Opinion

In re Application of Icebreaker Windpower, Inc.

  • 169 Ohio St. 3d 617
  • 207 N.E.3d 651
  • 2022 Ohio 2742
Court
Ohio Supreme Court
Filed
Aug 10, 2022
Status
Published
On the bench
Brunner, J.
Cited by
5 cases
Authority
More cited than 58.8%

The opinion

[Until this opinion appears in the Ohio Official Reports advance sheets, it may be cited as In

re Application of Icebreaker Windpower, Inc., Slip Opinion No. 2022-Ohio-2742.]

NOTICE

This slip opinion is subject to formal revision before it is published in an

advance sheet of the Ohio Official Reports. Readers are requested to

promptly notify the Reporter of Decisions, Supreme Court of Ohio, 65

South Front Street, Columbus, Ohio 43215, of any typographical or other

formal errors in the opinion, in order that corrections may be made before

the opinion is published.

SLIP OPINION NO. 2022-OHIO-2742

IN RE APPLICATION OF ICEBREAKER WINDPOWER, INC., FOR A CERTIFICATE OF

ENVIRONMENTAL COMPATIBILITY AND PUBLIC NEED FOR AN ELECTRIC

GENERATING FACILITY IN CUYAHOGA COUNTY, OHIO;

DEMPSEY ET AL., APPELLANTS; POWER SITING BOARD, APPELLEE;

ICEBREAKER WINDPOWER, INC., INTERVENING APPELLEE.

[Until this opinion appears in the Ohio Official Reports advance sheets, it

may be cited as In re Application of Icebreaker Windpower, Inc., Slip Opinion

No. 2022-Ohio-2742.]

Power Siting Board—Offshore wind-powered electric-generation facility—

Application for certificate of environmental compatibility and public need—

R.C. 4906.10(A)—Power Siting Board’s order granting certificate subject

to conditions affirmed—Board’s authority under R.C. 4906.10(A)(6) does

not extend to the power to make public-trust determinations.

(No. 2021-0153—Submitted December 7, 2021—Decided August 10, 2022.)

APPEAL from the Power Siting Board, No. 16-1871-EL-BGN.

__________________

SUPREME COURT OF OHIO

BRUNNER, J.

{¶ 1} Appellee, the Ohio Power Siting Board (“the board”), approved the

application of intervening appellee, Icebreaker Windpower, Inc. (“Icebreaker”), for

a certificate of environmental compatibility and public need to build a six-turbine

wind-powered electric-generation facility in Lake Erie. Appellants, W. Susan

Dempsey and Robert M. Maloney (hereafter, “the residents”), who are residents of

the village of Bratenahl on the southern shore of Lake Erie, have appealed the

board’s decision granting the certificate, raising two propositions of law. First, they

argue that there was insufficient evidence before the board for it to determine (1)

the nature of the probable environmental impact of the project under R.C.

4906.10(A)(2) and (2) whether the project represents the minimum adverse

environmental impact under R.C. 4906.10(A)(3). Second, they argue that the

board’s decision to issue the certificate violated the public-trust doctrine and thus

the project does not serve the public interest, convenience, and necessity under R.C.

4906.10(A)(6).

{¶ 2} For the reasons discussed below, we affirm the board’s decision.

I. FACTS AND PROCEDURAL BACKGROUND

{¶ 3} On February 1, 2017, Icebreaker filed an application with the board

for a certificate to build a six-turbine wind-powered electric-generation facility on

approximately 4.2 acres of submerged land in Lake Erie located between eight and

ten miles off the shore of Cleveland. The project would be the first freshwater

offshore wind-powered electric-generation facility in North America.

It has been described as a small-scale demonstration project that will provide

valuable information as to how offshore wind facilities interact with the

environment and that will test the viability of large-scale wind facilities on Lake

Erie and the other Great Lakes. See Power Siting Bd. No. 16-1871-EL-BGN, ¶ 2

(May 21, 2020).

2

January Term, 2022

{¶ 4} The proposed wind farm’s estimated electric-generation capacity is

20.7 megawatts, making it an “economically significant wind farm,” R.C.

4906.13(A) and Ohio Adm.Code 4906-1-01(R), the construction of which requires

the board’s approval, R.C. 4906.10 and 4906.20(A). R.C. 4906.10(A) provides that

the board shall not grant a certificate for the construction, operation, and

maintenance of a major utility facility unless it first makes eight substantive

findings, including “[t]he nature of the probable environmental impact” of the

facility, R.C. 4906.10(A)(2), and that “[t]he facility represents the minimum

adverse environmental impact,” R.C. 4906.10(A)(3).

{¶ 5} Several parties, including the residents, intervened before the board.

The residents do not want the facility to be built on Lake Erie, because they fear

that the project could lead to additional wind farms being built on the lake. The

most contentious issue before the board was whether Icebreaker had sufficiently

demonstrated under R.C. 4906.10(A)(2) and (3) the proposed facility’s probable

environmental impact on birds and bats. The residents argued that the board could

not determine the facility’s probable impact on birds and bats based on the evidence

that Icebreaker had submitted. The residents also claimed that the project violates

the public-trust doctrine, which provides that the state holds title to Lake Erie in

trust for the benefit of the people of Ohio, State ex rel. Squire v. Cleveland, 150

Ohio St. 303, 82 N.E.2d 709 (1948), paragraph two of the syllabus.

{¶ 6} On September 4, 2018, Icebreaker entered a joint stipulation with

several parties that purported to resolve most of the issues in the case. The residents

and the board’s staff opposed the stipulation. Icebreaker filed a revised stipulation

on May 15, 2019. The staff joined the revised stipulation, leaving only the residents

opposing Icebreaker’s application.

{¶ 7} On May 21, 2020, the board issued an order approving the revised

stipulation with certain modifications, thereby granting a certificate to Icebreaker

for the proposed project, subject to certain conditions. The board found, contrary

3

SUPREME COURT OF OHIO

to the residents’ arguments, that Icebreaker had submitted sufficient evidence for

the board to determine the probable environmental impact of the project on birds

and bats. However, the board found it necessary to impose a different risk-

mitigation measure than that which the revised stipulation proposed. The board

therefore modified the stipulation to require that the turbines be nonoperational

from dusk to dawn for eight months of the year until otherwise ordered by the board.

The board reasoned that it was necessary to shut down the turbines during the

specified times due to the lack of data regarding the actual impact that the project

would have on birds and bats at the project site and some uncertainty regarding

Icebreaker’s postconstruction collision-monitoring technology.

{¶ 8} As for the residents’ argument that the project violated the public-trust

doctrine, the board determined that it lacked jurisdiction over the issue. The board,

however, went on to reject the argument that the project violated the public-trust

doctrine.

{¶ 9} The residents and Icebreaker both sought rehearing of the board’s

order. On October 8, 2020, the board issued an entry denying the residents’

rehearing application. The board, however, granted Icebreaker’s rehearing

application in part and removed the turbine-shutdown requirement imposed in the

May 21 order. The board determined that it was unnecessary to impose that

requirement because the order had approved a process ensuring that Icebreaker

would provide the board with the necessary information both before construction

of the wind farm and during its operation. Power Siting Bd. No. 16-1871-EL-BGN,

¶ 30-32, 36 (Oct. 8, 2020).

{¶ 10} On November 5, 2020, the residents filed a rehearing application

challenging the board’s removal of the turbine-shutdown requirement. The board

did not rule on the rehearing application within 30 days; thus, it was denied by

operation of law. See R.C. 4903.10(B).

4

January Term, 2022

{¶ 11} The residents appealed the board’s determination to this court as of

right. The board and Icebreaker filed merit briefs defending the order. Amici curiae

Great Lakes Towing Company and Ohio Environmental Council submitted briefs

urging affirmance of the order.

II. STANDARD OF REVIEW

{¶ 12} Under R.C. 4906.12, we apply the same standard of review to power-

siting determinations that we apply to orders of the Public Utilities Commission of

Ohio. In re Application of Black Fork Wind Energy, L.L.C., 138 Ohio St.3d 43,

2013-Ohio-5478, 3 N.E.3d 173, ¶ 10. Under this standard, we will reverse, vacate,

or modify an order of the board only when, upon consideration of the record, we

conclude that the order was unlawful or unreasonable. R.C. 4903.13. “We will not

reverse or modify a board decision as to questions of fact when the record contains

sufficient probative evidence to show that the board’s decision was not manifestly

against the weight of the evidence and was not so clearly unsupported by the record

as to show misapprehension, mistake, or willful disregard of duty.” In re

Application of Champaign Wind, L.L.C., 146 Ohio St.3d 489, 2016-Ohio-1513, 58

N.E.3d 1142, ¶ 7. We review questions of law de novo. See id.

III. ANALYSIS

{¶ 13} Ohio law prohibits the board from granting a certificate of

environmental compatibility and public need unless it first determines the nature of

the probable environmental impact of the facility, R.C. 4906.10(A)(2), that the

facility represents the minimum adverse environmental impact, R.C.

4906.06(A)(3), and that the facility will serve the public interest, convenience, and

necessity, R.C. 4906.10(A)(6). In their first proposition of law, the residents raise

various challenges to the board’s determinations under R.C. 4906.10(A)(2) and (3).

In their second proposition of law, the residents argue that the board’s decision

granting the certificate violated the public-trust doctrine and, by extension, R.C.

4906.10(A)(6).

5

SUPREME COURT OF OHIO

A. Proposition of law No. 1: Whether the board erred in determining that

Icebreaker satisfied the requirements of R.C. 4906.10(A)(2) and (3)

{¶ 14} In their first proposition of law, the residents contest the board’s

determinations under R.C. 4906.10(A)(2) and (3), arguing that Icebreaker failed to

submit sufficient evidence for the board to properly assess the environmental risk

that the project poses to birds and bats. The board counters that the evidence in the

record was abundant and that it thoroughly considered it and made all the findings

required by R.C. 4906.10(A). Likewise, Icebreaker maintains that the board made

valid findings under R.C. 4906.10(A) that were fully supported by extensive

evidence in the record.

{¶ 15} Upon review, we hold that the board’s determinations under R.C.

4906.10(A)(2) and (3) were lawful and reasonable. Therefore, we reject the

residents’ first proposition of law.

1. Record evidence supports the board’s determination that Icebreaker satisfied

the requirements of R.C. 4906.10(A)(2)

{¶ 16} The board found that the probable environmental impact of the

project can be determined by evaluating migration patterns near the project site and

reviewing data regarding land-based wind farms in the Great Lakes region.

According to the board, the project was expected to primarily affect migrating birds

and bats, especially migrating nocturnal birds. The board found that the facility

would affect migrating birds and bats through collision, avoidance, and attraction.

But the board determined that any environmental impact would be severely reduced

by the project’s small scale, its location several miles offshore, and the flight

patterns of migrating birds. We hold that the board’s determinations in that regard

were amply supported by the record.

{¶ 17} First, the board generally cited myriad scientific studies submitted

as evidence that monitored birds and bats flying in the vicinity of the project site

and other offshore and near-shore parts of Lake Erie. The board specifically cited

6

January Term, 2022

radar monitoring of the project site, acoustic studies of bird and bat activity, aerial

studies of birds in the project area and birds migrating over Lake Erie, and a wind-

turbine-placement-favorability analysis conducted by the Ohio Department of

Natural Resources (hereafter, “ODNR”).

{¶ 18} Second, the board cited evidence showing that the small scale of the

project (six turbines) and its location between eight and ten miles offshore severely

reduced the impact that the facility will have on birds and bats. The board found

that because the project is located several miles offshore, it will not impact the

habitats of nesting birds or roosting bats. The board also determined that eagles

and other raptors were concentrated near the shoreline and were not expected to fly

near the project site and that very few waterfowl venture as far from the shoreline

as the project site.

{¶ 19} Third, the board cited the testimony of staff witness Erin Hazelton,

who testified that the nature of the probable environmental impact on birds and bats

will be collision, avoidance, and attraction. The board also cited radar studies

showing that most of the migrating birds are expected to fly above the rotor-swept

zone of the turbines and that only a small percentage of the birds are expected to

fly in the rotor-swept zone.

{¶ 20} Fourth, the board relied on a review by Icebreaker’s expert witness,

Dr. Caleb Gordon, of 42 land-based wind farms in the Great Lakes region, as well

as the board’s staff’s own review of Ohio’s land-based wind-farm projects. Based

on this evidence, the board estimated that the project could be expected to cause

between 21 and 42 fatal bird collisions per year. In addition, the board cited

evidence suggesting that an offshore facility may have less of an impact on

nocturnal migrating birds than a land-based wind facility.

{¶ 21} Fifth, the board relied on studies of bat fatalities at 55 land-based

wind-farm projects, as well as a bat-acoustic survey of activity near the project area.

Based on this evidence, the board found that the collision risk for bats near the

7

SUPREME COURT OF OHIO

project is low because bat activity is significantly greater on land than offshore

(almost ten times more frequent in terrestrial environments near Cleveland than

offshore).

{¶ 22} In summary, the board’s order contains a lengthy discussion of the

“nature of the probable environmental impact,” a factor that must be determined

under R.C. 4906.10(A)(2). On appeal, the residents bear the burden of

demonstrating that the board’s decision was against the manifest weight of the

evidence and was “so clearly unsupported by the record as to show

misapprehension, mistake or willful disregard of duty.” Champaign Wind, L.L.C.,

146 Ohio St.3d 489, 2016-Ohio-1513, 58 N.E.3d 1142, at ¶ 7. As explained below,

the residents have failed to meet that burden.

2. The residents’ evidence does not justify reversing the board’s determination

under R.C. 4906.10(A)(2)

{¶ 23} As shown above, the residents have not established that the board’s

determination under R.C. 4906.10(A)(2) lacked support in the record. And what

the residents attempt to establish through their evidence is either irrelevant or does

not justify reversal of the board’s determination.

a. The residents’ request for additional preconstruction radar monitoring

{¶ 24} The residents first point to a lack of data that they argue was

necessary for the board to make a determination under R.C. 4906.10(A)(2). They

claim that Icebreaker failed to submit sufficient preconstruction radar data showing

the number and density of birds and bats that fly through the project’s rotor-swept

zone. The residents assert that without this data, the board lacked the evidence

necessary to assess the risk that the project poses to birds and bats.

{¶ 25} The board determined that additional preconstruction radar

monitoring was not necessary to a determination under R.C. 4906.10(A)(2),

because the board’s task under that provision is to “identif[y] the nature of the

probable impact, not the actual impact.” Power Siting Bd. No. 16-1871-EL-BGN,

8

January Term, 2022

at ¶ 107 (May 21, 2020). The board determined that evidence in the form of studies

of land-based wind farms and existing radar data for migrating birds and bats at the

project site was sufficient to determine the probable impact—i.e., collision,

avoidance, and attraction—on birds and bats under R.C. 4906.10(A)(2). It is true

that the board acknowledged that preconstruction radar monitoring at the project

site would provide more detail regarding the flight patterns of migrating birds and

bats, particularly in the rotor-swept zone. But the board explained that the purpose

of preconstruction radar monitoring is to verify the number and density of birds and

bats in the project area so as to establish a baseline for comparison with

postconstruction radar-monitoring data. Accordingly, the board determined that

preconstruction radar data for the project site was necessary to ensure that any

adverse environmental impact was minimal under R.C. 4906.10(A)(3), but that

such data was not relevant to a determination of the probable environmental impact

under R.C. 4906.10(A)(2).

{¶ 26} The residents maintain that additional preconstruction radar

monitoring was necessary to determine the project’s probable environmental

impact. According to the residents, Icebreaker acknowledged the need for

additional radar studies in the following excerpt from its application:

While state and federal agencies have agreed that the

information regarding the impact to fish and wildlife supports a

finding that the permitting processes at the state and federal levels

can move forward, they have requested that [Icebreaker] conduct

additional field surveys prior to construction in order to provide a

direct comparison with postconstruction survey information, as a

means to assess the level of wildlife impact during the operational

phase of the project.

9

SUPREME COURT OF OHIO

(Emphasis added.) The residents maintain that despite these requests from other

state and federal agencies, Icebreaker has failed “to collect and submit to the Board

pre-construction radar studies for the rotor-swept zone of the Project site.”

{¶ 27} The language from Icebreaker’s application quoted above, however,

does not help the residents’ claim that Icebreaker needed to submit radar studies for

the rotor-swept zone before the board issued the certificate. The excerpt expressly

states that “the permitting processes at the state * * * level[] can move forward.”

Likewise, their reliance on the emphasized language from the excerpt is equally

unavailing because the excerpt says that the state and federal agencies requested

the additional field surveys “prior to construction,” not prior to certification.

{¶ 28} Moreover, the residents have failed to acknowledge that what these

agencies requested is precisely what the board has ordered. The board issued

Icebreaker a certificate subject to certain conditions. Relevant here is revised

stipulation condition No. 21, which requires Icebreaker to complete up to two years

of preconstruction radar monitoring and produce viable data for at least 75 percent

of the survey hours before construction may begin. The monitoring program must

also be able to determine the flight altitude of birds and bats flying near and through

the rotor-swept zone. Also relevant is revised stipulation condition No. 22, which

requires Icebreaker to demonstrate prior to construction that the requirements for

radar monitoring set forth in condition No. 21 have been satisfied for at least one

spring, summer, and fall migration season. And once the facility becomes

operational, Icebreaker must repeat the radar-monitoring process to determine the

precise impact of the project on birds and bats, including behavioral impacts such

as attraction and avoidance.

{¶ 29} In summary, the board required Icebreaker to submit evidence that

the residents now assert was necessary to grant the certificate—namely, additional

preconstruction radar studies that will then be used to assess the actual impact on

birds and bats once the project becomes operational. And although we do not

10

January Term, 2022

conclude that the board erred, the residents have not shown that the board’s failure

to require that the requested monitoring be conducted before issuance of the

certificate appreciably affected them. See Champaign Wind, L.L.C., 146 Ohio St.3d

489, 2016-Ohio-1513, 58 N.E.3d 1142, at ¶ 15 (this court will not reverse the

board’s order unless the appellant shows prejudice stemming from the board’s

error). Therefore, we hold that the residents have not demonstrated reversible error.

b. The residents’ claim that Icebreaker’s migration evidence is misleading

{¶ 30} The residents also cite a letter from the United States Fish and

Wildlife Service for the proposition that “assertions made by Icebreaker that birds

and bats migrate around Lake Erie, instead of crossing it, are affirmatively

misleading.” (Emphasis sic.) The residents’ reliance on the letter is misplaced.

{¶ 31} The Fish and Wildlife Service provided the letter in response to a

draft environmental assessment for the proposed project that was prepared by the

United States Department of Energy. The letter questions recent marine radar

studies cited in the assessment that demonstrate that migrating birds avoid flying

over large bodies of water like Lake Erie, because other studies demonstrate that

large numbers of migrating birds do fly over large bodies of water. The residents,

however, overlook the fact that the board never found that migrating birds avoid

flying over Lake Erie and instead fly around it. Rather, the board expressly found

that birds are expected to migrate north and south over Lake Erie, and the residents

do not challenge that finding.

c. The residents’ reliance on statements of the board’s staff’s counsel and on

the board chairman’s concurring opinion on rehearing

{¶ 32} The residents argue that the board’s staff admitted that additional

preconstruction radar data was necessary to determine the probable impact of the

project on birds and bats. The residents refer to the staff’s motion to suspend the

procedural schedule, in which staff requested “additional supplemental information

on the viability and design of the pre- and post-construction radar monitoring

11

SUPREME COURT OF OHIO

protocol that [Icebreaker] intends to utilize at the project site for determining

project impacts * * * [, because] this information is necessary to measure the effect

of off-shore turbines on birds and bats.”

{¶ 33} Counsel’s statement in a prehearing motion describing the staff’s

characterization of the quality of existing evidence is not record evidence. See

Champaign Wind, L.L.C., 146 Ohio St.3d 489, 2016-Ohio-1513, 58 N.E.3d 1142,

at ¶ 24. But even if it were record evidence, the residents have acknowledged that

staff later changed its position and determined that it had sufficient information to

determine the probable environmental impact of the project.

{¶ 34} The residents also claim that the board chairman undermined the

board’s order when, in their view, he stated in his concurring opinion on rehearing

that the probable and actual environmental impact of the project could not be

determined without evidence establishing the number and density of birds and bats

that fly through the rotor-swept zone. This argument lacks merit for two reasons.

{¶ 35} First, the residents have taken the chairman’s statement out of

context. The chairman did state in his concurring opinion that the order

“recognized an unlawful and unreasonable deficiency contained in the [revised

stipulation].” Power Siting Bd. No. 16-1871-EL-BGN, at 3 (Oct. 8, 2020)

(Chairman Sam Randazzo, concurring). The residents emphasize the chairman’s

statement that there were “open and significant issues associated with the

identification and mitigation of the risks to avian and bat populations.” But as we

read it, the chairman was referring to the revised stipulation’s failure to “identify a

lawful and reasonable process” for resolving the risk issues, not the fact that those

issues were left open and needed to be resolved. (Emphasis added.) Id. (Chairman

Sam Randazzo, concurring).

{¶ 36} Moreover, our role here is to determine whether the board’s order

was lawful and reasonable. And we note that the chairman’s concurring opinion is

not the order of the board.

12

January Term, 2022

3. The residents have failed to demonstrate that the board erred in determining

that the project satisfied the requirements of R.C. 4906.10(A)(3)

{¶ 37} When the board approved Icebreaker’s certificate, it left several

disputed issues unresolved. Among other things, the board required Icebreaker to

(1) demonstrate compliance with certain requirements for the preconstruction radar

monitoring and data gathering discussed above, (2) determine whether the

preconstruction radar technology will be deployed on a floating platform or a

stationary platform, (3) submit a bird-and-bat-impact mitigation plan that includes

a collision-monitoring plan, and (4) decide on a specific collision-detection

technology that will be used to collect data regarding the impact on birds and bats

after the project becomes operational. Rather than requiring Icebreaker to resolve

those matters before issuing the certificate, the board determined that the conditions

on its grant of the certificate were sufficient to protect birds and bats and to ensure

that the facility represented the minimum adverse environmental impact.

{¶ 38} The residents challenge the board’s deferral of those requirements,

arguing that without them, the board lacked sufficient evidence to determine that

the project represented the minimum adverse environmental impact under R.C.

4906.10(A)(3). They contend that the board could not have made this

determination given Icebreaker’s failure to submit the preconstruction radar data

and its failure to identify a suitable technology to monitor bird and bat activity at

the project site and detect collisions with the wind turbines. The residents maintain

that it was Icebreaker’s burden to submit this information before the board granted

the certificate and that the board erred in granting the certificate “subject to pre-

construction radar and collision monitoring conditions that the Board contends will

allow it to later” make the mandatory determination under R.C. 4906.10(A)(3). We

reject these arguments for the following reasons.

13

SUPREME COURT OF OHIO

a. The board’s decision imposing conditions on its grant of the certificate is

consistent with our precedent

{¶ 39} We have upheld the board’s practice of imposing conditions on

wind-farm construction certificates. See, e.g., In re Application of Buckeye Wind,

L.L.C., 131 Ohio St.3d 449, 2012-Ohio-878, 966 N.E.2d 869, ¶ 16-18 (lead

opinion); see also In re Application of Duke Energy Ohio, Inc., 166 Ohio St.3d 438,

2021-Ohio-3301, 187 N.E.3d 472, ¶ 52 (reaffirming the board’s authority under

R.C. 4906.10(A) to impose conditions on natural-gas-pipeline construction

certificates). In Buckeye Wind, a group of landowners neighboring a proposed wind

farm challenged the board’s decision granting a certificate to the wind farm’s

developer to build 70 wind turbines. Id. at ¶ 3-4. When the board approved the

certificate, it required the developer to resolve several disputed issues before a

preconstruction conference with the board’s staff. Id. at ¶ 14. Among other things,

the board authorized its staff to (1) approve new sites for three turbines, (2) review

and accept plans regarding the design and siting of electric-collection lines, (3)

determine the maximum potential distance that a dislodged turbine blade could be

thrown, and (4) determine the specific model of wind turbine to be used. Id.

{¶ 40} Each of those deferred issues related to and affected the facility’s

environmental impact under R.C. 4906.10(A)(2) and (3). We determined that the

board had not been required to resolve the issues before the certificate was issued,

because R.C. 4906.10(A) expressly allows the board to issue a certificate subject to

such conditions as it considers appropriate. Buckeye Wind, L.L.C. at ¶ 16. We

explained that R.C. 4906.10(A) “authorize[s] a dynamic process that does not end

with the issuance of a construction certificate.” Id. And we noted that “[t]he

General Assembly vested the board with authority to allow its staff to monitor [the

applicant]’s compliance with conditions that the board has set, conditions upon

which [the parties opposing the application] already had the chance to be heard.”

Id.

14

January Term, 2022

b. The board properly considered the factors in R.C. 4906.10(A)(3)

{¶ 41} Although the residents concede that Buckeye Wind applies here, they

argue that the board misapplied our precedent in that case by failing to “study the

factors listed in” R.C. 4906.10(A) before granting the certificate. According to the

residents, the board’s decision granting the certificate subject to conditions to be

reviewed later shows that the board lacked the evidence necessary to make a

determination under R.C. 4906.10(A)(3).

{¶ 42} Contrary to the residents’ claim, the board did consider the

requirements of R.C. 4906.10(A)(3) before granting the certificate. By requiring

that the board determine that “the facility represents the minimum adverse

environmental impact,” the statute directs the board to “consider[] the state of

available technology and the nature and economics of the various alternatives, and

other pertinent considerations.” Id. Among other considerations, the board found

that Icebreaker’s moving the project further away from the shore and the small scale

of the project minimized several potential adverse environmental impacts on

wildlife.

{¶ 43} The board also considered specific measures that were designed to

minimize the adverse environmental impact on birds and bats at the project site.

For example, the board required Icebreaker to submit a radar-monitoring plan prior

to construction that includes pre- and postconstruction monitoring and produces a

minimum percentage of viable monitoring data. The board also required Icebreaker

to install fully functioning collision-monitoring technology prior to operation. The

board allowed Icebreaker to delay choosing a specific collision-monitoring

technology in order “to ensure the latest technologies and advancements are being

utilized at the project.” And to limit the risk to birds and bats, the board required

15

SUPREME COURT OF OHIO

specific and expedited mitigation measures (including turbine-shutdown

requirements) in case of a significant mortality event1 or equipment failure.

{¶ 44} The residents have not shown that the board’s decision to issue the

certificate subject to conditions was unlawful or unreasonable. The board acted

within its authority when it imposed conditions on its grant of the certificate. And

the board thoroughly considered the requirements of R.C. 4906.10(A)(3) before it

issued the certificate subject to the conditions.

4. Whether the board erred in removing the condition for mandatory shutdown

{¶ 45} The residents argue that the board acted unlawfully and

unreasonably when it removed the requirement for mandatory turbine shutdown on

rehearing. According to the residents, the record establishes that without the

turbine-shutdown mandate, the board could not determine that the project

represents the minimum adverse environmental impact. We disagree.

a. The turbine-shutdown mandate: Its nature and the board’s reasons for

removing it

{¶ 46} The revised stipulation provided the board’s staff and ODNR with

authority to “feather” (i.e., shut down) the turbines during nighttime hours from

March 1 through January 1 in the event that the collision-detection system

employed at the project site failed to accurately detect collisions. This ten-month

period covered the spring and fall peak-migration periods and the summer

residency period, when migrating birds and bats are at their highest risk of harm by

facility operations.

{¶ 47} In the May 21, 2020 order, the board imposed a different risk-

mitigation measure, requiring Icebreaker to shut down the turbines during

nighttime hours from March 1 through November 1. The board reasoned that it

was necessary to shut down the turbines at the specified times upon commencement

1. Hazelton defined a significant mortality event as 21 detected collisions, facility-wide, within a

24-hour period.

16

January Term, 2022

of operations due to (1) the lack of data regarding the actual impact on birds and

bats at the project site, (2) the uncertainty concerning the postconstruction collision-

monitoring technology, and (3) the fact that the project would be the first offshore

wind-farm project in Ohio. Under the order, however, Icebreaker could seek less

restrictive operating limits after gathering and providing the board with data

regarding the flight patterns of migrating birds and bats in the project area.

{¶ 48} On rehearing, the board changed course and determined that the

turbine-shutdown mandate would be removed, “provided that, prior to any

construction or operation of the [p]roject, the [b]oard * * * address[es] the bird and

bat risk mitigation measures that shall apply to this project.” Power Siting Bd. No.

16-1871-EL-BGN, at ¶ 30 (Oct. 8, 2020). The board noted that “[p]ursuant to R.C.

4906.10(A)(3), the proposed facility must represent the minimum adverse

environmental impact, considering the state of available technology and the nature

and economics of the various alternatives, along with other pertinent

considerations.” Id. at ¶ 31. The board thus determined, after further review, that

it was unnecessary to impose the shutdown mandate because its order had set forth

a process to ensure that prior to and during operation of the facility, the necessary

information would be provided to the board for its review and approval. Id. at

¶ 30-32, 36. Based on that process and the supervision that it calls for, the board

was persuaded that the shutdown mandate could be eliminated without detracting

from any effort to establish the risk-mitigation protocols that will apply to the

project.

b. The residents fail to show error in the board’s decision

{¶ 49} In arguing that the shutdown mandate was necessary for the board

to determine that the project satisfied the requirements of R.C. 4906.10(A)(3), the

residents rely exclusively on the board’s staff report of investigation and the

testimony of staff witness Hazelton. The staff report did conclude that the

shutdown mandate was critical to assuring that the project would not significantly

17

SUPREME COURT OF OHIO

impact birds and bats, at least until there was sufficient preconstruction radar data

and an effective postconstruction monitoring plan. But that evidence is not

persuasive, because the staff changed its position on the shutdown mandate when

it joined the revised stipulation, which did not recommend the shutdown as a

condition to issuing the certificate. And in supporting the revised stipulation, staff

members testified that the shutdown condition contained therein (providing staff

and ODNR with discretion to determine when turbines are to be shut down),

coupled with other stipulated conditions, was sufficient to satisfy R.C.

4906.10(A)(3). Based on this evidence, the residents have failed to show that the

board erred in its decision.

5. Conclusion: Proposition of law No. 1

{¶ 50} The project, if completed, would be the first freshwater offshore

wind-powered electric-generation facility in North America. That the board

employed a flexible standard in granting the requested certificate poses no legal

problem—“an agency, particularly when facing new issues, may proceed on an

incremental, case-by-case basis,” Buckeye Wind, L.L.C., 131 Ohio St.3d 449, 2012-

Ohio-878, 966 N.E.2d 869, at ¶ 33.

{¶ 51} In summary, the board determined that Icebreaker’s evidence and

the conditions imposed under the revised stipulation showed sufficient compliance

with the statutory requirements. On appeal, it is the residents’ burden to show that

the board erred, but the residents have failed to do so. Accordingly, we reject the

residents’ first proposition of law.

B. Proposition of law No. 2: Whether the board’s decision to issue the

certificate violated the public-trust doctrine and, by extension, R.C.

4906.10(A)(6), because the project does not serve the public interest,

convenience, and necessity

{¶ 52} The residents claim that the board’s decision to grant the certificate

to Icebreaker violated the public-trust doctrine and thus the project does not serve

18

January Term, 2022

the public interest, convenience, and necessity under R.C. 4906.10(A)(6). The

residents argue that the public-trust doctrine prohibits the state—and the board as

its agent—from relinquishing its ownership interest in Lake Erie to the benefit of a

private, for-profit entity such as Icebreaker.

{¶ 53} The public-trust doctrine provides that the state of Ohio holds title

to the land under Lake Erie within the territorial limits of the state as trustee for the

benefit of the people of Ohio. Squire, 150 Ohio St. 303, 82 N.E.2d 709, at

paragraphs one and two of the syllabus. The state “may, by proper legislative

action, carry out its specific duty of protecting the trust estate and regulating its

use.” Id. at paragraph two of the syllabus. In effect, the public-trust doctrine

imposes an affirmative duty on the part of the state to protect the natural resources

and navigable waters of Lake Erie for the public.

{¶ 54} The residents raised their public-trust argument to the board in their

posthearing reply brief. The board rejected the argument on multiple grounds.

First, the board determined that whether the project violates the public-trust

doctrine is a question for judicial determination that is outside the board’s

jurisdiction. Second, the board determined that the project did not violate the

public-trust doctrine, because the state was not relinquishing any interest in Lake

Erie. The board noted that the project is subject to a submerged-land lease between

the state (through ODNR) and Icebreaker. According to the board, the terms of the

lease required Icebreaker to respect the public’s right to the free and unrestricted

use of the waters and its right of navigation in and around the facility. In addition,

the board reiterated that it had already examined the potential impact of the facility

on the lake, including any effects on recreational activities. Based on its review,

the board determined that due to the project’s small scale and its location at least

eight miles offshore, the project was expected to have a minimal impact on the

public’s enjoyment of Lake Erie.

19

SUPREME COURT OF OHIO

{¶ 55} Here, the residents argue that the board erred in determining that it

lacked jurisdiction to consider whether the project violated the public-trust

doctrine. They claim that the board has authority to determine public-trust issues

when it considers whether “[a] facility will serve the public interest, convenience,

and necessity” under R.C. 4906.10(A)(6).

{¶ 56} The residents, however, point to no language in R.C. 4906.10(A)(6)

that gives the board authority to make public-trust determinations concerning Lake

Erie. The board, as a creature of statute, may exercise only those powers that the

General Assembly confers on it. In re Black Fork Wind Energy, L.L.C., 156 Ohio

St.3d 181, 2018-Ohio-5206, 124 N.E.3d 787, ¶ 20. Yet R.C. 4906.10(A)(6) makes

no mention of any obligation of the state to hold the waters and submerged land of

Lake Erie in trust for the people of Ohio. We may not add words to a statute to

achieve a desired construction. In re Application of Columbus S. Power Co., 147

Ohio St.3d 439, 2016-Ohio-1608, 67 N.E.3d 734, ¶ 49. If the General Assembly

intended to vest the board with authority to make public-trust determinations

regarding Lake Erie, it could have chosen words to that effect.

{¶ 57} Moreover, the power to administer the public-trust doctrine is

expressly designated to ODNR. See R.C. 1506.10 (declaring that the waters and

submerged land of Lake Erie “belong[] to the state as proprietor in trust for the

people of the state” and designating ODNR “as the state agency in all matters

pertaining to the care, protection, and enforcement of the state’s rights designated

in [R.C. 1506.10]”); R.C. 1506.11(A) and (B) (authorizing ODNR’s director to

regulate the use of Lake Erie through leases of “all or any part of the state’s interest”

in the lake’s waters and underlying lands); see also State ex rel. Merrill v. Ohio

Dept. of Natural Resources, 130 Ohio St.3d 30, 2011-Ohio-4612, 955 N.E.2d 935,

¶ 51-55. And contrary to the residents’ assertion, the General Assembly has clearly

allowed for both private and public uses of Lake Erie. Specifically, R.C.

20

January Term, 2022

1506.11(B) provides that “any person who wants to develop or improve part of the

territory” may file an application for a submerged-land lease. (Emphasis added.)

{¶ 58} The provisions noted above show that the General Assembly acted

to protect the public trust in Lake Erie and vested those duties in ODNR. As a

result, the board’s authority under R.C. 4906.10(A)(6) does not extend to the power

to make public-trust determinations. Accordingly, we hold that the board did not

err in determining that it lacked jurisdiction to consider the residents’ public-trust

argument.

IV. CONCLUSION

{¶ 59} For the foregoing reasons, we affirm the board’s order granting the

certificate to Icebreaker.

Order affirmed.

O’CONNOR, C.J., and FISCHER, DEWINE, DONNELLY, and STEWART, JJ.,

concur.

KENNEDY, J., dissents, with an opinion.

_________________

KENNEDY, J., dissenting.

{¶ 60} The General Assembly has not created a statutory exception to R.C.

4906.10’s requirements for granting a certificate of environmental compatibility

and public need for the construction, operation, and maintenance of electric-

generation facilities that are “demonstration projects.” Therefore, appellee, the

Ohio Power Siting Board, lacked authority to grant intervening appellee, Icebreaker

Windpower, Inc., a certificate to build an offshore wind farm in Lake Erie without

first making all the findings that are required for certifying a major utility facility.

{¶ 61} R.C. 4906.10(A) prohibits the board from granting a certificate for

the construction, operation, and maintenance of a major utility facility unless it

determines, among other things, “[t]he nature of the probable environmental

impact,” R.C. 4906.10(A)(2), and “[t]hat the facility represents the minimum

21

SUPREME COURT OF OHIO

adverse environmental impact, considering the state of available technology and

the nature and economics of the various alternatives, and other pertinent

considerations,” R.C. 4906.10(A)(3). Icebreaker’s proposed facility would be the

first freshwater offshore electric-generation wind-farm project in the United States,

and for that reason, it is not currently possible to know all of the facility’s probable

impacts on the environment. And only after first determining the impact that the

facility will likely have on the environment, including its impact on aquatic and

avian wildlife, can the board determine whether the facility represents the minimum

adverse environmental impact, considering the state of available technology and

the viability of alternatives.

{¶ 62} Without additional information, the probable environmental impact

of constructing a wind farm in Lake Erie is unknown, and the board’s order granting

a certificate to Icebreaker was unreasonable and unlawful. Therefore, I would

reverse the board’s order granting the certificate. Because the majority does not, I

dissent.

Standard of Review

{¶ 63} We apply the same standard of review to an order of the board that

we apply to an order of the Public Utilities Commission of Ohio. In re Application

of Duke Energy Ohio, Inc., 166 Ohio St.3d 438, 2021-Ohio-3301, 187 N.E.3d 472,

¶ 11, citing R.C. 4906.12. “Under this standard, we will reverse, vacate, or modify

a board order ‘if, upon consideration of the record, [we are] of the opinion that such

order was unlawful or unreasonable.’ ” (Brackets added in Duke Energy Ohio.)

Id., quoting R.C. 4903.13. “We ‘will not reverse or modify a board decision as to

questions of fact when the record contains sufficient probative evidence to show

that the board’s decision was not manifestly against the weight of the evidence and

was not so clearly unsupported by the record as to show misapprehension, mistake

or willful disregard of duty.’ ” Id., quoting In re Application of Champaign Wind,

22

January Term, 2022

L.L.C., 146 Ohio St.3d 489, 2016-Ohio-1513, 58 N.E.3d 1142, ¶ 7. We review

legal questions de novo. Id.

R.C. 4906.10(A)

{¶ 64} At issue in this case are R.C. 4906.10(A)(2) and (A)(3), which

provide that the board may not grant a certificate for the construction, operation,

and maintenance of a major utility facility unless the board first “finds and

determines,” among other requirements, the following:

(2) The nature of the probable environmental impact; [and]

(3) That the facility represents the minimum adverse

environmental impact, considering the state of available technology

and the nature and economics of the various alternatives, and other

pertinent considerations.

Reviewing the meaning of these provisions returns us to a familiar place: statutory

construction. As we explained long ago, “[t]he question is not what did the general

assembly intend to enact, but what is the meaning of that which it did enact.”

Slingluff v. Weaver, 66 Ohio St. 621, 64 N.E. 574 (1902), paragraph two of the

syllabus. “When the statutory language is plain and unambiguous, and conveys a

clear and definite meaning, we must rely on what the General Assembly has said.”

Jones v. Action Coupling & Equip., Inc., 98 Ohio St.3d 330, 2003-Ohio-1099, 784

N.E.2d 1172, ¶ 12.

The Nature of the Probable Environmental Impact

{¶ 65} Here, R.C. 4906.10(A)(2) required the board to find and determine

the nature of the probable environmental impact of constructing, operating, and

maintaining the proposed wind farm in Lake Erie. Something is “probable” when

it is “based on or arises from adequate fairly convincing though not absolutely

23

SUPREME COURT OF OHIO

conclusive intrinsic or extrinsic evidence or support.” Webster’s Third New

International Dictionary 1806 (1993). It is “probable” if it “can reasonably and

fairly convincingly be accepted as true, factual, or possible without being

undeniably so.” Id. The word “probable” “applies to that which is so supported by

evidence that is adequate although not conclusive or by reason that it is worthy of

belief or acceptance.” Id.

{¶ 66} In this case, the board did not find and determine the nature of all the

probable environmental impacts of Icebreaker’s proposed wind farm. As the

majority points out, the most contentious question before the board was the

proposed facility’s probable environmental impact on wildlife, including birds and

bats. Yet in discussing the proposed facility’s environmental impact, the board

“recognized that the actual quantifiable impact [on birds and bats] is still unknown.”

(Emphasis added.) Power Siting Bd. No. 16-1871-EL-BGN, ¶ 105 (May 21, 2020).

According to the board, that did not preclude it from granting the certificate

because, in its view, R.C. 4906.10(A)(2) tasked it “with identifying the nature of

the probable impact, not the actual impact.” Id. at ¶ 107. The board essentially

assumed that the actual environmental impact of the project could be addressed

later.

{¶ 67} However, the board’s distinction between probable impact and

actual impact is a false one. The difference between a probable impact and an

actual one is the degree of certainty and the weight of evidence supporting whether

the impact will occur or has occurred. R.C. 4906.10(A)(2) requires the board to

determine the actual impacts that are likely to occur, including impacts on wildlife

such as avian and aquatic animals. Data about the number and density of birds and

bats passing through the project area was therefore necessary to determine how

those animals would be impacted by constructing a wind farm in their habitat. The

board cannot simply wait and see what evidence will be generated after it grants a

certificate. Rather, the board has a gatekeeping role of ensuring that the

24

January Term, 2022

environmental impacts of a facility are known and justified by public need before

the facility is constructed.

{¶ 68} The majority points out that “the board generally cited myriad

scientific studies submitted as evidence that monitored birds and bats flying in the

vicinity of the project site and other offshore and near-shore parts of Lake Erie.”

Majority opinion, ¶ 17. However, those studies could not reveal the full impact of

the proposed wind farm. For example, the studies that the board cited included

ones in which bird and bat carcasses were retrieved from the areas beneath land-

situated wind turbines and then counted. Power Siting Bd. No. 16-1871-EL-BGN,

at ¶ 105 (May 21, 2020). At a basic level, such studies show that wind turbines

impact wildlife by killing birds and bats. But studies quantifying the impact that

onshore wind farms have on wildlife are relevant here only to the extent that all

other variables in the studies are controlled, i.e., that birds and bats pass through

the rotor-swept zones of offshore facilities at the same frequency and in the same

concentrations as they do at onshore facilities. Such a basis for comparison was

not established by the evidence before the board.

{¶ 69} According to the testimony of Dr. Henry M. Streby, an ecology

professor with the University of Toledo, “[t]ens of millions to hundreds of millions

of birds fly over Lake Erie during every spring and fall migration.” And Dr. Streby

explained, “To date, no study has been conducted that could provide a scientifically

credible count or estimate of the number of birds that pass through the proposed

project area during any time period.” Dr. Streby opined that “adequate pre-

construction monitoring of bird activity in the Project area has not been completed,

rendering it impossible to make a reliable determination of the nature of the

probable environmental impact of the Project on birds.”

{¶ 70} Similarly, Erin Hazelton, the wind-energy administrator for the Ohio

Department of Natural Resources, Division of Wildlife, who coauthored the staff’s

report of its investigation regarding the proposed facility, disputed Icebreaker’s

25

SUPREME COURT OF OHIO

assessment that the proposed project would pose only a “low risk” to migratory

birds and bats. When asked whether she believed that “th[e] project is anything

other than low risk to migratory birds and bats,” Hazelton testified, “[W]e don’t

have the required data concerning pre-construction surveys, [so] it’s really difficult

to determine that now. So it may be accurate. It’s also possible that it’s not entirely

accurate.” The board’s staff report further noted that “there are still elements of

avoidance, attraction, and/or displacement that cannot be evaluated until the project

is constructed.”

{¶ 71} In an attempt to quantify the environmental impact of the proposed

facility, Icebreaker relied in part on a review of aerial surveys of birds flying over

Lake Erie. But these surveys tracked larger sea birds and were conducted by flying

an airplane across Lake Erie 29 times in a zigzag pattern between the Ohio shore

and the Canadian international boundary. During the flights, observers counted the

birds they saw over 664 miles of travel. However, Lake Erie’s surface area is about

10,000 square miles. The reliability of the results of these flyovers was therefore

limited by the small area that each flight covered, the limited ability to observe the

birds and bats (due to their size, their colors and the color of the water, and their

behaviors), meteorological factors such as the weather, and the heights of waves.

Naturally, these surveys could detect only relatively large birds, and birds could not

be accurately observed at night, despite that (as the majority points out) the

proposed wind farm was expected to primarily impact nocturnally migrating birds

and bats. These aerial studies provide little evidence quantifying the risk that the

proposed wind farm would pose to wildlife.

{¶ 72} The bird-and-bat risk assessment submitted by Icebreaker noted that

data from a NEXRAD weather-radar analysis of birds and offshore acoustic studies

of birds and bats revealed that “bats and many nocturnally migrating birds regularly

transit the Project area.” But as Dr. Streby pointed out, avian radar-detection

systems provide more useful data than NEXRAD weather-radar sweeps, because

26

January Term, 2022

NEXRAD radar does not encompass the rotor-swept zone and is not designed to

monitor migratory animals—it generally cannot track or quantify low-flying

animals. Dr. Streby provided evidence that “as early as 2010 the [United States

Fish and Wildlife Service] informed Icebreaker of the inappropriateness of

NEXRAD radar data for quantifying the use of the proposed project site by

migratory birds in the spring and fall.” Icebreaker’s risk assessment admitted that

“[t]he extent to which nocturnally transiting bird and bat migrants may exhibit

either avoidance or attraction to the facility is impossible to predict with

preconstruction data.” And it stated that although “[b]irds and bats are known to

collide with wind turbine blades causing injury or death[,] * * * [l]ess is known

about collision rates at offshore wind energy facilities.”

{¶ 73} Moreover, Icebreaker’s bird-and-bat-monitoring plan recognized

that “[d]ue to the unprecedented nature of this demonstration project, protocols for

determining potential impacts to birds and bats in an offshore environment have

not been previously established for the Great Lakes.” That plan explained that “[i]t

is critical that sufficient and accurate data are collected pre- and post-construction

in order to evaluate risk of the Project to avian and bat species.” This is exactly the

type of data that the board needed in order for it to find and determine the probable

environmental impact of the proposed wind farm, and such data was not submitted

to the board.

{¶ 74} The board granted the certificate of environmental compatibility and

public need even though the data needed to quantify the project’s impact on birds

and bats had not yet been collected and would not be collected until after

construction of the wind farm. The board therefore failed to require Icebreaker to

provide sufficient evidence showing the probable environmental impact of the

proposed wind farm. Because the board did not have sufficient evidence by which

to determine the nature of the probable environmental impact of the project, the

board should have denied Icebreaker’s application for a certificate.

27

SUPREME COURT OF OHIO

The Minimum Adverse Environmental Impact

{¶ 75} The board’s failure to determine the nature of the proposed wind

farm’s probable environmental impact also precluded it from making the finding

required under R.C. 4906.10(A)(3), which conditions the granting of a certificate

for the construction, operation, and maintenance of a major utility facility on “the

facility[’s] represent[ing] the minimum adverse environmental impact, considering

the state of available technology and the nature and economics of the various

alternatives, and other pertinent considerations.” The board cannot find that the

project represents the minimum adverse environmental impact without first

establishing the environmental impacts that the facility is likely to have.

{¶ 76} The board’s finding that the project satisfies R.C. 4906.10(A)(3) is

erroneous for another reason: the board’s decision to grant the certificate relied on

technology designed to minimize the environmental impact that does not currently

exist and is expected to be identified and developed sometime in the future.

{¶ 77} R.C. 4906.10(A)(3) does not prohibit the board from approving

proposed facilities that will have some environmental impact. Rather, the provision

requires the board to ensure that the proposed facility will minimize adverse

environmental impact when it is technologically and economically feasible to do

so. But here, the board found that the proposed wind farm would have a minimum

environmental impact by relying on a state of technology that currently does not

exist.

{¶ 78} For example, the board required Icebreaker to use a collision-

detection system so that the turbines could be feathered in the event that a specified

number of birds and bats collide with the turbines’ rotors within a 24-hour period.

Power Siting Bd. No. 16-1871-EL-BGN, at ¶ 152 (May 21, 2020). Yet it

acknowledged that “no specific technology has been chosen to date because

[Icebreaker] wants to ensure the latest technologies and advancements are being

utilized at the project, consistent with the intent of the statutory criterion to consider

28

January Term, 2022

‘the state of available technology’ and ‘other pertinent considerations,’ including

the fact that the application requests approval of a demonstration project.” Id. at

¶ 157, quoting R.C. 4906.10(A)(3). The board reasoned that “a portion of the initial

demonstration will be used to determine the collision monitoring technology’s

detection efficiency.” Id. at ¶ 158. That is so, it explained, because “the ability to

calculate and assess the actual environmental impact relies on technology and data

that is, to an extent, unknown.” Id. at ¶ 160. The board continued: “[T]his is to be

expected given the unprecedented nature of this project and that the purpose of this

demonstration project is to explore these uncertainties.” Id. And Icebreaker’s bird-

and-bat-monitoring plan recognized that “no proven effective technologies to

perform bird/bat collision monitoring at offshore wind energy facilities are

currently available.”

{¶ 79} But nothing in R.C. 4906.10(A)(3) permits the board to grant a

certificate based on unproven technology, nor does it envision a “process allowing

Staff to make the ultimate determination of whether the project represents the

minimum adverse environmental impact, without Board oversight or a public

hearing, after the Board’s issuance of the certificate,” Power Siting Bd. No. 16-

1871-EL-BGN, at ¶ 138 (May 21, 2020). Yet that is what the board’s order

contemplates. See id. at ¶ 152 (conditioning the grant of the certificate on “the

collision-detection technology [being] demonstrated to [the Ohio Department of

Natural Resources’] satisfaction through lab and field testing prior to start of

construction”); id. (“[the Ohio Department of Natural Resources] and Staff will

have the authority to direct mandatory feathering from March 1 through January 1,

during all nighttime hours, in the event the collision-detection system does not

accurately detect collisions”).

There Is No Exception for “Demonstration Projects” in R.C. 4906.10

{¶ 80} The board essentially held Icebreaker’s proposed wind farm in Lake

Erie to a lesser degree of scrutiny because, “as a first-of-its-kind project[,] the actual

29

SUPREME COURT OF OHIO

impacts of the facility are, naturally, still unknown.” Power Siting Bd. No. 16-

1871-EL-BGN, at ¶ 2 (May 21, 2020). The board explained that “as an

unprecedented demonstration project, unknown risks are to be expected and * * *

a major purpose of this project is to gather information about the impacts of an

offshore wind project in the Great Lakes.” Id. at ¶ 148. Again, it also noted that

“the ability to calculate and assess the actual environmental impact relies on

technology and data that is, to an extent, unknown.” Id. at ¶ 160. Therefore,

although it concluded that “the projected risk to avian and bat species associated

with this small demonstration projected is expected to be low,” the board

“recogniz[ed] * * * that there is a considerable unknown risk associated with the

number and density of birds and bats potentially migrating through the rotor-swept

zone.” Id. at ¶ 148.

{¶ 81} However, R.C. 4906.10(A)(3) does not relax the requirements for

granting a certificate for “demonstration projects.” The same criteria apply to all

proposed major utility facilities. And the provision is phrased in the present tense:

“The board shall not grant a certificate for the construction, operation, and

maintenance of a major utility facility * * * unless it finds and determines * * * (3)

[t]hat the facility represents the minimum adverse environmental impact,

considering the state of available technology and the nature and economics of the

various alternatives, and other pertinent considerations.” (Emphasis added.) The

findings that must be made before a certificate may be granted are therefore

unambiguous. And if the board is unable to make those findings at the time that it

reviews an application for a certificate—because the environmental impacts are

uncertain or because the technology needed to minimize them is unproven—the

board has no choice but to deny the application.

{¶ 82} It may make good policy to loosen the rules for an “unprecedented”

project that will advance science concerning wind energy. But “as a creature of

statute, the [board’s] authority is limited by the statutory scheme that created it.”

30

January Term, 2022

Northeast Ohio Regional Sewer Dist. v. Bath Twp., 144 Ohio St.3d 387, 2015-Ohio-

3705, 44 N.E.3d 246, ¶ 3. “ ‘[A] fundamental principle of the constitutional

separation of powers among the three branches of government is that the legislative

branch of government is “the ultimate arbiter of public policy.” ’ ” Kaminski v.

Metal & Wire Prods. Co., 125 Ohio St.3d 250, 2010-Ohio-1027, 927 N.E.2d 1066,

¶ 59, quoting Arbino v. Johnson & Johnson, 116 Ohio St.3d 468, 2007-Ohio-6948,

880 N.E.2d 420, ¶ 21, quoting State ex rel. Cincinnati Enquirer, Div. of Gannett

Satellite Information Network, Inc. v. Dupuis, 98 Ohio St.3d 126, 2002-Ohio-7041,

781 N.E.2d 163, ¶ 21. If it is necessary to “refine Ohio’s laws to meet the needs of

our citizens,” that role belongs to the General Assembly. Id.

{¶ 83} In sum, the record in this case demonstrates that the board approved

Icebreaker’s application for a certificate of environmental compatibility and public

need without making the findings required under R.C. 4906.10. It therefore erred

in granting the application. Consequently, I would reverse the board’s order

granting the certificate. Because the majority does not, I dissent.

_________________

Benesch, Friedlander, Coplan & Aronoff, L.L.P., Mark D. Tucker, and

John F. Stock, for appellants.

Dave Yost, Attorney General, John H. Jones, Section Chief, and Thomas G.

Lindgren, Kyle L. Kern, Cameron F. Simmons, and Katherine Walker, Assistant

Attorneys General, for appellee.

Dickinson Wright, P.L.L.C., Christine M.T. Pirik, Terrence O’Donnell,

Jonathan R. Secrest, Sara H. Jodka, and William V. Vorys, for intervening appellee.

Taft, Stettinius & Hollister, L.L.P., Aaron M. Herzig, and Anna M. Greve,

urging affirmance for amicus curiae Great Lakes Towing Company.

Miranda Leppla, Trent Dougherty, and Chris Tavenor, urging affirmance

for amicus curiae Ohio Environmental Council.

_________________

31