Opinion

ECC International Constructors, LLC

Court
Armed Services Board of Contract Appeals
Filed
Jan 6, 2022
Status
Published
On the bench
McIlmail
Cited by
0 cases
Authority
More cited than 5.2%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of - )

)

ECC International Constructors, LLC ) ASBCA No. 59586

)

Under Contract No. W912ER-10-C-0054 )

APPEARANCES FOR THE APPELLANT: R. Dale Holmes, Esq.

Michael H. Payne, Esq.

Cohen Seglias Palla Greenhall & Furman PC

Philadelphia, PA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Sarah L. Hinkle, Esq.

Geoffrey A. Mueller, Esq.

Matthew Tilghman, Esq.

Kathryn G. Morris, Esq.

Engineer Trial Attorneys

U.S. Army Engineers District, Middle East

Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

The parties each claim $940,274 in liquidated damages ostensibly withheld by the

government and arising from this contract for the design and construction of a military

compound in Afghanistan (see gov’t br. at 40; app. br. at 111, 117). We have issued

opinions in this and related appeals, and we assume familiarity with those opinions. ECC

Int’l Constructors, LLC, ASBCA No. 59643, 21-1 BCA ¶ 37,967 at 184,392; ECC Int’l

Constructors, LLC, ASBCA No. 59586, 21-1 BCA ¶ 37,862, reconsideration denied,

21-1 BCA ¶ 37,897; ECC Int’l Constructors, LLC, ASBCA No. 59138 et al., 19-1 BCA

¶ 37,252; ECC Int’l Constructors, LLC, ASBCA No. 59138 et al., 19-1 BCA ¶ 37,281.

The government has the burden of proving that the Board possesses jurisdiction to

entertain its claim for liquidated damages by demonstrating that the assessment of

liquidated damages is memorialized in a timely final decision by a contracting officer.

See ASFA Int’l Constr. Indus. & Trade, Inc., ASBCA No. 57880, 14-1 BCA ¶ 35,736

at 174,909; Parsons Evergreene, LLC, ASBCA No. 57794, 12-2 BCA ¶ 35,092

at 172,347. The government does not demonstrate that a contracting officer has issued a

final decision assessing liquidated damages (see gov’t br. at 2-3; gov’t reply at 1-3, 8, 29,

31). The government’s post-hearing reply brief references a January 18, 2014 contracting

officer’s final decision (gov’t reply at 1 (citing R4, tab 2)), but that decision addresses

appellant’s request for a time extension and more than $800,000; that decision does not

assess liquidated damages against appellant (see R4, tab 2 at 1, 12; tab 67 at 1, 3; 70 at 1).

Because the government does not satisfy its burden to establish our jurisdiction to

entertain its claim to liquidated damages, that claim is dismissed for lack of jurisdiction.

See ASFA, 14-1 BCA ¶ 35,736 at 174,910; Parsons Evergreene, 12-2 BCA ¶ 35,092

at 172,347. Consequently, what the government says is $940,274 in liquidated damages

is actually, at least at this point, a contract balance presumably owed to appellant.

Accordingly, we see no liquidated damages issue to adjudicate on its merits, and

dismiss appellant’s claim to liquidated damages, and its request for a 400-day extension

of the contract completion date in support of that liquidated damages claim (see app. br.

at 111-12), as moot, without prejudice. See Combat Support Assoc., ASBCA

Nos. 58945, 58946, 16-1 BCA ¶ 36,288 at 176,974. In view of this and our other

opinions related to this appeal, we find it unnecessary to address any of the parties’

remaining arguments. See Kellogg Brown & Root Servs., Inc. v. Sec’y of the Army,

973 F.3d 1366, 1370 (Fed. Cir. 2020); Lowder v. Dep’t of Homeland Security, 504 F.3d

1378, 1383 (Fed. Cir. 2007).

Dated: January 6, 2022

TIMOTHY P. MCILMAIL

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Vice Chairman

Acting Chairman Armed Services Board

Armed Services Board of Contract Appeals

of Contract Appeals

2

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 59586, Appeal of ECC

International Constructors, LLC, rendered in conformance with the Board’s Charter.

Dated: January 10, 2022

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

3

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.