Opinion

James Construction Group, LLC and Primoris Services Corporation v. Westlake Chemical Corporation

Court
Texas Supreme Court
Filed
May 20, 2022
Status
Published
Cited by
0 cases
Authority
More cited than 8.5%

noting that “the law abhors a forfeiture”

How later courts described this case

  • noting that “the law abhors a forfeiture”

Written by the judges who cited it.

The opinion

Supreme Court of Texas

══════════

No. 20-0079

══════════

James Construction Group, LLC and

Primoris Services Corporation,

Petitioners,

v.

Westlake Chemical Corporation,

Respondent

═══════════════════════════════════════

On Petition for Review from the

Court of Appeals for the Fourteenth District of Texas

═══════════════════════════════════════

CHIEF JUSTICE HECHT, joined by Justice Devine, Justice Busby,

and Justice Bland, dissenting in part.

Gregory Price, 55, suffered a fatal injury while working on a

construction project in December 2012 as a result of a serious safety

violation by his employer, James Construction. Price’s death was all

James’ fault. Price was standing on a ladder leaning against a truck

when a co-employee flagged the truck forward without checking to see if

Price was clear, even though that violated standard protocol and

common sense. Price fell, suffered a closed head injury, and died. His

tragic injury was entirely preventable, and OSHA issued James

multiple citations.

That was not the first time project owner Westlake Chemical had

to deal with James’ safety problems. In eight months as a general

contractor on the project in 2012, James had been cited multiple times

for safety violations. And despite Westlake’s repeated insistence that

James improve its record, safety violations continued even after Price’s

death. By April 2013, Westlake could take no more. Its managerial team

met with James’ team to tell them James was terminated for chronic,

serious safety violations. This upset James’ vice president. “[E]verybody

kills somebody on the job”, he said, “why are you penalizing us?”1 That

was the last straw for Westlake. A few days later, James acknowledged

in writing that it had been terminated.

Section 21.3 of the parties’ contract authorized Westlake to

terminate James for serious safety violations. The provision required

notice to James of the violations, Westlake’s dissatisfaction with

remediation efforts, and termination. Section 9.1 required that notices

be in writing. The Court acknowledges that “[s]ubstantial compliance is

the appropriate standard when evaluating whether a party complied

with a contractual notice condition.”2 Notice can be untimely, deficient,

sent in the wrong manner, or misdirected, and still be effective.3 “[A]s a

general principle of Texas law”, the Court declares, “a party’s minor

The Court dismisses the statement as “distasteful”. Ante at 36-37 n.20.

1

Westlake’s team was shocked. “It blew us away”, said one.

2 Id. at 20.

3 Id. at 22-23.

2

deviations from a contractual notice condition that do not severely

impair the purpose underlying that condition and cause no prejudice do

not and should not deprive that party of the benefit of its bargain.”4

The single exception, the Court holds, is the form of notice. If a

contract calls for a party to give written notice of a matter, then there

must be a writing of some kind, even if deficient, else the party forfeits

all contractual benefits, even though the opposing party was fully aware

of the matter and was not prejudiced in any way by the lack of a writing.5

The Court professes to have found no Texas case to the contrary, while

misreading a Fifth Circuit case and relying on dicta and inapposite

cases. Importantly, the Court altogether ignores a fundamental rule of

Texas law, that “[f]orfeitures are not favored in Texas, and contracts are

construed to avoid them.”6

Even if the Court were correct that parties must strictly comply

with the form of notice called for in their contract, Westlake met the

Court’s requirement of a writing, and the contents and manner of its

notices satisfy the substantial compliance standard the Court applies—

as found by the jury. The Court admits that Westlake’s emails regarding

safety violations, especially following Price’s death, may have been

sufficient for the first of three required notices. The Court faults

continuing email traffic between Westlake and James as being too

4 Id. at 23.

5 Id. at 29-30.

6 Aquaplex, Inc. v. Rancho La Valencia, Inc., 297 S.W.3d 768, 774 (Tex.

2009); see Sirtex Oil Indus., Inc. v. Erigan, 403 S.W.2d 784, 788 (Tex. 1966)

(noting that “the law abhors a forfeiture”).

3

encouraging and not expressive of Westlake’s dissatisfaction, though the

only reason for the emails was James’ continuing safety violations and

Westlake’s resulting concerns. And the Court concludes there was no

written notice at all of James’ termination, despite its project manager’s

letter to Westlake, stating: “Per the direction of Westlake[,] [James] has

discontinued mechanical work on the . . . project . . . .” James’ written

acknowledgment of termination should satisfy any requirement of a

writing.

With sleight of hand, the Court tries to make the issue whether

there were writings, then hold that there was at best only one of the

three the contract required because the writings that were indisputably

exchanged were deficient. The substance of Westlake’s notices is

governed, as the Court acknowledges, by the substantial-compliance

doctrine, and the jury found that Westlake satisfied it. The issue the

Court must address, yet avoids, is whether there is any evidence to

support the jury’s findings. There is.

This flaw in the Court’s analysis illustrates the difficulty of

carving out an exception to the substantial compliance rule generally

applicable to construction contracts. In some situations there may be no

writings at all, so that the issue is the form of the notice. But in many,

as here, there are writings, and the issue is not form, but substance, to

which the substantial-compliance doctrine applies.

The Court seeks to justify strict compliance with the form of

written notice by arguing that it “eliminates after-the-fact disputes

4

about exactly what notice was given.”7 But that is precisely why the

usual substantial compliance rule should apply. There are no such

credible disputes in this case. James’ safety violations were not “done in

a corner.”8 James had a terrible safety record and knew it. Even after a

fatal injury for which it was wholly at fault, and which was entirely and

easily preventable, James’ attitude was: “[E]verybody kills somebody on

the job”. This record does not contain even the slightest hint of dispute

about James’ safety record or the reason for its termination. The jury

affirmatively found that Westlake’s actual notice to James did not

“impair the purpose” of written notice “and caused no harm to James.”

On the other hand, the Court observes that the substantial-

compliance doctrine “serves the important purpose of preventing parties

from engaging in bad-faith, ‘gotcha’ tactics to avoid their own

contractual obligations based on a technicality.”9 Again, that is precisely

why the doctrine should apply in this case. Though James knew full well

everything of which Westlake repeatedly gave notice, the Court allows

James to escape its contractual obligation to pay the $1 million costs

Westlake incurred because of James’ termination. By the Court’s

reasoning, Westlake could have scribbled “terminated” on a napkin and

handed it to James’ angry project manager, and the result in this case

would be completely different. The absence of one word labeling what

everyone knew was happening results in a $1 million forfeiture of

contractual benefits awarded by the jury.

7 Ante at 27.

8 See Acts 26:26.

9 Ante at 24.

5

Finally, the Court holds that one provision of the parties’ contract

must be strictly enforced while another, which would also allow

Westlake to recover the same damages, does not mean what it says.

Section 17.2 gave Westlake, during James’ work, “the right to intervene

in any appropriate way,” particularly for safety’s sake. The Court

concludes that this remedy is subject to the notice requirements of

Section 21.3, ignoring the clear statement in Section 17.2: “This right is

in addition to any other remedies [Westlake] may have [under the

contract].” Because the provision authorizes Westlake to require James

to bear the cost of the intervention, the Court concludes that the

provision “implies” that James will still be on the job after the

intervention, even though the fact—not the implication—is that

Westlake claims James must bear the cost of the intervention after it

left the project. So: “written” means written, no matter what, but “any

appropriate way” means some appropriate way, not including

termination. The Court does not take notice of the inconsistency, much

less the irony, in its positions.

The jury found that James’ breaches of Sections 21.3 and 17.2 cost

Westlake $1,054,251.81, which the contract required James to

reimburse. Though James was well aware of its repeated, serious safety

violations and angry at Westlake for insisting on a safe jobsite, the Court

orders that Westlake forfeit its contractual rights for lack of a writing

that the jury found did not harm James. I disagree that Westlake failed

to comply with the notice requirements of Section 21.3 and that it cannot

recover its excess costs in completing the work under Sections 21.3 and

17.2. I therefore respectfully dissent.

6

I

The Court holds that the rule of substantial compliance applies to

contractual notice conditions in two ways. First, the rule applies to the

substance of the notice. In the example the Court cites, one parent’s

notice to the other of proposed international travel, required before the

other was required to consent, substantially complied with the divorce

decree even though it omitted significant information—like where they

would stay and when they would return.10

Second, the rule applies to the method of notice. In the Court’s

examples, notice need not be sent by registered mail, as the parties

contracted,11 or to the location directed in the contract,12 as long as it was

received. In the Court’s view, the content of the notice—which, after all,

is the very point of requiring that notice be given—and the manner of

the notice’s delivery need only substantially comply with the parties’

agreement. But if a contract calls for written notice, the Court decrees,

then there must be a writing, even if the parties’ contract does not insist

on strict compliance, and even if notice is completely ineffectual where,

as here, notice confers no information not already indisputably known

to both parties.

As rationales for its new rule, the Court offers precedent and

policy.

Id. at 22-23 (citing In re G.D.H., 366 S.W.3d 766, 771 (Tex. App.—

10

Amarillo 2012, no pet.)).

Id. at 23 (citing Barbier v. Berry, 345 S.W.2d 557, 562 (Tex. Civ.

11

App.—Dallas 1961, no writ)).

Id. (citing Tex. Utils. Elec. Co. v. Aetna Cas. & Sur. Co., 786 S.W.2d

12

792, 793 (Tex. App.—Dallas 1990, writ denied)).

7

A

As for precedent, the Court says it has found “no Texas cases

holding that a party’s provision of oral notice complies, substantially or

otherwise, with a requirement of written notice.”13 Actually, there is one,

which the Court has found but does not recognize: South Texas Electric

Cooperative v. Dresser–Rand Co.,14 decided by three Texas judges on the

federal appeals court applying Texas law.

In South Texas, Dresser contracted to repair any defects in the

electric turbine it sold the Co-op after the Co-op provided written notice

of such defects. If Dresser failed to make the repairs, the Co-op, after a

second, ten-day written notice to Dresser, had the right to repair the

defects itself at Dresser’s expense. From startup, vibrations in the

turbine impaired its use. Dresser knew of the problems, and for two

years the parties emailed back and forth about them. Finally, the Co-op,

“without providing Dresser further written notice, employed outside

consultants to do the repair work.”15

“[T]he jury found that [the Co-op] substantially complied with the

contract’s notice provisions”,16 and the Circuit held that was sufficient

to allow it to recover. The Circuit rejected Dresser’s argument that the

substantial-compliance doctrine did not apply to a contractual

requirement for written notice. Further, the Circuit held that “Dresser’s

13 Id. at 24.

14 575 F.3d 504 (5th Cir. 2009) (opinion by Haynes, J., joined by Jones,

C.J., and Higginbotham, J.).

15 Id. at 506.

16 Id.

8

arguments are contrary to well-established Texas law, recognizing the

applicability of the doctrine of substantial compliance to contractual

notice provisions.”17 Dresser knew that the Co-op was consulting with

experts, even though the Co-op did not give Dresser written notice that

the experts would repair the turbine at Dresser’s expense. The Circuit

concluded: “[T]he evidence here supports a conclusion that the

underlying purpose of the ten-day notice requirement . . . was fully

served by the actual notice received by Dresser.”18

This Court dismisses South Texas as inapposite because the

Circuit stated that the Co-op had hired outside consultants to repair the

turbine “without providing Dresser further written notice”,19 noting that

the parties had exchanged writings on the need for repairs. But the

Circuit’s opinion clearly states, and the Co-op did not dispute, that the

Co-op did not give Dresser the contractually required written notice that

repairs were to be made. Dresser argued on appeal that whatever it may

have known about the Co-op’s use of experts, it was entitled to the

written notice for which it contracted. This Court says that the Circuit’s

“focus was not on the lack of a writing”,20 but that was the very focus of

the entire case. The Circuit’s opinion refers to “written” notice five times.

The parties’ contract required written notice. None was given. The

Circuit applied the substantial-compliance doctrine and held, as the jury

had found, that the Co-op satisfied it.

17 Id. at 507.

18 Id. at 508.

19 Ante at 29 (quoting S. Tex. Elec. Coop., 575 F.3d at 506).

20 Id.

9

The Court also dismisses South Texas because “federal law” is not

needed to “fill in [a] gap” in Texas jurisprudence.21 With respect, the

Court’s statement makes no sense. South Texas did not apply federal

law; it applied Texas law to a Texas case. There was no “gap” in Texas

law; the applicability of substantial compliance to contractual written

notice provisions was “well-established”.22 The Court can certainly

disagree with South Texas; it cannot dismiss it.

The Court cites four cases in support of its holding. Two, Cheung–

Loon, LLC v. Cergon, Inc.,23 and Tennessee Gas Pipeline Co. v. Technip

USA Corp.,24 have nothing whatever to do with substantial compliance.

Both denied recovery because no notice of any kind was given. In the

former, the court stated that “appellees point to no evidence that any of

the alleged notifications informed [the opposing party] of their position

[or] the contractual right they now claim was breached.”25 In the latter,

a case factually similar to the present one, the court rejected the

argument that “no notice is required” of one party’s intent to repair

defective workmanship at the other’s expense.26 Neither the words

“substantial compliance” nor the concept appear in either case.

In a third case, Emerald Forest Utility District v. Simonsen

21 Id. at 28.

22 S. Tex. Elec. Coop., 575 F.3d at 507.

23 392 S.W.3d 738 (Tex. App.—Dallas 2012, no pet.).

24 No. 01-06-00535-CV, 2008 WL 3876141 (Tex. App.—Houston [1st

Dist.] Aug. 21, 2008, pet. denied).

25 Cheung–Loon, 392 S.W.3d at 745.

26 Tennessee Gas Pipeline, 2008 WL 3876141, at *20.

10

Construction Co., the court stated that “[t]he controlling issue is whether

[a party] warranted the sufficiency of the design of the sewer system.”27

In dicta, the court noted that “[w]hen a contract provides for a particular

form of notice, compliance with such provisions is a condition precedent

to invoking the contract rights which are conditioned on the notice.”28

But the court did not state that substantial compliance does not apply.

Again, neither the words nor the concept appear in the opinion.

The fourth case the Court cites is Shaller v. Commercial Standard

Insurance Co., a decision of this Court.29 The jury in the case found that

the insureds had not consented to the cancellation of two insurance

policies, but the court of appeals reversed judgment on the verdict,

holding that consent was established as a matter of law. This Court

reversed, holding that the insureds had no notice at all their policies

would be cancelled, and therefore whether the insureds consented was

a fact question for the jury.30 The Court added that a policy provision

requiring prior written notice of cancellation should be enforced absent

waiver, agreement, or estoppel,31 but it did not discuss substantial

compliance. Neither the words nor the concept appear in the opinion.

The Court can hold that the substantial-compliance doctrine

applies to construction contracts generally and notice provisions in

27 679 S.W.2d 51, 52 (Tex. App.—Houston [14th Dist.] 1984, writ ref’d

n.r.e.).

28 Id. at 54.

29 309 S.W.2d 59 (Tex. 1958).

30 Id. at 66.

31 Id.

11

particular and carve out a single exception for the form of notice. What

it cannot do—or at least what it cannot do legitimately—is claim for its

authority cases that do not discuss substantial compliance while

dismissing a contrary case that does.

B

The Court argues that its exception to the substantial compliance

rule is good policy because it avoids after-the-fact disputes over what

notice was given and what the parties actually knew. But while such

disputes are certainly worth avoiding, none exist in this case. Before and

after an on-the-job death, Westlake and James were in constant

conversation about how to improve safety on the project and whether

James could continue on as a contractor.

In this situation, there is a stronger countervailing policy: the

law’s abhorrence of forfeitures and construction of contracts to avoid

them. The Court agrees that Westlake would have strictly complied with

the written notice requirement if it had scribbled only a few words, like

“21.3” plus “safety”, “dissatisfied”, and “terminated”. For want of a few

words, Westlake forfeits the more than $1 million in damages found by

the jury. And words would have added nothing to the parties’ awareness

of the safety problems and the unavoidable consequences.

The Court apologizes that it must read contracts the way the

parties write them, but in this case, that is simply not true. Parties need

only substantially comply with the substance of a contract’s notice

requirements. The Court demands that formal requirements must be

read as written, but not substantive requirements. Here are the Court’s

words:

12

The courts’ unfailing refusal to deem oral notice compliant

with a contractual condition requiring written notice, like

the doctrine of substantial compliance as a general matter,

is consistent with our repeated affirmation that “[a]bsent

compelling reasons, courts must respect and enforce the

terms of a contract the parties have freely and voluntarily

entered.” The bargained-for requirement of written notice

necessarily serves a purpose beyond actual notice;

otherwise, its inclusion is useless.32

How is the application of substantial compliance in this case

inconsistent with respecting and enforcing the parties’ terms as written?

A bargained-for requirement of written notice is not useless, any more

so than a bargained-for requirement of registered mail or destination.

The requirement sets the standard for the parties’ desired certainty.

Allowing notice sent by regular mail or to a different office does not

disrespect the parties’ right to contract. Rather, it assumes the parties

contracted in good faith and not with the intent to spring technical

“gotchas” on each other to avoid their obligations. Notice tantamount to

written notice, which James clearly had, should be sufficient.

II

In the end, the Court’s rule that parties must strictly comply with

a contractual requirement for the form of notice is of little significance

to a decision in this case. The issue is not whether there were writings,

but what they contained. On this issue, the Court is bound by the jury’s

findings that Westlake substantially complied with the contract unless

there was no evidence to support them.

Westlake hired James in May 2012 as a general contractor to

32 Ante at 26-27.

13

work on Westlake’s chlor-alkali plant,33 only their contract did not

require Westlake to assign James work, or James to accept an

assignment. Westlake was free to retain other contractors to do work

James could do.

Section 21.3 of their contract provided:

If [Westlake] discovers or determines in its reasonable

opinion that . . . [James] has serious safety violations[,]

then [Westlake] may so notify James. Upon receipt of any

such notice [James] shall begin to remedy the breach or

defect cited within seventy-two (72) hours. If at any time

[Westlake] is not reasonably satisfied with the pace and the

quality of the remediation effort, [Westlake] will so notify

[James] and [Westlake] may thereafter, at its sole

discretion, elect to either terminate this Contract or portion

of the Work by providing notice to that effect. After

providing such notice [Westlake] shall have the

unrestricted right to take possession of the Work or the

portion thereof terminated and to purchase and/or hire

materials, tools, supervision, labor, and equipment for the

completion of the Work or of the unremedied condition, as

[Westlake] elects. Any extra costs in excess of the Contract

Price incurred by [Westlake] in this regard shall be at the

expense of [James]. This right is in addition to any other

remedies [Westlake] may have hereunder.

The provision thus called for Westlake to give three notices: of its

opinion that James had serious safety violations, of its dissatisfaction

with James’ remediation effort, and of termination of James’ work. The

contract required that all notices be written.

On December 28, James’ employee Gregory Price suffered a fatal

head injury on the job. He fell from a ladder propped against the side of

33 The chlor-alkali process produces chlorine and caustic soda by the

electrolysis of brine.

14

a truck, helping to load it, when the driver was directed to pull ahead

without checking to see that no one was near. OSHA cited James for a

serious safety violation. It was the latest in a steady stream of violations.

The same day, Westlake’s project manager, Abram Kuo,

forwarded to his counterpart at James, Rusty DeBarge, an email Kuo

had received from his superior stating that Price’s death was

“completely preventable”, asking for James’ incident rate of safety

violations, proposing a safety review for James to show how it would

prevent further incidents, and requiring James “to develop [a]

preventive safety mind set [sic] with some extraordinary measures on

job safety.” Kuo followed up in a meeting with DeBarge a few days later,

together reviewing James’ safety record and emphasizing the

importance of James’ improving its safety performance.

The Court calls it “questionable” whether the December 28 email

was the first notice under Section 21.3 because it did not mention that

provision and did not specify when James’ 72 hours to remediate began.

But the contract required neither. The Court itself holds that the

substance of the notice need only substantially comply with the

contractual requirement. It certainly did, as the jury found. By any

measure, an email stating that a preventable death on the job required

a complete safety review expresses a reasonable opinion that there had

been serious safety violations.

On January 18, DeBarge emailed Kuo to “appeal” “potential

changes in the execution of the project going forward”—specifically

James’ removal from the project. Kuo emailed back the same day,

confirming that Westlake might bring another contractor onto the

15

project. Quoting DeBarge’s email back to him, Kuo agreed that everyone

“would like to be judged by [their] intentions” but “are in fact judged by

the results.” Kuo added: “we all make mistakes and we all need to learn

from [them].” On January 30, Westlake transferred work from James to

a new contractor.

The Court concludes that this email was not the second notice

called for by Section 21.3 because, like the December 28 email, it did not

mention that provision, and because it acknowledged steps James had

taken to improve safety and did not express dissatisfaction with James’

performance. But the email exchange was precipitated by rumors

DeBarge had heard that Westlake was going to switch to another

contractor. Westlake was not terminating James because it was

satisfied with James’ work. The email exchange was premised on

Westlake’s dissatisfaction, and Westlake terminated part of James’

work a few days later.

As with the December 28 email, the Court concludes that the

January 18 email did not qualify as written notice under Section 21.3,

not because it was not written, but because it was lacking in substance.

But again, that must be determined under the substantial-compliance

doctrine, and the jury found for Westlake. There was clearly some

evidence in the January 18 email of Westlake’s dissatisfaction with

James’ safety performance, which unquestionably existed. The Court

never addresses the jury’s verdict.

Finally, on April 11, after additional incidents even under a new

site manager, James and Westlake representatives met in person.

Westlake told James that its work was being reassigned to a different

16

contractor and that James had “five days to get [its] remaining piping

and mechanical people off the job.” Additionally, James was told that

Westlake had “done everything [it could] do”, and despite Westlake’s

efforts to help James, James “[fell] back into the same pattern” of safety

problems. James’ vice-president responded angrily: “[E]verybody kills

somebody on the job[.] [W]hy are you penalizing us?” James immediately

withdrew from the project.

On May 8, DeBarge emailed Westlake that “[p]er the direction of

Westlake site management, [James] has discontinued mechanical work

on the Chlor-Alkali project and we have completed the demobilization of

the mechanical forces.” The Court rejects this writing as complying with

Section 21.3 because it was not sent by Westlake, but in reciting the

notice Westlake gave at the earlier meeting, paired with James’

withdrawal from the project, it served the same purpose as if coming

from Westlake. Indeed, it showed James’ own understanding of the

situation.

The writings between Westlake and James satisfy the

requirements of Section 21.3. Certainly, they substantially complied

with those requirements, as the jury found.

III

The Court holds that Section 21.3 of the contract must be read as

written, but not Section 17.2. That provision states:

[Westlake] shall at any time during the execution of the

Work by [James] have the right to intervene in any

appropriate way, if in the reasonable opinion of [Westlake],

(a) [James’] performance is likely to lead to (i) defective

Work, (ii) a material breach of this Contract, (b) the

progress achieved by [James] is insufficient or likely to

17

result in the Work not being completed by the completion

date stated in any Work Order or (c) [James] is performing

its duties under this Contract in an unsafe way or manner

in which [Westlake] believes may cause injury or damage

to persons or property. In such cases [Westlake] shall have

the right to require [James] to immediately take remedial

action to the satisfaction of [Westlake]. [James] shall be

solely accountable for all costs associated with such

intervention and remedial action, whether incurred by

[James], [Westlake] or any third party.

The Court concludes that intervention “in any appropriate way” does not

mean requiring safety improvements and termination without notice,

otherwise Section 21.3 would be meaningless. But Section 21.3 itself

expressly states that the right it gives Westlake to intervene in James’

work with notice “is in addition to any other remedies Westlake may

have hereunder.” Despite this plain statement, the Court reads Section

21.3 to confer an exclusive right to intervene, not an additional one.

Neither section need be read to trump the other. They provide

alternative ways for Westlake to proceed. But, according to the Court,

Section 17.2 prevails over Section 21.3 because “Texas courts regularly

enforce unambiguous contract language agreed to by sophisticated

parties in arms-length transactions.”34 The Court cannot have it both

ways. If “written” must be read literally, then so must “any appropriate

way”.

* * * * *

I would not except the form of notice required by construction

contracts from the substantial-compliance doctrine, which applies to the

rest of the contract. I would not insist that part of a contract must be

34 Ante at 18.

18

read literally and that another part cannot be. I would hold that there

is evidence to support the jury’s findings that Westlake substantially

complied with the contract’s notice requirements. And I would not forfeit

the $1 million damages awarded Westlake by the jury for want of a word

or two. Therefore, I respectfully dissent.35

Nathan L. Hecht

Chief Justice

OPINION DELIVERED: May 20, 2022

35James raises an additional ground for reversal related to agency. The

Court did not reach the issue because it held that Westlake may not recover

under Section 21.3. Ante at 16-17 n.10. I would affirm the court of appeals’

holding on the issue in Westlake’s favor. Additionally, as to Part II(C) of the

Court’s opinion, I agree with the result that Westlake can recover on its

indemnity claim, but I disagree with the Court's rationale that Westlake failed

to comply with Section 21.3's notice requirements. Cf. id. at 42-43.

19

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.