Opinion

Assist Consultants Inc.

Court
Armed Services Board of Contract Appeals
Filed
Oct 18, 2021
Status
Published
On the bench
D'Alessandris
Cited by
0 cases
Authority
More cited than 21.8%

single renewal of agreement after knowledge of breach while producer demanded more information was not ongoing acquiescence required to establish waiver

How later courts described this case

  • single renewal of agreement after knowledge of breach while producer demanded more information was not ongoing acquiescence required to establish waiver

Written by the judges who cited it.

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of - )

)

Assist Consultants Inc. ) ASBCA Nos. 61525, 62090

)

Under Contract No. W912ER-18-C-0009 )

APPEARANCES FOR THE APPELLANT: Lee-Ann C. Brown, Esq.

Douglas L. Patin, Esq.

Sabah K. Petrov, Esq.

Bradley Arant Boult Cummings LLP

Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.

Engineer Chief Trial Attorney

Rebecca L. Bockmann, Esq.

Matthew Tilghman, Esq.

Engineer Trial Attorneys

U.S. Army Engineer District, Middle East

Winchester, VA

OPINION ON THE GOVERNMENT’S MOTION FOR RECONSIDERATION BY

ADMINISTRATIVE JUDGE D’ALESSANDRIS

In an opinion dated April 29, 2021, the Board denied cross-motions for summary

judgement filed by appellant Assist Consultants, Inc. (ACI) and respondent, the United

States Army Corps of Engineers (USACE or government). Assist Consultants, Inc.,

ASBCA Nos. 61525, 62090, 21-1 BCA ¶ 37,850. The government timely filed a motion

for reconsideration, alleging error in our decision “insofar as it concludes that, as a matter

of law, a request for termination for convenience sufficiently replaces the requirement

that a contractor who has continued performance after discovering a breach must reserve

its rights to avoid a finding waiving its right to claim breach later” (gov’t mot. at 1). For

the reasons stated below, the government’s motion for reconsideration is denied.

DECISION

A motion for reconsideration is not the place to present arguments previously

made and rejected. “[W]here litigants have once battled for the court’s decision, they

should neither be required, nor without good reason permitted, to battle for it again.”

Dixon v. Shinseki, 741 F.3d 1367, 1378 (Fed. Cir. 2014) (quoting Official Comm. of the

Unsecured Creditors of Color Tile, Inc. v. Coopers & Lybrand, LLP, 322 F.3d 147,

167 (2d Cir. 2003)). Moreover, “[m]otions for reconsideration do not afford litigants the

opportunity to take a ‘second bite at the apple’ or to advance arguments that properly

should have been presented in an earlier proceeding.” Dixon, 741 F.3d at 1378; see also

Avant Assessment, LLC, ASBCA No. 58867, 15-1 BCA ¶ 36,137 at 176,384. On the

other hand, if we have made mistakes in the findings of fact or conclusions of law, or by

failing to consider an appropriate matter, reconsideration may be appropriate. See

Robinson Quality Constructors, ASBCA No. 55784, 09-2 BCA ¶ 34,171 at 168,911;

L&C Europa Contracting Co., ASBCA No. 52617, 04-2 BCA ¶ 32,708. The Board

recently summarized the standard for reconsideration stating “[i]n short, if we have

made a genuine oversight that affects the outcome of the appeal, we will remedy it.”

Relyant, LLC, ASBCA No. 59809, 18-1 BCA ¶ 37,146 at 180,841. Here, as in Relyant,

no such mistakes have been identified.

In our decision, we held that the government had satisfied its initial burden of

demonstrating that its termination for default was justified, but denied the government’s

motion for summary judgment, because there were material issues of fact regarding

ACI’s affirmative defense alleging a prior material breach by the government. Assist

Consultants, 21-1 BCA ¶ 37,850 at 183,799. Under the summary judgment standard of

review, we also denied the government’s argument that, even if its failure to disclose the

base access restrictions to bidders could constitute a material breach, that ACI had

waived the breach by preforming and not reserving its rights. Id. at 183,810. We

rejected the argument, noting that “the government’s argument completely ignores the

fact that ACI requested a no-cost termination for convenience immediately after the

preconstruction conference where the government announced that Afghan workers

would not be permitted on the base.” Id. The Board did not hold, as a matter of law,

that a request for a termination for convenience was legally sufficient to reserve ACI’s

right, but rather, cited the termination for convenience request as an example of a factual

issue preventing the entry of summary judgment.

To the extent the government argues in its motion for reconsideration that it is

entitled to entry of judgment as a matter of law, because ACI did not identify a specific

reservation of rights, we disagree and hold that there are material factual issues in dispute.

The government cites selectively from 13 Williston on Contracts § 39:35 (4th ed.) for the

proposition that ACI’s failure to expressly reserve its rights entitles the government to

judgment as a matter of law (gov’t reply at 2). However, read in full, Williston provides:

Mere silence, acquiescence, or inactivity is insufficient to

show a waiver of contract rights where there is no duty to

speak or act. But silence or inaction, coupled with

knowledge by the party charged with a waiver that the

contract’s terms have not been strictly met, and detrimental

reliance by the other, for such a length of time as to

manifest an intention to relinquish the known right may

result in a waiver of rights under the contract.

2

13 RICHARD A. LORD, WILLISTON ON CONTRACTS § 39:35 (4th ed. 2013) (footnotes

omitted).

ACI asserts, in opposition to the government’s motion for reconsideration, that it

did not have complete knowledge of the government’s breach until after the termination

and subsequent discovery (app. resp. at 4-10). ACI alleges that the government misled

ACI by stating that the USACE had received “no UAE confirmation” that there was a

policy denying access to Afghan passport holders (id. at 8; R4, tab 13), and that the

government’s statement was misleading because the government knew that it would not

get confirmation from the UAE authorities and that the USACE never tried to get

confirmation after the pre-construction meeting (app. resp. at 8). ACI’s allegations are

supported by Mr. Amiri’s declaration and an e-mail, produced in discovery, demonstrating

that the government was aware of a potential base access problem in June 2017, months

before the December 2017 award at issue here (app. mtn. sum. J. ex. 2). ACI further

points to its response to the show cause letter where ACI reported that it was “taking all

steps to submit the required documentation to the UAE and obtain a written position from

UAE authorities as to whether or not we will be allowed access” as proof that it did not

yet possess full knowledge regarding the ability of its Afghan workers to access the base

(app. resp. at 8 (quoting R4, tab 15)). The courts have held that waiver does not apply

during a limited course of action while a party seeks more information. See, e.g., O.K.

Sand and Gravel, Inc. v. Martin Marietta Corp., 819 F. Supp. 771, 783 (S.D. Ind. 1992)

aff’d 36 F.3d 565 (7th Cir. 1994) (single renewal of agreement after knowledge of breach

while producer demanded more information was not ongoing acquiescence required to

establish waiver).

The government cites to e-mails between ACI and its legal consultant to argue

that ACI knew on January 21, 2018, that it had a potential legal argument that the

government had materially breached the contract (gov’t reply at 5-7). However, the

government did not cite these documents in its summary judgment briefing, or even in

its opening brief in this motion for reconsideration. We do not consider new arguments

raised in a motion for reconsideration where the evidence was available to the moving

party at the time it filed its brief. Dixon, 741 F.3d at 1378; Avant Assessment, LLC,

15-1 BCA ¶ 36,137 at 176,384. Accordingly, we continue to find that there is a

material factual dispute regarding ACI’s knowledge. See Northern Helex Co. v. United

States, 455 F.2d 546, 551 (Ct. Cl. 1972).

ACI additionally notes that it never received a notice to proceed under the

contract, and thus, alleges that contract performance had not begun such as to trigger

the election doctrine (app. resp. at 8-9). The government disputes ACI’s interpretation,

again citing to documents in that record that it failed to cite in its dispositive motion

(gov’t reply at 21-24). The fact that ACI did contractual work without having received

a notice to proceed is relevant to the waiver argument in that the reasoning behind the

waiver provision is so that “one side cannot continue after a material breach by the

3

other (such as failure to pay), act as if the contract remains fully in force (although

stopping performance would be fair and convenient), run up damages, and then go

suddenly to court.” Northern Helex Co. v. United States, 455 F.2d at 551. Here, ACI

could not run up damages because it was performing the work at its own risk. The

government also fails to note how it relied to its detriment on ACI’s continued

performance, absent a notice to proceed.

Finally, the government’s motion seeks to treat the election requirement as

applying the moment the contractor first becomes aware of possible breach. The

government points to the fact that ACI performed for 23 days as evidence of a

knowing waiver (gov’t reply at 5-13). However, as noted in the government’s reply

brief, what is required is “reasonable promptness” (gov’t reply at 8 (quoting Supreme

Foodservice GMBH, ASBCA No. 57884 et al., 16-1 BCA ¶ 36,387 at 177,395)).

Whether 23 days is a reasonable time is an issue requiring further factual development.

See, e.g., TECOM, Inc., IBCA No. 2970-a-1, 95-2 BCA ¶ 27,607 at 137,597 (finding

no waiver after 4½ months of performance).

CONCLUSION

For the reasons stated above, the government’s motion for reconsideration is

denied.

Dated: October 18, 2021

DAVID D’ALESSANDRIS

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

4

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA Nos. 61525, 62090, Appeals of

Assist Consultants Inc., rendered in conformance with the Board’s Charter.

Dated: October 19, 2021

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

5

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.