Opinion

G.M. Shupe, Inc. v. United States

  • 32 Cont. Cas. Fed. 72,712
  • 5 Cl. Ct. 662
  • 1984 U.S. Claims LEXIS 1354
Court
United States Court of Claims
Filed
Jul 31, 1984
Status
Published
Author
Lydon
On the bench
Lydon
Cited by
77 cases
Authority
More cited than 95.1%

“Delay involving work not on the critical path generally had no impact on the eventual completion date of the project.”

How later courts described this case

  • “Delay involving work not on the critical path generally had no impact on the eventual completion date of the project.”
  • "The reason that the determination of the critical path is crucial to the calculation of delay damages is that only construction work on the critical path had an impact upon the time in which the project was completed." (emphasis added)
  • Government not prejudiced by contractor’s failure to assert formal claim within notice period where contracting officer knew operative facts and directed alternate performance as result of difficulties encountered
  • subcontractor could not recover allegedly compensable costs for trenching and grouting work, where the manner in which the claim was presented furnished no reasonable basis for the court to compute the costs

Written by the judges who cited it.

The opinion

OPINION

LYDON, Judge:

In this construction contract case, plaintiff seeks to recover damages on behalf of itself and on behalf of Continental Drilling Company (Continental), its subcontractor, from defendant arising out of its construction of the Nambe Palls Dam in New Mexico for the Bureau of Reclamation, Department of the Interior (BOR). Plaintiff filed its petition (complaint) in this court as a direct access ease under section 10(a)(1), (3) of the Contract Disputes Act of 1978, codified at 41 U.S.C. § 609 (1982). Plaintiff advances five separate theories of recovery in claiming some $4 million as damages it incurred in construction of the Nambe Falls Dam. Defendant has raised a number of defenses, legal and factual, to the various damage claims asserted by plaintiff, and, in addition, has asserted a counterclaim in its amended answer against plaintiff in which it seeks to recover $78,922.75 which defendant claims it mistakenly paid plaintiff as contract proceeds.

I.

After trial on the merits and the compilation of a voluminous trial record, the par *669 ties filed detailed and extensive proposed findings of fact and expansive briefs, which were followed by oral argument. Plaintiff has presented ten separate claims. It is clear that six of the claims represent claims by plaintiff itself. It is also clear that two of the claims represent claims by plaintiff on behalf of Continental. As to one of the remaining two claims, it seems clear that this claim represents claims by both plaintiff and Continental. As to the other remaining claim the record is most confusing as to whether the claim is that of the plaintiff alone or whether it also includes a claim by Continental. The manner in which the claims and attendant proof and defenses were presented created some confusion and difficulty for the court. For example, the parties were unable to agree on whether certain claimed damages belonged under one claim category or another. The record, as constructed, provides little help in resolving the matter. Again, Continental presented its claim for damages primarily on the total cost theory, but it did break out specifically the individual amounts it sought for two separate claims. However, neither the record nor the parties provided much help to the court in breaking out other claims Continental asserts under the total cost wrapper.

The following facts, which are specifically found by the court, are herein set forth by way of background in order to place discussion and consideration of the various claims asserted by plaintiff and Continental in proper perspective. Additional facts, specifically found by the court, will be set forth when each claim is discussed and ruled upon infra.

Plaintiff, incorporated in the State of Washington, was formed in 1972 by Gerald M. Shupe (G. Shupe). Plaintiff was owned and managed by G. Shupe, Michael Quinn and Larry Campbell (Campbell). Prior to the formation of plaintiff, G. Shupe and Quinn had extensive experience in the construction of dams. Both also had long experience in negotiating claims arising out of construction contracts. Continental, a California corporation, also had many years of experience in performing drilling and grouting work on dam structures. At time of trial, Richard O. Thies (Thies) was president and general manager of Continental. Thies had a degree in geology and had been with Continental since the early 1940’s, working his way up the company ladder from drill helper to president. Thies was experienced in drilling and grouting work and in estimating work related thereto.

On June 11, 1974, plaintiff was awarded a contract by BOR to construct the Nambe Falls Dam. The work site was about 25 miles north of Sante Fe, New Mexico. Five bids were received by BOR relative to this work. Plaintiff’s low bid, which was accepted, was $5,119,753. Of the remaining four bids, the lowest was $5,475,000 and the highest was $6,368,587. BOR’s estimate for performing the contract was $4,777,507. While the relative closeness of the government’s estimate and the second lowest bid suggests that plaintiff’s bid should be considered reasonable without more, the fact that plaintiff’s bid anticipated completing the job 6 months earlier than the required completion date set forth in the contract suggests an overly optimistic approach to the contract, especially in light of the information contained in the pre-bid information made available to bidders regarding the geology, and the rock and soil conditions of the work site.

The contract in question contained the usual General Provisions found in federal government construction contracts, e.g., Specifications and Drawings (Article 2), Changes (Article 3), Differing Site Conditions (Article 4), Damages For Delay (Article 5), Disputes (Article 6), Payments to Contractor and release from contractor (Article 7) and Suspension of Work (Article 23). The contract also contained specific provisions related to the nature of the contract, i.e., dam construction. For example, section 4.1.2 (Open-Cut Excavation, General) and section 4.1.3 (Excavation, All Classes, For Concrete Arch Dam And Thrust Block). In the contract, BOR estimated the amount of anticipated excavation under bid item 39 to be 20,000 cubic yards, *670 and estimated that use of 21,250 bags of grout should be anticipated in performing the pressure grouting work required under bid item 17.

Information concerning the geology of the dam site and the rock and soil conditions at the dam site was available to bidders. This information indicated that difficulties were to be expected in drilling in the rocks and formation of the work site, with rock breakage and cavings clearly to be anticipated. G. Shupe testified that this information provided an excellent and clear description of what was encountered by plaintiff during construction of the dam. Plaintiff does not contend that any of its claims result from differing site conditions. On the other hand, Continental does contend that it encountered a differing site condition in performing its drilling and grouting work. The record, however, will not support this contention by Continental. The court finds that the pre-bid information furnished bidders clearly described the actual conditions that were encountered at the work site.

Plaintiff was given notice to proceed with the contract work on June 13, 1974. Work on the dam commenced on June 20, 1974. BOR accepted the contract work as substantially complete on April 13, 1976, the original contract completion date.

Nambe Palls Dam, as constructed, is a composite structure consisting of a prestressed concrete thin arch dam, a concrete thrust block, and an earth embankment dam. In effect, the thrust block joins the concrete and earth dams; it forms the left abutment for the concrete thin arch dam and the right abutment for the earth dam. An uncontrolled overflow spillway occupies the top central portion of the thin arch dam. The spillway is designed to traject discharges downstream and away from the thin arch dam. A small outlet works, located in the lower portion of the thin arch dam, is designed to provide for the downstream river requirements.

The prestressed concrete thin arch dam is located in a small gorge of the Rio Nambe. The thin arch dam is about 320 feet long and has a maximum height of 150 feet. The right abutment of the thin arch dam is keyed into the foundation rock. However, on the left abutment, the topography was such that a concrete thrust block was constructed to serve as an artificial abutment. As indicated above, the thrust block, which was somewhat pyramid in shape, also functioned as an abutment for the earth embankment dam. The concrete thrust block was 280 feet long at its base and had a maximum height and width of 108 feet and 78.5 feet respectively. A 5-foot wide by 7.5-foot high gallery extends from one end of the thrust block to the other. In an area atop the thrust block where it joins the earth embankment dam an access house was located. This access house provided entry to the gallery where there were various gauges, measuring instruments and other electrical items. The earth dam embankment portion of the Nambe Falls Dam contains approximately 200,000 cubic yards of earth materials.

The concrete portion of the dam, i.e., the thin arch dam and the thrust block, was divided into nine vertical sections, or “Blocks”, to facilitate construction. There was a contraction joint between each concrete Block. Looking downstream at the dam site, concrete Block 1 is at the extreme right end of the thin arch dam, and concrete Block 9 is at the extreme end of the thrust block. Each of these nine concrete Blocks was composed of a series of “lifts”. A lift was a 7V2-foot high mass of concrete whose width varied depending on its location in the concrete portion of the dam. In other words, the lifts were not all uniform in size and shape. The number of lifts in a Block also varied, from 4 to 20, again depending on where the Block was located in the concrete portion of the dam.

At the bottom of the right abutment, there was the small “U” shaped gorge mentioned above. The axis or center of the thin arch dam was directly in the middle of this small gorge. On the left side of the gorge, unlike the right side, there is only a short 46-foot rise in the terrain, thereafter the terrain slopes gradually upward to the *671 area upon which the thrust block and earth dam were built. This short rise on the left side of the gorge forms the left abutment for the bottom portion of the arch dam. The bottom portion of the thin arch dam is anchored to this short rise of terrain by the same means it was tied into the right abutment, i.e., by fillets poured into an excavated portion of the rise. As a result, the use of fillets in this area only covers a short distance and the thrust block formed the left abutment for the remaining portion of the arch dam.

Following award of the contract, plaintiff, as required by the contract, submitted to BOR on June 20, 1974, a construction program work schedule, inter alia. This schedule was in the form of a bar graph which set forth the dates on which work on the various (87 in number) contract items and activities would be completed. The construction work schedule indicated that plaintiff contemplated completing the contract on or about October 10, 1975, 484 days after the Notice to Proceed had been issued, and 186 days earlier than the completion date of April 13, 1976, set forth in the contract.

By letter dated July 22, 1974, BOR advised plaintiff it had reviewed its submissions of June 20, 1974, supra, and offered comments and suggestions relative thereto. These suggestions and comments by BOR raised questions about certain aspects of plaintiffs contemplated work program which reflected some concern as to the viability of the completion dates proposed by plaintiff.

On July 23, 1974, plaintiff again submitted a construction program work schedule which the record suggests was identical in material respects to the one submitted on June 20, 1974, and discussed above. On August 2, 1974, BOR wrote plaintiff a letter identical to the July 22, 1974, letter discussed above. On October 4, 1974, plaintiff submitted a revised construction program work schedule which did not differ from the June 20, 1974, submission regarding the contract completion date. The record indicates that plaintiff did not concern itself with the suggestions and comments of BOR relative to its contemplated construction work schedule set forth in the BOR letters of July 22, 1974, and August 2,1974. On December 3,1974, BOR advised plaintiff that its revised construction program was approved. The totality of the record supports a finding that BOR’s approval of the plaintiffs contemplated construction work schedule did not carry with it any agreement or acceptance or assurance that plaintiff would be able to complete the contract work by the contemplated date of October 10, 1975, some 186 days earlier than the date set forth in the contract; nor did it reflect a consensus by BOR that plaintiffs contemplated early completion date was reasonable and reasonably attainable.

As indicated previously, plaintiff substantially completed performance of the contract in issue on April 13, 1976. On July 7,1976, plaintiff executed a Release of Claims. This Release stated in pertinent part:

* * * [A]fter completion of all work and prior to final payment, the contractor [plaintiff] will furnish the United States [BOR] with a release of all claims;

NOW, THEREFORE, in consideration of the above premises and the payment by the United States to the contractor of the amount now due under the contract, to wit, the sum of twenty-one thousand three hundred fifty-seven and no/100 _______________ dollars ($21,357.00), the contractor hereby remises, releases, and forever discharges the United States, its officers, agents, and employees of and from all manner of debts, dues, liabilities, obligations, accounts, claims and demands whatsoever, in law and equity, under or by virtue of the said contract except: * * *

The release as executed by plaintiff contained 19 noted exceptions, totaling $2,719,-009. The following claims, and the amounts thereof, at issue in this case, were excepted from the operation of this release as follows:

*672 Date Description Amount Litigation Claim No.

December 22, 1975 Foundation Excavation 862,193 [Claim 1]

November 7, 1975 Upstream and Downstream Fillet Design Change 553,601 [Claim 2]

January 13, 1976 Excavation Changes in the Core Trench 141,644 [Claim 3]

November 26, 1975 Vertical Contraction Joint Treatment 165,929 [Claim 4]

January 8, 1976 Increased Costs and Delays Resulting from Concrete After-Cooling 55,059 [Claim 5]

January 15 and February 3, 1976 Galley Drain Holes 92,357 [Claim 6]

December 23, 1975 Changed Work Proposal for Change Order No. 1 and Ensuing Work on Embankment Cutoff Trench Drilling and Grouting Design 618,699 [Claim 7A]

April 6, 1976 Request for Equitable Adjustment Resulting from Minimal Foundation Grout Take 129,963 [Claim 7B]

April 22, 1975 Request for Equitable Adjustment Resulting from Excessive Bit Cost 99,564 [Claim 7C]

$2,719,009

Subsequent to execution of the release, plaintiff, by letters dated December 3, 1976, and April 7, 1977, requested BOR to consider settlement of all its claims based on the purported total cost for the work, in lieu of evaluating each excepted claim on its individual merit. Plaintiffs total cost claim, as submitted, was $5,565,297.38. However, the contracting officer, in his consideration of plaintiff’s claims, only considered those claims excepted from the release and not yet settled. Negotiations subsequent to execution of the release between plaintiff and the contracting officer resulted in full settlement of 10 of the 19 claims noted as exceptions to the release. On July 5, 1979, the contracting officer issued his findings of fact and decision on the 9 remaining claims noted as exceptions to the release and not otherwise settled. In this decision, the contracting officer denied plaintiff’s claims and further concluded that the plaintiff had been overpaid on certain of the claims and that, accordingly, the government had a proper claim against plaintiff for $78,922.75.

On August 30, 1979, plaintiff filed its petition [now complaint] with the United States Court of Claims setting forth four Causes of Action. On October 30, 1981, plaintiff filed an amended petition with the Court of Claims adding a Fifth Cause of Action [the spillway impingement claim]. On January 15, 1982, defendant filed its answer to plaintiff’s amended petition and asserted five Affirmative Defenses and a counterclaim in the amount of $78,922.75. Plaintiff’s reply to defendant’s counterclaim was filed on August 5, 1982.

Subsequent to filing the petition mentioned above, plaintiff on December 14, 1981, submitted another claim, set forth in its amended petition, designated as “the *673 spillway impingement claim” with the contracting officer contending that it was not aware of the existence of this claim “prior to the last few months.” The claim was certified to the contracting officer. Plaintiff advised the contracting officer that the spillway impingement claim was for $1,383,098 and was within the total cost claim of $4,697,602 previously submitted to the contracting officer but was not specifically identified because it was unknown to plaintiff at the time. On April 16,1982, the contracting officer issued findings of fact and decision denying this claim on the grounds that the claim was barred by the release plaintiff executed on July 7, 1976, and since it was asserted after final payment was made, the General Provisions of said contract precluded allowance of any such claim (see Articles 3(f) and 4(c) of the General Provisions, Standard Form 23-A, Oct. 1969 Edition).

II.

Before proceeding with the consideration and disposition of the ten claims asserted by plaintiff and its subcontractor, Continental, the court directs its attention to the affirmative defenses raised by defendant to certain of these claims, and to the five theories plaintiff and/or Continental advance in support of their efforts to recover damages.

A. Release

Defendant asserts that plaintiff’s claim for damages relating to primary excavation (which defendant construes to mean excavation work coming down the right abutment), which is part of claim No. 1, plaintiff’s claim for that portion of the concrete aftercooling claim which arose prior to June 10, 1975, which is part of claim No. 5, and plaintiff’s spillway impingement claim, which is claim No. 1.1, are barred by the operation of the general release plaintiff executed on July 7, 1976. Plaintiff concedes that this release, if held to be valid, effectively bars recovery on these claims. However, plaintiff argues that the release should not stand in the way of recovery by plaintiff on these claims because the release was obtained by economic duress, or by mutual mistake, or by failure of consideration, or by unilateral mistake.

It is well settled that execution by a contractor of a release which is complete on its face reflects the contractor’s unqualified acceptance and agreement with its terms and is binding on both parties. Inland Empire Builders, Inc. v. United States, 191 Ct.Cl. 742, 752 , 424 F.2d 1370, 1376 (1970). It is also well established that where a contractor has the right to reserve claims from the operation of a release, but fails to exercise that right, which is the situation in the case at bar with respect to the claims set forth above, it is neither improper nor unfair to preclude the contractor from maintaining a suit based on events which occurred prior to the execution of the release. H.L.C. & Associates Constr. Co. v. United States, 176 Ct.Cl. 285, 293 , 367 F.2d 586, 590 (1966).

There are, of course, special and limited circumstances in which a claim may be prosecuted despite the execution of a general release. See J.G. Watts Constr. Co. v. United States, 161 Ct.Cl. 801, 806-807 (1963). Plaintiff asserts that the facts in this case fit into the mold of such special and limited circumstances sufficient to avoid the operation of the release. The record, however, does not support such assertions.

First, plaintiff claims that economic duress vitiates the release. Case law does support the proposition that economic duress will serve to render a release inoperable. See Winn-Senter Constr. Co. v. United States, 110 Ct.Cl. 34, 65-66 , 75 F.Supp. 255, 260 (1948). In Winn-Senter, the release, which was held inoperable, was executed when a claim, not listed as an exception thereon, was pending before the contracting officer for decision. In executing the release, the contractor believed the claim before the contracting officer at the time would not be affected thereby. The Court of Claims concluded in the Winn-Senter case that the conduct of the parties in continuing to consider a claim after exe *674 ration of the release made it plain they never construed the release as barring the claim. No such facts are present in this case. None of the claims in question were pending before the contracting officer when the release was executed, nor were the claims considered after the execution of the release. Indeed, the contracting officer refused to consider any claim not listed as exceptions in the release.

In order to substantiate the allegations of economic duress, plaintiff must show more than a reluctance to accept the release and of financial embarrassment. Plaintiff must prove that the duress in question resulted from defendant’s conduct and not by the plaintiff’s necessities. Fruhauf Southwest Garment Co. v. United States, 126 Ct.Cl. 51, 62 , 111 F.Supp. 945, 951 (1953). There were no acts of the defendant, relative to execution by plaintiff of the release in question, that could be deemed coercive or which would constitute duress. The contract, which plaintiff signed, contained a provision (Article 7, General Provisions) which provided for the execution of a release prior to receipt of final payment. Such a provision cannot be deemed to be coercive since plaintiff was free to note as many exceptions thereto as it wished. In this case, plaintiff listed 19 exceptions. 1 He did not list the three claims set forth above. Plaintiff had the alternative to note as exceptions the claims in question. Defendant has not been shown to be guilty of any coercive acts relative to plaintiff’s voluntary execution of the release. Plaintiff did not protest being asked to execute the release nor was it inhibited in any way by BOR in listing its exceptions to the release. Compare James Shewan & Sons, Inc. v. United States, 73 Ct.Cl. 49, 81-83 (1931). Plaintiff has failed to prove the necessary elements of duress as set forth by the Court of Claims in Fruhauf Southwest Garment Co. v. United States, supra. See B.D. Click Co. v. United States, 222 Ct.Cl. 290, 305 , 614 F.2d 748, 756 (1980); Johnson, Drake & Piper, Inc. v. United States, 209 Ct.Cl. 313, 321-323, 327-331 , 531 F.2d 1037, 1042-1044, 1046-1048 (1976). See also Inland Empire Builders, Inc. v. United States, supra, 191 Ct.Cl. at 753-754 , 424 F.2d at 1376-1377 .

Second, plaintiff claims that a mutual mistake as to material facts existed relative to execution of the release and thus plaintiff should not be bound by the release. Again, case law supports the view that where it is shown that by reason of a mutual mistake, neither party intended that the release cover a certain claim, the court will reform the release. See J.G. Watts Constr. Co. v. United States, supra, and cases cited therein. There are no facts in this record which would support a finding of mutual mistake. This is not a case where both parties agreed that a contractor should, in performing a contract, be paid for state taxes on contract materials as part of the contract price and that after completion of the contract and execution of a release the state changed its laws and imposed taxes on the contractor. In such circumstances, a mutual mistake exists and reformation of the release is justified since neither party could have been aware when the release was executed that such a cost *675 had been incurred. See Duhame v. United States, 133 Ct.Cl. 360, 363 , 135 F.Supp. 742, 743, 744 (1955); Harrison Eng’g and Constr. Corp. v. United States, 107 Ct.Cl. 205 , 68 F.Supp. 350 (1946). In this case, plaintiff certainly was aware, or should have been aware, of the costs and claims connected with contract performance. 2 The actions of the contracting officer after the release was executed certainly demonstrate that BOR intended that the executed release have a binding efféct on all claims not listed as exceptions therein. Any mistake in this regard was, at best, a unilateral mistake on plaintiff’s part, not a mutual mistake of both parties. Plaintiff’s claim of a mutual mistake in the execution of the release must be rejected.

Next, as might be expected, plaintiff claims the release should be rescinded because of plaintiff’s unilateral mistake in not excepting the claims in question from the release. As a general rule, mutual mistake underscores a claim for reformation, and unilateral mistake is usually associated with a claim for rescission. Where rescission of a release is sought, unilateral mistake can sometimes be grounds for granting relief. Relief on the grounds of unilateral mistake, however, presents a thorny problem. See 3 A. Corbin, Corbin on Contracts §§ 608, 609 (1960). See also Hester v. New Amsterdam Casualty Co., 268 F.Supp. 623 (D.S.C.1967), a case cited by plaintiff in support of its unilateral mistake — rescission contention, but which, on the facts, is inapposite.

In essence, although not articulated as such in plaintiff’s brief, plaintiff seeks to rescind the release under equitable principles. However, plaintiff has failed to make a showing of entitlement to any relief in this regard. See Inland Empire Builders, Inc. v. United States, supra, 191 Ct.Cl. at 756 , 424 F.2d at 1378 . Moreover, it is not unreasonable to conclude in this case, that any unilateral mistake of plaintiff in not including an exception when executing a general release upon completing the contract and receiving payment therefor, will not avoid the binding effect of the release. Plaintiff stresses that it only signed the release because it expected BOR to settle all its claims by payment thereof. However, the subjective and unmanifested intention of plaintiff’s president (G. Shupe) will not avoid the otherwise general effect of a release. See H.L.C. & Associates Constr. Co. v. United States, supra, 176 Ct.Cl. at 295 , 367 F.2d at 591-592 .

Finally, plaintiff argues that since the release was given in exchange for sums already due, the release was inoperative for failure of consideration. This argument is without merit. United States v. William Cramp & Sons Co., 206 U.S. 118 , 27 S.Ct. 676 , 51 L.Ed. 983 (1907); Inland Empire Builders, Inc. v. United States, supra, 191 Ct.Cl. at 751-752 , 424 F.2d at 1376 .

In this case, the release is deemed operative and, therefore, serves to bar the claims, or portions thereof, described above. See plaintiff’s interest claim, discussed in Part V, infra, which is also deemed barred by the July 7,1976, release. Further, plaintiff is barred, in any event, from recovering on any claims asserted in this litigation which involve any amounts in excess of the amounts set forth in the release relative to the excepted claims listed therein. See A.L. Coupe Constr. Co. v. United States, 134 Ct.Cl. 392, 399 , 139 *676 F.Supp. 61, 65 (1956), and cases cited therein. 3

B. Theories Of Recovery

Plaintiff seeks to recover over $4 million from defendant as damages arising out of its contract -with BOR to construct the Nambe Falls Dam. In its submissions, plaintiff concedes that the release sets forth $2,719,009 as the exclusion amount of the exceptions thereto. Plaintiff claims entitlement to over $4 million on the alternative recovery theories of total cost, quantum meruit, jury verdict, breach of contract and equitable adjustment.

Under the total cost theory, a contractor seeks to recover the difference between the actual costs incurred in contract performance and its bid or estimated costs. The total cost theory of recovery was not favored by the United States Court of Claims and was tolerated only when no other mode of recovery was available, and when the reliability of the supporting evidence was fully substantiated. WRB Corp. v. United States, 183 Ct.Cl. 409, 426-427 (1968). The court is not persuaded that it was impossible or highly impracticable for plaintiff to determine the costs it incurred relative to each asserted claim. Plaintiffs assertion that this can be explained by the fact it lost some of its records is unconvincing. 4 Further, there is some question as to the realistic nature of plaintiffs bid. In the court’s view, based on the totality of the record, it was unrealistic of plaintiff to expect to complete this contract 6 months earlier than the contract completion date in view of the geology of the work site and the instability of the rock which had to be excavated. Further, plaintiff’s construction program schedule was suspect in that, given the potential construction problems and difficulties evident in the bid documents, plaintiff’s early completion schedule was overly optimistic. Finally, the record indicates that plaintiff was responsible for some of the added costs it incurred. Indeed, plaintiff concedes it was responsible for some overexcavation and it seems clear plaintiff was responsible for some inefficiencies in contract performance, a fact noted by plaintiff’s subcontractor. Plaintiff’s efforts to take refuge in the total cost approach by claiming it took into account its own deficiencies and shortcomings is a feeble justification for acceptance of such an approach since the integrity of the approach has been tainted and this record does not persuade that it should be ignored by viewing the approach as a “modified total cost” recovery approach. See WRB Corp. v. United States, supra, 183 Ct.Cl. at 426-427 . This record will not support a recovery in this case based on the total cost theory by either plaintiff or its subcontractor, Continental.

Plaintiff’s jury verdict approach to recovery is likewise most unpersuasive on *677 this record. While the United States Court of Claims has allowed jury verdict recoveries, it has done so where there was no more reliable method for computing damages and the evidence was sufficient to enable the court to make a fair and reasonable approximation. See WRB Corp. v. United States, supra, 183 Ct.Cl. at 425 , and cases cited therein. Here, the court is of the view that a more reliable method for computing damages for these various claims was available and should have been followed by plaintiff. Plaintiff’s officials had long experience in construction contracts and in negotiating claims. More importantly, the record in this case and the confusion and complexity built into the damage figures presented by plaintiff preclude the court from being able to make a fair and reasonable approximation necessary for resorting to a total award jury verdict remedy, assuming one to be justified. Plaintiff is not entitled to a total award recovery in this case on the basis of a jury verdict.

Next, plaintiff seeks recovery on the basis of quantum meruit. However, it is well settled that recovery in this court, as was the holding in its predecessor court, on a quantum meruit basis is an action on a contract implied-in-law, as distinguished from a suit on a contract implied-in-fact, and is therefore beyond the jurisdiction of this court. See Fincke v. United States, 230 Ct.Cl. 233, 246-247 , 675 F.2d 289, 296-297 (1982), and cases cited therein. This fact serves to distinguish United States v. Algernon Blair, Inc., 479 F.2d 638 (4th Cir.1973), cited and relied on by plaintiff, which involved a suit by a subcontractor, suing in the name of the United States, against a prime contractor and its surety in the District Court in a Miller Act case. Algernon Blair was not a Tucker Act case.

Plaintiff also seeks recovery on the theory of breach of contract. However, it seems clear that plaintiff’s claims, and the claims of its subcontractor, are redressable under various provisions of the contract. Accordingly, plaintiff is limited to the relief provided by the contract, i.e., equitable adjustments, and is not entitled to any further or different relief. See L.W. Foster Sportswear Co. v. United States, 186 Ct.Cl. 499, 502 , 405 F.2d 1285, 1287 (1969). Despite its arguments in its briefs and at oral argument to the contrary, plaintiff does seem to recognize that all its claims can be resolved on the basis of equitable adjustment determination (see plaintiff’s initial post-trial brief, p. 3, note 1).

III.

Plaintiff makes much of the fact that it anticipated completing the Nambe Falls Dam contract 6 months earlier than contemplated in the contract. It did substantially complete the contract within the time period called for by the contract. It is, of course, settled that a contractor is not precluded from recovering delay (or impact) damages merely because it completed a contract within the period provided by the contract. See Coley Properties Corp. v. United States, 219 Ct.Cl. 227, 234-235 , 593 F.2d 380, 384-385 (1979). In this case, plaintiff seeks to recover, inter alia, damages for over 5 months (160 calendar days) of delay in contract completion which it attributes to governmental actions. Both parties resort to a “critical path method” (CPM) of construction analysis in support of their positions regarding recovery of delay damages. 5 Each party attacks the *678 other’s critical path method analysis and defends its own. In its consideration of the various damage claims asserted by plaintiff, the court must determine whether government-caused delay was responsible for said damages, and, if so, determine the amount thereof. In this discussion, the court will follow the claim numbering and description format utilized by plaintiff.

A. Claim 1 — Foundation Excavation Changes

Under claim 1, plaintiff seeks to recover $1,033,864. 6 Defendant maintains that plaintiff is only entitled to recover $27,937 related to thrust block foundation work.

Facts

Under the contract, it was estimated that the foundation for the concrete dam would entail excavation of 20,000 cubic yards (c.y.) of material. The actual amount of material excavated was determined by BOR to be 23,350 c.y. This difference forms the basis, in part at least, for plaintiff’s claim 1. However, plaintiff concedes that it is responsible for some of this so-called overexcavation and defendant maintains that plaintiff’s method of performance contributed greatly to said overexcavation. Further, plaintiff contends that its overexcavation problems resulted, in the main, from the geology of the site. As indicated previously, the site geology was accurately reflected in the pre-bid documents made available to plaintiff. Plaintiff was aware of this site geology situation before it submitted its bid and presumably took these facts and potentialities into consideration, or should have, when preparing its bid. The manner in which this claim has been characterized and/or presented by plaintiff has produced a somewhat confusing and contradictory claim which has caused no end of problems for the court.

Defendant maintains that the bulk of claim 1 embraces a claim for primary excavation. Primary excavation involved the initial removal by means of drilling, blasting and scaling, of the bulk of material necessary to achieve a competent foundation. In the vernacular of this case, primary excavation was concerned basically with going down the slope or hill. Plaintiff concedes that any claim for primary excavation is barred by the release it executed, if said release is determined to be valid — which is the case here as discussed previously. Plaintiff, however, contends that claim 1 only involves work it performed going up the slope or hill. Cleanup work, going up the hill, plaintiff argues, should not be characterized as primary excavation. It is not unfair, on the basis of the briefs and oral argument, to attribute some of the confusion in the presentation of claim 1 to plaintiff’s efforts to avoid the effect of the release. Upon careful review of a conflicting and sometimes confusing record, the court concludes that the bulk of claim 1 involves primary excavation and is therefore barred by the release. As to that segment of claim 1 that involves foundation work which is properly within the ambit of claim 1, i.e., work in the thrust block, plaintiff is entitled to recover $27,937. As to that segment of claim 1, as framed by plaintiff, which involves cleanup work in the arch dam foundation area, it is concluded that this segment more properly belongs in claim 2 and thus will be dealt with when that claim is considered.

*679 As indicated previously, the concrete portion of the dam consisted of a thin arch dam (arch dam) and a thrust block. Excavation work in both the thrust block and arch dam areas was conducted in two stages. The first stage involved drilling, blasting holes, and blasting with explosives to the excavation grade or lines specified by the contract. 7 After the plaintiff blasted to the design grade or line, it scaled off any loose material from the excavated surface. The blasted material was then removed from the area, as was any loose and remaining unstable rock. The foundation was cleaned with high pressure jets of air and water. This stage of excavation has been deemed the primary excavation or going down the slope or hill stage. After completion of this primary stage of excavation, BOR inspectors examined the foundation area to ensure the competency of the rock surface upon which the concrete dam was to be placed.

The second stage of excavation was the final cleanup phase. This stage took place immediately prior to pouring concrete lifts onto the rock foundation and involved removal of all loose or disintegrated material. The foundation surface was then cleaned with high pressure jets of air and water. After this final cleanup, the concrete was poured onto the rock foundation. Unlike the primary excavation stage, cleanup excavation did not proceed as one coherent operation. Rather, it was really a part of the concrete operation since the time of final cleanup for a particular foundation area depended upon the timing of the concrete pouring in that particular area. In other words, cleanup excavation was dependent upon the concrete pouring schedule because cleanup for each off-rock concrete lift had to be done immediately prior to the pouring of concrete. Cleanup excavation proceeded in the same sequence as the pouring of the off-rock concrete lifts.

Foundation excavation work for the concrete portion of the Nambes Falls Dam began in the thrust block area. The drilling and blasting work for primary excavation of the thrust block began on July 26, 1974, and was completed to the contract excavation grade or line as of September 7, 1974. Although not entirely clear in the record, final cleanup on the thrust block appears to have begun sometime in September or October 1974. Concrete placement in the thrust block began on October 29, 1974.

Plaintiff excavated a total of 17,273 c.y. from the thrust block area. This was 810 c.y. more than the prebid estimate of 16,-563 c.y. The record does not indicate precisely how much of this overexcavation took place in the primary stage of excavation and how much took place during cleanup excavation. Given the differing nature of the two types of excavation, however, it is reasonable to conclude in the absence of any persuasive evidence to the contrary, that in all probability most of the 810 c.y. of overexcavation took place during the primary stage of excavation.

In the thrust block area, unlike the arch dam right abutment area, no clear dividing line exists between primary and cleanup excavation. The record shows that plaintiff spent a considerable amount of time involving foundation cleanup work in the thrust block area. Plaintiff claims that an additional crew worked on thrust block foundation preparation for 15 weeks between September 15,1974, and January 16, 1975. Defendant asserts that a review of *680 the work records shows plaintiff spent 233 crew hours, not the 344 crew hours it claims on this work. The court determines that defendant’s assertions in this area are more accurate than plaintiff’s since defendant’s assertions were based upon plaintiff’s work records for this work period. Plaintiff’s contention, on the other hand, is based upon the unpersuasive assumption that an extra crew worked throughout the September 15, 1974 — January 16, 1975, period on foundation preparation only in the thrust block area. However, defendant’s analysis of plaintiff’s own work records showed the exact times that this extra crew worked on foundation preparation and defendant used that data in support of its assertions.

Plaintiff completed the off-rock 8 placement of concrete on the thrust block on January 16, 1975. Plaintiff notified BOR on April 2, 1975, that it was claiming additional amounts for cleanup excavation in the thrust block area. All concrete placement e.g., off-rock and all other, in the thrust block area was substantially completed by April 14, 1975. Concrete placement on the thrust block took 24 weeks instead of the 19 weeks plaintiff contemplated, but it did not delay the eventual completion of the Nambe Falls Dam project since this work was not on the critical path. In any event, the record shows that most of this delay was due to time spent on formwork and not time spent on foundation preparation.

While plaintiff was proceeding with foundation excavation work on the thrust block, it was making plans to commence foundation excavation work on the arch dam. On August 26,1974, plaintiff submitted a work plan or work schedule to BOR for the left and right abutments of the arch dam. In its plan, plaintiff scheduled excavation on the first two sections of the right abutment to proceed simultaneously with excavation on the left abutment. On August 27,1974, plaintiff submitted its drilling and blasting plan to BOR. This plan showed 14 separate blasting lifts on the right abutment and 2 separate blasting lifts on the left abutment. 9 Each lift was to consist of 12-foot vertical blasting holes. On August 29, 1974, BOR approved plaintiff’s blasting plan subject to modification if the results proved unsatisfactory. This plan scheduled arch dam foundation excavation to be a 6-week activity.

On August 30,1974, plaintiff began excavation of the right abutment with an excavation blast (shot) on that date. Plaintiff then discontinued work on the right abutment in order to perform primary work on the left abutment during the month of September 1974. Plaintiff made two shots on the left abutment and, as of September 20, 1974, a substantial portion of the right abutment had been drilled and shot to the contract grade or line.

During the course of its excavation work in September, plaintiff recognized that it would need to blast trim shots in the bottom of the gorge later in the fall of 1974. Because of the late dates of these planned trim blasts, plaintiff foresaw that this blasting would be performed in the same area where concrete placement for the thrust block and completed foundation grouting were planned. The contract had a provision in paragraph 1.15.13 specifically governing blasting during concrete placement which stated: “Also, except for very light controlled blasts, subject to the approval of the contracting officer, no blasting will be permitted within a distance of 100 feet of concrete placement or of completed foundation grout holes.” This provision served the obvious function of preventing the concrete and foundation grout from blasting damage.

*681 In order to secure permission for blasting in the gorge during the late fall, plaintiff requested BOR’s approval for blasts of not more than 50 pounds (lbs.) within 100 feet of concrete placement and completed foundation grouting. Plaintiff’s president, G.M. Shupe, testified that light blasting is blasting in the range of 10-20 lbs. per detonation. Therefore, even by plaintiff’s president’s own definition, plaintiff’s request for 50 lbs. per detonation was beyond the scope of the contract since the contract only allowed the contracting officer to approve “very light controlled blasting.” Thus, the contracting officer reasonably denied plaintiff permission to blast with up to 50 lbs. per detonation in the area in question.

In October 1974, plaintiff again began to excavate the right abutment of the arch dam. Prior to October, plaintiff sought and received permission to use 40-foot long slope holes for blasting on the right abutment. As indicated earlier, plaintiff had planned to use 12-foot slope holes for this blasting. Plaintiff also advised BOR that it intended to drill its blasting holes behind the contract excavation line. Plaintiff’s reason for wanting this setback was to avoid leaving protrusions (also called “tights”) which otherwise would have to be removed in the latter phase of the primary excavation process. By setting its drills behind the contract excavation line, plaintiff hoped to ensure that no protrusions would remain. Although plaintiff requested only a 1-foot setback, the testimony of the witnesses, including one of plaintiff's, established conclusively that the drill setup required a setback of greater than 1 foot to adequately ensure a 1-foot setback all the way down the slope. Although plaintiff maintains that its setback was only 1 foot, the court concludes, based upon all the relevant evidence, that plaintiff’s setback its drills an average of IV2 feet. Plaintiff agreed to bear the expense of any overexcavation which resulted from the 40-foot slope blast holes and the setback of the drills behind the contract excavation line.

Plaintiff excavated the right abutment during October, November, and December 1974. This primary excavation of the arch dam was completed on January 9, 1975. Plaintiff had planned to complete this excavation by November 1, 1974, 69 days earlier than it was actually completed. On January 9, 1974, BOR accepted the arch dam foundation as suitable for concrete. As of that date, primary excavation on the right and left abutments had been completed. Plaintiff excavated a total of 3,527 c.y. from the right abutment. The pre-bid estimate of material to be removed from the right abutment was 2,278 c.y.; thus, plaintiff had a overexcavation in the amount of 1,249 c.y. In the left abutment, plaintiff had an overexcavation in the amount of 1,394 c.y. since it removed 2,553 c.y. of material and the pre-bid estimate was 1,159 c.y.

On the right abutment, most of the overexcavation took place during the primary excavation phase, that is before January 9, 1975. Defendant contends that the overexcavation on the right abutment was the result of two factors: plaintiff’s setback of its drills on the right abutment and plaintiff’s blasting techniques. Plaintiff concedes an amount of overexcavation for the setback of its drills; however, it asserts that its blasting techniques on the right abutment were reasonable for the condition of the rock to be excavated. Specifically, defendant contends that plaintiff in excavating the right abutment should have: (1) used presplitting blasting as it had in the thrust block area; (2) kept its original plan to use 12-foot blasting lifts instead of substituting 40-foot lifts, and (3) used timed delays inside each blast pattern. 10 Defendant presented expert testimony asserting that plaintiff should have used these techniques; while plaintiff presented expert testimony that the blasting techniques used *682 were reasonable and that the techniques suggested by defendant were unsuitable for the type of excavation involved in the right abutment area.

After a review of the expert testimony presented on the matter by the parties, and the record as a whole, the court finds that the blasting techniques used by plaintiff on the right abutment were utilized in an attempt to speed up the excavation process, not in an attempt to control the amount of overexcavation. The court, on this record, cannot determine which of the three factors mentioned by defendant was primarily responsible for the overexcavation. Rather, the court concludes that the three factors taken together demonstrate that plaintiff’s emphasis in its blasting program was on speeding up excavating, not on controlling overexcavation. The record suggests rather persuasively that plaintiff was intent on making up for time previously lost by adoption of blasting and drilling methods that put more emphasis on quick performance than on concern for overexcavation. The record shows that reasonable and competent experts differed on the appropriateness of using the three methods suggested by defendant. However, the court determines, based on a preponderance of the evidence in the record, that given the fracturing characteristics of the foundation rock and plaintiff’s awareness of these characteristics, plaintiff should have adopted a more cautious approach to blasting on the right abutment.

The record supports also the probability that had the blasting efforts of plaintiff been more deliberate and cautious, e.g., use of 12-foot lifts, presplitting and predetonation, much less overexcavation would have taken place. It is not without some significance that plaintiff used presplitting in its thrust block foundation work and there is no evidence it was unsuccessful. On this record, one cannot determine whether presplitting on the right abutment would have posed a safety problem or not. There is ample evidence in the record that use of the 40-foot drill holes increased the tendency of the drill bits to wander away from their intended course and thus resulted in greater excavation than would have been the case with 12-foot holes. In short, one had greater control over the drilling effort with 12-foot holes than one did with 40-foot holes. On the other hand, the use of 12-foot holes was more time consuming than was the use of 40-foot holes. Given the known characteristics of the rock foundation, plaintiff should have at least tried the three methods advocated by defendant and waited to see the results before proceeding with more accelerated blasting techniques. Thus, plaintiff’s blasting and drilling techniques were the direct and the most significant cause of the overexcavation on the right abutment.

On December 21, 1974, during the excavation of the right abutment, BOR directed plaintiff to remove an area of unstable rock downstream from the right abutment. Plaintiff performed this additional excavation work on December 21, 1974. This December 21, 1974, directive was the only BOR directive which authorized plaintiff to perform primary excavation on the right abutment in addition to that required by the contract. The record shows that the excavation performed pursuant to the December 21, 1974, directive was minor and caused no delay in completion of the project. Moreover, plaintiff received adequate reimbursement for the work since BOR paid it at the unit price for all work done pursuant to the directive.

On January 9, 1975, when the arch dam foundation was accepted for concrete placement by BOR, plaintiff was 69 days behind on its schedule for the construction of the arch dam. This delay was primarily caused by two factors: plaintiff’s inability to excavate the left and right abutments concurrently, as plaintiff had planned in its original work schedule, and the overexcavation and removal of material in the concrete dam foundation areas. As discussed earlier, defendant was not responsible for causing the failure to proceed concurrently with excavation on the left and right abutment nor was defendant responsible for causing the overexcavation.

*683 The final cleanup and concrete phase of construction began on the arch dam after the acceptance of the arch dam foundation on January 9, 1975. The first concrete pouring for the arch dam took place on January 23, 1975. This final cleanup was required by the contract. The relevant contract provision provided: “Just prior to placing concrete, a final cleanup of the rock surface shall be made by barring, wedging, picking, or other approved methods. All loose, shattered, or disintegrated material shall be removed, and the final surface cleaned with jets of air and water under high pressure.”

There is dispute between the parties on the reason why it took 14 days after BOR accepted the arch dam foundation to begin the concrete pouring. Plaintiff had originally scheduled this interim period as 3 days; thus, the concrete pouring was delayed 11 days from plaintiff’s original schedule. Plaintiff maintains that this delay was caused by excessive BOR inspectors’ directives relative to cleanup excavation; defendant contends that this period involved only the performance of contract work as indicated by the inspectors. While the evidence on the matter is conflicting, the court determines that plaintiff was only performing work required by the contract during the January 9 to January 23, 1975, period. This work included drilling and grouting in the arch dam foundation area, placement of crack detection tape in the foundation, and cleanup preparation. The foundation cleanup excavation performed during this period was not in excess of that required by the contract, but was work required by the terms of the contract. In fact, from the evidence presented it is clear that plaintiff did not complain to BOR during this period before the first arch dam concrete pour about excessive cleanup excavation work being required.

As of January 9, 1975, plaintiff had completed all primary excavation on the arch dam and had entered into the concrete pouring phase of the project.

DISCUSSION

Plaintiff bases its foundation excavation claim on paragraph 4.1.3 of the contract. Paragraph 4.1.3 provides, in pertinent part:

When the excavation has been completed to the approximate grade established by the contracting officer, the surface shall be cleaned off with an air and water jet under high pressure for purposes of inspection. If the foundation is found to be unsatisfactory, as determined by the contracting officer, additional excavation shall be made as directed, and the surface again cleaned for inspection: Provided, That any increase in cost due to redimensioning or resloping will be paid to the contractor in accordance with Paragraph 4.1.2. This procedure shall be repeated until a satisfactory foundation is obtained.

Plaintiff contends that it was required to reslope and redimension both the arch dam and thrust block foundations because of BOR directives. The record does not support this contention. Implicit in plaintiff’s contention is the assertion that these directives were responsible for most of the overexcavation of material during performance of the foundation excavation work. As a result, plaintiff maintains that it is entitled to an equitable adjustment pursuant to paragraph 4.1.2 of the contract.

It is difficult, however, to discern precisely what extra work plaintiff is claiming in this Foundation Excavation Changes Claim. Plaintiff presents its claim in broad and ambiguous terms. Furthermore, there is often no logical relationship between plaintiff’s individual itemized damages and the general nature of the claim asserted. For example, in the Foundation Excavation Changes Claim, Claim 1, plaintiff seeks $566,685 as additional concrete costs, without explaining why concrete costs should be included in an excavation claim. The court concludes that the inclusion of said concrete costs appears to result from the total cost nature of plaintiff’s claim. Apparently, plaintiff has simply allocated its additional job costs to various asserted claims without regard to whether a rational *684 relationship exists between the costs allocated and the substantive nature of the claim to which they were allocated. 11

Plaintiff’s counsel maintained at oral argument that claim 1 involved only a claim for extra cleanup excavation work (i.e., going up the hill) beyond the scope of the contract and that primary excavation (coming down the hill) was not part of the claim. It is evident from plaintiff’s submissions, however, that plaintiff’s claim 1 does, indeed, involve primary as well as cleanup excavation work. The conflict between plaintiff’s counsel’s characterization of the claim and the substance of the claim is indicative of the confusion and ambiguity which permeates plaintiff’s claim. 12 This confusing and ambiguous presentation of the claims made it extremely difficult for the court to discern the essence of plaintiff’s claim. In a case with as complex and voluminous a record as the one at bar, the court’s task, at best, is time consuming and difficult; but it is much more so in the present case due to the manner in which plaintiff’s claim 1 has been presented.

While made more difficult because of plaintiff’s ambiguous presentation of claim I, the court has determined that claim 1 is (1) a claim for both primary and cleanup excavation in the thrust block, and (2) a claim for only primary excavation in the arch dam. The reason for this determination is that cleanup excavation was an integral part of another of plaintiff’s claim, i.e., “Claim 2 — Fillet Design Changes.” Cleanup excavation in the arch dam area was a part of the concrete pouring operation of the fillets for the arch dam. This cleanup excavation took place immediately prior to the placement of each off-rock concrete pour. Thus, cleanup excavation was directly affected by the fillet design change, which is the basis of plaintiff’s claim 2, since the fillet design change had a direct effect upon the amount of foundation area which had to undergo cleanup excavation. Claim 1 as presented by plaintiff, appears to contain some overlapping with claim 2 in relation to the damages claimed by plaintiff, i.e., duplication of costs. The court’s determination of the scope and reach of claims 1 and 2 avoids this problem of possible duplication of damages and presents, hopefully, the true essence of claim 1.

As determined earlier, plaintiff’s claim for primary excavation is barred by the July 7, 1976, release. Even if plaintiff’s claim is deemed not barred by this release, plaintiff still would not be entitled to an equitable adjustment on its foundation excavation changes claim except as indicated below. There are two reasons for this: First, plaintiff did not comply with the contract’s requirement that it receive written directives in order to obtain an equitable adjustment under the contract clause it bases its claim on. Second, plaintiff’s blasting techniques, and drill setback, not BOR directives, were primarily responsible for plaintiff’s excavation problems.

Paragraph 4.1.2 of the contract, which was referenced in paragraph 4.1.3 — the source of plaintiff’s claim, provides in pertinent part:

Any and all excess excavation for the convenience of the contractor or overexcavation performed by the contractor for *685 any purpose or reason, except as may be ordered in writing by the contracting officer, and whether or not due to the fault of the contractor, shall be at the expense of the contractor. * * * [Emphasis supplied.]

Plaintiff did not comply with this provision of the contract since it received no written directive to perform foundation excavation (other than the December 21, 1974, directive discussed earlier). Plaintiffs contention that it was entitled to rely on the directives of government inspectors relative to removal of non-contract excavation must be rejected in view of the specific provision of paragraph 4.1.2 that any such directive must be ordered in writing by the contracting officer. No such requirement, except where otherwise indicated herein, was met by plaintiff relative to the excavation claim it advances in claim 1. See Woodcraft Corp. v. United States, 146 Ct.Cl. 101, 103 , 173 F.Supp. 613, 614 (1959). If plaintiff felt that BOR was requiring excavation beyond that required by the contract, it certainly could have, and should have, requested BOR to issue a formal written directive, as it did for the December 21, 1974, BOR oral directive. See Turnbull, Inc. v. United States, 180 Ct.Cl. 1010, 1020 , 389 F.2d 1007, 1012 (1967). As will be discussed in claim 2, plaintiff requested written directives on other occasions when ordered to do work for which plaintiff felt additional compensation was due, e.g., removal of clay seam on left abutment on March 7,1975, and removal of loosened rock and installation of rock bolts on right abutment on April 8 and 9, 1975. Moreover, plaintiff’s failure to request such a written directive, when it had demonstrated through its request relating to the December 21, 1974, oral BOR directive that it recognized the need for such a directive, strongly suggests that plaintiff did not believe it was entitled to an equitable adjustment for such overexcavation. Plaintiff’s failure to request or receive a written directive for excavation work (with the exception of work performed pursuant to the December 21, 1974, directive) precludes plaintiff from receiving an equitable adjustment for any extra excavation work. See Plumley v. United States, 226 U.S. 545 , 33 S.Ct. 139 , 57 L.Ed. 342 (1913); General Bronze Corp. v. United States, 168 Ct.Cl. 176, 186-188 , 338 F.2d 117, 123-124 (1964). See also Woodcraft Corp. v. United States, supra, 146 Ct.Cl. at 1031 , 173 F.Supp. at 614 . It is not unreasonable to assume, under these circumstances, that the excavation work performed by plaintiff was at the time either work required by the contract or the result of plaintiff’s construction methods which plaintiff recognized at the time it was performing the work as being its responsibility. The totality of this record supports this finding.

As discussed earlier, the court has found that plaintiff’s blasting techniques and drill operations (the lVk-foot setback), not BOR directives, caused overexcavation during foundation excavation work. On this additional ground, plaintiff is not entitled to an equitable adjustment for overexcavation. Plaintiff, not defendant, had the responsibility to ensure that its blasting and drilling did not cause excessive excavation beyond the contract design line, and absent a written directive from the contracting officer, plaintiff was responsible for all overexcavation.

The only item plaintiff can recover for in claim 1 is certain excavation in the thrust block area. There is no clear line of demarcation between primary excavation and cleanup operations in the thrust block area. Defendant concedes liability for additional foundation work in the thrust block area but allows plaintiff only $27,937 in damages for this work while plaintiff seeks $40,526. Accordingly, the issue here is which damage computation is correct. Both parties calculate their damages based upon the same period of thrust block foundation work, September 15, 1974, to January 16, 1975. Plaintiff bases its damage calculations on the fact that an extra crew was working during this period. Plaintiff’s calculations further assume that this extra crew was always involved in foundation work. Defendant, on the other hand, used plaintiff’s own work records and BOR in *686 spector’s reports to determine how much time this crew actually spent on this foundation work. Given the fact that defendant’s damage calculations are supported by work records and inspector’s reports, while plaintiff’s are not, defendant’s damage figures are deemed more reliable and persuasive relative to the extra excavation foundation costs which plaintiff incurred in the thrust block area.

Plaintiff has raised a number of other arguments and positions relative to why it believes it is entitled to recover over $1 million on claim 1. The court has considered these various contentions and has found them to be unpersuasive.

On the basis of the above discussion, the court finds that plaintiff is entitled to recover $27,937 as an equitable adjustment for extra work performed on the foundation in the thrust block area. In all other respects, plaintiff’s claim 1 for foundation excavation changes is denied. 13

B. Claim 1.1 — Spillway Impingement

Under claim 1.1, plaintiff seeks to recover $1,420,596. This claim, as indicated earlier, is barred by the release since it was not set forth therein as an exception thereto. Plaintiff contends that the BOR directed the excavation of some 2,620 c.y. of material in an area of the work site which plaintiff has designed the “spillway impingement” area. The area was downstream of the left abutment and the thrust block area. Plaintiff maintains that during September and October 1974, it removed 2,620 c.y. of material from the spillway impingement area. It is to be noted that this 2,620 c.y. of material is not included in the BOR’s recorded excavated removal figure of 23,500 c.y. Indeed, there is no reliable evidence in the record that BOR directed the removal of this amount of material in the area under consideration and the BOR has no record of the removal of any such quantity of material from said area. Further, plaintiff never notified the contracting officer relative to removal of this large amount of material from this area within the time period required by the contract, or before final payment. Indeed, plaintiff never presented this claim to the contracting officer until after suit was filed in this court, some 6 years later.

FACTS

The origin of this claim, as presented by plaintiff, is to be found in settled events which occurred during contract performance.

Under the terms of the contract, plaintiff was required to excavate a notch in rock running from the downstream toe of the thrust block in the vicinity of block 4 for the placement of a 12-inch drain pipe. The purpose of the pipe was to drain water from the thrust block gallery into the Nambe Falls River which flowed through an outlet works located in the arch dam into the gorge below the dam. This excavation, as originally planned, would have left standing adjacent to the drainpipe a knob or nose of rock on the arch dam side of the drainpipe.

On August 24, 1976, plaintiff exploded a blasting shot for thrust block excavation. This August 24th shot loosened the knob of rock adjacent to the 12-inch drainpipe. Plaintiff’s personnel discussed the matter with BOR personnel and expressed their concern about this loosened knob of rock. On September 3, 1974, BOR orally directed *687 that the knob of rock be removed. Plaintiff executed blasts on September 18, and September 24, 1974, to remove the knob of rock adjacent to the drainpipe. The September 24, 1974, shot also was for excavation of the drainpipe area. The removal of the material excavated by these two shots took 5 days and was accomplished by pushing the material into the gorge with a backhoe. The excavation work for the knob and the drainpipe involved removal of a total of 355 c.y. of material. This 355 c.y. figure was included in the BOR total cubic yardage figure of 23,500, mentiont . earlier. Of this 355 c.y., 178 c.y. were removed during excavation of the knob of rock and 177 c.y. were removed during excavation for the drainpipe. Thus, only 178 c.y. was noncontract work for which BOR paid plaintiff additional compensation at unit prices set forth in the contract. Removal of the remaining 177 c.y. was contract work covered by the contract price.

Plaintiff maintains that additional excavation took place beyond that required for the drainpipe and the unstable knob of rock and that this was the spillway impingement excavation for which it now seeks compensation. However, plaintiff presents no written directives relative to removal of excavation from this spillway impingement area. The oral directives which plaintiff contends were for spillway work, were clearly directives to remove the above-mentioned unstable knob of rock and were not directives to perform spillway impingement work as asserted by plaintiff. Moreover, of the four blasts plaintiff contends were for spillway impingement work, i.e., the blasts of August 24, 1974; September 18, 1974; September 24, 1974; and November 14, 1974, all were made to perform excavation for which plaintiff has already been compensated. The August 24th shot was for thrust block excavation; the September 18th shot was for removal of the unstable knob of rock adjacent to the drainpipe. The September 24th shot was for excavation of the notch for the drainpipe and the November 14th shot was for excavation of the left abutment.

Plaintiff’s claim for 2,620 c.y. of material removed from the spillway impingement area is most unpersuasive for several reasons. First, testimony by plaintiff has been inconsistent as to the amount of excavation this spillway impingement area involved. Initially, plaintiff claimed it excavated 1,500 c.y. of material. This figure later changed several times to 2,500 c.y., then 2,800 c.y. and now 2,620 c.y. BOR which surveyed and recorded excavated material removed from the project site has no record of removal of said material which is the subject of this claim. 14 Second, it is difficult for the court to accept the fact that plaintiff could have excavated from one area some 2,600 c.y. of material, excavation only slightly less than the total overexcavation on the left and right abutments combined, without realizing that it had done so until more than 6 years after the excavation had been performed, especially in light of the fact that on other occasions when BOR directed noncontract excavation, plaintiff promptly asserted claims therefor. These facts make one skeptical about the bona fides of the claim. Finally, while BOR had survey records relative to excavation in the thrust block arch dam and the knob and drainpipe areas, it had no survey records at all of any such excavation as plaintiff now claims. This fact casts serious doubts as to the validity of this claim.

Given the above considerations, the court finds that plaintiff excavated only 178 c.y. of noncontract material in the area it labeled the spillway impingement area. Any other noncontract excavation in the spill *688 way impingement area, if in fact there was any, was not done at the direction of BOR, and thus defendant is not responsible for any such overexcavation under paragraph 4.1.2 of the contract.

Discussion

Plaintiff’s spillway impingement claim requires little discussion. This claim is clearly barred by the release. 15 See Part II A, supra. Even if the release were deemed to be inoperative, the court is not persuaded that plaintiff excavated 2,620 c.y. of noncontract material from the area it designated as the spillway impingement area. Any such excavation, if done, was clearly not done at the directive, oral or written, of the BOR. If any such excavation was done, it was performed by plaintiff for its convenience or for some other purpose or reason and as provided by paragraph 4.1.2 of the contract such excavation * * * shall be at the expense of the contractor. * * * See Woodcraft Corp. v. United States, supra, 146 Ct.Cl. at 103 , 173 F.Supp. at 614 .

Mention should be made of plaintiff’s damage computations for this claim. They present the same problems dealt with under claim 1, i.e., ambiguity, confusion and lack of logical relationship between itemized damages claimed and the nature of the claim to which they were allocated. For example, at oral argument, plaintiff’s counsel advised the claim 1.1 was “primarily a delay claim.” However, examination of the damage items sought under claim 1.1 show that over 70 percent of the amount claimed is for concrete costs incurred by plaintiff. This is so even though no concrete was involved in the spillway impingement area and the claim itself was strictly an excavation claim. Only some $342,760 of the $1,420,596 claimed is for delay damages. The only explanation perceived for inclusion of concrete costs in this purely excavátion claim is the use by plaintiff of the total cost approach to damages and the subsequent allocation of various costs to some of the individual claims. To add to the confusion, many of plaintiff’s Requested Findings of Fact under claim 1.1 relate to primary excavation activities on the right abutment. These facts are more properly germane to claim 1 and not claim 1.1. It may well be, although the court is unsure of this, that there is duplication in the claims for excavation and removal under claim 1 and claim 1.1 in this regard. In either event, there is no basis on this record to allow plaintiff any recovery for excavation of 2,620 c.y. of material.

Plaintiff is not entitled to any recovery on claim 1.1.

C. Claim 2 — Fillet Design Changes

Under claim 2, plaintiff seeks to recover $1,055,946. In the release that plaintiff executed, it excepted this claim from said release in the amount of $553,-601. As a result, plaintiff, in any event, cannot recover more than $553,601 on this claim. See Part A, supra. The bulk of plaintiff’s claim emanates from a design change in the arch dam fillet work. Smaller elements of the claim (removal of clay seam and removal of rock on right abutment) relative to BOR directives involving work that took place during the fillet placement period were also deemed part of this claim. Defendant concedes liability for these claims. However, the parties dispute the quantum due plaintiff relative to these claims. Defendant maintains that damages in this regard should not exceed $262,834 for the fillet design change claim and the other claims.

Facts

Plaintiff made its first concrete pour in the arch dam area on January 23, 1975. This first pour was made directly onto the *689 rock foundation at the bottom of the gorge. During the early stages of its concrete pouring operation, plaintiff realized that a problem existed with the design of the concrete fillets as staked out for the fillet forms by BOR personnel. While an oversimplification, a fillet was described by G.M. Shupe as a “fill in piece of concrete between the dam structure and the foundation.” As originally designed, the concrete fillets were to be poured onto the excavated portions of the arch dam abutments. The excavated portion of the abutments was called a keyway. The tops of the concrete fillets were planned to be 4 feet higher than the excavation line on the abutments. Under the original design, the tops of the fillets were not to extend beyond the sides of the right abutment keyways. Consequently, the tops of the fillets were planned to intersect the keyway sides at a 90-degree angle. However, as a result of the overexcavation in the right abutment, especially on the keyway sides, the tops of the fillets, if built with their tops 4 feet from the original design grade, would have stuck out beyond the keyway sides. As a result, the fillets could not intersect the keyway sides at a 90-degree angle as planned.

On September 10, 1974, long before plaintiff began work on the fillets, plaintiff received drawings which revised the design of the fillets originally set forth in the contract. These drawings did not constitute a major change in fillet design. These drawings did, however, contain a note which addressed potential problems in fillet height due to overexcavation. Specifically, these September 10, 1974, drawings contained a note stating: “Final excavation may differ from lines shown and may result in revision of the fillets as determined by the ‘Contracting Officer’.” In addition, the Denver office of BOR had a document entitled: “Design Considerations for Construction of Nambe Falls Dam, April, 1974.” In the section pertaining to fillets, this document specifically stated: “In general, the fillets were designed for a height of 4.0 feet, plus or minus, normal to the excavation * * Some adjustments to these elevations may be required because of modifications to the foundation excavation. Clearly, BOR intended the fillets to be adjusted for any overexcavation.

BOR personnel at the construction site, however, failed to make any adjustment in the fillet design to account for the overexcavation which took place on the right abutment. BOR personnel at the project site had the responsibility for setting the stake lines for the fillet forms. These stake lines set the shape, size, and height of the concrete fillets and plaintiff set its forms to these stake lines. BOR personnel set these stake lines, so that the height of the fillets was the same as it was in the September 10, 1974, contract drawings, that is BOR personnel set fillet height at 4 feet from the original line of excavation.

In fact, as defendant concedes, BOR personnel erred in setting the height of the fillets 4 feet from the contract excavation line. As mentioned above, the overexcavation which took place on the right abutment meant that when the fillet tops were set at their original height, the tops extended beyond the sides of the right keyway. This extension beyond the right keyway meant that the tops could not intersect the key-way sides at the 90-degree angle originally planned. The error of BOR personnel came in failing to adjust the height of the fillets so that the tops were 4 feet from the actual line of excavation, rather than 4 feet from the contract excavation line. Defendant concedes that BOR personnel should have made this adjustment to the actual line of excavation if they had correctly followed the fillet design plans.

After BOR staked the first fillet to be poured, plaintiff discussed the design problem with BOR. Subsequent to these discussions, BOR directed a change in the design of the fillets. Although the problem with the fillet height arose in the context of overexcavation on the right abutment, the record indicates that this BOR directed change was for fillets on both the left and right abutment. The fillet change directed by BOR involved a change of the angle at which the fillets intersected with *690 the arch dam abutments. Basically, BOR did not change the actual height of the fillets, but instead had the fillets intersect the abutments at a 45-degree angle instead of the 90-degree angle called for by the September 10, 1974, plans. This particular solution to the problem seems to have been prompted by the fact that the September 10, 1974, plans showed fillet tops protruding from the keyway. In the drawing of this protruding section, the top of the fillet intersected the abutment at a 45-degree angle. This drawing of the protruding fillet in the September 10, 1974, plans appears to have been the basis for BOR’s design change for all the fillets in the arch dam area.

This fillet design change to a 45-degree angle of intersection with the arch dam abutments resulted in both increased cleanup excavation and increased concrete form-work. The increased cleanup excavation was caused by the fact that the higher fillet with a 45-degree angle of intersection created a much larger area of rock foundation to have concrete poured on it. As discussed in claim 1, excavation proceeded in two phases: primary and cleanup. Cleanup excavation took place just prior to the placement of an off-rock concrete lift. During the cleanup phase, BOR personnel inspected the rock foundation area and instructed plaintiff to remove any loose or incompetent material from the foundation area. The record clearly supports the conclusion that during this fillet cleanup excavation phase in the arch dam area, plaintiff performed cleanup excavation in excess of that required by the contract because of the larger foundation area created by the fillet design change.

Defendant concedes that the fillet design change resulted in a greater foundation area for cleanup work and, therefore, required more cleanup excavation. It should be emphasized that the fillet design change did not entail additional primary excavation. It only involved additional cleanup excavation. There is no dispute about this fact as plaintiffs claim herein is only for additional cleanup foundation work. It should be noted here that plaintiff has included foundation preparation cleanup excavation both in this claim and in claim 1. As indicated in the discussion of claim 1, the court has concluded that all cleanup excavation in the arch dam area properly belongs in this claim both in order to avoid duplication of damages and because of the causative relationship which existed between the fillet design changes and the increased foundation cleanup work.

A subsidiary factor causing the extra cleanup excavation was the fractured and joined nature of the foundation rock. In certain spots on the right abutment, the condition of the rock was such that plaintiff had to remove larger quantities of loose or shattered rock than was anticipated. Although it is difficult on this record to determine the exact quantity of material removed from the right abutment during cleanup excavation, defendant submitted a model exhibit which visually depicted the amount of excavation removed both during cleanup and primary excavation. This model was based on BOR survey data and records. Plaintiff contends that this exhibit only partially shows the amount of overexcavation produced by cleanup excavation work. Plaintiff, however, did not present the court with any specific data demonstrating greater amounts of excavation during this cleanup phase. 16 In fact, plaintiff seems to rely on defendant’s model exhibit in support of one of its Request *691 ed Findings of Fact in part at least. The court finds that defendant’s model exhibit presents an acceptable and reasonable approximation by way of a visual depiction of the cleanup excavation which took place on the right abutment during the fillet period of construction. The model indicates that cleanup work was much, much less than espoused by plaintiff and supports defendant’s contentions and conclusions relative thereto.

One of plaintiff’s main contentions on overexcavation is that BOR directed plaintiff to excavate large quantities of material during the cleanup phase of excavation. The record, however, fails to support plaintiff’s contention. Although plaintiff had to excavate increased quantities of material from the right abutment, the court is not persuaded that this quantity was of the magnitude asserted by plaintiff. Plaintiff also stresses that the jointed and fractured nature of the rock was the primary cause of the overexcavation during the cleanup phase. The record discloses that the jointed and fractured condition of the foundation rock was known by plaintiff prior to bid and during foundation work preceding the cleanup work. The increased area to be cleaned up, rather than the condition of the rock, was the main reason for the extra work during the cleanup phase of the fillet phase of the construction work.

The change in the fillet design also caused plaintiff to perform additional work while constructing the fillet forms for pouring concrete. As a result of the change in design, the size of the fillets greatly increased. In addition, the design change required plaintiff to use a hanging form which was built-in place. A hanging built-in-place form needed to be anchored to the rock by rods, and a hanging form also required a great amount of tailoring to shape the form to the rock foundation. The original design for the fillets would have allowed use of a flat panel which would not have required all the additional form work mentioned.

In addition to excess cleanup excavation and additional form work, plaintiff also had to perform other noncontract cleanup work in the arch dam foundation area during its fillet concrete placement operation. On March 5 and 6, 1975, BOR verbally advised plaintiff that certain loose material in the area of Blocks 1 and 2 on the right abutment would have to be removed. As directed, plaintiff removed this material. On March 12,1975, plaintiff, by letter, requested BOR to issue a written change order so that it could receive an equitable adjustment for this work. On March 18, 1975, BOR denied plaintiff’s request for an equitable adjustment for this work.

On March 7, 1975, BOR discovered a clay seam in the right abutment and BOR directed plaintiff to excavate the seam. Plaintiff removed the clay seam and filled the resulting cavity with concrete during the period March 8 to March 10, 1975. To accomplish this work, plaintiff worked two shifts on March 8 and three shifts on March 9, 1975. At the end of the second (or swing) shift on March 10,1975, plaintiff had completed the work and poured the concrete lift which had been scheduled for March 7, 1975. On March 8, 1975, one day after receiving BOR’s directive, plaintiff sent BOR a letter requesting a written change order and an equitable adjustment for the clay seam work.

By a letter dated April 2, 1975, plaintiff again informed BOR of its claims stemming from BOR directives of December 21, 1974 (see claim 1 discussion); March 6, 1975; and March 7, 1975. Plaintiff also alleged in this letter that BOR was directing cleanup excavation work in excess of that required by the contract.

On April 8 and 9, 1975, BOR verbally directed plaintiff to remove loose rock on the downstream side of the right abutment and to install rock bolts to secure the remaining rocks in this area. The excavation and rock bolting was completed in 5 calendar days, April 9 to April 13, 1975, and delayed the completion of that project for 5 calendar days. On April 11, 1975, plaintiff wrote a letter to BOR requesting a written change order and an equitable adjustment for this work of April 8 and 9, 1975.

*692 In the latter part of April 1975, BOR began to respond to plaintiff’s letters requesting equitable adjustments. By letter dated April 25, 1975, BOR addressed plaintiff’s March 8, 1975, letter and acknowledged that plaintiff was entitled to an equitable adjustment for work performed pursuant to the March 7, 1975, directives (clay seam work). Subsequent to this letter, the parties attempted to negotiate an equitable adjustment but were unable to reach agreement.

BOR also responded to plaintiff’s letters of April 2, 1975, and April 11, 1975. On April 29, 1975, BOR sent plaintiff a letter answering plaintiff’s April 2, 1975, letter. In this letter, BOR stated that the December 21, 1974, directive (removal of loose rock on the right abutment) and the March 6,1975, directive (removal of loose material in the area of Blocks 1 and 2) involved contract required excavation work. BOR, therefore, refused plaintiff an equitable adjustment for this work. However, BOR acknowledged again that the March 7, 1975, directive (clay seam work) entitled plaintiff to an equitable adjustment. BOR subsequently issued a unilateral change order for work performed pursuant to the March 7,1975, directive because the parties were unable to agree on an equitable adjustment. This change order (No. 5) awarded plaintiff $10,850 as an equitable adjustment for the clay seam removal work. This change order made no award for delay damages.

On June 26, 1975, BOR responded by letter to plaintiff’s claim that the work performed on April 8 and 9, 1975, pursuant to BOR directives (rock bolting, etc. on right abutment) entitled it to an equitable adjustment. This claim was covered by change order No. 5, and, since the parties could not agree on price, was issued unilaterally. This change order awarded plaintiff $13,000 for the rock bolting and related work. No award was made for delay damages relative to this rock bolting claim.

Plaintiff’s concrete pouring operation also encountered problems and delays in areas other than those involving cleanup excavation and offrock concrete placement. One such operation which was delayed was plaintiff’s construction of the diversion works, the system of culverts, pipes and conduits which diverted the flow of the Rio Nambe during construction of the arch dam. Plaintiff had planned a 7-day period between the pouring of the concrete lift (block 2, lift 3) containing the permanent diversion hold for the diversion pipe and the pouring of the concrete lift (block 3, lift 2) which had the temporary diversion pipe running through it. In fact, plaintiff poured the lift with the permanent diversion hold on February 11, 1975, and was not ready until March 7, 1975, to pour the lift which contained the temporary diversion pipe. This was a period of 24 calendar days, 17 days longer than planned for by plaintiff.

The court finds that a substantial portion of this 17-day delay was due to the construction of the diversion works itself, a contract mandated operation. Further during this 17-day period plaintiff poured a concrete lift which it had not originally planned to pour until after the completion of the diversion works. Plaintiff contends that this 17-day delay period was due to fillet extra cleanup excavation ordered by BOR. Plaintiff, however, has failed to present persuasive evidence that such extra cleanup excavation caused the 17-day delay. The record persuades that this 17-day period was consumed for the most part in performing the contract required diversion work.

Another delay encountered by plaintiff during the concrete placement operation took place during plaintiff’s construction of the outlet works, a small concrete structure housing pipes and valves which was located almost in the middle of the arch dam (block 2, lifts 9 and 10). Plaintiff had scheduled the forming and pouring of the outlet works to take 7 days. In fact, the work took 20 days. A total of 20 shifts were used to form the outlet works between March 31, 1975, and April 23, 1975. BOR was not responsible for the delay in the construction of the outlet works as *693 plaintiff was performing work required by the contract.

On June 13, 1975, during the concrete placement operation, plaintiff encountered another delay when the carpenters employed by plaintiff went on strike and walked off the job. The strike lasted until June 25, 1975, at which time the carpenters started work again. BOR was in no way responsible for this 11-day delay period.

Still another delay in the concrete placement period, during off-rock pour, occurred while construction of the cantilevered spillway, located in the top middle of the arch dam, was taking place. Plaintiff had planned to take 7 weeks to form and pour the concrete lifts which made up the cantilevered spillway. In fact, this forming and pouring work took 11 weeks. The record suggests that plaintiff suffered no extraordinary delays in this period. Rather, it appears that plaintiff simply underestimated the amount of work if would take to form the cantilevered structure. Since this work was not on the critical path, the delay in this work did not delay the eventual completion of the project. However, this work, the delays involved, and the reasons for those delays do indicate that plaintiff encountered delays on this project due to its own underestimation of the work involved, rather than because of noncontract work ordered by BOR.

Plaintiff completed concrete placement in the arch dam area on September 12, 1975. During this concrete placement operation, plaintiff made a total of 26 off-rock concrete pours. Thus, only 26 concrete pours involved foundation cleanup excavation pri- or to the placement of concrete. During the periods when plaintiff was performing the off-rock pours, it was generally on a 3-shift basis. These 3 shifts operated on a 6- and 7-day work week schedule during off-rock concrete placement work in the arch dam.

Plaintiff gave BOR timely notice of its fillet claim when it provided BOR written notification of this claim on April 2, 1975. This April 2nd letter also informed BOR that plaintiff believed that BOR was directing additional hand excavation and cleanup work beyond that required by the contract. On November 7, 1975, plaintiff transmitted its written cost proposal for increased costs in the fillet area of $553,601 and a time extension of 49 calendar days.

The contracting officer authorized BOR personnel to negotiate an equitable adjustment with plaintiff in an internal memorandum dated July 22, 1975. This memo stated, in pertinent part: “Since this is a change we directed primarily to improve the fillet design, we should give consideration to the Contractor’s request for an equitable adjustment.” BOR, however, rejected plaintiff’s claim on May 7, 1976.

As mentioned earlier, the court has found that the fillet design change caused plaintiff added expense and delay both in its foundation cleanup excavation and in its construction of the fillet forms. Defendant concedes liability for these two items. However, the parties disagree on the amount of damages which plaintiff is entitled to recover.

Plaintiff seeks a total amount of $1,055,-946 as damages on claim 2. Of this amount, plaintiff seeks $7,464 (before addons) for foundation preparation outside of the design prism, $34,484 (before add-ons) for foundation cleanup costs; and $220,569 (before add-ons) for extra fillet form costs. Plaintiff also seeks delay damages for 63 calendar days (55.5 work days) or $500,610. These claim costs (before add-ons) total $763,127. Add-ons include job overhead (8 percent), home office overhead (8.5 percent), profit (10 percent), tax (4 percent), and bond (0.5 percent). Add-ons total approximately $292,819. Plaintiff included as a cost item in claim 2 the cost of certain earth dam embankment work of $99,744, plus add-ons of $22,442. 17 This claim is *694 ostensibly based on a total cost approach, i.e., it represents part of the excess costs over the bid costs plaintiff incurred on the earth dam embankment work. It is merely a line item in plaintiff’s damage schedule for claim 2. There is little explanation of this claim item in the record and the court concludes, as a result, that said claim lacks merit in any event.

Defendant, on the other hand, maintains that plaintiff is only entitled to an equitable adjustment of $262,834 on claim 2. This amount includes $3,732 (before add-ons) for foundation preparation, $4,812 (before addons) for foundation cleanup, and $142,352 (before add-ons) for increased costs of fillet forms. These cost figures total $150,896. Add-ons total approximately $65,106. Defendant did not allow for any delay damages on the fillet changes claim. Defendant does allow 8 calendar days (6 work days) of delay for excavation work on the clay seam, and removal of loose rock and installation of rock bolts in the right abutment. Defendant allows $40,902 (before add-ons) for the 6 work days of delay; add-ons total approximately $5,930. Plaintiff was paid for the costs it incurred in performing this extra work, but has not been paid for any delay damage.

In computing both its direct costs and its delay costs for the fillet design change, it appears that plaintiff did not make use of actual time and labor work records for the project. Instead, plaintiff extrapolates an additional work time figure from its estimate of the increased surface area which the fillet change caused. This estimate was derived, it would appear, from the model which plaintiff constructed of the project. In other words, plaintiff uses its estimate of the percentage increase in work surface area to derive the increased labor time it spent on a particular phase of fillet construction work. Plaintiff did not use actual labor time data recorded in contract documents. For example, plaintiff estimates an increased fillet form area of 220.1 percent (4,814 square feet (s.f.)) as built versus 1,504 s.f. as bid). By applying this 220.1 percentage figure to the average labor time for formwork on each fillet (24 hours), plaintiff arrives at an estimate of 53 hours as the increase in labor time for each fillet caused by the design change. Thus by multiplying this average increase figure of 53 hours by the number of off-rock concrete pours (26), plaintiff derives an estimate of 1,378 hours as the added labor time spent by the fillet forming crew as a result of the fillet design change and claims $220,569 as a result thereof.

Defendant, on the other hand, relies on the actual work records for its computation of the fillet form costs plaintiff should receive. Based upon the information contained in the daily reports of BOR inspectors for the dam project, defendant determined that plaintiff spent 175 additional shifts on form work. Based upon this information and resultant computation, defendant argues the plaintiff is entitled to recover $142,352 because of additional formwork caused by the fillet design changes. This $142,352 amount includes the cost of labor, construction equipment, 18 and form hardware.

For the additional cleanup excavation costs, defendant relies on an exhibit prepared by one of its expert witnesses which was based on contract work records. This exhibit charts the construction progress of the project. The exhibit shows, inter alia, only 8 additional work shifts for cleanup excavation work in the arch dam foundation area. On the basis of this analysis, defendant argues that plaintiff is entitled to only $4,812 (before add-ons) for these 8 extra work shifts for cleanup work. Plaintiff seeks $34,484. In addition, defendant also awards plaintiff $3,732 for foundation preparation outside of design prism whereas plaintiff claims $7,464. With respect to the latter claim item, defendant has merely reduced by one-half the amount sought by *695 plaintiff for this item without explaining the basis of the cost, i.e., what it entailed. 19

In order to come to a conclusion on the damage issue on claim 2, the court has found it necessary to consider each of the three damage items separately: fillet form costs, cleanup excavation costs (which includes what has been denoted as foundation preparation costs), and delay costs.

As to fillet form cost, the court finds that defendant’s presentation on damages is more persuasive than plaintiff’s. Plaintiff based its figures on the increase in the size of the fillet form area. Plaintiff did not persuasively demonstrate that there existed a direct relationship between increase in fillet form size area and the number of manhours needed to construct the fillets. Thus, plaintiff failed to convince the court that its method of calculating fillet form costs truly reflected the additional costs incurred by plaintiff for this work.

Defendant’s damage calculations, on the other hand, bore a closer relationship to direct cost incurred by plaintiff because of its additional fillet form construction work. The use of actual work records showing time spent by plaintiff forming the oversized fillets allowed defendant to calculate with a reasonable degree of accuracy the cost of the additional work in fillet form construction. Therefore, the court accepts defendant’s figure of $142,352 as the amount to which plaintiff is entitled because of additional fillet form construction work.

The calculation of damages for additional cleanup excavation resulting from the fillet design change is more difficult than calculation of fillet form costs. Plaintiff has included this item in both claim 1 and claim 2 and thus made it difficult to assess precisely how much plaintiff seeks for this item. Defendant’s calculations are not as persuasive as its fillet form calculations were since it is unclear precisely how defendant reaches the amount it set forth for this claim item. Defendant’s calculations, in part at least, are based upon the actual work records of the project. Thus, although less than ideal, the court determines that defendant’s damage calculations are more persuasive than plaintiff’s on this claim item. The court, therefore, accepts defendant’s figure of $4,812 for cleanup cost.

The court, however, does not accept defendant’s figure of $3,732 for foundation preparation costs. Defendant simply accepted plaintiff’s figure of $7,464 and reduced it by one-half because of defendant’s contention that plaintiff agreed to and benefited from the fillet design change. The court does not accept defendant’s argument that plaintiff must share the costs resulting from the fillet design change. The court finds that defendant was responsible for the fillet design change and, accordingly, should bear appropriate costs associated with that change. Since defendant does not oppose award of these costs on substantive grounds, it is reasonable that defendant should bear the full cost of $7,464, not 50 percent of said cost.

In summary, plaintiff is entitled to recover $142,352 for extra form work, $4,812 for extra cleanup work and $7,464 for foundation preparation work, a total of $154,628 representing direct costs of fillet design change and related extra concrete work. Appropriate add-ons to this figure total $66,570. Thus, plaintiff’s total direct cost recovery is $221,198.

In addition to its claim for direct costs, plaintiff also seeks a total of $567,-986 (including add-ons) for “delay” costs *696 resulting from the fillet design change. While the parties are wont to refer to this aspect of the claim as “delay damages,” the claim is really one for compensation for extended performance due to a change issued under the Changes clause of the contract. For the sake of convenience, and because the parties use the phrase, the court will utilize the phrase “delay damages” as shorthand for “compensation for extended performance due to a change under the changes clause of the contract.” See Merritt-Chapman & Scott Corp. v. United States, 192 Ct.Cl. 848, 851-853, 873-874 , 429 F.2d 431, 432, 444, 445 (1970); Paul Hardeman, Inc. v. United States, 186 Ct.Cl. 743, 749-752 , 406 F.2d 1357, 1361-1363 (1969). Basically, plaintiff contends that the fillet design change delayed completion of the project by 55.5 work days (63 calendar days). 20 Defendant concedes liability for $47,026 which is the amount of delay damages (including add-ons) for 6 work days (8 calendar days). The 8 calendar days of delay conceded by defendant occurred as a result of the removal of the clay seam (3 calendar days) and rock bolting and related work on the right abutment (5 calendar days). Defendant makes no award for delay damages as a result of the fillet design change. Defendant does not assert that legal reasons preclude plaintiff from being awarded delay damages for the fillet design change. Instead, its position presumably is that plaintiff should not get delay damages for fillet design changes because said work was not on that critical path and/or that there were concurrent delays which preclude the award of said damages under the circumstances of this case. These are factual assertions. However, defendant does address the issue of delay damages in case the court finds, as it does, that plaintiff is entitled to delay damages for the fillet design change.

The primary difference between the parties regarding the proper number of delay days to be accorded plaintiff turns on which party’s critical path analysis is accepted by the court. See note 5, supra. For plaintiff, the concrete placement operation in the arch dam was on the critical path from January 23, 1975, to September 12, 1975. Defendant, on the other hand, contends that the arch dam concrete placement operation was on the critical path from January 23, 1975, to June 24, 1975. Thus, for defendant all work occurring in the arch dam on or after June 24,1975, had no impact on the completion of the project, and, according to defendant, plaintiff is entitled to no delay damages for work in the arch dam area which occurred after June 24, 1975.

The court adopts defendant’s interpretation of the critical path for the reasons discussed in section IV, infra, of the opinion. This determination, however, does not fully resolve the delay damage differences between the two parties. An examination of both the additional fillet form work and the additional cleanup excavation work in the arch dam area reveals that some of this work took place while the arch dam concrete placement operation was on the critical path. Of the 125 additional shifts which defendant concedes plaintiff spent on fillet form work, 74 involved work on lifts which were poured prior to June 24, 1975. Thus, the work of these 74 additional shifts took place while the arch dam concrete placement operation was on the critical path. It is reasonable on this record to conclude that this extra form work delayed the eventual completion of the project. Given the fact that this fillet form work was an integral part of the arch dam concrete placement operation and the fact that the concrete placement operation itself was on the critical path until June 24, 1975, it is certainly reasonable to conclude *697 that this extra work delayed the completion of the project.

Defendant fails to explain how it can award plaintiff direct costs for this fillet form work without also awarding delay costs for some of the fillet work which occurred before June 24, 1975, and is conceded to be work on the critical path. Defendant’s failure to allow any delay costs for this work is inconsistent with its contention regarding critical path work and its acceptance of liability for the direct cost of fillet form work. In the court’s view, defendant also has some liability for delay costs as a result of the fillet design change.

The principal difficulty for the court lies in determining how many of the 125 additional shifts spent on concrete fillet form work and how many the additional shifts spent on cleanup excavation actually caused a compensable delay in the completion of the project. As mentioned above, defendant has not directly addressed the issue of delay damages for this additional fillet form work and additional cleanup excavation work. Plaintiff also has provided little help since it chose not to respond to defendant’s damage calculations in its objections to defendant’s Requested Findings of Fact. Instead of responding to defendant’s damage calculations, plaintiff chose to rely on its damage presentation in its Requested Findings of Facts. The court does determine that plaintiff’s method of calculating delay damages for the fillet design change was unpersuasive and improperly attributed a great deal more delay to BOR and this particular claim than was warranted by the evidence in the record. Indeed, plaintiff seeks 63 calendar days delay for fillet design change when the plaintiff itself attributes only 56 calendar days of delay to the period of construction involving the concrete fillets. Plaintiff, inexplicably, includes 15 calendar days of delay in its fillet work delay consideration which occurred during the primary phase of excavation on the arch dam, i.e., before January 9, 1975.

As a result of the complexity of the record and the parties’ failure to address precisely how much delay is attributable to the additional fillet form work and cleanup excavation work, the court was forced to calculate, as best it could, the delay caused by the additional fillet form work and additional cleanup excavation work. Based on its review of the record, the court determines that the 125 additional shifts spent on form work and the 8 additional shifts spent on cleanup excavation resulted in a total delay to the project of 15 days.

In order to translate the above-discussed additional shifts into days of delay, the court deemed it necessary to determine, first, how many shifts involved the period when arch dam work was on the defendant’s critical path, and second how many shifts involved a time period when other concurrent work delayed the project. The record shows that 74 forming shifts and 4 excavation cleanup shifts took place while the arch dam work was on the critical path, for a total of 78 shifts involving work on the critical path. Of these 78 shifts, the record indicates 29 shifts were concurrent with the construction of the diversion works on the excavation of the clay seam which work was also on the critical path. One shift involved cleanup excavation during the placement of the crack detection tape. Although it is difficult on this record to determine the precise number of shifts involved, the record appears that 4 shifts were concurrent with the delay in the outlet works, the construction of which took place while the arch dam concrete operation was on the critical path. Accordingly, removing concurrent delay shifts (33 shifts) from the 78 shifts on the critical path leaves 45 shifts as a basis for delay damage consideration.

The court concludes that a total of 45 extra shifts were involved in the additional fillet form work and cleanup excavation caused by the fillet design change. Since plaintiff was working 3 shifts a day during this period, the 45 extra shifts involved a total of 15 work days of additional work (45 divided by 3). Since these 15 days of work took place while the fillet design change work was on the critical path, the *698 court concludes that plaintiff is entitled to delay damages for these 15 work days. The court concedes that it is possible that this determination is less than precise or exact. Because of the complexity of the record and the failure of the parties to adequately address the delay implications of the additional shifts for arch dam cleanup and fillet form work, the court had a difficult time arriving at a precise number to reflect the delay days caused by the fillet design change. The court believes that, under the circumstances of this case, 15 delay days is a fair and reasonable figure for the additional work caused by the fillet design change. It certainly fits within the mold of an “equitable adjustment.”

Plaintiffs compensable delay period is determined to be 21 workdays; this includes the 15 workdays attributable to additional form work and cleanup excavation as well as the 6 workdays conceded by defendant for clay seam and rock bolting work. This determination produces a delay damage figure of $143,157 (21 X $6,817), plus an additional $21,433 in add-ons for profit, taxes, and bonding expenses, for a total delay damage figure of $164,590.

Discussion

The Nambe Falls Dam contract contained the standard “Changes” provision (Oct. 1969 Edition) often included in government contracts. This provision provided, in pertinent part:

CHANGES

(a) The Contracting Officer may, at any time, without notice to the sureties, by written order designated or indicated to be change order, make any change in the work within the general scope of the contract, including but not limited to changes:

(i) In the specifications (including drawings and designs);

(ii) In the method or manner of performance of the work;

# * # * * *

(d) If any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment shall be made and the contract modified in writing accordingly. * * *

The contract also contained a “Suspension of Work” clause.

Although plaintiff in its presentation of claim 2 does not seem to rely on the Changes provision, it is clear that it is this provision which provides the basis for its claim. Defendant has conceded liability for the fillet design change, a concession which is clearly warranted by the facts and circumstances of this case. BOR personnel had the responsibility under the September 10, 1974, design drawings, of adjusting the height of the fillets to compensate for any overexcavation. When plaintiff, for reasons discussed in claim 1, excavated beyond the contract design line, BOR personnel at the construction site failed to adjust the height of the fillets. It was this failure by BOR to adequately follow the fillet design instructions that created the necessity of a change in the fillet design. Consequently, the fillet design change was accomplished within the scope of the contract Changes provision, and plaintiff is entitled to an equitable adjustment under said provision for an increase in the cost of the performance of the work due to said change, whether or not changed by the change order itself.

The statement of facts, supra, for claim 2 provided the court’s factual conclusions and related reasoning on the damage issue. There is no reason to repeat those determinations again. However, several matters require further discussion relative to claim 2.

For reasons discussed earlier, plaintiff’s claim for cleanup excavation in the arch dam has been included in claim 2. Plaintiff contends that cleanup excavation, in fact, involved extensive resloping and redimensioning work beyond the scope of the contract required cleanup excavation work. Paragraph 4.1.3 of the contract required plaintiff to perform “a final cleanup of the *699 rock surface * * * by barring, wedging, picking, or other approved methods.” The record show that the vast majority of the cleanup excavation in the arch dam was contract work required under paragraph 4.1.3 of the contract. To the extent that BOR required cleanup excavation beyond the scope of contract required work, such work is either included in the 8 shifts for which plaintiff receives compensation under this opinion as part of the 15 workdays of delay computed above, or such work was within the scope of the rock bolting work and clay seam work for which plaintiff received a written change order and compensation.

Plaintiffs claim for delay damages for fillet design work also deserves additional comment. Plaintiff did not use the project’s work records to determine when and how much additional time it spent on cleanup excavation and fillet form work as a result of the BOR’s fillet design change. Instead, plaintiff determined the additional time required for cleanup excavation in the arch dam by reference to plaintiff’s own estimate of the percentage increase in rock foundation surface area. Similarly, for fillet form work, plaintiff derives its work time figures from the percentage increase in the fillet form area sizes.

After using the time figures for cleanup excavation in the arch dam and fillet form work arrived at by the method just described, plaintiff compares the total time it calculated for fillet form work and arch dam cleanup excavation with the amount of time it originally bid. The resulting percentage increase as determined by plaintiff (86.3 percent) is then used by plaintiff to calculate how much of the 56 calendar day (c.d.) delay in arch dam construction is attributable to fillet form work and extra cleanup as a result of the fillet design change. Plaintiff arrives at a figure of 49 c.d. (44 work days (w.d.)) to which it then inexplicably adds 15 c.d. (11.5 w.d.) delay which occurred during primary excavation in the arch dam.

As mentioned earlier, the court found plaintiff’s method of calculating delay damages both unreliable and unreasonable. Its method disproportionately inflates the amount of delay time attributable to the fillet design change. Plaintiff’s method also fails to account adequately for the fact that the arch dam concrete placement operation incurred delays which were not the result of additional BOR ordered work.

Defendant’s calculation of the additional work by reference to the time and labor records from the project is more accurate than plaintiff’s method of calculation, since it reflects work actually performed, not hypothetical labor time projections. Damage estimates based upon actual cost are preferred over estimates based hypothetical costs. Lilley-Ames Co. v. United States, 154 Ct.Cl. 544, 549, 550 , 293 F.2d 630 (1961). Similarly, work time estimates based upon actual work records are preferred over estimates based upon hypotheticals. Thus, the court accepts defendant’s estimate of the amount of additional work which the fillet design change required. However, since defendant failed to calculate the delay caused by this additional work, it was necessary for the court to make such delay calculations based upon the evidence of record.

Plaintiff is entitled to recover delay damages for the delay caused by the additional work described above which resulted from the fillet design changes. As mentioned previously, the basis for plaintiff’s claim must be the Changes clause in the contract. Under the Changes clause, plaintiff can recover delay damages as compensation for extended performance due to the change. Pathman Constr. Co. v. United States, 227 Ct.Cl. 670, 673 (1981); Merritt-Chapman & Scott Corp. v. United States, supra, 192 Ct.Cl. at 851 , 429 F.2d at 432 ; Paul Hardeman, Inc. v. United States, supra, 186 Ct.Cl. at 749-752, 406 F.2d at 1361-1363 . Defendant implicitly acknowledged this legal principle when it conceded delay damages for the clay seam work and the rock bolting work, which occurred during the arch dam concrete placement operation. Defendant, as indicated earlier, failed to allow delay damages for the additional *700 fillet form work and the additional arch dam cleanup excavation work. The court now allows plaintiff to recover such damages as part of an equitable adjustment award.

The court has determined that plaintiff is entitled to 15 w.d. of delay for the additional fillet form work and cleanup excavation work, all of which plaintiff performed during the arch dam concrete placement operation. It is clear that plaintiff cannot recover for all the additional fillet form work and arch dam cleanup excavation work it performed. Some of this work occurred after June 24, 1975, the date the arch dam concrete placement operation left the critical path. However, as to the additional work which took place while the arch dam concrete placement operation was on the critical path, not all such work delayed the eventual completion of the project. Some of this additional work occurred during plaintiffs construction of the diversion work and still other of the above-mentioned additional work took place during the construction of the outlet works.

Both the construction of the outlet works and the diversion works, which were work items involved in the concrete placement operation while the concrete placement operation was on the critical path, created project delays which were attributable to plaintiff, not BOR. It is well established the plaintiff cannot recover for delay caused by the government when that delay is concurrent with other delay not caused by the government. Broome v. United States, 203 Ct.Cl. 521, 528 , 492 F.2d 829, 833 (1974); Commerce Int’l Co. v. United States, 167 Ct.Cl. 529 , 543, 338 F.2d 81, 90 (1964) and cases cited therein. From the court’s review of the record, it is evident that some of the extra arch dam cleanup excavation work and fillet form work was concurrent with work on the diversion works and the outlet works. Therefore, defendant is not liable for any of this concurrent delay. Other above-mentioned additional work took place while plaintiff performed the clay seam work and rock bolting work for which plaintiff has been separately awarded delay damages. Based upon the court’s review of a difficult and complex record, defendant is responsible for 15 w.d. of delay for additional arch dam cleanup excavation and additional fillet form work. When combined with the 6 w.d. conceded by defendant for clay seam and rock bolting work, plaintiff is entitled to recover delay damages for a total of 21 w.d. Defendant’s per day delay figure of $6,817, which the court accepts, for 21 days, plus add-ons, produces an award for delay damage to plaintiff of $164,590.

Plaintiff, therefore, is entitled to recover $221,198 as direct costs incurred as a result of the fillet design change and related concrete placement work and $164,590 for 21 days of delay which also resulted from said fillet design change and related concrete placement work, for a total recovery of $385,788.

Based on the above discussion, the court concludes that plaintiff is entitled to recover $441,687 under claim 2. In reaching the conclusion, the court observes that it did so recognizing that the complexity of the issues, the somewhat unclear presentations of the parties, and the sheer volume of the record might well have produced a difference result to another trier of fact.

D. Claim 3 — Core Trench Changes

Plaintiff seeks to recover $15,318 for two work items in the core trench area of the earth dam. Plaintiff excepted three core trench work items from the July 7, 1976, release. In its post-trial submission, plaintiff withdrew one of these work items, dewatering of a spring, as a claim item in this case. Defendant admits in its submissions, that plaintiff is entitled to recover $54,057 on the remaining two work items. As is evident, defendant proposes an award greater than that sought by plaintiff. This fact is explained by the different critical path analyses of the parties which produce differing delay damage conclusions.

Facts

Claim 3 consists of two claim items. Under the first claim item plaintiff seeks increased costs resulting from removal of a *701 gravel lens (or seam) and resloping of the sides of the cutoff trench in the earth embankment area. Under the second claim item, plaintiff seeks increased costs for fill work (zone 1) in the earth embankment area and the increased cost of compacting this special fill.

a. Gravel lens claim

In September 1974, BOR observed an area of pervious gravel material in the cutoff trench. The cutoff trench was an excavated area beneath the earth dam, which was designed to be filled with impervious material to prevent water seepage. Therefore, it was necessary to remove this previous gravel area to ensure against water seepage.

In September 1974, BOR directed plaintiff to remove the gravel lens. Plaintiff requested that it be allowed to postpone the removal of the gravel lens until a later time because it was using the core trench area as an access road. BOR agreed to plaintiffs request.

In July 1975, plaintiff removed the gravel lens. The removal of this material required plaintiff to reslope the sides of the cutoff trench. BOR paid plaintiff at the unit price for this work but allowed no delay damages. In fact, as defendant concedes, the gravel lens and resloping work delayed the project for 6 work days (w.d.) or 8 calendar days (c.d.)

Defendant claims plaintiff is entitled to recover direct costs of $2,140, which includes add-ons for home office overhead, job overhead, profit, taxes, and bonding expenses, as compensation for the removal of the gravel lens and resloping the side slopes of the core trench. In addition, defendant also states that plaintiff is entitled to recover $47,026 as compensation for the 6 w.d. of delay caused by the gravel lens and resloping work. This amount of $47,-076 also includes add-ons for profit, taxes, and bonding expenses. Thus, defendant finds plaintiff entitled to recover a total of $49,166 for the gravel lens and resloping work due to a valid change order.

After a review of the record, the court concludes that defendant’s quantum determinations provide fair and reasonable compensation for plaintiff’s removal of the gravel lens and the resloping of the core trench sides and are therefore adopted by the court herein.

b. Zone compaction

As mentioned above, the cutoff trench was designed to be filled with previous material. In order to assure proper compaction, the contract specified in certain areas that the zone 1 fill was to be put down in layers not exceeding 6 inches. Specifically, the contract provided that: “The material shall be placed in the earth fill in continuous, approximately horizontal layers not more than 6 inches in thickness after being compacted.” The contract also provided: “The contractor shall be permitted to construct separate portions of the embankment below original ground surface, subject to the approval of the contracting officer.”

Plaintiff contends that it sought permission from the contracting officer to construct certain zone 1 portions of the earth dam, which were below the ground surface and next to the thrust block, in separate lifts larger than those specified in the contract. Plaintiff further contends that the method of placing the zone 1 fill which it proposed to the contracting officer reflected general industry practice. Plaintiff maintains that it should have been allowed to construct the earth dam as it requested and that the contracting officer improperly refused its request to construct the portion of the earth dam next to the thrust block in separate large fill lifts. The contracting officer, in fact, allowed plaintiff some variation from the contract provision of 6-inch fill lifts. He allowed plaintiff to build this portion of the dam area in 3V2 foot lift differentials.

While the liability question is clouded on this claim, defendant’s concession that plaintiff is entitled to some recovery on this claim is treated as an admission of liability by defendant. Defendant calculates that plaintiff is entitled to recover $4,901 for *702 this claim item. Plaintiff originally sought $12,109 for this item. Plaintiff, however, does not take issue with defendant’s computation in its submissions or at oral argument. Upon review of the record and the contract documents, there is support for a liability determination against defendant on this issue. Further, based on its review of the record, the court determines that defendant’s cost figure of $4,901 is more persuasive than plaintiff’s cost figure relative to the additional work plaintiff performed on this work item, and is deemed, on this record, to be an appropriate equitable adjustment for this claim item. Plaintiff sought no delay damages for this claim item and defendant did not find plaintiff entitled to any delay damages on this claim item. The court, on its review of the record, concludes that plaintiff is not entitled to delay damages on this claim item.

Discussion

Defendant has consented to recovery on claim 3 in an amount which exceeds the amount plaintiff seeks. The reason for this consent by defendant is that defendant’s critical path of the project included the cutoff trench excavation and resloping work in the earth embankment area, while plaintiff’s did not. 21 Consequently, defendant includes delay damages for the 6 w.d. of delay caused by this work in its computations, while plaintiff seeks no delay damges for the gravel lens claim item. Since the court has accepted defendant’s critical path for the reasons discussed in the damages section of this opinion, section IV, defendant’s damage computation for the gravel lens is controlling here.

Accordingly, the court concludes that plaintiff is entitled to recover $54,057 under claim 3.

E. Claim 4 — Vertical Contraction Joint Treatment

Plaintiff seeks $38,880 for work involving sandblasting concrete curing compound from the contraction joints in the concrete dam. Plaintiff excepted this item from the release in the amount of $165,929. Plaintiff contends that this was extra work required by BOR, and thus it is entitled to an equitable adjustment for performing the same. Defendant contends that the sandblasting work was required by the contract, and therefore plaintiff is not entitled to additional compensation.

Facts

The concrete dam (consisting of both the arch dam and the thrust block) was composed of a series of vertical concrete section called blocks. The concrete dam contained a total of 9 such blocks. Between each block was a joint called a contraction joint. The contraction joints were made of concrete. Like all portions of the concrete dam, these contraction joints had to undergo a curing process. The purpose of the curing process was to prevent the freshly poured concrete from losing moisture rapidly through evaporation. Such rapid moisture evaporation could produce deficiencies in the concrete, such as cracking.

Paragraph 5.1.20, of the contract dealt with curing of the concrete in general. The description and specifications for the membrane curing method were contained in subparagraph 5.1.20(c) which stated: “Wax-base compound curing — Curing by this method shall be by application of a wax-base curing compound on concrete surfaces to form a water-retaining film on the surfaces.”

The contract provision dealing with the curing of contraction joints which were to be grouted gave the contractor the option of using either water curing or membrane *703 curing. This option for method of concrete curing existed only for contraction joints which were to be grouted; all other contraction joints had to be cured by the membrane curing method.

In the fall of 1974, when plaintiff began its concrete placement operation, it used a water method to cure the grouted concrete contraction joints. However in late fall 1974, the freezing temperatures made the water method difficult to use. Consequently, plaintiff switched to a membrane method of curing the contraction joints in November 1974. BOR personnel, then, directed plaintiff to remove the membrane compound by light sandblasting. This removal of the compound was necessary to ensure that the grout to be applied to these joints could establish a proper bond. The membrane compound hindered proper adherence of the grout to the concrete surface unless the membrane compound was removed by light sandblasting prior to application of the grout.

The contract contained a provision which specifically directed such sandblasting. Paragraph 5.3.4(b) stated, in pertinent part: “That where contraction joints to be grouted are coated with sealing compound at the option of the contractor, they shall be lightly sandblasted to effectively remove the curing compound * * *.”

An internal memorandum from plaintiffs vice-president, who was also project manager of the Nambe Falls dam project during all times relevant to this claim, to G.M. Shupe indicated plaintiff’s awareness of the need to sandblast the curing compound. On or about November 15, 1974, which was during the period when plaintiff switched from the water method of curing to the membrane method, the project manager wrote: “Since we have the curing compound on hand and don’t have the extra insulation, we are planning to use curing compound on the vertical surfaces until we encounter difficulty in the light blasting required.” This memorandum indicates rather clearly that plaintiff understood the pertinent contract provisions as requiring light sandblasting of contraction joints to which curing compound had been applied at the time it made a decision to switch to membrane curing.

When BOR directed the sandblasting, plaintiff protested that such work was outside the contract requirements. Specifically, plaintiff pointed to the fact that the contract used two terms, “curing compound” and “sealing compound,” to describe the membrane compound method of curing. Plaintiff asserted that the use of the two terms was ambiguous because a contractor could not discern whether the two terms referred to the same compound or to two different compounds. As a result, plaintiff contended that it was unclear which compound had to be sandblasted.

The contract provision (Par. 5.3.4(b)) involving the sandblasting requirement, does use the terms “sealing compound” and “curing compound” interchangeably. In pertinent part, this provision stated:

Except for contraction joints to be grouted, the surface of the concrete first placed at a contraction joint shall be coated with sealing compound before the concrete on the other side of the joint is placed. * * *

Contraction joints to be grouted do not require sealing compound. * * * Provided, That where contraction joints to be grouted are coated with sealing compound at the option of the contractor, they shall be lightly sandblasted to effectively remove the curing compound without exposing appreciable areas of aggregate before the placing of adjacent concrete.

In the spring of 1975, when freezing temperatures no longer hindered a water method of concrete curing, plaintiff did not switch back to the water method. Instead, plaintiff continued to use the membrane method of curing the concrete pouring operation. Moreover, despite plaintiff’s assertions to the contrary, plaintiff’s concrete pouring operation was not delayed into the winter methods as a result of additional excavation in the thrust block resulting from BOR directives. A review of the record discloses that plaintiff had sched *704 uled the vast majority of the concrete placement in the thrust block, where plaintiff’s concrete placement operation began, for the months of November 1974, December 1974, and January 1975. Furthermore, plaintiff’s batch plant which mixed the concrete for the project was not operating until late October 1974. Clearly then, it was plaintiff’s construction schedule and equipment batch plant problems which were responsible for the pouring of concrete in freezing temperatures and the resultant need to use membrane concrete curing.

Finally, it should be noted that although the contract referred to both “sealing compound” and “curing compound” in its provisions dealing with concrete curing, the specifications for both “sealing compound” and “curing compound” were precisely the same. The contract specifically stated in which publications the specifications for “curing compound” and “sealing compound” could be found. The record shows no attempt by plaintiff to determine whether “curing compound” was, in fact, a different membrane compound than “sealing compound.” In fact, the record shows that plaintiff did not even notify the contracting officer of the ambiguity it perceived before submitting its bid.

Discussion

Plaintiff’s basic argument is that the use of the two terms, “curing compound” and “sealing compound,” to describe the membrane method of curing created an ambiguity in regards to plaintiff’s sandblasting responsibilities under the contract. Specifically, plaintiff maintains that it interpreted the contract as requiring sandblasting of “sealing compound,” but not “curing compound.” Thus, plaintiff maintains that when it submitted its bid it intended to use “curing compound” as a membrane curing method and did not believe that sandblasting would be required. Plaintiff argues that the use of two terms to describe one membrane curing process was responsible for his misinterpreting the contract. Since BOR drafted the contract, plaintiff contends that BOR is responsible for plaintiff’s misinterpretation of the sandblasting requirements.

Plaintiff’s argument suffers from a number of flaws. The most obvious is the fact that the contract was not even arguably ambiguous about the necessity of sandblasting curing compound. The relevant contract provision (Par. 5.3.4(b)) specifically stated: “[T]hey [contraction joints] shall be lightly sandblasted to effectively remove the curing compound * * Thus, although the contract, at times, used “curing compound” and “sealing compound” interchangeably, the contract specifically used the term “curing compound” when referring to what material had to be sandblasted from the contraction joints. Plaintiff’s contention that it planned to use “curing compound” and thus did not realize the sandblasting requirement has little appeal in view of the specific direction in the contract referring to “curing compound.”

Moreover, a reasonable reading of the contract as a whole demonstrates no ambiguity because of the interchangeable use of “sealing compound” and “curing compound.” The context within which both terms were used in the contract demonstrate they were both referring to the same membrane curing compounds. In fact, the two terms themselves indicated that they were referring to the identical method of concrete curing. Membrane compound works as a curing agent because it forms a seal on the concrete surface which inhibits the evaporation of moisture. Thus, it is only logical that a membrane “sealing” compound is also a membrance “curing” compound. Contracts must be construed with business sense as they would naturally be understood by intelligent and experienced contractors such as plaintiff. See Hol-Gar Mfg. Corp. v. United States, 169 Ct.Cl. 384, 388 , 351 F.2d 972, 975 (1965); Deloro Smelting And Refining Co. v. United States, 161 Ct.Cl. 489, 495, 497 , 317 F.2d 382, 386, 387 (1963). An experienced contractor, such as plaintiff, well-versed in concrete construction should certainly have understood that “curing *705 compound” and “sealing compound” were two different terms for an identical material.

In fact, plaintiffs memorandum of November 15, 1974, demonstrates that at the time plaintiff adopted the membrane curing method it was aware of the necessity for sandblasting. Furthermore, despite plaintiff’s assertions of extra expense as a result of the sandblasting, plaintiff continued to use the membrane compound method even when warmer weather would have allowed it to switch back to the water method. The above facts suggest rather clearly that plaintiff understood the contract to require sandblasting.

Even if the court were to accept plaintiff’s contention that the contract provisions involving concrete curing and sandblasting were ambiguous, plaintiff would still be unable to recover on this claim. The ambiguity, as now perceived by plaintiff, in the sandblasting provision should have been patent to a knowledgeable and experienced contractor such as plaintiff. The contract provision involved here contained the two terms in question within the same sentence. Thus, the sentence in question read “where contraction joints to be grouted are coated with sealing compound * * * they shall be lightly sandblasted to effectively remove the curing compound.” (Par. 5.3.4(b).) If one did not interpret “curing compound” and “sealing compound” to mean the same compound, the sentence makes no sense. Unless the terms indicated the same compound, there would be no curing compound on the contraction joints to be sandblasted off. Therefore, plaintiff’s purported reading of this contract provision demonstrates a patent ambiguity.

It is well established that when faced with a patent ambiguity in a government contract, a contractor has a duty and a responsibility to have the ambiguity resolved before bidding on that contract. S.O.G. of Arkansas v. United States, 212 Ct.Cl. 125, 128 , 546 F.2d 367, 369 (1976) and cases cited therein. Therefore, plaintiff, at the very least, should have notified the contracting officer of the purported ambiguity before submitting its bid on this contract. Plaintiff’s failure to do so bars it, in any event, from recovering any damages which resulted from its interpretation of the alleged ambiguous contract provision.

For reasons discussed above, plaintiff is not entitled to recover on claim 4.

F. Claim 5 — Additional Concrete Cooling

Under claim 5, plaintiff seeks $48,008 for costs which it alleges resulted from its having to cool the concrete longer than the period specified in the contract. On audit by the FBI, corrections and adjustments reduced plaintiff’s claim figure to $35,872. These corrections and adjustments are adopted by the court. Plaintiff maintains that it exceeded the maximum number of cooling days set forth in the contract, and thus should receive an equitable adjustment for this longer period. Plaintiff excepted this concrete cooling claim from the release and both parties agree that the claim excepted from the release covers the period June 10, 1975, through November 25, 1975. Plaintiff so conceded this limitation on its cooling claim in a Stipulation of Facts which it executed and filed with the court, in its briefs, and at oral argument. Defendant accepts no liability for the claim and argues that plaintiff did not exceed the contract required cooling period when the days plaintiff failed to meet the contract specifications for cooling are taken into account.

Facts

The contraction joints in the concrete dam, as indicated in the discussion of claim 4, were the joints between the concrete blocks which comprised the concrete dam. In order to ensure that the concrete dam would adjust for any volumetric shrinkage and act as a monolithic structure, it was necessary to grout these joints. These joints were rather large. To properly grout these joints, it was necessary to cool the concrete to open up the joints. This opening up of the joints allowed the grout to be properly applied.

*706 Under the contract, plaintiff was responsible for supplying the concrete cooling equipment. The contract specifications required plaintiff to provide a refrigeration plant having a capacity of at least 110 tons of refrigeration per day and capable of furnishing 300 gallons per minute (gpm) of refrigerated water at a minimum temperature of 35 degrees Fahrenheit (F). The contract required plaintiff to furnish, install, and operate this equipment.

Paragraph 5.3.1 of the contract provided details of plaintiffs responsibilities for cooling the concrete. This paragraph provided in pertinent part: “[W]ater shall be circulated through these [temperature control] coils to reduce the peak temperature of the concrete, to obtain desirable temperature gradients within the concrete, and obtain the desired temperature of 40° F in the concrete at the time the contraction joints are grouted * * * the amount of water circulated through each temperature control coil shall be not less than 4 gpm.”

As mentioned earlier, the concrete was divided into blocks, i.e., vertical sections of the dam which ran from the bottom to the top of the dam. There were a total of 9 blocks, vertical sections, in all of the concrete dam. For the purposes of grouting, the concrete dam was also divided into three horizontal sections called grouting lifts. The first grouting lift consisted of approximately the bottom xk of the concrete dam; the second grouting lift consisted of approximately the middle % of the concrete dam; the third grouting lift consisted of approximately the top xk of the concrete dam. Plaintiffs concrete cooling claim for additional cooling costs involves only cooling in the top lh of the concrete dam, the third grouting lift. This third grouting lift involved a total of 8 blocks.

Under the contract, plaintiff was required to provide final cooling of the concrete blocks for a maximum of 30 days. The contract in paragraph 5.3.1 provided for additional compensation for this cooling process under the following conditions: “Upon completion of all final cooling in the dam, the average number of days required for the final cooling period for each block lift undergoing final cooling will be determined. If this average final cooling period per grouting lift exceeds 30 days, an equitable adjustment will be made for any necessary increases in cost in accordance with Clause No. 3 [the “Changes” provision of the contract] of the General Provisions.”

In its cooling operation for the third grouting lift, plaintiff spent a total of 317 days operating the cooling equipment. Since there were 8 blocks in this third lift and the contract required 30 days average per block, under the contract plaintiff had to operate the cooling equipment for 240 days without additional compensation (8 blocks X 30 days). Thus, the maximum number of days in dispute is 77 (317 days— 240 days). However, during this period the water was being circulated (flow through the coils) at less than 4 gpm for 46 days. In addition for 126 days during this period, plaintiff circulated water at 40° F. or greater. During the cooling of the third grouting lift plaintiff met both the contract requirements for temperature and flow for only 153 days of the total of 317 days involved. There were some days when plaintiff failed to meet both requirements on the same day.

Plaintiff does not dispute the fact that it met the contract requirements for only 153 days during cooling of the third grouting lift. Instead, plaintiff argues that BOR had control over the cooling operation. As a result of this control, plaintiff argues that BOR caused the deficiencies in the flow and temperature of the cooling water because of the manner in which it directed the cooling hoses to be placed on the concrete blocks. These cooling hoses connected the embedded temperature coils with the refrigeration plant. Thus, plaintiff blames the cooling inefficiencies on BOR’s running of the concrete cooling operation.

The court determines that BOR did, to some extent, control the concrete cooling operation including the placement of hoses *707 on the concrete blocks. 22 The court, however, determines that there were other factors which contributed more significantly to the inability of the cooling operation to meet the temperature and flow specifications in the contract during final cooling in the third grouting lift. First, plaintiff requested permission from BOR to allow it to place concrete at a temperature 5° F. higher than that required by the contract, 55° F. rather than 50° F. In return for BOR’s permission for this 55° F. temperature, plaintiff agreed that BOR would incur no added expense for this higher concrete temperature. Second, concrete cooling for the third grouting lift took place during the months of May through September, a period which included the hottest months of the year. Plaintiff’s cooling hoses were not insulated and this fact caused the water in the hoses to heat up during circulation, so that it was difficult for the refrigeration equipment to reduce the temperature of the circulating water to lower than 40° F. as was needed to ensure compliance with the contract specifications. The record is clear that the temperature of the water in the hoses had to be lower than 40° F. in order to meet the contract requirement of cooling the concrete to 40° F.

The record is conflicting and unclear how and to what extent defendant’s direction of the placement of the cooling hoses contributed to the inability of the refrigeration equipment to cool properly the water circulating through the embedded temperature coils. Based upon a review of the total record, the court is persuaded that plaintiff’s placement of the concrete at a temperature 5° F. higher than the original contract requirement was the primary reason that the concrete cooling operation failed to meet contract specifications and thus exceeded the maximum average of cooling days allowed by the contract. In addition, plaintiff’s use of uninsulated hoses to circulate the refrigerated water up to and through the temperature control coils in the concrete blocks was also a factor in plaintiff’s failure to achieve the flow and temperature requirements of the contract during portions of the concrete cooling period for the third grouting lift. Any effect of the manner of BOR’s placement of the cooling hoses on the temperature and flow requirements of the contract were outweighed by plaintiff’s failure to insulate the cooling hoses and by plaintiff’s pouring the concrete at 55° F. rather than 50° F.

The court determines that, after taking into consideration the days for which plaintiff is responsible for the failure to meet the temperature and flow requirements of the contract, the average number of cooling days per concrete block did not exceed an average of 30 days per block during the period June 10, 1975, through November 25, 1975.

Discussion

Plaintiff’s arguments in support of claim 5 are primarily factual in nature and thus the court’s factual findings, supra, effectively dispose of most of plaintiff’s contentions. There is one aspect of plaintiff’s claim, however, which bears discussion. Plaintiff’s basic position on claim 5 is grounded on the proposition that it supplied refrigeration equipment in accordance with the contract specifications, and therefore it had no further responsibility for the cooling process. It’s contention is that any extension in the final concrete cooling period must necessarily be BOR’s responsibility as a result of BOR’s right to control the cooling operation. Plaintiff's argument rests on the assumption that, under the contract, it only had to provide cooling equipment in compliance with the contract and it had no other cooling responsibilities.

Plaintiff’s argument is premised upon a faulty interpretation of the contract. While it is true the contract provided specifications concerning refrigeration plant tonnage, capacity, and rate of flow, the *708 contract also specifically provided in paragraph 5.3.1 how this refrigeration capacity was to be utilized during final cooling: “Temperature control coils shall be imbedded in the mass concrete of the concrete dam * * *. As provided herein, water shall be circulated through these coils * * to obtain the desired temperature of 40° F. in the concrete at the time the contraction joints are grouted.”

The contract did not specifically provide that the hoses from the refrigeration plant to the embedded temperature control coils were to be insulated. The contract, however, did specifically provide that the water in the temperature control coils had to have the capacity of bringing the concrete temperature to 40° degrees F. which could be done only if the water circulating through the coils was somewhat less than 40° F. Thus, the contract specifically stated the purpose for which the refrigeration plant was to be used. The contract must be given the meaning which a reasonably intelligent person would derive from the contract language. Hol-Gar Mfg. Corp. v. United States, supra, 169 Ct.Cl. at 388 , Deloro Smelting and Refining Co. v. United States, supra, 161 Ct.Cl. at 495, 317 F.2d at 386, 387 . Any reasonably intelligent and experienced contractor such as plaintiff would have understood that it had to provide not only refrigeration equipment in accordance with the contract specifications, but also provide a method of circulating the refrigerated water to ensure that it could cool the concrete to 40° F. Plaintiff, therefore, had a contractual obligation to ensure that its cooling equipment, including the hoses from the refrigeration plant to the embedded temperature coils, could accomplish the purpose stated in the contract. Moreover, plaintiff had the responsibility to ensure that this purpose could be accomplished in light of all reasonably foreseeable circumstances which might have an impact on the process.

Plaintiff failed to meet this contract responsibility when it did not insulate the hoses running from the refrigeration plant to the temperature control coils. Certainly, summer heat and its impact on the water circulating in uninsulated hoses was a foreseeable circumstance which plaintiff had a contractual obligation to provide for. The contract by not providing specifications for insulated hoses left to plaintiff the decision concerning how to ensure that the water was kept properly cool during circulation despite intense summer heat. Plaintiff did not take precautions against the impact of the summer heat on the cooling hoses by insulating the hoses and thus took the chance that the heat would have no great impact on the water circulating in these hoses. Plaintiff, not defendant, must bear the responsibility for this decision.

In summation, the court has concluded that the primary factors resulting in the extended cooling period for the third grouting lift in respective orders of importance were: (1) plaintiff’s placement of the concrete at 55° F. rather than 50° F. specified in the contract, (2) plaintiff’s failure to properly account for the effect of the summer heat on the circulating water by insulating the hoses which circulated the refrigerated water to the embedded temperature control coils. The court cannot in any definitive way determine whether BOR’s control and direction of the cooling operation may have contributed to the inefficiency of the cooling operation. While plaintiff dwells on BOR’s right to exercise some degree of control over the cooling operation, and complains, in generalities, about BOR’s control and direction over the cooling operation, it did not present sufficient specifics as to how and when such control and direction occurred and how it caused inefficiency in the process.

The court was not able, on this record, to assign a specific number of days to each of the three above mentioned factors: temperature variance, uninsulated hoses, and BOR’s degree of control of the cooling operation. However, the court is persuaded that the temperature variance factor, and to a lesser extent, the uninsulated hose factor were chiefly responsible for the inability of the cooling operation to per *709 form up to contract specification. The court concludes, from the record as a whole, that if plaintiff had poured concrete at 50° F. instead of 55° F. and if it had insulated the cooling hoses, the average cooling time per block in the third grouting lift most probably would not have exceeded 30 days per block. Plaintiff, therefore, is responsible for any and all days by which the final cooling period for the third grouting lift exceeded the 30-day per block average specified in the contract.

Accordingly, plaintiff is not entitled to any recovery under claim 5.

G. Claim 6 — Changes In Gallery Drainholes

Under claim 6, plaintiff seeks $78,836 as an equitable adjustment under the Changes clause of the contract for additional drainage holes drilling and grouting work in the concrete dam gallery area. The matter as presented in the Requested Findings of the parties was such as to suggest that the subcontractor, Continental, was also making a claim under claim 6. However, it is concluded this is not so. Claim 6 is on behalf of plaintiff only. While the events of claim 6 involved Continental, it is clear Continental incurred no additional costs or delay relative thereto, a fact conceded by Continental’s attorney at oral argument. Plaintiff provided support services (compressed air, water, electricity, and labor) to Continental for the gallery drilling and grouting operation. On the basis of providing these services, plaintiff seeks to recover costs and delay damages as a result of the gallery drainhole changes.

Plaintiff excepted claim 6, from the July 7, 1976, release in the amount of $92,357. Defendant contends plaintiff is only entitled to $2,139 as an equitable adjustment for changes in the gallery drainholes.

Facts

On October 9, 1975, plaintiff’s drilling and grouting subcontractor Continental encountered a water loss while drilling a drainage hole in the concrete dam gallery. Continental then moved its drilling rig 100 feet away from this hole, and attempted to drill another drainage hole. Continental again suffered a loss of water while drilling this other hole. Such a drill water loss should not have occurred during the drilling of the drainage holes because this gallery area had previously had a grout curtain pumped into it. Such a grout curtain should have ensured the impermeability of the foundation in the gallery areas by filling the voids in the foundation. The fact that Continental suffered a water loss while drilling these two drainholes demonstrated that the previously installed grout curtain had not adequately filled the voids in the foundation in these two locations. Therefore, on October 14, 1975, BOR ordered Continental to discontinue the drilling drainage holes until the two holes which had suffered drill water loss had been grouted. 23

In fact, BOR’s October 14,1975, directive effectively precluded any further drainage hole drilling in the thrust block gallery area. Paragraph 3.3.2 of the contract specifically prohibited drilling within 100 feet of a grouting operation. Thus until the completion of the grouting of the two drainage holes which had lost water, no further drainage holes could be drilled in this concrete dam gallery area since this area was within 100 feet of the two drainage holes which had to be grouted.

Continental chose not to grout immediately the two drainage holes in question in the thrust block gallery area because its grouting equipment was being used for contract required work on the right abut *710 ment. 24 Continental did not want to move its equipment into the gallery area until the work on the right abutment was completed. Continental continued performing the right abutment grouting work required by the contract until October 21, 1975. Continental spent from October 21 to October 24, 1975, preparing to grout the two gallery area drainage holes. On October 24, 1975, Continental grouted the first of the two gallery area drainage holes. On October 31, 1975, Continental completed grouting the second drainage hole in the thrust block gallery area.

It is unclear from the record how much of the October 24 through October 31, 1975, period was spent performing grouting work on the second drainhole. In its presentation, defendant is not consistent on the period for which plaintiff should be reimbursed. In its Objections to Plaintiffs Requested Findings, defendant maintains that plaintiff should be compensated only for its support service work during the period October 24-31, 1975. Yet, in its Requested Findings on damages, defendant allows plaintiff damages for the period October 21-October 24, 1975, but without explanation allows no labor and supply costs only equipment costs. Despite the confusion in the presentation and in the record, the court determines that plaintiff provided support services from October 21 through October 31, 1975, for additional drainage hole grouting work as a result of the October 14, 1975, BOR change directive. Thus, plaintiff spent a total of 9 work days (w.d.) (11 calendar days (c.d.)) providing support services for the additional drainage hole grouting work and incurred additional costs relative thereto.

Again, although the record is not entirely clear on the matter, the court concludes that all additional drilling work which resulted from the October 14, 1975, change directive was completed on or by October 31, 1975. All drainage hole work performed after October 31, 1975, involved work required by the contract. While plaintiff argues that it had to provide additional support services after October 31, 1975, because Continental had to drill through the grout placed in the two drainage holes when it redrilled these holes, the court finds, however, that plaintiff has been adequately compensated for this work. 25 The reason plaintiff has been adequately compensated is because any such additional services provided after October 31, 1975, were counterbalanced by contract required services which were provided during the period from October 21 through October 31, 1975, for which plaintiff has received additional compensation in this opinion. Since the court was not able to separate out the contract services provided during the October 21-October 31, 1975, period, the inclusion of this whole 11 c.d. (9 w.d.) period more than adequately allows for any small post-October 31, 1975, non-contract drilling services which may have been provided to Continental by plaintiff.

On October 20, 1975, plaintiff advised BOR by letter of its intention to make a claim for both direct and delay costs resulting from the October 14, 1975, BOR directive on the gallery drainage holes. On January 15, 1976, BOR responded to plaintiffs letter and stated that plaintiff was entitled to “an equitable adjustment to your contract to compensate for these changes in your work schedule.” Defendant concedes that plaintiff is entitled to recovery for providing support services to Continental for 4 w.d., October 21 to October 25, 1975. Thus, defendant concedes plaintiff is entitled to recover $2,139, for equipment costs and add-ons for job overhead, home office overhead, profit, taxes, and bond expenses. Defendant, without explanation, allows no amount for labor *711 and supply expenses. Defendant allows no amount for delay damages since it maintains the drainage hole work was not on the critical path.

The court determines that plaintiff is entitled to 9 w.d. of service support costs since it spent from October 21 through October 31, 1975, on the drainage hole grouting work relating to the October 14, 1975, BOR directive. The court has adopted the FBI audit figures for plaintiffs claim 6 costs for air and water plant costs as well as labor and supply costs. The court determines that the FBI audit figures for plaintiffs support costs are more reliable and reasonable than the figures used by plaintiff for the reasons generally discussed in Part

This text is long and has been trimmed here. Open the source document for the complete record.