Opinion

McGarry Contracting Co. v. Board of Education

  • 258 A.D. 1061
  • 17 N.Y.S.2d 631
  • 1940 N.Y. App. Div. LEXIS 8893
Court
Appellate Division of the Supreme Court of the State of New York
Filed
Feb 5, 1940
Status
Published
Cited by
0 cases

The opinion

In an action brought originally to recover for a balance due upon a contract for the erection of the foundations for a public school, and for the reasonable value of extra work, the plaintiff, during the pendency of the action, was awarded partial summary judgment for the balance due on the contract. The issues relating to the claim for the reasonable value of the extra work (first cause of action), and those relating to the defendant’s retention of $475 for alleged delay by the plaintiff in the performance of the contract (second cause of action) were tried before the court and a jury. The trial justice at the close of the plaintiff’s case dismissed the first cause of action; and the jury, by direction of the court, found a verdict in favor of the plaintiff against the defendant for $475 on the second cause of action. From so much of the judgment entered dismissing the first cause of action, and from that part of the judgment which awards costs to the defendant in the sum of $118, and from part of an order resettling said judgment, plaintiff appeals. Judgment, and order resettling *1062 judgment, in so far as appealed from, unanimously affirmed, with costs. No opinion. Present — Lazansky, P. J., Hagarty, Johnston, Adel and Taylor, JJ.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.