Opinion

NORTHERN IND. PUBLIC SERV. v. US Steel

  • 907 N.E.2d 1012
Court
Indiana Supreme Court
Filed
Jun 23, 2009
Status
Published
On the bench
Shepard
Cited by
0 cases
Authority
More cited than 26.0%

The opinion

ATTORNEYS FOR APPELLANT ATTORNEYS FOR APPELLEE

FILED

Gregory S. Colton John Wickes

Merrillville, Indiana Todd Richardson

Joseph Rompala

Jon Laramore Bette Dodd Jun 23 2009, 1:23 pm

Peter L. Hatton Steven Griesemer

Karl Mulvaney

Elizabeth A. Herriman

Nana Quay-Smith

CLERK

Robert L. Hartley of the supreme court,

court of appeals and

Indianapolis, Indiana Indianapolis, Indiana tax court

ATTORNEYS FOR AMICUS CURIAE STATE OF INDIANA

Gregory F. Zoeller

Attorney General of Indiana

Thomas M. Fisher

Solicitor General of Indiana

Beth Krogel Roads

Indiana Utility Regulatory Commission Counsel

Indianapolis, Indiana

In the

Indiana Supreme Court

No. 93S02-0809-EX-00489

NORTHERN INDIANA PUBLIC SERVICE

COMPANY,

Appellant (Respondent below),

v.

UNITED STATES STEEL CORPORATION

Appellee (Complainant below).

Appeal from the Indiana Utility Regulatory Commission

Cause No. 43204

On Petition to Transfer from the Indiana Court of Appeals, No. 93A02-0706-EX-00467

June 23, 2009

SHEPARD, Chief Justice.

Northern Indiana Public Service Company and its customer U.S. Steel settled a rate and

service dispute in 1999. In this case, U.S. Steel asked the Indiana Utility Regulatory

Commission to interpret the order it issued in 1999 approving a settlement between the parties.

We affirm the Commission.

Facts and Procedural History

Northern Indiana Public Service Company is a public utility that provides electricity to a

steel production facility in Gary, known as the “Gary Works,” operated by United States Steel

Corporation, a large industrial manufacturer of steel products.

In 1999, NIPSCO and U.S. Steel settled a longstanding electric power dispute involving

U.S. Steel’s electric generation and transmission facilities in Illinois. They agreed to the

preliminary terms of the settlement in a Term Sheet in May 1999. A few weeks later, in June

1999, the parties executed six other documents: a Letter Agreement, a Settlement Agreement, a

Contract for Electric Industrial Power Service (“Contract”), an Operation and Control

Agreement/Operation Agreement, a Facility/Property Lease, and an Access/Use License

Agreement. They submitted the Settlement and Contract to the Indiana Utility Regulatory

Commission, which approved it by an order dated July 8, 1999 after notice and an evidentiary

hearing. Six years later, when a price adjustment provision in the Contract became effective, the

parties disagreed on its application. NIPSCO maintained the price adjustment applied both to the

Energy Charge (a fixed number of hours of use each month given by the agreement) and the

Demand Charge (for energy use beyond the number of hours given for the Energy Charge’s

fixed number). U.S. Steel insisted it applied only to the Energy Charge.

2

On November 17, 2006, U.S. Steel filed a complaint seeking to enforce its interpretation

of the Contract. U.S. Steel then filed its motion for summary judgment. After briefing and oral

argument, the Commission granted U.S. Steel’s motion for summary judgment, an unusual

procedure for the Commission, on May 9, 2007, pursuant to 170 Ind. Admin. Code 1-1.1-26(a)

(2007). NIPSCO appealed to the Court of Appeals, which reversed. N. Ind. Pub. Serv. Co. v.

U.S. Steel Corp., 881 N.E.2d 1065 (Ind. Ct. App. 2008). We granted transfer, 898 N.E.2d 1223

(Ind. 2008)(table).

I. Standard of Judicial Review

The General Assembly created the Indiana Utility Regulatory Commission primarily as a

fact-finding body with the technical expertise to administer the regulatory scheme devised by the

legislature. United Rural Elec. Membership Corp. v. Ind. & Mich. Elec. Co., 549 N.E.2d 1019

(Ind. 1990); See Ind. Code § 8-1-1-5 (2008). The Commission’s assignment is to insure that

public utilities provide constant, reliable, and efficient service to the citizens of Indiana. Ind.

Bell Tel. Co. v. Ind. Util. Regulatory Comm’n, 715 N.E.2d 351, 354 n.3 (Ind. 1999). The

Commission can exercise only power conferred upon it by statute. United Rural Elec.

Membership Corp., 549 N.E.2d at 1021.

The Indiana Code authorizes judicial review of Commission orders as follows:

Any person, firm, association, corporation, limited liability

company, city, town, or public utility adversely affected by any

final decision, ruling, or order of the commission may, within

thirty (30) days from the date of entry of such decision, ruling, or

order, appeal to the court of appeals of Indiana for errors of law

under the same terms and conditions as govern appeals in ordinary

civil actions, except as otherwise provided in this chapter and with

the right in the losing party or parties in the court of appeals to

apply to the supreme court for a petition to transfer the cause to

said supreme court as in other cases. An assignment of errors that

the decision, ruling, or order of the commission is contrary to law

3

shall be sufficient to present both the sufficiency of the facts found

to sustain the decision, ruling, or order, and the sufficiency of the

evidence to sustain the finding of facts upon which it was rendered.

Ind. Code § 8-1-3-1 (2008).

This section includes language almost identical to provisions for judicial review of other

administrative agency actions.1 See McClain v. Review Bd. of Ind. Dept. of Workforce Dev.,

693 N.E.2d 1314, 1317 n.1 (Ind. 1998).

This amounts to a multiple tiered review. On the first level, it requires a review of

whether there is substantial evidence in light of the whole record to support the Commission’s

findings of basic fact. Citizens Action Coalition of Ind., Inc. v. N. Ind. Pub. Serv. Co., 485

N.E.2d 610, 612 (Ind. 1985).2 Such determinations of basic fact are reviewed under a substantial

evidence standard, meaning the order will stand unless no substantial evidence supports it.

McClain, 693 N.E.2d at 1317-18. In substantial evidence review, “the appellate court neither

reweighs the evidence nor assesses the credibility of witnesses and considers only the evidence

most favorable to the Board’s findings.” Id. The Commission’s order is conclusive and binding

1

The language referred to is “An assignment of errors that the decision, ruling, or order of the

commission is contrary to law shall be sufficient to present both the sufficiency of the facts found to

sustain the decision, ruling, or order, and the sufficiency of the evidence to sustain the finding of facts

upon which it was rendered.” Ind. Code §§ 3-8-8-6 (Election Commission), 22-3-4-8(d) & 22-3-7-27(f)

(Workers' Compensation Board), 22-4-17-12 (Unemployment Insurance Review Board), 23-2-3.1-11

(Securities Commissioner) (2008). The Indiana Administrative Orders and Procedures Act, which does

not apply to the IURC, lays out a similar standard of review: “The court shall grant relief . . . only if it

determines that a person seeking judicial relief has been prejudiced by an agency action that is: (1)

arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law; (2) contrary to

constitutional right, power, privilege, or immunity; (3) in excess of statutory jurisdiction, authority, or

limitations, or short of statutory right; (4) without observance of procedure required by law; or (5)

unsupported by substantial evidence.” Ind. Code § 4-21.5-5-14(d) (2008).

2

The decision in Citizens Action Coalition, 485 N.E.2d at 612-13, addressed these levels following the

order of the statute, but we begin today with review of findings of fact and proceed to review of ultimate

conclusions, as we did in McClain, 693 N.E.2d at 1317.

4

unless (1) the evidence on which the Commission based its findings was devoid of probative

value; (2) the quantum of legitimate evidence was so proportionately meager as to lead to the

conviction that the finding does not rest upon a rational basis; (3) the result of the hearing before

the Commission was substantially influenced by improper considerations; (4) there was not

substantial evidence supporting the findings of the Commission; (5) the order of the

Commission is fraudulent, unreasonable, or arbitrary. Id. at 1317 n.2. This list of exceptions is

not exclusive. Id.

At the second level, the order must contain specific findings on all the factual

determinations material to its ultimate conclusions. Citizens Action Coalition, 485 N.E.2d at

612. McClain described the judicial task on this score as reviewing conclusions of ultimate facts

for reasonableness, the deference of which is based on the amount of expertise exercised by the

agency. McClain, 693 N.E.2d at 1317-18. Insofar as the order involves a subject within the

Commission’s special competence, courts should give it greater deference. Id. at 1318. If the

subject is outside the Commission’s expertise, courts give it less deference. Id. In either case

courts may examine the logic of inferences drawn and any rule of law that may drive the result.

Id. Additionally, an agency action is always subject to review as contrary to law, but this

constitutionally preserved review is limited to whether the Commission stayed within its

jurisdiction and conformed to the statutory standards and legal principles involved in producing

its decision, ruling, or order. Citizens Action Coalition, 485 N.E.2d at 612-13.

NIPSCO advocates that we apply a de novo standard because the case involves summary

judgment and a question of law. (Appellant’s Br. at 7-8.) It cites two recent Court of Appeals

opinions reviewing decisions of the Commission de novo: Ind. Bell Tel. Co. v. Time Warner

Commc’ns of Ind., L.P., 786 N.E.2d 301 (Ind. Ct. App. 2003), and Cowper v. Collier, 720

N.E.2d 1250 (Ind. Ct. App. 1999), trans. denied, 735 N.E.2d 230 (Ind. 2000). (Opposition to

Transfer at 6-7.)

5

Indiana Bell involved a challenge of the Commission’s interpretation of an

interconnection agreement between competing carriers. 786 N.E.2d at 303-04. In affirming the

Commission’s decision, the opinion did not treat the Commission’s order granting summary

judgment any differently than it would a trial court’s decision, nor did it consider doing so,

though it noted that it was not a typical contract in light of the Commission’s regulatory role in

determining whether to approve the contract at issue in the case. Id. at 305. Instead, the Court of

Appeals applied the de novo standard as if a trial court had interpreted the contract and gave

Ameritech, the party advocating for that low level of deference, “the benefit of the doubt”

because AT&T failed to cite authority for its alternative standard. Id.

The decision in Cowper v. Collier arose from a trial court review of a Natural Resource

Commission’s order upholding its administrative law judge’s decision after a trial on the merits.

Cowper, 720 N.E.2d at 1254. The opinion in Cowper reviewed the NRC’s decision de novo

because “the law is the province of the judiciary and the reviewing court is not bound by any

agency’s conclusions of law,” and “the construction of an unambiguous written contract is

generally a question of law for the court.” Id. at 1255. Applying contract case law, the opinion

reversed in part and remanded the NRC order. Id. at 1256.

NIPSCO argues that the current appeal is not the product of a regulatory settlement but

rather a dispute between two private parties over interpreting the Contract. (Reply Br. at 11.)

Because a court’s role in interpreting a contract is “to give effect to the parties’ intent at the time

the contract was made and as reflected by the language they used,” NIPSCO says that

interpreting the Contract is a question of law appropriate for de novo review by the judiciary.

(Opposition to Rehearing at 3.) NIPSCO asserts that in the proceeding the Commission “made

no use of ratemaking principles or agency expertise,” and therefore deserves no deference on the

question of contract interpretation. (Opposition to Transfer at 6.)

This paints too simple a picture of the processes under which the Contract became a

Commission order. Regulatory settlements bear important differences from agreements

6

governed purely by the law of contracts. Such an agreement does not become effective until and

unless the Commission acts on the agreement. Ind. Code § 8-1-2-24 (2008). A contract between

private parties takes on public interest ramifications once the Commission approves it. U.S.

Gypsum, Inc. v. Ind. Gas Co., 735 N.E.2d 790, 803 (Ind. 2000), quoting Citizens Action

Coalition of Ind., Inc. v. PSI Energy, Inc., 664 N.E.2d 401, 406 (Ind. Ct. App. 1996). The

Commission maintains the authority and statutory responsibility to supervise and regulate the

Contract. In responding to U.S. Steel’s request that it interpret and enforce its 1999 order, the

Commission received affidavits and reviewed the Contract, bills, its own order, the rate structure,

and other documents. (Pet. to Transfer at 5; App. at 4-8.) Both NIPSCO and U.S. Steel asserted

that there were no disputes over the material facts, making the matter appropriate for summary

resolution. As it commonly does in hearing the disputes before it, the Commission did more than

find facts; it deployed its expertise in the subject matter, one source of judicial deference to the

Commission’s decision-making. See U.S. Gypsum, 735 N.E.2d at 795.

Here, the Commission approved the contract when the parties entered it, effectively

making it an order of the Commission. This means the Commission interpreted its own order,

not a contract entered by the parties and later disputed. As the Seventh Circuit once said in

reviewing an order of the Environmental Protection Agency,

[W]hen the document is an order, the court or agency that issued it

is, sensibly enough, considered to have special insight into its

meaning, so review is deferential . . . . And the order itself is full

of technical terms, and we think the EPA is entitled to some scope

in interpreting their meaning as well. It is, to repeat, its own order.

Employers Ins. of Wasau v. Browner, 52 F.3d 656, 666 (7th Cir. 1995), cert. denied, 516

U.S. 1042 (1996).

7

NIPSCO acknowledges, as it must, that the initial approval of the Contract required the

Commission to exercise its expertise under Ind. Code § 8-1-2-24. (Reply Br. at 10.) As U.S.

Steel points out, this puts NIPSCO in the difficult position of arguing that in the present

enforcement proceeding, “the Commission misinterpreted its own prior order.”3 (Appellee’s Br.

at 16.) Approving such contracts and resolving disputes revolving around them is intrinsic to the

Commission’s regulation of utility rates.

Appellate courts apply a de novo standard when reviewing a trial court’s summary

judgment order because the reviewing court faces the same issues that were before the trial court

and analyzes them the same way. Carie v. PSI Energy, Inc., 715 N.E.2d 853 (Ind. 1999). By

contrast, review of an agency order does not involve the same analysis on appeal. As Justice

Arterburn wrote, “ratemaking is a legislative, not a judicial function . . . .” Pub. Serv. Comm’n

v. City of Indianapolis, 235 Ind. 70, 81, 131 N.E.2d 308, 312 (1956). Agencies are not judicial

bodies. They are executive branch institutions which the General Assembly has empowered with

delegated duties. As such, an adjudication by an agency deserves a higher level of deference

than a summary judgment order by a trial court falling squarely within the judicial branch. We

therefore apply the established standard of review for judicial review of Commission orders.

As our opinion in McClain summarized the statutory standard of review, “basic facts are

reviewed for substantial evidence, legal propositions are reviewed for their correctness.”

McClain, 693 N.E.2d at 1318. Ultimate facts or “mixed questions” are evaluated for

reasonableness, with the amount of deference depending on whether the issue falls within the

Commission’s expertise. See id.

3

Not only was the Commission the same institution that reviewed the parties’ settlement and entered the

order, the Presiding Commissioner who took the laboring oar to the Contract in the first place also led the

proceedings in the dispute now before us. (Appellee’s Br. at 16, citing App. at 10, 49.)

8

In this case, interpreting the Commission’s order is a question falling well within the

Commission’s expertise. NIPSCO acknowledges the 1999 order itself involved the

Commission’s special competence, and interpreting the meaning of the order is not substantively

different than approving the Contract. We therefore consider this question as a mixed question

of law and fact with a high level of deference, examining the logic of the inferences made and

the correctness of legal propositions without replacing our own judgment for that of the

Commission.

II. The Commission did not err in interpreting the Contract

Article 5 of the Contract outlines the rates NIPSCO is to charge U.S. Steel. Article 5.1

provides that “This Contract is a requirements contract for firm service with no minimums or

take-or-pay conditions. . . . [E]ffective October 1, 2005 through the end of the Contract term; a

market based price adjustment factor will be used to adjust the kilowatt-hour prices set forth in

Article 5.2 . . . .” (App. at 32.) Article 5.2 sets forth the bifurcated rate structure including a

Demand Charge and an Energy Charge. (App. at 33.) The Demand Charge language refers to

“all kilowatts of billing demand,” while the Energy Charge language refers to “kilowatt-hour[s].”

(App. at 33.) The Commission found that the language of the Contract unambiguously supported

U.S. Steel’s interpretation that the Adjustment applied only to the Energy Charge, that the

definitive Contract superseded any earlier expressions of intent, and that the Term Sheet did not

make the Contract ambiguous or demonstrate a contrary intent. (App. at 13-17.) In reaching

these conclusions, the Commission applied utility and contract law consistent with established

principles.

Both parties contend that the Contract was not ambiguous, and the Commission agreed.

(App. at 13.) The Commission observed that an unambiguous contract is not subject to

construction and that parol or extrinsic evidence may not be used to expand, vary, or explain its

9

terms. (App. at 13, citing United Consulting Engineers v. Bd. of Comm’rs of Hancock County,

810 N.E.2d 351, 354 (Ind. Ct. App. 2004).)

NIPSCO argues that the Term Sheet, Letter Agreement, and Settlement Agreement

should be considered to ascertain the intent of the parties and that the Contract contemplates the

agreement consists of all seven documents. (Appellant’s Br. at 11-17.) The Commission notes

that the parties submitted only the Settlement and Contract for its approval in 1999, and any

agreement for a special rate must be submitted and approved by the Commission. (App. at 14-

15.) Inasmuch as “neither the Term Sheet nor the Letter Agreement was filed with the

Commission as part of the parties’ agreement,” the Commission concluded that they could not be

part of the approved agreement. (App. at 14.)

Furthermore, the Commission looked to the Contract’s language and contract law to find

“that the Contract is the fully integrated agreement of the parties for the purchase of electricity

and that neither the Term Sheet nor Letter Agreement was incorporated therein.” (App. at 14).

The Commission concluded:

If an agreement is fully integrated, then evidence of prior or

contemporaneous written or oral statements and negotiations

cannot operate to either add to or contradict the written agreement.

Franklin v. White, 493 N.E.2d 161, 166-67 (Ind. 1986). Based on

the undisputed evidence and the language of the documents, we

find as a matter of law that the Term Sheet and Letter Agreement

were not incorporated into the Contract and therefore can not be

used to alter or amend the unambiguous Contract terms as to the

application of the Adjustment.

(App. at 16.)

The Commission also considered NIPSCO’s contention that the Term Sheet should be

available as evidence to illuminate the meaning of the settlement approved by the Commission in

1999. Only the Term Sheet and the Contract contain pricing terms. (App. at 32-35, 121.) The

Term Sheet provides for a uniform rate while the Contract contains the bifurcated Energy Charge

10

and Demand Charge rates, though both documents had the market-based pricing adjustment.

(App. at 33, 121.) NIPSCO argues that the Term Sheet thus shows that the parties intended the

market adjustment to apply to all aspects of the Contract’s pricing. (Appellant’s Br. at 19.) The

Commission disagreed, instead interpreting the Term Sheet as setting out the preliminary terms

of the future agreement, which changed from the Term Sheet to the Contract. (App. at 16-17.) It

concluded that the change from a uniform rate in the Term Sheet to the two-part rate in the

Contract was a part of several changes with the overall effect of shifting more demand risk to

U.S. Steel. (App. at 17.)

NIPSCO argued that the Adjustment applies to the Demand Charge because Article 5.1

applies to “kilowatt-hour prices” and the Demand Charge is for kilowatts up to a specified

number of hours. The Commission rejected this interpretation, reasoning:

The only kilowatt hour prices set forth in Article 5.2 are those that

apply to the kilowatt hours that are subject to the energy charge.

The fact that the demand charge includes up to a certain amount of

kilowatt hours of use does not alter the fact that the demand charge

is a price for kilowatt demand. Therefore, we find that NIPSCO’s

attempt to apply the Adjustment to kilowatt hours not included in

the energy charge is a misapplication of the agreed upon Contract

terms and of the rates approved by the Commission on July 8,

1999.

(App. at 14.)

On appeal, NIPSCO argues that Article 5.1’s phrase “kilowatt hour prices” indicates

application to both the Energy Charge and the Demand Charge because the same price is

specified for all five of the time periods provided for under the Energy Charge, so these could

not be described in the plural. (Appellant’s Br. at 9-10.) U.S. Steel counters that though the

number is the same for each period, it clearly includes five distinct prices for the Energy Charge,

which allows for the plural. (App. at 33-34, Appellee’s Br. at 23.) Additionally, the Contract

provided for the equal meaning of plural and singular in Article 1 definitions. (App. at 29.) In

11

light of these considerations and the deference owed to the Commission, NIPSCO’s assertion

does not persuade us that the Commission’s interpretation of the Contract is unreasonable.

None of the Commission’s conclusions run afoul of reasonable application of the well-

established principles of contract law.

III. Conclusion

We affirm the Commission’s order.

Dickson, Boehm, and Rucker, JJ., concur.

Sullivan, J., would have denied transfer, believing the analysis and conclusion of the Court of

Appeals to be correct.

12

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.