Opinion

CBRE v. Super. Ct.

Court
California Court of Appeal
Filed
Jun 4, 2024
Status
Published
Cited by
0 cases
Authority
More cited than 16.3%

The opinion

Filed 6/4/24

CERTIFIED FOR PUBLICATION

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

CBRE et al., D083130

Petitioners,

v.

(Super. Ct. No. 37-2021-

THE SUPERIOR COURT OF SAN

00033025-CU-PO-CTL)

DIEGO COUNTY,

Respondent;

JAKE JOHNSON,

Real Party in Interest.

ORIGINAL PROCEEDING on a petition for writ of mandate after the

superior court denied summary judgment. Marcella O. McLaughlin, Judge.

Petition granted.

Niddrie Addams Fuller Singh, John S. Addams; Wingert Grebing

Brubaker & Juskie, Alan K. Brubaker, Ian R. Friedman and Steven J.

Scordakis for Petitioners.

Hoffman & Forde, Michael Dicks; Berding & Weil, Anne L. Rauch and

Trinette S. Sachrison for Real Party in Interest.

No appearance for Respondent.

Jake Johnson was injured while working as an electrician on a

construction project in a building owned by Property Reserve, Inc. (PRI) and

managed by CBRE (collectively, Petitioners). When injured, Johnson was

employed by PCF Electric (PCF), a subcontractor hired by Crew Builders

(Crew), the general contractor for the project. Johnson filed a complaint

against Petitioners, Crew, and PCF for damages.

Petitioners moved for summary judgment based on the Privette

doctrine, which generally protects entities that hire independent contractors

from liability for injuries sustained by employees of the independent

contractor while working on a project. (See Privette v. Superior Court (1993)

5 Cal.4th 689 (Privette).) The trial court denied Petitioners’ motion, finding a

triable issue of fact as to when they hired Crew for the project. In the instant

petition for writ of mandate, Petitioners assert the trial court erred by

focusing on the execution date of the written contract, and they ask this court

to issue a writ compelling the trial court to grant their motion for summary

judgment.

We agree the trial court erred in denying Petitioners’ motion for

summary judgment. A written contract is not required to invoke the Privette

doctrine, and the undisputed facts establish that Petitioners delegated

control over the tenant improvements to Crew prior to Johnson’s injury.

The undisputed facts also establish that no exception to the Privette

doctrine applies. Prior to Johnson’s injury, Petitioners and Crew mutually

agreed to proceed with the project without obtaining permits such that the

permitting process was never within the scope of the contracted work.

Because the evidence conclusively shows PCF was able to discover any non-

code-compliant wiring itself, even in the absence of permits, the “concealed

hazardous condition” exception to the Privette doctrine is inapplicable as a

matter of law. Further, because the decision to forego the permitting process

did not affect the means by which PCF and its employees performed the

2

electrical work for which they were hired or the manner in which they

ensured their own safety, the “retained control” exception to the Privette

doctrine is equally inapplicable.

Because no triable issues of material fact preclude summary judgment,

we grant Petitioners’ requested relief.

I.

PRI owns an office building in San Diego managed by CBRE. On

April 9, 2019, PRI entered into a lease agreement with a new tenant for a

suite in the building. The lease was to commence on June 1 and required PRI

to make certain tenant improvements.

During the lease negotiations, Petitioners solicited a bid from Crew to

act as the general contractor for the tenant improvement project, and on

March 4, Crew submitted its bid. Crew believed a permit was required for

the work, as reflected in the bid. The parties began negotiating a formal

service contract; however, they had a standing relationship, and it was

common for Crew to begin work for Petitioners before finalizing a contract.

On March 18, Crew sent CBRE a timeline for the project that still

included the permitting process, noting the project would need to begin the

following week to meet the tenant’s move-in date. On March 22, CBRE’s

senior real estate manager asked for an updated timeline “without a permit,”

indicating, “[w]e’ll probably get started on this one right away.”

On April 5, PRI requested that CBRE ask Crew to make changes to the

bid, including omitting permits because PRI did not think they were needed.

Crew’s April 5 bid excluded permits but still included other line items to

bring the project “up to code.” On April 8, Crew submitted a revised and final

bid excluding additional permit-related line items at Petitioners’ request.

3

PRI’s asset manager “gave the ok to begin” on April 9, and work on the

project commenced.

In soliciting bids from subcontractors, Crew indicated the project “won’t

be permitted.” Crew subcontracted the electrical work on the project to PCF.

PCF began work on the project on April 10 but did not execute a formal

written subcontract with Crew until April 15.

PCF’s April 15 bid included researching the existing electrical system

and putting it in “safeoff,” a safe working condition also called

“lockout/tagout,” prior to commencing work. PCF’s site superintendent

inspected the site, traced the circuits, and performed lockout/tagout prior to

demolition at the outset of the project. Johnson was not involved in this

process.

On April 26, Johnson was working as foreman on the electrical wiring

in the suite. Johnson knew no permits had been pulled for the project. He

also knew the 277-volt power circuit was turned on to power the building’s

lights, as the mandatory temporary lighting had been removed the prior day.

However, he believed the 277-volt system was “separate and apart” from the

120-volt system he was working on, as currently required by code. Further,

he did not know there were no engineering plans, as-built drawings, as-built

plans, building inspections, or plans to bring the building up to code. Prior to

April 26, someone had removed the PCF superintendent’s lockout/tagout.

While attempting to replace a cover on a junction box labeled as 120-volt and

containing wires color-coded as 120-volt under the current code, Johnson

touched a live 277-volt wire, fell off a ladder, and sustained serious injuries.

According to the deposition testimony of PCF’s site superintendent and

person most knowledgeable, “a foreman on a job site like that should not have

trusted color codes or voltages,” and he personally uses both his meter and

4

his “hot stick” to test every “[o]utlet, switch, box, anything. Any wire, any

electrical.” PCF’s preconstruction manager said PCF protocol was to hot-

stick every box, even after inspection and lockout/tagout. Petitioners’ expert

similarly opined that best practice is for an electrician to “assume all circuits

‘hot’ until you’ve proved they’re not.” He also opined “[t]here was no possible

role for CBRE or PRI in the required lockout/tagout process.”

Petitioners and Crew executed their formal service contract on May 13.

The contract included a paragraph specifying Crew was to obtain all permits,

licenses, and approvals necessary to perform and complete the work, at its

sole cost and expense.

Johnson filed a complaint against Petitioners, Crew, and PCF for

damages arising out of the April 26 incident. After discovery, Petitioners

filed a motion for summary judgment, asserting all Johnson’s claims as to

them were barred by the Privette doctrine. Johnson opposed, asserting:

(1) there was no contract delegating responsibility for workplace safety

between Petitioners and Crew or PCF at the time of the incident, and

(2) material issues of fact remained as to whether an exception to the Privette

doctrine applied.

The trial court denied Petitioners’ motion, concluding there was a

triable issue of material fact as to when Petitioners hired Crew for the project

such that Petitioners were not entitled to judgment as a matter of law. In so

concluding, the trial court relied on the deposition testimony of PRI’s asset

manager who, when asked about PRI’s policy as to tenant improvement

contracts, responded, “we didn’t do anything oral.” He further explained

that, “as the landlord, we would . . . wash [our] hands, so to speak, of the deal

once we had the lease signed, . . . and then everything would turn over to

CBRE.” While he knew CBRE would sign agreements with the contractor

5

Petitioners chose, he was not involved and thus did not “know the

progression of when those would be signed and things like that.”

The trial court, however, simultaneously granted Crew’s motion for

summary judgment, concluding Privette barred Johnson’s claims against it

because there was no evidence (1) Crew retained control over any aspect of

PCF’s performance of the contracted work or (2) the mislabeled junction box

was a “concealed hazard” not reasonably discoverable by PCF. It also

granted PCF’s motion for summary judgment, finding workers’ compensation

to be the sole remedy for Johnson’s injury. Johnson obtained recovery

through workers’ compensation.

II.

“‘Where the trial court’s denial of a motion for summary judgment will

result in trial on nonactionable claims, a writ of mandate will issue.’” (CRST,

Inc. v. Superior Court (2017) 11 Cal.App.5th 1255, 1259-1260.) Petitioners

contend the trial court erred in denying their motion and seek a writ of

mandate compelling the trial court to vacate its previous order and enter a

new one granting summary judgment under Privette.

A.

In Privette, the California Supreme Court recognized the common law

principle that “a person who hired an independent contractor generally was

not liable to third parties for injuries caused by the contractor’s negligence in

performing the work.” (Privette, supra, 5 Cal.4th at p. 693.) The doctrine

presumes that the hirer of an independent contractor “ordinarily delegates to

that independent contractor all responsibility for the safety of the contractor’s

workers.” (Sandoval v. Qualcomm Incorporated (2021) 12 Cal.5th 256, 264

(Sandoval).) This presumption “is grounded in two major principles: first,

that independent contractors by definition ordinarily control the manner of

6

their own work; and second, that hirers typically hire independent

contractors precisely for their greater ability to perform the contracted work

safely and successfully.” (Id. at p. 269.) Thus, we generally presume “that a

hirer delegates all control over the contracted work, and with it all

concomitant tort duties, by entrusting work to a contractor.” (Id. at p. 270.)

However, “that presumption gives way to two recognized exceptions:

where the hirer . . . withholds critical information regarding a concealed

hazard . . . or retains control over the contractor’s work and actually exercises

that control in a way that affirmatively contributes to the worker’s injury.”

(Sandoval, supra, 12 Cal.5th at p. 264.)

B.

A trial court shall grant a motion for summary judgment “if all the

papers submitted show that there is no triable issue as to any material fact

and that the moving party is entitled to a judgment as a matter of law.”

(Code Civ. Proc., § 437c, subd. (c).)

As the moving party, Petitioners had the initial burden of establishing

that Johnson as plaintiff either could not prove or that there was a complete

defense to each cause of action as alleged in the complaint. (§ 437c(p)(2);

Aguilar v. Atlantic Richfield Co. (2001) 25 Cal.4th 826, 850, 853 (Aguilar).)

Assuming Petitioners met that burden by asserting that the Privette doctrine

immunized them against all stated causes of action, the burden then shifted

to Johnson to present evidence demonstrating a triable issue of material fact:

in other words, evidence that would allow a reasonable trier of fact to make a

factual finding in favor of Johnson by concluding one of the Privette doctrine’s

exceptions applies. (§ 437c(p)(2); Aguilar, supra, 25 Cal.4th at pp. 843, 850.)

We review the trial court’s order denying Petitioners’ motion for

summary judgment under the same legal standard as the trial court and

7

independently assess the correctness of the ruling. (Moore v. Regents of

University of California (2016) 248 Cal.App.4th 216, 231.) “[W]e examine the

record de novo, liberally construing the evidence in support of the party

opposing summary judgment and resolving doubts concerning the evidence in

favor of that party.” (Miller v. Department of Corrections (2005) 36 Cal.4th

446, 460.) Nonetheless, a party “cannot avoid summary judgment by

asserting facts based on mere speculation and conjecture, but instead must

produce admissible evidence raising a triable issue of fact.” (LaChapelle v.

Toyota Motor Credit Corp. (2002) 102 Cal.App.4th 977, 981.)

C.

Petitioners assert they met their initial burden by presenting evidence

sufficient to establish that, prior to the date of Johnson’s injury, they hired

Crew as an independent contractor, who in turn hired PCF, thus activating

the Privette presumption of complete delegation. They contend the trial court

improperly focused on the date of execution of the written services contract

with Crew and, contrary to the trial court’s apparent reasoning, the Privette

doctrine applies even without a written contract.

In response, Johnson claims the trial court correctly identified a

material factual dispute regarding the scope of the agreement: specifically,

what safety protocols Petitioners delegated to Crew and when. He contends

there are triable issues of fact as to whether Petitioners fall under one of the

Privette doctrine’s exceptions, either because they (1) failed to disclose a

dangerous, concealed condition in the non-compliant electrical wiring or

(2) retained control by instructing Crew to proceed without a permit.

1.

We begin with Petitioners’ claim that the trial court incorrectly focused

on the execution date of Petitioners’ written contract with Crew as a disputed

issue determinative of the Privette doctrine’s applicability.

8

First, to the extent the trial court suggested a written contract was

necessary for Privette to attach, our high court recently rejected that premise

in Sandoval. It explained the doctrine is not based in a contract’s terms but

rather in the delegation implicit when a hirer turns over control of the

worksite to the contractor to undertake the work, whether by written or

informal agreement. (Sandoval, supra, 12 Cal.5th at pp. 271, 274.) Thus, the

nonexistence of a written contract at the time of Johnson’s injury is

immaterial.

Second, to the extent the trial court found, and Johnson maintains,

that a triable issue of fact exists as to whether Petitioners delegated control

over the tenant improvement project to Crew prior to the effective date of the

agreement at all, we disagree.

Although below Johnson asserted as an undisputed fact that “PRI hired

Crew Builders as the general contractor,” he now claims otherwise,

insinuating several items of evidence raise an inference that the parties

“fraudulently re-characterized their arrangement as one of general

contractor” after Johnson’s injury to “allow[ ] them to argue the presumptions

of implied delegation under Privette.” We, however, agree with Petitioners

that the evidence on which Johnson relies does not reasonably give rise to the

speculative inference he advances.

Here, as Petitioners assert, undisputed evidence establishes that

Petitioners had previously hired Crew, a licensed general contractor, for

numerous tenant improvement projects on the property. Petitioners and

Crew thus had developed an “understanding” that Crew would begin work on

projects before a formal contract was finalized. Petitioners asked Crew to

immediately start this project in accordance with that understanding. Crew

defined the full scope of the project’s work in its detailed bid and formulated

9

the construction schedule for the project, subject to input from Petitioners.

There is no dispute Crew subcontracted all the electrical work for the project

to PCF, which began work as a subcontractor on April 10, and no dispute that

Johnson was working on the project as an employee of PCF on the day of the

incident several weeks later. On this evidence, Petitioners hired Crew and

implicitly delegated complete control of the worksite, including its safety, to

Crew before the date of Johnson’s injury.

Johnson’s attempts to rebut that presumption and raise triable issues

fail. He points to (1) the testimony from PRI’s asset manager and person

most knowledgeable stating he personally did not have, and he did not “know

of anyone” else who had, an oral contract with Crew prior to entering into the

formal services contract; and (2) the May 3 effective date of the written

contract between Crew and Petitioners, to support an inference that, under

its management agreement with PRI, CBRE retained control over the tenant

improvement project until the written agreement took effect. We, however,

agree with Petitioners that the asset manager’s testimony is irrelevant.

Whether PRI’s asset manager “knew” of any informal agreement between

Petitioners and Crew, and whether such agreements were against PRI policy,

does not preclude such agreements from existing, particularly given the asset

manager also stated he would “wash [his] hands” once the lease was signed

such that “everything would turn over to CBRE” to contract with the

contractor. Given the asset manager’s clear lack of personal knowledge on

the issue of the Crew contract, his statements are of no evidentiary value.

We further agree with Petitioners that despite the May 3 effective date of

Crew’s contract with Petitioners, the contract clearly specifies that any work

performed prior to the execution date “shall be governed by the terms and

conditions of this Contract.” This supports, rather than undermines, Crew’s

10

assumption of a general contractor role from the get-go. Crew’s final bid,

which was incorporated as the scope of work in the final written agreement,

and Crew’s timeline for the project evidence that Crew was acting as general

contractor at the time of Johnson’s injury.

Johnson further relies on the fact that Crew’s April 15 contract with

PCF states “NONE” as the date Crew entered into a prime contract with

Petitioners to claim Crew “disavowed” that role. Yet we are not persuaded by

this speculative inference. Instead, the reasonable inference the evidence

supports is that “NONE” was intended to convey the undisputed fact that the

relevant contract was not yet finalized. Johnson additionally points to a

provision in CBRE’s February 2018 Health, Safety and Environmental

Minimum Performance Requirements for Contractors (Manual) providing

that “[t]here may be periods of time when CBRE is designated by their client

to serve as the Prime Contractor,” in which circumstance CBRE will “have

the sole responsibility for oversight of all construction means, methods,” and

safety procedures, to show that CBRE was acting as the general contractor at

the time of the incident. But the fact that PRI can designate CBRE to serve

as a general contractor is not evidence CBRE was acting in that capacity

here. Johnson points to no evidence showing PRI so designated CBRE for

this project. Even if PRI had designated CBRE as the prime contractor, that

does not prevent CBRE from delegating any control it had over the project to

Crew as the general contractor. The same is true of the provision in PRI’s

contract with CBRE vesting CBRE with the responsibility to keep the

premises “in full compliance with all laws, orders, requirements, and

regulations” and supervise construction projects, as well as the provisions in

the Manual providing that contractors must receive authorization from

CBRE before shutting down electrical systems, locking/tagging out systems,

11

reenergizing any systems, or initiating emergency lock removal procedures.

Johnson cites no authority holding any of these duties nondelegable nor

evidence that these duties were not delegated in this instance.

Ultimately, the evidence Johnson cites does not support his claim that

CBRE, rather than Crew, was the project’s general contractor prior to

execution of the formal agreement and thus does not support Johnson’s

speculation that the contract fraudulently “recharacterized” the role for

which Crew was hired. Accordingly, we conclude the evidence establishes

that Petitioners hired Crew as the general contractor for this project, as that

term is used in the context of the Privette doctrine, and they turned the

premises over to Crew to begin its work prior to Johnson’s injury, thereby

activating the doctrine’s presumption of delegation. (Alvarez v. Seaside

Transportation Services LLC (2017) 13 Cal.App.5th 635, 643-644.)

2.

The conclusion that Petitioners hired Crew in a manner sufficient to

invoke the Privette presumption of delegation does not end the relevant

inquiry, however, given the presumption is subject to two exceptions.

(Sandoval, supra, 12 Cal.5th at p. 264.)

a.

We begin with Johnson’s claim that triable issues of fact exist as to

whether the Privette exception for failure to disclose a concealed hazard

applies. In Kinsman v. Unocal Corp., our Supreme Court held a landowner

can be liable for an injury to a contractor’s employee where (1) “the

landowner knew, or should have known, of a latent or concealed preexisting

hazardous condition on its property;” (2) “the contractor did not know and

could not have reasonably discovered this hazardous condition;” and (3) “the

landowner failed to warn the contractor about this condition.” (Kinsman v.

Unocal Corp. (2005) 37 Cal.4th 659, 664 (Kinsman).)

12

As the Kinsman test is conjunctive, we focus on Johnson’s claim that

triable issues of fact exist as to whether PCF or Johnson could reasonably

have discovered “the hazardous condition.” Whether the alleged hazard was

the lack of permits or the mislabeled and miswired junction box is somewhat

unclear from Johnson’s brief. Either way, however, the evidence on which

Johnson relies is misdirected in that it focuses on what permit inspections

and as-built drawings could have revealed rather than what PCF and

Johnson were independently capable of discovering.

To the extent the lack of permits or permit-related plans and drawings

is alleged to be a “hazardous condition,” because it potentially allowed

conditions not compliant with current code requirements to remain on site,

Petitioners argue that condition was reasonably discoverable by PCF

“inquiring whether a permit, as-built drawings, and engineering plans were

obtained.” We agree. Johnson cites no evidence showing this simple measure

was impracticable or impossible.

To the extent the non-code-compliant junction box itself is the

hazardous condition, Johnson acknowledges the trial court granted Crew’s

motion for summary judgment based on its finding that there was “no

evidence . . . suggesting PCF – an electrical subcontractor – could not have

reasonably discovered the hazardous condition.” Petitioners likewise claim

the energized wire was readily discoverable by metering it. Again, we agree.

The undisputed testimony of PCF’s site superintendent established

that Johnson’s meter would have revealed the 277-volt wire in the junction

box had he used it. According to Petitioners’ expert, Johnson’s hot stick,

which he had nearby at the time of the accident, also would have revealed the

wire was energized and unsafe. PCF’s preconstruction manager said it was

best practice to hot-stick each electrical item, even after initial inspection of

13

the worksite and lockout/tagout. Petitioners’ expert echoed the sentiment by

opining electricians should assume a wire is hot until proven not. This

evidence establishes there were reasonable—indeed, easy—ways for Johnson

or any other PCF employee to discover the dangerously live 277-volt wire in

the 120-volt junction box. Johnson points to no evidence to the contrary.

Thus, the Kinsman exception is inapplicable as a matter of law.

b.

Johnson primarily contends the retained control exception to the

Privette doctrine announced in Hooker v. Department of Transportation

(2002) 27 Cal.4th 198 (Hooker) applies. In Hooker, our Supreme Court

rejected the notion a hirer could be liable “merely because [it] retained the

ability to exercise control over safety at the worksite,” instead concluding

“imposition of tort liability on a hirer should depend on whether the hirer

exercised the control that was retained in a manner that affirmatively

contributed to the injury of the contractor’s employee.” (Id. at p. 210.)

Johnson argues a triable issue of material fact remains as to (1) the

scope of Petitioners’ delegation of control to Crew at the time of the accident

and (2) whether Petitioners affirmatively contributed to Johnson’s injury. He

claims that, “[n]ot only did [Petitioners] decline to delegate the most

fundamental construction workplace safeguard required by law [i.e., the

permitting process], but they also strategically instructed all involved in the

[tenant improvements] to skip that process to meet their goals of speeding

through the [project].” Petitioners respond that their decision to proceed with

the project without obtaining permits was not a retention of control over

safety procedures for the project; accordingly, their delegation to Crew was

complete and Privette bars liability.

14

Construing all evidence and reasonable inferences in favor of Johnson,

we conclude the retained control exception does not apply here.

i.

In the decades since Hooker was decided, the high court has clarified

and further refined the retained control exception.

In Sandoval, the court explained that “[a] hirer ‘retains control’ where

it retains a sufficient degree of authority over the manner of performance

of . . . the work the contractor has agreed to perform”—i.e., the “‘contracted

work.’” (Sandoval, supra, 12 Cal.5th at p. 274.) “[A] hirer’s authority over

the contracted work amounts to retained control only if the hirer’s exercise of

that authority would sufficiently limit the contractor’s freedom to perform the

contracted work in the contractor’s own manner.” (Id. at p. 275.) A corollary

is that “[a] hirer’s authority over noncontract work . . . does not give rise to a

retained control duty unless it has the effect of creating authority over the

contracted work.” (Id. pp. 274-275, italics added.)

Even where a hirer retains control over contracted work, the hirer only

“‘actually exercise[s]’” that control if it “in fact involve[s] itself, such as

through direction, participation, or induced reliance,” in the contract work

and “exert[s] some influence over the manner in which the contracted work is

performed.” (Sandoval, supra, 12 Cal.5th at p. 276.) No affirmative act is

required; a failure to act can suffice. (Id. at p. 277.) Our Supreme Court,

citing prior decisions, recently provided a nonexhaustive list of situations in

which courts have concluded retained control was actually exercised,

including “directing the manner or methods in which the contractor performs

the work; interfering with the contractor’s decisions regarding the

appropriate safety measures to adopt; requesting the contractor to use the

hirer’s own defective equipment in performing the work; contractually

prohibiting the contractor from implementing a necessary safety precaution;

15

or reneging on a promise to remedy a known hazard.” (Gonzalez v. Mathis

(2021) 12 Cal.5th 29, 47 (Gonzalez).)

For a hirer’s actual exercise of retained control to affirmatively

contribute to the injury, it must contribute “in a way that isn’t merely

derivative of the contractor’s contribution to the injury.” (Sandoval, supra,

12 Cal.5th at p. 277.) The contribution need not be substantial. (Id. at

p. 278.) If “the contractor’s conduct is the immediate cause of injury,” the

high court explained that inducing “the contractor’s injury-causing

conduct”—as the hirer in McKown v. Wal-Mart Stores, Inc. did when it

requested a contractor use defective equipment in completing the contracted

work—affirmatively contributes to the injury. (Id. at p. 277, citing McKown

v. Wal-Mart Stores, Inc. (2002) 27 Cal.4th 219, 225 (McKown).) Yet if the

hirer’s exercise of control merely provides an opportunity for the hirer to

prevent the injury-causing conduct, as in Hooker, an affirmative contribution

to the injury is lacking. (Ibid., citing Hooker, supra, 27 Cal.4th at p. 214.)

The hirer’s exercise of retained control also affirmatively contributes to

the injury if it independently contributes to the injury. (Sandoval, supra,

12 Cal.5th at p. 277.) Such would be the case if the hirer “‘promises to

undertake a particularly safety measure, then . . . negligent[ly] fail[s] to do

so,’” or prohibits the contractor from taking safety measures “that might have

prevented injury.” (Ibid., citing Hooker, supra, 27 Cal.4th at p. 212, fn. 3;

Ray v. Silverado Constructors (2002) 98 Cal.App.4th 1120, 1133-1134 (Ray).)

ii.

Bearing these principles in mind, we conclude the retained control

exception is inapplicable as a matter of law because Petitioners only retained

control over noncontract work that did not create “authority over the

contracted work.” (Sandoval, supra, 12 Cal.5th at pp. 274-275.)

16

The undisputed evidence establishes that, while Crew included permits

in its initial bids, when Petitioners requested Crew omit permits, Crew

willingly complied. The evidence is clear the Crew employee responsible for

submitting the bid knew permits were required. Crew was free to walk away

from the project at that point in time, or insist that permits remain a part of

the project. Yet the evidence does not show it did so. Instead, even as

negotiations as to the scope of the project were ongoing, Crew communicated

that the project was not permitted in soliciting bids from subcontractors.

Crew’s April 8 bid, which resulted in Petitioners giving the green light to

begin work on the project, did not include permits. This evidence

conclusively shows that at the time of Johnson’s accident, permits were not

part of the contracted work. Petitioners did not retain control over whether,

when, and how to pull permits as part of the project; everyone simply agreed

from the beginning permits were not part of the project at all.

To the extent Johnson disputes PRI’s knowledge of whether permits

were required, as Petitioners note, he fails to explain how PRI’s alleged

motive to save money and time and get a paying tenant into the space more

quickly is at all relevant to the retained control exception. Although Johnson

claimed during oral argument that the time constraints prevented

contractors from taking safety measures, he points to no safety measures

beyond the permit process itself prevented by that short timeframe.

Similarly, whether and the degree to which the formal contract between

Petitioners and Crew delegated control over the permitting process is

immaterial to the understanding the parties had and were operating under

prior to and at the time of Johnson’s accident. Finally, to the extent Johnson

questions the extent to which Crew delegated its control over safety

17

procedures to PCF, we need only resolve whether Petitioners retained any

such control, and we conclude they did not.

The authorities and evidence on which Johnson relies to claim

otherwise do not persuade us. Analogizing to Brown v. Beach House Design

& Development (2022) 85 Cal.App.5th 516 (Brown), Johnson primarily

contends alleged contractual irregularities, addressed and rejected above,

make the scope of the delegation of workplace safety to Crew, if any, a triable

issue. Yet we note Brown is also unhelpful to Johnson on the issue of safety

delegation as it pertains to permits. In Brown, the Court of Appeal

determined triable issues of fact prevented summary judgment in favor of a

general contractor when a subcontractor’s employee fell from scaffolding

erected by a different subcontractor, given uncertainties arising from the

language in the contract with the scaffolding subcontractor as to whether the

contract was even still in effect and whether safety over the scaffolding as to

other contractors’ employees was ever delegated to it by the general

contractor in the first place. (Id. at pp. 521, 523, 531-532.) As Petitioners

argue, this case is factually distinguishable given it does not concern injuries

arising from the provision of defective equipment. The safety of scaffolding

erected during and as of part of the project is clearly part of the contracted

work and a matter over which someone, whether the general contractor or

the subcontractor, exercised control. Such is not the case as to permits

entirely omitted from the scope of work at the time of the injury.

Nonetheless, invoking Regalado v. Callaghan (2016) 3 Cal.App.5th 582

(Regalado), Johnson claims Petitioners “exercised control over the safety of

the work site because of the lack of proper permitting.” Johnson’s

characterization of Regalado, however, is oversimplistic. In Regalado, the

evidence established that the owner/builder of a pool installation “was

18

responsible for obtaining permits and calling for inspections” and, having

failed to do so, told the contractor he hired for the project that he did. (Id. at

pp. 588-589, 597.) One of the contractor’s employees was injured due to the

contractor’s installation of an unventilated propane heater in the vault

housing the pool equipment, which expert testimony established would not

have been allowed had permits been sought. (Ibid.) As Petitioners note,

however, they did not promise to obtain permits and renege; instead, permits

were excluded by agreement from the scope of the contracted work such that

no one assumed control over that process. Further, unlike in Regalado,

where the very installation of the heater in the vault, work the contractor

was hired to do, would not have been approved and would not have happened

in that way had permits been sought, Johnson cites no evidence showing that

requiring him to perform the contracted electric work in an environment that

could contain non-code-compliant electrical systems influenced or restricted

the manner in which he could perform his contracted electrical work.

Johnson also relies on Tverberg v. Fillner Const., Inc. (2012)

202 Cal.App.4th 1439 (Tverberg). There, a general contractor subcontracted

out to different contractors (1) the construction of a canopy and (2) the

installation of large posts that required the digging of holes near the site for

the canopy. (Tverberg, supra, 202 Cal.App.4th at pp. 1442-1443.) The canopy

subcontractor asked the general contractor to cover the holes but was told it

lacked the equipment “to do so that day.” (Id. at p. 1443.) The request was

ignored again the following day, and the canopy subcontractor fell into a hole

and was injured. (Ibid.) The Court of Appeal concluded the general

contractor may have negligently exercised its retained control by ordering the

creation of the holes and requiring the canopy subcontractor to work near

them. (Id. at p. 1448.) Further, the evidence supported an inference that the

19

general contractor had undertaken to cover the holes when the needed

equipment was available yet failed to do so. (Ibid.) While Johnson claims

Petitioners’ direction to Crew to not get permits is comparable, here,

Petitioners did not tell PCF they would obtain permits and then not. Nor did

they interfere with the performance of PCF’s contracted electrical work or the

manner in which it was to be completed. Further, unlike the general

contractor in Tverberg, who directed the creation of a hazardous condition in

the vicinity of the canopy subcontractor’s work, Johnson does not identify

evidence that Petitioners created the miswired and mislabeled junction box.

At most, they allowed a preexisting and potentially dangerous condition to

persist, which is insufficient for liability to attach under the retained control

exception. (Hooker, supra, 27 Cal.4th at pp. 215-216.)

Johnson additionally claims Petitioners’ decision to forego the

permitting process is similar to what happened in Ray, where the hirer, a

transportation agency, and its general contractor contractually prohibited a

subcontractor hired to construct connector bridges from erecting barricades to

close roadways without advance written permission. (Ray, supra,

98 Cal.App.4th at pp. 1132-1133.) Because (1) the general contractor

retained exclusive control to close roads and (2) both the transportation

agency and the general contractor had a duty to the driving public, triable

issues of fact prevented summary judgment where the subcontractor’s

employee was killed by construction materials blown onto the road during

unexpected high winds. (Id. at pp. 1134-1136, 1139.) We agree with

Petitioners that they did not prevent PCF and Johnson from undertaking

measures to ensure safety, much less, as in Ray, “‘the one safety measure

that might have saved the plaintiff’s life.’” (Kinsman, supra, 37 Cal.4th at

p. 671.) Rather, we agree with Petitioners that the undisputed evidence

20

shows there were safety measures available here to prevent Johnson’s

electrocution and fall, as explained above.

Finally, in Browne v. Turner Construction Co. (2005) 127 Cal.App.4th

1334 (Browne), a company hired a general contractor that in turn hired a

subcontractor to install a fire sprinkler system. (Browne, supra,

127 Cal.App.4th at p. 1337.) The subcontractor’s employee fell off a ladder

and was injured. (Ibid.) He claimed he had to use a ladder because the hirer

and contractor had removed hydraulic lifts previously available in the work

area. (Id. at p. 1338.) He also claimed the hirer and contractor had installed

a fall protection system they required workers to use but had removed the

system several months prior. (Id. at pp. 1338-1339.) The evidence thus

suggested the hirer and contractor “actually created the situation in which”

the employee’s injuries “were likely to occur.” (Id. at pp. 1345-1346.) The

Court of Appeal therefore concluded the retained control exception could

apply, as it was “undisputed that [the hirer and general contractor]

undertook to arrange and supply the means and methods of work, including

safety systems and devices, which they then withdrew before the work was

completed, leaving plaintiff with no safe means of completing the work.” (Id.

at pp. 1345.) While Johnson claims Petitioners similarly actively contributed

to his injuries by directing Crew not to undergo the permitting process, we

agree with Petitioners that Browne is distinguishable given Petitioners never

affirmatively undertook a duty to supply equipment for the method of work

and withdraw it. Instead, Petitioners never undertook the permitting process

at all.

During oral argument, Johnson also claimed similarities to McKown, in

which a retailer that hired a contractor requested that the contractor use the

retailer’s own forklifts if possible to perform the work for which it was hired.

21

(McKown, supra, 27 Cal.4th at p. 225.) The forklifts lacked a safety feature,

leading the Supreme Court to conclude the retailer affirmatively contributed

to the injury by inducing the contractor to carry out its contracted work in a

particular manner. (Ibid.) But that is not the case here. Omitting the

permitting process from the scope of the contracted work for the project did

not affect the manner in which PCF carried out the electrical work for which

it was hired.

Instead, this case is analogous to Sandoval, a case on which Petitioners

rely. There, a company hired a contractor “to inspect and verify the

amperage capacity” of its switchgear equipment. (Sandoval, supra,

12 Cal.5th at pp. 265-266.) That contractor in turn hired Sandoval to assist

in an inspection of “the main cogen circuit.” (Id. at p. 266.) The company’s

employees fully powered down the power to the main cogen and reminded the

contractor’s team that some circuits remained live. (Id. at pp. 266-267.)

Sandoval was electrocuted by an arc flash from a live circuit the contractor

exposed. (Id. at p. 267.)

The Supreme Court concluded the company owed Sandoval no retained

control duty arising from its control over the power-down process, because

that process “was not within the scope of work” the company “had entrusted

to” the contractor. (Sandoval, supra, 12 Cal.5th at p. 279.) The power-down

process was instead noncontract work that could only give rise to a retained

control duty if it resulted in retained control over the contracted work of

inspecting the main cogen. (Id. at p. 280.) Even though the company’s

performance of the power-down process limited the contractor’s freedom to

power down other circuits, that “imposed too little a degree of control over”

how the contractor performed its inspection. (Ibid.) Even if the company

effectively required the contractor “to perform its work in . . . the presence of

22

live circuits,” the contractor “was aware of and had ample freedom within the

scope of its entrusted work to accommodate the presence of the live circuits

effectively in its own manner.” (Ibid.) Accordingly, the company did not owe

Sandoval any duty to prevent his injury. (Id. at p. 281.)

The same is true here. Obtaining permits was never within the scope

of the work delegated to Crew. Arguably, obtaining permits also was not

noncontract work, given the clarity of the evidence that neither Petitioners

nor anyone else ever intended to pull any. But even as noncontract work, the

failure to pull permits here “imposed too little a degree of control over” how

Crew completed the tenant improvement process, or how PCF completed the

electrical work, entrusted to each of them. (Sandoval, supra, 12 Cal.5th at

p. 280.) The evidence here establishes that Crew “approach[ed]” the work

“the exact same way as [it] would with a permit.” The evidence also shows

PCF and its employees had “ample freedom” to complete the work entrusted

to them, even while accommodating any possibly non-code-compliant

electrical components by, for example, investigating the site, completing the

lockout/tagout protocol and keeping it in place throughout the work, and hot-

sticking and metering the wiring. While Johnson notes that PRI controlled

access to the building’s electrical rooms, he does not explain how that fact

affects these available safety measures.

Petitioners also invoke SeaBright Ins. Co. v. US Airways, Inc. (2011)

52 Cal.4th 590 (SeaBright) and Delgadillo v. Television Center, Inc. (2018)

20 Cal.App.5th 1078 (Delgadillo), both of which held that, “even where an

unsafe condition exists on the premises due to the landowner’s failure to

comply with specific statutory and regulatory duties, the landowner is not

liable because it is the contractor who is responsible for its own workers’

safety.” (Gonzalez, supra, 12 Cal.5th at p. 48.) In Gonzalez, our Supreme

23

Court concluded this general principle applies “even where the contractor is

unable to minimize or avoid the danger through the adoption of reasonable

safety precautions.” (Id. at pp. 45, 48, 53-54.) Although “there will

sometimes be financial and other real world factors that might make it

difficult for an independent contractor to raise safety concerns with the hirer

or to simply walk away from a job it has deemed to be unsafe,” the contractor

“can typically factor the cost of added safety precautions or any increased

safety risks into the contract price” and “purchase workers’ compensation to

cover any injuries sustained while on the job.” (Id. at p. 51.)

While Johnson claims this case is distinguishable from SeaBright and

Delgadillo in that Petitioners “expressly directed their contractors . . . to skip

the required steps to meet the regulatory requirements,” as already

discussed, this argument depends on a view of the permitting process as part

of the contracted work. Yet the evidence is clear that it was not.

Johnson urges us to consider the policy implications of allowing Privette

to shield a hirer from liability despite entering into an upfront agreement to

“flout[ ]” the law. We, however, agree with Petitioners that those who enter

into such agreements are held accountable in appropriate ways such that our

decision will not encourage such agreements to proliferate. As Johnson’s

return acknowledges, a person who violates the permit requirements in the

Land Development Code is strictly liable for a misdemeanor under the San

Diego Municipal Code, and can be subjected to fines, custody, injunctive

relief, civil penalties, abatement, and other reasonable mitigation measures.

(See San Diego Mun. Code, §§ 121.0311-121.0312.) As Petitioners noted

during oral argument, this liability applies not only to them, but also to

contractors like Crew and PCF, who have an independent obligation to

comply with the Land Development Code, including its permitting

24

requirements. (See id. §§ 121.0302(b)-(c).) The record evidence is also

undisputed that, should the city determine Petitioners were engaging in

unpermitted work, the city could stop the work and require Petitioners to

take on the time and expense of going through the permitting process,

anyway.

In short, the evidence establishes that (1) obtaining permits for the

project was never part of the work entrusted to Crew or PCF and (2) the

removal of the permitting process from the scope of work did not impact the

manner in which contractors performed their contracted work or provided for

their own safety. Accordingly, no triable issue of fact giving rise to the

retained control exception remains. The Privette doctrine applies as a matter

of law, and Petitioners presumptively delegated any “injury-prevention tort

duty” they owed Johnson. (See Sandoval, supra, 12 Cal.5th at p. 281.)

Under these circumstances, a jury trial to determine whether and the extent

to which permits may have prevented Johnson’s injuries is unwarranted. (Id.

at pp. 282-283.)

25

III.

Let a writ of mandate issue directing the respondent superior court to

vacate its order denying PRI’s and CBRE’s motion for summary judgment

and enter a new order granting the motion. Costs are awarded to PRI and

CBRE.

CASTILLO, J.

I CONCUR:

O’ROURKE, Acting P. J.

26

KELETY, J., Dissenting.

A jury should decide whether Property Reserve, Inc. (PRI) and CBRE

(collectively, Petitioners) retained control over a construction project when

they instructed their general contractor, Crew Builders (Crew), not to obtain

legally necessary permits; and, whether that instruction contributed to the

injuries sustained by Jake Johnson while working as an electrician for a

subcontractor, PCF Electric (PCF), hired by Crew. For this reason, I dissent

from the majority opinion.

As the majority correctly states, when reviewing the trial court’s ruling

on a motion for summary judgment, “we examine the record de novo, liberally

construing the evidence in support of the party opposing summary judgment

and resolving doubts concerning the evidence in favor of that party.” (Miller

v. Department of Corrections (2005) 36 Cal.4th 446, 460.) To survive the

motion and proceed to trial, Johnson need only provide evidence

demonstrating a triable issue of material fact. In my view, he did so here. In

reaching the opposite conclusion and directing the trial court to enter

summary judgment in favor of Petitioners, the majority overlooks important

evidence that supports Johnson’s position.

From the outset, the majority characterizes the decision to proceed

without permits as a mutual agreement between Petitioners and Crew. The

majority then concludes, based at least in part on this characterization, that

“the permitting process was never within the scope of the contracted work.”

(Maj. opn., ante, at p. 2.) However, when viewed in a light most favorable to

Johnson, the evidence supports a conclusion that there was no such

agreement, and, further, but for CBRE’s instruction, the permitting would

have been within the scope of the work.

First, as to the existence of some kind of “agreement” between the

parties, when asked at oral argument, counsel for Petitioners conceded that

“Petitioners made the decision not to obtain permits” and instructed Crew not

to pursue the permit process. Johnson presented evidence confirming that

concession. Crew employee Courtney Ciurej testified that it was typical for

CBRE to make the decision whether or not to seek permits, and in this case,

they decided not to, to save time and money. Crew had other projects with

Petitioners, including projects underway in the same building, and this was

the regular course of dealing between CBRE and Crew. CBRE acknowledged

that if the contractors were “caught” without the required permits, CBRE and

PRI would accept responsibility for any fines or delays resulting from CBRE’s

instruction to the contractors to forego the permit process, showing that they

understood the ramifications of that decision.

Second, it is my view that the obligation to obtain permits would have

been included within the scope of the contracted work in the absence of

CBRE’s instruction to forego them. In their motion for summary judgment,

Petitioners and their expert emphasized that they could not be responsible

for any injuries resulting from the lack of permits because the underlying

contract required Crew and PCF to obtain all necessary permits. It is true

that the written contract included the permitting requirement, but the

contract was not executed until after the contractors had been hired, after the

work had begun without permits, and after Johnson had been electrocuted;

and, the contract made no reference to CBRE’s instruction to the contractors

to forego the permitting process. Under the circumstances, it is hard to see

the final contract as anything more than post hoc window dressing.

Nonetheless, the inclusion of a permitting requirement in the final contract

2

contradicts the majority’s conclusion that the legally required permits were

somehow outside the scope of the contracted work.

Nor is it apparent that CBRE’s instruction to forego the requisite

permitting had no impact on the contractor’s performance of the work.

Johnson alleged that by choosing to disregard the mandatory permitting

process, Petitioners saved approximately $30,000, primarily by avoiding

inspections and the need for engineering or “as-built” drawings of the existing

electrical structure. Had those drawing been done, they would have shown

changes to circuitry and could have helped identify any unexpected

underlying conditions. Petitioners did not truly dispute these allegations.

Rather, they again attempt to place the blame on Crew, stating that they

“contractually obligated Crew [ ] and Crew [ ] contractually obligated PCF [ ] to

obtain whatever permits were required by law to do the work.” At a

minimum, there is a disputed issue of fact regarding the impact of

Petitioners’ direction not to obtain the requisite permits.

Beyond that, I reject the notion that simply deciding and instructing

that the project proceed without permits was all that PRI and CBRE needed

to do to remove the permitting process from the scope of work, thereby

absolving themselves of any related liability. By endorsing that notion, the

majority opinion essentially leaves building owners and property managers

like PRI and CBRE free to dictate whether obtaining a legally required

permit is within the scope of work for any given contract. This cannot be the

case. The parties and the majority agree that the contracted work required a

permit. It was not a choice that the parties could simply decide to exclude. It

was a legally required step in completing the contracted work, the purpose of

which is to “ensure projects comply with the minimum standards that help

3

safeguard life or limb, public health, property and welfare.”1 Petitioners do

not dispute this.

For the same reasons, I also disagree with the majority’s conclusion

that we need not consider the policy implication of allowing Privette2 to

shield a hirer from liability in this circumstance simply because the hirer

may still be liable for a misdemeanor under the San Diego Municipal Code.

(Maj. opn., ante, at p. 24.) As noted above, CBRE had willingly agreed to

accept responsibility for consequences if the contractors were “caught”

without permits, so it is clear that any remedy associated with such an

infraction does little to assist workers like Johnson who are injured because

of such decisions. The policy considerations behind the Privette doctrine

include fairly spreading the risk created by a contractor’s work and

encouraging workplace safety. (SeaBright Ins. Co. v. US Airways, Inc. (2011)

52 Cal.4th 590, 599.) Allowing hirers to shield themselves from liability by

“entering into an upfront agreement to ‘flout[ ]’ the law” at the expense of

workers serves neither of these purposes. (Maj. opn., ante, at p. 24.)

Petitioners did not simply fail to comply with their own statutory and

regulatory duties; they affirmatively directed the contractors to comply with

their decision. (Cf. Gonzalez v. Mathis (2021) 12 Cal.5th 29, 47−48.) Counsel

for Petitioners conceded this point at oral argument, agreeing that

Petitioners “[took] away something the contractor ordinarily would be

delegated to do,” and, in fact, was legally obligated to do. Thus, in my view,

Johnson has presented evidence from which a reasonable trier of fact could

1 City of San Diego, Developmental Services, Electrical Permit,

<sandiego.gov/development-services/permits/electrical-permit> [as of June 4,

2024], archived at <https://perma.cc/ D5PL-UZZU>.)

2 Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette).

4

conclude that Petitioners made a unilateral decision to proceed without

permits and, by affirmatively directing Crew and the other contractors to do

the same, Petitioners “exercised the control that was retained in a manner

that affirmatively contributed to [Johnson’s] injury.” (Hooker v. Department

of Transportation (2002) 27 Cal.4th 198, 210; see also Sandoval v. Qualcomm

Incorporated (2021) 12 Cal.5th 256, 277 [hirer’s affirmative exercise of

retained control satisfies the affirmative contribution requirement when the

hirer prohibits the contractor from taking safety measures that might have

prevented the injury].)

The majority suggests that Crew was complicit in Petitioners’ decision

as they were “free to walk away from the project” or insist that permits be

obtained if they did not agree. (Maj. opn., ante, at p. 17.) Perhaps they

should have. They too had a legal obligation not to work on the project

without first obtaining a permit.

Regardless, though, the fact that neither Crew nor PCF refused to

proceed without a permit is not relevant in determining whether the retained

control exception to Privette applies. In virtually every case where courts

have applied the retained control exception, the contractors made the choice

not to walk away. The contractor in Tverberg could have refused to continue

work until the nearby holes were covered (Tverberg v. Fillner Const., Inc.

(2012) 202 Cal.App.4th 1439, 1443); the contractor in Ray could have refused

to continue work on the bridge without authority to close nearby roadways or,

alternatively, could have precluded its workers from leaving the area over

which they did have some control (Ray v. Silverado Constructors (2002) 98

Cal.App.4th 1120, 1132−1133); the contractor in Browne could have refused

to continue work after the hirer removed the hydraulic lifts and fall

protection system (Browne v. Turner Construction Co. (2005) 127 Cal.App.4th

5

1334, 1337−1339); and the contractor in McKown could have refused to allow

its workers to use Wal-Mart’s forklifts (McKown v. Wal-Mart Stores, Inc.

(2002) 27 Cal.4th 219, 225 (McKown)). The contractor’s failure to do so was

not dispositive in those cases and it should not be dispositive here.

Indeed, in McKown, the California Supreme Court expressly

acknowledged that the choice was not so simple for a contractor—much like

Crew in this case—that had several open contracts with one of the world’s

largest retailers. (See McKown, supra, 27 Cal.4th at p. 225.) Refusing to use

Wal-Mart’s forklifts would have delayed the work and incurred additional

costs, such that the contractor “may well have believed that refusal to [do

what Wal-Mart asked] would have generated ill will.” (Id. at p. 226.)

Likewise, here, there is ample evidence that CBRE and PRI wanted to forego

the permitting process to save time and money. Refusing to comply with

CBRE’s instruction to skip the permitting process may have cost Crew the

project, and jeopardized other projects that it was working on within the

same building. In my view, the entirety of the responsibility for that choice

should not fall on Crew, PCF, or Johnson, just as it did not fall on the

contractor in these other cases.

Finally, the majority suggests that Johnson could have prevented his

own injury by using his hot stick or meter to test the wire that ultimately

caused his injuries. But the standard for determining liability in this context

is also not simply who had the last opportunity to avoid the accident. Rather,

absent summary judgment, a jury would be entitled to allocate fault across

all relevant parties. (See McKown, supra, 27 Cal.4th at p. 223 [“A jury found

that Wal-Mart was negligent in providing unsafe equipment and allocated 55

percent of the responsibility for the accident to [the] employer, 23 percent to

Wal-Mart, 15 percent to the manufacturer . . . and 7 percent to McKown”].)

6

Here, as in McKown, there is a triable issue of fact regarding the extent

to which Petitioners and others contributed to Johnson’s injury. Johnson

presented evidence that PCF had conducted thorough circuit tracing, that he

believed he was working solely on a 120-volt circuit that was powered down

at the time of the incident, and that he therefore had no reason to test the

wire that ultimately caused his injuries. Construing the evidence in a light

most favorable to him, as we must in the context of a motion for summary

judgment, it is plausible that a jury could find that the rogue wire would have

been identified during the permitting process, had it occurred, but that, in

the absence of updated circuit maps or line drawings, it was reasonable for

Johnson to believe that the lines he was working on at the time of the injury

were solely tied to the 120-volt powered-down circuitry.

Craig Overway, the person most knowledgeable for PCF, testified that

PCF had tested every circuit in the suite to determine whether it was 120-

volt or 277-volt. On the day of the incident, Johnson was asked to work on

120-volt lines as they related to drop down furniture outlets and a TV outlet.

He knew the 277-volt system was powered on because of the need for

overhead lighting, but understood that the powered-down 120-volt system he

was working on was separate and apart from the powered-on 277-volt

system. Petitioners’ expert, Loud, confirmed that outlets near the area where

Johnson was working were powered by the 120-volt circuit in the junction box

at issue. Danny Machado from Crew explained that it was okay to have the

lights on—and okay to re-energize the 277-volt circuit—“[i]f you’re working

on a box that has nothing to do with lighting.” That is precisely what

Johnson believed he was doing.

Unfortunately, though, there was a live 277-volt wire in the junction

box at issue. Overway testified it was “definitely not right” to have 277- and

7

120-volt wires in the same junction box; there should have at least been a

divider at a minimum; and the presence of the 277-volt wire was a dangerous

condition. Ryan Netherton, the person most knowledgeable for Crew,

testified that it was at least possible that the wire was part of a rogue circuit

that had originated from somewhere else, perhaps another suite. Overway

and Machado explained that typically, one would create as-built drawings for

a project, and that those drawings would show any changes to the circuitry,

or other underlying conditions that did not match the original building plan.

But Overway had never seen any as-built drawings for any of the work he

had done in the building. Such drawings would have been created as part of

the permitting process.

San Diego Municipal Code section 129.0307, subdivision (e) specifies

that, to obtain a permit, the request must include plans that “show a single

line diagram of service, feeders, conduit, and wire sizes.” Thus, it is

reasonable to conclude that by directing that the project proceed without

permits, Petitioners removed the need, and the associated expense and time,

of creating the requisite “as-built” line drawings. If they had instead allowed

Crew to undertake the steps necessary to obtain a permit, the 277-volt line

that injured Johnson may well have been identified during that process.

Even short of identifying that specific wire, if PCF had at least been aware

that there was an overlapping 277-volt circuit (perhaps originating from a

neighboring unit) in the area where Johnson was working, they may have

required additional precautions. These are questions for a jury to consider.

8

For these reasons, I believe that Johnson has raised triable issues of

fact as to whether Petitioners retained control over the contracted work by

directing Crew to forego the permitting process; and, as to whether that

direction affirmatively contributed to Johnson’s injury. I would deny the

petition.

KELETY, J.

9