Opinion

Colony Construction

Court
Armed Services Board of Contract Appeals
Filed
Nov 22, 2023
Status
Published
Cited by
0 cases
Authority
More cited than 14.5%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

Colony Construction ) ASBCA No. 63630

)

Under Contract No. W912WJ-22-P-0131 )

APPEARANCE FOR THE APPELLANT: Mr. Jay Harris

President

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Theresa A. Negron, Esq.

Engineer Trial Attorney

U.S. Army Engineer District, New England

OPINION BY ADMINISTRATIVE JUDGE SMITH

ON THE GOVERNMENT’S MOTION TO DISMISS

The U.S. Army Corps of Engineers (USACE or respondent) has moved to

dismiss this appeal for failure to state a claim upon which relief can be granted or, in

the alternative, for a more definite statement under Board Rule 6. We deny the motion

because the appellant states a claim upon which relief can be granted, namely to vacate

respondent’s termination for default. Per Rule 6, appellant’s submissions also contain

sufficient information to proceed past the pleading phase – especially where

respondent will have the initial burden of proof to justify its default termination.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

Appellant Colony Construction (Colony) was awarded a $156,000 contract to

upgrade a campground electrical system (R4, tab 3). After several preconstruction

exchanges between the parties, and no work in the field, USACE became dissatisfied

with Colony’s submittals and issued a cure notice and a show cause notice, to which

Colony responded (R4, tabs 18-19, 21-22, 24-26). Considering those responses

insufficient, USACE terminated Colony’s contract for default (R4, tab 2). Proceeding

pro se, Colony challenges the default termination here. In addition to its

contemporaneous communications with USACE, Colony has made submissions to the

Board that contain contentions that challenge specific aspects of USACE’s termination

decision and seeks conversion of the termination from default to convenience.

DECISION

Our rules are prefaced upon informal, expeditious, and inexpensive resolution

of disputes and Rule 15 allows appellants to proceed without counsel. Here, Colony is

proceeding pro se, its submissions are informal, and some have been untimely. But

we do not penalize contractor-appellants who are inexperienced in Board litigation or

unfamiliar with forms of pleadings and other submissions. Elizabeth Constr. Co.,

ASBCA No. 60723, 17-1 BCA ¶ 36,839 at 179,519 (citing Haines v. Kerner, 404 U.S.

519, 520 (1972)).

Looking at the sum of Colony’s submissions and drawing reasonable inferences

in Colony’s favor, we readily discern Colony’s claim which it succinctly states as

follows. “Colony Construction claims that the Corps has wrongly terminated contract

#W912WJ-22P-0131 for ‘default’ and not ‘convenience.’ We pray that the Board will

change the designation accordingly. Colony is asking for no monetary damages” (app.

resp. at 1). This is a vintage claim upon which relief can be granted. Kellogg Brown

& Root Services, Inc. v. United States, 728 F.3d 1348, 1365 (Fed. Cir. 2013).

Respondent’s motion to dismiss is denied.

USACE’s request for a more definite Complaint because “. . . it is difficult to

determine from the Complaint what Colony may be attempting to plead” (gov’t mot.

at 3), is similarly unconvincing. USACE bears the initial burden to justify its default

termination and has already provided an explanation in the termination notice/final

decision (R4, tab 2). Johnson Mgmt. Grp. CFC, Inc. v. Martinez, 308 F.3d 1245,

1249 (Fed. Cir. 2002). (“The government bears the burden of proof in establishing the

validity of a default termination”). USACE has also submitted a 164-page Rule 4 file

which contains 26 documents showing the events that lead to the termination.

In response, Colony’s contemporaneous documents and its submissions here

make contentions regarding the timeliness of its submittal documents and USACE’s

responses or lack thereof (R4, tabs 22, 25-26). This includes Colony’s specific

allegation that it sent substantially more submittal documents than USACE has

acknowledged (compl. ¶ 13).

Considering USACE’s burden of proof, the Rule 4 record, and Colony’s

submissions, we conclude that the issues before the Board are sufficiently defined per

Rule 6. This appeal is a garden-variety default termination challenge by a pro se

contractor-appellant. USACE should be equipped to move forward in the proceedings

and attempt to justify its termination decision, to which Colony will have an

opportunity to respond.

2

CONCLUSION

Respondent’s motion is denied. Our September 26, 2023, suspension is lifted

and the response to appellant’s complaint is due within 30 days of receipt of this

decision. *

Dated: November 22, 2023

BRIAN S. SMITH

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 63630, Appeal of Colony

Construction, rendered in conformance with the Board’s Charter.

Dated: November 22, 2023

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

*

We note that our rules provide for expedited resolution of uncomplicated or

small-dollar appeals, which the parties should consider.

3

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.