“The focus of this requirement [appeal rights] is the protection of the contractor. When the contractor’s determination regarding appeal is unaffected by the defect, the notice does not fail in its protective purpose.”
How later courts described this case
- “The focus of this requirement [appeal rights] is the protection of the contractor. When the contractor’s determination regarding appeal is unaffected by the defect, the notice does not fail in its protective purpose.”
- A communication from a contracting officer can constitute a valid final decision even if it does not contain the boilerplate language.
- The amount claimed must be “readily ascertainable to the party against whom the claim was made.”
- “A letter can be a final decision under the CDA even if it lacks the standard language announcing that it constitutes a final decision.”
Written by the judges who cited it.
The opinion
ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
PAE Applied Technologies LLC ) ASBCA No. 63233
)
Under Contract No. N66604-05-C-1277 )
APPEARANCES FOR THE APPELLANT: Nicole J. Owren-Wiest, Esq.
Erin N. Rankin, Esq.
Catherine O. Shames, Esq.
Crowell & Moring LLP
Washington DC
APPEARANCES FOR THE GOVERNMENT: Craig D. Jensen, Esq.
Navy Chief Trial Attorney
Philip Hadji, Esq.
Trial Attorney
OPINION BY ADMINISTRATIVE JUDGE TAYLOR
In this appeal, we face the interesting question of the Respondent, the
United States Department of the Navy (Navy or the government), moving to dismiss
the appeal due to lack of subject matter jurisdiction asserting its own demand letter
was not a contracting officer’s final decision (COFD) under the Contract Disputes Act
(CDA). The Navy’s demand letter sought the repayment of a specified amount
previously paid appellant for allegedly COVID-related costs (R4, tab 396). The Navy
contends it issued that demand letter merely to invite PAE Applied Technologies LLC
(appellant or PAE) to comment on its refusal to adequately substantiate the COVID-
related costs and did not intend it to be a COFD (gov’t mot. at 1). For the reasons
discussed below, we deny the Navy’s motion to dismiss and conclude the
government’s March 2, 2022, letter demanding payment from PAE is a government
claim and final decision under the CDA.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION
On January 28, 2005, PAE and the Navy executed cost reimbursement Contract
No. N66604-05-C-1277 (the contract) for PAE to provide maintenance and operations
at the Atlantic Undersea Test & Evaluation Center (AUTEC) (R4, tab 1 at 1, 92). The
contract incorporates by reference FAR 52.216-7, ALLOWABLE COST AND
PAYMENT (DEC 2002) and FAR 52.233-1, DISPUTES (JUL 2002) (id. at 27-28).
FAR 52.233-1 defines a claim, in part, as:
(c) “Claim,” as used in this clause, means a written
demand or written assertion by one of the contracting
parties seeking, as a matter of right, the payment of money
in a sum certain, the adjustment or interpretation of
contract terms, or other relief arising under or relating to
this contract.
FAR 52.233-1, DISPUTES (JUL 2002).
Beginning in March 2021, the Navy and PAE exchanged correspondence
relating to the applicability of the Coronavirus Aid, Relief, and Economic Security Act
(CARES Act) to the contract, the purported fees charged on COVID-related costs, and
the allowability of such costs under the contract (compl. ¶¶ 48-56; app. supp. R4,
tabs 432-33, 443, 445-46).
On March 2, 2022, Ms. Tracy Hamilton, the contracting officer, sent a letter
entitled “DEMAND FOR PAYMENT FOR UNALLOWABLE COVID COSTS” to
PAE (R4, tab 396). The demand letter indicated the government had determined PAE
invoiced, and the government had paid, unallowable COVID costs on the contract (id.
at 7163). The letter further stated, “the Government demands reimbursement of the
funds in the amount of $4,302,782.81 plus applicable indirect rates plus two percent
(2%) fee” (id.). The letter proceeded to break down the unallowable COVID charges
paid to date per contract price line item and sub-line item (id. at 7163-65). The letter
indicated interest would accrue on any amount not paid within 30 days of the demand
for payment (id. at 7165-66). Ms. Hamilton also advised PAE to contact her in writing
if it believed the debt was invalid or the amount was incorrect (id. at 7166). Finally,
the letter stated the payment office could initiate procedures to offset the debt against
any payments otherwise due PAE, and PAE could submit a request for installment
payments or deferment of collection if immediate payment was not practicable or if
PAE disputed the amount (id.). Ms. Hamilton’s letter did not state it was a COFD and
did not include a notice of appeal rights.
On March 29, 2022, PAE appealed Ms. Hamilton’s demand letter to the Board.
On May 5, 2023, more than one year after PAE filed its appeal, Ms. Hamilton
withdrew her demand letter (app. opp’n ex. 1). The contracting officer, however, in
her Declaration attached as an exhibit to the government’s motion, indicates she still
intends to pursue the Navy’s questions about these costs and has initiated an audit with
the Defense Contract Audit Agency (gov’t mot. ex. A ¶ 14). The Navy filed a motion
to dismiss the appeal for lack of jurisdiction on May 22, 2023.1
1
We note the Navy has not moved to dismiss this appeal due to the contracting
officer’s withdrawal of the COFD. As previously noted in the Board’s May 8,
2023, Order, “When a contracting officer unequivocally rescinds a government
2
DECISION
The Navy moves to dismiss PAE’s appeal for lack of subject matter jurisdiction
asserting the government’s March 2, 2022, demand letter: (1) is not labeled as a
COFD; (2) does not include the mandatory CDA appeal language; (3) does not
demand a sum certain dollar amount; and (4) does not make an unequivocal demand
(gov’t mot. at 1-2).
I. Standard of Review
When considering a motion to dismiss for lack of subject matter jurisdiction,
the Board accepts only uncontroverted allegations as true for purposes of the motion,
and “other facts underlying the jurisdictional allegations are subject to fact-finding.”
L-3 Commc’ns Integrated Sys., LP, ASBCA Nos. 60713, 60716, 17-1 BCA ¶ 36,865
at 179,625; see also Cedars-Sinai Medical Center v. Watkins, 11 F.3d 1573, 1583-84
(Fed. Cir. 1993). The Board relies on the record for fact-finding when evaluating the
facts supporting jurisdiction. Kellogg Brown & Root Servs., Inc., ASBCA No. 62681
et al., 22-1 BCA ¶ 37,974 at 184,426.
The CDA grants the Board jurisdiction over appeals from decisions of
contracting officers. See 41 U.S.C. § 7105(e)(1)(A). A contracting officer’s decision
asserting a government monetary claim must be both a valid claim and a contracting
officer’s final decision on that claim. M. Maropakis Carpentry, Inc. v. United States,
609 F.3d 1323, 1327 (Fed. Cir. 2010); L-3 Commc’ns Integrated Sys., LP, 17-1 BCA
¶ 36,865 at 179,625 (“Pursuant to the CDA, for a government claim, this Board’s
jurisdiction is dependent on a contracting officer asserting a claim in the form of a
contracting officer’s final decision issued to the contractor.”). The Federal Circuit has
also held a claim must be submitted in writing and contain a “clear and unequivocal
statement that gives . . . adequate notice of the basis and amount of the claim.”
Cont. Cleaning Maint., Inc. v. United States, 811 F.2d 586, 592 (Fed. Cir. 1987). “The
Board treats a determination regarding the adequacy of a claim to be jurisdictional.”
L-3 Commc’ns Integrated Sys., LP, 17-1 BCA ¶ 36,865 at 179,625.
claim, the government’s action moots the appeal, leaving the Board without
jurisdiction to entertain the appeal further.” Bd. Order, May 22, 2023 (citing
Scot Cardillo d.b.a. Eng’rs Tooling Support, ASBCA No. 62501, 22-1 BCA
¶ 38,153 at 185,297). Here, the contracting officer has expressed an intention
to continue to question these costs despite the withdrawal of her demand letter
(gov’t mot. ex. A ¶ 14).
3
II. The Navy’s March 2, 2022, Demand Letter Asserts A Valid Claim And
Final Decision
Since the CDA does not define the term “claim”, we look to the FAR definition
of a claim incorporated into the contract through the disputes clause. See K-Con Bldg.
Sys. v. United States, 778 F.3d 1000, 1005 (Fed. Cir. 2015); Kellogg Brown & Root
Servs., Inc., 22-1 BCA ¶ 37,974 at 184,427. The contract defines the term “claim”, in
part, as “a written demand ... by one of the contracting parties seeking as a matter of
right, the payment of money in a sum certain....” (R4, tab 1 at 28) (citing by reference
FAR 52.233-1, DISPUTES (JUL 2002)). As such, a monetary claim must “adequately
specify both the amount sought and the bases for the request.” Kellogg Brown & Root
Servs., Inc., 22-1 BCA ¶ 37,974 at 184,427 (citing K-Con Bldg. Sys. Inc., 778 F.3d at
1005). Moreover, “[T]he statement of claim must provide a basis for meaningful
dialogue between the parties aimed toward settlement or negotiated resolution of the
claim if possible, or for adequate identification of the issues to facilitate litigation
should that be necessary following issuance of the decision.” Blake Constr. Co.,
ASBCA No. 34480 et al., 88-2 BCA ¶ 20,552 at 103,890.
In this case, the Navy’s March 2, 2022, demand letter indicates it seeks the
return of certain unallowable “non-productive COVID costs” the government
previously paid the appellant and demands “reimbursement of the funds in the amount
of $4,302,782.81 plus applicable indirect rates plus two percent (2%) fee” (R4, tab 396
at 7163). Furthermore, the letter indicates “any amounts not paid within 30 days from
the date of this demand for payment will bear interest” (id. at 7165). The government’s
letter provides adequate notice that the government’s claim is for the return of
previously reimbursed unallowable COVID costs and specifies a specific dollar
amount. L-3 Commc’ns Integrated Sys., LP, 17-1 BCA ¶ 36,865 at 179,625-26
(government final decisions provided adequate notice of both the basis and amount of
the claims). We find the Navy’s March 2, 2022, demand letter is a valid claim and
COFD under the CDA.
The Navy contends it issued the March 2, 2022, demand letter “to invite PAE to
comment on its refusal to adequately substantiate COVID-related costs” and not as a
final decision (gov’t mot. at 1). In support of its contention, the Navy first argues the
letter does not state that it is a COFD as required by 41 U.S.C. ¶ 7103(a)(3) (id. at 9).
A contracting officer’s demand letter, however, does not need to be labeled as a final
decision to be a CDA claim. Alliant Techsystems, Inc. v. United States, 178 F.3d
1260, 1267 (Fed. Cir. 1999) (“A letter can be a final decision under the CDA even if it
lacks the standard language announcing that it constitutes a final decision.”). The
CDA requires, “[E]ach claim by the Federal Government against a contractor relating
to a contract shall be the subject of a written decision by the contracting officer.”
41 U.S.C. ¶ 7103(a)(3). The CDA does not state a claim must say it is a COFD.
4
In our recent Kellogg Brown & Root Services, Inc., decision, we found the
contracting officer’s demand letters demanding liquidated damages and the repayment
of provisional accelerated payments to be final decisions on government claims even
though the demand letters were not labeled as final decisions. Kellogg Brown & Root
Servs., Inc., 22-1 BCA ¶ 37,974 at 184,428; see also Placeway Constr. Corp. v.
United States, 920 F.2d 903, 907 (Fed. Cir. 1990) (A communication from a
contracting officer can constitute a valid final decision even if it does not contain the
boilerplate language.). We find the March 2, 2022, demand letter is a claim under the
CDA even though it is not labeled as a COFD.
The Navy next contends the March 2, 2022, demand letter is not a valid COFD
because it does not include the mandatory contractor appeal language (gov’t mot. at 9).
Appellant, in its response to the government’s motion, correctly notes the Federal
Circuit and this Board have long held that a contracting officer’s omission of appeal
rights or other FAR part 33 requirements in a final decision only affects CDA
jurisdiction if the omission prejudices the contractor (app. opp’n at 15-16); see, e.g.
Decker & Co. v. West, 76 F.3d 1573, 1579-80 (Fed. Cir. 1996) (“The focus of this
requirement [appeal rights] is the protection of the contractor. When the contractor’s
determination regarding appeal is unaffected by the defect, the notice does not fail in
its protective purpose.”); Kellogg Brown & Root Servs., Inc., 22-1 BCA ¶ 37,974
at 184,429 (valid final decisions despite omission of appeal rights). In this case, PAE
has clearly not been harmed by the Navy’s failure to include the appeal rights in the
government’s demand letter since it did, in fact, timely appeal that demand.
The Navy also argues the March 2, 2022, demand letter is not a valid COFD
because it fails to state a “sum certain” amount (gov’t mot. at 10-12). The Navy
contends the $4,302,782.81 demanded in the contracting officer’s letter is qualified by
the statements “plus applicable indirect rates” and “plus applicable burdens” included
in the letter (id. at 10) (citing R4, tab 396 at 7163). The Navy is mistaken.
The government’s March 2, 2022, letter demands “reimbursement of the funds
in the amount of $4,302,782.81 plus applicable indirect rates plus two percent (2%)
fee” (R4, tab 396 at 7163). The demand letter further breaks down the alleged
unallowable COVID charges paid to date to PAE per contract price line item and
sub-line item (id. at 7163-65). Appellant notes the government’s claim seeks the
repayment of previously paid amounts and asserts the government should know the
amount it previously paid appellant for these costs (app. opp’n at 14 n.9).
In her declaration, attached as an exhibit to the government’s motion, the
contracting officer stated, “I essentially demanded that PAE simply pay-back all the
amounts it had invoiced (and been paid) for all contract line items (“CLINS”) and
sub-line items (“SLINs”) that appeared to include unsubstantiated COVID-19 costs”
(gov’t mot. ex. A ¶ 9). The government contracting officer further asserted she was
5
unable to ascertain whether that was the correct amount because she did not know
whether PAE applied the proper indirect fringe rates to the disallowed billed COVID
costs because PAE did not provide her with sufficient information allowing her to
determine whether the correct indirect rates had been applied (id. at ¶ 7). The
government asserts that the contracting officer had “to lump together various labor
costs that should not be grouped together for purposes of calculating indirect rates or
applicable burdens” (gov’t mot. at 11).
Appellant correctly notes that whether PAE applied the correct indirect rates to
the disallowed costs goes to the ultimate determination of whether those costs are
allowable but does not impact whether the government’s claim included a sum certain
for the Board’s jurisdiction (app. opp’n at 14). See L-3 Commc’ns Integrated Sys., LP,
17-1 BCA ¶ 36,865 at 179,626 (motion to dismiss denied even though contracting
officer did not provide detailed information showing the basis for the disallowed costs
since the final decision provided adequate notice for the basis of the claim and a sum
certain.) As such, the contracting officer’s lack of knowledge concerning the correct
applicable indirect rates does not deprive the Board of jurisdiction over this appeal.
The government further contends the government’s demand letter does not meet
the sum certain requirement since one cannot calculate the total amount from a
“simple mathematical calculation” or from any supporting documentation (gov’t mot.
at 11). The government is incorrect. As discussed above, the sum certain amount the
government requested in its demand letter is the amount the government previously
reimbursed PAE for the alleged COVID costs. (Id. at ex. A ¶ 9). The additional
language concerning applicable indirect rates and fee does not change the demanded
sum certain amount.
Moreover, the FAR’s sum certain requirement is intended to give adequate
notice of the claim amount to the other party. Creative Mgmt. Servs. LLC v. United
States, 989 F.3d 955, 963 (Fed. Cir. 2021) (The amount claimed must be “readily
ascertainable to the party against whom the claim was made.”). Here, PAE knows the
government’s claim amount – the amount the government claims it previously paid
PAE for the alleged COVID related costs. In addition, PAE should be able to apply its
own indirect rates to the underlying costs and then add the applicable 2% fee amount
to arrive at the correct payment amount (app. opp’n at 12). The government, too, can
calculate this amount, so both parties were in a position to know exactly what the
government was demanding of PAE. Of course, PAE will have to establish the correct
payment amount for these costs during this appeal.
Finally, the Board has previously rejected the notion that the requisite sum
certain cannot be subject to any qualifications. Ball Aerospace & Techs. Corp.,
ASBCA No. 57558, 11-2 BCA ¶ 34,804 at 171,275 (government’s argument that sum
certain requirement cannot be subject to any qualifications is “an overstatement of the
6
Board’s precedent”). We find the government’s demand letter asserts a sum certain
amount. 2
Finally, the Navy contends the government’s March 2, 2022, demand letter is
not a COFD since the contracting officer did not intend the letter to be a COFD, the
letter advised PAE to contact the contracting officer if it believed the debt or the
amount were incorrect, and the letter indicated PAE could submit a request for
installment payments or deferment of collection (gov’t mot. at 12-15). In support of
its position, the Navy relies heavily on the Federal Circuit’s decision in Sharman Co.
v. United States, 2 F.3d 1564 (Fed. Cir. 1993), overruled in part by Reflectone, Inc. v.
Dalton, 60 F.3d 1572 (Fed. Cir. 1995). 3 In Sharman, the Federal Circuit held the facts
in that case did not demonstrate that the demand letter at issue was a final decision.
Sharman Co., 2 F.3d at 1571. The Federal Circuit’s decision in Sharman rested, in
part, on its finding that the amount the contracting officer demanded was not yet in
dispute at the time he issued his demand (id.).
Appellant responds that the Federal Circuit specifically overruled the Sharman
decision in Reflectone (app. opp’n at 18) (citing Reflectone, 60 F.3d at 1579, n.10). In
Reflectone, the Federal Circuit overruled its prior opinions, including Sharman, that a
claim had to be in dispute at the time it was submitted to the contracting officer for
CDA jurisdiction to attach. Reflectone, 60 F.3d at 1579. The government does not
dispute Reflectone overruled that portion of Sharman finding a claim had to be in
dispute at the time it was submitted to the contracting officer (gov’t reply at 10). The
government, however, asserts Sharman is still good law with regards to its finding that
the contracting officer’s demand letter was not a final decision since it identified itself
as a “notice and demand for payment” rather than being labeled as a final decision and
2
In its opposition, appellant requests a limited stay based upon the Federal Circuit’s
pending decision in ECC International Constructors, LLC v. Secretary of the
Army as an alternative if the Board found the Navy’s claim did not meet the
FAR’s sum certain requirement (app. opp’n at 20-22). The Federal Circuit
issued its decision on that case on August 22, 2023, finding the CDA sum-
certain requirement is a nonjurisdictional rule. ECC International
Constructors, LLC v. Secretary of the Army, No. 2021-2323 (Fed. Cir. Aug. 22,
2023). Since we find the Navy’s claim meets the sum certain requirement, our
decision is not impacted by the Federal Circuit’s decision.
3
In its initial motion, the Navy also relied upon the Court of Federal Claims decision
in Boeing Co. v. United States, 25 Cl. Ct. 441 (1992), rev’d, 991 F.2d 811 (Fed.
Cir. 1993) (unpublished table decision). In its reply motion, the Navy
acknowledged the Court of Federal Claims decision in Boeing was no longer
good precedent since the Federal Circuit had reversed and vacated that decision
finding the demand letter at issue was final (gov’t reply at 12-13).
7
specifically invited Sharman “to submit a proposal for deferment of collection....”
(Sharman, 2 F.3d at 1570; see also gov’t reply at 11).
We need not determine whether the Federal Circuit would have reached a
different result in Sharman after Reflectone since, as we noted in our recent Kellogg
Brown & Root Services, Inc. decision, the Federal Circuit found the facts in that case
“did not demonstrate that the demand letter was a final decision.” Kellogg Brown &
Root Servs., Inc., 22-1 BCA ¶ 37,974 at 184,429 n.*. Here, the facts are different.
“Whether a communication is a ‘claim’ within the meaning of the CDA is a question
of judgment, which must be exercised on a case-by-case basis as the particular facts
present themselves.” Parsons Evergreene, ASBCA No. 58634, 18-1 BCA ¶ 37,136
at 180,728 (citing Holk Dev., Inc., ASBCA Nos. 40579, 40609, 90-3 BCA ¶ 23,086
at 115,938); see also Cont. Cleaning Maint., Inc., 811 F.2d 586, 592 (Fed. Cir. 1987).
Moreover, “[A] claim need not be submitted in any particular form or use any
particular wording, but it must provide a clear and unequivocal statement that gives the
contracting officer adequate notice of the basis and amount of the claim.” Tolliver
Grp., Inc., 20 F.4th 771, 776 (Fed. Cir. 2021) (quoting K-Con Bldg. Sys., Inc. v. United
States, 778 F.3d 1000, 1005 (Fed. Cir. 2015)). Likewise, the government must make a
“clear and unequivocal statement” giving “adequate notice” of the basis and amount of
its claim. L-3 Commc'ns Integrated Sys., LP, 17-1 BCA ¶ 36,865 at 179,625
(requiring government to provide “clear and unequivocal statement” to meet “adequate
notice” requirement).
To determine whether the government submitted a CDA claim “we apply a
common sense analysis, looking at specific communications on a case-by-case basis
and the ‘totality of previous correspondence between the parties’.” Kellogg Brown &
Root Servs., Inc., 22-1 BCA ¶ 37,974 at 184,427 (quoting Holmes & Narver, Inc.,
ASBCA No. 51430, 99-1 BCA ¶ 30,131 at 149,054); Selevive Group, LC, ASBCA
Nos. 63292, 63293, 22-1 BCA ¶ 38,220 at 185,636. Prior to the Navy’s March 2,
2022, demand, the Navy and PAE exchanged correspondence concerning the
allowability of the alleged COVID costs (compl. ¶¶ 48-56; app. supp. R4, tabs 432,
433, 443, 445-46). Moreover, the contracting officer admits she issued the demand
letter to “break the stalemate that had arisen between me and PAE about the backup
for its COVID-19 costs” (gov’t mot. ex. A ¶ 9). In this case, the Navy’s March 2,
2022, demand for payment was clear and unequivocal that it sought recovery of the
payments previously paid to PAE for the alleged COVID-19 costs. PAE knew both
the basis and amount of the government’s claim. Based on our review of the totality
of the communications between the Navy and PAE, we conclude the March 2, 2022,
demand letter is a final decision.
Finally, the government contends the March 22, 2022, demand letter is not a
valid CDA claim because the contracting officer did not intend it to be a COFD (gov’t
mot. at 9-10) (citing gov’t ex. A ¶¶ 9, 11). A contracting officer’s subjective intent is
8
not controlling as to whether a communication is a final decision. See IBM Corp.,
ASBCA Nos. 28821, 29106, 84-3 BCA ¶ 17,689 at 88,207. Rather, we look to the
“totality of [previous] correspondence between the parties” to determine whether a
CDA claim exists. Kellogg Brown & Root Servs., Inc., 21-1 BCA ¶ 37,974 at 184,427.
As discussed above, we find the parties had reached a “stalemate” regarding the
allowability of these costs resulting in the contracting officer’s issuance of the demand
letter.
CONCLUSION
The Navy’s motion to dismiss is denied.
Dated: August 24, 2023
ARTHUR M. TAYLOR
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
RICHARD SHACKLEFORD J. REID PROUTY
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Opinion and Decision of the
Armed Services Board of Contract Appeals in ASBCA No. 63233, Appeal of PAE
Applied Technologies LLC, rendered in conformance with the Board’s Charter.
Dated: August 24, 2023
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
9