MIDDLETON, P. J.

Epitomized Opinion

Published Only in Ohio Law Abstract

This was an action by the Construction Company against the Board of Education for damages for breach of contract. The Construction Company claimed that delay in the work was due to the fault of the Board of Education. The Board of Education in its second defense set up a certain provision of the contract which provided: “Claims by the party J of the first part for damages, by reason of / any delay on the part of the Board or its agents, will not be allowed, and any such delay shall work a corresponding extension of the time for the completion of the contract.” The Construction Company claimed that the clause was inconsisteht with other clauses of the contract and was without consideration. The judgment was rendered for the defendant, whereupon plaintiff prosecuted error. In sustaining the judgment of the lower court, the Court of Appeals held:

1. Under the provisions of this contract the plaintiff expressly waived its right to sue and recover damages for any delay.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.