Opinion

Brown v. Beach House Design & Development

Court
California Court of Appeal
Filed
Nov 21, 2022
Status
Published
Cited by
0 cases
Authority
More cited than 11.1%

The opinion

Filed 10/21/22; Certified for Publication & Modified 11/21/22 (order attached)

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION THREE

KYLE BROWN, as represented, etc., B314946

Plaintiff and Appellant, (Los Angeles County

Super. Ct. No. 19STCV20315)

v.

BEACH HOUSE DESIGN &

DEVELOPMENT,

Defendant and Respondent.

APPEAL from a judgment of the Superior Court of

Los Angeles County, Gary Y. Tanaka, Judge. Reversed.

Dordick Law Corporation, Gary A. Dordick and John M.

Upton, for Plaintiff and Appellant.

Yee & Associates, Steven R. Yee and William G. Sorkin, for

Defendant and Respondent.

‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗‗

Plaintiff Kyle Brown (plaintiff) was severely injured when

he fell from a significant height while working as a carpenter at a

construction site. Plaintiff alleged that he fell from defective

scaffolding, and he sued the general contractor and the

scaffolding subcontractor for negligence. The trial court granted

summary judgment for the general contractor, concluding that

plaintiff’s claims against it were barred by exceptions to the

peculiar risk doctrine articulated by the California Supreme

Court in Privette v. Superior Court (1993) 5 Cal.4th 689 (Privette)

and subsequent authority.

We reverse. While Privette and subsequent cases held that

a general contractor cannot be vicariously liable for the

negligence of its subcontractors, plaintiff’s claim against the

general contractor alleged direct, not vicarious, liability. Further,

there were triable issues of material fact as to whether the

general contractor fully delegated to the scaffolding subcontractor

the duty to maintain the scaffolding in a safe condition. The

motion for summary judgment therefore was improperly granted.

FACTUAL AND PROCEDURAL BACKGROUND

I. Background.

Defendant Beach House Design and Development (Beach

House) was the general contractor responsible for remodeling a

residence in Hermosa Beach, California (the property). Beach

House subcontracted with O’Rourke Construction, Inc.

(O’Rourke) to do finish carpentry, and with A&D Plastering Co.

(A&D) to erect scaffolding and to patch plaster. Plaintiff, a

carpenter, was employed by O’Rourke.

On June 16, 2017, O’Rourke’s carpenters, including

plaintiff, were on the property to mill, prime, and install window

casings. After lunch, while working by himself, plaintiff fell from

the north side of the building onto a concrete walkway, suffering

2

severe injuries. It appears that no one saw plaintiff fall, and

plaintiff has no recollection of the incident.

After plaintiff’s fall, Jeffrey Strnad, Beach House’s

principal, and Alex Daniels, A&D’s principal, inspected the

scaffolding above the area where plaintiff fell. They found that

some of the scaffolding was not properly secured to the building,

and planks, crossbars, ties, and guardrails had been cut or were

missing. Both men said the scaffolding was not safe to use in

that condition.

II. The present action; Beach House’s motion for

summary judgment.

Plaintiff, through his guardian ad litem Barbara Brown,

sued Beach House for negligence. Plaintiff asserted that he had

fallen from scaffolding Beach House had failed to properly

maintain, resulting in permanent injuries, substantial medical

expenses, and loss of income. In September 2019, plaintiff filed

an amendment substituting A&D for a Doe defendant.

Beach House moved for summary judgment. It asserted

that under Privette and its progeny, a general contractor is liable

to a subcontractor’s employee for an injury resulting from an

unsafe workplace only if the general contractor affirmatively

contributed to the conditions that led to the injury. In the

present case, Beach House asserted there was undisputed

evidence that it did not supply the scaffolding or any other

equipment used by plaintiff, did not control the manner or means

by which plaintiff performed his work, and did not take any

affirmative act that contributed to plaintiff’s injury. That

evidence included the following:

Plaintiff was an employee of O’Rourke, with whom Beach

House subcontracted to install casings for windows and exterior

3

doors, do interior door trim work, frame bay windows, waterproof

exterior doors, and install exterior siding. The subcontract

between Beach House and O’Rourke provided that O’Rourke

would furnish “all materials, labor, tools, supplies, equipment,

permits, services, and supervision necessary for completion of the

scope of work [as] noted in the attached proposal.”

The scaffolding on the property was provided and installed

by A&D, which also did plastering work on the project. The A&D

subcontract provided that Beach House would pay A&D $8,495 to

install the scaffolding and $1,500 to do plaster work. The

subcontract further provided that A&D would “furnish scaffold

and equipment that may be necessary to do the Work

expeditiously,” “provide traffic and safety controls at all times

while using such equipment at the Project,” and “[promptly]

remove and replace any defective material, damaged [sic] caused

by Subcontractor or Work upon notice from Contractor, Owner or

Architect.”

Strnad, Beach House’s managing member, stated in a

declaration that Beach House did not direct the means or

methods of the work performed by O’Rourke or its employees,

including plaintiff, and it did not provide any equipment or

materials to O’Rourke. Beach House also did not direct the

means or methods of the work performed by A&D. Strnad had

“no information that Beach House and/or its employees

contributed in any way to the purportedly defective railing on the

scaffolding, plaintiff’s purported slipping, and/or plaintiff’s

purported fall.”

4

III. Plaintiff’s opposition to motion for summary

judgment.

Plaintiff opposed the motion for summary judgment. He

contended there were triable issues as to whether Beach House

furnished dangerous equipment to plaintiff and negligently

exercised control over the job site, including the scaffolding.

Specifically, he asserted there was evidence that Beach House

retained control over the safety of the job site through its safety

plan and daily walk-throughs, and that Beach House was

responsible for procuring and maintaining the scaffolding for the

use of its subcontractors and their employees, including O’Rourke

and plaintiff. That evidence included the following:

Tony O’Rourke, an O’Rourke principal, testified that in his

experience, scaffolding usually is provided by the general

contractor. 1 O’Rourke had never set up scaffolding or chosen a

scaffolding company, and O’Rourke’s bid for the work in this case

did not include the cost of scaffolding. O’Rourke expected that

Beach House would provide scaffolding because O’Rourke’s scope

of work included installing second and third story windows,

which could not be reached without scaffolding.

Alex Daniels, an A&D principal, testified that he and his

son Danny were the A&D employees who erected scaffolding and

inspected it for safety. Once scaffolding was erected, it was not

Daniels’s practice to inspect it daily; Daniels believed daily

inspection of the scaffolding was the responsibility of the

superintendent or contractors. A&D did not have an agreement

with Beach House about allowing other subcontractors to use the

1 Throughout this opinion, we will use “O’Rourke” to refer

both to Tony O’Rourke and O’Rourke Construction.

5

scaffolding, but Daniels never told Beach House not to allow

other contractors to use the scaffolding.

Strnad, Beach House’s principal, testified that Beach

House subcontracted with A&D to erect, maintain, supervise, and

tear down the scaffolding. Beach House’s employees did not

inspect the scaffolding after it was erected because Strnad

believed “that wasn’t our role or duty in the contract with A&D.

Their responsibility was to furnish the scaffold. They took full

responsibility to supervise the scaffold and maintain it.”

Matthew Linden, Beach House’s site supervisor, testified

that he never inspected the scaffolding to ensure it was in a safe

condition because that was A&D’s responsibility. He agreed,

however, that A&D was not on site every day; to the contrary, he

said A&D’s plastering work took only about six months, but the

scaffolding remained on the job site for at least a year. Linden

acknowledged that A&D employees did not come to the site to

inspect the scaffolding on days they were not performing work,

and he said that during periods when A&D was not on site, he

was not aware that anyone was making sure the scaffolding was

safe.

Linden authenticated a weekly task document prepared by

Beach House stating that during the week of June 12, 2017,

A&D “[s]et scaffolding at West and South Elev for Mezz desk

fascia and trim installation,” “[s]et scaffolding on top of Canopy

for South elev siding installation,” and “[i]ncrease[d] scaffolding

height at East front elev for siding installation.” Linden agreed

that this document suggested Beach House had instructed A&D

to erect scaffolding for the use of O’Rourke and his employees.

Linden also authenticated an invoice from A&D to Beach House

for “Scaffold Rental––invoice due for scaffold rental above

6

contract for 05/17/2017 through 06/17/2017 (32 days at $84.95 per

day).”

IV. Order granting summary judgment; appeal.

The trial court granted the motion for summary judgment

on May 26, 2021. It explained that under Privette, a general

contractor is not liable for injuries suffered by a subcontractor’s

employee unless (1) the general contractor retained control over

the subcontractor’s work and the exercise of control affirmatively

contributed to the employee’s injuries, or (2) the general

contractor provided unsafe equipment that affirmatively

contributed to the subcontractor’s employee’s injury. In the

present case, Beach House provided competent evidence that it

did not retain control over how plaintiff performed his work, did

not provide equipment to plaintiff, and did not contribute to any

purported defect in the scaffolding. In response, plaintiff

presented evidence that Beach House maintained a safety plan

that included daily walk-throughs, had supervisory responsibility

over the job site, and provided the scaffolding. The court found

that plaintiff’s evidence did not establish that any of Beach

House’s affirmative conduct caused plaintiff’s injuries because

Beach House did not direct the means or methods by which

plaintiff conducted his work. Further, plaintiff’s evidence did not

establish that Beach House was responsible for the condition of

the scaffolding because plaintiff’s evidence “actually confirms

that the scaffold was provided by A&D,” not Beach House. The

court thus concluded that plaintiff had failed to establish that an

exception existed to the Privette doctrine.

The trial court entered judgment for Beach House on

July 23, 2021. Plaintiff timely appealed.

7

DISCUSSION

I. Standard of review.

“ ‘A trial court properly grants summary judgment when

there are no triable issues of material fact and the moving party

is entitled to judgment as a matter of law. (Code Civ. Proc.,

§ 437c, subd. (c).) “The purpose of the law of summary judgment

is to provide courts with a mechanism to cut through the parties’

pleadings in order to determine whether, despite their

allegations, trial is in fact necessary to resolve their dispute.”

[Citation.]

“ ‘A defendant who moves for summary judgment bears the

initial burden to show the action has no merit—that is, “one or

more elements of the cause of action, even if not separately

pleaded, cannot be established, or that there is a complete

defense to [that] cause of action.” (Code Civ. Proc., § 437c,

subds. (a), (p)(2).) Once the defendant meets this initial burden

of production, the burden shifts to the plaintiff to demonstrate

the existence of a triable issue of material fact. [Citation.] “From

commencement to conclusion, the moving party defendant bears

the burden of persuasion that there is no triable issue of material

fact and that the defendant is entitled to judgment as a matter of

law.” [Citation.] We review the trial court’s ruling on a summary

judgment motion de novo, liberally construing the evidence in

favor of the party opposing the motion and resolving all doubts

about the evidence in favor of the opponent. [Citation.] We

consider all of the evidence the parties offered in connection with

the motion, except that which the court properly excluded.

[Citation.]’ (Grotheer v. Escape Adventures, Inc. (2017)

14 Cal.App.5th 1283, 1292–1293.)” (Delgadillo v. Television

Center, Inc. (2018) 20 Cal.App.5th 1078, 1085–1086.)

8

II. Applicable law.

A. The Privette doctrine.

At common law, a person who hired an independent

contractor to perform a task generally was not liable to third

parties for injuries caused by the independent contractor’s

negligence. Central to this rule of nonliability “ ‘was the

recognition that a person who hired an independent contractor

had “ ‘no right of control as to the mode of doing the work

contracted for.’ ” ’ ” (SeaBright Ins. Co. v. US Airways, Inc. (2011)

52 Cal.4th 590, 598 (SeaBright).)

The “peculiar risk” doctrine created an exception to the

common law rule that a hirer is not liable for the torts of an

independent contractor. Under the doctrine of peculiar risk, “a

person who hires an independent contractor to perform work that

is inherently dangerous can be held liable for tort damages when

the contractor’s negligent performance of the work causes injuries

to others. By imposing such liability without fault on the person

who hires the independent contractor, the doctrine seeks to

ensure that injuries caused by inherently dangerous work will be

compensated, that the person for whose benefit the contracted

work is done bears responsibility for any risks of injury to others,

and that adequate safeguards are taken to prevent such injuries.”

(Privette, supra, 5 Cal.4th at p. 691.) The doctrine of peculiar risk

thus represents a limitation on the common law rule and a

corresponding expansion of hirer vicarious liability.

In its 1993 decision in Privette, supra, 5 Cal.4th 689, the

California Supreme Court held that the peculiar risk doctrine did

not apply to injured employees of independent contractors.

Privette concerned a roofing contractor’s employee who was

injured when he fell off a ladder and was burned by hot tar. The

9

employee sued the owner of the home he had been roofing,

contending that the homeowner was liable for his injuries under

the doctrine of peculiar risk. (Id. at pp. 692–693.) The Supreme

Court held that while the homeowner would be liable to an

“innocent bystander” (id. at p. 701) injured by the independent

contractor’s negligence, he was not liable to the independent

contractor’s employee. The court explained: “[T]he peculiar risk

doctrine seeks to ensure that injuries caused by contracted work

will not go uncompensated, that the risk of loss for such injuries

is spread to the person who contracted for and thus primarily

benefited from the contracted work, and that adequate safety

measures are taken to prevent injuries resulting from such work.

[Citation.] But in the case of on-the-job injury to an employee of

an independent contractor, the workers’ compensation system of

recovery regardless of fault achieves the identical purposes that

underlie recovery under the doctrine of peculiar risk. It ensures

compensation for injury by providing swift and sure

compensation to employees for any workplace injury; it spreads

the risk created by the performance of dangerous work to those

who contract for and thus benefit from such work, by including

the cost of workers’ compensation insurance in the price for the

contracted work; and it encourages industrial safety.” (Ibid.)

Thus, the court concluded, “when considered in light of the

various goals that the workers’ compensation statutes seek to

achieve, [the conclusion] that peculiar risk liability should extend

to the employees of the independent contractor, does not

withstand scrutiny.” (Id. at pp. 701–702.)

In subsequent cases, the Supreme Court expanded the

Privette doctrine to hold that a hirer could not be held vicariously

liable to an independent contractor’s employees under a variety of

10

tort theories. (E.g., Toland v. Sunland Housing Group, Inc.

(1998) 18 Cal.4th 253 [hirer of an independent contractor not

liable to contractor’s employee for failing to specify that the

contractor should take special precautions to avert a risk];

Camargo v. Tjaarda Dairy (2001) 25 Cal.4th 1235 [hirer of an

independent contractor not liable to contractor’s employee for

negligent hiring]; Tverberg v. Fillner Construction, Inc. (2010)

49 Cal.4th 518, 522 (Tverberg) [“Having assumed responsibility

for workplace safety, an independent contractor may not hold a

hiring party vicariously liable for injuries resulting from the

contractor’s own failure to effectively guard against risks

inherent in the contracted work”], italics omitted.)

B. Hooker and McKown: negligent exercise of

retained control.

In 2002, our Supreme Court issued two companion

decisions addressing the circumstances in which a contractor’s

employee may sue the hirer of the contractor for negligent

exercise of retained control over a worksite. Hooker v.

Department of Transportation (2002) 27 Cal.4th 198 (Hooker)

concerned the death of a crane operator, Hooker, who was killed

on a California Department of Transportation (Caltrans) site.

The decedent was employed by a general contractor hired by

Caltrans to construct a highway overpass. The overpass was

25 feet wide, and the crane with the outriggers extended was

18 feet wide, so Hooker had to retract the crane’s outriggers to

allow other construction vehicles to pass. Shortly before the fatal

accident, Hooker retracted the outriggers; he then attempted to

swing the boom without first reextending the outriggers, causing

the crane to tip over. Hooker was thrown to the pavement and

killed. (Id. at p. 202.)

11

Hooker’s widow sued Caltrans, asserting it had negligently

exercised control over the job site. The trial court granted

Caltrans’s motion for summary judgment, and the Supreme

Court affirmed. The court explained that a hirer may be liable

for a contractor’s employee’s injury only when the hirer’s conduct

“affirmatively contributed” to the employee’s injury. (Hooker,

supra, 27 Cal.4th at pp. 211–212.) In the case before it, although

Caltrans was aware that Hooker was retracting the crane’s

outriggers to allow traffic to pass, it had not ordered him to do so.

(Id. at p. 214.) Under these circumstances, the court said

Caltrans’s actions had not affirmatively contributed to Hooker’s

death. It explained: “[U]nder the standard we announce today,

summary judgment was appropriate here. Plaintiff raised triable

issues of material fact as to whether defendant retained control

over safety conditions at the worksite. However, plaintiff failed

to raise triable issues of material fact as to whether defendant

actually exercised the retained control so as to affirmatively

contribute to [Hooker’s death]. While the evidence suggests that

the crane tipped over because the crane operator swung the boom

while the outriggers were retracted, and that the crane operator

had a practice of retracting the outriggers to permit construction

traffic to pass the crane on the overpass, there was no evidence

Caltrans’s exercise of retained control over safety conditions at

the worksite affirmatively contributed to the adoption of that

practice by the crane operator. There was, at most, evidence that

Caltrans’s safety personnel were aware of an unsafe practice and

failed to exercise the authority they retained to correct it.” (Id. at

p. 215, italics added.)

The court reached a different result in McKown v. Wal-

Mart Stores, Inc. (2002) 27 Cal.4th 219 (McKown). Plaintiff

12

McKown was an employee of an independent contractor hired by

Wal-Mart to install speakers in the ceilings of Wal-Mart stores.

Wal-Mart requested that the contractor use Wal-Mart’s forklifts

whenever possible and furnished McKown a forklift for his use.

(Id. at p. 223.) That forklift was defective, and McKown was

injured as a result. (Ibid.)

A jury found that Wal-Mart was negligent in providing the

contractor with unsafe equipment and allocated 23 percent of the

responsibility for the accident to Wal-Mart. The Supreme Court

affirmed. (McKown, supra, 27 Cal.4th 219.) It explained that in

Hooker, it had held “that a hirer of an independent contractor is

not liable to an employee of the contractor merely because the

hirer retained control over safety conditions at a worksite, but

that a hirer is liable to an employee of a contractor insofar as a

hirer’s exercise of retained control affirmatively contributed to

the employee’s injuries.” (Id. at p. 225.) Thus, “when a hirer of

an independent contractor, by negligently furnishing unsafe

equipment to the contractor, affirmatively contributes to the

injury of an employee of the contractor, the hirer should be liable

to the employee for the consequences of the hirer’s own

negligence.” (Ibid.) In other words, “ ‘where the hiring party

actively contributes to the injury by supplying defective

equipment, it is the hiring party’s own negligence that renders it

liable, not that of the contractor.’ ” (Id. at p. 225.)

Subsequent to Hooker and McKown, the Supreme Court

noted in Kinsman v. Unocal Corp. (2005) 37 Cal.4th 659, 671

(Kinsman) that a useful way to understand its cases “is in terms

of delegation.” It explained that while an independent contractor

generally is presumed to have delegated to a subcontractor the

duty to provide a safe workplace for the subcontractor’s

13

employees, “when the [independent contractor] does not fully

delegate the task of providing a safe working environment, but in

some manner actively participates in how the job is done, and

that participation affirmatively contributes to the employee’s

injury, the hirer may be liable in tort to the employee.” (Ibid.)

Most recently, our Supreme Court clarified the

Hooker/McKown exception to the Privette rule 2 in Sandoval v.

Qualcomm Inc. (2021) 12 Cal.5th 256 (Sandoval). There, it

reaffirmed that although under its precedents a hirer

presumptively delegates to an independent contractor the

responsibility to do work safely, the hirer retains a duty of care to

the contractor’s employees if it does not fully delegate control to

the independent contractor. (Id. at pp. 269, 274.) To establish

that the hirer owes a duty of care to the contractor’s employees,

therefore, the plaintiff must establish both that the hirer

retained control over the contracted work, and that the hirer

actually exercised that retained control in a manner that

affirmatively contributed to the contract worker’s injury. (Id. at

p. 274.) The court noted, however, that neither “actual exercise”

nor “affirmative contribution” require that the hirer’s alleged

negligence consist of an affirmative act. Instead, “[t]he hirer’s

negligence may take the form of any act, course of conduct, or

failure to take a reasonable precaution that is within the scope of

2 Plaintiff suggests that Hooker and McKown articulate two

different exceptions to the Privette rule. In fact, as Beach House

notes, Hooker and McKown represent different applications of the

same exception––namely, that a hirer will be liable when it

exercises control over any part of an independent contractor’s

work in a manner that affirmatively contributes to a worker’s

injuries. (See Gonzalez v. Mathis (2021) 12 Cal.5th 29, 42.)

14

its duty under Hooker. . . . [¶] If a plaintiff proves that the hirer

actually exercised retained control in a way that affirmatively

contributed to the contract worker’s injury, the plaintiff

establishes that the hirer owed the contract worker a duty of

reasonable care as to that exercise of control.” (Id. at pp. 277–

278.)

III. Triable issues of material fact exist as to whether

Beach House negligently exercised retained control

by furnishing unsafe scaffolding to O’Rourke and its

employees.

Under the authorities discussed above, whether Beach

House owed a duty of care to plaintiff turns on whether it

retained control over plaintiff’s performance of the contracted-for

work and exercised control in a way that contributed to plaintiff’s

injuries. Although plaintiff will have the burden of proof at trial,

it was Beach House’s burden on summary judgment to

demonstrate the absence of triable issues of material fact as to

these issues––that is, that plaintiff cannot prevail on his claim as

a matter of law.

The central allegation of plaintiff’s complaint is that

plaintiff fell from the scaffolding because Beach House failed to

maintain it in a safe condition. Beach House acknowledged in its

motion for summary judgment that a general contractor may be

liable for providing unsafe equipment to a subcontractor that

causes injury to the subcontractor’s employee, but it urged it had

no duty to inspect or maintain the scaffolding because it did not

“supply, control, or assemble” it.

It appears undisputed that A&D, not Beach House,

supplied and erected the scaffolding. That fact alone is not

dispositive of Beach House’s motion for summary judgment,

15

however. As we have said, a general contractor may exercise

retained control over a job site by “requesting [a subcontractor] to

use the [general contractor’s] own defective equipment in

performing the work.” (Gonzalez v. Mathis, supra, 12 Cal.5th at

pp. 46–47, citing McKown, supra, 27 Cal.4th at pp. 225–226.)

If it does so, the general contractor need not own the allegedly

defective equipment to be liable for injuries caused by its use––

instead, under the principles discussed above, the general

contractor may assume a duty of care to its subcontractor’s

employees if it “undert[akes] to arrange and supply” equipment

for the employees’ use. (See, e.g., Browne v. Turner Construction

Co. (2005) 127 Cal.App.4th 1334, 1345.)

Where a general contractor contracts with a third party to

supply equipment for the use of its subcontractors, the

contractor’s potential liability to its subcontractors’ employees for

defective equipment turns on the extent of the contractor’s

delegation to the third party––that is, whether the contractor

“fully delegate[d]” to the third party the duty to maintain the

equipment in a safe condition. (Kinsman v. Unocal Corp., supra,

37 Cal.4th at p. 671; Sandoval, supra, 12 Cal.5th at p. 274.) If

the general contractor fully delegates to the third party the duty

to provide safe equipment, the third party is responsible for any

failure to take reasonable precautions to keep the equipment in a

safe condition. But if the general contractor does not fully

delegate the task of providing safe equipment, it may be liable in

tort to an employee. (Sandoval, at p. 671; see also Kinsman, at

p. 671; Ray v. Silverado Constructors (2002) 98 Cal.App.4th 1120

[cited with approval in Ray; reversing grant of summary

judgment for independent contractor where there was a triable

issue as to whether the general contractor, who was alleged to

16

have acted negligently by failing to close a road, had retained the

sole authority to close the road].)

Applying these principles to the present case suggests that

the essential questions for purposes of Beach House’s motion for

summary judgment are (1) whether Beach House undertook to

supply scaffolding for the use of O’Rourke and its employees,

(2) whether Beach House fully delegated to A&D the alleged duty

to provide and maintain the scaffolding, and (3) if Beach House

did not fully delegate the responsibility to maintain the

scaffolding to A&D, whether it exercised its retained control in a

manner that affirmatively contributed to plaintiff’s injury. As we

discuss, there are triable issues of material fact as to each of

these questions.

A. There are triable issues of fact as to whether

Beach House undertook to supply scaffolding

for O’Rourke and its employees.

In support of its motion for summary judgment,

Beach House asserted through the declaration of its principal,

Strnad, that it “did not provide any equipment or materials to

O’Rourke to perform its work,” including the scaffolding. Beach

House also relied on subcontracts it entered into with A&D and

O’Rourke, which required the subcontractors to “furnish all labor,

materials, equipment, and other facilities required to complete

the Work” and to “furnish scaffold and equipment that may be

necessary to do the Work.”

In response, plaintiff contended that triable issues of

material fact existed as to whether Beach House procured the

scaffolding for the use of O’Rourke’s employees (as well as for

others), therefore assuming a duty of care for its maintenance.

Plaintiff cited the following evidence in support:

17

● O’Rourke’s work on the project included installing

exterior trim on the second and third floors, which required the

use of scaffolding.

● Tony O’Rourke testified that in his experience,

scaffolding typically is provided by the general contractor for the

use of its subcontractors. O’Rourke’s bid on the project did not

include the cost of scaffolding because he understood scaffolding

would be provided by Beach House.

● O’Rourke observed other subcontractors using the

scaffolding erected by A&D, and he believed he and his

employees had permission to use it. He has never asked for

permission to use scaffolding on a job site, and he was not told

not to use the scaffolding in connection with this project. After

plaintiff’s accident, he and his employees were permitted to use

the scaffolding once it was repaired.

● A&D’s plastering work took about six months, but

the scaffolding remained up on the property for more than a year.

● Beach House’s site manager was aware that

O’Rourke’s employees made regular use of the scaffolding, and he

never asked them not to do so.

● A task document prepared by Beach House stated

that during the week of June 12, 2017, A&D increased the height

of the scaffolding “for siding installation.” The siding was

installed by O’Rourke’s employees. Beach House’s site manager

acknowledged that the task document appeared to instruct A&D

to “erect scaffolding for the use of O’Rourke Construction

employees.”

● Beach House paid an invoice from A&D to Beach

House dated June 29, 2017 “for scaffold rental.”

18

Taken together, this evidence would allow a reasonable

jury to conclude that Beach House undertook to provide

scaffolding for the use of its subcontractors, including plaintiff.

B. There are triable issues as to whether Beach

House fully delegated to A&D the responsibility

to provide and maintain the scaffolding.

Beach House contended below that even if it undertook to

provide scaffolding for the use of O’Rourke and its employees, it

delegated to A&D through the Beach House/A&D subcontract the

responsibility to provide and maintain the scaffolding, and thus

any failure to do so properly was a breach of A&D’s duty, not

Beach House’s. The undisputed facts did not support this

conclusion, however.

As an initial matter, we cannot conclude with certainty

that the A&D subcontract provided by Beach House in support of

its motion for summary judgment remained in effect at the time

of plaintiff’s injury on June 16, 2017. That subcontract defined

A&D’s scope of work with reference to the “attached proposal,”

which stated that A&D would “[s]et scaffolding where needed for

lathing and plastering for a period of 90 days.” (Italics added.)

Other documents provided in connection with the motion for

summary judgment suggested that the scaffolding was initially

erected on September 20, 2016, approximately nine months

before the accident. Accordingly, we cannot conclude that Beach

House and A&D were continuing to operate under the terms of

the A&D subcontract in June 2017.

In any event, even if the subcontract remained in effect in

June 2017, it did not clearly set forth who was responsible for

inspecting and maintaining the scaffolding after its installation—

that is, during the more than one-year period that the scaffolding

19

remained up on the property. Beach House suggested that

inspection and maintenance of the scaffolding was A&D’s

responsibility under paragraph 5.1(4) of the contract, which

addressed “safety controls” relating to the scaffolding.

Paragraph 5.1(4), however, said only that A&D would furnish

scaffolding and “provide traffic and safety controls at all times

while using such equipment at the Project.” (Italics added.) In

other words, while this paragraph appeared to require A&D to

provide safety controls while A&D’s employees were using the

scaffolding, it did not clearly require A&D to provide such

controls at other times or for the protection of other

subcontractors or their employees.

Nor did other evidence before the trial court establish that

there were no triable issues of material fact as to who had the

responsibility to maintain the scaffolding in a safe condition.

Beach House’s principal, Strnad, and its site manager, Linden,

testified that it was A&D’s responsibility, not Beach House’s, to

inspect the scaffolding and safely maintain it. But A&D’s

principal, Daniels, testified that once scaffolding is erected, he

does not examine it on a daily basis because it is the

responsibility of “the superintendent or contractors on a daily

basis to inspect.” Daniels further testified that when he contracts

to erect scaffolding on a job site, he relies on the general

contractor to monitor the scaffolding during periods when he and

his employees are not actively working at the site and to “stop

people from making alterations to [the] scaffolding.” And,

although site manager Linden testified that he believed A&D was

responsible to insure the safety of the scaffolding, he conceded he

knew A&D employees did not come to the job site to inspect the

scaffolding on days they were not performing plastering work.

20

For all of these reasons, there are triable issues of material fact

as to whether Beach House fully delegated to A&D the

responsibility to maintain the scaffolding during the duration of

the project.

Further, we reject Beach House’s suggestion that plaintiff

is judicially estopped from urging that Beach House was

responsible for maintaining the scaffolding because he asserted

otherwise in his opposition to A&D’s motion for summary

judgment. The opposition to which Beach House refers was not

before the trial court when it ruled on Beach House’s motion for

summary judgment, and thus it is not a proper part of our

appellate record. (See, e.g., People v. Avila (2004)

117 Cal.App.4th 771, 780, fn. 4 [“We review the correctness of the

trial court’s ruling at the time it was made and not by reference

to evidence produced at a later date”]; In re Zeth S. (2003)

31 Cal.4th 396, 405 [“It has long been the general rule and

understanding that ‘an appeal reviews the correctness of a

judgment as of the time of its rendition, upon a record of matters

which were before the trial court for its consideration’ ”].) In any

event, to establish judicial estoppel, Beach House must establish,

among other things, that the party against whom judicial

estoppel is asserted “ ‘was successful in asserting the first

position (i.e., the tribunal adopted the position or accepted it as

true)’ ” and “ ‘the two positions are totally inconsistent.’ ” (The

Swahn Group, Inc. v. Segal (2010) 183 Cal.App.4th 831, 842.) In

the present case, Beach House has not shown either that plaintiff

successfully asserted that A&D was responsible for maintaining

the scaffolding or that the plaintiff’s position on appeal and in

opposition to A&D’s motion for summary judgment were

inconsistent. To the contrary, we see no inconsistency in the

21

assertion that Beach House and A&D had nonexclusive

responsibility for maintaining the scaffolding in a safe condition.

Accordingly, Beach House has not established that plaintiff’s

claim is barred by the doctrine of judicial estoppel.

Finally, we reject Beach House’s suggestion that liability in

the present case is barred by Brannan v. Lathrop Construction

Associates, Inc. (2012) 206 Cal.App.4th 1170, 1172 (Brannan).

There, a bricklayer’s employee was injured when he fell from

scaffolding erected by another subcontractor. But unlike in the

present case, the plaintiff in Brannan did not allege that the

scaffolding had been provided by the general contractor for his

use or that it was defective. To the contrary, it was undisputed

that the parties had agreed that the bricklayer’s employees would

not use the scaffolding. (Id. at p. 1174.) The court’s holding in

Brannan that summary judgment had been properly granted for

the general contractor, therefore, is not relevant to our analysis.

C. There are triable issues as to whether Beach

House exercised retained control in a manner

that affirmatively contributed to plaintiff’s

injury.

Finally, Beach House contended below that because

plaintiff did not allege it engaged in any affirmative misconduct,

it could not be liable for plaintiff’s injury as a matter of law. Not

so. As noted above, our Supreme Court has explained that the

critical inquiry for purposes of evaluating the exercise of retained

control “is the relationship between the [general contractor’s]

conduct and the [subcontractor’s] conduct, not whether the

[general contractor’s] conduct, assessed in isolation, can be

described as ‘affirmative conduct.’ ” (Sandoval, supra, 12 Cal.5th

at p. 277, italics added.) That is, “neither ‘actual exercise’ nor

22

‘affirmative contribution’ requires that the [general contractor’s]

negligence (if any) consist of an affirmative act. The [general

contractor’s] negligence may take the form of any act, course of

conduct, or failure to take a reasonable precaution that is within

the scope of its duty under Hooker. (See Rest.3d Torts, Liability

for Physical and Emotional Harm, § 3, com. c, pp. 29–30; Hooker,

supra, 27 Cal.4th at p. 212, fn. 3 [noting that a hirer may be

liable based on failing to undertake a promised safety measure];

Ray, supra, 98 Cal.App.4th at pp. 1133–1134 [finding triable

issue on affirmative contribution where hirer retained exclusive

authority over road barricades and failed to erect barricade

around fallen debris that contractor was trying to clear when

injury occurred].)” (Sandoval, at p. 277, italics added.)

Under this standard, were a jury to conclude that Beach

House assumed a duty to provide scaffolding for the use of

O’Rourke employees and that it failed to fully delegate to A&D

the duty to maintain the scaffolding in a safe condition, it could

also reasonably conclude that Beach House’s alleged failure to

inspect and maintain the scaffolding gave rise to liability.

Accordingly, there are triable issues as to whether Beach House

exercised retained control in a manner that affirmatively

contributed to plaintiff’s injury. 3

3 Because we are reversing the grant of summary judgment,

we will deny Beach House’s request for appellate sanctions for

pursuing a frivolous appeal.

23

DISPOSITION

The judgment is reversed. Appellant is awarded his

appellate costs. Respondent’s request for appellate sanctions is

denied.

NOT TO BE PUBLISHED IN THE OFFICIAL

REPORTS

EDMON, P. J.

We concur:

EGERTON, J.

ADAMS, J. *

* Judge of the Los Angeles Superior Court, assigned by the

Chief Justice pursuant to article VI, section 6 of the California

Constitution.

24

Filed 11/21/22

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION THREE

KYLE BROWN, as represented, B314946

etc.,

(Los Angeles County

Plaintiff and Appellant, Super. Ct. No. 19STCV20315)

v. ORDER MODIFYING OPINION

AND CERTIFYING OPINION FOR

BEACH HOUSE DESIGN & PUBLICATION [NO CHANGE IN

DEVELOPMENT, JUDGMENT]

Defendant and Respondent.

THE COURT:

It is ordered that the opinion filed herein on October 21,

2022, be modified as follows:

On page 16, in the second sentence of the first full

paragraph, change the citation from “Sandoval, at p. 671” to

“Sandoval, at p. 274” and change “cited with approval in Ray” to

“cited with approval in Sandoval” so the citation reads:

“But if the general contractor does not fully delegate the

task of providing safe equipment, it may be liable in tort to

an employee. (Sandoval, at p. 274; see also Kinsman, at

p. 671; Ray v. Silverado Constructors (2002) 98 Cal.App.4th

1120 [cited with approval in Sandoval; reversing grant of

summary judgment for independent contractor where there

was a triable issue as to whether the general contractor,

who was alleged to have acted negligently by failing to close

a road, had retained the sole authority to close the road].)”

[There is no change in the judgment.]

The opinion in the above-entitled matter filed October 21,

2022, was not certified for publication in the Official Reports. For

good cause it now appears that the opinion should be published in

the Official Reports and it is so ordered.

____________________________________________________________

EDMON, P. J. EGERTON, J. ADAMS, J. *

* Judge of the Los Angeles Superior Court, assigned by the

Chief Justice pursuant to article VI, section 6 of the California

Constitution.

2

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.