Opinion

Colorado Interstate Gas Co. v. Federal Energy Regulatory Commission

  • 599 F.3d 698
  • 389 U.S. App. D.C. 436
Court
Court of Appeals for the D.C. Circuit
Filed
Mar 29, 2010
Status
Published
Author
Griffith
On the bench
Garland, Griffith, Edwards
Cited by
14 cases
Authority
More cited than 73.9%

The opinion

United States Court of Appeals

FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued October 5, 2009 Decided March 26, 2010

No. 08-1243

COLORADO INTERSTATE GAS COMPANY,

PETITIONER

v.

FEDERAL ENERGY REGULATORY COMMISSION,

RESPONDENT

On Petition for Review of Orders

of the Federal Energy Regulatory Commission

Howard L. Nelson argued the cause for petitioner. With

him on the briefs was Kenneth M. Minesinger. Stephanie D.

Neal entered an appearance.

Robert M. Kennedy, Attorney, Federal Energy Regulatory

Commission, argued the cause for respondent. With him on

the brief were Cynthia A. Marlette, General Counsel, and

Robert H. Solomon, Solicitor.

Before: GARLAND and GRIFFITH, Circuit Judges, and

EDWARDS, Senior Circuit Judge.

Opinion for the Court filed by Circuit Judge GRIFFITH.

2

GRIFFITH, Circuit Judge: Petitioner, Colorado Interstate

Gas Company (CIG) operates a natural gas pipeline that

includes a gas storage facility in Fort Morgan, Colorado. An

accidental leak at the Fort Morgan facility led to the loss of a

substantial amount of gas, which CIG asked its shippers to

replace. The shippers refused, and the Federal Energy

Regulatory Commission (FERC) took their side in the orders

on review. FERC held that under its tariff CIG could only

recover from its shippers gas that was lost in the course of

normal pipeline operations, which this was not. We deny

CIG’s petition for review because FERC’s interpretation of

the tariff was reasonable, and its conclusion that the loss did

not result from normal operations was supported by

substantial evidence.

I.

At 12:30 p.m. on October 22, 2006, CIG learned of a gas

leak at its Fort Morgan facility when a nearby landowner

“noticed water coming to the surface within the boundaries”

of CIG’s facility. Affidavit of Larry D. Kennedy, Jr., at 1.

CIG immediately initiated its “Emergency Operating

Procedures” and designated Larry D. Kennedy, Jr., CIG’s

Manager of Reservoir Services, as its “Incident Response

Commander.” Id. Two hours after first learning of the leak,

CIG identified the #26 gas well as the source. At

approximately 7:00 p.m., CIG inserted a cast iron bridge plug

into the tank, which prevented additional gas from escaping.

CIG notified federal, state, and local authorities, as

required by the various regulations that govern unexpected

releases of natural gas. In the immediate aftermath of the leak,

CIG “communicated with the public and local authorities by

the use of newsletters, E-Mails, and public meetings on a

3

regular basis,” and the pipeline established a “hot-line” for

concerned citizens. Id. at 3. Days later, as an added

precaution, CIG inserted a second plug to ensure the leak was

completely stopped. During a subsequent investigation, CIG

discovered that the leak had been caused by a crack in the

tank’s casing approximately 847 feet below ground level.

The amount of gas lost at Fort Morgan was substantial—

between 451,000 and 720,000 decatherms—and this dispute

stems from CIG’s attempt to recover gas from its shippers to

offset the loss. Whether CIG may recover this loss depends on

the language of its tariff.

The amount of gas a shipper delivers to a pipeline will

never be exactly the same as the amount of gas that arrives at

the destination. In the course of moving gas from one place to

another, some of it is lost due to small leaks or metering

errors. Gas lost in this way is known as lost and unaccounted-

for gas. In addition, some gas is used by the pipeline to power

the compressors that move the shippers’ gas through the

pipeline. This kind of gas is known as fuel gas. Both of these

quantities vary substantially and unpredictably, which makes

it difficult to know in advance what the cost of shipping will

be. FERC permits a pipeline to adjust its tariff in two ways in

an effort to provide more certainty to the pipeline’s bottom

line. Notice of Inquiry, Fuel Retention Practices of Natural

Gas Companies, 72 Fed. Reg. 55,762, 55,762 (Oct. 1, 2007)

[hereinafter Notice of Inquiry]; see Am. Gas Ass’n v. FERC,

593 F.3d 14, 17 (D.C. Cir. 2010). Each method involves the

pipeline retaining a percentage of the gas shipped as a hedge

against uncertain future costs.

First, the pipeline may include in its tariff a provision that

fixes a percentage of the transported gas that may be retained.

The percentage must be approved by FERC in a proceeding

4

under section 4 of the Natural Gas Act. See 15 U.S.C.

§ 717c(a) (2006). In section 4 proceedings, FERC generally

considers every element of a pipeline’s cost of providing

service before approving the proposed retention percentage as

just and reasonable. See ANR Pipeline Co., 110 FERC

¶ 61,069, at 61,338 (2005). Under this approach, the retention

percentage remains constant until the pipeline initiates

another section 4 proceeding.

Second, a pipeline may include in its tariff a provision

known as a fuel tracker, which tracks the amount of gas that is

reimbursable and permits periodic changes to the retention

percentage in what is known as a limited section 4 filing

based upon the difference between what the pipeline

estimated that amount to be and what it actually turned out to

be. See 18 C.F.R. § 154.403 (2009); ANR Pipeline Co., 110

FERC at 61,338–39; Notice of Inquiry, 72 Fed. Reg. at

55,762. In a limited section 4 proceeding, FERC evaluates the

reasonableness of the proposed retention percentage based

solely on the fuel tracker. This accelerated process allows the

pipeline to quickly account for the gas that is reimbursable by

avoiding the lengthy process of general section 4 review.

Tariffs with fuel trackers must also include a “true-up

provision,” under which the pipeline either remits to the

shippers any mistakenly retained gas or recovers additional

gas if the initial retention percentage was insufficient to

compensate the pipeline. See ANR Pipeline Co., 110 FERC at

61,338–40.

CIG’s tariff includes a fuel tracker, and four months after

the Fort Morgan accident the pipeline made a limited

section 4 filing with FERC seeking to increase its fuel

retention percentage from 0.00% to 0.06%. The lion’s share

of the gas that CIG sought to recover was lost in the Fort

Morgan leak. Several shippers protested CIG’s filing,

5

contending that the Fort Morgan loss was unrecoverable.

They argued that CIG could only increase its retention

percentage to account for normal operating losses and not for

accidents like the Fort Morgan leak. See Colo. Interstate Gas

Co., 121 FERC ¶ 61,161, at 61,719–20 (2007) [hereinafter

Order Following Technical Conference]. FERC agreed,

rejected CIG’s proposed retention percentage, and accepted

CIG’s limited section 4 filing “subject to the removal of the

. . . Fort Morgan gas loss.” Id. at 61,724. CIG petitioned for

rehearing, which FERC denied. FERC elaborated on the

reasoning in its initial order, concluding that CIG’s

interpretation of its tariff was unreasonable, contrary to FERC

precedent, and failed to account for the industry’s usage of the

term “lost, unaccounted-for” gas to refer to a discrete category

of gas. Colo. Interstate Gas Co., 123 FERC ¶ 61,183, at

62,237, 62,240 (2008) [hereinafter Rehearing Order].

CIG timely petitioned this court for review of FERC’s

decisions. We have jurisdiction under 15 U.S.C. § 717r(b).

See Nat’l Fuel Gas Supply Corp. v. FERC, 468 F.3d 831, 839

(D.C. Cir. 2006).

II.

The disposition of CIG’s petition turns on FERC’s

interpretation of the tariff’s fuel tracker to bar recovery for the

gas lost in the Fort Morgan leak. We review a challenge to

FERC’s interpretation under the Administrative Procedure

Act’s arbitrary and capricious standard of review, using a

two-step, Chevron-like analysis. See 5 U.S.C. § 706(2)(A);

Old Dominion Elec. Coop., Inc. v. FERC, 518 F.3d 43, 48

(D.C. Cir. 2008). We first “consider de novo whether the

[tariff] unambiguously addresses the matter at issue. If so, the

language . . . controls for we must give effect to the

unambiguously expressed intent of the parties.” Ameren

6

Servs. Co. v. FERC, 330 F.3d 494, 498 (D.C. Cir. 2003)

(internal quotation marks and citation omitted). “If the tariff

language is ambiguous, we defer to the Commission’s

construction of the provision at issue so long as that

construction is reasonable.” Koch Gateway Pipeline Co. v.

FERC, 136 F.3d 810, 814–15 (D.C. Cir. 1998).

We start by asking if the tariff clearly addresses whether

CIG is entitled to increase its retention percentage due to the

losses from the Fort Morgan leak. In a number of its

provisions, the tariff describes circumstances in which the

pipeline may recover from the shipper losses incident to the

transportation of gas. We begin with Article 6.1, which states,

“Shipper shall furnish Fuel Reimbursement as defined in

Article 1 of the General Terms and Conditions.” Colo.

Interstate Gas Co., FERC Gas Tariff, at Fourth Revised Sheet

No. 92. “Fuel Reimbursement,” as defined in Article 1.30,

“shall mean the compressor Fuel Gas and Lost, Unaccounted

For and Other Fuel Gas as described in Article 42 of the

General Terms and Conditions.” Id. at Thirteenth Revised

Sheet No. 230A. Neither party challenges that the tariff

permits reimbursement for fuel gas, leaving for our resolution

the meaning of the phrase “Lost, Unaccounted For and Other

Fuel Gas as described in Article 42.” Article 42, which is the

tariff’s fuel tracker, is entitled “Fuel and L&U” and describes

the gas eligible for reimbursement as “Lost, Unaccounted For

and Other Fuel ‘(L & U and Other Fuel).’” Id. at First Revised

Sheet No. 380F, Original Sheet No. 380G. All gas eligible for

reimbursement will be “stated in terms of a percentage of

Receipt Quantities, computed and adjusted quarterly.” Id. at

First Revised Sheet No. 380F. This is the retention

percentage.

CIG contends that these provisions clearly define the

kinds of losses for which CIG may increase its retention

7

percentage. According to CIG, the comma that appears

between “Lost” and “Unaccounted For” in Article 1.30

reveals that the tariff describes a three-item list of the types of

gas that qualify for reimbursement: (1) lost gas;

(2) unaccounted-for gas; and (3) other fuel gas.1 See

Petitioner’s Br. at 26. CIG argues that the gas lost in the Fort

Morgan leak is subject to reimbursement because it was

“lost.” This is a reasonable reading of Article 1.30, but it is

incomplete. It fails to take into account the way Article 42

suggests that “lost, unaccounted-for” gas is a single category.

In both its title, “Fuel and L&U,” and its parenthetical, “L &

U and Other Fuel,” Article 42 uses the abbreviation “L&U” in

ways that suggest “lost, unaccounted-for” gas is a discrete

classification.

But neither view is compelling to the exclusion of the

other. The tariff simply does not provide a clear answer to the

question of whether a pipeline may recover any gas that is

merely “lost.” On this issue, the tariff is “reasonably

susceptible of different constructions or interpretations,”

Ameren Servs. Co., 330 F.3d at 499 (internal quotation marks

omitted), and does not unambiguously establish what losses

justify an increase in CIG’s retention percentage.

We thus proceed to the second step of our Chevron-like

analysis and assess the reasonableness of FERC’s

interpretation. FERC gave three reasons for its conclusion that

CIG’s tariff does not permit recovery for the Fort Morgan gas.

1

“Other fuel gas” is gas that the pipeline uses for its own

operations, excluding gas used to power machinery to transport gas.

See Colo. Interstate Gas Co., 128 FERC ¶ 61,117 at 61,614 n.5

(2009) (“‘[O]ther fuel gas’ . . . reflects gas consumed in processing

activities, and is different from compressor fuel gas.”).

8

First, FERC applied the industry understanding of the

phrase “lost, unaccounted-for” gas. Rebutting CIG’s argument

that it may recover any gas that is merely “lost,” FERC

concluded that the comma between the words “lost” and

“unaccounted-for” “does not change the trade usage and tariff

understanding of L&U as a single term.” Rehearing Order, at

62,241; see also Transwestern Pipeline Co., 51 FERC

¶ 61,343, at 62,116 n.3 (1990) (“Lost and unaccounted for gas

occurs from leakage, variations in metering at different

locations and other reductions in the volume of gas

transmitted . . . . incurred as part of a pipeline’s daily

operations.”). Relying on the trade usage of the term is

appropriate, as construing terms in light of their commonly

understood meaning is a hallmark of reasonable

interpretation. See Indep. Petrochemical Corp. v. Aetna Cas.

& Sur. Co., 944 F.2d 940, 945 (D.C. Cir. 1991); see also

United States v. Martinez-Noriega, 418 F.3d 809, 815 (8th

Cir. 2005) (“Trade usage of a term is also highly relevant to a

determination of the parties’ intended meaning.”). We have

consistently required that FERC interpret tariffs in light of

their “commercial . . . context,” and the Commission did so

here. Consol. Gas Transmission Corp. v. FERC, 771 F.2d

1536, 1547 (D.C. Cir. 1985) (internal quotation marks

omitted). CIG counters that FERC should never have

considered trade usage because the terms of the tariff clearly

establish the kinds of gas losses that are recoverable. See

Reply Br. at 4. But as we have just explained, the tariff was

not clear on this point, and FERC rightly looked to this kind

of extrinsic evidence. With such ambiguity, we afford FERC

“substantial deference . . . even where the issue simply

involves the proper construction of language.” Koch Gateway,

136 F.3d at 814 (internal quotation marks omitted). FERC

relied on its understanding of industry parlance and

reasonably construed the tariff’s use of “L&U.”

9

Second, FERC’s interpretation of the fuel tracker ensures

that no provision of the tariff lacks legal effect. FERC noted

that CIG’s contrary interpretation would render meaningless

the Commission’s “review of CIG’s quarterly L&U and fuel

gas reimbursement percentage true-ups” under Article 42.5.

Order Following Technical Conference, at 61,722. Article

42.5 of CIG’s tariff requires the pipeline to reconcile the

actual amount of gas retained under the prevailing retention

percentage with the amount of gas that qualifies under the fuel

tracker. If CIG could recover any loss at all—including

catastrophic, abnormal losses—FERC would never need to

examine CIG’s data offered in connection with its true-ups.

See id. CIG’s proposed interpretation renders the true-up

provision of the fuel tracker a nullity, whereas FERC’s

interpretation does not. FERC reasonably gave effect to all the

tariff’s provisions—yet another maxim of reasonable

interpretation. See RESTATEMENT (SECOND) OF CONTRACTS

§ 203(a) (2009) (“[A]n interpretation which gives a

reasonable, lawful, and effective meaning to all the terms is

preferred to an interpretation which leaves a part . . . of no

effect.”).

Third, FERC’s construction of CIG’s tariff is consistent

with how FERC has approached recovery claims for lost,

unaccounted-for gas under other fuel trackers. In particular,

FERC employed the test announced in Williams Natural Gas

Co., 73 FERC ¶ 61,394, at 61,215 (1995), which involved the

application of a similar fuel tracker. In Williams, FERC “put

forth a standard for recovering losses in tracking mechanisms

that described two categories of losses: losses resulting from

normal pipeline operations, which are recoverable; and losses

resulting from the malfunction of underground storage

mechanics, which are not recoverable in an L&U tracking

mechanism.” Rehearing Order, at 62,239. Following

Williams, FERC determined that the key factual determination

10

in this case was whether the Fort Morgan loss more closely

approximated a normal operating loss, which is recoverable,

or an abnormal malfunction of underground storage

mechanics, which is not. We give deference to FERC’s

interpretations of its own precedents and conclude that it was

reasonable for FERC to use the approach sanctioned in

Williams to determine the outcome here. See NSTAR Elec. &

Gas Corp. v. FERC, 481 F.3d 794, 799 (D.C. Cir. 2007).

In contrast, CIG argues that FERC has departed from its

precedents. CIG reads these cases to limit FERC’s inquiry to

the prudence of the pipeline’s actions when considering if lost

gas is eligible for reimbursement. See Petitioner’s Br. at 20–

24. But CIG misreads those decisions. In the case upon which

CIG relies most, High Island Offshore System, LLC (HIOS),

118 FERC ¶ 61,256 (2007), FERC permitted the pipeline to

change its retention percentage because the reported level of

lost and unaccounted-for gas was “not an anomaly.” Id. at

62,235. Critically, however, the Commission in HIOS did not

purport to describe the types of costs that are eligible for

recovery, whereas Williams provided just such a holding. By

following the rule outlined in Williams, FERC did not

unlawfully diverge from its precedents.

Additionally, CIG maintains that FERC’s interpretation

was unreasonable because the Williams distinction between

“normal” and “unusual” is not rationally related to whether a

pipeline could increase its retention percentage. The pipeline

argues that this standard “deprives CIG of an opportunity to

recover its prudently incurred costs.” See Petitioner’s Br. at

14. This argument fails for two reasons. First, it wrongly

implies that such losses are never recoverable. The decisions

below made no such prohibition and concluded simply that

CIG could not recover these costs through a limited section 4

filing. FERC left open the possibility that a pipeline could

11

recover losses like those at Fort Morgan in a regular section 4

case.2 See Rehearing Order, at 62,240. Second, the standard

announced in Williams and applied below is rationally related

to whether a pipeline can use an accelerated procedure

without the lengthy investigation entailed in a section 4 case.

By only permitting recovery for normal operating losses,

FERC and the parties save the time and resources required to

undertake a general rate case for frequently recurring

expenses. The pipeline and its shippers reasonably anticipate

that normal costs will occur each year, and the limited section

4 filing ensures that both parties can quickly resolve these

claims.

III.

We turn finally to CIG’s contention that FERC was

arbitrary and capricious in determining that the Fort Morgan

loss was not a normal operating event. This court “uphold[s]

FERC’s factual findings if supported by substantial

evidence.” Wash. Gas Light Co. v. FERC, 532 F.3d 928, 930

(D.C. Cir. 2008) (internal quotation marks omitted).

“Substantial evidence is ‘such relevant evidence as a

reasonable mind might accept as adequate to support a

conclusion.’” Butler v. Barnhart, 353 F.3d 992, 999 (D.C.

Cir. 2004) (quoting Richardson v. Perales, 402 U.S. 389, 401

(1971)).

The circumstances of the Fort Morgan incident amply

support FERC’s finding that this accident, which led to

substantial gas loss over the period of a few days, was not

2

As part of a prior settlement agreement, CIG has agreed to a

moratorium on section 4 actions. See Petitioner’s Br. at 4 n.1. That

CIG has voluntarily taken that option off the table has no impact on

what FERC is required to do under the law.

12

normal. FERC reasonably described the accident as “a totally

unexpected non-routine malfunction of underground storage

mechanics . . . not associated with routine maintenance or

other normal operations activity.” Order Following Technical

Conference, at 61,723. Indeed, CIG responded by initiating

“Emergency Operating Procedures” and establishing a hot-

line for concerned residents of the area. A reasonable person

could accept this evidence as adequate to conclude the Fort

Morgan incident was not part of CIG’s “normal pipeline

operations.” FERC’s determination was supported by

substantial evidence.

IV.

For the foregoing reasons, the petition for review is

Denied.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.