Opinion

Kellogg Brown & Root Services, Inc.

Court
Armed Services Board of Contract Appeals
Filed
Nov 24, 2021
Status
Published
On the bench
Herzfeld
Cited by
0 cases
Authority
More cited than 22.3%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - )

)

Kellogg Brown & Root Services, Inc. ) ASBCA Nos. 62681, 62843, 62844

)

Under Contract No. W912GB-13-C-0011 )

APPEARANCES FOR THE APPELLANT: Daniel J. Kraftson, Esq.

Sean M. Howley, Esq.

Jonathan J. Straw, Esq.

Kraftson Caudle PLC

McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Paul L. Huhtanen, Esq.

Herbert J. Aldridge, Esq.

Paul Cheverie, Esq.

LuzDanielle O. Bolong, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Europe

OPINION BY ADMINISTRATIVE JUDGE HERZFELD

ON THE GOVERNMENT’S MOTION TO DISMISS

Respondent, the United States Army Corps of Engineers asserts that appellant,

Kellogg Brown & Root Services, Inc. (KBR), did not timely appeal the agency’s final

decisions assessing liquidated damages and recoupment of provisional payments. The

Army Corps of Engineers asserts that the government claims were embedded in the

contracting officer’s final decision denying KBR’s certified claim and KBR’s timely

appeal of that final decision did not properly appeal the government claims within that

decision. We disagree. Indeed, KBR timely appealed every document that could be

construed as a contracting officer’s final decision on these government claims. For the

reasons discussed below, we deny the Army Corps of Engineers’ motion to dismiss and

conclude that the letters demanding payment from KBR constituted the government

claims and contracting officer’s final decisions.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In 2009, President Obama mandated that the government have a European

missile defense system operational “in the 2015 timeframe” (R4, tab 38). On July 9,

2013, the Army Corps of Engineers and KBR executed Contract No. W912GB-13-C-

0011 (Contract) for a firm, fixed-price amount of $134,211,592 to construct an Aegis

Ashore Missile Defense System site on Deveselu Air Base in Deveselu, Romania (R4,

tab 3 at 1-2). The Contract and modifications included milestone dates for KBR’s

completion of certain tasks by specific dates starting with the first milestone in

November 2013 and with project completion to occur in September 2015 (R4, tab 1

at 2-3, tab 65 at 2 (Modification No. A00003)). The Contract also stated that the Army

Corps of Engineers would assess liquidated damages if contractor-caused delay resulted

in KBR missing the September 2015 completion deadline and three interim milestones

(R4, tab 3 at 7; see also tab 3 at 54 (Contract includes Federal Acquisition Regulation

(FAR) 52.211-12, LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000))).

On December 3, 2014, the parties modified the contract to accelerate efforts to

complete the project and to increase funding for the contract (R4, tab 75 at 4-7 –

Modification No. P00007). The modification – P00007 – advised that new payments

based on this funding “[we]re not advance payments” and reminded KBR that “time is of

the essence and the Government is not waiving the right to assess liquidated damages”

(R4, tab 75 at 2-3). The Army Corps of Engineers stated that the modification was

“provisional and contingent upon KBR’s ability to demonstrate excusable delays” but

that “the Government will not collect any liquidated damages pending KBR’s

substantiation of delays” (R4, tab 75 at 3). After several additional contract

modifications, the Army Corps of Engineers added a total of $27 million to the contract

funding to assure timely completion of the project (R4, tab 97 at 2 (Modification

No. P00023)). KBR substantially completed the project on December 19, 2015 to meet

the presidential mandate (consolidated & amended compl. ¶ 73; gov’t answer to

appellant’s consolidated & amended compl. ¶ 73).

On May 31, 2016, KBR submitted a request for equitable adjustment to receive

compensation of $75,000,900 for impacts and delays to the project (R4, tab 118 at 2). On

August 4, 2017, the Army Corps of Engineers denied the request (R4, tab 137).

On March 15, 2019, KBR submitted a certified claim, which requested a 411-day

extension of the contract completion date to November 4, 2016 (and commensurate

extensions to the interim milestones) and payment of $50,206,830.98 based on the Army

Corps of Engineers’ delays and constructive and written changes (including accelerated

performance) (R4, tab 2 – KBR’s Certified Claim). KBR claimed it incurred $88.2 million

in costs due to the delay, but subtracted $37.9 million in accelerated provisional and other

payments made by the Army Corps of Engineers during performance, so sought only

$50.2 million in damages (R4, tab 140 at 13).

On July 1, 2020, the contracting officer issued a final decision denying KBR’s

entire certified claim, concluding that the delay damages were unrecoverable because

KBR had failed to demonstrate any excusable delays (R4, tab 1). The contracting officer

acknowledged that KBR’s claim reduced its $88.2 million in damages based on

2

provisional and other payments that the Army Corps of Engineers had already made and,

thus, only sought $50.2 million in its certified claim (R4, tab 1 at 1 n.1). The decision

informed KBR of its right to appeal the decision to the Board or file an action at the

United States Court of Federal Claims (R4, tab 1 at 107-08).

In addition to denying KBR’s claim as failing to demonstrate any excusable

delays, the decision also discussed recoupment of the provisional payments and

liquidated damages (R4, tab 1). As to the provisional payments, the contracting officer

found that KBR had failed to demonstrate any delays were attributable to the government

and stated “the $27M in provisional payments made under the modification are subject to

recoupment or offset by the Government due to KBR’s failure [to] substantiate . . .

excusable delay” (R4, tab 1 at 48). In its conclusion and section denoted as the

“decision,” the contracting officer repeated the finding that KBR had “failed to justify

excusable delay as required under Modification No. P00007 and in accordance with the

terms of that bilateral modification the Government is entitled to recoup or offset the

provisional payments for acceleration by modification of the Contract or other measures

permitted by the FAR” (R4, tab 1 at 107).

As to liquidated damages, the decision referenced the liquidated damages provisions

of the Contract (including modifications), the number of days of delay, and the dollar

amount penalty for each day of unexcused delay (R4, tab 1 at 3, 17-18, 32-33). The

decision did not provide a dollar figure for the liquidated damages owed based on the

Contract and days of delay (see generally R4, tab 1). The contracting officer concluded,

“Concerning liquidated damages, the Contractor has not demonstrated entitlement to waiver

of liquidated damages under the terms of the Contract in the claim and the Government

reserves the right to collect those damages in a future decision” (R4, tab 1 at 107).

On September 24, 2020, KBR filed a combined notice of appeal and complaint

with the Board (ASBCA No. 62681). KBR attached a copy of the entire July 1, 2020

contracting officer’s final decision to its filing. KBR stated, “KBR is justly due the

amounts sought in its Claim and, as such, KBR hereby appeals the Contracting Officer’s

Final Decision.” (Notice of Appeal & compl. at 2) KBR repeated that its claim sought

$88,167,545.49, but had reduced it by $37,960,714.51 based on provisional and other

payments by the government. (Notice of Appeal & compl. ¶ 79) KBR’s complaint also

alleged that the contracting officer’s final decision “asserted, without analysis or support,

that KBR is responsible for the delays to the Project. These assertions of performance

failures by KBR and its subcontractors in the Decision were made without analytical

basis or support.” (Notice of Appeal & compl. ¶ 84)

On December 10, 2020, the contracting officer sent KBR two “demand letters”

regarding the provisional payments and liquidated damages (R4, tabs 154, 156). The letter

demanding repayment of the $27 million in provisional acceleration payments concluded:

3

As stated in the [contracting officer’s final decision], I have

concluded that KBR did not demonstrate entitlement to

excusable delay to the activities accelerated by Modification

No. P00007 and hereby demand repayment of the amounts

paid to KBR for ‘provisional acceleration efforts’ under

Modification Nos. P00007, 12, 14, 19, and 23 under the terms

of the Contract and FAR subpart 32.6 - Contract Debts.

(R4, tab 154 at 2) The contracting officer also stated that KBR could request “that the debt

be paid in installments or that collection of the debt be deferred due to the impracticability

of payment or pending resolution of disputes concerning the amount owed” (R4, tab 154

at 3). However, the letter did not include any notice of Contract Disputes Act (CDA)

appeal rights.

The letter demanding KBR pay liquidated damages followed the same form (R4,

tab 156). The contracting officer quoted the July 1 decision, which had stated the Army

Corps of Engineers had “reserve[d] the right” to collect liquidated damages “in a future

decision” (R4, tab 156 at 1). “This letter gives notice of the Government’s assessment and

collection of liquidated damages under the terms of the Contract and issues a demand for

payment of liquidated damages not offset by the unpaid balance of the Contract” (R4,

tab 156 at 1). The demand letter asserted KBR owed $6,398,210 in liquidated damages

(R4, tab 156 at 2). The agency “will administratively offset these damages from the

unpaid amounts obligated on the Contract, $2,421,685” and demanded KBR pay the

remainder (R4, tab 156 at 2). Similar to the other demand letter, the contracting officer

advised KBR that it could request “the debt be deferred due to the impracticability of

payment or pending resolution of disputes concerning the amount owed” (R4, tab 156

at 3). However, this letter also did not include any notice of CDA appeal rights.

On January 20, 2021, KBR responded to each demand letter and requested that the

Army Corps of Engineers defer collection of the debt pending the resolution of KBR’s

on-going appeal at the Board (R4, tabs 155, 157).

On March 8, 2021, KBR filed two notices of appeal with the Board each stating

that “KBR understands the December 10, 2020 letter to be the Contracting Officer’s Final

Decision with regard” to the liquidated damages and the provisional acceleration

payments, respectively. KBR attached each demand letter to the respective notice of

appeal. On March 12, 2021, the Board docketed these appeals as ASBCA Nos. 62843

(recoupment of provisional payments) and 62844 (liquidated damages), consolidated

them with appeal No. 62681, and directed KBR to file a complaint (and permitted KBR

to file a consolidated complaint). On April 12, 2021, KBR filed a consolidated and

amended complaint.

4

DECISION

The Army Corps of Engineers moves to dismiss KBR’s appeals challenging the

government claims as untimely because it asserts: (1) KBR’s timely notice of appeal of

the July 1, 2020 contracting officer’s final decision (ASBCA No. 62681) failed to state

KBR specifically intended to appeal the alleged government claims in that decision

(gov’t mot. at 8-9; gov’t reply at 8-10); and (2) KBR’s subsequent appeals (ASBCA

Nos. 62843 and 62844) challenging the agency’s demand letters are not valid contracting

officer’s final decisions and KBR’s appeals should be dismissed as untimely (gov’t mot.

at 4-8; gov’t reply at 4-8). For the reasons discussed below, KBR timely appealed the

government claims, which were memorialized in the demand letters issued by the

contracting officer (CO).

I. Standard of Review

Claims for the recoupment of provisional payments and for liquidated damages, as

here, constitute government claims. M. Maropakis Carpentry, Inc. v. United States, 609

F.3d 1323, 1330 (Fed. Cir. 2010) (liquidated damages); Alaska Aerospace Corp., ASBCA

No. 59794, 16-1 BCA ¶ 36,498 at 177,844 (recoupment). CDA jurisdiction over a

government monetary claim requires both a valid government claim and a contracting

officer’s final decision asserting or demanding payment of the claim. Maropakis, 609 F.3d

at 1327; L-3 Commc’ns Integrated Sys., LP, ASBCA Nos. 60713, 60716, 17-1 BCA ¶

36,865 at 179,625 (“Pursuant to the CDA, for a government claim, this Board’s jurisdiction

is dependent on a contracting officer asserting a claim in the form of a contracting officer’s

final decision issued to the contractor.”). “The government bears the burden of establishing

jurisdiction for a government claim.” L-3 Commc’ns, 17-1 BCA ¶ 36,865 at 179,625.

However, the contractor bears the burden for establishing that it timely appealed a

contracting officer’s final decision. R&R Sys. Sols., LLC, ASBCA Nos. 61269, 61405, 19-1

BCA ¶ 37,269 at 181,358. We rely on the record for fact-finding when evaluating facts

supporting jurisdiction. Najmaa Alshimal Co., ASBCA No. 62701, 21-1 BCA ¶ 37,872

at 183,899 (citing CCIE & Co., ASBCA Nos. 58355, 59008, 14-1 BCA ¶ 35,700

at 174,816).

II. By Timely Appealing the Contracting Officer’s Final Decision Denying the

Contractor’s Claim, the Contractor Timely Appealed Any Alleged Government

Claims Embedded in the Same Contracting Officer’s Final Decision

“A contractor, within 90 days from the date of receipt of a contracting officer’s

decision under section 7103 of this title, may appeal the decision to an agency board as

provided in section 7105 of this title.” 41 U.S.C. § 7104(a). The 90-day limitation is

jurisdictional and, thus, may not be waived. Cosmic Constr. Co. v. United States, 697

F.2d 1389, 1390 (Fed. Cir. 1982).

5

The Army Corps of Engineers asserts that its July 1, 2020 contracting officer’s

final decision rendered a final decision on a valid government claim for liquidated

damages and recoupment of provisional payments, but KBR’s September 24, 2020

appeal of that decision (ASBCA No. 62681) somehow failed to appropriately challenge

the alleged government claims (gov’t mot. at 8-9; gov’t reply at 8-10). Indeed, the Army

Corps of Engineers does not contend that KBR’s notice of appeal was untimely. It could

not, given that KBR noticed its appeal on September 24, 2020 – within 90 days of the

July 1, 2020 decision. Instead, the Army Corps of Engineers looks to KBR’s combined

notice of appeal and complaint, asserting that the complaint fails to plead an appeal of the

government claims. We disagree with the agency’s contentions.

KBR timely appealed the July 1, 2020 contracting officer’s final decision. The

CDA speaks of appealing a “decision,” not whether the contractor intends to appeal

claims within a decision. 41 U.S.C. § 7104(a). Our rules state, “A notice of appeal shall

indicate that an appeal is being taken and should identify the contract by number, the

department and/or agency involved in the dispute, the decision from which the appeal is

taken, and the amount in dispute, if any.” ASBCA Rule 1(b). Similar to the simple

statutory requirement, the only thing a notice of appeal “shall” include is that the

contractor is appealing, everything else is something the contractor “should” do.

Here, KBR’s notice of appeal met the statutory minimum required – it appealed a

contracting officer’s final decision within 90 days, explicitly stating: “KBR is justly due

the amounts sought in its Claim and, as such, KBR hereby appeals the Contracting

Officer’s Final Decision” (Notice of Appeal & compl. at 2). Indeed, the notice of appeal

and complaint also included the information we encourage contractors to include,

identifying the contract number, the agency, the contracting officer’s final decision

appealed (which KBR attached), and the amount of money at issue – $88.2 million

(which includes the disputed provisional payments and implicitly the liquidated

damages). (Notice of Appeal & compl. at 1, ¶ 79)

The government points to KBR’s subsequent appeals of the December 10, 2020

demand letters as evidence that KBR did not believe its September 24, 2020 notice of

appeal was appealing the alleged government claims within the contracting officer’s final

decision (gov’t reply at 8-9). KBR can hardly be blamed for filing subsequent appeals

and not being more explicit in its initial appeal. The statements in the July 1, 2020

contracting officer’s final decision denying KBR’s claim were unclear whether the Army

Corps of Engineers was even asserting government claims in the decision. For example,

the final decision stated that the $27 million in provisional payments was “subject to

recoupment or offset” to be accomplished “by modification of the Contract or other

measures permitted by the FAR” and “reserve[d] the right” to collect liquidated damages

“in a future decision” (R4, tab 1 at 48, 107).

6

Regardless of any confusion, we have repeatedly recognized that a contractor

timely appeals a contracting officer’s final decision that includes both contractor and

government claims even where the contractor’s notice of appeal fails to mention the

government claim embedded within the final decision appealed. G. Bliudzius

Contractors, Inc., ASBCA Nos. 42366, 42367, 93-1 BCA ¶ 25,439 at 126,685

(construing contractor’s “notices of appeal as indicating an intent on appellant’s part to

contest the Government’s assessment of liquidated damages” in the same contracting

officer’s final decision denying contractor’s request for a time extension, which

contractor specifically appealed); G.S.E. Dynamics, Inc., ASBCA No. 25227, 81-1 BCA

¶ 15,096 at 74,698-99 (“The Government appears to contend that the appeal from its final

decision of 11 April 1980 presented to the Board only appellant’s claim for work

performed on the Government furnished forgings. This is, however, clearly too narrow a

view of the matter.”). KBR was not explicit regarding appealing the alleged government

claims, but its timely appeal of the contracting officer’s final decision within the 90-day

jurisdictional appeal period sufficed to meet the timeliness requirements for appealing the

alleged government claims.

Ultimately, we conclude that KBR timely appealed the July 1, 2020 final decision.

However, the agency’s motion begs the question whether the July 1, 2020 contracting

officer’s final decision actually stated government claims (or whether the December 10,

2020 contracting officer’s demand letters stated the government claims). We address that

question next, because the parties disagree which communication constitutes a final

decision on the government claims.

III. The July 1, 2020 Contracting Officer’s Final Decision Did Not State Valid

Government Claims, But the Demand Letters Stated Valid Government

Claims and Constituted Final Decisions KBR Timely Appealed

The CDA does not define a claim, but the United States Court of Appeals for the

Federal Circuit has adopted the definition of a “claim” found in the FAR (and the

Disputes clause): “[A] written demand or written assertion by one of the contracting

parties seeking, as a matter of right, the payment of money in a sum certain, the

adjustment or interpretation of contract terms, or other relief arising under or relating to

the contract.” K-Con Bldg. Sys. v. United States, 778 F.3d 1000, 1005 (Fed. Cir. 2015)

(quoting Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1575 (Fed. Cir. 1995) (en banc)

(quoting FAR definition of “claim”)); FAR 2.101 (definition of “claim”); (R4, tab 3 at 33

(Contract incorporating FAR 52.233-1, DISPUTES (JUL 2002) that uses this definition));

CCIE & Co., 14-1 BCA ¶ 35,700 at 174,816.

A monetary claim must “adequately specify both the amount sought and the basis

for the request[.]” K-Con Bldg. Sys., Inc., 778 F.3d at 1005. A proponent of a claim

cannot simply state that it intends to assert a claim at a later time, but must make a

written demand or assertion for a monetary sum certain. Maropakis, 609 F.3d at 1328

7

(“A claim cannot be based merely on intent to assert a claim without any communication

by the contractor of a desire for a contracting officer decision.”). Indeed, just like a

contractor, the government must make a “clear and unequivocal statement” giving

“adequate notice” of the basis and amount of the claim. L-3 Commc’ns, 17-1 BCA

¶ 36,865 at 179,625 (requiring government to provide “clear and unequivocal statement”

to meet “adequate notice” requirement); SRA Int’l, Inc. v. Dep’t of State, CBCA 6563,

20-1 BCA ¶ 37,543 at 182,312 (same); Raytheon Co. v. United States, 105 Fed. Cl. 236,

298 (2012) (requiring “adequate notice” of government claim), aff’d, 747 F.3d 1341 (Fed.

Cir. 2014). To determine the validity of a claim, we apply a common sense analysis,

looking at specific communications on a case-by-case basis and the “totality of previous

correspondence between the parties.” Holmes & Narver, Inc., ASBCA No. 51430, 99-1

BCA ¶ 30,131 at 149,054.

The July 1, 2020 decision did not state government claims for liquidated damages

or recoupment of the provisional payments. First, as noted above, the contracting officer

did not demand or assert a claim for money, but merely “reserve[d] the right” to collect

liquidated damages “in a future decision” and stated that KBR was “subject to

recoupment or offset” of provisional payments that the Army Corps of Engineers would

accomplish “by modification of the Contract or other measures permitted by the FAR”

(R4, tab 1 at 48, 107). These were mere assertions of legal rights that stated an intent to

seek a legal remedy in the future. However, “[t]he mere assertion of a legal right to a

remedy falls short of a written demand for payment of a sum certain.” Philips Lighting

N. Am. Corp., ASBCA No. 61769 et al., 20-1 BCA ¶ 37,679 at 182,929; ACEquip, Ltd.,

ASBCA No. 53479, 02-2 BCA ¶ 31,978 at 158,019 (“Although the Termination

Contracting Officer (TCO) mentioned that the Government was assessing liquidated

damages, just as the CO had previously communicated to appellant, the TCO did not seek

payment of liquidated damages. Thus, the TCO’s final decision was not a Government

claim for such damages within the meaning of the CDA.”), modified on other grounds,

03-1 BCA ¶ 32,109; cf also Hanley Indus., Inc., ASBCA No. 56976, 10-1 BCA ¶ 34,425

at 169,930 (concluding there was no final decision because the contracting officer

“reserve[d] the right to submit the total dollar amount of its demand for these actions to

[contractor] at a later date”). Because the contracting officer’s decision was unclear and

equivocal in making a demand or assertion for payment, the July 1, 2020 decision did not

include a valid government claim.

Second, as to the claim for liquidated damages, the July 1, 2020 decision also

lacked a sum certain. Parsons Evergreene, LLC, ASBCA No. 57794, 12-2 BCA

¶ 35,092 at 172,346 (“There remains the necessity that the assessment of the liquidated

damages be memorialized in a final decision by the contracting officer.”). Notably, it was

unclear what exact dollar amount of the liquidated damages the Army Corps of Engineers

intended to seek and how it intended to recover – by recoupment, offset, or seeking

repayment. Only when the Army Corps of Engineers issued the demand letter for the

liquidated damages did the agency explain the sum certain amount owed (R4, tab 156).

8

Moreover, this demand letter constituted the “future decision” promised in the July 1,

2020 contracting officer’s final decision denying KBR’s claims (R4, tab 1 at 107).

Given the totality of the correspondence between the parties, the contracting

officer’s December 10, 2020 demand letters constituted the government claims and the

contracting officer’s final decisions (R4, tabs 154,156). IBM Corp., ASBCA No. 60332,

18-1 BCA ¶ 37,002 at 180,192 (“We conclude that the government first asserted its claim

on 8 March 2013, when it issued a demand letter for the sum certain amount . . . .”). The

Army Corps of Engineers’ contracting officer’s demand letters were clear and unequivocal

that the agency sought recovery of a sum certain owed by KBR for the liquidated damages

and provisional payments; and, most importantly, KBR timely appealed those claims

(ASBCA Nos. 62843 and 62844).

The Army Corps of Engineers asserts that the demand letters did not serve as

contracting officer’s final decisions (gov’t mot. at 5-8; gov’t reply at 4-6). We disagree.

Even if not labeled a “final decision,” a communication from a contracting officer can

constitute a valid final decision. Placeway Constr. Corp. v. United States, 920 F.2d 903,

906-07 (Fed. Cir. 1990). Indeed, the FAR even permits a contracting officer to issue a

demand letter as part of a final decision. FAR 32.604(a)(3) (“Issue the demand for

payment as part of a final decision, if a final decision is required by 32.605(a).”).

The agency offers several authorities to assert otherwise. As the agency correctly

notes, we have concluded in some circumstances that demand letters did not constitute

final decisions (gov’t mot. at 5-6). For example, the agency cites Santa Fe Builders, Inc.,

where we found that the “demand letter cannot qualify because it expressly stated that a

contracting officer’s decision would be issued at a future date.” Santa Fe Builders, Inc.,

ASBCA No. 52021, 00-2 BCA ¶ 30,983 at 152,919. Here, however, the July 1, 2020

contracting officer’s final decision on KBR’s claims deferred a decision on the

government claims by stating the liquidated damages would be recovered in a “future

decision” and that the provisional payments were “subject to” recovery at a later date

(R4, tab 1 at 48, 107). The demand letters served as the future decisions on government

claims promised in the earlier correspondence.

The Army Corps of Engineers also cites Boeing v. United States, as providing

another example that a demand letter cannot serve as a final decision and distinguished

Placeway (gov’t reply at 4-5). Boeing v. United States, 25 Cl. Ct. 441, 446-47 (1992),

rev’d & vacated, 991 F.2d 811 (Fed. Cir. 1993) (unpub. tbl. dec.). In Boeing, the Claims

Court found that a demand letter was not a final decision. 25 Cl. Ct. at 446-47.

However, the Federal Circuit reversed and vacated that specific determination: “We hold

the demand was final.” 1993 WL 76280 at *1. *

*

The Federal Circuit changed its rules in 2020 and now permits parties to cite

non-precedential decisions (while previously it prohibited parties from citing

9

The Army Corps of Engineers asserts that the later demand letters may not vitiate

the finality of an earlier final decision, relying on Aerospace Facilities Grp., Inc.,

ASBCA No. 61026, 18-1 BCA ¶ 37,105 at 180,605. In Aerospace Facilities, however,

we concluded that the government’s ambiguous actions vitiated a prior final decision.

Aerospace Facilities, 18-1 BCA ¶ 37,105 at 180,606. In any event, here the prior “final

decision” did not include a valid government claim and stated the agency intended to

issue future decisions regarding recoupment of provisional payments and for liquidated

damages. The Army Corps of Engineers’ actions here, like that in Aerospace Facilities,

sowed ambiguity into any finality of the July 1, 2020 decision.

The Army Corps of Engineers also asserts that we have found demand letters could

not constitute contracting officer’s final decisions because they lacked finality, prejudicing

a contractor by failing to include notice of the contractor’s appeal rights. Transportes

Especiales de Automoviles, S.A., ASBCA No. 43851, 93-2 BCA ¶ 25,745 at 128,113

(failing to inform contractor of appeal rights); Al’s Enters., Ltd., ASBCA No. 14031, 71-1

BCA ¶ 8,896 at 41,338 (pre-CDA appeal concluding “demand letters did not purport to be

final decisions of the contracting officer”). However, the CDA requires the contracting

officer to include the appeal rights for the “protection of the contractor.” Decker & Co. v.

West, 76 F.3d 1573, 1579 (Fed. Cir. 1996). And, as KBR correctly notes, there is no harm

where a contractor does not detrimentally rely on an agency’s failure to include the

required CDA appeal rights in a final decision. Fla. Dep’t of Ins. v. United States, 81 F.3d

1093, 1098 (Fed. Cir. 1996); JAAAT Tech. Servs., LLC, ASBCA No. 61792 et al., 21-1

BCA ¶ 37,878 at 183,950-51; (app. resp. at 8-9). Here, the agency’s failure to include the

appeal rights did not harm KBR because it timely appealed the final decisions.

Ultimately, based on our review of the totality of the communications between the

Army Corps of Engineers and KBR, we conclude that the facts of these appeals

demonstrate that the demand letters constitute final decisions. Accordingly, KBR timely

appealed those final decisions.

non-precedential dispositions issued prior to January 1, 2007). Compare Fed. Cir.

R. 32.1(c) (Dec. 2020) with Proposed Amendments to Federal Circuit Rules of

Practice (Apr. 2020), available at https://cafc.uscourts.gov/wp-

content/uploads/FCRProposedAmendments-PublicRedlineCopy-April2020.pdf.

The agency’s counsel was not alone in misdiagnosing the import of subsequent

adverse appellate history. KBR’s counsel also did not include subsequent

appellate history in Sharman Co. v. United States, 24 Cl. Ct. 763 (1991), which

KBR cited to support its assertion that a demand letter could be a final decision

(app. resp. at 9-10). The Federal Circuit reversed on that issue, concluding the

facts did not demonstrate that the demand letter was a final decision. Sharman Co.

v. United States, 2 F.3d 1564, 1571 (Fed. Cir. 1993), overruled on other grounds

by, Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1579 n.10 (Fed. Cir. 1995) (en banc).

10

CONCLUSION

The Army Corps of Engineers’ motion to dismiss is denied.

Dated: November 22, 2021

DANIEL S. HERZFELD

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 62681, 62843, 62844,

Appeals of Kellogg Brown & Root Services, Inc., rendered in conformance with the

Board’s Charter.

Dated: November 24, 2021

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

11

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.