Opinion

United States v. Renda Marine, Inc.

  • 667 F.3d 651
  • 2012 U.S. App. LEXIS 796
  • 2012 WL 104999
Court
Court of Appeals for the Fifth Circuit
Filed
Jan 13, 2012
Status
Published
Author
Benavides
On the bench
Benavides, Prado, Alvarez
Cited by
57 cases
Authority
More cited than 88.2%

The opinion

Case: 10-41296 Document: 00511725216 Page: 1 Date Filed: 01/13/2012

IN THE UNITED STATES COURT OF APPEALS

FOR THE FIFTH CIRCUIT United States Court of Appeals

Fifth Circuit

FILED

January 13, 2012

No. 10-41296 Lyle W. Cayce

Clerk

UNITED STATES OF AMERICA,

Plaintiff-Appellee

v.

RENDA MARINE, INC.,

Defendant-Appellant

Appeal from the United States District Court

for the Eastern District of Texas

Before BENAVIDES and PRADO, Circuit Judges, and ALVAREZ, District

Judge.*

BENAVIDES, Circuit Judge:

In this case, Renda Marine, Inc. (“Renda”) appeals the district court’s

denial of its motion for partial dismissal for lack of subject matter jurisdiction

and motion for partial summary judgment. Renda also appeals the district

court’s grant of the Government’s motion for judgment on the pleadings. For the

following reasons, we AFFIRM.

*

District Judge of the Southern District of Texas, sitting by designation.

Case: 10-41296 Document: 00511725216 Page: 2 Date Filed: 01/13/2012

No. 10-41296

I. FACTUAL AND PROCEDURAL BACKGROUND

In October 1998, Renda contracted with the Army Corps of Engineers to

dredge a portion of the Houston Ship Channel and to construct containment

levees and other structures at a disposal facility for dredge material. Renda

experienced difficulties with the dredging and construction work, including

allegedly unexpected site conditions that made completion of the work at the

original contract price impossible. Renda submitted its claims for additional

compensation to a contracting officer (“CO”) pursuant to the Contracts Dispute

Act (“CDA”), 41 U.S.C. § 601, et seq.1 The CO issued a unilateral contract

modification in favor of Renda that increased the contract price by $3,083,833.

The Army Corps of Engineers paid Renda this amount. Unsatisfied with the

decision, Renda filed suit in the Court of Federal Claims (“CFC”) to recover an

additional $906,364. The CFC determined that Renda was entitled to neither

the additional $906,364 it sought, nor the equitable adjustment of $3,083,833

made by the CO.

While Renda’s modification suit was pending before the CFC, the CO

issued a final decision on six different claims the Government had brought

against Renda for post-termination costs of completing certain aspects of the

work originally covered by the contract. The CO granted the total amount of

those claims, which was $11,860,016. The CO’s decision also stated that the

Government withheld $259,840.85 in retainage. Renda did not appeal this

decision directly. Rather, on July 1, 2004, Renda sought leave to amend its

complaint in the ongoing CFC litigation to challenge the CO’s decision granting

1

At the time of the district court’s decision, the CDA was codified at 41 U.S.C. §§ 601-

613. On January 4, 2011, the CDA was revised and published as 41 U.S.C. §§ 7101-7109. This

opinion will reference the previous section numbers, in order to remain consistent with the

district court opinion.

2

Case: 10-41296 Document: 00511725216 Page: 3 Date Filed: 01/13/2012

No. 10-41296

the Government $11,860,016. The CFC denied Renda’s motion and the Federal

Circuit affirmed that denial.

On November 24, 2008 the Government filed the present lawsuit in federal

district court, seeking to enforce the decisions of the CFC. In Count I, the

Government alleges that Renda owes it $11,860,016, pursuant to the CO’s

decision on the six counterclaims. In Count II, the Government seeks repayment

of $3,083,833—the amount paid to Renda in excess of the original contract

price—based on the CFC’s determination that Renda was not entitled to any

equitable adjustment of the contract price.

Renda filed a motion for partial dismissal, arguing that the district court

lacked subject matter jurisdiction over Count II of the complaint because the

Government allegedly failed to comply with the requirements of the CDA.

Renda also filed a motion for partial summary judgment, arguing that the

statute of limitations barred Count I. On September 30, 2010, the district court

denied Renda’s motions, granted the Government’s motion for judgment on the

pleadings on both claims, and entered judgment against Renda. The district

court held that it had jurisdiction to enforce the CFC’s decision that Renda was

not entitled to the $3,083,833 the Government had paid it, and that the

Government had timely filed its suit to enforce the $11,860,016 judgment

against Renda. The district court also held that Renda was not entitled to any

offset of the Government’s recovery based on funds the Government had kept in

retainage. Renda then timely filed this appeal of the district court’s judgment.

II. STANDARD OF REVIEW

A challenge to this court’s subject matter jurisdiction may be raised at any

time on appeal. Arbaugh v. Y&H Corp., 546 U.S. 500, 506 (2006); Edge

Petroleum Operating Co. v. GPR Holdings, L.L.C. (In re TXNB Internal Case),

483 F.3d 292, 298 n.6 (5th Cir. 2007). When considering a motion to dismiss for

lack of subject matter jurisdiction, a district court may consider: “(1) the

3

Case: 10-41296 Document: 00511725216 Page: 4 Date Filed: 01/13/2012

No. 10-41296

complaint alone; (2) the complaint supplemented by undisputed facts evidenced

in the record; or (3) the complaint supplemented by undisputed facts plus the

court’s resolution of disputed facts.” Rodriguez v. Christus Spohn Health Sys.

Corp., 628 F.3d 731, 734 (5th Cir. 2010) (quoting Ramming v. United States, 281

F.3d 158, 161 (5th Cir. 2001)). The party asserting jurisdiction has the burden

of proof. Ramming, 281 F.3d at 161.

We review de novo a district court’s grant of judgment on the pleadings

under Federal Rule of Civil Procedure 12(c). Brittan Communs. Int’l Corp. v.

Sw. Bell Tel. Co., 313 F.3d 899, 904 (5th Cir. 2002). “[W]e must look only to the

pleadings and accept all allegations contained therein as true.” Id. “The issue

is not whether the plaintiffs will ultimately prevail, but whether they are

entitled to offer evidence to support their claims.” Ferrer v. Chevron Corp., 484

F.3d 776, 780 (5th Cir. 2007).

We also apply a de novo standard of review to a motion to dismiss under

Rule 12(b)(1), and motions for summary judgment under Rule 56. LeClerc v.

Webb, 419 F.3d 405, 413 (5th Cir. 2005). Summary judgment is appropriate if

the moving party can show that “there is no genuine dispute as to any material

fact and the movant is entitled to judgment as a matter of law.” FED. R. CIV. P.

56(a). “A factual dispute is ‘genuine’ where a reasonable party would return a

verdict for the non-moving party.” Chiu v. Plano Indep. Sch. Dist., 339 F.3d 273,

282 (5th Cir. 2003) (citation omitted). In considering a summary judgment

motion, we view the evidence in the light most favorable to the non-moving

party. United Fire & Cas. Co. v. Hixson Bros., Inc., 453 F.3d 283, 285 (5th Cir.

2006). However, “[u]nsubstantiated assertions, improbable inferences, and

unsupported speculation are not sufficient to defeat a motion for summary

judgment.” Brown v. City of Houston, 337 F.3d 539, 541 (5th Cir. 2003).

4

Case: 10-41296 Document: 00511725216 Page: 5 Date Filed: 01/13/2012

No. 10-41296

III. ANALYSIS

A. The Contract Disputes Act

“The Contract Disputes Act is a comprehensive statutory scheme for

resolving contractual conflicts between the United States and government

contractors.” United States v. J&E Salvage Co., 55 F.3d 985, 987 (4th Cir. 1995);

Menominee Indian Tribe v. United States, 614 F.3d 519, 521 (D.C. Cir. 2010)

(accord); Anselma Crossing, L.P. v. United States Postal Serv., 637 F.3d 238, 246

(3d Cir. 2011) (stating that “the policy goals of the CDA [are] to collect contract

disputes against the government in a forum . . . with both the requisite expertise

and the ability to provide consistency in applying the laws related to government

contracts”). The CDA applies to any express or implied contract entered into by

an executive agency for: “(1) the procurement of property, other than real

property in being; (2) the procurement of services; (3) the procurement of

construction, alteration, repair or maintenance of real property; or, (4) the

disposal of personal property.” 41 U.S.C. § 602(a). “It is well-established

therefore that disguised contract actions may not escape the CDA.” J&E

Salvage Co., 55 F.3d at 988 (noting that the source of the rights the government

sought to vindicate were based in contract, even though the government styled

its action as one sounding in tort); Trevino v. Gen. Dynamics Corp, 865 F.2d

1474, 1489 (5th Cir. 1989) (finding claim subject to CDA, as essence of claim was

to obtain money from the government).

The CDA was intended “to streamline the settlement of controversies over

federal government contracts,” and it “generally affords private contractors a

two-step review process.” Bethlehem Steel Corp. v. Avondale Shipyards, Inc.,

951 F.2d 92, 93 (5th Cir. 1992). First, there must be a final decision by a CO on

a claim before that claim can be submitted to a federal court. Trevino, 865 F.2d

at 1489 (“The decision, or failure to decide, by a contracting officer is an absolute

jurisdictional prerequisite to filing a suit under the Contract Disputes Act.”); see

5

Case: 10-41296 Document: 00511725216 Page: 6 Date Filed: 01/13/2012

No. 10-41296

also, e.g., J&E Salvage Co., 55 F.3d at 987; Menominee Indian Tribe, 614 F.3d

at 521; Sharman Co. v. United States, 2 F.3d 1564, 1566 (Fed. Cir. 1993),

overruled on other grounds by Reflectone, Inc. v. Dalton, 60 F.3d 1572 (Fed. Cir.

1995) (en banc)2; Transamerica Ins. Corp. ex rel. Stroup Sheet Metal Works v.

United States, 28 Fed. Cl. 418, 422 (1993). After a CO has issued a decision, a

party may appeal that decision to the relevant board of contract appeals within

90 days, or file suit in the CFC within 12 months. Menominee Indian Tribe, 614

F.3d at 521.

A claim has been defined as “the assertion as a matter of right to a sum

certain as presently due and owing, on which there was a final decision by the

contracting officer.” Sharman Co., 2 F.3d at 1567; see also Joseph Morton Co. v.

United States, 757 F.2d 1273, 1281 (Fed. Cir. 1985) (stating that the word

“claim” does not mean “the whole case between the contractor and the

Government,” but instead, it means “each claim under the CDA for money that

is one part of a divisible case.”); United States v. Intrados/Int’l Mgmt. Grp., 277

F. Supp. 2d 55, 64 (D.D.C. 2003) (“A valid claim submitted to a contracting

officer includes such routine submissions as ‘vouchers, invoices, and similar

requests for payment[, which] are submitted for work done or equipment

delivered by the contractor in accordance with the expected or scheduled

progression of contract performance.’” (quoting James M. Ellett Constr. Co., Inc.

v. United States, 93 F.3d 1537, 1542 (Fed. Cir. 1996) (internal quotation marks

and citation omitted))). The Federal Acquisitions Regulation (“FAR”)3 defines

a “claim” as “a written demand or written assertion by one of the contracting

parties seeking, as a matter of right, the payment of money in a sum certain, the

2

The Federal Circuit Court of Appeals has exclusive jurisdiction over appeals from

agency boards of contract appeals in CDA cases, and from the CFC. 28 U.S.C. § 1295(3), (10).

3

“The Federal Acquisitions Regulation applies to all acquisitions as defined in part 2

of the FAR, except where expressly excluded.” 48 C.F.R. § 1.104.

6

Case: 10-41296 Document: 00511725216 Page: 7 Date Filed: 01/13/2012

No. 10-41296

adjustment or interpretation of contract terms, or other relief arising under or

relating to the contract.” 48 C.F.R. § 2.101; see also In re Remington Rand Corp.,

836 F.2d 825, 830 (3d Cir. 1988) (citing FAR definition).

B. Count I

In Count I, the Government seeks to collect the $11,860,016 that the CO

determined Renda owed for the post-termination costs of completing work

originally covered by the contract. In the district court, Renda argued that the

suit was filed after the statute of limitations had run. Section 2415 of Title 28

of the United States Code provides alternative limitations periods for

government contract actions for money damages. The Government must file suit

either “within six years after the right of action accrues or within one year after

final decisions have been rendered in applicable administrative proceedings

required by contract or by law, whichever is later.” 28 U.S.C. § 2415(a).

In finding for the Government, the district court considered both

alternative statute of limitations periods. Although noting that a contract claim

generally accrues at the time of breach, the district court agreed with the

Government’s argument that it was not suing for breach of contract, but rather

to enforce the CO’s final decision issued on November 26, 2002. Therefore,

under the six-year limitations period, the Government’s suit, filed on November

24, 2008, appeared timely. However, the district court ultimately relied on the

one-year savings clause after finding that it provided the Government with the

most time to file suit. The district court held that an appeal to the CFC

constituted an applicable administrative proceeding triggering the savings

clause. The court noted that it would not have had jurisdiction to consider the

Government’s claims against Renda until the Federal Circuit had affirmed the

CFC’s denial of Renda’s motion to amend its complaint in the separate, ongoing

CFC litigation regarding the $3,083,833 the Government had overpaid Renda.

The Government could not enforce the CO’s decision until it was clear that

7

Case: 10-41296 Document: 00511725216 Page: 8 Date Filed: 01/13/2012

No. 10-41296

Renda was barred from challenging it. The Federal Circuit’s decision affirming

the CFC’s denial of Renda’s leave to amend its complaint was rendered on

December 11, 2007. Therefore, according to the district court, the Government’s

suit was timely.

Here, Renda again argues that the statute of limitations had run on the

Government’s ability to collect the $11,860,016, because the Government had to

file its claim within six years of Renda’s breach of contract. In addition, Renda

argues that the applicable administrative proceedings came to an end on

November 26, 2003, when the one-year time period within which Renda could

appeal the CO’s decision elapsed. Because Renda did not timely appeal, it

argues that the CO’s decision became “final and conclusive and not subject to

review by any forum, tribunal, or Government agency” one year after the

decision issued. 41 U.S.C. §§ 605(b), 609(a). According to Renda, its efforts to

collaterally attack the CO’s decision by amending its complaint in separate CFC

litigation cannot constitute “administrative proceedings required by contract or

law.” 28 U.S.C. § 2415(a) (emphasis added). The Government responds that the

claim it seeks to enforce is not the contract claim, but the CO’s decision. Thus,

the six-year statute of limitations began to run when the CO issued that

decision, not when Renda breached the contract, because the right to sue did not

accrue until the CO had determined that Renda owed the Government

$11,860,016. Alternatively, the Government contends that Renda’s Court of

Federal Claims and Federal Circuit litigation constitute applicable

administrative proceedings because Renda was attempting to undo the CO’s

decision during those proceedings.

Renda is correct that, traditionally, a contract claim accrues when the

contract is breached. See FDIC v. Belli, 981 F.2d 838, 840 (5th Cir. 1993)

(stating that “the ordinary usage of the term ‘accrues’ is that a cause of action

‘accrues’ when ‘it comes into existence’” (citation omitted)); Phillips Petroleum

8

Case: 10-41296 Document: 00511725216 Page: 9 Date Filed: 01/13/2012

No. 10-41296

Co. v. Lujan, 4 F.3d 858, 861 (10th Cir. 1993) (holding that the government’s

right of action accrued on the date of breach); United States v. Kass, 740 F.2d

1493, 1497 (11th Cir. 1984) (same); see also 48 C.F.R. § 33.201 (“Accrual of a

claim means the date when all events, that fix the alleged liability of either the

Government or the contractor and permit assertion of the claim, were known or

should have been known.”). However, we agree with the district court that it

makes little sense to hold that the Government’s cause of action for Renda’s

breach of contract and separate cause of action to enforce a decision regarding

that breach accrued on the same date. The only appellate court to deal with a

case on-point came to the same conclusion. In United States v. Suntip, the Ninth

Circuit held that the statute of limitations did not bar a suit to enforce a CO’s

decision because the right of action did not accrue until the CO issued its

decision on the contract claim. 82 F.3d 1468, 1475 (9th Cir. 1996).

Distinguishing between a claim on the contract and an action to enforce a CO’s

decision, the court noted that “the government’s present suit is similar to a suit

on a judgment,” id. at 1474, and depended “upon its contracting officers’

decisions being final, conclusive, and not subject to further challenge on the

merits,” id. at 1475. Because “the government cannot take legal action on its

claim until it first makes it the subject of a decision by a contracting officer[,] .

. . . [t]ime cannot run against the government until it is procedurally possible for

it to sue.” Id. at 1476 (internal quotation marks and citations omitted); see also

United States v. Kasler Elec. Co., 123 F.3d 341, 344 (6th Cir. 1997) (citing Suntip

and noting that “the government merely sought summary enforcement of an

order that it contends is final and unreviewable”). Therefore, because the

Government filed suit within six years of the CO’s decision that Renda owed the

Government $11,860,016, its suit was timely.

Our reading of the statute of limitations in 28 U.S.C. § 2415(a) (and that

of the Ninth Circuit) is admittedly imperfect. If the Government has six years

9

Case: 10-41296 Document: 00511725216 Page: 10 Date Filed: 01/13/2012

No. 10-41296

from a CO’s decision to file a suit to enforce it, then the savings clause serves no

purpose in a situation such as this one. This is because the CO’s decision

becomes final one year after it is rendered if it is not timely appealed, such that

the savings clause, which allows the Government one year from a final decision

in an applicable administrative proceeding to file suit, saves nothing where the

Government already has six years from the date of the decision to file. See

United States v. Am. States Ins. Co., 252 F.3d 1268, 1273 (11th Cir. 2001)

(“Allowing the Government six years from a final decision in which to sue would

render this one-year provision meaningless.”). Even in situations where a party

appeals the CO’s decision, it is unlikely that it will routinely take the CFC longer

than six years from the date of that decision (rather than the date of breach) to

rule on the appeal. For instance, in the separate action that forms the basis for

Count II of this suit, the CFC issued its decision on July 28, 2005–slightly more

than four years after the contract modification issued by the CO on March 14,

2001. See Renda Marine, Inc. v. United States, 66 Fed.Cl. 639 (Fed. Cl. 2005).

While a further appeal to the Federal Circuit could conceivably draw the dispute

out beyond six years, it is not likely that an appeal to an Article III court

constitutes an “applicable administrative proceedin[g].” § 2415(a). See S.Rep.

No. 89–1328, at 2504 (1966) (stating that the savings clause was necessary

because “[a]n administrative proceeding ordinarily consumes a considerable

period of time) (emphasis added); Suntip, 82 F.3d at 1476-77 (finding that an

action in the Court of Federal Claims is an “administrative proceeding,” in part

because the Federal Courts Improvement Act of 1982 changed the CFC from an

Article III to an Article I court). Nevertheless, Congress chose the language in

§ 2415(a), allowing the Government to file suit “within six years after the right

of action accrues or within one year after final decisions have been rendered in

applicable administrative proceedings required by contract or by law, whichever

is later,” and there may be cases in which related administrative proceedings

10

Case: 10-41296 Document: 00511725216 Page: 11 Date Filed: 01/13/2012

No. 10-41296

stretch out beyond six years from a CO’s decision. Furthermore,

notwithstanding the identified difficulties with the statute, Congress provided

six years for the Government to bring a claim. The Government cannot seek to

enforce a CO’s decision until that decision has been rendered, nor do the federal

courts have jurisdiction until that time. Thus, this suit clearly falls within the

statute of limitations.

While we ultimately agree with the district court’s holding that the

Government’s suit was timely, we do not agree that administrative proceedings

relating to Count I terminated when the Federal Circuit affirmed the CFC’s

denial of Renda’s motion to amend its complaint in the separate, ongoing

litigation. Such a collateral attack by Renda was not “required by law,”

§ 2415(a), and the CO’s decision became final and enforceable one year after its

issuance, when Renda failed to timely appeal. Consequently, the savings clause

would have granted the Government only one year from that date to file suit, or

until November 26, 2004. Furthermore, the district court found that the

Government’s suit was timely because it was filed within one year of the Federal

Circuit’s ruling, but as discussed above, we are not convinced that an appeal to

the Federal Circuit constitutes “an applicable administrative proceedin[g].” Id.

Consequently, we hold that the Government’s suit to collect the $11,860,016

owed by Renda was timely because it was filed within six years of the CO’s

decision, rendered on November 26, 2002.

C. Renda’s Set-Off Claim

Renda argues that even if Count I is not barred by the statute of

limitations, the Government’s recovery should be reduced by $259,840.85, an

amount Renda claims the Corps withheld as a set-off from amounts earned by

and owed to Renda. The district court rightly noted that offset is an affirmative

defense, Giles v. Gen. Elec. Co., 245 F.3d 474, 494 n.36 (5th Cir. 2001), such that

it is Renda’s burden to “establish beyond peradventure all of the essential

11

Case: 10-41296 Document: 00511725216 Page: 12 Date Filed: 01/13/2012

No. 10-41296

elements of the defense,” Addicks Serv., Inc. v. GGP-Bridgeland, LP, 596 F.3d

286, 293 (5th Cir. 2010) (emphasis original) (quotation marks and citations

omitted). According to the district court, the CO’s decision letter stated that the

$259,840.85 was an amount remaining in retainage, and “[n]othing in the

contracting officer’s decision letter indicates that this amount is intended to

offset the amounts claimed in the Corps’ $11,860,016.00 counterclaim.”

Therefore, in order to consider Renda’s claim, the district court would have had

to revisit the merits of the CO’s decision, which it did not have jurisdiction to do.

See Kasler, 123 F.3d at 344 (stating that appeal to an agency board or the CFC

are the only options for challenging a CO’s decision, and “the merits of the

contracting officer’s decision itself were not within the jurisdiction of the district

court”).

We agree with the district court that the CO’s decision letter does not

expressly state that the $259,840.85 the Government kept in retainage was

intended to offset the $11,860,016 that Renda owed the Government. The letter

mentions the retainage in the section on liquidated damages. It states that “the

Government is withholding approximately $259,840.85 in retainage,” and in the

following sentence says that it is also “withholding $236,016.00 in liquidated

damages.” Those liquidated damages are then calculated into the $11,860,016

total that Renda owes. While the retainage and damages related to the claim

are discussed together, the CO never clarifies whether the retainage should be

applied to the total owed by Renda. Thus, as the district court held, it is not

obvious from the letter whether the retainage was an offset, and any effort to

make that determination would require a revisitation of the merits of the CO’s

decision. Renda did not appeal that decision, and cannot now collaterally attack

it through this federal suit. Therefore, because Renda has failed to prove its set-

off claim “beyond peradventure,” we affirm the district court’s denial of its

motion for partial summary judgment on this claim.

12

Case: 10-41296 Document: 00511725216 Page: 13 Date Filed: 01/13/2012

No. 10-41296

D. Count II

In Count II, the Government seeks to enforce the CFC’s decision that the

Government overpaid Renda $3,083,833. Renda argues that the district court

lacked subject matter jurisdiction over Count II because the Government never

made an affirmative claim to the CO for repayment of the $3,083,833, nor did

the Government make a counterclaim for that amount in the CFC. Because only

Renda’s claim for additional compensation was at issue in the CFC, and the CO

did not issue a written decision awarding any amount to the Government, Renda

argues that the district court lacked jurisdiction over the Government’s suit.

The district court rejected Renda’s argument that the Government had to

file its own administrative claim to recover the $3,083,833. As the district court

noted, the CDA requires that “[a]ll claims by a contractor against the

government related to a contract shall be in writing and shall be submitted to

the contracting officer for a decision[;] [a]ll claims by the government against a

contractor relating to a contract shall be the subject of a decision by the

contracting officer.” 41 U.S.C. § 605(a). Thus, the language of the statute

differentiates between the two parties, requiring that a contractor submit any

claim to the CO, while a claim by the government must only be the subject of a

CO’s decision. The district court therefore ruled that the Government did not

need to file a separate claim to recover the money it had already paid Renda,

because the Government’s claim for repayment had been “the subject of a

decision by the contracting officer.” Accordingly, no further action was required

on the Government’s part.

In United States v. T & W Edmier Corp., 465 F.3d 764 (7th Cir. 2006),

cited by the district court in support of its decision, the Seventh Circuit held that

the CDA “does not require the United States to file an administrative claim in

any situation, as far as we can make out,” including “in order to recover an

overpayment that ensues from a decision by the Board that the United States

13

Case: 10-41296 Document: 00511725216 Page: 14 Date Filed: 01/13/2012

No. 10-41296

owes less than the contracting officer awarded.”4 Id. at 766. Instead, the

Seventh Circuit found that “[w]hat is required when the government seeks a

payment from the contractor is not an independent claim, but a decision .” Id.

The court in Edmier ruled that “the Contract Disputes Act allows the appellate

board to make an independent decision and decrease as well as increase the

award” granted by a CO. Id. Because a dispute over a CO’s decision thus

receives “full administrative consideration,” the Seventh Circuit held that “there

is no reason to rerun the process before the United States may collect any net

balance in its favor.” Id. But cf. Wilner v. United States, 26 Cl. Ct. 260, 279

(1992) (finding that the CDA “requires such a written claim by the Government

as a prerequisite to the Government’s assertion of a claim for affirmative relief

[seeking repayment of sums already paid]”), vacated on other grounds and

remanded, 24 F.3d 1397 (Fed. Cir. 1994).5 Other courts have similarly endorsed

the CFC’s ability to either increase or decrease the appealed CO’s award. See

Assurance Co. v. United States, 813 F.2d 1202, 1206 (Fed. Cir. 1987) (“We must

conclude from the face of the Disputes Act that a contract appeals board can,

with respect to a contracting officer’s decision that has been appealed to it,

reduce as well as increase the award made by that contracting officer.”);

Transamerica Ins. Corp., 28 Fed. Cl. at 422 (“Furthermore, on appeal ‘the

contracting officer’s award is not to be treated as if it were the unappealed

4

Edmier involved an appeal to the Armed Services Board of Contract Appeals. The

CDA authorizes appeals of a CO’s decision to either an agency board, or to the Court of Federal

Claims. See 41 U.S.C. § 606(a)-(b). The CDA treats such appeals equally, and subjects them

to the same requirements.

5

The district court distinguished Wilner on the basis that “the court determined the

sums sought by the government were the result of unilateral modifications, not the contracting

officer’s subsequent final decision that had been appealed,” while “the CFC considered Renda’s

Flare Area claim (the modification and claim for additional relief) as a unitary claim, not

separate decisions by the contracting officer.” We agree that Wilner presented a situation

different than that here, where the CO’s entire decision is at issue.

14

Case: 10-41296 Document: 00511725216 Page: 15 Date Filed: 01/13/2012

No. 10-41296

determination of a lower tribunal which is owed special deference on appeal . . .

[and a reviewing factfinder may] reduce as well as increase the award made by

the contracting officer . . . .’” (quoting Assurance Co., 813 F.2d at 1206)).

Here, Renda initiated its claim for $4,691,688, and that claim was subject

to a decision by a CO. When Renda filed suit in the CFC seeking additional

money, the CFC considered the entire amount awarded pursuant to the

modification, and ultimately determined that Renda was entitled to less than the

CO had granted. We agree with the CFC’s determination that Renda’s appeal

put its entire award at issue. Furthermore, we find that the district court’s

reading of the statute, mirroring the Seventh Circuit’s interpretation in Edmier,

is in keeping with one of the policies animating the CDA: efficiency. See S.Rep.

No. 95-1118, at 3 (stating that “the complexity of government procurement

demands the enactment of a more efficient procedure”). It would be wholly

inefficient to require the Government to submit a separate claim to a CO for

repayment of a sum to which the CFC and Federal Circuit have already ruled

the Government is entitled, especially since the CO would be bound by those

decisions.

Consequently, we hold that the district court had subject matter

jurisdiction over the Government’s claim for repayment of the $3,083,833 it had

overpaid Renda, and the district court properly granted judgment in the

Government’s favor on that claim.

IV. CONCLUSION

For the foregoing reasons, the judgment of the district court is

AFFIRMED.

15

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.