Opinion

Lodge Construction, Inc. v. United States

Court
United States Court of Federal Claims
Filed
Jan 10, 2022
Status
Published
On the bench
David A. Tapp
Cited by
0 cases
Authority
More cited than 27.1%

explaining how to count False Claims Act violations

How later courts described this case

  • explaining how to count False Claims Act violations
  • misrepresentations render a claim false to the “extent of the exaggeration.”
  • “It is apparent that this reckless disregard standard prevents defendants from simply pointing to confusion over invoices and billing records as a complete defense.”
  • holding that a contractor cannot escape fraud claims by feigning ignorance that would permit double-billing

Written by the judges who cited it.

The opinion

In the Cited States Court of Federal Claims

No. 13-499; 13-800

Filed: January 10, 2022

LODGE CONSTRUCTION, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant.

Michael H. Payne, Cohen Seglias Pallas Greenhall & Furman, Philadelphia, PA, and Edward

Parrott, Watt, Tieder, Hoffar & Fitzgerald, L.L.P., McLean, VA, for Plaintiff.

John H. Roberson, Senior Trial Counsel, with whom were Steven Hough, Trial Attorney, Joana

Cristei, Trial Attorney, Deborah A. Bynum, Assistant Director, Martin F. Hockey, Jr., Acting

Director, Commercial Litigation Branch, and Brian M. Boynton, Acting Assistant Attorney

General, Civil Division, U.S. Department of Justice, Washington, D.C., for Defendant.

POST-TRIAL OPINION AND ORDER

TAPP, Judge.

“Men must turn square corners when they deal with the Government.” Rock Island A. &

L.R. Co. v. United States, 254 U.S. 141, 143 (1920) (Holmes, J.). In this case, the Court is

presented with whether Lodge Construction, Inc. (“Lodge”) fraudulently submitted cost claims

to the United States. At trial, the United States showed that Lodge misrepresented the value of

certain equipment, billing the United States for operating four off-road dump trucks collectively

valued at over $3,500,000 when the trucks were actually worth less than $100,000 combined.

The United States also demonstrated that Lodge designed a ratio to inflate its total equipment,

labor, and overhead costs—a ratio through which Lodge, at times, billed taxpayers at rates

between $2,000 and $22,000 per hour for work performed by a single laborer or piece of

equipment. Lodge also manipulated that already-dubious ratio by seeking compensation for work

performed on days outside of the claim period, often with nominal expenditures of manpower,

effort, and resources. Those examples and others support the Court’s conclusion that Lodge

committed two violations of the False Claims Act when it certified and submitted two false

claims to the U.S. Army Corps of Engineers (“the Army Corps”).

This case should serve as a cautionary tale to government contractors. For those who seek

to recoup sums of money from the Federal Government, and thus burden taxpayers, rudimentary

recordkeeping and approximated claims are likely insufficient. When job cost data and

recordkeeping are inaccurate, the claim will inevitably contain errors and the line between

negligence and reckless disregard for the truth becomes vanishingly thin. Cross it, and the

government contractor’s claim becomes fraudulent as a matter of law, a designation that carries

financial, practical, and stigmatic consequences. Here, while some elements of Lodge’s claims

may reflect nothing more than slapdash formulae, overwhelming evidence establishes that

substantial portions of those claims are patently deceitful.

It is now apparent that Lodge failed to earnestly undertake the obligations of claim

certification: to ensure a claim submitted for payment is accurate and truthful. Lodge failed to

accurately identify the equipment it used and support the valuation of that equipment with proper

documentation in an act of deceit to increase its claim. Lodge used a dubious metric, riddled with

errors, to measure its inefficiencies and dishonestly inflate Lodge’s claims. Lodge employed an

artifice through which it sought to inflate costs of its equipment by reporting operation hours to

the Army Corps differently than it recorded them internally. And finally, Lodge sought double

recovery of costs for which Lodge assumed the risk of increased operation.

Despite originally admitting its claims contained errors, Lodge later reversed course and

doubled down on its claims. Perhaps as a feature of the latter strategy, Lodge made clear that its

claims were not the product of a mistake but were intentional. However, Lodge’s claims were

also false. Lodge knew or should have known them to be false. And when a contractor acts

intentionally or with reckless disregard for accuracy, submitting a false claim for payment is

fraud.

I. Background and Procedural History

This case is procedurally complex. A brief overview will provide context to the findings

of fact and conclusions of law. The dispute stems from a construction project to rehabilitate a

levee in South Florida. The project was known as “Site 1 Impoundment Phase I” or simply “Site

1.” Although Lodge’s performance on that project is not directly at issue here, the Court

reiterates the overview it provided in its recent opinion, Lodge Constr., Inc. v. United States, 153

Fed. Cl. 430 (2021).

In August 2010, the Army Corps awarded Lodge a competitively-bid fixed price contract

to rehabilitate a levee in Palm Beach County—part of the Army Corps’ broader “Everglades

Update” restoration mission. The levee rehabilitation work required removal of the top layers of

the existing levee slopes and replacement of those layers with soil cement and other mechanical

means of shoring up the levee. (Joint Stipulation of Facts (“JSOF”) 4 2, ECF No. 43). The levee

was adjacent to the L-40 canal.

L-40 CAMEL

io

CANTRECTOR

STAGING 4REA

PHASE 1 DEWATERING

EFFLUENT STORAGE

AERA (S00 ACRES)

SITE 1 IMPOUNDMENT

CONTRACTOR

STAGING AREA

LIMITE: OF

CONSSTPRLIC THD

HLL SEORS CANAL

Lodge Construction, Inc. v. United States, Case No. 13-499, Lodge’s MSJ on Liability Ex. C, ECF No. 19-2

Lodge divided the project area into six numbered sections, starting with Section 1 at the

east end of the site. The project also required subsurface work, so Lodge constructed a temporary

cofferdam so that it could perform that subsurface work “in the dry.”' Lodge performed work a

few feet above the groundwater table, so the project required significant dewatering efforts.

Pursuant to the solicitation, Lodge was required to submit a design based on the Army

Corps’ subsurface geotechnical site inspection and analysis. After revisions, the Army Corps

accepted Lodge’s final cofferdam design proposal in July 2011, and Lodge began work soon

thereafter. In mid-March 2012, water breached two sections of the cofferdam’s sheet pile wall in

Section 2, flooding the project site.” After the failure, the Army Corps retroactively disapproved

' A cofferdam is “a watertight enclosure from which water is pumped to expose the bottom of a

body of water and permit construction[.]” Cofferdam, Meriam Webster’s Online Dictionary,

https://www.merriam-webster.com/dictionary/cofferdam (last visited Jan. 7, 2022). For an

overview of the Army Corps’ cofferdam and wet construction techniques, see generally Patrick

O’Bannon, Working in the Dry: Cofferdams, In-River Construction, and the United States Army

Corps of Engineers (United States Army Corps of Engineers, Pittsburg District, 2009) available

at https://usace.contentdm.oclc.org/digital/collection/p16021coll4/id/156/ (last visited Jan. 7,

2022).

* Lodge maintains that the breach was caused by a differing site condition. The Army Corps,

however, maintains that Lodge’s cofferdam design was defective. Resolution of that issue is not

ripe.

Lodge’s cofferdam design. Lodge and the Army Corps corresponded over the next few months,

and the Army Corps eventually sent Lodge a Cure Notice, demanding Lodge submit a revised

cofferdam design by May 29, 2012 or be terminated for default.

Later in the summer of 2012, Lodge submitted three certified claims to the Contacting

Officer. First, on June 21, 2012, Lodge certified and submitted its “Design Claim” related to the

Army Corps’ retroactive disapproval of Lodge’s cofferdam design, stating:

I [Cabot Lodge Dunn] certify that the claim is made in good faith; that the

supporting data are accurate and complete to the best of my knowledge and

belief; that the amount requested accurately reflects the contract adjustment

for which [Lodge] believes the Government is liable; and that I am duly

authorized to certify the claim on behalf of [Lodge].

(JX104.008; JSOF 15). The “Design Claim” sought $679,279 in compensation and 63

additional calendar days to complete the work on Site 1. (JSOF § 16). The Contracting Officer

denied Lodge’s Design Claim on October 29, 2012. Ud. at J 17).

On June 26, 2012, Lodge, using identical language to its prior claim, certified and

submitted its “Dewatering Claim” seeking $3,282,123 in compensation and 91 additional

calendar days to complete the work. (JX108.53; JSOF ff 18, 20). Lodge premised this claim on

three alleged conditions that impacted performance: (1) the failure of impounded water to

percolate away from the project; (2) constructive changes the Army Corps made to the contract

specifications; and (3) a differing site condition.* (JSOF § 19). The Dewatering Claim asserted

that inefficiencies attributable to those conditions were the Army Corps’ responsibility; Lodge

measured those inefficiencies using a ratio that it multiplied by a cost pool including operation

costs for equipment such as off-road dump trucks, a soil cement batch plant, and dewatering

pumps. (/d. at § 21). The Contracting Officer denied Lodge’s Dewatering Claim on December

28, 2012. (Id. at § 22).

On July 6, 2012, Lodge, again using the identical language of its earlier claims, certified

and submitted its “Wall Breach Claim” seeking $1,805,760 in compensation, alleging that a

differing site condition caused the failure of Lodge’s cofferdam design. (Case No. 13-800,

Compl. J 66-79, ECF No. 1; Case No. 13-500, Lodge’s Mot. for Leave to Amend at 3, ECF

No. 66). Lodge’s Wall Breach Claim sought compensation for Lodge’s estimated costs to fix the

cofferdam’s sheet pile failures. (Case No. 13-800 Compl. {] 66-79). The Contracting Officer

denied Lodge’s Wall Breach Claim on October 15, 2012. (USA MSJ on Fraud Ex. 11, ECF No.

20-4 (the Contracting Officer’s final decision letter)).

The Army Corps ultimately terminated Lodge for default on July 23, 2012, and this

litigation followed. Lodge, together with its surety (The Hanover Insurance Company), asserted

causes of action that included each of these three Contract Disputes Act (“CDA”) claims in

separate complaints spanning four case numbers: Case Nos. 13-499, 13-500, 13-800, and 16-

3 Percolation in this context refers to the tendency of water to pass through soil under the

impoundment areas.

1187. Hanover Ins. Co. v. United States, 134 Fed. Cl. 51, 56 (2017). The Court consolidated

these cases under Lead Case No. 13-500. /d. at n.1. On April 5, 2017, Lodge moved for leave to

amend its Complaint in Case No. 13-800 to withdraw its Wall Breach Claim and increase its

request for damages associated with its Design Claim to include costs incurred after Lodge had

submitted its claim. Jd. at 58. Lodge explained that “the [Army Corps’ ] termination of the

contract prevented it from performing the work and incurring the costs set forth in its wall breach

claim, and thus the wall breach claim should not have been included in the original [Case No.

13-800] complaint.” /d. The Court granted Lodge’s request and Lodge filed an amended

complaint? in Case No. 13-800 on April 27, 2017. /d. The next day, the United States answered

in all four cases, asserting as an affirmative defense that Lodge’s claims (and those of its

sureties) were “barred by illegality as a result of submitting a false claim.” /d. The United States

also requested, and the Court granted, leave to assert fraud counterclaims against Lodge, seeking

forfeiture, damages, and civil penalties pursuant to the Special Plea in Fraud defense, 28 U.S.C.

§ 2514; the anti-fraud provision of the CDA, 41 U.S.C. § 604; and the False Claims Act, 31

U.S.C. § 3729. Hanover Ins. Co., 134 Fed. Cl. at 58.

The United States’ counterclaims accused Lodge of fraud in its submissions to the

Contracting Officer and fraud in maintaining those claims in this Court. Specifically, the United

States alleged fraud related to three categories of conduct: (1) false delay-day costs; (2) double-

billing and exaggerated equipment costs; and (3) improperly passed-through claims of a

subcontractor. (See, e.g., Case No. 13-500, Def.’s Am. Answer and Counterclaims at 16, 19, 21,

ECF No. 95). Over the next two years, the parties conducted discovery on the fraud issues. (See,

e.g., Case No. 13-500, Scheduling Order, ECF No. 153 (setting final deadlines for fraud

depositions and expert reports)). This case was transferred to the undersigned on December 3,

2019. (ECF No. 16).

On October 26, 2020, by agreement of the parties, the Court dismissed certain claims by

and against Lodge’s surety. (Case No. 13-500, Order Transferring, ECF No. 204). In that Order,

the Court also severed the cases that involved Lodge’s surety and transferred those two cases,

Case Nos. 13-500 and 16-1187, to the District of Massachusetts, designating Case No. 13-499 as

the new lead case. (/d.). The Court then directed the parties to file partial summary judgment

briefs regarding both Lodge’s affirmative CDA claims against the United States and the United

States’ fraud counterclaims against Lodge. (See Docketing Order, ECF No. 18).

On April 14, 2021, this Court denied summary judgment on all issues and dismissed the

United States’ counterclaim under 41 U.S.C. § 604 for lack of subject matter jurisdiction. Lodge

Constr., Inc., 153 Fed. Cl. at 440. The Court then set this matter for trial on two of the three

fraud allegations—the false delay-day costs and the exaggerated equipment costs—setting aside

the pass-through claims issue for further proceedings. (ECF Nos. 32, 47).

Beginning August 2, 2021, the Court conducted a trial on the two fraud issues. Trial

* Lodge filed several amended complaints across the various case numbers pertaining to this

litigation. Here, the Court refers to the Amended Complaint Judge Sweeney permitted to be filed

in Case No. 13-800—the case she identified as “Lodge I?’—but docketed as ECF No. 74 in Case

No. 13-500.

concluded on August 6. On August 30, 2021, the parties simultaneously filed post-trial briefing.

(USA Trial Brief, ECF No. 84; Lodge Trial Brief, ECF No. 85).

Il. Findings of Fact

Lodge’s alleged fraudulent conduct can be broken down into four categories. First, the

United States asserts that Lodge fraudulently overvalued its Euclid off-road dump trucks, thereby

inflating the costs Lodge billed to the Army Corps. Second, the United States alleges that Lodge

fraudulently inflated its costs by manipulating both the numerator and denominator of its

“inefficiency ratio”—an idiosyncratic numerical value that Lodge multiplied by a “cost pool” to

capture alleged inefficiencies due to water on the project site. Third, the United States asserts

that Lodge double-billed the Army Corps for costs relating to the ownership and operation of its

“batch plant,” a concrete manufacturing facility constructed on site. Fourth, the United States

alleges that Lodge fraudulently included the operating costs of its dewatering pumps in its

certified Dewatering Claim even though Lodge was already compensated for those costs through

a fixed monthly price arrangement.

During trial, the Court heard testimony from seven fact witnesses—including Lodge

employees, independent contractors retained by Lodge, representatives from the Army Corps and

Lodge’s surety—and four expert witnesses. Three trial witnesses were central to the Site 1

project and Lodge’s certified claims: Cabot Dunn, Katrin Callaway, and William Gore.

Lodge is directed by Cabot “C.L.” Dunn, the founder, president, and controlling

shareholder of Lodge. (Dunn, TR at 813:13-1075:15).° By January of 2012, Mr. Dunn was the

sole shareholder of Lodge.° The company did not undertake any significant financial transactions

without his approval. (/d. at 814:13—-17, 821:20-23). At the time of Lodge’s performance on Site

1, Mr. Dunn had been at the company’s head for 25 years. (/d. at 814:8—12). Through Lodge, Mr.

> A transcript of the trial is docketed at ECF Nos. 78-82. The Court will reference the witness’s

name in trial citations to reflect their time on the stand, but quotations may reflect questions or

statements of counsel where appropriate. Discussions between attorneys and the Court will be

noted as a “Colloquy.”

° In this regard, the acts, knowledge, and intent of Mr. Dunn are effectively equivalent to the

acts, knowledge, and intent of Lodge as a corporate entity, organized under Florida law. Davies

v. Owens-Illinois, Inc., 632 So. 2d 1065, 1066 (Fla. Dist. Ct. App. 1994) (“It is well settled that

the actions of corporate directors and officers are attributable to the corporation itself”); see JJ

Corp. v. United States, 576 F.2d 327, 338 (Fed. Cir. 1978) (holding that in tax cases, “[t]he

corporate purpose or intent [1s] measured by the purpose or intent of its board of directors and

officers[.]”); see also United States v. Philip Morris USA Inc., 566 F.3d 1095, 1118 (D.C. Cir.

2009) (“[T]to determine whether a corporation made a false or misleading statement with

specific intent to defraud, we look to the state of mind of the individual corporate officers and

employees who made, ordered, or approved the statement.”); (see also Compl. at ¢ 1, ECF No.

1). The Court does not, at this stage, make any determination as to whether the corporate entity

may be disregarded. Whether or not the corporate veil may be pierced requires a more searching

inquiry. That issue is not before the Court.

Dunn had substantial experience performing construction contracts valued in the tens of millions

of dollars; over the course of his career, he has worked on hundreds of millions of dollars’ worth

of construction projects. (Ud. at 814:18-815:7). To say Mr. Dunn was an experienced

businessman in the field of construction is an understatement.

Although concepts utilized in private construction projects and government construction

projects largely overlap, Mr. Dunn’s experience with government contracts was limited in some

respects. However, Mr. Dunn was not a novice federal contractor. Mr. Dunn had experience with

submitting applications for payment to government entities. (Dunn, TR at 816:7—14). He

previously worked on several heavy site civil construction projects for government entities,

including the construction of several post offices and projects for the South Florida Water

Management District. (/d. at 816:24—817:21). At the same time Lodge worked on Site 1, Lodge

constructed a library in downtown Fort Myers pursuant to another federal contract. (/d. at 818:4—

21). Site 1 was the first project in which Mr. Dunn had bought or sold heavy construction

equipment.’ (/d. at 819:2—25). Mr. Dunn signed and certified each of the claims Lodge submitted

to the Army Corps. (JSOF § 23).

Katrin Callaway was also central to the Site 1 project and Lodge’s claims. Ms. Callaway

worked for Lodge as an independent contractor. (Callaway, TR at 214:13-505:15). Ms. Callaway

earned an oceanic engineering degree in 1995 and began working with construction firms in

1996. Ud. at 216:9-16). With the South Florida Water Management District, Ms. Callaway

learned how to use Primavera, a construction scheduling software program. (/d. at 217:2—-13).

Lodge retained Ms. Callaway in 2010 to prepare construction schedules for the Site 1 project

using Primavera. (/d. at 218:10—219:13). She prepared Lodge’s original baseline schedule and

modifications throughout the project. (/d.). Ms. Callaway also assisted in preparing the project

updates and, in concert with Mr. Dunn and Paul Perkins, a retained construction consultant with

Army Corps experience, prepared the inefficiency ratio portion of Lodge’s Dewatering Claim.

(Id. at 219:2—5, 223:14—224:3).

Lastly, beginning in 2011, William “Bill” Gore served as the project manager for Lodge.

(Gore, TR at 513:20-656:8). Mr. Gore earned a civil engineering degree, has significant civil

construction experience, and helped Lodge prepare its bid for the Site 1 contract. /d. at 516:8-

23). As the project manager for Site 1, Mr. Gore estimated the cost of dewatering for the project,

particularly with respect to the dewatering pumps. (/d. at 516:24—517:14). During the project,

Mr. Gore was responsible for preparing and submitting pay estimates to the Army Corps. (/d. at

522:5—14). Mr. Gore left Lodge in 2012 and did not directly prepare Lodge’s certified claims but

did assist through discussions with Paul Perkins and Cabot Dunn. (/d. at 518:2—25, 519:3-

52:19). In fact, Mr. Dunn “made a conscious decision” to exclude Mr. Gore from reviewing the

final version of the Dewatering Claim. (/d. at 521:1—9).

Tn this context, the parties understood “heavy equipment” to mean construction vehicles such as

bulldozers, dump trucks, and backhoes.

A, Euclid Dump Trucks

Lodge used four oversized off-road “Euclid” dump trucks, at least one of which was

more than 20 years old and the newest was more than 15 years old, to move material for this

project. Lodge included costs associated with the use of those trucks in its Dewatering and

Design claims. (JSOF { 33; see, e.g., JX109.116 (Dewatering Claim costs); JX104.146 (Design

Claim costs)). Specifically, Lodge’s Euclid truck costs total $229,459 of the $1.6 million owned

equipment cost pool. (JX119.016, .110). Lodge arrived at this total by billing each of its four

Euclids to the Army Corps at operating rates of $133.89 per hour and standby rates of $31.71 per

hour. (JSOF ¥ 35). Lodge derived those rates by referencing the U.S. Army Corps of Engineers

equipment manual (“USACE Manual”). (/d. at | 36; JX001 (USACE Manual)). However, in

referencing the manual, Lodge compared the rates it derived from third-party equipment costing

software program (Equipment Watch) to USACE Manual rates without regard to whether the

rates corresponded to comparable equipment. More bluntly, the rates Lodge gleaned from the

USACE Manual were for equipment that materially differed from the Euclids.

Lodge first utilized Equipment Watch, a job costing software program used within the

construction industry, to estimate the rates for its Euclids. (JX001.411; Dunn, TR at 1014:2-12,

1014:21-1015:1; PX116). Equipment Watch provided an operating rate of $138.27 per hour for

the Euclids, which Lodge used in its project costing ledger. (JX118.153). Lodge then compared

the Equipment Watch rate to rates for other equipment listed in the USACE Manual, determined

the Manual rate most similar in dollars per hour, and used the USACE Manual rate ($133.89) in

its claims. (JSOF 4 38; Dunn, TR 1035:21—1036:9).* Lodge then used those converted rates to

determine project costs for the Euclids to submit its certified Dewatering and Design claims,

despite Lodge’s knowledge that the USACE Manual rates were mandatory, not simply

guidelines. (JX069; JX083; Rousseau, TR at 169:6—19; Perkins, TR 712:6—713:1; JX060;

DX209).

The Federal Acquisition Regulations (“FAR”) specify how contractors must calculate

equipment ownership and operating rates. FAR § 31.105 gives a contractor several options to

determine equipment rates, including using “[p]redetermined schedules of construction

equipment rates[.]” FAR § 31.105(d)(2)(i). That section also provides several examples,

including “the Construction Equipment Ownership and Operating Expense Schedule published

by the U.S. Army Corps of Engineers, industry sponsored construction equipment cost guides, or

commercially published schedules of construction equipment use cost[.]” FAR §

31.105(d)(2)a)(B) (emphasis added). Lodge chose to report its equipment ownership and

operating rates using the USACE Manual, therefore it was bound to follow the instructions

contained therein.

The USACE Manual contains requirements for how contractors must use it to establish

operating rates for equipment. Table 2-1 of the USACE Manual contains specific equipment

codes and lists operating rates for those pieces of equipment. (JX001.033). If a piece of

® The USACE Manual rate that most closely resembled the rate Lodge derived from Equipment

Watch and assigned to the project cost was for a 2006 773D Caterpillar Truck, purchased new in

2006. (JX001.252).

equipment is not listed, the USACE Manual provides alternative methodologies for calculating

operating rates. (JX001.337). Specifically, the USACE Manual allows contractors to select a

piece of equipment that has very similar operational specifications and value, or else directs

them to use the “CHECKRATE” spreadsheet to calculate operating costs:

[I]f the contractor’s actual equipment is not listed in tables 2-1 and 2-2, an

equivalent piece of equipment may be chosen from the tables. To be

considered equivalent, the contractor ’s equipment must be no more or less

than 10 percent of the configuration (size, capacity, and horsepower) and

value as compared to the equipment in tables 2-1 and 2-2. In either case, if

the equipment is not equivalent, the equipment rate must be calculated using

the methodology in chapter 2.

(JX001.337-338 (emphasis added); see also Rousseau, TR at 147:12—24; Schaeb, TR 1163:4—

1165:21).

Lodge charged Adam Rousseau with equipment costing for the certified claims, but he

did not recall who set the rates for the Euclid trucks and did not verify their accuracy. (Rousseau,

TR at 169-171:18). Adam Rousseau worked for Lodge from early 2011 to mid-2012. (/d. at

135:9-208:22). During the Site 1 project, Mr. Rousseau worked as a laborer and then in an office

managing timesheets and daily construction reports. (/d. at 139:7—19). When working in the

office, Mr. Rousseau worked directly for Mr. Dunn. (/d. at 139:20-140:7). In preparing Lodge’s

Dewatering Claim, Mr. Dunn relied on Mr. Rousseau’s compilation of equipment operating

costs. (/d. at 141:11-144:19). Mr. Rousseau did not have significant construction or government

contracts experience prior to his employment with Lodge. (DX172; Rousseau, TR at 137:2-

138:20).

Mr. Rousseau knew that Lodge was required to use the CHECKRATE spreadsheet or the

USACE Manual to arrive at operating rates for the Euclids. (DX237; Rousseau, TR at 151:5—-12,

152:7-153:19, 169:6-19). Mr. Rousseau was responsible for entering data in the CHECKRATE

formula to compute operating rates but could not recall checking the accuracy of rates provided

to him. (Rousseau, TR at 170:3—25). Either Mr. Rousseau was aware, or through a minimum

examination he would have discovered that Lodge used operating rates for equipment purchased

new in 2006 with a value exceeding $880,000 each. (Schaeb, TR at 1163:4—1164:10;

JX001.252). In the USACE Manual, operating rates for newer equipment include both operation

costs (such as fuel and maintenance) as well as ownership costs (such as depreciation and

interest). (Schaeb, TR at 1161:13-1163:3).

In claiming equivalency, Lodge ignored the considerable discrepancy in value and age

between the equipment it used, and the equipment Lodge claimed it used. The USACE Manual

rate was based on a new vehicle; Lodge acquired used equipment. The USACE Manual rate

pertained to 2006 models; Lodge’s trucks were manufactured between 1988 and 1993. (Dunn,

TR at 911:19—913:16; Schaeb, TR at 1164:11—1167:20; JX072.5—.8). The USACE Manual rate

reflected equipment worth over $880,000; Lodge internally recorded that the purchase price of

each Euclid was between $14,000 and $24,000. (Dunn, TR at 911:19-913:16; Schaeb, TR at

1164:11—1167:20; JX072.5-.8). Thus, the total purchase price Lodge listed for its trucks totaled

less than $100,000, yet Lodge billed for the costs of operating and owning trucks with a

combined estimated value of over $3,520,000.

The USACE Manual assumes that equipment of that age would have been fully

depreciated, thus the operating rates would necessarily be lower to reflect only direct costs of

operation—fuel and maintenance. (Schaeb, TR at 1163:14-1164:10). Additionally, the decreased

value of older equipment necessarily reduces interest costs. (/d.). Lodge used USACE Manual

rates for a piece of equipment with a large discrepancy in both value and age from the actual

equipment deployed on the project. The misrepresentation in equipment type and value renders

the claim false with respect to the Euclid operating rates.

Lodge’s selection of the false operating rates for its Euclids was intentional. Lodge did

not provide the Army Corps with an explanation of its method for arriving at the operating rates

for the Euclids. (Dunn, TR at 907:2—908:4). For the purposes of litigation, Lodge has taken the

position that the rates reflect capital improvements to the Euclids, increasing their value. (Order

on Mot. in Lim. at 5, ECF No. 72; Case No. 13-499, Lodge Ans. To CCs at 155, ECF No. 102

(“Lodge admits that it utilized rates for more recently purchased equipment but did so to account

for the recent repairs and rebuilding of the engines performed by Lodge on its equipment.”)).

However, Lodge has produced no documentation whatsoever showing the exact cost and nature

of those improvements and refused to estimate the increase in the capital value of the Euclids.

(Dunn, TR at 913:17—917:14).

Nor did Lodge adduce testimony that established any notable capital improvement to its

aged Euclids. The absence of such testimony is telling. Other than vague allusions, Lodge did not

produce a single receipt, invoice for parts, or mechanic who could substantiate that any repair or

improvement had occurred much less a degree of improvement which would render twenty-year-

old vehicles the functional equivalent of similarly sized vehicles manufactured in 2006

collectively valued at several million dollars. Moreover, what little testimony that was presented

established that Lodge “cannibalized”’ one of the four Euclids for parts to repair the other three

Euclids. (Dunn, TR at 918:12—919:2). Lodge also valued this vehicle, despite it being stripped

for repairs to the other three Lodge trucks, as if it were also of a different make and newer 2006

model valued at over $880,000.

Lodge acquired the Euclids in used condition through a related party financed

transaction, subject to a lien from SunTrust Bank. (Rousseau, TR at 161:8—16; Dunn, TR

904:22-906:8, 910:14—23). In its internal equipment records, Lodge listed a purchase price for

each of the four Euclids between $14,000 and $24,000. (JX072.5—.8). After Lodge’s involvement

in the project, SunTrust Bank sought to force a sale to satisfy its lien on the Euclids. Lodge

entertained offers of approximately $40,000 for all four Euclids together. (DX397; Dunn, TR at

” Though Lodge takes issue with the use of the word “cannibalized” to describe what took place,

the Court finds it an apt description. Lodge dismantled one Euclid and used those parts to repair

and maintain the other three, leaving the “cannibalized” Euclid in other than sound working

condition. (Dunn, TR at 918:9-23); FAR 31.105(d)(2) (equipment must be in “sound workable

condition”).

10

925:12—928:9). Lodge was aware that this represented a fair objective value for that equipment.

(Dunn, TR at 928:5—9).

Lodge understood that the Army Corps would likely view its operating rates as a

misrepresentation. In fact, Paul Perkins—the consultant Lodge hired to assist in preparing its

certified claims—warned Lodge that the Euclid operating rates utilized in its Dewatering Claim

were inflated. !° ([X068; Dunn, TR at 921:17—923:17; Perkins, TR at 661:16—786:14). Mr.

Perkins advised Lodge that, because the trucks were fully depreciated, the operating rates from

the USACE Manual would not provide a sufficient basis for Lodge’s equipment costs as part of

its Dewatering Claim. (Perkins, TR at 715:11—719:3). And he also cautioned that using

Equipment Watch or similar rates was an inappropriate method for calculating equipment costs.

(Perkins, TR at 712:6—713:1; JX060). Despite these warnings, Lodge knowingly and

intentionally submitted a certified claim containing inflated rates. (Dunn, TR at 1066:7—1067:20

(Cabot Dunn stating that despite Paul Perkins’ advice, he “made a call” to use the inflated rates

because he “felt like the Euclids were closer to new than they were used[.]”)). But, as mentioned

previously, Lodge made no effort to justify this belief or seek the Army Corps’ approval. (Dunn,

TR at 907:2—908:4, 913:17—917:14). Mr. Dunn’s subjective belief as to the value of Lodge’s

trucks is irrelevant, belies any error in Lodge’s submission of erroneous operating rates, and

contradicts Lodge’s previous legal arguments. (See, e.g., Case No. 13-500, Lodge’s Opp. to Mot.

for Leave at 22, ECF No. 84 (“Lodge should have adjusted the published rates to account for the

age and actual purchase price of the dump trucks.”)).

In addition, the notion that Mr. Dunn possessed that subjective belief related to the value

of the Euclids is not credibly supported by the evidence. Mr. Dunn is a “seasoned and

experienced businessman” with knowledge of how markets dictate the objective fair value of

assets. (Dunn, TR at 818:23—25, 924:4-925:5). Following Lodge’s termination from the project,

in advance of a construction equipment auction market, a broker offered Lodge $40,000 for the

four Euclids together—an arm’s length transaction. (DX397; Dunn, TR at 925:12—928:9). Mr.

Dunn was aware of this offer and considered it reasonable in a “depressed market in 2013[.]”

(Dunn, TR at 928:5—9). He understood that the operating rates Lodge submitted to the Army

Corps were based on equipment purchased new in 2006 and valued in excess of $880,000. (/d. at

919:9-921:11). In light of this evidence, Lodge’s $880,000 valuation of each of the four Euclids

is not the product of a mistake; it is knowing, intentional, and duplicitous.

B. The Inefficiency Ratio

Lodge’s Dewatering Claim alleged that the United States should be held partially

responsible for higher-than-expected water levels on the project site which delayed Lodge’s

progress. (F.g., Case No. 13-500, Lodge Am. Compl. at 3-8, ECF No. 74; see also JX109.211

(explaining that the ratio was based on “[t]he construction inefficiencies encountered as a result

10 Mr. Perkins earned a degree in geology and joined the Army Corps shortly after graduating

college. (Perkins, TR at 667:12—668:3). Mr. Perkins has experience in reviewing certified claims

as a member of the Army Corps, and in submitting certified claims through his work as a

consultant. (/d. at 669:2—7). Mr. Dunn relied on Mr. Perkins’s expertise with respect to

preparation and submission of Lodge’s certified claims. (/d. at 669:8—12).

11

of the inability to effectively dewater the site[.]”)). Lodge attempted to account for alleged

inefficiencies on the project by applying a unique “inefficiency ratio” to a pool of overhead,

labor, and equipment costs accrued between July 6, 2011 and January 14, 2012. (JX109.209).

This inefficiency ratio was developed and applied by Ms. Callaway. (Callaway, TR at 219:2-8).

Ms. Callaway developed Lodge’s baseline schedule contained in its bid and the

subsequent modifications during performance. (/d. at 219:9-13, 222:11—122). She also assisted

Mr. Dunn and Mr. Perkins with the preparation of the certified Dewatering Claim that Lodge

submitted to the Army Corps. (/d. at 241:13-214:15, 265:12—23). In fact, Ms. Callaway was

primarily responsible for preparing the delay analysis Lodge used in its Dewatering Claim. (/d. at

258:8-15). The Dewatering Claim relied on Ms. Callaway’s baseline schedule, as well as the

modifications and the “inefficiency ratio” that Ms. Callaway created to measure the impact of

project delays due to water. (JX109.213). This was the first time Ms. Callaway had utilized an

inefficiency ratio in presenting claims to the Army Corps. (Callaway, TR at 255:14—22). Ms.

Callaway’s inefficiency ratio was unique to Lodge’s claims. (/d. at 490:17—24).

The inefficiency ratio was intended to measure the impacts of excavation work in Section

1 of the project. (IX109.208).'! In the baseline schedule, Section 1 was 2,500 linear feet, but

Lodge made a “management decision to limit Section 1 to only 2,000 linear feet” in order to “get

the production work going.” (JX109.209). This adjustment is important to note because it

reduces the days allocated to work in Section 1 in the baseline schedule. (/d.). Ms. Callaway

produced the ratio by placing the “actual days” of work over the “baseline allocated days.” (U/d.).

She tallied 285 “actual days” and 115 “allocated days” to calculate an inefficiency ratio of 2.478

or 247.8%. (/d.). In simple terms, this ratio indicated that Lodge spent approximately 2.5 times

longer than expected to do the work in Section 1. (Schaeb, TR at 1150:18-1151:13).

Construction Inefficiency Ratio Calculation

A. Baseline Allocated Days (2.500 LF): 114

B. Actual Days (2,000 LF): 285

Ratio (B'A.) = 2 478 (247 8%)

Lodge Construction, Inc. v. United States Trial Exhibit: JX109.209

Ms. Callaway’s testimony is suspect. At a minimum, her status as an independent fact

witness is improbable. Aside from the inconsistent responses and flawed recollection at trial,

several other issues during trial raise questions about the integrity of Ms. Callaway’s testimony.

Ms. Callaway represented that one of the law firms representing Lodge was her client and paid

her $150 per hour for preparation in advance of trial and her testimony as a fact witness.

(Callaway, TR at 382:13-383:1).

' As mentioned previously, Lodge originally divided the project into six sections, each 2,500

feet in length. The cofferdam failed in Section 2. (See Lodge’s MSJ on Liability, Ex. C).

12

Curiously, just prior to an overnight break in the trial, Lodge’s counsel—Edward

Parrott—represented that his firm had an attorney-client relationship with Ms. Callaway which

allowed him to speak with her during the intermission. (/d. at 293:1—17). Ms. Callaway later

clarified that Mr. Parrott’s firm represented her without charge. (Callaway, TR at 382:13-22).

That dynamic, where a lay witness is both a client of a law firm at no cost and providing services

for which the firm is compensating her for testimony on issues relating to her involvement in a

fraudulent scheme, is unusual and concerning.

While “it is not improper to pay a witness’s expenses” incident to testimony at trial, the

arrangement here raises eyebrows. See Model Rules of Pro. Conduct Rule 3.4(b) and cmt. 3

(Am. Bar. Ass’n 9th ed.); ABA Formal Ethics Op. 96-402 (1996) (nonexpert witness may be

compensated for time spent attending trial or deposition or preparing for testimony if payment

not conditioned upon the content of testimony and does not violate any law). The fact that Ms.

Callaway believed the law firm representing Lodge and questioning her at trial to be her “client,”

while the law firm simultaneously asserted that it represented her legal interests, is a curious

arrangement. Although the parties submitted bench memos regarding the propriety and

admissibility of Ms. Callaway’s testimony, (ECF Nos. 73 & 74), the only conclusion the Court

draws is that Ms. Callaway is not an objective broker of fact. See United States v. Beard, 761

F.2d 1477, 1481 (11th Cir. 1985) (Even when a fact witness swears to testify truthfully,

receiving compensation impacts credibility); cf U.S. v. Cervantes-Pacheco, 826 F.2d 310, 316

(Sth Cir. 1987) (“Finally, the trial court should give a careful instruction to the jury pointing out

the suspect credibility of a fact witness who has been compensated for his testimony.”). The

Court’s conclusion is bolstered by the content of Ms. Callaway’s testimony.

In addition, during an overnight intermission, an interaction between Mr. Parrott and Ms.

Callaway regarding her testimony caused Ms. Callaway to feel “extremely uncomfortable,”

compelling Mr. Parrott to bring the matter to the Court’s attention the following morning.

(Callaway, TR at 318:12-320:12, 379:11-396:8). After its direct examination, the United States

moved for sanctions and exclusion of Ms. Callaway’s testimony. (/d. at 394:9-24). At the close

of trial, the Court denied the United States’ motion to exclude Ms. Callaway’s testimony.

(Colloquy, TR at 1439:16—1440:8). Later, during a break in Mr. Dunn’s testimony, Mr. Parrott

revealed that Ms. Callaway and Mr. Dunn had met during a break in the trial despite the Court’s

instructions that fact witnesses remain sequestered even after their testimony concluded. (Dunn,

TR at 854:1-861:12). Though Ms. Callaway was not an employee of Lodge, Ms. Callaway and

Mr. Dunn have a close personal and professional relationship. (/d. at 857:1-859:24). Mr. Dunn

has worked with Ms. Callaway for “many years” and considers her a friend, speaking with her

“frequently” outside of the context of this particular project. (/d.). Mr. Dunn and his counsel both

represented that during the overnight interaction, Mr. Dunn and Ms. Callaway did not discuss the

trial. 7d. at 854:1-861:12).

Credibility determinations are solely within the province of the trial court sitting as the

factfinder. Medichem, S.A. v. Rolabo, S.L, 437 F.3d 1157, 1171 (Fed. Cir. 2006) (“[D]eference is

appropriately accorded to assessments of witness credibility because only the trial judge can be

aware of the variations in demeanor and tone of voice that bear so heavily on the listener’s

understanding of and belief in what is said.”) (internal quotations omitted). The Federal Circuit

has encouraged trial courts to look to the same hallmarks of credibility as those a jury would be

instructed to consider. Purifoy v. Dep't of Veterans Affairs, 838 F.3d 1367, 1373 n.1 (Fed. Cir.

13

2016). Accordingly, the Court has assessed the credibility of Ms. Callaway according to several

factors, including her demeanor at trial, her motives for obscuring the truth, her financial

interests in a continued relationship with Lodge, and her interests in maintaining a personal

relationship with Mr. Dunn, as well as the extent to which her testimony is consistent, plausible,

and supported or contradicted by other evidence. See D.C. Std. Civ. Jury Instr. No. 2-9

(Credibility of Witnesses); Eleventh Circuit Pattern Jury Instructions (Civil) 3.4 (2020). Despite

being an independent contractor, Ms. Callaway’s personal relationship with Mr. Dunn and the

financial relationship between Ms. Callaway, Lodge, and Lodge’s law firm shade Ms.

Callaway’s credibility. !*

i. The Calculation of “Actual Days”

The Dewatering Claim did not clearly explain what counted as an “actual day” for the

purposes of the ratio’s numerator. (JX109.208; Schaeb, TR at 1154:25—1155:10). Ms. Callaway

offered conflicting explanations about what the “actual days” represented. She explained in a

deposition prior to trial that “285” represented the actual days of work in Section 1 from start to

finish. (Callaway, TR at 266:17-267:11)."° At trial, she recollected that those days were based on

activity in Section 1 as reflected in the “daily reports’—logs of labor and equipment work. (/d. at

268:12—269:1). In reality, the 285 days reflected “activity days,” which Lodge tallied any time it

recorded any labor or equipment hours, no matter how minimal, in any subsection within Section

1.4 Ud. at 471:6-472:12; JX119.008). Using this scheme, Lodge could (and did) log multiple

“activity days” in a single calendar day. (See, e.g., Callaway, TR at 329:16—-331:3 (logging five

activity days on March 8, 2012)). Going further, Lodge’s methodology allowed Lodge to count

multiple activity days in a single calendar day when it spent just a few hours (or minutes)

working.

Ms. Callaway recorded activity from the daily logs as tick marks in a “Production

Values” spreadsheet. (JX095; Lodge’s Mot. in Lim. Ex. B § 7, ECF No. 69-1 (Affidavit of Ms.

Callaway)). Basically, if a laborer or piece of equipment worked in a single subsection for any

period at all, no matter how briefly, a tick mark was entered and later counted as a full activity

day. Ms. Callaway struggled to consistently describe how she carried activity from the daily logs

to the ratio. In a previous deposition, Ms. Callaway testified that she did not use the spreadsheet

to prepare the ratio. (Callaway, TR at 267:17—271:20). At the deposition, she testified that it was

2 Similar to Ms. Callaway, Mr. Perkins testified that he would be compensated by Mr. Parrott’s

firm as a fact witness while the same firm was representing him. (Perkins, TR at 662:8—664:3).

The United States objected to Mr. Perkins’ testimony. (/d. at 664:4—9). The Court denied the

United States’ motion to exclude Mr. Perkins’ testimony, though it raises credibility concerns

like those raised by Ms. Callaway’s financial arrangement. (Colloquy, TR at 1439:16—1440:8).

'S There are 192 calendar days, including weekends, between July 6, 2011 and January 14, 2012.

4 Lodge actually divided Section 1 into subsections numbered alphabetically according to their

position and whether they were on the north or south side. (JX119.008 n.13). For example,

“Section 1AN” would denote the north side of the first subsection within Section 1 abutting the

cofferdam, and “Section 1AS” would denote the south side of the same subsection.

14

“mere coincidence” that both the spreadsheet and Lodge’s Dewatering Claim registered 285

actual days of work. (/d.). But just before trial, Ms. Callaway signed an affidavit stating that she

reviewed the daily logs to prepare the spreadsheet and used the spreadsheet to prepare the ratio.

(Affidavit of Ms. Callaway at J] 6-7; see also JSOF { 49).

Several examples illustrate how Lodge’s rudimentary methodology grossly inflated

Lodge’s inefficiency ratio. On March 8, 2012, Lodge counted five activity days for two hours

and forty minutes of work in Section 1. (Callaway, TR at 336:18—25). On March 9, Lodge

worked in Section 1 for 90 minutes and logged five activity days. Ud. at 343:9-16). On March

10, Lodge tallied seven activity days for nine hours of shoveling and raking by a single laborer

and 10.5 equipment hours. (/d. at 347:12-349:20). On March 12, Lodge used one piece of

equipment for three hours and logged two activity days. (/d. at 356:11—17). On March 13, Lodge

counted four activity days for 13.5 hours of equipment time. (/d. at 368:8—13). On January 20,

2012, Lodge recorded two activity days but has no record of performing work in Section 1 that

day. Ud. at 370:25—3713). On February 10, Lodge counted two activity days justified by 50

minutes of bulldozer activity. (Callaway, TR at 375:19-22). Ms. Callaway repeatedly

acknowledged that her methodology for counting “actual days”—aka, activity days—was not

reasonable, accurate, or truthful, offering only that the misrepresentation was not intentional.

(See, e.g., id. at 337:1—18, 343:13-344:8, 350:14-17, 357:14-359:9, 368:14-369:6).

In addition to the overcounts, Lodge’s rudimentary and inconsistent methodology for

recording activity days also led to undercounts. (See Lodge Trial Brief at 16). For example, on

October 27, 2011, Lodge logged one activity day while recording 26 hours of work in Section 1.

(Callaway, TR at 424:19-425:4; PX46—49). Ms. Callaway believed, without evidence, that the

undercounted activity days would outnumber the overcounts. (/d. at 427:14—23). In addressing

the issue of overcounts and undercounts, Ms. Callaway admitted that in calculating activity days

her “methodology was flawed[.]” Ud. at 475:3—5).

As illustrated in the examples above, Lodge’s method allowed Lodge to record multiple

activity days in a single calendar day, even when minimally working in Section 1. Lodge’s

inefficiency ratio was not an appropriate measure of efficiency because it does not consider

input, effort, or the resources and costs expended in an activity day. (Schaeb, TR at 1151:6—10).

The Court finds that the testimony of a litigation consultant proffered by the United States, Eric

Schaeb, was particularly helpful in conceptualizing the difficulties with Lodge’s methodology. !°

Mr. Schaeb offered two salient examples that highlighted the conceptual problem with Lodge’s

methods. (JX119.009). In the first, Mr. Schaeb highlights that whether Lodge performed a

certain amount of work within the same subsection mattered greatly:

If Lodge performed 8 hours of embankment work on Section 1AN on a given

calendar day, that is counted as 1 activity-day. However, if Lodge performed

'S Mr. Schaeb focuses on costs, revenues, and damages in government contracts and construction

matters. (Schaeb, TR at 1145:11—1213:6). He earned a degree in finance and management and

was educated in the fields of accounting and cost calculations and methodologies. (JX119.031).

At trial, the Court accepted Mr. Schaeb as an expert on quantification of damages, project cost

accounting, and analysis of construction costs. (Schaeb, TR at 1145:25—1146:16).

15

4 hours of embankment fill work on Section 1AN in the morning and 4 hours

of embankment fill work on Section 1CN in the afternoon, that single

calendar day is counted as 2 “activity-days,” 1 activity day for each section

of the levee despite being the same number of man-hours and same overall

level of effort.

(JX119.009). In the second example, Mr. Schaeb highlighted an even bigger problem with

Lodge’s formula. Lodge assumed that the amount of equipment or number of man-hours utilized

were irrelevant to the tally of activity days:

Lodge’s counting method is also flawed because it treats every activity-day

as equal regardless of whether 4 man-hours were worked or 40 man-hours

were worked on an activity. An example of the problem with this approach

can be shown with two different scenarios. In Scenario A, 8 laborers work 5

ten-hour work days to accomplish a task, or 400 man-hours. In Scenario B, 5

laborers work 10 eight-hour work days to accomplish the same task, also 400

man-hours. However, under Lodge’s approach of only counting days worked

rather than man-hours, Scenario B would be twice as inefficient (or half as

efficient) as Scenario A because Scenario B took 10 days and Scenario A

took 5 days.

(Id.).

Ms. Callaway is an intelligent and experienced professional with command of the

mathematical principles involved here and a conceptual understanding of construction

scheduling. (Callaway, TR at 216:9-218:13). Ms. Callaway understood that either increasing the

activity days or decreasing the planned days would result in a higher ratio. /d. at 247:24-248:4).

Ms. Callaway also understood that an increase in the ratio directly increased Lodge’s costs and

therefore, the value of its Dewatering Claim. (/d. at 498:22—499:5). Moreover, Ms. Callaway

never sought the Army Corps’ guidance on the appropriate method to account for alleged

inefficiencies. (/d. at 502:10—24).

Mr. Perkins was not initially consulted about using an inefficiency ratio to calculate the

costs of project inefficiencies. (Perkins, TR at 780:20—781:8). When reviewing the Dewatering

Claim in preparation for its submission to the Army Corps, Mr. Perkins advised Lodge that a

blanket inefficiency ratio was inappropriate. (JX070.021—.022; Perkins, TR at 698:5—699:18). In

fact, Mr. Perkins advised Lodge that if it did intend to use an inefficiency ratio, the ratio should

be tailored to the equipment and effort expended and accompanied by a narrative explanation for

each inefficiency factor. (JX070.022). Lodge did not adopt that cautionary approach.

Ms. Callaway carefully reviewed and considered the daily logs in creating the Production

Values spreadsheet. (Callaway, TR at 473:1—18). The Court finds that Ms. Callaway’s tally of

activity days was not a mistake, but the intentional product of her methodology. Only when it

would be untenable to deny did Ms. Callaway acknowledge the flaws in her methodology. But

the mathematical and conceptual flaws were or should have been apparent to someone of Ms.

Callaway’s education and experience. The Court finds that Lodge’s inflation of its inefficiency

ratio using Ms. Callaway’s methodology was knowing and intentional.

16

ii. Activity After January 14, 2012 and Erroneously Tallied Days

In late January 2012, Lodge presented payment requests to the Army Corps that showed

for “[b]illing purposes,” work in Section 1 was complete as of January 14, 2012. (JX038;

Callaway, TR at 278:2—281:10). Lodge’s Dewatering Claim ostensibly sought compensation for

inefficiencies in work performed between July 6, 2011 and January 14, 2012. (JX109.209). In

preparing the inefficiency ratio Lodge used to calculate the value of its certified claim, Ms.

Callaway referenced the Production Values spreadsheet. (JSOF { 49). In doing so, she included

55 activity days in the numerator of the inefficiency ratio that correspond to work performed

after January 14, 2012. (Callaway, TR at 269:12—270:12).

Ms. Callaway had some trouble consistently describing the nature of Lodge’s work in

Section 1 after January 14, 2012—the purported end date of Lodge’s Dewatering Claim. In a

pre-trial deposition, Ms. Callaway testified that Lodge performed minimal work in Section 1

after January 14, and that those days should not be counted as “actual days” for the purposes of

the inefficiency ratio. (/d. at 287:14—-19). At trial, after consultations with Lodge’s counsel, Ms.

Callaway amended her testimony to align with Lodge’s litigation position—that work was

performed after January 14, 2012 and activity days after that date were properly added to the

numerator of the inefficiency ratio and incorporated in Lodge’s Dewatering Claim. (/d. at 289:2-

289:21). Prior to trial, Ms. Callaway testified that she did not use the Production Values

spreadsheet to calculate activity days for the inefficiency ratio and the correlation between the

spreadsheet and activity day total was a coincidence. (/d. at 270:3—271:20). Ms. Callaway then

testified at trial that she used the Production Values spreadsheet to reperform her analysis by

comparing the daily reports to her tick marks in the spreadsheet. (/d. at 324:7—325:24). Notably,

Lodge did not provide the Production Values spreadsheet to the Army Corps in support of its

claim. (Dunn, TR at 949:10-950:2).

The Production Values spreadsheet is the source of Ms. Callaway’s activity days tally.

That spreadsheet includes tallies for days after January 14, 2012. Lodge submitted the

Dewatering Claim to the Army Corps with the knowledge that the inefficiency ratio included

days outside the claim period and intended to be compensated for costs that it incurred outside

the claim period. (Callaway, TR at 289:2—21). Ms. Callaway reviewed the daily reports after

January 14, 2012 and intentionally added activity days outside the claim period. (/d. at 320:21-—

321:4). She was aware that Lodge would use her ratio to calculate costs Lodge was seeking from

the Army Corps. (/d. at 321:5—16). Ms. Callaway’s tally of days outside of the claim period and

incorporation of those days into the inefficiency ratio was intentional, not the product of a

mistake. She provided these activity day tallies to Mr. Dunn, thereby making him aware that the

inefficiency ratio incorporated days outside of the claim period. (/d. at 274:2—275:4). Mr. Dunn

also affirmed that inclusion of activity days outside the claim period was Lodge’s intention, not a

mistake. (Dunn, TR at 947:8-948:18).

iii. The P00009 Contract Modification

Lodge’s contract provided that Lodge was to complete the project within 720 days of the

Army Corps’ Notice to Proceed. (JSOF 4 3). The Army Corps issued the Notice to Proceed on

October 20, 2010 fixing Lodge’s deadline to complete the project as October 8, 2012. (/d.). After

receiving the Notice to Proceed, Lodge divided the work into six sections. (/d. at § 6). On June 6,

17

2011, the Army Corps issued Request for Proposal number 0005 (“RFP-0005”) to consolidate

excavation work in two separate line items into a single, new line item. (/d. at 9 9). CLIN 0007

was increased by 260,000 cubic yards, to a total of 554,300 from 294,300 cubic yards. (See

JX061.002, JX113.002). CLIN 0021 was decreased by 260,000 cubic yards to balance out the

increase to CLIN 0007 and complete the consolidation. (JX061.002). In July 2011, Lodge began

pumping water from the Section 1 construction area into water impoundment areas. (JSOF 4 7).

In doing so, Lodge experienced difficulties in dewatering Section 1 because the water in the

impoundment areas failed to percolate away from the project as expected. (/d.).

After ongoing discussions about the material Lodge was expected to excavate in the new

line item, Lodge submitted a formal Request for Equitable Adjustment (“REA”) in October

2011. (Ud. at ¥ 10). In December 2011, the Army Corps granted Lodge’s request in part through

contract modification P00009. (/d. at § 11). POO0009 authorized $1,990,000 in additional

compensation for Lodge and 81 additional days for Lodge to complete the project, in effect

creating a new, January 3, 2013 completion deadline. (/d.; JX061.030).

When Ms. Callaway adjusted the project schedule to account for the PO0009

modification, she spread the additional 81 planned days across all six sections of the project.

(Callaway, TR at 443:1—445:2; JX061.027—28). For Section 1A however, Ms. Callaway allotted

additional time for evaluation of the site conditions. (Callaway, TR at 445:3—20; JSOF 4 44).

When Lodge prepared the inefficiency ratio as part of its Dewatering Claim, Lodge

utilized the “original number of days from the baseline schedule which were intended for

completion of 2,500 linear feet[.]” (JX109.209).!* In its original baseline schedule, Lodge

allocated 115 days to excavation in Section 1. Lodge used that figure in the denominator of its

inefficiency ratio. (JX109.209). Because that figure came from the original baseline schedule, the

figure did not account for the additional planned days the Army Corps granted Lodge in contract

modification POO009. Lodge never sent the Corp a revised schedule incorporating the 81-day

extension. (Callaway, TR at 240:6—18; Andres, TR at 1129:25—1130:3, 1132:2-11).

Lodge offered conflicting accounts as to whether it intentionally or mistakenly excluded

P00009 from its inefficiency ratio. At trial, the Court accepted three statements from Lodge’s

prior filings as party admissions. (Colloquy, TR at 316:25-317:16). In Lodge’s Opposition to the

United States’ Motion for Leave to File Amended Answers Asserting Counterclaims in Fraud

(Case No. 13-500, ECF No. 84), Lodge admitted that it should have accounted for contract

modification P00009 in its inefficiency ratio: “Lodge acknowledges now, as Ms. Callaway did at

her deposition, that Lodge’s calculations should have taken into account, to some degree, the 81

days provided by Modification P-00009. Lodge admittedly did not.” (Case No. 13-500, Lodge’s

Opp. to Mot. for Leave at 23-24). Lodge claimed that this oversight was the product of a

mistake: “Undoubtedly, Lodge did overlook the additional days provided by Modification P-

00009 when calculating the impacts of the dewatering problems, but there is a reasonable

'6 As noted previously, Lodge reduced the length of Section 1 to 2,000 linear feet in order to

expedite dry work in that section. Lodge noted that in calculating its inefficiency ratio, it did not

prorate the number of days allocated to Section 1 commensurate with the reduction in linear feet

of excavation. (JX109.209).

18

explanation for this mistake.” (/d. at 24). Lodge urged the Court to accept that this mistake was

justified because the project was in crisis: “Therefore, it is understandable that Lodge, while it

was dealing with two major crises on the Project, overlooked the fact that the original durations

in the schedules had not been updated to reflect the additional time given for them in

Modification [P00009].” (/d.). Lodge’s statements are consistent with Ms. Callaway’s prior

deposition testimony, in which she stated that it would have “[p]robably” made sense for Lodge

to adjust its inefficiency ratio “to reflect that there had been extensions based on the REA”

because Lodge “got credit for the time” through P00009. (Callaway, TR at 260:13-261:19).

However, these statements and Ms. Callaway’s prior testimony are both at odds with her

trial testimony. At trial, Ms. Callaway stated that it was her intent to exclude the 81 days granted

by P00009 because the baseline schedule was “the correct schedule to use” for the inefficiency

ratio. Ud. at 252:17—22). She stated that it was her intent to exclude those days specifically to

show “the magnitude of the impact that Lodge experienced with the dewatering problem[.]” Ud.

at 251:9-17). Ms. Callaway’s trial testimony is consistent with contemporaneous emails from

Mr. Dunn. On April 15, 2012, Mr. Dunn emailed Ms. Callaway asking her to transmit a

December progress schedule that omitted the 81 days granted by PO00009 because, in Mr. Dunn’s

view, omission “would best represent the time impact portion of the REA.” (JX094). The Court

finds that Lodge knowingly and intentionally excluded the 81-day contract extension granted by

modification POQ0009 from its inefficiency ratio denominator.

Underlying the United States’ fraud claim with respect to P00009 is the implication that

Lodge attempted to double-bill the Army Corps for work Lodge performed in Section 1. The

United States contends that Lodge was compensated for the extension of time and additional

work through P00009 then sought additional compensation by applying the inefficiency ratio to a

cost pool in its Dewatering Claim. (USA Trial Brief at 32). And in applying an inefficiency ratio

that failed to account for the POO0009 modifications, the ratio was inflated, thereby inflating the

Dewatering Claim. (/d.).

There is some ambiguity as to whether Lodge performed any work in Section 1 pursuant

to P0O0009. In consideration of the additional compensation and time Lodge received to complete

the project, Lodge was expected to excavate an additional 260,000 cubic yards of material across

the project. (See JX061.0001). But Lodge never finished performance on the baseline scope of

work or started billing the new line item for the increased scope of work. (Gannon, TR at

110:18-111:9; Dunn, TR at 1065:20—22, JX113.002 (Lodge’s final pay application showing

104,958 cubic yards excavated)). And Lodge was insistent that, though it was unclear where the

extra PO0009 excavation would have occurred, it would have been outside of Section 1.

(Compare Callaway, TR at 446:10-—22, 453:8-454:6 and Dunn, TR at 1069:20-1070:20, 1071:9-

15 with Gannon, TR at 104:8—105:1 (unable to refute Lodge’s assertions regarding excavation in

Section 1) and Andres, TR at 1138:13-1139:11, 1143:3-23 (same)). In sum, all that is clear is

that though Lodge was authorized to bill for excavating 554,300 cubic yards in CLIN 0007,

inclusive of the PO0009 modification, Lodge only excavated and billed for 104,954 cubic yards

prior to termination. (JX113.002). Thus, the Court cannot find that Lodge’s work in Section 1

implicated PO0009 through the added excavation material or the increased compensation

authorization.

19

However, Lodge’s work in Section 1 did implicate the extra days granted in modification

P00009. (JX061.028). The Army Corps granted Lodge extra days of work in Section 1, which

meant an increase to the cost pool through added equipment and labor costs and allocated

overhead. In that way, Lodge incorporated P00009 cost impacts into its Dewatering Claim cost

pool but failed to incorporate those days in the inefficiency ratio. (See Van Noy, TR at 1422:11-

24 (discussing duplication of cost impacts)). Therefore, even if the Army Corps were not

compensating Lodge by increasing the cubic yardage, the Army Corps was compensating Lodge

by granting additional days during which Lodge added costs to its cost pool.

C. Lodge ’s Batch Plant Costs

Part of the project involved reinforcing the levee with soil cement. To produce the soil

cement, Lodge commissioned a “batch plant”—a stationary piece of equipment consisting of a

bin for storage of soil material, scales, cement mixer, and a silo. (Gannon, TR at 72:23-73:8).

The batch plant was powered by a generator. (/d. at 72:23—73:8). “The purpose of the batch plant

was to mix water, Portland cement, and soil excavated from the site, to produce soil cement used

to armor the levee.” (JSOF 4 53). The batch plant was the largest and most valuable piece of

equipment on the project. (Lester, TR at 1245:21—25).

rg ee

ae “aah?”

ed ae mh wh |

Batch Plant completed assembly.

Lodge Construction, Inc. v. United States Trial Exhibit: JX029.007

Lodge’s Dewatering and Design claims sought compensation for costs related to ownership and

operation of the batch plant. (See, e.g., JX109.116 (Dewatering Claim costs); JX104.146 (Design

Claim costs)).

At trial, the United States raised three issues related to Lodge’s treatment of the batch

plant costs in its Dewatering and Design claims. First, the United States asserts that Lodge’s

inclusion of any batch plant ownership costs was fraudulent because the Army Corps reimbursed

Lodge in full for the installation and commissioning of the batch plant. (USA Trial Brief at 39-

40). Second, the United States takes issue with the operating rate at which Lodge billed the Army

20

Corps. (/d.). Third, the United States alleges that Lodge improperly calculated the hours of

operation for the batch plant. (/d.). Each issue merits consideration.

i. Ownership of the batch plant

Through third parties, Lodge purchased the batch plant for $707,600 ($656,750 for the

batch plant itself plus $50,850.31 for shipping and handling) and the generator for $110,372—a

total of $817,972. (JSOF 44 55-56; JX048). Lodge purchased the batch plant from R&S

Concrete Batch Plants, Loadcraft Industries Ltd. (Dunn, TR at 963:19—25). Lodge intended the

batch plant to produce soil cement for use on the project. (Gannon, TR at 72:23—73:8). Soil

cement is a compacted mixture of soil or aggregate, cement mix, and water. (Gore, TR at 603:1-

6).

Lodge’s arrangement with the Army Corps to purchase the batch plant was atypical.

(Gannon, TR at 78:8-20; DX344.002). Lodge and the Army Corps reached an agreement by

which the Army Corps would pay Lodge a total of $1,227,600 in two equal installments for

purchase, installation, and commission of the batch plant. (SOF 4 57). The Army Corps agreed

to pay for the batch plant in advance to assist Lodge with the large up-front costs. (Gannon, TR

at 78:21—25). Lodge financed $900,000 of the purchase price of the batch plant through SunTrust

Bank. (JSOF 4 61). The Army Corps paid Lodge the first installment after Lodge mobilized the

batch plant and paid the second installment after Lodge produced a trial batch of cement that met

the contract’s specifications. (/d.). The Army Corps paid Lodge in full for the purchase of the

batch plant several months before Lodge submitted its certified claims. (/d. at § 65).

Lodge billed and the Army Corps paid $1,227,600 in total through that arrangement. (/d.

at 9 58). This is reflected in CLIN 0009, which Lodge understood “encompassed all the efforts to

get that first trial batch installed.” (JX028.012; Gore, TR at 528:11-18). Lodge made five

progress payments toward the total cost of the batch plant, inclusive of shipping. (DX166).

However, the final invoice from February 2011 indicates that Lodge still owed the batch plant

vendor $215,037.81. U/d.). That invoice remained outstanding on August 12, 2011. Ud). Mr.

Dunn explained that Lodge withheld payment due to Lodge’s issues in getting the batch plant

certified as well as related back-charges and offsets. (Dunn, TR at 966:9-24). Lodge never paid

that remaining balance. (/d. at 966:25—967:2). In addition, as of October 2012, Lodge owed

SunTrust Bank over $500,000 on its loan to finance the purchase of the batch plant. (JSOF § 64).

SunTrust Bank eventually seized the batch plant due to Lodge’s failure to pay down this loan.

(Dunn, TR at 971:21-972:19). After Lodge’s termination, the Army Corps paid SunTrust

approximately $100,000 to keep the batch plant on site for the replacement contractor to use in

completing the project. (Gannon, TR at 82:10—83:10).

CLIN 0009 also included production and placement of soil cement. (JX028.012). The

production line item in CLIN 0009 encompassed extracting material to process it in order to

produce the soil cement. (Gore, TR at 530:6-16). The placement line item within CLIN 0009

included actual production— “utilizing the batch plant to make the soil cement and place it on

the levee.” Ud. at 530:17-19).

Lodge made several capital improvements to the batch plant that were not contemplated

in the purchase price. Because of the amount of water on the project site, Lodge experienced

21

unanticipated difficulties that plagued the operation of the batch plant. Lodge made

modifications to the batch plant to improve the efficiency of soil cement production. (/d. at

648:7—12). Because of the amount of water on site, the soil material used to produce soil cement

in the batch plant needed to be prepared for cement production. (/d. at 604:13-606:7).

Specifically, the soil material was thick, sticky, and pasty, and resisted falling from the hopper

into the cement mixer. (/d. at 604:16—605:7). Pneumatic gates on the hopper opened on a

periodic timer to measure and control the flow of soil material into the mixer. (/d. at 605:7-17).

Due to its consistency, the soil material resisted falling into the mixer as contemplated, leading to

an imbalance of the three ingredients—Portland cement mix, soil, and water. (Gore, TR at

605:10-17). That imbalance affected the quality of the final soil cement product preventing the

cement from being certified to the contract specifications. (/d. at 605:15—17). Therefore, Lodge

made modifications to the batch plant and soil preparation process to improve the efficiency of

soil cement production.

Lodge tried several techniques to improve cement production. One of those techniques

was working the soil material by physically manipulating it—a technique known as “farming”—

to allow the soil to dry out before placing it in the hopper. (/d. at 605:24—606:7). That technique

proved inadequate. (/d.at 606:10—15). Lodge tried welding steel inside the hopper to create

steeper angles—utilizing gravity to help material fall into the mixer—but that technique also

proved inadequate. (/d. at 606:16—23). Lodge then directed laborers, using hammers, to beat on

the side of the hopper to shake material loose so that it would fall into the mixer. (/d. at 606:24—

607:3). The success of that technique inspired Lodge to install remote-controlled vibrators on the

outside of the hopper walls to agitate the material so that it would fall into the mixer. (Gore, TR

at 607:4-15). The combination of soil farming, adding steel plates, and installing vibrators

finally proved adequate for Lodge to produce soil cement that met the contract’s specifications.

(Id. at 607:10-15). Lodge had not anticipated that soil cement production would require that

level of effort and the improvements Lodge made were not contemplated in the purchase price of

the batch plant. (/d. at 607:16—24).

ii. Batch Plant Operating Rate

In calculating its Dewatering Claim impacts, Lodge incorporated batch plant operation

and standby costs from July 5, 2011 through January 14, 2012 in its cost pool to which it applied

the inefficiency ratio. (JSOF ¥ 59). In calculating Design Claim impacts, Lodge included batch

plant standby costs for the period of March 29, 2012 through May 30, 2012. (/d. at 7 60). Lodge

claimed operating rates based on an hourly rental rate of $339.09 and standby costs of $56.16 per

hour. (/d. at | 62; see also JX109.097).

In preparing its Dewatering and Design claims, Lodge referenced its internal equipment

costing records. (Compare JX083 (Weekly Costs Spreadsheet) with JX109.093 et seq.

(Dewatering Claim) and JX104.146 ef seg. (Design Claim)). Because the batch plant was a

custom piece of equipment designed specifically for this project, Lodge originally obtained

operating rates from Equipment Watch. (Dunn, TR at 1017:2—11). In June 2011, Equipment

Watch provided Lodge with monthly, weekly, daily, and hourly operating cost rates for the batch

plant. (JX051). Equipment Watch determined that the hourly operating rate for the batch plant

was $339.09. (JX051). Throughout the course of the project, Lodge’s internal equipment costing

records listed the batch plant operating rate at $339.09. (JX083.004).

22

On March 13, 2012, in preparing to submit its Dewatering Claim, Lodge used the

CHECKRATE spreadsheet to determine an operating rate of $235.88 per hour and standby costs

of $56.16 per hour. (JSOF § 63; JX081). That same day, Mr. Rousseau sent Mr. Dunn an email

with his calculations of these rates at 12:43 PM. (JX081). Later that evening, at 11:53 PM, Mr.

Dunn sent Adam and two others an updated spreadsheet containing, among other things,

equipment cost rates. (IX083.001). Four days later, Mr. Rousseau commented on the updated

spreadsheet and recommended some changes to operating rates which he flagged by highlighting

the cells in the spreadsheet. (/d.). Importantly, Mr. Rousseau commented on Lodge’s internal rate

for a 1999 Bobcat in cell row 77, indicating his opinion that the hourly operating rate was

surprisingly high. (/d.). The rate Lodge listed for the 1999 Bobcat was $235.88—matching

exactly the rate Mr. Rousseau calculated for the batch plant using the CHECKRATE

spreadsheet. (JX083.004). The equipment rate Lodge utilized for the batch plant—$339.09—was

listed in the row of cells just above the 1999 Bobcat equipment information:

Construction Owned

Weekly Standby Total Hours

Costs Owned Operated This

Filename: Copy of Total Weekly Costs Spreadzhaet BLANK2.xiex

Lodge Construction, Inc. v. United States Trial Exhibit: JX083.004

When presented with relevant documents at trial, Mr. Dunn credibly testified that he

intended to enter the CHECKRATE operating rate for the batch plant in cell row 76 of Lodge’s

internal spreadsheet, but instead entered that rate in the cell row for the 1999 Bobcat. (Dunn, TR

at 1040:2-16). In attempting to correct the error flagged by Mr. Rousseau’s comments, Mr. Dunn

neglected to ensure that the operating rate for the batch plant aligned with the CHECKRATE

figure. (/d. at 1040:10—16). Thus, the Equipment Watch figure remained in Lodge’s internal

equipment cost spreadsheet that Lodge later utilized to prepare its Dewatering Claim. The Court

concludes that Lodge’s usage of the erroneous Equipment Watch rate was the product of a

mistake.

23

iii. The batch plant operation time

As mentioned above, the batch plant was powered by a generator. (Rousseau, TR at

181:4—6). The generator featured a meter that measured operating hours. (/d. at 181:16—20). A

laborer operated the batch plant from the control center. (/d. at 184:23—185:5; JX081). But unless

the generator was running, the control room could not be operated, and the batch plant could not

produce soil cement. (/d. at 181:7—14).

Lodge reported run-time for the batch plant in two different ways. For internal reporting

purposes, Lodge referenced the hours metered by the generator to log the duration the batch plant

operated. (/d. at 181:24—182:18). For internal reporting purposes, the hours the generator was

running and the hours the batch plant was running “should have been the same.” (/d. at 184:12—

19). When reporting batch plant run-time to the Army Corps, however, Lodge used the amount

of time the control center operator logged on his timesheet. (IX081; Rousseau, TR at 184:20—

185:25).!’ Mr. Dunn was aware of this discrepancy because, in contemporaneous emails, Mr.

Dunn specifically asked Mr. Rousseau to clarify his methodology. (TX081). Mr. Dunn asked

whether the run-time Lodge would report for the batch plant should match the run-time Lodge

internally reported for the generator. (/d.). Mr. Rousseau responded “No,” and explained that he

was reporting different values to the Army Corps based on whether Lodge employee Mike

Wederath logged hours as a batch plant operator that day:

From: Adam Rousseau

To: Cabot Dunn

Sent: 3/13/2012 12:55:01 PM

Subject: RE: Batch Plant

No, | give Debbie the actual metered hours from the generator and lump E018/M003 together on Mike Wederath's

timesheet for LCI coding purposes. However, to the Corps | report the two separately and the batch plant’s operating

hours coincide with Mike’s time at the plant (so if Mike works 700AM-500PM the plant gets 10 operating hours/O

standby hours, if he works 7OOAM-400PM the plant gets 9 operating hours/1 standby hour, etc.). The generators

operating hours coincide with the meter reading (the same as any other piece of metered equipment)

From: Cabot Dunn

Sent: Tuesday, March 13, 2012 12:46 PM

To: Adam Rousseau

Subject: RE: Batch Plant

10-4 The operating hours you give Debbie each week for the batch plant are the same as the generator. Correct?

Cabot L. Dunn Jr.

Lodge Construction, Inc,

2161 MeGregor Bul.

Ft Myers, FL S591

Lodge Construction, Inc. v. United States Trial Exhibit: JX081

17 When confronted with his contemporaneous emails to Mr. Dunn in which Mr. Rousseau

admitted a discrepancy in reporting operating time, Mr. Rousseau repeatedly testified that he was

unable to remember what he was referring to in the emails. (See, e.g., Rousseau, TR at 184:22,

185:4—5, 188:23—24). That testimony was not credible. During this period of testimony, Mr.

Rousseau was evasive, unresponsive, and attempted to provide needlessly confusing responses to

questions on which there could be no dispute as to the truthful answer given the clarity of the

documents.

24

Attempting to clarify Lodge’s method of reporting run-time, counsel for the United States

presented Mr. Rousseau with several versions of a hypothetical in which Mr. Wederath would

have logged hours at the batch plant but the generator would not be running. (Rousseau, TR at

186:1—189:13). Mr. Rousseau added further confusion regarding Lodge’s methodology by

stating that if Mr. Wederath were at the batch plant, Mr. Wederath would record his time as a

batch plant operator, as opposed to a laborer, and would be compensated differently. (/d. at

186:4—13). Mr. Rousseau then testified that there were times Mr. Wederath would have been at

the batch plant, but the batch plant was not operating. (/d. at 188:10—12). In that situation,

according to Mr. Rousseau, Mr. Wederath would have been classified as a laborer. (/d. at

188:17—20). Curiously, Mr. Rousseau could remember all these machinations but was unable or

unwilling to clarify his email that stated, “the batch plant’s operating hours coincide with Mike’s

time at the plant[.]” (See JX081). On subsequent questioning from Lodge’s counsel, Mr.

Rousseau did not clarify his testimony. (Rousseau, TR at 199-208). And Lodge made no

mention of this issue in its post-trial brief.

The claims documents undercut Mr. Rousseau’s characterization of how Lodge was

distributing Mr. Wederath’s time between batch plant operation and general labor. The claims

documents show that there is simply no way to look at Mr. Wederath’s time sheet and derive an

accurate measure of batch plant operating time. Each week of both the Dewatering Claim and the

Design Claim, Lodge billed the Army Corps the operating and standby costs of the batch plant—

40 total hours each week. (F.g., JX109.093, .097, .100, .104; see also, e.g., JX104.146, .149,

152, .155). Likewise, each week without fail, Lodge billed the Army Corps for 40 hours of labor

performed by Mr. Wederath. (F.g., JX109.095, .099, .102, .106; see also, e.g., JX104.148, .150,

.153, .156). Each week, Mr. Wederath earned $1,000, or $25 per hour, regardless of how many

hours the batch plant was operated. (Compare, e.g., JX104.149, (zero operating hours, 40

standby hours), and JX104.150 with JX109.097 (28 operating hours, 12 standby hours) and

JX109.099). Despite Mr. Rousseau’s contention, Mr. Wederath’s pay did not differ based on

whether he was working as a batch plant operator or a laborer. (Rousseau, TR at 186:4—-13 (“If

[Mike Wederath] wasn’t at the plant, it was my understanding that Lodge wouldn’t pay him as a

batch plant operator. So he might get paid as a laborer.”)).

But even further examination of the claims documents reveals that Mr. Wederath’s hours

worked bore no relation at all to the operation of the batch plant. For the week ended July 20,

2011, Lodge billed 40 standby hours for the batch plant and zero operating hours. (JX109.100).

Wederath worked 40 hours and earned $1,000. (JX109.102). For the week ended December 7,

2011, Lodge billed 42 operating hours for the batch plant and zero standby hours. (JX109.181).

Mike Wederath worked 40 hours and still earned $1,000. (JX109.182). If Mr. Wederath’s time at

the batch plant and batch plant operation hours corresponded, as Lodge contended, one would

expect that Mr. Wederath would earn less when the batch plant operated for fewer hours. But

even assuming his rate of pay, whether classified as a batch plant operator or a laborer, was

equal, when the batch plant operated for more than 40 hours during a week, one would expect

Mr. Wederath’s pay, and/or his hours worked, to increase for that week. Mr. Wederath’s pay and

hours worked remained constant, no matter how many hours Lodge recorded operating the batch

plant. This example shows there was no correlation between hours Mr. Wederath recorded on his

time sheet and batch plant operating hours.

25

Moreover, the weekly operating time Lodge reported for the batch plant’s generator is

inconsistent with the weekly operating time Lodge reported for the batch plant. (JX047 (purchase

invoice for 405kW John Deere SAE generator); see also JX119.109 (Schaeb expert report

associating the “John Deere SAE Generator” with the batch plant)). Lodge reported those

operating times differently, despite Lodge’s acknowledgment that without the generator running,

the batch plant could not operate. (Rousseau, TR at 181:7—14, 184:12—19 (“Those numbers

should have been the same.”).

For fifteen of the weeks Lodge sought compensation in its Dewatering Claim, Lodge

reported operating hours for the batch plant identical to those hours it reported for the generator.

(JX109.100, .112—.113, .116—.117, .120-.121, .124—.125, .133, .144—.145, .149, .153, .160-.161,

165, .169, .173, .177, .185, .189, 193, .197, .201, .205 (fifteen weeks)). For nine of the weeks in

the Dewatering Claim however, Lodge reported more operating hours for the batch plant than it

did for the generator. (JX109.094, .097, .104, .108, .129, .137, .141, .157, .181 (nine weeks)).

The difference in those hours is often substantial. (E.g., JX109.093—.094 (8 generator hours,

20.65 batch plant hours), .097 (18 generator hours, 28 batch plant hours), .181 (26.25 generator

hours, 42 batch plant hours)). The same is true of the Design Claim, though the batch plant sat

idle for four weeks during that period. (JX104.146, .164, .167, .170 (four weeks where Lodge

reported that the batch plant ran longer than the generator); JX104.149, .152, .155, .158 (zero

hours for both the generator and batch plant)).

There are only two instances where Lodge reported running the generator more than it

ran the batch plant. (JX109.129 (5 generator hours, 4 batch plant hours); JX104.161 (2.75

generator hours, zero batch plant hours)). Given running the generator was a prerequisite to

running the batch plant, one might expect that the generator operating hours would occasionally

outpace the batch plant operating hours. However, based on the testimony of Lodge employees

and the expert from the United States, the inverse would be impossible. The Court finds that had

Lodge properly recorded batch plant operating time based on generator operating time, Lodge

would have reported far fewer operating hours for the batch plant in both its Dewatering and

Design claims.

Mr. Rousseau’s inability to provide a credible and coherent account of the events

surrounding Lodge’s method for reporting batch plant run-time leaves the Court with little

reliable information on which to make a factual finding in Lodge’s favor. The claims documents

contradict Mr. Rousseau’s testimony and indicate that there was no correlation between batch

plant operation time and Mr. Wederath’s work hours. The Court finds that Lodge utilized

different metrics to report run-time for the batch plant: in submitting its Dewatering and Design

claims, Lodge used Mr. Wederath’s timesheet; but for its internal reporting purposes, Lodge used

the metered hours from the generator. However, the Court is convinced by the evidence that

generator hours were the only reasonable or reliable metric to calculate batch plant operating

time. Consequently, Lodge’s calculation of its equipment costs with respect to the batch plant

was false because it relied on a wholly inappropriate metric for measuring run-time.

As a matter of common sense and experience in the contracting industry, Mr. Dunn was

aware that using a time metric that did not correspond to the actual run-time of the batch plant

would render Lodge’s calculation of total batch plant operating costs misleading. (Dunn, TR at

817:22-818:25 (testifying to his experience in the business of construction)). Lodge knew the

26

hours for the batch plant run-time should have been determined using the meter on the generator.

Mr. Dunn indicated that understanding by attempting to confirm that the operating hours Lodge

reported internally for the batch plant were the same as those reported for the generator. (JX081

(Mr. Dunn asking Mr. Rousseau “The operating hours you give Debbie each week for the batch

plant are the same as the generator. Correct?”)). Once Mr. Rousseau responded in the negative,

Mr. Dunn knew Lodge’s claim incorporated operating hours that were based on an employee

timesheet rather than the generator’s meter. And Mr. Dunn reviewed the rate information in the

Dewatering Claim concerning the costs of operating the batch plant. (Dunn, TR at 950:14—18).

In setting forth those costs in Lodge’s Dewatering and Design claims, Lodge fully intended that

the Army Corps would pay based on that inappropriate time metric. (Dunn, TR at 950:19-23).!°

D. The Dewatering Pumps

The contract included a line item for “Dewatering” in a fixed price lump sum amount of

$11 million. (SOF { 66; see also JX029.004). That line item, Contract Line Item Number

(“CLIN”) 0005, was divided into five pay items, three of which related to the construction of the

cofferdam. (JSOF 4 67; see also JX028.008). Those three line-items—CLINs 5-000, 5-010, and

5-020—comprised $7,450,000 of the $11 million. SOF 4 67; see also JX028.008). The other

two line-items—CLINs 5-100 and 5-110—totaled $3,550,000 and were related to dewatering

activities. (JSOF {| 68-69). CLIN 5-100—totaling $910,000—related to dewatering the “borrow

pits” from which material was extracted to create soil cement. (/d.). CLIN 5-110—totaling

$2,640,000—telated to dewatering the area inside the cofferdam to achieve dry conditions

required for work on the levee. (/d.).

The Army Corps and Lodge agreed to divide payments for CLINs 5-100 and 5-110 into

equal monthly installments. (/d. at 70). The Army Corps would pay Lodge fifteen monthly

installments of $60,666.67 for CLIN 5-100 and fourteen monthly installments of $188,571 for

CLIN 5-110. (/d.).° In calculating the financial impact for the inefficiency portion of its

Dewatering Claim, Lodge applied its inefficiency ratio to a pool of costs—which included

operating and standby costs for Lodge’s dewatering pumps—from July 5, 2011 through January

14, 2012. Ud. at | 71). Lodge’s Design Claim included standby costs of $545,236 for its

dewatering pumps for the period from March 29, 2012 through May 30, 2012. (JSOF 4] 72-73).

The fixed sum payments allocated risk to both parties—whether the pumps were used more or

less than anticipated, the Army Corps would pay Lodge those fixed sums. (Gannon, TR at

88:16—89:9; Gore, TR at 539:10—24). In other words, if Lodge completed the project early, the

Army Corps would still pay Lodge the full fixed price.

'8 Mr. Dunn testified that he could not remember the Design Claim. (Dunn, TR at 951:8-10).

However, he also testified that he did not believe the Design Claim contained errors. (/d. at

897:24-898:17).

' Lodge and the Corps originally agreed to bill CLIN 5-110 in seventeen installments at

$155,294.12. When Lodge finally began dewatering the cofferdam area, the Corps and Lodge

revised the terms to compress the payments into fourteen months. The fixed total sum remained

unchanged. (Gannon, TR at 95:12-18).

27

The fixed sum payments compensated Lodge for storage costs and pump costs, which

included “fuel, maintenance and monitoring, and modif[ications] as needed” as well as any costs

associated with moving the pumps or “adding and reducing as pumping efforts are warranted.”

(JX028.008). As of January 20, 2012—the date of Lodge’s twelfth invoice to the Army Corps—

Lodge had billed $1,508,571.43 to CLIN 5-110 for eight months of dewatering operations in the

cofferdam area. (JX038.008, .031; Gore, TR at 544:3-545:19). That eight-month period

encompassed the six months that comprised Lodge’s Dewatering Claim, which ran from July 6,

2011 through January 14, 2012. (Schaeb, TR at 1175:8-15; JX109.209). Lodge’s Dewatering

Claim included equipment costs for running the dewatering pumps in the cofferdam area despite

those costs having already been compensated by the Army Corps’ monthly installment

payments. (Schaeb, TR at 1173:21-1174:19). The costs of running the dewatering pumps in the

cofferdam area were added to Lodge’s cost pool which Lodge then multiplied by its inefficiency

ratio as part of its Dewatering Claim. (/d.). Lodge added those costs despite the all-inclusive

nature of CLIN 5-110, which Lodge understood would be compensated by fixed monthly

payments regardless of how much dewatering progress Lodge made in that month. (Gore, TR at

539:21—24). Thus, Lodge’s Dewatering Claim sought compensation for equipment costs related

to dewatering the cofferdam to which it was not entitled because it had already been

compensated through the fixed price arrangement.

Lodge offered some evidence that inclusion of dewatering operations in its Dewatering

Claim cost pool related to its differing site condition claim. (Case No. 13-500, Lodge’s Opp. to

Mot. for Leave at 26; Dunn, TR at 1074:25—1075:10). For example, Lodge offered a “theory”

that the weight of the water on the site, increased due to rainfall, pulled water up from the

groundwater table due to displacement. (Gore, TR at 597:18-599:21). No expert testimony

supported this vague assertion. Lodge takes a litigation position that its actual monthly costs

exceeded the costs anticipated when it computed the lump sum amount for dewatering in its bid

for the contract. (Case No. 13-500, Lodge’s Opp. to Mot. for Leave at 26). Lodge maintains that

the monthly installments did not contemplate additional costs that Lodge experienced as a result

of unanticipated conditions and therefore, Lodge was entitled to bill for those unanticipated

costs. (/d.). Even setting aside the all-inclusive nature of the fixed price arrangement, Lodge

provided little evidence supporting its claim that, due to rain, the pumps had to work longer and

harder than either party anticipated. (See Gore, TR at 597:18-598:11, 629:19-630:8 (testifying

about the increased runtime of the dewatering pumps)). Lodge could not identify any

documentation of increased effort expended by its dewatering pumps. (Dunn, TR at 974:10—

975:5). Furthermore, Lodge has no documentation of a baseline operating effort from which to

measure any increased effort by the dewatering pumps. (/d.).

Perhaps more pertinently, Lodge’s pumps were not utilized in direct relation to its

differing site condition claim. Lodge used the pumps to move water from the levee area to the

impoundment areas. (Gore, TR at 539:25—540:12). Lodge’s differing site condition claim, which

was not at issue in this trial, generally alleged that the water impoundment areas failed to

percolate as expected. (Case No. 13-500, Lodge’s Opp. to Mot. for Leave at 25). Therefore, as

Lodge tells it, Lodge encountered more water on the site and had to undertake operations to

move water out of the impoundment areas adding unanticipated costs. (Gore, TR at 540:13—15).

But Lodge moved the water out of the impoundment areas to offsite locations—namely the

Hillsboro Canal to the south—using gravity. U/d. at 540:20-542:3). Lodge did not use its

dewatering pumps to move water out of the retention areas to offsite locations. (/d. at 541:16-

28

542:3; Dunn, TR at 848:1—849:9). In summary, Lodge’s alleged differing site conditions would

not implicate Lodge’s dewatering pumps because the dewatering pumps moved water from the

levy to the impoundment areas but were never used to move water from the impoundment areas

to offsite locations. Therefore, any contention that Lodge was entitled to bill for dewatering

pump operating costs in addition to the fixed installment payments is unsupportable.

Mr. Dunn knew that Lodge was being paid a fixed sum through monthly installments for

dewatering operations. (Dunn, TR at 973:19—24). He understood that the fixed sum, though

divided into monthly payments, was all-inclusive and imposed risk on both parties:

Lodge’s Counsel: Okay. Can you describe in simple terms the deal between

you and the Corps of Engineers for the dewatering pumps? Was it a fixed-

price deal?

Mr. Dunn: It was just a lump-sum price.

Lodge’s Counsel: And you would get paid per month for, say, 1/14 of those

costs if it was a 14-month job?

Mr. Dunn: Yes.

Lodge’s Counsel: All right. And you did bill monthly and you got paid

monthly; correct?

Mr. Dunn: Yes.

Lodge’s Counsel: Well, and that was a fixed price. So if you did more

dewatering, you'd have to eat that cost; nght?

Mr. Dunn: Correct.

Lodge’s Counsel: And if you did less, you'd be a winner?

Mr. Dunn: Under normal conditions.

Lodge’s Counsel: Right.

Mr. Dunn: And under the conditions that we anticipated when we bid the

project.

Lodge’s Counsel: And so in your claim under the construction inefficiency

ratio, you attempt to recover extra dewatering pump costs; right?

Mr. Dunn: Absolutely. Yes.

Lodge’s Counsel: Okay. And those are above what you had billed for and

received during the course of the project?

[objection]

29

Lodge’s Counsel: Are those above?

Mr. Dunn: Yes. Yes.

(Dunn, TR at 1073:10—-1075:14). He also knew Lodge, in its Dewatering Claim, was seeking

additional compensation for dewatering operations over and above the monthly installments. (/d.

at 972:20—973:6). It was his intention, in submitting the Dewatering Claim, for the Army Corps

to pay Lodge for dewatering operations over and above the monthly installment amount. (/d.).

Mr. Gore reviewed each of Lodge’s pay estimates, signed them, and submitted them to the Army

Corps. (Gore, TR at 531:15—532:9). Therefore, he was aware that Lodge was being compensated

for dewatering operations through fixed monthly installments. (See, e.g., id. at 539:21—24).

Though Mr. Gore did not directly prepare Lodge’s certified claims, he did assist that

preparation through discussions with Paul Perkins and Cabot Dunn. (/d. at 518:2—25, 519:3-—

52:19). Curiously, Mr. Dunn “made a conscious decision” to exclude Mr. Gore from reviewing

the final version of the Dewatering Claim. (/d. at 521:1—9). Mr. Dunn relied primarily on Mr.

Gore’s work in submitting its Dewatering Claim, but Mr. Dunn could not recall “[going] through

the pay applications in detail to determine exactly what [Lodge was] billing for.” (Dunn, TR at

973:7-18).

The Court finds that Lodge was aware of the fixed price for dewatering and knowingly and

intentionally included dewatering pump operating costs in its certified Dewatering Claim that

Lodge submitted to the Army Corps. Further, the Court finds that Lodge knew or should have

known that those operating costs were not compensable under the contract’s fixed price

arrangement for dewatering operations.

Ill. Conclusions of Law

The United States brings two counterclaims in fraud against Lodge: (1) a False Claims

Act claim under 31 U.S.C. § 3729 ef seq.; and (2) a Special Plea in Fraud claim under 28 U.S.C.

§ 2514. (Case No. 13-500, Def.’s Am. Answer and Counterclaims, ECF No. 95; see also Case

No. 13-499, Def.’s Am. Answer and Counterclaims, ECF No. 12). Each of these claims requires

the United States to show not only presentation of a false claim, but also a level of knowledge

and intent on the part of Lodge and its agents. “False” means untrue, deceitful, or erroneous.

False, Black’s Law Dictionary p. 718 (10th ed. 2014).

“Under the False Claims Act, ‘[a]ny person who. . . knowingly presents’ to the

government ‘a false or fraudulent claim for payment or approval’ ‘is liable to the United States

Government for a civil penalty . .. plus 3 times the amount of damages which the Government

sustains.’” Daewoo Eng’g & Const. Co. v. United States, 557 F.3d 1332, 1340 (Fed. Cir. 2009)

(quoting 31 U.S.C. § 3729(a)). A “claim” includes any request or demand for money presented

to an officer, employee, or agent of the United States. 31 U.S.C. § 3729(b)(2). Although a

“claim” is a term of art under the False Claims Act, for context, a “false claim” is commonly

understood as an “assertion or statement that is untrue,” especially “overbilling.” False Claim,

Black’s Law Dictionary p. 719 (10th ed. 2014). False Claims Acct liability applies not only to

formal claims submitted to the government for payment but also to submission of “false

record[s] or statement[s] material to a false or fraudulent claim[.]” 31 U.S.C. § 3729(a)(1)(B). A

30

statement is material if it has “a natural tendency to influence, or be capable of influencing, the

payment or receipt of money or property.” § 3729(b)(4). The False Claims Act contains a civil

penalty that may be imposed if the trial court finds fraud, regardless of whether the government

sustained any actual damages. § 3729(a). The United States seeks imposition of that penalty

here. (Case No. 13-500, Def.’s Am. Answer and Counterclaims at 28).

Whether a contractor “knowingly” presents a false claim or makes a false statement or

record is broadly defined. The False Claims Act requires a showing of actual knowledge,

deliberate ignorance, or reckless disregard for the truth of a false or fraudulent claim. 31 U.S.C. §

3729. “[R]eckless disregard in this context is not a ‘lesser form of intent,’ but an extreme version

of ordinary negligence.” United States v. Krizek, 111 F.3d 934, 942 (D.C. Cir. 1997) (internal

quotations omitted). A False Claims Act “violation may be established without reference to the

subjective intent of the defendant.” /d. (finding that “[i]n failing ‘utterly’ to review the false

submissions, [the defendant] acted with reckless disregard.”). “[T]he False Claims Act covers

not just those who set out to defraud the government, but also those who ignore obvious

deficiencies in a claim.” Horn & Assocs., Inc. v. United States, 123 Fed. Cl. 728, 763 (2015)

(explaining that Congress intended the False Claims Act to encompass “the problem of the

‘ostrich-like’ refusal to learn of information which an individual, in the exercise of prudent

judgment, had reason to know.”).

The Court of Federal Claims has applied the “reckless disregard” standard to encompass

false claims submitted and attributable to complicated cost accounting schemes and less-than-

precise recordkeeping. UMC Elecs. Co. v. United States, 43 Fed. Cl. 776, 793 (1999), aff'd, 249

F.3d 1337 (Fed. Cir. 2001) (“It is apparent that this reckless disregard standard prevents

defendants from simply pointing to confusion over invoices and billing records as a complete

defense.”). As Judge Horn explained in UMC Elecs.:

[A]t a minimum, every party filing a claim before the contracting officer and

this court has a duty to examine its records to determine what amounts the

government already has paid or whether payments are actually owed to

subcontractors or vendors. The case law stands for the proposition that a

failure to make a minimal examination of records constitutes deliberate

ignorance or reckless disregard, and a contractor that deliberately ignored

false information submitted as part of a claim is liable under the False Claims

Act. To find otherwise would allow parties filing an action in this court to

“double-bill” the government and then hide behind a posture of feigned

ignorance.

Id. at 794 (internal citation omitted) (emphasis added). “The government must establish a

violation of the FCA by a preponderance of the evidence.” Veridyne Corp. v. United States, 758

F.3d 1371, 1378 (Fed. Cir. 2014).

The Special Plea in Fraud counterclaim is a forfeiture claim and affirmative defense to

liability. The relevant part of the code, titled “Forfeiture of fraudulent claims,” reads:

A claim against the United States shall be forfeited to the United States by

any person who corruptly practices or attempts to practice any fraud against

31

the United States in the proof, statement, establishment, or allowance

thereof. In such cases the United States Court of Federal Claims shall

specifically find such fraud or attempt and render judgment of forfeiture.

28 U.S.C. § 2514. In pursuing a Special Plea in Fraud claim, “the government bears the burden

of proving that the claimant (1) knew the claim was false and (2) intended to deceive the

government by submitting it.” Young-Montenay, Inc. v. United States, 15 F.3d 1040, 1042 (Fed.

Cir. 1994). The forfeiture penalty is mandatory, and must be imposed as to the entire claim if the

trial court finds a fraudulent act or attempt:

There is no suggestion in the statute that a contract can be divided up into

performance sectors to allow payment of some claims on a corrupted contract

while other claims on the same contract are forfeited. The effects of a

fraudulent act, therefore, have an impact on every aspect of contract

performance and the entirety of the claim, making it impossible to distinguish

between tainted and untainted claims, for which reason the contractor may

not recover on any claims under the contract.

UMC Elecs., 43 Fed. Cl. at 790-91 (collecting cases).

The Special Plea in Fraud counterclaim demands the claimant carry a heavier burden of

proof than the False Claims Act. To prevail under 28 U.S.C § 2514, the United States must

establish, by clear and convincing evidence, that the contractor submitted claims with knowledge

of their falsity and with an intent to defraud the United States government. Veridyne Corp., 758

F.3d at 1376-77. In order to reach that burden, the claimant must “place in the ultimate

factfinder an abiding conviction that the truth of its factual contentions [is] ‘highly probable.

State of Florida v. State of Georgia, 141 §. Ct. 1175, 1180 (2021) (quoting Colorado v. New

Mexico, 467 U.S. 310, 316 (1984)).

399

Importantly, with respect to both claims, mere mistakes do not rise to the level of fraud.

United States ex rel. Lamers v. City of Green Bay, 168 F.3d 1013, 1018 (7th Cir. 1999)

(summarizing innocent mistake cases). Exploration of legal gray areas is also not fraud. UMC

Elecs. Co., 43 Fed. Cl. at 794 (“A contractor, upon submission of a claim, who is aware of and

takes advantage of a disputed legal issue does not knowingly commit fraud.”). Inconsistencies, if

they can be reasonably explained, also do not constitute fraud. Larry D. Barnes, Inc. v. United

States, 45 F. App’x 907 (Fed. Cir. 2002) (“Inconsistencies, even if the discrepancy is large, do

not rise to the level of fraud if there is a reasonable explanation for them.”) (emphasis added).

A. Lodge’s Dewatering Claim was fraudulent with respect to the costing of the Euclid

Trucks.

In submitting its Dewatering and Design claims to the Army Corps, Lodge used operating

and standby rates for a 2006 773D Caterpillar Truck, a piece of equipment specifically listed in

the USACE Manual. (Dunn, TR at 921:5—16, 927:12—17). In doing so, Lodge represented to the

Army Corps that the equipment Lodge used on the project was either identical to that piece of

equipment listed in the USACE Manual or “equivalent” in terms of size, capacity, horsepower,

and value. (JX001.337—.338; Schaeb, TR at 1163:4—1165:21). That representation was false.

32

Universal Health Servs., Inc. v. United States, 136 S. Ct. 1989 (2016) (False Claims Act

“liability can attach when the defendant submits a claim for payment that makes specific

representations about the goods or services provided, but knowingly fails to disclose the

defendant’s noncompliance with a statutory, regulatory, or contractual requirement.”); see also

Crane Helicopter Ser., Inc. v. United States, 45 Fed. Cl. 410, 413-414 (1999) (discussing

whether misrepresentation of equipment used during contract performance renders a claim

“false”) abrogated on other grounds by Kellogg Brown & Root Servs., Inc. v. United States, 728

F.3d 1348 (Fed. Cir. 2013). Lodge used older Euclid R50 trucks, not the Caterpillar 773D trucks

listed in the USACE Manual. Lodge’s Euclids were worth, at most, between $14,000 and

$24,000 each—far less than a 2006 773D Caterpillar Truck, which the USACE Manual valued at

$888,686 per truck. (JX072.5—072.8; JX001.252). Although Lodge argues its trucks were rebuilt,

Lodge offered no evidence to support the value of any capital improvements. (Dunn, TR at

913:17-917:14).

Lodge submitted these false claims to the Army Corps with the knowledge that they were

false. Lodge knew that its Euclids were not accurately valued at $888,686 each—it possessed

information about the purchase price and considered that value in seeking a sale after any capital

improvements. (/d. at 904:22—-906:8, 925:12—928:9; DX397). That value—$40,000 for all four

Euclids—varies greatly from the $3,554,744 collective value had the trucks been the same make

and model as the ones Lodge reported using. Mr. Perkins advised Mr. Dunn that Lodge would

need to adjust the rates of its trucks because the USACE Manual rate for the 773D Caterpillar

would be inappropriate. (JX068; Perkins, TR at 712:6-713:1, 717:5—719:3). Lodge proceeded to

submit its Dewatering and Design claims using the false rate anyway. (Dunn, TR at 1066:7—

1067:20). The United States submits that, after Lodge applied its inefficiency ratio and amended

its Complaint to assert additional Design Claim damages, Lodge sought a total of $128,562 for

the Euclids after applying credits for repair time. (USA Trial Brief at 15).

Lodge’s arguments that mispricing its Euclids was not fraudulent are unpersuasive. First,

Lodge argues that Equipment Watch is a reputable equipment costing database and therefore,

Lodge’s use of that database was not a misrepresentation. (Lodge Trial Brief at 20-21). Given

Lodge’s knowledge that it was required to comply with the USACE Manual rates, the reputation

of Equipment Watch is irrelevant. Even if it were permissible, Lodge only used that database to

analogize an erroneous rate from the USACE Manual. Lodge did not use the Equipment Watch

rate in its claims or otherwise explain to the Army Corps why it believed that rate should be

considered analogous to the 773D Caterpillar rate. The USACE Manual contains clear

instructions, which Lodge understood, regarding costing equipment not listed in Table 2-1.

Lodge wholly ignored those instructions.

Second, Lodge makes much of the fact that it “reduced” the operating rates for Euclids

when it carried them from its job costing ledger to the Dewatering and Design claims. (See, e.g.,

Lodge Trial Brief at 22—23). But Lodge only reduced its operating rates so they would align with

the USACE Manual rates, rather than appear to be obviously independently derived. It is not far-

fetched to believe that Lodge might have reduced the Euclid operating rates in an attempted

effort to avoid detection. See Sonnentheil v. Moerlein Brewing Co., 172 U.S. 401, 410 (1899)

(“Parties contemplating a fraud frequently pursue such devious courses to conceal their designs,

and resort to such subtle practices to mislead. . ..”); ef In re Gen. Motors LLC, 257 F. Supp. 3d

372, 442 (S.D.N.Y. 2017) (“fraudulent concealment is characterized by deceptive acts or

33

contrivances intended to hide information, mislead, avoid suspicion, or prevent further inquiry

into a material matter.”) (internal quotations omitted).

Regardless of why or whether Lodge reduced the operating rates for its Euclids, Lodge’s

argument misses the same point made previously; Lodge knew that by selecting the USACE

Manual to report its rates, it was required to use the USACE Manual methodology in costing its

equipment. It failed to do so. Neither the USACE Manual nor FAR § 31.105 allows the

contractor to mix and match equipment rate schedules to report ownership and operating costs.

Because Lodge did not use the methodology required by the USACE Manual, any reductions to

an erroneous rate are also irrelevant.

In summary, the United States has established—by clear and convincing evidence—that

Lodge’s Dewatering and Design claims were false with respect to the operating and standby

costs of its Euclid R50 dump trucks. The United States has also established—by clear and

convincing evidence—that Lodge knew its Dewatering and Design claims contained materially

false records and statements when it certified and submitted its claims to the Army Corps.

Consequently, the Court finds that, under both 31 U.S.C. § 3729 and 28 U.S.C. § 2514, Lodge’s

Dewatering and Design claims were fraudulent with respect to the costs of its Euclid trucks.

B. Lodge knew or should have known that its Inefficiency Ratio would produce a

fraudulent claim.

Lodge’s method for calculating its inefficiency ratio was flawed in at least two ways.

First and foremost, it was not a reasonable, accurate, or truthful measure of inefficiency. Second,

even if it were a true measure of inefficiency in concept, the inefficiency ratio captures days that

are not properly part of the Dewatering Claim at all. Standing alone, each flaw renders Lodge’s

claim false. The combination of the two flaws belies that Lodge simply made a mistake in

calculating its Dewatering Claim. Lodge knew or should have known that the inefficiency ratio

would produce a fraudulent claim.

With respect to the denominator, contract modification PO0009 should have been

incorporated to some extent—a fact Lodge has acknowledged. However, though its exclusion

may have caused Lodge’s affirmative claims to fail on their merits, that issue was not before the

Court in this trial. Lodge’s failure to account for modification POO009 was not, on its own,

fraudulent because it turns on a legitimately disputed legal question. See UMC Elecs. Co., 43

Fed. Cl. at 794.

Lodge’s inefficiency ratio was inaccurate, and thus the value of the Dewatering Claim

was inaccurate. The inaccuracies are attributable to the true number of actual days in the

numerator of the ratio. Lodge’s methodology for tallying actual days spent working on Section 1

demonstrates a failure to make a minimum examination of records and thus, constitutes a

reckless disregard for the accuracy of the Dewatering Claim. The United States demonstrated

Lodge’s reckless disregard for the accuracy of its Dewatering Claim by clear and convincing

evidence. The United States has also shown that, more likely than not, Lodge intentionally used

the inefficiency ratio to fraudulently inflate its Dewatering Claim. Consequently, the Court finds

that Lodge’s inefficiency ratio was fraudulent under both 31 U.S.C. § 3729 and 28 U.S.C. §

2514.

34

i. Lodge knew or should have known that its “inefficiency ratio” was not a

reasonable, accurate, or truthful measure of inefficiency.

Lodge used a rudimentary “tick mark” methodology to tally actual days in its attempt to

demonstrate that the work Lodge performed in Section 1 overran the days it allocated for that

work. However, as Ms. Callaway acknowledged, that methodology was so fundamentally flawed

that it does not reasonably, accurately, or truthfully characterize inefficiencies. By incorporating

that tally into the inefficiency ratio and applying the ratio to a cost pool, Lodge grossly

overstated the value of its Dewatering Claim. That overstatement renders Lodge’s Dewatering

Claim false. Brunswick Bank Trust Co. v. United States, 707 F.2d 1355, 1365 (Fed. Cir. 1983)

(misrepresentations render a claim false to the “extent of the exaggeration.”).

Ms. Callaway’s utilization of that tick mark method shows a reckless disregard for the

accuracy of Lodge’s certified claim. In her review of the daily logs, Ms. Callaway did not

determine whether the inefficiency ratio would measure effort expended or resources used.

Despite her training in scheduling, significant education, and experience in the construction

industry, Ms. Callaway made no effort to consider whether a tick mark was an appropriate

measure of a single activity day. She failed to consider whether each incremental increase in the

number of activity days would reasonably correspond to an increase in her ratio. Finally, despite

knowing that increasing the ratio would increase the total damages claimed, Ms. Callaway made

no effort to reconcile the dollar value of each activity day she included in her ratio with the

actual resources Lodge might expend in a legitimate activity day.

The United States’ expert, Eric Schaeb, demonstrated that Lodge’s ratio valued each

activity day at approximately $6,500 per day. (Schaeb, TR at 1159:11—13). Applying that value

to several days where work was minimal, the United States credibly demonstrated that Lodge

often billed the Army Corps at rates of $2,000, $2,167, $4,333, $10,800, and even $21,677 per

hour for work frequently performed by only a single laborer or piece of equipment. (USA Trial

Brief at 24-25). The Court concludes that Lodge’s failure to examine the effort or resources

expended and consider whether the tick mark methodology reasonably, accurately, and truthfully

measured daily inefficiencies clearly and convincingly shows Lodge exhibited a reckless

disregard for the accuracy of its Dewatering Claim.

But Lodge’s conduct likely goes beyond mere reckless disregard for the accuracy of its

claim. The Court additionally concludes that, more likely than not, Lodge intentionally used its

inefficiency ratio as a tool to inflate the damages calculation of the claim it presented to the

Army Corps. “The court may . . . consider circumstantial evidence in making its determination.”

Alcatec, LLC v. United States, 100 Fed. Cl. 502, 517 (2011), aff'd, 471 F. App’x 899 (Fed. Cir.

2012) (citing Kamen Soap Prods. Co. v. United States, 129 Ct. Cl. 619, 642 (1954) (“About the

only way a just conclusion can be reached is by placing the questioned documents and

statements alongside well-known and established facts.”)). As stated above, at the time she

prepared the inefficiency ratio, Ms. Callaway understood the relationship between increasing the

ratio and increasing the amount of damages Lodge would be seeking in its Dewatering Claim.

Mr. Perkins reviewed the Dewatering Claim; he recommended against using the ratio or tailoring

it to the effort expended and equipment used. Mr. Perkins saw this issue as “the big one,”

warning Mr. Dunn that the Army Corps would “immediately object to this method of calculating

impacts.” (JX075; Dunn, TR at 1043:12—22). Though Lodge reduced the inefficiency ratio “to be

35

conservative” based on Mr. Perkins’s warnings, Lodge still utilized the ratio in its Dewatering

Claim despite knowing the revisions would not abate Mr. Perkins’s concerns. (Dunn, TR at

1044:15—24). Furthermore, reducing the amount of a false claim to make it more plausible does

not negate an act of fraud. In fact, if anything, it indicates that Lodge attempted to conceal its

fraudulent acts by reducing its inflated claims to a degree that might evade detection. See Martin

v. Consultants & Administrators, Inc., 966 F.2d 1078, 1103 (7th Cir. 1992) (“Of course people

who commit frauds often try to conceal them, as distinct from merely hoping that no one will

notice so long as they don’t advertise the fraud.”) (Posner, J. concurring).

Lodge certified and submitted its Dewatering Claim seeking $3,282,123.02. (JSOF [J 18,

20). Lodge asserted that the cost impact of the inefficiencies was $2,073,699.42. (JX109.092).

Lodge arrived at that figure by multiplying its costs of “anticipated production” ($1,402,759.53)

by its 247.83% inefficiency ratio to arrive at its “actual cost” of production ($3,476,458.95).

(/d.). Lodge then added the costs of labor and equipment to install culverts and applied “credit

for equipment down time due to repairs” to arrive at a total inefficiency-adjusted cost of

$1,983,387.17. Ud.). Lodge added this sum to the claims it intended to pass through from its

subcontractor—$1,084,017.52—and applied a 7% profit markup to arrive at the total costs of its

Dewatering Claim, adjusted for its alleged inefficiencies. (/d.). Though the United States has not

sought to recover any actual damages, the Court includes these figures to contextualize the

amount of the fraud.

The Court concludes that the persuasive circumstantial evidence demonstrates Lodge

knew, even after revisions, that its inefficiency ratio was not an accurate measure of

inefficiencies. Lodge based its Dewatering Claim on that ratio anyway. The United States has

demonstrated, by clear and convincing evidence, that Lodge presented its Dewatering Claim—

with reckless disregard for its falsity—to the Army Corps seeking payment. The Court

additionally concludes it is more likely than not that, in utilizing the inefficiency ratio, Lodge’s

intention was to fraudulently inflate its Dewatering Claim. Therefore, the United States has

demonstrated that under both 31 U.S.C. § 3729 and 28 U.S.C. § 2514, Lodge’s Dewatering

Claim was fraudulent.

ii. Lodge’s “inefficiency ratio” fraudulently counts days outside the claim period.

Even if the ratio were a conceptually reasonable measure of inefficiencies, which it is not

Lodge’s erroneous inclusion of days outside of the claim period was an intentional

misrepresentation that rendered the Dewatering Claim fraudulent. Lodge’s Dewatering Claim

purported to capture the effects of inefficiencies due to dewatering difficulties from July 6, 2011

to January 14, 2012. (JX109.209 (“The impacts covered as a part of this Contract Disputes Act

(‘CDA’) claim occurred from July 6, 2011 through January 14, 2012[.]”)). However, in

calculating the number of activity days for the numerator of her ratio, Ms. Callaway included

activity days that correspond to work performed after January 14, 2012. Lodge’s inclusion of

those 55 days inflated its inefficiency ratio from 200% to 247%. (Schaeb, TR at 1159:1—10).

Inflation of the ratio increased Lodge’s Dewatering Claim by $358,953, rendering Lodge’s

Dewatering Claim clearly and convincingly false.

2

Lodge’s inclusion of days outside of that period clearly and convincingly shows, at the

least, a failure to make a minimum examination of records in reckless disregard as to the

36

accuracy of its certified claim. But the evidence also clearly and convincingly supports a finding

that Lodge intentionally included the 55 days to fraudulently inflate its ratio and, by that fact, its

Dewatering Claim. As the Court noted previously, Ms. Callaway testified inconsistently

regarding whether inclusion of those days was proper or intentional. The Court has also noted its

concerns as to Ms. Callaway’s credibility. The Court accepted as a judicial admission that Ms.

Callaway previously testified that “no days after January 14, 2012 should be counted in the

calculations of the actual duration delays[.]” (Opinion on Mot. in Lim., ECF No. 72). But Mr.

Dunn adamantly affirmed at trial that the inclusion of those 55 days after January 14, 2012 was

intentional, not a mistake in preparing the claim:

The United States: Okay. Now, Lodge, in fact, used days after January 14th,

2012, in its dewatering claim; correct?

Mr. Dunn: I am familiar with the 55-day issue, yes.

The United States: And Lodge knew that including days after January 14th

would make the inefficiency ratio indicate higher inefficiency; correct?

Mr. Dunn: Based upon the way the ratio works, that -- yeah, actual days

would increase the inefficiency ratio.

The United States: And a higher inefficiency ratio meant there would be a

higher cost claim against the government; correct?

Mr. Dunn: The higher the inefficiency ratio, the higher the cost claim, yes,

that’s correct.

The United States: Okay. There’s no mistake of mere carelessness with

respect to Lodge’s claims after January 14th, 2012; correct?

Mr. Dunn: I didn’t understand the question. “Carelessness”?

The United States: This is not a mistake. Including the days after January

14th, 2012, was not mere carelessness with respect to Lodge’s claims;

correct?

Mr. Dunn: [ don't think this claim is careless.

The United States: Right. Lodge knew what it was doing. And it intended

to obtain money from the United States in connection with the days after

January 14th, 2012; correct?

Mr. Dunn: We intended to be paid for our -- the delays that we were

suffering based upon this.

The United States: Can you answer the question that I asked you? Lodge

knew what it was doing. And it intended to obtain money from the United

States in connection with the days after January 14th, 2012; isn’t that correct?

37

Mr. Dunn: If -- yes, if they were included in the actual, we were.

(Dunn, TR at 947:8-948:18).

In arguing that its Dewatering Claim was not fraudulent, Lodge contends that (1) it

retained Mr. Perkins to assist with claim preparation; (2) it ultimately reduced its claims with

credits and set-offs; and (3) any falsities are essentially a wash given the mistakes Lodge made in

the Army Corps’ favor. (Lodge Trial Brief at 39-46). None of these arguments are relevant to the

two basic issues the Court is required to decide in a fraud case—whether the claim submitted

was false and whether the contractor knew it was false when submitted. Simply because Lodge

might demonstrate calculations that might hypothetically accrue to the benefit of the United

States, none of which have been convincingly established, does not mean Lodge is relieved of its

burden of truthfulness in presenting its claims. The Court finds Lodge’s arguments unpersuasive

and undeserving of extensive discussion.

With Mr. Dunn’s assertions, the United States has clearly and convincingly demonstrated

that Lodge intentionally included 55 days after January 14 in its inefficiency ratio, despite

representing to the Army Corps that its Dewatering Claim contained costs from July 6, 2011

through January 14, 2012. Lodge knew the effect that increasing the inefficiency ratio would

have on the damages asserted in the Dewatering Claim. Therefore, the Court concludes—by

clear and convincing evidence—that Lodge fraudulently exaggerated its Dewatering Claim in

violation of both 31 U.S.C. § 3729 and 28 U.S.C. § 2514.

The United States submits that removing the 55 days Lodge fraudulently included in its

inefficiency ratio would reduce the inefficiency factor from 247.83% to 200%. (USA Trial Brief

at 23; Schaeb, TR at 1159:1—10). In isolation, this adjustment reduces Lodge’s Dewatering

Claim by $358,953. (Schaeb, TR at 1159:1-10). Though the United States has not sought to

recover actual damages, the Court includes these calculations to contextualize the amount of the

fraud.

iii. Lodge’s failure to incorporate the impacts of contract modification PO0009

was not fraudulent.

Contract modification P00009 consolidated two CLINs into CLIN 0007. As part of the

modification, the Army Corps authorized Lodge to bill an additional $1,990,000 and granted

additional days to complete excavation. In calculating its inefficiency ratio and submitting its

Dewatering Claim to the Army Corps, Lodge did not incorporate those additional days.

Though the United States asserts that Lodge’s failure in this regard was fraudulent, the

Court disagrees. Lodge never submitted pay applications against the increased authorization.

Lodge did not complete excavation of the original amount of material allocated in CLIN 0007.

But most importantly, Lodge’s Dewatering Claim explicitly stated that, in calculating its

inefficiency ratio, Lodge was utilizing the original baseline schedule which did not account for

contract modification P00009. Putting aside the issues addressed above—i.e., whether the

inefficiency ratio was a reasonable and accurate measurement of inefficiencies—the denominator

of the ratio was not a misrepresentation and thus cannot form the basis of a false claim. But even

if Lodge did misrepresent the schedule it used, Lodge’s explanation that it did not perform

38

excavation work pursuant to P00009 is a reasonable one. To be clear, the Court does not opine

that Lodge’s interpretation of the impact of PO0009 is the correct one, merely a reasonable one

that may be flawed in practice. Errors based on flawed reasoning are not fraudulent. U.S. ex rel.

Lamers, 168 F.3d at 1018 (“errors based simply on faulty calculations or flawed reasoning are

not false under the [False Claims Act].”) (citing Wang v. FMC Corp., 975 F.2d 1412, 1420-21

(9th Cir. 1992)).

Unlike the numerator of the inefficiency ratio, Lodge offered a sensible explanation of its

reasoning that it did not take advantage of contract modification POO009. That explanation is

supported in part by the fact that Lodge did not seek any additional compensation that PO0009

authorized it to seek for increased excavation. Though, as Ms. Callaway noted, Lodge probably

should have accounted for the extra days P00009 allowed Lodge to bill for equipment costs, the

Court recognizes that that impact may not have been immediately obvious to Lodge at the time it

submitted its claim. This is, again, in contrast to the numerator of the ratio which was so

fundamentally flawed as to obviously distort the cost impact of any alleged inefficiencies. Thus,

the Court concludes that Lodge’s failure to account for contract modification PO0009 was not

fraudulent under either 31 U.S.C. § 3729 or 28 U.S.C. § 2514.

C. Lodge ’s batch plant costs were fraudulent in some respects.

The United States asserts that Lodge’s Dewatering Claim fraudulently included the costs

of operating its batch plant in three ways. (USA Trial Brief at 39-42). First, the United States

argues that to the extent Lodge sought operating costs that included costs of ownership, Lodge’s

Dewatering Claim was knowingly false. Second, the United States asserts that Lodge used an

operating rate from Equipment Watch rather than the rate required by the USACE Manual,

rendering the Dewatering Claim false. Third, the United States alleges that Lodge improperly

calculated batch plant operation hours, falsely inflating the time of operation.

The Court concludes that Lodge fraudulently inflated batch plant run-time. However,

ownership of the batch plant turns on a disputed legal question and Lodge’s operating rate was

the product of a mistake. Therefore, those issues do not rise to the level of fraud.

i. The United States has not met its burden to show that batch plant ownership

costs were fraudulent.

As previously discussed, in an unusual arrangement, the Army Corps paid Lodge up front

for the entire cost to purchase, deliver, and install the batch plant. Lodge then financed roughly

75% of the purchase costs through SunTrust Bank. Despite receiving credits from the batch plant

vendor and failing to pay the principal of the loan from SunTrust, Lodge’s Dewatering Claim

sought to claim ownership costs. The United States asserts that Lodge was not entitled to claim

ownership costs related to the batch plant, yet Lodge included operating and standby costs that

featured adjustments for ownership costs. (USA Trial Brief at 40).

Part 31 of the FAR contains guidance as to whether contractors are permitted to take

depreciation on owned assets. Specifically, FAR § 31.205-11 provides that depreciation, rental,

and use charges “are unallowable on property acquired from the Government at no cost by the

contractor... ..” Lodge argues that it did not acquire the batch plant from the Government, it

39

acquired the batch plant from Loadcraft Industries, Inc., and the Government simply provided an

advance. (Lodge Trial Brief at 34). Indeed, Lodge financed the purchase of the batch plant

through SunTrust Bank, incurring interest as a cost of capital. Contractors may seek to recoup

costs of capital under FAR § 31.205-10.

Whether Lodge “acquired” the batch plant from Loadcraft Industries or the Army Corps

is amixed question of fact and law. As mentioned above, a contractor does not commit fraud

when it is “aware of and takes advantage of a disputed legal issue[.]” UMC Elecs. Co., 43 Fed.

Cl. at 794. The Court declines to resolve the legal question of batch plant ownership at this stage;

that question would be more appropriate in the context of assessing the Army Corps’ liability to

Lodge. In any event, because ownership is a disputed legal question in this case, the United

States cannot meet its burden to demonstrate fraud under either 31 U.S.C. § 3729 or 28 U.S.C. 8

2514.

ii. Lodge mistakenly reported its batch plant operating rate.

In submitting its Dewatering Claim, Lodge utilized an operating rate of $339.09 per hour.

It derived that rate from Equipment Watch. However, Lodge’s use of that rate rather than the

USACE Manual rate of $235.88 appears to have been an error due to Mr. Dunn mis-keying an

internal spreadsheet. As described previously, Mr. Dunn updated the spreadsheet, attempting to

replace the Equipment Watch rate with the USACE Manual rate. However, the evidence

suggests he updated the wrong cell pertaining to a different piece of equipment. In correcting that

error, Mr. Dunn failed to notice that the Equipment Watch rate remained in the batch plant cell.

The Court concludes that Lodge’s use of the Equipment Watch rate rather than the

USACE Manual rate is a mistake and cannot be considered fraud under either 31 U.S.C. § 3729

or 28 U.S.C. § 2514. See US. ex rel. Lamers, 168 F.3d at 1018; cf Argus Chemical Corp. v.

Fibre Glass-Evercoat, 812 F.2d 1381, 1385 (Fed. Cir. 1987) (holding that, in patent fraud cases,

“inadvertent errors or honest mistakes which are caused by neither fraudulent intent or design .. .

do not constitute fraud . . ..”) (quoting Cataphote Corp. v. DeSoto Chem. Coatings, Inc., 450

F.2d 769, 772 (9th Cir. 1971)).

iii. Lodge fraudulently inflated batch plant operating run-time.

To total its equipment costs related to the batch plant, Lodge multiplied the operating rate

by the run-time. However, Lodge’s measurement of run-time was based on a particular

employee’s hours worked, not the hours metered by the batch plant generator. The generator was

the only reasonable or accurate measurement of batch plant run-time given that the generator

must have been running for the batch plant to operate. Lodge misstated the operation costs of the

batch plant by using an employee timesheet instead of the generator’s metered hours. Therefore,

the operating costs of running the batch plant as included in Lodge’s Dewatering and Design

claims are false. *°

?° Even after the cofferdam failed, Lodge recorded batch plant operating time in its Design

Claim. (See, e.g., JX109.146, .164, .167, .170).

40

Mr. Rousseau’s email to Mr. Dunn shows that Lodge, under the direction of Mr. Dunn,

knew that it was reporting a rate based on employee timesheets rather than metered hours.

(JX081). Lodge’s use of the generator’s metered hours demonstrates that Lodge knew and

understood metered hours to be the appropriate metric for measuring batch plant run-time.

Nevertheless, Lodge intended to submit the Dewatering and Design claims while knowingly

using an inappropriate and inaccurate run-time metric. In conclusion, Lodge’s Dewatering and

Design claims were knowingly false with respect to the equipment costs of the batch plant.

Although the Court concludes that the batch plant run-time was knowingly false when

submitted, the evidence of Lodge’s fraudulent intent is circumstantial. “The court may . . .

consider circumstantial evidence in making its determination.” Alcatec, LLC, 100 Fed. Cl. at 517

(2011), aff'd, 471 F. App’x 899. But because of the gaps in the evidence, the Court is unable to

find that the evidence clearly and convincingly supports that conclusion. Nevertheless, a

preponderance of the evidence supports the Court’s conclusion that under the False Claims Act,

31 U.S.C. § 3729, Lodge’s batch plant operating costs were fraudulently submitted to the Army

Corps.

D. The Dewatering Pumps

Lodge included the operating and standby costs for its dewatering pumps—between June

5, 2011 and January 14, 2012—in the cost pool to calculate its certified Dewatering Claim.

(Schaeb, TR at 1173:21—1174:19). Effectively, Lodge represented to the Army Corps it was

entitled to recover the cost of the dewatering pumps in this six-month period. (JX038.008, .031;

Gore, TR at 544:3-545:19). However, Lodge had already been paid a lump sum for dewatering

activities that allocated risk to both parties. Consequently, Lodge’s representation had no

colorable or plausible basis and was therefore false. Daewoo Eng’g & Const. Co., 557 F.3d at

1339-40.

Lodge submitted this claim to the Army Corps with the knowledge that it was false. First,

Lodge knew the contract’s line items for dewatering activittes—CLINs 5-100 and 5-110—were

fixed price lump-sums paid in equal monthly installments. (JSOF §] 70). In fixed price contracts,

contractors assume the risk of unexpected costs. Lakeshore Eng’g Servs., Inc. v. United States,

748 F.3d 1341, 1347 (Fed. Cir. 2014). Here, Lodge knowingly assumed that risk when entering

the contract. (Case No. 13-500, Lodge’s Opp. To Mot. for Leave at 26; Gannon, TR at 88:16—

89:9; Gore, TR at 539:10—24). Further, Mr. Dunn admitted he knew the “lump-sum price” for the

dewatering pumps was all-inclusive. (Dunn, TR at 972:20-973:6). As a result, Lodge was

responsible for any costs exceeding the fixed price lump sum. (Gannon, TR at 88:16—89:9; Gore,

TR at 539:10—24). The United States proved by clear and convincing evidence that Lodge was

aware of the fixed price for costs associated with dewatering pumps.

Second, Lodge knowingly and intentionally included fraudulent dewatering pump

operating costs in its Dewatering Claim when it certified and submitted that claim to the Army

Corps. Lodge knew it already billed the Army Corps for the eight-month period containing June

5, 2011 through January 14, 2012. (See, e.g., Gore, TR at 539:21—24). Each of Lodge’s pay

estimates was reviewed by Mr. Gore before submission to the Army Corps. (/d. at 531:15-

532:9). Mr. Dunn reviewed Mr. Gore’s work when preparing and submitting Lodge’s

Dewatering Claim. (Dunn, TR at 973:7-18). Therefore, Lodge knew that including the

4]

dewatering pump costs would, in effect, “double-bill” the Army Corps. UMC Elecs. Co, 43 Fed.

Cl. at 794 (holding that a contractor cannot escape fraud claims by feigning ignorance that would

permit double-billing). Notably, Mr. Dunn admitted that Lodge intended to recover costs that

exceeded the fixed payments for CLIN 5-100 and CLIN 5-110 when it included the dewatering

pump costs in its Dewatering Claim. (Dunn, TR at 972:20-973:6). Therefore, the Court is

persuaded by clear and convincing evidence that Lodge knowingly and intentionally included

fraudulent costs in the Dewatering Claim. Veridyne Corp., 758 F.3d at 1376-77.

Even if Lodge did not have actual knowledge that including the operation costs for the

dewatering pumps was fraudulent, Lodge acted in reckless disregard for the accuracy of its

Dewatering Claim. At a minimum, Lodge was obligated to examine its records to determine

whether the government already paid the costs associated with the dewatering pumps. UMC

Elecs. Co, 43 Fed. Cl. at 794 (“every party filing a claim before the contracting officer and this

court has a duty to examine its records to determine what amounts the government already has

paid or whether payments are actually owed|[.]”). If it had, Lodge would have discovered it

previously billed the Army Corps for the six-month period between July 6, 2011 and January 14,

2012. (Schaeb, TR at 1175:8-15; JX109.209; JX038.008, .031; Gore, TR at 544:3-545:19). In

effect, Lodge “double billed” the Army Corps for the dewatering pumps’ operating costs. Failure

to make a minimum examination of regards satisfies the requisite intent for fraud under the False

Claims Act and the Special Plea in Fraud statutes. 31 U.S.C. § 3729; 28 U.S.C. § 2514.

Finally, Lodge’s inclusion of the operation costs of the dewatering pumps was not merely

an innocent mistake or an inconsistency. See City of Green Bay, 168 F.3d at 1018. Lodge

conceded it intentionally sought to recover additional dewatering pump costs, above the agreed

upon monthly amounts. (Dunn, TR at 972:20—-973:6). Lodge included $606,515 in costs related

to the dewatering pumps in its cost pool, inclusive of the inefficiency ratio factor and after the

7% profit markup. (Schaeb, TR at 1175:8—22). Before applying those adjustments, Lodge billed

the Army Corps for approximately $244,730 in dewatering pump operating costs for which

Lodge was already compensated. Accordingly, the Court concludes the United States

demonstrated by clear and convincing evidence that, under 31 U.S.C. § 3729 and 28 U.S.C. §

2514, Lodge’s Dewatering claim was fraudulent with respect to the dewatering pumps.

I. Additional Issues

Having found that Lodge practiced fraud against the United States by submitting false

claims for payment that contained statements and records material to those false claims, the

Court now turns to the applicable penalties. In addition, Lodge has requested the Court take

judicial notice of a decision in an indirectly related case pending in the District of Massachusetts.

i. False Claims Act penalties.

Although the United States attempts to quantify the “amount of the fraud” with respect to

the Dewatering and Design claims and the misrepresentations therein, the United States does not

contend that the Army Corps actually paid the amounts Lodge sought in those claims. (See USA

Trial Brief at 14-15). Conversely, the parties agree both claims were denied. (JSOF 4 17, 22).

Thus, without proof of actual damages, the Court is constrained to only impose statutory

penalties. Daewoo Eng’g & Const. Co., 557 F.3d at 1341.

42

As discussed above, False Claims Act liability attaches a mandatory civil penalty to both

formal claims submitted to the government for payment but also submission of “false record[s]

or statement[s] material to a false or fraudulent claim[.]” 31 U.S.C. § 3729(a)(1)(B). The amount

of allowable civil penalties is set by reference to two statutes. The False Claims Acct itself lists a

minimum penalty of “$5,000 and not more than $10,000, as adjusted by the Federal Civil

Penalties Inflation Adjustment Act of 1990[.]” § 3729(a)(1).

The Federal Penalties Inflation Adjustment Act revises the penalties upward, pursuant to

regulations established by individual agencies. See Bipartisan Budget Act of 2015, Pub. L. No.

114-74, § 701, 129 Stat 584, 599-600 (2015) (amending the Federal Civil Penalties Inflation

Adjustment Act). But “[fJor all violations occurring on or before November 2, 2015,” the civil

penalties must be no less than $5,500 and no more than $11,000. 28 C.F.R. § 85.3(a)(9)

(Department of Justice Regulation). Here, the violations occurred in 2013 when Lodge submitted

its false Dewatering and Design claims to the Army Corps. See Jana, Inc. v. United States, 41

Fed. Cl. 735, 743 (1998) (“the submission of a false claim, whether or not the claim is paid, is a

violation of [the False Claims Act] for which the false claimant is liable to the government for

civil penalties .. ..”) (emphasis added); see also 31 U.S.C. § 3731(b)(a) (suggesting a “violation”

occurs prior to any legal action instituted to affix liability).

The number of penalties to be assessed depends on the “acts” that violated the False

Claims Act and does not necessarily correspond to the number of claims submitted. See United

States v. Bornstein, 423 U.S. 303, 313 (1976) (explaining how to count False Claims Act

violations). Instead, the number of penalties is a fact-bound inquiry in which courts must “focus .

.. [on] the specific conduct of the person from whom the Government seeks to collect the

statutory [penalties].” /d.; see also Krizek, 111 F.3d at 939 (“The gravamen of these cases is that

the focus is on the conduct of the [party defending the claim]. The Courts asks, ‘With what act

did the [party defending the claim] submit his demand or request and how many such acts were

there?’”). In Miller v. United States, 213 Ct. Cl. 59, 72 (1977), the court rejected the United

States’ argument that “each false item used in reaching a final figure” could be counted

separately. Here, the Court finds it appropriate to impose two penalties—one each for fraudulent

acts in compiling the Dewatering Claim and the Design Claim.

However, given the extent and egregiousness of the fraudulent costs, particularly with

respect to the inefficiency ratio multiplier, the Court exercises its discretion to impose the

maximum penalty for each claim. Therefore, the Court assesses and orders Lodge to forfeit to the

United States a sum of $22,000 in civil penalties for violations of the False Claims Act, 31

U.S.C. § 3729.

ii. Special Plea in Fraud penalties.

The Special Plea in Fraud counterclaim is alternatively viewed as an affirmative defense,

as it mandates forfeiture of claims tainted by fraud. Hanover Ins. Co., 134 Fed. Cl. at 64

(referring to the United States’ 28 U.S.C. § 2514 counterclaim as the “Special Plea in Fraud

defense[.]”). Accordingly, the Court is bound to forfeit Lodge’s Dewatering and Design claims

as causes of action before the Court. Daewoo Eng’g & Const. Co., 557 F.3d at 1341 (‘forfeiture

under 28 U.S.C. § 2514 requires only part of the claim to be fraudulent.”). The Special Plea in

Fraud does not carry monetary penalties other than forfeiture.

43

Lodge’s Complaint filed in Case No. 13-800 appeals the Army Corps’ denial of its

Design Claim. (Case No. 13-800, Compl., ECF No. 1). Despite the withdrawal of its monetary

claims, Lodge maintains entitlement to 129 additional calendar days. (Case No. 13-500, Lodge’s

2d Am. Compl. at 13, ECF No. 122). That claim must be forfeited in its entirety.!

iii. Lodge’s Motion to Take Judicial Notice.

On September 28, 2021, several weeks after the conclusion of trial, Lodge filed a motion

requesting that the Court take judicial notice of a decision in Hanover Insurance Co. v. United

States, Case No. 20-11989-PBS (D. Mass. Sept. 20, 2021). That case involves Lodge’s surety

and was formerly consolidated with this case under Case No. 13-500. The court in Massachusetts

held that a civil complaint initiating litigation is not a “claim” under either the False Claims Act

or the CDA. /d. at 11. The court granted summary judgment in favor of Hanover, preventing the

United States from pursuing counterclaims in fraud premised on Hanover allowing a

subcontractor to pass through certain claims that Hanover had settled with the subcontractor. /d.

at 1.

Lodge urges the Court to take notice of the District Court’s decision dismissing the

United States’ fraud counterclaims against Hanover Insurance. (Lodge Mot. to Take Notice, ECF

No. 86). In response, the United States correctly points out that courts may take judicial notice of

facts, but not legal conclusions. (USA Resp. to Take Notice, ECF No. 87). Lodge does not

appear to dispute that the Court’s discretion to take judicial notice is so limited. (Lodge Reply in

Supp., ECF No. 88).

Lodge’s Motion is granted-in-part. The Court takes notice that a decision was rendered in

Hanover Insurance Co. v. United States, Case No. 20-11989-PBS. The Court, with due respect to

its colleagues in the District of Massachusetts, notes that it is not bound by that decision or the

conclusions contained therein. In addition, the Court need not now express any opinion regarding

the pass-through claim issue, nor does it.

IV. Decision and Order of Judgment

In brief, Lodge knowingly and intentionally submitted false claims accompanied by false

records and statements with respect to the type of equipment it utilized on the project. Lodge’s

Dewatering and Design claims are fraudulent insomuch as Lodge reported using USACE Manual

operating and standby rates for equipment that materially differed from its Euclid R50 dump

trucks.

Lodge knowingly and intentionally, or at minimum with reckless disregard for accuracy,

utilized an “inefficiency ratio” that was not a reasonable or an accurate measure of inefficiency;

*1 Lodge also maintains its appeal of the Army Corps’ allegedly wrongful termination for default

in Case No. 13-499. (/d.; Case No. 13-499, Compl. at 10, ECF No. 1). That claim seeks to

convert Lodge’s termination for default into a termination for convenience; Lodge is no longer

pursuing its Dewatering Claim as a cause of action in the Court of Federal Claims. (Case No. 13-

500, Lodge’s 2d Am. Compl. at 13). It is not presently clear what, if any, part of Lodge’s

Complaint in Case No. 13-499 remains viable.

44

but even if it were, the ratio incorporated days outside of the claim period to inflate its damages

calculation. In utilizing this ratio to calculate its Dewatering Claim damages, Lodge submitted a

false claim accompanied by false records and statements. Consequently, Lodge’s Dewatering

Claim is fraudulent.

Lodge knowingly and intentionally, or at minimum with reckless disregard for accuracy,

inflated the operation costs of its batch plant by misrepresenting the run-time for that piece of

equipment. As a result, Lodge’s Dewatering and Design claims are fraudulent in that respect and

are accompanied by false records and statements.

Lodge knowingly and intentionally, or at minimum with reckless disregard for accuracy,

included costs for running dewatering pumps in its Dewatering Claim despite having already

received fixed monthly payments for operating the dewatering pumps. In attempting to double-

bill the Army Corps for those costs, Lodge’s Dewatering Claim was fraudulent and was

accompanied by false records and statements.

After careful consideration of the testimony, documents, and arguments presented at trial,

the Court makes the foregoing findings of fact and conclusions of law. In summary:

(1) The Court FINDS AND CONCLUDES, with support from clear and convincing

evidence, that Lodge Construction, Inc. submitted a fraudulent claim to the United

States Army Corps of Engineers on June 21, 2012 (the Design Claim).

(2) The Court FINDS AND CONCLUDES, with support from clear and convincing

evidence, that Lodge Construction, Inc. submitted a fraudulent claim to the United

States Army Corps of Engineers on June 26, 2012 (the Dewatering Claim).

(3) Pursuant to 31 U.S.C. § 3729, Lodge Construction, Inc. is ORDERED to pay to

the United States $22,000 in civil penalties for false claims, statements, and

records associated with Lodge’s certified Dewatering and Design claims

submitted for payment to the United States Army Corps of Engineers.

(4) Lodge Construction, Inc.’s Design Claim, as stated in Lodge’s Complaint, Case

No. 13-800, and Lodge’s Second Amended Complaint, Case No. 13-500, is

FORFEITED pursuant to 28 U.S.C. § 2514.

(5) Pursuant to RCFC 54(b), there being no just reason for delay, the Clerk is

DIRECTED to enter judgment in favor of the United States in Case No. 13-800.

(6) Lodge Construction, Inc.’s Motion to Take Judicial Notice (ECF No. 86) is

GRANTED-IN-PART.

(7) Further proceedings are required to assess the viability of Lodge’s Complaint in

Case No. 13-499. In addition, the United States has asserted counterclaims in

fraud that were not within the scope of this limited trial. The Court SCHEDULES

a status conference on February 1, 2022 to address outstanding issues. That status

conference will be conducted in Washington, D.C. at the National Courts

Building at 2:00 PM (ET).

45

(8) The Court reserves a decision on costs for a later date.

IT IS SO ORDERED.

3/ David A. Tapp

DAVID A. TAPP, Judge

46