microbial (mold) growth would occur in a wet building that stays wet for twenty-four to

forty-eight hours. He also explained that even if water intrusion in a building is minimal,

high humidity, above fifty percent, will also cause rapid mold growth. In the aftermath of

the hurricane, Dr. Bonner observed similar damage due to rapid mold growth in other

buildings in southern Mississippi. Additionally, Dr. Bonner acknowledged that some mold

damage existed in the courthouse before Hurricane Katrina, but forty percent of the mold

damage was attributable to the hurricane. A majority of the panel finds that Dr. Bonner’s

conclusion that forty percent of the mold damage in the courthouse was related to Hurricane

Katrina was persuasive. His education, professional background, and environmental testing

experience that included fifteen years of testing air quality for the presence of mold made

him highly qualified to render an opinion, and a majority considers his conclusions to be

soundly based.

1

The costs that the BOS incurred for mold remediation and Dr. Bonner’s report

are rounded off to the nearest dollar.

CBCA 1772-FEMA

5

FEMA argued that the courthouse was in need of repair before the hurricane due to

cracks in the mortar and gaps around windows where water could have entered the building

with resulting mold damage. The courthouse, however, was a usable facility before

Hurricane Katrina. It was only when courthouse personnel returned to work after the

hurricane that the air quality in the courthouse was such that mold remediation became

necessary. Although there had been reported complaints about air quality in the courthouse

before Hurricane Katrina, those complaints had been resolved by adjusting a damper or

taking other actions to improve air circulation.

FEMA has not shown that the mold damage to the courthouse was the result of

negligence. Before power was restored to the courthouse, reasonable efforts were taken by

BOS personnel to mitigate further damage. Those efforts included boarding up the broken

windows, vacuuming water, and running fans. The heat and high humidity inside the

courthouse during the nine-day power outage could not be controlled. FEMA has argued the

BOS should have obtained a generator to restore power to the air conditioning system, but

such large capacity generators were only available for facilities such as hospitals, nursing

homes, and shelters where lifesaving measures were a priority.

Additionally, FEMA cites the example of mold remediation work at the Pearl River

Community College (PRCC), which included cleaning and disinfecting air conditioning

systems, to show that the BOS was negligent for not having taken similar measures. The

mold remediation work at the PRCC was performed by a contractor under a hurricane plan

that had the purpose of resuming operations at the college as quickly as possible. The fact

that such mold remediation was accomplished at the PRCC, which had over forty buildings,

does not lead to the conclusion that the BOS was negligent for not having done similar work.

There is no evidence that the BOS had either the opportunity or means to contract with a

mold remediation contractor immediately after the hurricane in the same manner as the

PRCC. It was also established at the hearing that Forrest County had an emergency

management plan to coordinate lifesaving and property saving measures, and that plan did

not include such details as air conditioning systems. The BOS took reasonable property

saving measures using the personnel and equipment that were available in the midst of a

major disaster. A majority of the panel, therefore, does not find that the BOS was negligent

under such circumstances.

Decision

For the purpose of determining the amount of public assistance that should be

awarded by FEMA, a majority of the panel finds that forty percent of the mold damage was

related to Hurricane Katrina, and the award of public assistance shall be forty percent of

proven costs for mold remediation less insurance for mold damage. The total documented

CBCA 1772-FEMA

6

cost for mold remediation was $225,381 and the cost for Dr. Bonner’s work and written

report was $17,460. Those costs totaled $242,841. It was acknowledged at the hearing by

the BOS that there was insurance for the courthouse in the amount of $25,000 for mold

damage. Although it was unclear whether an insurance claim was submitted, the panel

deducts $25,000 from the public assistance award. The amount of public assistance to be

awarded is forty percent of $242,841, which equals $97,136, minus $25,000, which equals

$72,136.

It is the determination of a majority of the panel in this matter, consequently, that

FEMA shall pay public assistance in the amount of $72,136 for mold remediation costs for

the Forrest County Courthouse.

______________________

H. CHUCK KULLBERG

Board Judge

______________________

ANTHONY S. BORWICK

Board Judge

“The arbitration panel shall have sufficient authority regarding the award or denial of

disputed public assistance applications for covered hurricane damage . . . for a project the

total amount of which is more than $500,000.” Pub. L. No. 111-5, § 601, 123 Stat. 115, 164

(2009)). Because I conclude that the applicant has not demonstrated that the $500,000

threshold is satisfied to permit this arbitration panel to resolve the merits of this dispute, I do

not join the majority. I conclude that the panel is not authorized to bind FEMA in this matter.

______________________

JOSEPH A. VERGILIO

Board Judge

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.