Opinion

New Jersey Board of Public Utilities v. FERC

Court
Court of Appeals for the D.C. Circuit
Filed
Aug 9, 2022
Status
Published
Cited by
0 cases
Authority
More cited than 1.2%

The opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued March 14, 2022 Decided August 9, 2022

No. 15-1183

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

HUDSON TRANSMISSION PARTNERS, LLC, ET AL.,

INTERVENORS

Consolidated with 15-1188, 16-1153, 19-1002, 20-1074, 20-

1077, 20-1082, 20-1269, 20-1351, 20-1382

On Petitions for Review of Orders

of the Federal Energy Regulatory Commission

Richard P. Bress argued the cause for petitioners. With

him on the joint briefs were Neil H. Butterklee, Susan J.

LoFrumento, Sebrina M. Greene, Gary D. Levenson, William

R. Hollaway, Lucas C. Townsend, David L. Schwartz, Eric J.

Konopka, Shannon M. Grammel, Lawrence G. Acker, Gary D.

Bachman, and Michael Diamond. Elias G. Farrah and Andrew

F. Neuman entered appearances.

2

Kevin M. Lang, John Sipos, John C. Graham, and Alina

Buccella were on the joint brief for intervenors City of New

York and New York State Public Service Commission in

support of petitioners.

Elizabeth E. Rylander, Attorney, Federal Energy

Regulatory Commission, argued the cause for respondent.

With her on the brief were Matthew R. Christiansen, General

Counsel, Robert H. Solomon, Solicitor, and Susanna Y. Chu,

Attorney.

David M. Gossett argued the cause for intervenors

American Electric Power Service Corporation, et al. in support

of respondent. With him on the joint brief were John

Longstreth, Donald A. Kaplan, Richard P. Sparling, Stacey

Burbure, Cara J. Lewis, and Steven M. Nadel. Kenneth R.

Carretta, Amanda R. Conner, Vilna W. Gaston, William M.

Keyser III, Morgan Parke, Bradley Miliauskas, and P. Nikhil

Rao entered appearances.

No. 20-1079

NEW JERSEY BOARD OF PUBLIC UTILITIES,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

PUBLIC SERVICE ELECTRIC AND GAS COMPANY, ET AL.,

INTERVENORS

Consolidated with 20-1080, 20-1081

3

On Petitions for Review of Orders

of the Federal Energy Regulatory Commission

Alec Schierenbeck, Deputy State Solicitor, Office of the

Attorney General for the State of New Jersey, argued the cause

for petitioner. With him on the briefs were Andrew J. Bruck,

Acting Attorney General, and Paul Youchak and Nathaniel

Levy, Deputy Attorneys General. Alex Moreau, Deputy

Attorney General, entered an appearance.

Susanna Y. Chu, Attorney, Federal Energy Regulatory

Commission, argued the cause for respondent. With her on the

brief were Matthew R. Christiansen, General Counsel, Robert

H. Solomon, Solicitor, and Elizabeth E. Rylander, Attorney.

Lucas C. Townsend argued the cause for intervenors

Consolidated Edison Company of New York, Inc., et al. in

support of respondent. With him on the brief were Neil H.

Butterklee, Susan J. LoFrumento, Richard P. Bress, David L.

Schwartz, Eric J. Konopka, Gary D. Levenson, William R.

Hollaway, Lawrence G. Acker, Gary D. Bachman, and Brian

M. Zimmet.

Before: KATSAS and RAO, Circuit Judges, and

SILBERMAN, Senior Circuit Judge.

Opinion for the Court filed PER CURIAM.

PER CURIAM: Part of the electricity transmission grid in

northern New Jersey was aging, storm-damaged, and

vulnerable to short circuits. In response, PJM Interconnection,

LLC (“PJM”)—the regional transmission organization

4

responsible for managing the grid in New Jersey—authorized

a series of upgrades to facilities owned by the Public Service

Electric and Gas Company (“PSE&G”). One set of

improvements centered on the transmission corridor between

PSE&G’s Bergen and Linden switching stations; a second

involved repairs to and around PSE&G’s Sewaren substation.

Together, these two projects cost around $1.3 billion. Initially,

PJM assigned most of the projects’ costs to entities that reroute

electricity from northern New Jersey into the New York

market. Thereafter, the New York-based entities gave up their

rights to withdraw electricity from New Jersey, and PJM

reassigned their costs to PSE&G.

The Federal Energy Regulatory Commission (“FERC” or

“the Commission”) approved both rounds of cost allocations.

The petitions for review in these two cases are about whether

these cost allocations were “just and reasonable” under the

Federal Power Act, 16 U.S.C. §§ 824d(a), 824e(a), and

whether FERC’s orders were “arbitrary [and] capricious” in

violation of the Administrative Procedure Act (“APA”), 5

U.S.C. § 706(2)(A). In effect, they are about who must pay the

bill.

I.

The thirteen petitions for review before us challenge

twenty FERC orders, involve numerous parties, implicate a

series of related legal issues, and arise from a complex

procedural history. We begin by setting out the regulatory and

factual background needed to understand these petitions.

A.

The Federal Power Act gives FERC “jurisdiction over

facilities that transmit electricity in interstate commerce,” Old

Dominion Elec. Coop. v. FERC, 898 F.3d 1254, 1255 (D.C.

5

Cir. 2018), and requires that the rates charged for such

transmission be “just and reasonable,” 16 U.S.C. § 824d(a).

“For decades, the Commission and the courts have understood

this requirement to incorporate a ‘cost-causation principle’—

the rates charged for electricity should reflect the costs of

providing it.” Old Dominion, 898 F.3d at 1255. “[A]lthough

the Commission need not allocate costs with exacting

precision, the costs assessed against a party must bear some

resemblance to the burdens imposed or benefits drawn by that

party.” Pub. Serv. Elec. & Gas Co. v. FERC (“Artificial

Island”), 989 F.3d 10, 13 (D.C. Cir. 2021) (cleaned up).

Utilities, independent system operators, and regional

transmission organizations must seek approval from FERC for

new rates through the process outlined in section 205 of the

Federal Power Act. See 16 U.S.C. § 824d(d)–(e). Section 206

permits “the Commission [to] investigate—on its own

initiative or based on a third-party complaint—whether an

existing rate is ‘unjust, unreasonable, [or] unduly

discriminatory.’” Artificial Island, 989 F.3d at 13 (quoting 16

U.S.C. § 824e(a)). “[U]ndue discrimination occurs [where]

entities [that] are similarly situated” are charged different rates

for no discernable reason. Mo. River Energy Servs. v. FERC,

918 F.3d 954, 958 (D.C. Cir. 2019) (cleaned up). In a section

206 proceeding, if FERC finds the existing rate is “unjust,

unreasonable, [or] unduly discriminatory,” it must “determine

the just and reasonable rate.” 16 U.S.C. § 824e(a).

B.

These petitions arise out of the legal relationships between

the parties as well as the FERC-approved method by which

PJM allocates the costs of major infrastructure projects on its

transmission grid.

6

1.

PJM is the regional transmission organization responsible

for coordinating the transmission of electricity in the mid-

Atlantic region, which stretches from North Carolina to New

Jersey. The dominant electricity provider in northern New

Jersey is PJM-member PSE&G. Across the Hudson River, the

New York grid is managed by the New York Independent

System Operator, Inc. (“NYISO”). Electricity in New York

City is transmitted and sold by the Consolidated Edison

Company of New York, Inc. (“ConEd”) and the New York

Power Authority (“NYPA”), among other utilities.

The PJM and NYISO grids are interconnected, with large

quantities of electricity flowing between New Jersey and New

York across the jurisdictional line. Two of the longstanding

connections between these grids are central to the petitions

before us. First, beginning in the 1970s, PSE&G entered into

an electricity swapping agreement with ConEd. The parties

clarified the terms of this “wheeling agreement” most recently

in a 2009 settlement. See PJM Interconnection, LLC, 132

FERC ¶ 61,221 (2010) [ConEd-PSE&G Settlement Order].

Under the settlement, ConEd agreed to redirect 1,000

megawatts of electricity from upstate New York into PSE&G’s

transmission network in northern New Jersey; in return,

PSE&G agreed to route the same amount of electricity from

New Jersey into New York City. Id. at P 23. This wheeling

agreement allowed ConEd to serve its customers in New York

City without having to build a new transmission line into the

city. See id. at P 2.

Second, because the prices of electricity on the PJM and

NYISO grids sometimes diverge, a handful of “merchant

transmission facilities” have sprung up to capitalize on the

arbitrage opportunity. Two such facilities—Linden VFT, LLC

7

(“Linden”) and Hudson Transmission Partners, LLC

(“Hudson”)—are petitioners here. When prices in New Jersey

are lower, Linden and Hudson reroute electricity from New

Jersey into the New York market and resell it at a profit. 1 In

order to provide reliable, on-demand service to their New York

customers, Linden and Hudson have historically held “firm

transmission withdrawal rights,” which permit them to extract

an agreed-upon amount of electricity from the PJM grid at

(almost) any time.

2.

One of PJM’s primary responsibilities is overseeing the

coordinated development of the mid-Atlantic grid and

apportioning the costs of major grid improvements among its

member utilities.

In 2011, FERC’s “Order No. 1,000” directed each

planning region to select an ex ante “method, or set of methods,

for allocating the costs of new transmission facilities selected

in [its] regional transmission plan,” and to submit their chosen

method for FERC’s approval. Transmission Planning and

Cost Allocation by Transmission Owning and Operating

Public Utilities, 136 FERC ¶ 61,051 at P 558 (2011) [Order

No. 1,000]; see id. at P 603. The Commission gave each region

leeway to design its own cost allocation method, id. at PP 605–

06, but set out six general cost allocation principles that are

binding on all planning regions. As relevant here, Order No.

1,000 requires that every region’s cost allocation method

reflect the Federal Power Act’s cost causation principle

(Principle 1), and that the costs of any new project be assigned

1

Hudson’s primary customer is NYPA. By contract, NYPA is

responsible for the full costs of any improvements to the PJM grid

that are assigned to Hudson.

8

only to parties within the project’s planning region, unless a

party outside the region agrees to assume costs (Principle 4).

Id. at PP 622, 657. Order No. 1,000 required each region to use

its ex ante cost allocation method only for “regional plan”

projects—that is, projects undertaken to meet the region’s

minimum transmission capacity and grid reliability criteria.

See Old Dominion, 898 F.3d at 1256.

Pursuant to Order No. 1,000, PJM developed an ex ante

cost allocation method and incorporated it into its Open Access

Transmission Tariff. For projects that improve grid reliability,

PJM’s method allocates half the costs of high-voltage facilities,

and all the costs of low-voltage facilities, through a “flow-

based method” called “solution-based distribution-factor

analysis,” or “DFAX.” See PJM Tariff, Sched. 12(b)(iii). As

explained further below, see infra Part IV.A.1, “[t]he flow-

based method assigns costs based on how much each utility

uses the facility in question over time,” Long Island Power

Auth. v. FERC, 27 F.4th 705, 711 (D.C. Cir. 2022); see

Artificial Island, 989 F.3d at 14. Using proprietary software,

the DFAX method models how electricity will flow across a

new transmission facility at moments of peak grid use (i.e., at

“peak load”), and assigns costs proportionally, based on the

projected use of the facility by utilities in each “zone” of the

PJM grid. PJM spreads the DFAX costs of regional plan

projects over a number of years, to account for utilities’

evolving use of the grid.

The DFAX method also assigns costs to entities that

withdraw electricity from the PJM grid. Merchant

transmission facilities like Linden and Hudson are assigned

DFAX costs based on their firm withdrawal rights. See PJM

Tariff, Sched. 12(b)(iii)(A)(3). In other words, the DFAX

method assumes that when the grid is running at peak load,

merchant transmission facilities will extract the full amount of

9

electricity to which they are entitled. Similarly, the DFAX

method assigns ConEd costs based on the assumption that,

pursuant to its wheeling agreement with PSE&G, ConEd will

withdraw 900 megawatts from the PJM grid when it is at peak

load. See id. Sched. 12(b)(xi); ConEd-PSE&G Settlement

Order, 132 FERC ¶ 61,221 at P 13.

FERC approved PJM’s cost allocation method in 2013.

See PJM Interconnection, LLC, 142 FERC ¶ 61,214 (2013).

C.

This brings us to the two projects at issue here. In 2013,

PJM approved 26 related improvements to the transmission

corridor between PSE&G’s Bergen and Linden switching

stations (collectively, “the Bergen project” or “Bergen”). The

purpose of the Bergen project was not to increase the total

amount of electricity that can flow across the PJM grid; rather,

the project was approved to mitigate the risk of short circuits

on PSE&G’s facilities. Because the anticipated short circuits

would overwhelm any commercially available circuit breaker,

PJM directed PSE&G to expand the corridor into a double-

circuit line capable of transmitting electricity at higher

voltages. This solution to PSE&G’s short-circuit issue

incidentally protected the corridor against thermal overloads.

Around the same time, PJM approved three low-voltage

subprojects to repair aging infrastructure in and around

PSE&G’s Sewaren substation (“the Sewaren project” or

“Sewaren”). Hurricane Sandy had exposed Sewaren’s

vulnerability to inclement weather. These upgrades were

meant to harden it against future storms and protect it from

short circuits. Like Bergen, the Sewaren project was not

approved to increase the overall transmission capacity of the

PJM grid. Rather, both were “reliability projects” intended to

make the grid’s existing infrastructure more resilient.

10

D.

In 2014, PJM first assigned the costs of the Bergen and

Sewaren projects in two section 205 filings. Those initial cost

allocations triggered a long-running series of FERC

proceedings that only recently concluded, giving rise to the

petitions under review.

1.

We begin at the beginning, with PJM’s 2014 rate filings.

Pursuant to its Tariff, PJM allocated most of the costs of the

Bergen project ($763 million, out of a total cost of $1.2 billion),

and all the costs of the Sewaren project ($125 million), via

DFAX. 2 PJM’s 2014 filings assigned most of the DFAX costs

for Bergen to ConEd ($629 million), with the remainder spread

between Hudson ($69 million), PSE&G ($52 million), and

Linden ($13 million). The costs of Sewaren, meanwhile, were

split between ConEd ($64 million) and Linden ($61 million).

In two subsequent 2015 and 2016 filings, PJM reallocated

Bergen’s DFAX costs to reflect the project’s evolving design

and updated grid-use data. 3

2

Most of the Bergen subprojects were high-voltage; a few were low-

voltage. For the former, half the costs were allocated on a pro rata

basis—“based on the level of customer demand within each zone”

on the PJM grid—rather than through DFAX. Old Dominion, 898

F.3d at 1256; see PJM Tariff, Sched. 12(b)(i)(A)(1). Those pro rata

cost allocations are not at issue in the petitions before us.

3

In early 2015, PJM changed its Tariff’s cost allocation method for

projects, like Sewaren, that are added to the regional plan to meet the

planning standards of individual utilities. See PJM Interconnection,

LLC, 154 FERC ¶ 61,096 at PP 2, 12 (2016). Beginning in 2015,

therefore, PJM ceased assigning Sewaren’s costs via DFAX.

11

Over the protests of ConEd, Linden, Hudson, and NYPA,

FERC accepted each of the four cost allocations. The

protestors argued that the DFAX method was built on certain

modeling conventions that systematically distorted the cost

assignments for the Bergen and Sewaren projects, minimizing

PSE&G’s cost responsibility and magnifying theirs. 4 See infra

Part IV. More fundamentally, they argued that PJM’s rate

filings violated the cost causation principle: the goal of these

projects was to make PSE&G’s infrastructure more reliable,

yet parties other than PSE&G had been assigned the vast

majority of the costs. Finally, they protested that the Tariff

gave PJM discretion to adjust any “objectively unreasonable”

DFAX cost allocation, but that PJM had unfairly declined to

exercise that discretion in the filings at issue. PJM Tariff,

Sched. 12(b)(iii)(G).

In response, FERC explained that it had previously

approved DFAX as a just and reasonable cost allocation

method. PJM had properly applied this cost allocation method

in the contested filings, so they were per se just and reasonable.

Because “[t]he reasonableness of the Solution-Based DFAX

methodology is beyond the scope of [a section 205]

proceeding,” FERC declined to scrutinize the DFAX method’s

modeling conventions. PJM Interconnection, LLC, 147 FERC

¶ 61,028 at P 43 (2014). Finally, FERC agreed with PJM that

4

The protestors argued that, by design, the DFAX method arbitrarily

favors large utilities like PSE&G at the expense of smaller entities.

More specifically, they insisted that it was not just and reasonable for

PJM’s Tariff (1) to exempt from DFAX costs any utility whose flows

across a facility are de minimis compared to its overall flows on the

PJM grid; (2) to “net” total flow, such that a utility’s positive and

negative electric flows cancel each other out; and (3) to base DFAX

costs on how electricity flows across the grid at peak load.

12

the Tariff did not give it the discretionary authority to adjust

DFAX costs ex post.

2.

Meanwhile, shortly after PJM made its initial 2014 filings,

ConEd and Linden each lodged section 206 complaints. First,

they again objected to the structural assumptions on which the

DFAX method was built. Second, they argued that it was not

just and reasonable to use DFAX to assign the Bergen and

Sewaren projects’ costs. Most projects selected for PJM’s

regional plan are “flow-based”—they are approved in response

to pent-up transmission demand and expand the total amount

of electricity that can flow across the PJM grid. DFAX was

designed with such projects in mind, on the grounds that

utilities should pay for grid expansions based on their use of

the grid’s increased capacity. But Bergen and Sewaren were

categorically distinct; they are “non-flow-based.” The short-

circuit issues they resolved were not caused by excessive

electricity flows across PSE&G’s facilities, and the utilities

who benefited from their resolution were different from those

whose electricity flows across the upgraded facilities. The

DFAX method therefore failed to match the costs of these

projects to their beneficiaries, as required by the Federal Power

Act.

FERC addressed ConEd’s complaint first. The policy

behind Order No. 1,000, it explained, was to establish a clear,

ex ante cost allocation method for major infrastructure projects

in each planning region. To that end, PJM’s Tariff did not give

it discretion to apply different cost allocation methods to

different kinds of reliability projects. FERC also found that the

DFAX method reasonably identified the beneficiaries of non-

flow-based projects, and so rejected the argument that the

DFAX method was unsuited to Bergen and Sewaren. See

13

Consol. Edison Co. of N.Y., Inc., 151 FERC ¶ 61,227 at PP 54–

55 (2015) [ConEd Complaint Order].

In 2016, FERC reaffirmed this position on rehearing, see

Consol. Edison Co. of N.Y., Inc., 155 FERC ¶ 61,088 at PP 40–

42 (2016) [ConEd Complaint Rehearing Order], and rejected

Linden’s complaint for the same reasons, see Linden VFT,

LLC, 155 FERC ¶ 61,089 at PP 54–58 (2016) [First Linden

Complaint Order]. In addition, FERC upheld the DFAX

method’s modeling conventions as just, reasonable, and not

unduly discriminatory. See ConEd Complaint Rehearing

Order, 155 FERC ¶ 61,088 at PP 45–46, 49.

Importantly, at the same time it rejected ConEd and

Linden’s complaints, FERC also affirmed the use of DFAX in

a closely related proceeding, which concerned the costs of a

third non-flow-based project in southern New Jersey (“the

Artificial Island project” or “Artificial Island”). See Del. Pub.

Serv. Comm’n, 155 FERC ¶ 61,090 at PP 65–73 (2016)

[Artificial Island Order].

3.

Soon after FERC denied its rehearing application, ConEd

notified PSE&G that it planned to allow their wheeling

agreement to lapse. PJM thereafter submitted a fifth cost

allocation, to take effect after the wheeling agreement ended.

This 2017 filing eliminated ConEd’s cost liability entirely,

placing Bergen’s DFAX costs onto Hudson ($634 million),

Linden ($132 million), and PSE&G ($128 million). The New

Jersey Board of Public Utilities (“the Board”) objected to the

filing on behalf PSE&G’s customers; Linden, Hudson, and

NYPA objected as well. Linden also lodged a section 206

complaint, protesting the cost reallocation. FERC

preliminarily accepted PJM’s 2017 filing, but did not

14

substantively address the cost allocation or Linden’s second

complaint for another three years.

Meanwhile, Hudson and Linden also took steps to

extricate themselves from cost liability for the Bergen project.

PJM’s Tariff assigns DFAX costs to merchant transmission

facilities only if they hold firm withdrawal rights, which entitle

them to extract electricity from the PJM grid on demand. See

PJM Tariff, Sched. 12(b)(iii)(A)(3). Hudson and Linden asked

PJM to convert their firm withdrawal rights to non-firm ones,

which would absolve them of DFAX costs for Bergen going

forward. The New Jersey Board intervened in the ensuing

proceedings, protesting that the proposed conversions would

unfairly foist Bergen’s entire cost onto PSE&G. But FERC

found “no reasonable basis” for preventing Hudson and Linden

from converting their withdrawal rights to non-firm ones.

Linden VFT, LLC, 161 FERC ¶ 61,264 at P 24 (2017) [Linden

Conversion Order]; PJM Interconnection, LLC, 161 FERC

¶ 61,262 at P 42 (2017) [Hudson Conversion Order].

Soon thereafter, the New Jersey Board brought a section

206 complaint. It argued that although ConEd, Linden, and

Hudson were Bergen’s primary beneficiaries, PJM had unfairly

allowed them to evade cost responsibility after construction

had begun, leaving local ratepayers to foot the bill. FERC

disagreed. Under Order No. 1,000, PJM had no authority to

place Bergen’s costs on ConEd—a utility based outside the

PJM region—after the wheeling agreement lapsed. FERC also

approved the part of PJM’s Tariff allocating DFAX costs only

to merchant transmission facilities with firm withdrawal rights.

Since PJM does not have to account for non-firm withdrawal

rights in planning its grid, it made sense to exempt facilities

with such rights from DFAX costs. FERC concluded that the

Tariff’s cost allocation method was just and reasonable and had

been properly applied in the circumstances. See N.J. Bd. of

15

Pub. Utils., 163 FERC ¶ 61,139 at P 50 (2018) [Board

Complaint Order], reh’g denied, 170 FERC ¶ 61,180 (2020)

[Board Complaint Rehearing Order].

4.

In 2018, FERC granted rehearing in the Artificial Island

proceeding—the same complaint it had earlier rejected. See

Artificial Island, 989 F.3d at 15–16 (recounting FERC’s volte-

face). The Artificial Island project was intended to stabilize

three nuclear generators in southern New Jersey. Like the

short-circuit issues remedied by the Bergen and Sewaren

projects, the stability issue that prompted the Artificial Island

project was not caused by pent-up transmission demand. All

three projects, in other words, were “non-flow-based.” After

reconsidering its initial Artificial Island order, FERC

determined that the beneficiaries of at least some non-flow-

based projects—namely, those addressing stability issues—are

“not necessarily captured” by the DFAX method. Del. Pub.

Serv. Comm’n, 164 FERC ¶ 61,035 at P 41 (2018) [Artificial

Island Rehearing Order], reh’g denied, 166 FERC ¶ 61,161

(2019) [Artificial Island Second Rehearing Order]. It therefore

directed PJM to adopt a different cost allocation method for

stability related projects. See Artificial Island Rehearing

Order, 164 FERC ¶ 61,035 at P 42; Artificial Island Second

Rehearing Order, 166 FERC ¶ 61,161 at P 43.

In 2020, FERC disposed of the outstanding filings and

complaints related to the Bergen and Sewaren projects. First,

it denied rehearing of Linden’s first complaint, which

challenged PJM’s 2014 cost allocations. FERC continued to

find that the DFAX method’s modeling conventions were just,

reasonable, and nondiscriminatory, and that DFAX reasonably

captured the beneficiaries of short-circuit projects like Bergen

and Sewaren. See Linden VFT, LLC, 170 FERC ¶ 61,122 at

16

PP 41, 44, 47 (2020) [First Linden Complaint Rehearing

Order].

Second, FERC approved PJM’s 2017 cost reallocation—

the cost distribution that came into effect after the end of

ConEd’s wheeling agreement—and denied Linden’s second

complaint (protesting the same cost allocation). See PJM

Interconnection, LLC, 170 FERC ¶ 61,124 at PP 33–35 (2020)

[Cost Reallocation Order]; Linden VFT, LLC, 170 FERC

¶ 61,123 at PP 31–35 (2020) [Second Linden Complaint

Order]. In a rehearing application contesting both orders,

Linden argued that “the use of the solution-based DFAX

method to allocate costs for a non-flow-based project was

unjust and unreasonable.” PJM Interconnection, LLC, 172

FERC ¶ 61,176 at P 14 (2020) [Second Linden Complaint

Rehearing Order]. The Bergen project “addresses a non-flow

related reliability issue,” just like the non-flow-based stability

issue in Artificial Island, but FERC had treated the two projects

differently. Id. at P 22. In response, FERC explained that it

had made a one-time exception in Artificial Island for stability

related projects, and that no such carve-out was warranted for

short-circuit projects. See id. at PP 22–24. FERC also

reiterated that the DFAX method’s modeling conventions were

just, reasonable, and nondiscriminatory. See id. at PP 27–29.

E.

As FERC successively denied their rehearing applications,

ConEd, Linden, Hudson, and NYPA (collectively, “the New

York entities”) petitioned for review of FERC’s orders

approving PJM’s five cost allocations from 2014 to 2017, as

well as its orders denying ConEd’s complaint and Linden’s two

complaints. Before they had extricated themselves from cost

liability for the Bergen and Sewaren projects, the New York

entities had been assessed approximately $115 million in costs.

17

The petitions in Consolidated Edison Co. of New York, Inc. v.

FERC (“ConEd v. FERC”) challenge FERC’s approval of

those already-paid costs. The City of New York and the New

York State Public Service Commission have intervened on

behalf of the New York entities, arguing against the cost

allocations; a group of transmission owners, including PSE&G,

have intervened on behalf of FERC, arguing in favor of the cost

allocations.

The New Jersey Board petitioned for review of FERC’s

orders permitting Linden and Hudson to convert their firm

withdrawal rights to non-firm ones, as well as its orders

denying the Board’s complaint. The petitions in New Jersey

Board of Public Utilities v. FERC (“New Jersey Board v.

FERC”) concern PJM’s reassignment of Bergen’s DFAX costs

to PSE&G—and, by extension, New Jersey ratepayers—

beginning in 2017. ConEd, Linden, Hudson, NYPA and

NYISO have intervened on FERC’s behalf, in favor of the post-

2017 cost allocations; PSE&G has intervened on the Board’s

behalf, arguing against the post-2017 cost allocations.

The New York entities and New Jersey Board both claim

that FERC’s myriad orders ran afoul of the APA and violated

the Federal Power Act’s cost causation and nondiscrimination

principles. With two inconsequential exceptions, we have

jurisdiction over their petitions under 16 U.S.C. § 825l(b). 5

5

The petition in No. 20-1269 sought review of the Second Linden

Complaint Order after the parties’ application for rehearing was

deemed denied by operation of law. See 16 U.S.C. § 825l(a).

Because that petition was untimely filed, we dismiss it for lack of

jurisdiction. See id. § 825l(b). That dismissal has no practical

consequence, however, because after FERC affirmatively rejected

the parties’ application for rehearing of the same order years later,

18

II.

This court must set aside any order of the Commission that

is “arbitrary, capricious, an abuse of discretion, or otherwise

not in accordance with law.” 5 U.S.C. § 706(2)(A). “In matters

of ratemaking, our review is highly deferential, as issues of rate

design are fairly technical and, insofar as they are not technical,

involve policy judgments that lie at the core of the regulatory

mission.” Alcoa Inc. v. FERC, 564 F.3d 1342, 1347 (D.C. Cir.

2009) (cleaned up). FERC’s ratemaking orders will not stand,

however, if they are “either unreasonable or inadequately

explained.” Artificial Island, 989 F.3d at 17 (cleaned up).

FERC’s reasoning must be grounded in “substantial evidence,”

16 U.S.C. § 825l(b), which is “such relevant evidence as a

reasonable mind might accept as adequate to support a

conclusion,” Myersville Citizens for a Rural Cmty., Inc. v.

FERC, 783 F.3d 1301, 1309 (D.C. Cir. 2015) (cleaned up).

III.

The New York entities argue that FERC failed to

reasonably explain why the DFAX method should be used to

they again petitioned for review—this time in a timely fashion, in

No. 20-1351.

Similarly, we dismiss the petition in No. 20-1077, which seeks

review of FERC’s orders preliminarily accepting PJM’s 2017 cost

reallocation, for lack of jurisdiction. “The decision to accept a rate

filing” without approving its lawfulness “is undeniably

interlocutory” and therefore unreviewable. Papago Tribal Util.

Auth. v. FERC, 628 F.2d 235, 240 (D.C. Cir. 1980). Again, however,

this dismissal is inconsequential, since FERC’s final approval of

PJM’s 2017 filing is properly before us in No. 20-1382, which seeks

review of the Cost Reallocation Order.

19

allocate the costs of the Bergen and Sewaren projects, but

should not be used to allocate the costs of a similar project in

Artificial Island. We agree.

A.

In 2016, FERC determined that DFAX was an appropriate

method of assigning costs for all the projects selected for PJM’s

regional plan, whether they were flow-based or non-flow-

based. Within that latter category, FERC specifically found

that DFAX was appropriate even if “a short-circuit or stability

violation is the [project’s] primary driver.” ConEd Complaint

Rehearing Order, 155 FERC ¶ 61,088 at P 41. It therefore

reasoned that PJM had properly used the DFAX method to

assign the costs of the three non-flow-based projects before

it—Bergen and Sewaren (short-circuit projects) and Artificial

Island (a stability project). “The solution-based DFAX

method,” FERC explained, does not turn on “the immediate

[problem] that drove the need for the project.” Id. at P 40.

While “the initial nature of the problem may not necessarily be

related or entirely related to flows,” DFAX still identifies the

utilities that will use the new facilities and appropriately

assigns them costs. Id. FERC therefore refused to create new

cost allocation methods for different kinds of non-flow-based

projects (stability projects, short-circuit projects, etc.). “[S]uch

a case-by-case … approach,” it found, “would create the same

uncertainty that ex ante cost allocation is intended to avoid.”

ConEd Complaint Order, 151 FERC ¶ 61,227 at P 55.

By the time FERC issued its 2020 orders regarding the cost

allocations for Bergen and Sewaren, however, it had reversed

its position regarding the Artificial Island project. On

rehearing in 2018, FERC distinguished between flow-based

projects on the one hand and stability related projects like

Artificial Island on the other. Flow-based problems, such as

20

“thermal overload and voltage related reliability issues,” are

caused by excessive electricity flows across a facility, and are

therefore resolved by expanding the grid’s transmission

capacity. Artificial Island Rehearing Order, 164 FERC

¶ 61,035 at P 39. As a result, “the change in power flows [is]

consistent with the intended solution.” Id. (quoting a PJM

filing). DFAX reasonably picks out the beneficiaries of such a

project because the utilities that use the upgraded facility are

the same ones whose ability to transmit electricity was

formerly constrained. See id.

By contrast, FERC explained that a stability related

problem like the one in Artificial Island is not caused by

excessive demand (i.e., it is “non-flow-based”). While such a

problem can be solved by expanding the grid’s overall

transmission capacity, the utilities that use that new capacity

are not necessarily the beneficiaries of a stability related

project. Thus, although the “DFAX method will reveal parties’

use of the new transmission facility, such use is neither

connected with the need for the project, nor provides benefits

to the parties being assigned cost responsibility.” Artificial

Island Second Rehearing Order, 166 FERC ¶ 61,161 at P 38.

FERC therefore concluded that while DFAX is just and

reasonable for allocating the costs of flow-based projects, it

was not similarly appropriate for allocating the costs of non-

flow-based projects addressing stability issues. Artificial

Island Rehearing Order, 164 FERC ¶ 61,035 at PP 38–41.

B.

The New York entities argue that FERC should have

extended this same logic to the Bergen and Sewaran projects.

FERC, they say, failed to explain why it continued to apply the

DFAX method to Bergen and Sewaren, even after directing

PJM to use a different method for Artificial Island. All three

21

projects addressed non-flow-based issues, so their costs should

all have been allocated similarly. 6 “A fundamental norm of

administrative procedure requires an agency to treat like cases

alike. If the agency makes an exception in one case, then it

must either make an exception in a similar case or point to a

relevant distinction between the two cases.” Westar Energy,

Inc. v. FERC, 473 F.3d 1239, 1241 (D.C. Cir. 2007).

6

The New York entities raised this objection directly in their

application for rehearing of the Second Linden Complaint Order and

the Cost Reallocation Order. See Second Linden Complaint

Rehearing Order, 172 FERC ¶ 61,176 at P 22. However, they did

not similarly cite Artificial Island when applying for rehearing of the

First Linden Complaint Order, instead arguing generally that “a

flow-based method is the wrong way to measure benefits for non-

flow based reliability concerns, such as the short-circuit concerns

underlying [Bergen and Sewaren].” First Linden Complaint

Rehearing Order, 170 FERC ¶ 61,122 at P 41.

Ordinarily, we lack jurisdiction to consider an argument not

raised before FERC on rehearing “with specificity.” Ameren Servs.

Co. v. FERC, 893 F.3d 786, 793 (D.C. Cir. 2018) (cleaned up). In

this case, however, FERC did not change its position in Artificial

Island until after the parties had applied for rehearing of the First

Linden Complaint Order, so they have a “reasonable ground” for

failing to specifically raise the issue. 16 U.S.C. § 825l(b). At the

time FERC issued the First Linden Complaint Rehearing Order, it

had been considering Artificial Island’s cost allocations alongside

Bergen’s and Sewaren’s for six years and had only recently changed

its approach in Artificial Island. In that context, the parties’ general

argument that DFAX is unsuited to non-flow-based projects was

sufficient to alert FERC to the need to distinguish its recent decision

in Artificial Island from the position it initially took with respect to

Bergen and Sewaren in 2016. We therefore have jurisdiction to

consider whether, in the First Linden Complaint Rehearing Order,

FERC acted arbitrarily in treating Bergen and Sewaren differently

from Artificial Island.

22

In attempting to distinguish the Bergen and Sewaren

projects from Artificial Island, FERC claimed it had “not

ma[de] a generalized finding regarding all non-flow-based

constraints,” Second Linden Complaint Rehearing Order, 172

FERC ¶ 61,176 at P 23, but instead had made a narrow

exception for stability related projects, which are “analytically

unique,” id. at P 24 (citing Artificial Island Rehearing Order,

164 FERC ¶ 61,035 at P 40). FERC explained that in order to

resolve the short-circuit issues on the Bergen-Linden corridor,

PSE&G had expanded the corridor into a double-circuit line

capable of greater electricity flows. This “reconfigur[ation]

[of] the transmission system” was “similar to the planning

process for resolving thermal overloads,” which are flow-

based. Id.; cf. First Linden Complaint Rehearing Order, 170

FERC ¶ 61,122 at P 41. According to FERC, in other words,

the solution PJM adopted for Bergen made it like a flow-based

project, and DFAX was therefore an appropriate way to assign

its costs. Second Linden Complaint Rehearing Order, 172

FERC ¶ 61,176 at P 24.

But in Artificial Island, FERC did not find that stability

projects are “analytically unique” in the abstract. Rather, it

found that “stability is analytically unique compared to voltage

or thermal overload problems,” which are both flow-based.

Artificial Island Rehearing Order, 164 FERC ¶ 61,035 at P 38

(emphasis added). In other words, FERC contrasted the mine-

run of flow-based projects on the PJM grid on the one hand

with the specific, non-flow-based stability project at Artificial

Island on the other. But in the Artificial Island proceeding

FERC said nothing about whether—like stability projects—

short-circuit projects should also be treated differently from

flow-based projects. In fact, the testimony on which it relied

recognized both “the short circuit issue and the stability issue”

as awkward fits for the DFAX method, because neither are

23

flow-based. J.A. 1091–92. 7 Therefore, FERC could not

rationally explain its decision to treat Bergen and Sewaren

differently from Artificial Island by simply pointing to its

earlier finding that “stability is analytically unique compared

to voltage or thermal overload problems.” Instead, FERC

needed to explain why stability is “analytically unique”

compared to short-circuit issues.

FERC failed to do so. It conceded that, like the stability

issue at Artificial Island, “short-circuit problems are not

directly caused by flow overloads on a facility.” First Linden

Complaint Rehearing Order, 170 FERC ¶ 61,122 at P 41.

Nonetheless, FERC reasoned that DFAX should still be used

to assign Bergen’s costs because Bergen was similar to a

thermal overload project. FERC did not adequately explain

why that similarity mattered. Short-circuit issues, not thermal

overloads, were the primary impetus for Bergen. While Bergen

expanded the grid’s overall capacity, the same is true of

Artificial Island. In both cases, the increased capacity

incidentally benefited the utilities whose electricity flows

across the new facilities. Critically, however, other parties also

benefited in both cases. After Bergen’s completion, PSE&G

benefited from facilities that are resistant to short circuits,

while other grid users also benefited from protection against

the second-order effects of short circuits. Likewise, in

Artificial Island, FERC recognized that the utilities that relied

on the generators at issue benefited from their improved

stability. See Artificial Island Second Rehearing Order, 166

FERC ¶ 61,161 at P 39.

Pointing to those other beneficiaries, FERC concluded in

Artificial Island that the utilities whose electricity flows across

7

In this Part and Part IV, citations to the joint appendix refer to the

one in ConEd v. FERC.

24

facilities built to address stability issues should not be assigned

costs via DFAX; instead, it reallocated Artificial Island’s

DFAX costs to the utilities that depended on the newly

stabilized nuclear generators. See id. at PP 13, 43. Here, by

contrast, FERC used DFAX to assign the costs of Bergen and

Sewaren to the utilities whose electricity flows across

PSE&G’s facilities—even though, like Artificial Island, those

projects also conferred non-flow-based benefits to other

entities. Given the similarities between the projects, basic rule

of law principles required FERC to justify its different

treatment of the projects. It needed to explain why, in contrast

to Artificial Island, the costs of Bergen and Sewaren should be

assigned via DFAX to the utilities whose electricity flows

across the upgraded facilities, rather than to the projects’ other

beneficiaries.

We do not hold that the use of the DFAX method for short-

circuit projects violates the cost causation principle per se. On

remand, FERC may be able to provide a more satisfactory

explanation of the distinction between stability related projects

and those that address short-circuit issues and to articulate why

DFAX cost allocations are appropriate for the latter but not the

former. But the Commission “must provide an adequate

explanation to justify treating similarly situated parties

differently.” Comcast Corp. v. FCC, 526 F.3d 763, 769 (D.C.

Cir. 2008). It failed to do so here.

IV.

In addition to challenging the application of the DFAX

method generally, the New York entities attack three specific

conventions used in it: the de minimis threshold, netting, and

the peak-load assumption.

25

A.

We begin with the de minimis threshold.

1.

The DFAX method divides the costs of a transmission

facility among zones in proportion to each zone’s use of the

facility. See First Linden Complaint Rehearing Order, 170

FERC ¶ 61,122 at P 7. For the facility in question, PJM first

uses certain models, which estimate the flow of electricity at

peak demand, to determine what it calls the “distribution

factor” of each zone. The distribution factor for a zone

represents the zone’s use of the facility divided by the zone’s

total load or use of all facilities on the PJM grid. PJM Tariff,

Sched. 12(b)(iii)(A). For example, if a zone uses 1,000

megawatts of electricity from a facility and its total load is

10,000 megawatts, then its distribution factor for the facility is

0.1 or 10%.

PJM then performs various arithmetic calculations to

assign costs based on each zone’s use of the facility at issue.

First, it multiplies the distribution factor of a zone by its total

load, which yields the zone’s use of the facility. Id. Sched.

12(b)(iii)(B)(1). In the example above, the zone’s use of the

facility would be 1,000 megawatts. Second, PJM divides that

number by all zones’ use of the facility. Id. Sched.

12(b)(iii)(B)(2). For example, if a zone uses 1,000 of the 5,000

megawatts from a facility, PJM calculates a quotient of 0.2.

Third, PJM multiplies that quotient by the total cost of the

facility to produce the relevant cost allocation. Id. Sched.

12(b)(iii)(B)(5). If the facility in this example costs $1 million,

PJM would allocate $200,000 in costs to the zone.

The de minimis threshold adds an important qualification

to this process. In FERC’s view, zones that receive very small

26

benefits from a facility should be assigned no costs for it. First

Linden Complaint Rehearing Order, 170 FERC ¶ 61,122 at

P 44. To that end, zones with a distribution factor below 1%

are deemed to have no flows over the facility and thus are

assigned no costs. PJM Tariff, Sched. 12(b)(iii)(A)(6).

Because distribution factors measure a zone’s use of a facility

relative to its total load, the de minimis exception depends on

the size of the zone, not on the zone’s share of the facility’s

total flow. For example, suppose a zone uses 9 megawatts of a

facility’s total flow of 30 megawatts. Although the zone uses

nearly a third of total flow, its use will be deemed de minimis

if, say, the zone itself has a total load of 1,000 megawatts

(which corresponds to a distribution factor of 0.9%). In that

event, the sheer size of the zone will cause it to be assigned no

costs.

2.

As implemented through distribution factors, the de

minimis threshold thus operates as a too-big-to-pay rule. We

agree with the New York entities that this violates the cost

causation principle and causes undue discrimination. The cost

causation principle requires “comparing the costs assessed

against a party to the burdens imposed or benefits drawn by

that party.” Midwest ISO Transmission Owners v. FERC, 373

F.3d 1361, 1368 (D.C. Cir. 2004). And undue discrimination

occurs when similarly situated entities are charged different

rates for no good reason. Mo. River Energy Servs., 918 F.3d at

958. As explained above, the de minimis threshold exempts

zones from bearing any costs based on their load size—a

quality unrelated to the burdens they impose on or the benefits

they receive from any individual facility. And in so doing, it

unduly discriminates against small zones, which must absorb

higher cost allocations after large zones are exempted.

27

Peak load sizes vary greatly across the relevant zones,

which makes the de minimis exception border on absurd. For

instance, the peak load of PSE&G is about 11,000 megawatts,

whereas PJM assigned Linden and Hudson peak loads of only

330 and 320 megawatts respectively. So if PSE&G used 100

megawatts of flow across a transmission facility (yielding a

distribution factor slightly under 1%), and if Hudson had 4

megawatts of flow across the same facility (yielding a

distribution factor slightly over 1%), then PSE&G but not

Hudson would be exempt from paying any of the facility’s

costs, even though PSE&G derived 25 times more of the

benefits. And because the large PSE&G would not have to pay

any costs of the facility, the small Hudson would have to bear

a substantially greater share of those costs.

PJM’s allocations for the Bergen project illustrate this

dynamic. For one subproject, the DFAX method determined

that PSE&G received 65.5% of the benefits, while ConEd and

Hudson together received only about 16%. Yet after applying

the de minimis threshold, PSE&G was removed from the cost

allocation, and so ConEd and Hudson were assigned 99.98%

of the upgrade costs. J.A. 1018–20. And after ConEd

withdrew from its wheeling agreement, PSE&G received

72.7% of the subproject’s benefits and Hudson only 6%. Yet

the de minimis threshold excluded PSE&G from any cost

allocation, and Hudson then became responsible for 99.98% of

the upgrade costs. Id. at 1404–07. Other examples abound.

See, e.g., id. at 1022–23 (PSE&G received 46% of a

subproject’s benefits and ConEd only 27%, yet ConEd was

allocated 100% of its costs); id. at 1295 (listing nine

subprojects for which Hudson received between 6% and 16%

of the benefits, but was allocated over 99% of the costs); id. at

1408–09 (subproject for which Linden and Hudson received

33% of the benefits, but were allocated 100% of the costs).

This scheme plainly violates the rule that FERC “may not

28

single out a party for the full cost of a project, or even most of

it, when the benefits of the project are diffuse.” Old Dominion,

898 F.3d at 1255 (cleaned up). Because the de minimis

threshold regularly produces “wholesale departure[s] from the

cost-causation principle,” it cannot be considered just and

reasonable. See id. at 1261.

3.

FERC asserted three justifications for the de minimis

threshold, but none is persuasive.

First, it observed that the threshold identifies “entities that

have relatively little use of the transmission facility relative to

their load.” First Linden Complaint Rehearing Order, 170

FERC ¶ 61,122 at P 44. Similarly, the intervenors supporting

FERC characterize the threshold as a measure of relative

reliance—i.e., the degree to which a zone depends on one

facility instead of others—as opposed to relative use. These

are accurate statements of how the threshold works, but they

are not justifications for a threshold keyed to the relative size

of the zone, rather than to the relative use of the facility.

Second, FERC denied that the de minimis threshold

depends on a zone’s size. Id. at P 45. The Commission is

correct that the threshold is keyed to a distribution factor,

which measures the shift in power over a transmission facility

when a zone’s peak load is increased by one megawatt,

regardless of its size. PJM Tariff, Sched. 12(b)(iii)(A). But

this measurement is done precisely because the resulting

distribution factor will measure “use by the load of each Zone.”

Id. (emphasis added). FERC’s second rationale is thus wrong

as well as inconsistent with its first, which claimed support

from the fact that the de minimis threshold identifies zones with

small use relative to their load.

29

Third, FERC noted that the DFAX analysis is performed

annually, so “the zones that qualify for the de minimis

exemption may change” over time. First Linden Complaint

Rehearing Order, 170 FERC ¶ 61,122 at P 45. We are at a loss

to understand how that fact, reflecting the truism that things

change, bears on whether the exception here is reasonably

related to project costs or benefits.

B.

We now turn to netting. For zones with many delivery

points, PJM “nets” the flows to each delivery point to calculate

total flow. PJM Tariff, Sched. 12(b)(iii)(A)(4). Electricity can

flow in both positive and negative directions. PJM assigns a

negative value to flows in the negative direction, which

decreases a zone’s total flow. For instance, a zone with one

delivery point that receives +100 megawatts and another that

receives +50 megawatts will be deemed to have net flows of

+150 megawatts. But a zone with one delivery point that

receives +100 megawatts and another that receives −50

megawatts will be deemed to have net flows of only +50

megawatts. The New York entities challenge this offsetting of

positive and negative flows.

1.

The New York entities contend that netting violates the

cost causation principle and unduly discriminates against them.

Transmission facilities benefit zones by bringing electricity to

their delivery points, and this benefit is the same regardless of

whether the electricity flows in the positive or negative

direction. But netting causes markedly different cost

allocations. If a zone with one delivery point receives +150

megawatts, while another with two delivery points receives

flows of +100 and −50 megawatts at each point respectively,

the former zone will pay three times as much as the latter for

30

the same benefit. The New York entities contend that this

discrepancy systematically favors large zones like PSE&G,

which have many delivery points and so are more likely to have

offsetting positive and negative flows. In contrast, each

merchant transmission facility has only one delivery point and

so cannot benefit from netting.

FERC approved netting because it produces a different

benefit by creating extra capacity for the transmission line.

Because “power flows in opposite directions offset each other,”

a zone’s “negative flows decrease the amount of power flowing

over the line and make additional capacity available.” First

Linden Complaint Rehearing Order, 170 FERC ¶ 61,122 at

P 49. For instance, a transmission facility with 75 megawatts

of capacity cannot accommodate +100 megawatts of flows in

the absence of counterflows. But with the addition of −50

megawatts of counterflows, the net flow is only +50

megawatts, and the facility can accommodate all the flows.

FERC concluded that zones with flows in only one direction

should bear more costs for using up more capacity.

This conclusion is reasonable. Because counterflows

increase capacity, FERC could reasonably treat them as

benefits that the zones confer on the facility, rather than

benefits that they derive from it. So understood, counterflows

can reasonably be considered a basis for discounting rather

than increasing a zone’s cost allocation. On this point, we do

not suggest that FERC’s approach is the only reasonable one.

But because it is reasonable, we must uphold it on deferential

review. See Old Dominion, 898 F.3d at 1260.

The New York entities raise two further objections. They

contend that FERC’s defense of netting is inconsistent with

PJM’s rationale for replacing its previous cost allocation

method with the present DFAX method. And they claim it is

31

unduly discriminatory to net within a zone but not across

zones. The entities did not raise either objection in their

applications for rehearing, so we do not have jurisdiction to

consider them. 16 U.S.C. § 825l(b); see Ameren Servs. Co. v.

FERC, 893 F.3d 786, 793 (D.C. Cir. 2018).

2.

After FERC issued the orders under review, another

merchant transmission facility owner filed a section 206

complaint challenging the netting and de minimis provisions of

PJM’s Tariff. Neptune Reg’l Transmission Sys., LLC, 175

FERC ¶ 61,247 at PP 1, 4, 8 (2021). Following its preliminary

review in Neptune, FERC undertook to “look anew” at whether

both provisions “have become unjust and unreasonable,” and it

ordered further proceedings to do so. Id. at PP 45–46.

The New York entities request a remand for FERC to

reconsider netting here, given its Neptune order. But we

evaluate agency action “at the time of decision,” PBGC v. LTV

Corp., 496 U.S. 633, 654 (1990), and an agency decision “is

not arbitrary or capricious merely because it is not followed in

a later adjudication,” MacLeod v. ICC, 54 F.3d 888, 892 (D.C.

Cir. 1995). Despite this, the entities note, we have sometimes

remanded if the agency has changed the rule underlying a

decision pending review. See Williston Basin Interstate

Pipeline Co. v. FERC, 165 F.3d 54, 62–63 (D.C. Cir. 1999).

But FERC did not reject netting in Neptune; it merely ordered

further proceedings to examine the practice in greater detail. A

remand here is thus unwarranted.

We hold only that FERC reasonably explained its decision

to approve netting in these proceedings. In doing so, we do not

prejudge Neptune, and we do not foreclose the Commission

from reconsidering its position on netting given whatever

evidence and arguments may be developed in that case.

32

C.

Finally, we address the peak-load assumption. When

modeling the flow of electricity, PJM assumes that each zone

is at its peak demand. For merchant transmission facilities, this

means PJM assumes that they are exercising their full firm

withdrawal rights. PJM Tariff, Sched. 12(b)(iii)(A)(3). The

merchant transmission facilities object that this assumption

overestimates their use of the transmission facilities, because

they generally do not reroute electricity into New York City

when demand in New Jersey is at its peak. FERC

acknowledged that merchant transmission facilities may be less

likely than other zones to exercise full delivery rights at times

of peak demand. Nonetheless, it found the assumption

reasonable because PJM must be able to meet peak load to

guarantee system reliability. First Linden Complaint

Rehearing Order, 170 FERC ¶ 61,122 at P 15. The entities

complain this explanation is inconsistent with FERC’s defense

of netting, which the Commission justified as “realistically

reflect[ing] how energy flows on an integrated transmission

system.” Id. at P 14. If FERC evaluates netting based on how

electricity realistically flows, the challengers contend, it should

do the same for the peak-load assumption.

We see no inconsistency. Maintaining grid reliability is

one of a system operator’s most important goals, Blumenthal v.

FERC, 552 F.3d 875, 879 (D.C. Cir. 2009), so PJM could

reasonably plan for a worst-case scenario in which all zones

exercise their full delivery rights. But even under that scenario,

positive and negative flows still would offset each other and

thus create additional capacity. As explained above, FERC

may reasonably take that fact into account in deciding whether

to add or subtract opposite-direction flows.

33

V.

Finally, the New York entities challenge FERC’s

interpretation of the PJM Tariff. They contend that the Tariff

requires a departure from the DFAX method if its application

would violate the cost causation principle. We disagree.

The interpretive dispute centers on the interplay between

Schedule 12(b)(iii) of the Tariff, which outlines how to carry

out the DFAX analysis, and paragraph (G) of that provision,

which confers some discretion to depart from the prescribed

methodology. Under that paragraph, if PJM “determines in its

reasonable engineering judgment that … the DFAX analysis

cannot be performed or that the results of such DFAX analysis

are objectively unreasonable,” it “may use an appropriate

substitute proxy for the Required Transmission Enhancement

in conducting the DFAX analysis.” The New York entities

maintain that “objectively unreasonable” results include ones

that do not conform to the cost causation principle. And in their

view, an “appropriate substitute proxy” includes a different

cost allocation methodology.

FERC read paragraph (G) differently. It objects that the

New York entities invite an ex post allocation inquiry that is

both standardless and contrary to Order No. 1,000’s

requirement that costs be assigned ex ante. First Linden

Complaint Rehearing Order, 170 FERC ¶ 61,122 at P 55.

According to FERC, results of the DFAX analysis are

“objectively unreasonable” only if the flows it models “are not

consistent with the normal expected flow results that an

engineer would expect to see.” Id. And because PJM engineers

“had no difficulty determining flows across” the Bergen and

Sewaren projects, the DFAX analysis results were not

objectively unreasonable. Id. Moreover, paragraph (G) gives

PJM discretion only to use “‘an appropriate substitute proxy

34

for the Required Transmission Enhancement in conducting the

DFAX analysis,’” not general discretion to modify the

method’s “cost responsibility assignments.” Id. at P 56

(quoting PJM Tariff, Sched. 12(b)(iii)(G)).

We review FERC’s tariff interpretations with a “Chevron-

like analysis.” La. Pub. Serv. Comm’n v. FERC, 10 F.4th 839,

845–46 (D.C. Cir. 2021) (cleaned up). Under that framework,

we enforce unambiguous tariff language but defer to FERC’s

reasonable interpretation of ambiguous text. Id. at 846.

FERC’s interpretation is permissible. Any determination

of unreasonableness by PJM must be “objective[]” and the

product of PJM’s “engineering judgment,” which suggests a

purely technical determination. Judging whether the method

accurately models the flow of electricity fits that description.

Ensuring compliance with the cost causation principle does

not. Aligning project costs and benefits necessarily includes

questions of fairness and the need to balance “competing

goals.” S.C. Pub. Serv. Auth. v. FERC, 762 F.3d 41, 88 (D.C.

Cir. 2014) (per curiam). And courts have long recognized that

ratemaking is “much less a science than an art,” Ala. Elec.

Coop., Inc. v. FERC, 684 F.2d 20, 27 (D.C. Cir. 1982),

requiring “both technical understanding and policy judgment,”

FERC v. Elec. Power Supply Ass’n, 577 U.S. 260, 295 (2016).

Moreover, even when PJM finds objectively unreasonable

results, it does not have discretion to abandon the DFAX

method. Paragraph (G) allows PJM to use a “substitute proxy”

only “for the Required Transmission Enhancement,” i.e., the

transmission facility, and only “in conducting the DFAX

analysis.” It does not permit a proxy method. In other words,

PJM can look past modeled flows that seem objectively

unreasonable, replace them with flows from a comparable

35

facility that the DFAX analysis can more accurately model, and

then rerun the analysis. Nothing more.

Two other textual clues reinforce this view. The

immediately preceding paragraph of the Tariff speaks of using

a “proxy” in precisely this way. When the facility to be

modeled is a direct-current facility, it “shall be replaced in the

model with a comparable proxy [alternating-current] facility.”

PJM Tariff, Sched. 12(b)(iii)(F)(1). Additionally, whenever

PJM uses a proxy under paragraph (G), it must “state in a

written report … a recommendation as to what changes, if any,

should be considered in conducting the DFAX analysis.” Id.

Sched. 12(b)(iii)(G) (emphasis added). This presupposes that

even if PJM uses a proxy facility, it will not abandon the DFAX

method altogether.

Finally, FERC’s interpretation fits better with the principle

of ex ante cost allocation established by Order No. 1,000.

Under FERC’s reading, PJM must apply all the existing cost

allocation rules unless doing so is infeasible because the DFAX

analysis does not accurately model flows. When that is the

case, PJM’s discretion is limited to identifying a proxy facility

to which the existing rules will otherwise apply. Under the

New York entities’ reading, PJM must decide in each case

whether to apply the existing rules or entirely new ones, based

on its own view of the fairness of the results produced by the

existing rules. Such an approach is ex ante in name only.

VI.

For its part, the New Jersey Board seeks review of FERC’s

order affirming the reallocation of the New York entities’ costs

for the Bergen project to PSE&G after they relinquished their

rights to withdraw electricity from the PJM grid, as well as its

orders permitting Linden and Hudson to convert their firm

withdrawal rights to non-firm ones. The Board raises three

36

main arguments. First, the Board claims that FERC erred in

determining that ConEd’s cost responsibility for the project

ended when its transmission service agreements ceased. This

was so since the project was built to benefit ConEd and ConEd

previously agreed to accept its share of costs. Second, it is

argued that Linden unreasonably evaded cost allocations for

the project by the device of pairing non-firm transmission

withdrawal rights and firm point-to-point transmission service,

which ensures Linden retains the same benefits from the

project. Third, the Board also contends that FERC did not

properly consider whether the cumulative effect of relieving

the New York entities of cost responsibility resulted in an

unjust and unreasonable rate.

A.

We start with the New Jersey Board’s first argument that

ConEd was obliged to continue to pay project costs even after

it ceased receiving service upon the termination of the ConEd-

PSE&G power exchange transmission service—“wheeling”—

agreement.

The 2009 settlement between PSE&G and ConEd, which

clarified the parties’ rights and obligations under the wheeling

agreement, was signed by the New Jersey Board, ConEd, PJM,

NYISO, and PSE&G. Under that agreement, ConEd “shall pay

Transmission Enhancement Charges during the term of

its … service.” J.A. 614. 8 But the agreement makes clear that

“ConEd shall have no liability for Transmission Enhancement

Charges … after the termination of[] said term of service.” Id.

8

In this Part, citations to the joint appendix refer to the one in New

Jersey Board v. FERC.

37

FERC approved the settlement. 9 See ConEd-PSE&G

Settlement Order, 132 FERC ¶ 61,221 at P 23. Here, ConEd’s

service agreements expired on April 30, 2017, and it did not

renew them.

Under the PJM Tariff, ConEd’s cost responsibility for PJM

regional plan projects “shall be in accordance with the terms

and conditions of the settlement” and “shall be adjusted at

the … termination of service under the ConEd Service

Agreements.” PJM Tariff, Sched. 12(b)(xi)(A)–(B). FERC

relied on the settlement agreement and its incorporation into

the PJM Tariff to support its cost allocation decision. See

Board Complaint Order, 163 FERC ¶ 61,139 at P 56 & n.94.

Similarly, FERC recognized that the Joint Operating

Agreement (“JOA”) between PJM and NYISO, which

established protocols to improve the reliability and market

operations of their systems, precluded the continued allocation

of the Bergen project’s costs to ConEd. Id. at PP 2, 54–55.

FERC noted that, under JOA section 35.10.6, “neither the

NYISO Region nor the PJM Region shall be responsible for

compensating another region” for project costs unless both

NYISO and PJM jointly decide to undertake an interregional

project together. Id. at P 54; Board Complaint Rehearing

Order, 170 FERC ¶ 61,180 at PP 12, 14. FERC correctly

explained that the Bergen project was planned solely by PJM.

Board Complaint Order, 163 FERC ¶ 61,139 at P 54; Board

Complaint Rehearing Order, 170 FERC ¶ 61,180 at P 12. That

cost allocation provision applies even where, as here, PJM and

NYISO share mutual benefits between their systems that derive

9

We note that the New Jersey Board participated in the settlement

negotiations and signed the settlement agreement. If the Board took

issue with these provisions, it should not have agreed to the

settlement.

38

simply from their interconnection. Board Complaint Order,

163 FERC ¶ 61,139 at P 55. FERC recognized that “the JOA

specifically states that ‘PJM and NYISO shall not charge one

another for such [mutual benefits].’” Id.

Accordingly, under these three agreements, FERC

correctly determined that ConEd did not have to pay project

costs after the termination of the service agreements.

The New Jersey Board contends that all of this misses the

point. The relevant question, it says, is not whether a cost

allocation complies with previously approved agreements or

orders, but whether the resulting cost allocation,

notwithstanding those agreements, is unjust and unreasonable.

And, it points out that previously approved cost allocation

methods can be unjust and unreasonable as applied to a

particular rate decision.

As a general principle, under FERC’s Order No. 1,000,

which implements the cost causation principle, costs must be

allocated roughly in accordance with benefits. Order No.

1,000, 136 FERC ¶ 61,051 at P 612. But that order also

provides—in Principle 4—that “[t]he allocation method for the

cost of a transmission facility selected in a regional

transmission plan must allocate costs solely within that

transmission planning region unless another entity outside the

region or another transmission planning region voluntarily

agrees to assume a portion of those costs.” Id. at P 657. Here,

after ConEd’s service agreements expired, it no longer agreed

to pay costs. And, as noted, the Bergen project was planned

solely by PJM.

The New Jersey Board responds that there is tension

between Principle 4 and the general cost causation principle

because it may allow some project beneficiaries—here,

39

ConEd—to avoid all cost responsibility. That is true. But it

appears to us that Principle 4 is a permissible limitation on the

cost causation principle. Indeed, we have concluded as much,

as FERC points out. Board Complaint Order, 163 FERC

¶ 61,139 at P 54 n.83.

In South Carolina Public Service Authority v. FERC,

Petitioners argued that Principle 4 was inconsistent with the

cost causation principle because it did not fully allocate costs

to out-of-region entities who still received some benefits. 762

F.3d at 88. We held that, even if Principle 4 “may lead to some

beneficiaries escaping cost responsibility,” there are other

geographic policy considerations in play and FERC may

permissibly approve a rate that does not perfectly track cost

causation. Id.; see also Carnegie Nat. Gas Co. v. FERC, 968

F.2d 1291, 1293–94 (D.C. Cir. 1992) (noting that there is “no

requirement in the Act itself that rates precisely match cost

causation and responsibility” and that instead “the Commission

may rationally emphasize other, competing policies and

approve measures that do not best match cost responsibility and

causation”). We noted that FERC developed Principle 4 in

light of concerns about the monitoring costs, efficiency, and

feasibility of involuntary interregional cost allocation. S.C.

Pub. Serv. Auth., 762 F.3d at 88–89. Accordingly, we

concluded that Principle 4 is an important qualification on the

cost causation principle. It reflects FERC’s reasonable

considered judgment about how best to balance its competing

policy goals on a ratemaking matter, which we review with

deference. Id.; see also Artificial Island, 989 F.3d at 17.

Therefore, we think that FERC reasonably relied on Order

No. 1,000 and its Principle 4 to determine that it was just and

reasonable for ConEd to be released from costs for the Bergen

project going forward.

40

B.

Next, the New Jersey Board contends that “FERC’s

decision to allow Linden to avoid cost allocations for the

Corridor Project” was “arbitrary” because “the Commission

did not grapple with the interaction between firm Point-to-

Point service and non-firm Withdrawal Rights.” The Board

notes that, at the same time Linden renounced its firm

withdrawal rights, it separately bargained for and received firm

“point-to-point” transmission service from utilities on the PJM

grid. The Board therefore argues—and it is a powerful

argument—that, as a practical matter, Linden’s relinquishment

of its firm withdrawal rights and its election of firm point-to-

point service allowed Linden to receive the same benefits from

the Bergen project without any of the costs. 10 FERC insists

that we cannot consider this argument because it was not

adequately presented in its requests for rehearing.

Under 16 U.S.C. § 825l(b), “[n]o objection to [an] order of

the Commission shall be considered by the court unless such

objection shall have been urged before the Commission in the

application for rehearing ….” The argument the New Jersey

Board makes before us, unfortunately, appears nowhere in its

requests for rehearing before FERC. Instead, the Board’s

10

That is because PJM, despite being able to curtail service to a

customer with non-firm withdrawal rights, cannot curtail service to

that same customer if it has firm point-to-point rights. So even

though Linden does not have to pay costs under PJM’s Tariff because

DFAX cost allocations are linked to firm withdrawal rights, it

continues to receive the same service as it did when it held firm

withdrawal rights by subscribing to firm point-to-point service.

Once that power is transmitted to Linden’s facility, PJM cannot

prevent Linden from exporting that power in the exact same way as

it had before converting from firm to non-firm withdrawal rights,

including into NYISO’s market.

41

rehearing requests generally challenge FERC’s handling of the

cost allocation issue. But we have held that a petitioner “must

raise each argument with ‘specificity’; objections may not be

preserved either ‘indirectly,’ or ‘implicitly.’” Ameren Servs.

Co., 893 F.3d at 793 (citations omitted). Accordingly, we lack

jurisdiction to consider the Board’s challenge to Linden’s cost

allocations. 11

C.

Finally, it will be recalled, the New Jersey Board claims

that FERC conducted a “siloed analysis” that did not consider

the “total effect” of its orders on the rates for New Jersey

ratepayers. Taken together, that the project was built in part to

serve New York customers, ConEd did not renew its

transmission service agreements, and Hudson and Linden

converted their withdrawal rights have led to an unjust and

unreasonable cost allocation, the Board says. Essentially, the

Board protests that its ratepayers pay an “exceedingly

disproportionate share” of the costs of the project.

But FERC did perform the kind of back-end analysis that

the New Jersey Board claims was required. FERC recognized

that the Bergen project was planned by PJM, and relied on

PJM’s statement that the project would still be needed in New

Jersey “even if there were no flows on the transmission

facilities interconnecting New York and New Jersey.” Board

Complaint Order, 163 FERC ¶ 61,139 at P 54 n.85. In its order

denying the Board’s complaint, FERC, applying Principle 4,

11

Although the New Jersey Board generally seeks judicial review of

FERC’s orders concerning Hudson’s post-2017 cost allocation, it

does not make this particular argument as to Hudson. Instead, the

Board asks us to consider the Hudson cost allocation only as part of

its “total effect” claim, which we address in Part VI.C.

42

concluded that because the Bergen project “was planned by a

single region, i.e., PJM, and without a voluntary commitment

to share cost responsibility by the other region, i.e., NYISO, it

is just and reasonable for the costs of the project to be allocated

solely within that region, PJM.” Id. at P 54. And, in denying

rehearing on this very argument, FERC noted that “[t]he fact

that New Jersey ratepayers now pay higher rates as a result of

a combined set of permissible circumstances does not by itself

render such rates unjust and unreasonable.” Board Complaint

Rehearing Order, 170 FERC ¶ 61,180 at P 12.

Thus, looking at the matter from the stratosphere, FERC

did consider the “total effect” of its decision and permissibly

concluded—after evaluating who incurred the costs and who

reaped the benefits of the project—that the overall cost

allocation for the New York entities was not unjust or

unreasonable. FERC’s cost allocation determination was

therefore neither “unreasonable” nor “inadequately explained.”

Artificial Island, 989 F.3d at 17.

VII.

In light of the foregoing, we deny the petitions for review

in New Jersey Board v. FERC, and we grant in part and deny

in part the petitions in ConEd v. FERC.

In denying the New York entities’ applications for

rehearing of both the First and Second Linden Complaint

Orders, FERC failed to adequately distinguish its decision in

Artificial Island from its treatment of the Bergen and Sewaren

projects. In addition, FERC upheld the de minimis threshold,

which we have found to be unlawful, in its orders denying

rehearing of the First and Second Linden Complaint Orders and

the ConEd Complaint Order. We therefore vacate FERC’s

denial of Linden’s two complaints and remand for further

43

proceedings on both issues. We likewise vacate its denial of

ConEd’s complaint and remand for further proceedings solely

on the de minimis issue.

With one exception, we leave in place all the section 205

orders approving PJM’s cost allocations. In all but one of those

orders, FERC determined that when PJM files cost allocations

under section 205, its role is limited to determining whether

PJM correctly applied the methodology required by its Tariff

rather than examining the lawfulness of that methodology. The

New York entities do not challenge this procedural ruling,

which forms an independent basis for rejecting their

challenges. 12 We do vacate, however, the Cost Reallocation

Order and remand on both the Artificial Island and de minimis

issues. FERC did not raise a procedural bar to the New York

entities’ challenges there, instead rejecting them on the merits

for reasons we have found defective. See Cost Reallocation

Order, 170 FERC ¶ 61,124 at P 32; Second Linden Complaint

Rehearing Order, 172 FERC ¶ 61,176 at P 18. On remand,

FERC may consider in the first instance whether the challenges

to PJM’s 2017 cost reallocation are procedurally barred.

So ordered.

12

FERC argues that we lack jurisdiction over the petitions in Nos.

15-1183 and 15-1188—which seek review of its 2014 order

approving PJM’s initial cost allocations for Bergen—because that

order was nonfinal. But we indisputably have jurisdiction over at

least one “companion case” raising the same objections as those in

Nos. 15-1183 and 15-1188, and so may reject those petitions on the

merits without reaching the jurisdictional argument FERC presses.

Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 98 (1998)

(emphasis omitted) (citing Norton v. Mathews, 427 U.S. 524, 530–

31 (1976)).

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.