Opinion

Mendoza v. Fonseca McElroy Grinding Co., Inc.

  • 282 Cal. Rptr. 3d 369
  • 11 Cal. 5th 1118
  • 492 P.3d 993
Court
California Supreme Court
Filed
Aug 16, 2021
Status
Published
Cited by
21 cases
Authority
More cited than 91.9%

“While this court may restate the certified question . . . , we lack the power to reshape the federal litigation that gave rise to the question in the first instance.”

How later courts described this case

  • “While this court may restate the certified question . . . , we lack the power to reshape the federal litigation that gave rise to the question in the first instance.”

Written by the judges who cited it.

The opinion

IN THE SUPREME COURT OF

CALIFORNIA

LEOPOLDO PENA MENDOZA et al.,

Plaintiffs and Appellants,

v.

FONSECA MCELROY GRINDING CO., INC., et al.,

Defendants and Respondents.

S253574

Ninth Circuit

17-15221

Northern District of California

3:15-cv-05143-WHO

August 16, 2021

Justice Corrigan authored the opinion of the Court, in which

Chief Justice Cantil-Sakauye and Justices Kruger, Groban,

and Jenkins concurred.

Justice Cuéllar filed a dissenting opinion, in which Justice Liu

concurred.

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

S253574

Opinion of the Court by Corrigan, J.

California’s Labor Code requires that certain kinds of jobs

performed on a public works project be compensated at a per

diem rate no less than the prevailing wage paid in the area

where the work is done. (Lab. Code,1 § 1771.) The Labor Code

delineates with specificity the kinds of “public work” covered by

the prevailing wage statutes. (See §§ 1720–1720.9.)

The question here is whether the prevailing wage must be

paid for plaintiffs’ mobilization work, which involved

transporting heavy machinery to and from a public works site.

It is undisputed that operation of the machinery at the site

qualifies as “public work.” However, plaintiffs do not contend

that mobilization is “public work” as that term is defined in the

applicable statutes. Instead, they argue that, under Labor Code

section 1772, they are “deemed to be employed upon public

work” because their mobilization work was performed “in the

execution” of a public works contract. Plaintiffs urge an

interpretation of section 1772 that would enlarge the scope of

the prevailing wage law to encompass activities that the

Legislature has not otherwise defined as public work.

This expansive interpretation is unsupported by either the

statutory language or legislative history. Section 1772 was not

intended to define or expand the categories of work covered by

1

Further unspecified section references are to the Labor Code.

1

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

the prevailing wage law. As a result, plaintiffs’ reliance on that

statute is misplaced.2

I. BACKGROUND

Defendants are a roadwork construction company and its

successor, which work on both public and private projects. Part

of the road construction process involves using milling

equipment to break up existing roadbeds so that new roads can

be built. Plaintiffs are unionized engineers who operate the

equipment. Sometimes the heavy milling machines are not kept

at the job site but are stored instead at a permanent yard or

other offsite location. In such cases, plaintiffs report to the

offsite location, load the equipment onto trailers, and bring it to

the job site. This preparatory activity and equipment

transportation is known as mobilization.3

A master agreement between defendants and plaintiffs’

union established wage rates for onsite construction. A separate

memorandum of agreement (memorandum) set a lower wage

rate for mobilization. When assigned to public works projects,

plaintiffs here were paid according to the master agreement and

memorandum, receiving the prevailing wage for onsite work and

the lesser memorandum rate for mobilization.

2

To be clear, although we conclude that section 1772, standing

alone, does not afford coverage for mobilization, we do not hold

more broadly that mobilization necessarily falls outside the

scope of the prevailing wage law’s protections. (See post, at pp.

33–34.)

3

More specifically, mobilization entails: loading the milling

machines onto a trailer; securing the equipment; checking light,

brake, and fluid levels of the truck transporting the trailer;

driving to the construction site; and returning the truck and

trailer to the storage yard.

2

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

Plaintiffs sued in federal court alleging, inter alia, failure

to pay the prevailing wage for mobilization done in connection

with public works projects. The parties filed cross-motions for

partial summary judgment limited to whether mobilization fell

under the prevailing wage law. The district court ruled for

defendants, concluding that mobilization was not covered by

prevailing wage protection.

After all remaining issues were settled, plaintiffs appealed

the mobilization decision to the United States Court of Appeals

for the Ninth Circuit. The sole issue raised was “whether

transporting heavy equipment to be used on public works

construction is [done] ‘in the execution of the contract’ under

California Labor Code section 1772.” We accepted the Ninth

Circuit’s request4 to decide whether the mobilization activity

was covered by section 1772.5

II. DISCUSSION

A. Prevailing Wage Law Overview

California’s prevailing wage law was enacted in 1931 as

an uncodified measure. (1931 Act; Stats. 1931, ch. 397, §§ 1–6,

pp. 910–912.) Its federal counterpart, the Davis-Bacon Act (40

U.S.C. § 3141 et seq.), was enacted the same year but is not

4

Cal. Rules of Court, rule 8.548(a).

5

The Ninth Circuit framed the question as follows: “Is

operating engineers’ offsite ‘mobilization work’ — including the

transportation to and from a public works site of roadwork

grinding equipment — performed ‘in the execution of [a]

contract for public work,’ [section 1772], such that it entitles

workers to ‘not less than the general prevailing rate of per diem

wages for work of a similar character in the locality in which the

public work is performed’ pursuant to section 1771 of the

California Labor Code?”

3

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

completely coextensive with California's version of the law.

(Kaanaana v. Barrett Business Services, Inc. (2021) 11 Cal.5th

158, 165 (Kaanaana).) State and federal prevailing wage laws

“responded to the dire economic conditions of the Great

Depression, when private construction diminished severely and

‘the oversupply of labor was exploited by unscrupulous

contractors to win government contracts . . . .’ ” (Kaanaana, at

pp. 165–166; see Universities Research Assn. v. Coutu (1981) 450

U.S. 754, 773–774.)

The prevailing wage law is a minimum wage provision

whose overall purpose is “to protect and benefit employees on

public works projects.” (Lusardi Construction Co. v. Aubry

(1992) 1 Cal.4th 976, 985 (Lusardi).) “This general objective

subsumes within it a number of specific goals: to protect

employees from substandard wages that might be paid if

contractors could recruit labor from distant cheap-labor areas;

to permit union contractors to compete with nonunion

contractors; to benefit the public through the superior efficiency

of well-paid employees; and to compensate nonpublic employees

with higher wages for the absence of job security and

employment benefits enjoyed by public employees.” (Id. at

p. 987.) Courts liberally construe the law to fulfill its purpose.

(City of Long Beach v. Department of Industrial Relations (2004)

34 Cal.4th 942, 949–950.)

Those employed on “public works” must generally be paid

at least the “prevailing rate of per diem wages for work of a

similar character” in the area. (§ 1771.) Under the current

statutory scheme, the prevailing wage law does not apply to

work done by a public agency with its own labor force. (Ibid.)

As we will discuss at some length, this statutory exclusion for

4

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

government workers was not always in place. (See post, at pp.

10–20.)

A contractor or subcontractor that does not pay the

prevailing wage rate on a public works project is liable for the

deficiency and subject to a penalty. (§ 1775, subd. (a).) The

statutory payment obligation is independent of any contractual

requirement. (Lusardi, supra, 1 Cal.4th at pp. 981–982.) For

that reason, the fact that the parties’ memorandum provides

lesser pay for mobilization does not settle the question here. If

the statutory scheme requires payment of the prevailing wage

for a particular type of labor, it is irrelevant that the parties may

have agreed to a lesser amount.

The prevailing wage law describes with particularity the

kind of “public works” that fall within its scope.6 Since the law’s

adoption in 1931, it has encompassed certain “construction or

repair work.” (Stats. 1931, ch. 397, § 4, p. 912.) Over the years,

the statutory definition of “public works” has been amended to

clarify and expand the scope of the activities it embraces. As

applicable here, section 1720, subdivision (a)(1) (hereafter

section 1720(a)(1)) currently defines “public works” as

“[c]onstruction, alteration, demolition, installation, or repair

work done under contract and paid for in whole or in part out of

public funds . . . .”7 Other provisions of section 1720,

6

The prevailing wage law uses the plural term “public works”

as well as the singular term “public work.” (See §§ 1720, subd.

(a)(1) & (2), 1770, 1771, 1772.) We use the terms

interchangeably.

7

Although plaintiffs apparently did mobilization work on both

public and private construction projects, we are concerned here

only with work done under contract paid for in whole or in part

with public funds.

5

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

subdivision (a) not involved here provide additional definitions

of “public works” in different contexts like street and sewer work

(subd. (a)(3)), carpet laying (subd. (a)(4) & (5)), and tree removal

(subd. (a)(8)). Still other definitions of “public works” are

contained in additional statutes. (§§ 1720.2–1720.9.)

Plaintiffs’ operation of milling machines at the job site

clearly constitutes “public work” under section 1720(a)(1)

because it involved “[c]onstruction, alteration, demolition,

installation, or repair work,” and all the labor engaged in here

was “done under contract and paid for in whole or in part out of

public funds . . . .” But here we are concerned with mobilization,

not onsite machine operation. Plaintiffs do not argue that

mobilization fits within one of the definitions of “public works”

in the prevailing wage law. Instead, they rely on section 1772,

which derives from a provision in the uncodified 1931 Act. (See

Stats. 1931, ch. 397, § 1, p. 910.) That section currently reads:

“Workers employed by contractors or subcontractors in the

execution of any contract for public work are deemed to be

employed upon public work.” (§ 1772.) Plaintiffs claim their

entitlement to the prevailing wage for offsite mobilization flows

from this “deeming” provision.

This court has not previously interpreted section 1772. As

discussed in more detail below, in recent decades a number of

lower courts have concluded that section 1772 applies to tasks

that are “ ‘ “an integrated aspect of the ‘flow’ process of

construction.” ’ ” (Williams v. SnSands Corp. (2007) 156

Cal.App.4th 742, 753 (Williams); see Sheet Metal Workers’

Internat. Assn., Local 104 v. Duncan (2014) 229 Cal.App.4th

192, 205–206 (Sheet Metal).) In effect, the framework adopted

by these cases extends the coverage of the prevailing wage law

to activities not statutorily defined as “public work,” so long as

6

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

that labor is integrated into construction or other defined public

work. Over the years that interpretation led to controversy as

to just what it meant for labor to be integrated into “the ‘flow’

process of construction” (Williams, at p. 753) and so to qualify

as part of the “execution of [a] contract for public work” (§ 1772).

The federal district court applied the “integrated aspect” test

(Williams, at p. 753) but sided with defendants, concluding that

mobilization is independent of, rather than integrated into, the

construction work performed by plaintiffs at the public works

site.

Before considering the interpretation of section 1772

adopted in recent lower court cases, we examine the section’s

meaning anew, focusing first on its language and then on its

legislative history.

B. Section 1772

Familiar principles guide our interpretation. Our

fundamental task is to determine the legislative intent and

effectuate the law’s purpose, giving the statutory language its

plain and commonsense meaning. We examine that language,

not in isolation, but in the context of the statutory framework as

a whole to discern its scope and to harmonize various parts of

the enactment. (Coalition of Concerned Communities, Inc. v.

City of Los Angeles (2004) 34 Cal.4th 733, 737.) “If the language

is clear, courts must generally follow its plain meaning unless a

literal interpretation would result in absurd consequences the

Legislature did not intend. If the statutory language permits

more than one reasonable interpretation, courts may consider

other aids, such as the statute’s purpose, legislative history, and

public policy.” (Ibid.)

7

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

The operative language of section 1772 has remained

largely unchanged since 1931, when it first appeared as part of

the uncodified prevailing wage law.8 (Stats. 1931, ch. 397, § 1,

p. 910.) Considering section 1772 in the context of the overall

development of the prevailing wage law, it appears its aim was

quite modest: to ensure that the benefits of the prevailing wage

law extend to those employed by contractors or subcontractors.

As noted, the obligation to pay prevailing wages does not

now apply to work carried out by a governmental entity’s own

labor force. Before the adoption of a statute expressly setting

forth this exclusion (§ 1771), there was a vigorous debate about

whether the prevailing wage law as originally enacted applied

to government workers, as we explain below. (See post, at pp.

16–18; see generally Bishop v. City of San Jose (1969) 1 Cal.3d

56 (Bishop).) One aim of the public works scheme was and is to

protect laborers who are not part of a governmental labor force.

(Lusardi, supra, 1 Cal.4th at p. 987.)

A governmental entity electing not to use its own labor

force on a public works project could, conceivably, contract

individually with outside workers to perform the required tasks.

Alternatively, it could award a public works contract to a

contractor or subcontractor that would use those it hired to do

the work. It appears that section 1772 was enacted to ensure

that nongovernmental laborers were entitled to the prevailing

wage whether they worked under a contract directly with a

government entity, or under an agreement with a contractor or

subcontractor awarded a public works contract. That is to say,

these nongovernmental workers are entitled to the prevailing

8

See post, at pages 10 to 15.

8

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

wage notwithstanding their employment relationship with a

private contractor. Even though their employment agreement

was with a private entity, they were “deemed” to be employed

upon public work if they were engaged in the private

contractor’s “execution of [a] contract for public work.” (§ 1772.)

The obligation to pay prevailing wages to those employed

on public works arises out of section 1771, which links the

obligation to the kind of work done. Section 1772, in turn,

clarifies that workers employed by contractors or subcontractors

“are deemed to be employed upon public work,” so long as they

are employed by the contractor or subcontractor in “the

execution of any contract for public work.” Section 1774 further

specifies that “[t]he contractor to whom the contract is awarded,

and any subcontractor under him, shall pay not less than the

specified prevailing rates of wages to all workmen employed in

the execution of the contract.” Section 1772 describes a

category of persons entitled to the prevailing wage based on the

work they do, while section 1774 describes who must pay them

the prevailing wage to which they are entitled.

The structure of the prevailing wage law tends to confirm

this understanding. The scheme appears in division 2, part 7,

chapter 1 of the Labor Code. Article 1 of the law, entitled “Scope

and Operation,” defines the extent of prevailing wage coverage.

(§§ 1720–1743.) Article 2, entitled “Wages,” addresses the

wages to be paid to those performing work encompassed by the

law’s defined scope. (§§ 1770–1785.) Section 1772 is found in

article 2.9

9

These article enumerations and headings were included in the

Legislature’s 1930’s codification of the Labor Code. (See Stats.

1937, ch. 90, pp. 241–243.)

9

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

In the case of the prevailing wage law, the subject of each

article is consistent with its heading. Within article 1, sections

1720 to 1720.9 describe the types of labor to which the law

applies.10 In article 2, section 1772 focuses on the types of

workers entitled to receive the prevailing wage when they

perform work defined as “public work.” As we have recently

pointed out, however, the “protections afforded by the prevailing

wage laws only extend to activities that qualify as public work.”

(Kaanaana, supra, 11 Cal.5th at p. 167.) Nothing in the plain

language of section 1772 indicates it was intended to expand the

categories of public work covered by the prevailing wage law.

C. The Evolving Context of Section 1772 and Its

Continuing Vitality

Support for this interpretation is found in the legislative

history of section 1772. As noted, California and the federal

government enacted prevailing wage laws during the Great

Depression, when contractors intent on winning government

contracts were able to exploit the oversupply of labor. (See

Kaanaana, supra, 11 Cal.5th at pp. 165–166.)

The current California scheme traces back to the 1931 Act.

(Stats. 1931, ch. 397, § 1, p. 910.) Section 1 of that uncodified

measure contained two sentences that roughly correspond to

sections 1771 and 1772 in the current version of the prevailing

wage law. Section 1 of the 1931 Act provided, in relevant part:

10

An exception to this principle is found in section 1771 (of art.

2), which extends coverage to “contracts let for maintenance

work.” This exception to the general structure of the prevailing

wage law was added many decades after the scheme was

codified as part of the Labor Code. (Stats. 1974, ch. 1202, § 1, p.

2593.)

10

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

“Not less than the general prevailing rate of per diem wages for

work of a similar character in the locality in which the work is

performed . . . shall be paid to all laborers, workmen and

mechanics employed by or on behalf of the State of California, or

by or on behalf of any county, city and county, city, town, district

or other political subdivision of the said state, engaged in the

construction of public works, exclusive of maintenance work.

Laborers, workmen and mechanics employed by contractors or

subcontractors in the execution of any contract or contracts for

public works with the State of California, or any officer or public

body thereof, [or any political subdivision], shall be deemed to be

employed upon public works.” (Stats. 1931, ch. 397, § 1, p. 910,

italics added.)

The first sentence quoted above extended coverage to

those “employed by or on behalf” of the government in

constructing public works.11 The second sentence “deemed to be

11

It appears the reference to workers “employed by” the state

and its political subdivisions signified direct employees of the

government. While courts in two states have interpreted their

prevailing wage laws to exclude direct governmental employees

despite language applying the law to those employed “by or on

behalf” of the government, they did so only because of specific

constitutional concerns or because the provision was overridden

by a more specific statute excluding governmental employees.

(See Bradley v. Casey (Ill. 1953) 114 N.E.2d 681, 683; State ex

rel. Tucker v. Div. of Labor (W.Va. 2008) 668 S.E.2d 217, 229.)

The 1931 Act contained no provision excluding government

workers from its scope. By contrast, a rudimentary prevailing

wage law enacted in the 1890’s expressly excluded from its wage

protections “persons employed regularly in any of the public

institutions” of the state or its subdivisions. (Stats. 1897, ch. 88,

§ 1, p. 90.) That law was repealed when the 1931 Act took effect.

(See Stats. 1931, ch. 396, § 1, p. 909; Stats. 1931, ch. 397, § 1, p.

11

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

employed upon public works” those who work for contractors or

subcontractors. The latter sentence, which is the predecessor of

section 1772, appeared to clarify that prevailing wage protection

extends not only to those employed directly by the government,

as confirmed in the first sentence, but also to those who were

employed by contractors or subcontractors.12

The statutory construction used in the 1931 Act parallels

prevailing wage legislation in other states that extended the law

to workers “employed by or on behalf” of public entities. Indeed,

the statutory language at issue appears in state prevailing wage

laws adopted before the federal Davis-Bacon Act was enacted.

In an 1891 Kansas law applied to workers “ ‘employed by or on

behalf’ ” of the state or its political subdivisions, the legislation

clarified that “ ‘persons employed by contractors or

subcontractors in the execution of any contract . . . shall be

deemed to be employed by or on behalf of’ ” the state or one of its

political subdivisions for purposes of the law. (Johnson,

Prevailing Wage Legislation in the States (Aug. 1961) 84:8

Monthly Lab. Rev. 839, 840, italics added.) The italicized

provision, which could be found in other state prevailing wage

910.) It is telling that the Legislature chose not to include a

similar exclusion for government workers in the 1931 Act. It

only took such action in 1974. (Stats. 1974, ch. 1202, § 1, p.

2593.)

12

Although the reference in the first sentence to workers

employed “on behalf of” governmental entities might be

construed to extend to work done under contract, the import of

that language could be subject to debate. (See Division of Labor

Stand. v. Friends of Zoo (Mo. 2001) 38 S.W.3d 421, 422–424.)

The second sentence left no doubt that the protections of the law

extended to employees of private contractors engaged in public

works.

12

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

laws, was interpreted by the Arizona Supreme Court to ensure

that those employed by private contractors receive the benefit of

wage guarantees provided to governmental workers by deeming

them to be public employees for purposes of the law. (See State

v. Miser (Ariz. 1937) 72 P.2d 408, 413.)

Some early state prevailing wage laws, like the 1931 Act,

employed a slightly different formulation, clarifying that those

“ ‘employed by contractors or subcontractors in the execution of

any contract . . . for public works . . . shall be deemed to be

employed upon public works.’ ” (Logan City v. Industrial

Commission of Utah (Utah 1934) 38 P.2d 769, 770, italics

added.) Whether the “deeming” conferred by different statutes

was extended to government employment status, as in Kansas,

or to the status of employment on a contract for public work, the

apparent purpose was the same. Either formulation was

designed to ensure that daily wage workers employed by private

contractors on public works would receive the prevailing wage.

The language that is now incorporated in section 1772 has

no counterpart in the federal Davis-Bacon Act. (See 40 U.S.C.

§§ 3141–3148.) That is not surprising. The Davis-Bacon Act by

its plain terms has never extended to governmental

employees.13 There was no need to clarify that workers

13

As originally enacted, the Davis-Bacon Act required that

“every contract” for certain public work include a provision

specifying that the wages paid “by the contractor or

subcontractor on the public buildings covered by the contract”

shall be at least the prevailing rate. (Pub. L. No. 798 (Mar. 3,

1931) 46 Stat. 1494.) The federal statutory scheme thus only

extended to contract work. (See also Pub. L. No. 402, § 2 (Aug.

30, 1935) 49 Stat. 1011, 1012.) The Davis-Bacon Act continues

to apply exclusively to work performed by contractors or

subcontractors. (See 40 U.S.C. § 3141(a) & (c).)

13

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

employed by private contractors received the benefits of the

federal law because they were its only intended beneficiaries.

But that was not the case in California, at least at the time of

the 1931 Act. While California’s prevailing wage law is said to

share the purposes of the federal Davis-Bacon Act (City of Long

Beach v. Department of Industrial Relations, supra, 34 Cal.4th

at p. 954), the statutory language adopted in the 1931 Act bears

a closer relation to state prevailing wage laws from that period.

When the prevailing wage law was codified in 1937,

section 1 of the 1931 Act was split into two new sections, 1771

and 1772. (Stats. 1937, ch. 90, p. 243.) Section 1771 provided:

“Not less than the general prevailing rate of per diem wages for

work of a similar character in the locality in which the public

work is performed, and not less than the general prevailing rate

of per diem wages for legal holiday and overtime work shall be

paid to all workmen employed on public works, exclusive of

maintenance work.” (Ibid.) Section 1772 provided: “Workmen

employed by contractors or subcontractors in the execution of

any contract for public work are deemed to be employed upon

public work.” (Ibid.)

Again, the original function of section 1772 appears to

have been simply to ensure that those employed by a contractor

or subcontractor were given the same protection as others,

including those employed by the government itself. Prevailing

wages were due “all workmen employed on public works”

(former § 1771, added by Stats 1937, ch. 90, p. 243), with

workmen employed by contractors or subcontractors “deemed to

be employed upon public work” for the purposes of the statutory

obligation to pay prevailing wages (former § 1772, added by

Stats 1937, ch. 90, p. 243).

14

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

The 1937 codification of the prevailing wage law notably

omitted the reference to those employed “by or on behalf” of the

state or its political subdivisions. (Compare former § 1771,

added by Stats. 1937, ch. 90, p. 243, with Stats. 1931, ch. 397,

§ 1, p. 910.) But there is little reason to believe the omission

reflected a legislative intent to exclude governmental workers

from the scope of the prevailing wage law.14 Section 1771 as

adopted in 1937 applied to all “workmen employed on public

works,” with no exclusion for direct governmental employees.

(Former § 1771, added by Stats. 1937, ch. 90, p. 243.) The

explicit exclusion of prevailing wage entitlement for government

workers was not adopted by the Legislature for nearly 40 years.

(Stats. 1974, ch. 1202, § 1, p. 2593.)

Because section 1772 has not been substantively amended

since it became part of the Labor Code in 1937,15 its essential

function as to contract work should be no different than when it

was originally enacted: If public work is performed in the

execution of a contract, the fact a laborer is doing that work as

an employee of a contractor or subcontractor does not eliminate

entitlement to prevailing wages.

14

The California Code Commission prepared a Proposed Labor

Code in 1936 that recommended the codification of various labor

statutes into a single Labor Code. Notably, the Proposed Labor

Code contained no comment or annotation associated with

proposed section 1771 that would indicate an intent to change

the meaning or scope of the provision in the 1931 Act from which

that statute was derived. (Cal. Code Com. Office, Proposed

Labor Code (1936) p. 88.)

15

The sole amendment to the text enacted in 1937 was to replace

“[w]orkmen” with “[w]orkers.” (Stats. 1992, ch. 1342, § 7,

p. 6602.)

15

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

The principal counterargument to this original

understanding of section 1772 is that, at least as of today, the

statute might be considered surplusage. Decades after section

1772 was enacted, the companion statute, section 1771, was

amended to directly specify that its protections extend only to

work done under outside contract: “This section is applicable

only to work performed under contract, and is not applicable to

work carried out by a public agency with its own forces.” (Stats.

1974, ch. 1202, § 1, p. 2593.) Because section 1771 is now

expressly limited to contract work, there is no longer any need

to clarify that those employed by contractors or subcontractors

are also entitled to prevailing wage protection.

Even if section 1772 might be considered surplusage now,

that was not the case when it was first enacted. There is

considerable historical support for this interpretation in

addition to the legislative history. In the years after the

codification of the Labor Code, the Attorney General on several

occasions confirmed the understanding that, as originally

enacted, section 1771 applied to a government’s own employees.

In 1944, the Attorney General was asked to opine about a public

works project that had originally been put out to bid but that

was to be completed with day laborers hired by and under the

supervision of the county. The Attorney General concluded that,

under section 1771, the county was obligated to pay prevailing

wages for construction work performed by the day laborers hired

directly by the county. (3 Ops.Cal.Atty.Gen 399, 401 (1944).)

Sixteen years later, the Attorney General again concluded

that prevailing wage requirements applied to government

employees. (35 Ops.Cal.Atty.Gen. 1 (1960).) Specifically, the

Attorney General opined that prevailing wage requirements

applied to employees of a flood control district while

16

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

constructing things like channels and dams. In addition, the

prevailing wage law applied to county employees that

constructed storm-water conduits, highway bridges, and

buildings. (Ibid.) The Attorney General noted that former

section 1720, subdivision (a) (now 1720(a)(1)), which applies to

contract work, was not implicated. However, the work was

covered under former subdivisions (b) and (c) of section 1720,

which applied to work done for certain special districts and to

street, sewer, or other improvement work done under the

direction and supervision of the state or one of its political

subdivisions.16 (35 Ops.Cal.Atty.Gen., at p. 2.)

Consistent with the Attorney General’s 1960 opinion, a

1961 survey of prevailing wage laws in the 50 states reported

that California’s prevailing wage law applied to specified

governmental employees: those working on “irrigation,

reclamation, street, and sewer projects.” (Johnson, Prevailing

Wage Legislation in the States, supra, 84:8 Monthly Lab. Rev. at

p. 842, fn. 17.) California was identified as one of 14 states that,

at the time, extended prevailing wage protection to government

workers. (Ibid.) For at least three decades following its

enactment, section 1771 could have been understood as covering

certain governmental workers while section 1772 served the

purpose of clarifying that employees of private contractors were

likewise protected.

This court took a contrary view of section 1771’s coverage

in Bishop, supra, 1 Cal.3d 56. Interpreting that provision in

light of sections 1720 and 1724, the court concluded “that section

1771 is by its own terms applicable only to work performed

16

Former subdivisions (b) and (c) of section 1720 now appear, in

substance, in subdivision (a)(2) and (3) of that same statute.

17

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

under contract, and is not applicable to work carried out by a

public agency with its own forces.” (Bishop, at p. 64.) Thereafter

the Legislature codified this holding when it amended section

1771 in 1974. (O.G. Sansone Co. v. Department of

Transportation (1976) 55 Cal.App.3d 434, 459 (Sansone).)

Bishop was a closely contested 4–3 decision. The majority

focused on provisions in the prevailing wage law emphasizing

the law’s application to contracted work, noting that “the entire

tenor [of the law] discloses a legislative purpose to deal only with

contracted public work, and not with work done by a

municipality by force account.” (Bishop, supra, 1 Cal.3d at p.

64.) It is true that the bidding process and the intricacies of

private contracts can require specificity and provisions not

involved when governmental entities use their own workers.

The court also emphasized that the Legislature had not

amended the prevailing wage law since a 1959 Court of Appeal

decision concluded the “ ‘prevailing wage and competitive

bidding statutes have no application to work undertaken by

force account or day labor.’ ” (Id. at pp. 64–65, citing Beckwith

v. County of Stanislaus (1959) 175 Cal.App.2d 40, 48.) But the

statement in the 1959 decision was dicta and unsupported by

any analysis or citation to legal authority. (Beckwith, at p. 48.)

Indeed, the case did not concern the application of the prevailing

wage law or cite a single provision in that scheme. (Bishop, at

p. 72 (dis. opn. of Peters, J.).) Further, the Legislature’s

subsequent inaction, assuming it was even aware of the passing

reference to the prevailing wage law in the 1959 decision, has

no bearing upon the legislative intent at the time section 1771

was enacted decades earlier.

The lengthy dissent in Bishop pointed out, among other

things, that the majority’s interpretation largely ignored other

18

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

subdivisions of section 1720 defining “public works” to include

activities not performed under contract, including work

performed by special governmental districts as well as street

and sewer work. (Bishop, supra, 1 Cal.3d at p. 70 (dis. opn. of

Peters, J.).) The majority also failed to consider the legislative

history of section 1771 and its interplay with section 1772.

The incomplete analysis in Bishop led to an erroneous

interpretation of section 1771, and for that reason Bishop v. City

of San Jose, supra, 1 Cal.3d 56 is overruled to the extent it is

inconsistent with our conclusion that section 1771 as originally

enacted applied to direct governmental employees. Because

Bishop was superseded by statute when section 1771 was

amended to exclude government employees, the overruling of

the Bishop majority’s section 1771 analysis has no practical

effect. Government employees are now expressly excluded from

the scope of the prevailing wage law. (§ 1771.) However, our

rejection of Bishop does confirm that section 1772 as we have

interpreted it served an important purpose at its inception,

when the prevailing wage law extended to those employed

directly by the government. The statute was not surplusage at

the time of its enactment.

Even if Bishop were correctly decided and section 1771 did

not apply to government workers at the time of its enactment,

section 1772 would still have served a valuable purpose, if only

to clarify the application of the law. It could certainly have been

argued that employees of subcontractors engaged in public work

came within the prevailing wage law. But section 1772 removed

any doubt and continues to do so. A contractor cannot avoid the

prevailing wage obligation by parsing out tasks to

subcontractors. Further, section 1772 has been interpreted to

extend prevailing wage entitlement to workers whose services

19

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

are used by a main contractor or subcontractor even when there

is no formal employment relationship. As the Public Works

Manual prepared by the Office of the Labor Commissioner

suggests, section 1772 extends protection to workers “whose

services are ‘utilized’ in furtherance of the business of another,

notwithstanding the technical absence of an employer-employee

relationship, or a person ‘engaged in’ a task for another under

contract, or orders to do it.” (Dep. of Industrial Relations, Div.

of Labor Standards Enforcement, Public Works Manual (May

2018) § 2.2, p. 3.) Thus, section 1772 continues to serve an

important purpose in defining the types of workers entitled to

the law’s protection.

D. Plaintiffs’ Focus on “Execution” and “Deemed”

Plaintiffs’ attempt to expand the scope of the prevailing

wage law beyond the definition of “public works” largely rests on

the meaning of the terms “execution” and “deemed” in section

1772.

Plaintiffs first point to the term “execution” in section

1772, as used in the phrase “in the execution of any contract for

public work.” They claim the term broadly means “carrying out

and completion of all provisions of the contract, regardless [of]

whether that work would constitute a public work[] if it were

viewed independently.” (See Williams, supra, 156 Cal.App.4th

at p. 750.) This interpretation would bring within the scope of

the prevailing wage law any activity required to fulfill a public

works contract, even if the work did not qualify as a defined

“public work.”

This expansive role for the phrase “in the execution of” is

inconsistent with the Legislature’s approach to defining what is

encompassed by that term. When the Legislature has expanded

20

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

the reach of the law, it has done so by changing the definitions

of “public works” in article 1. (See generally §§ 1720–1720.9.)

These amendments reflect a deliberate and specific intent to

delineate and parse out what kind of labor constitutes “public

works.” Over the decades the Legislature has revisited and

refined the scope of public works definitions. For example, the

Legislature has taken care to specify that “public works” means

certain hauling of refuse to an outside location, but not if the

refuse consists of recyclable materials that are separated and

sold. (§ 1720.3.) As another example, the hauling and delivery

of ready-mixed concrete to fulfill a public works contract

constitutes a “public work,” but this same provision does not

extend to the hauling and delivery of asphalt. (§ 1720.9, subd.

(a).)

Plaintiff’s proposed interpretation would render these

distinctions meaningless if section 1772 extends the prevailing

wage law to any work required to fulfill a public works contract.

There is little reason to believe the Legislature would take great

pains to specify what constitutes “public works” in article 1

while broadening the scope of coverage through section 1772 to

encompass activities not expressly falling within those carefully

crafted definitions. Plaintiffs provide no limiting principle to

their proposed expansion. Nor does the plain language of

section 1772 furnish any limitation on plaintiffs’ proposed

understanding.

A more reasonable interpretation of “in the execution of”

is that it simply clarifies which workers are entitled to the

prevailing wage when employed by contractors. All workers are

not universally so entitled. Laborers receive the benefits of the

law if they are employed to carry out public works. The qualifier

“in the execution of [a] contract for public work” in section 1772

21

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

establishes that limitation. The effect of plaintiff’s proposal

runs contrary to legislative intent. The Legislature has taken

great care over decades to precisely categorize, in article 1, just

what kinds of labor constitute public works. Yet plaintiffs’

approach would throw aside that careful drafting by allowing a

different result under an interpretation of an imprecise statute

that has gone largely unchanged for over 90 years. If the

Legislature so intends, it is, of course, empowered to take that

action. We will not divine such an intention on its behalf.

Plaintiffs also focus on the use of the word “deemed.” They

argue that even if work being performed under contract is not

“public work” when considered in isolation, it could still be

“deemed” a public work if the terms of section 1772 are satisfied.

In effect, they would expand the scope of the prevailing wage

law by “deeming” as “public work” an activity the Legislature

has not so designated.

This approach misconceives the role that “deemed” plays

in section 1772. As used in the statute, “deemed” modifies the

types of workers entitled to the prevailing wage, not the types of

labor those workers perform. The statute is not structured to

say that work done “in the execution of any contract for public

work [is] deemed to be . . . public work.” Instead, it is the

workers who are “deemed to be employed upon public work.”

(§ 1772.) Section 1772 focuses on which workers are entitled to

the prevailing wage, not upon the types of work that qualify for

coverage.

Further, interpreting “deemed” in the sense urged by

plaintiffs would assign undue importance to opaque language

that does not otherwise signal an intent to expand the law’s

scope. If the Legislature had intended to expand the scope of

22

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

the prevailing wage law to capture work that does not fit within

the provisions defining “public works,” it is unlikely it would

have used such a subtle approach to achieve that end. “ ‘The

Legislature “does not, one might say, hide elephants in

mouseholes.” ’ ” (Jones v. Lodge at Torrey Pines Partnership

(2008) 42 Cal.4th 1158, 1171.)

E. Judicial and Administrative Decisions

1. Court of Appeal Cases

While this court has not previously interpreted section

1772, the provision has been the subject of several lower court

opinions. None of these decisions provides a persuasive reason

to depart from the interpretation outlined here. For the reasons

explained below, we disapprove those decisions in whole or in

part.

No California case meaningfully touched upon section

1772 for decades after its enactment. The first case arguably to

do so was Sansone, supra, 55 Cal.App.3d 434, in 1976. There,

the court considered whether truck drivers who delivered

materials used in building roads were entitled to the prevailing

wage. The court quoted sections 1772 and 1774 but otherwise

included no analysis or discussion of those statutes. (Sansone,

at p. 441.) The issue as framed was whether the trucking

companies that employed the drivers were subcontractors

within the meaning of the prevailing wage law. (Ibid.)

Finding no California cases discussing who qualifies as a

subcontractor under the prevailing wage law, the court turned

to the federal Davis-Bacon Act (40 U.S.C. § 3141 et seq.).

(Sansone, supra, 55 Cal.App.3d at p. 442.) Under the federal

scheme, a supplier of standard building materials, referred to as

a “bona fide” materialman or material supplier, is not

23

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

considered a subcontractor. A bona fide material supplier is

therefore exempt from the obligation to pay its employees,

including truck drivers, the prevailing wage. For the Davis-

Bacon Act exemption to apply, the supplier must sell goods to

the general public, the location from which the supplies are

obtained may not be established specifically for the particular

public works project, and the supply location cannot be situated

on the public works site. (Ibid.)

Sansone held the trucking companies qualified as

subcontractors who used their employees to fulfill a public

works contract and, thus, were obligated to pay prevailing

wages. (Sansone, supra, 55 Cal.App.3d at p. 445.) Two key

factors distinguished the companies from those material

suppliers exempt from federal prevailing wage requirements.

First, the roadbuilding materials were obtained from a location

adjacent to the project site and established specifically to serve

that site. (Id. at pp. 443–444.) Second, the trucking companies

were carrying out a term of the prime contract, which required

the prime contractor to furnish the materials. (Ibid.)

In reaching its decision, the Sansone court also looked to

Green v. Jones (Wis. 1964) 128 N.W.2d 551 (Green), a decision of

the Wisconsin Supreme Court interpreting that state’s

prevailing wage law. (Sansone, supra, 55 Cal.App.3d at p. 443.)

The Wisconsin decision contrasted hauling from a commercial

location operating continuously, which would not be covered,

with hauling from a location set up solely to serve the project,

which would be covered. (Id. at p. 444.) But the Wisconsin court

went further, stating that regardless of the source of the

materials, the drivers would be covered if the materials were

immediately utilized on the improvement. (Ibid.) In assessing

coverage, it considered whether “ ‘[t]he drivers’ tasks were

24

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

functionally related to the process of construction’ ” and the

“ ‘delivery of materials was an integrated aspect of the “flow”

process of construction.’ ” (Ibid., citing Green, at p. 563, italics

added.) While Sansone ostensibly focused on whether the

trucking companies were subcontractors rather than material

suppliers, its approach has served to influence California’s

section 1772 jurisprudence. That influence was due in part to

Sansone’s citation to Green and its embrace of the notion that

work integrated into the construction process is covered under

the prevailing wage law. (See Williams, supra, 156 Cal.App.4th

at pp. 752–754; Sheet Metal, supra, 229 Cal.App.4th at pp. 205–

206.)

The next California case to address section 1772 was

Williams, supra, 156 Cal.App.4th 742, which like Sansone

involved truckers hauling materials. In Williams, truckers

removed unused construction materials like excess rock and

sand from construction sites. (Williams, at pp. 746–747.) The

Williams court characterized the legal question as whether the

truckers removing the construction materials were employed

“ ‘in the execution’ ” of the contract under section 1772.

(Williams, at p. 749.) The court concluded the truckers were

not entitled to the prevailing wage under that statute. (Id. at

p. 753.)

Williams began the analysis by focusing on the definition

of “execution” within section 1772, concluding that the term

“plainly means the carrying out and completion of all provisions

of the contract.” (Williams, supra, 156 Cal.App.4th at p. 750.)

Then, while acknowledging that Sansone concerned who is or is

not a subcontractor under the prevailing wage law, Williams

turned to that case to “inform[] [the] assessment of the intended

reach” of the law to workers employed “ ‘in the execution’ ” of a

25

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

public works contract. (Ibid.) Relying on Sansone and Green,

Williams emphasized a task’s functional relationship to the

process of construction and whether a task was “ ‘an integrated

aspect of the “flow” process of construction.’ ” (Id. at p. 751,

citing Green, supra, 128 N.W.2d at p. 563.) In assessing

coverage, Williams considered whether a task was required to

carry out a term of the public works contract, whether the work

was performed at the project site or a site “integrally connected”

to the project site, and whether work performed off the actual

construction site was necessary to fulfill the contract. (Williams,

at p. 752.)

There was no evidence of a functional relationship

between the actual construction and the subsequent removal of

unused materials. Accordingly, Williams held the removal work

was “unrelated to the performance of the prime public works

contract . . . .” (Williams, supra, 156 Cal.App.4th at p. 753.) It

was “no more an integral part of the process of the public works

project than the delivery of generic materials to the public works

site by a bona fide material supplier.” (Ibid.) According to the

Williams court, “there was no evidence from which a

determination could be made that the off-hauling was ‘an

integrated aspect of the “flow” process’ [citation] of the

project.”17 (Williams, at p. 754.)

17

After Williams the Legislature amended the definition of

“hauling of refuse,” a covered public work under section 1720.3,

to clarify that the term “includes, but is not limited to, hauling

soil, sand, gravel, rocks, concrete, asphalt, excavation materials,

and construction debris.” (§ 1720.3, subd. (b), as amended by

Stats. 2011, ch. 676, § 1.) Consistent with our analysis here, it

did so by amending the relevant section in article 1.

26

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

The only other California case to consider the meaning of

section 1772 is Sheet Metal, 229 Cal.App.4th 192, which

concerned coverage for offsite fabrication. In Sheet Metal, a

community college entered into a public works contract to

upgrade its facilities, including the update of a heating and

cooling system. A firm that made a variety of ductwork and

other sheet metal components at its permanent offsite facility

subcontracted to make, and then install, its components into the

college system. (Id. at p. 196.) The issue was whether the firm’s

workers who made the ductwork offsite were entitled to the

prevailing wage. The court concluded there was no such

entitlement. It reasoned “the work was not done ‘in the

execution’ of the contract within the meaning of section 1772.”

(Id. at p. 214.) It observed that the offsite facility’s location and

existence were wholly unrelated to the particular public works

project. (Ibid.)

Sheet Metal built upon the foundation deduced from

Sansone and Williams, which emphasized that the critical factor

in assessing coverage under section 1772 is “whether it is

integrated into the flow process of construction.” (Sheet Metal,

supra, 229 Cal.App.4th at p. 206.) The decision also relied to a

significant extent on a federal regulation defining the “site of the

work” for purposes of the Davis-Bacon Act to exclude

“ ‘permanent . . . fabrication plants . . . of a contractor or

subcontractor whose location and continuance in operation are

determined wholly without regard to a particular Federal or

federally assisted contract or project.’ ” (Sheet Metal, at p. 210,

citing 29 C.F.R. § 5.2(l)(3) (2014).)

These three cases are the only published California

opinions that have purported to interpret section 1772 since its

enactment. Plaintiffs urge they should be disregarded because

27

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

they apply a standard derived from the federal Davis-Bacon

Act’s limitation on coverage to persons “employed directly on the

site of the work.”18 (40 U.S.C. § 3142(c)(1).) According to

plaintiffs, California’s prevailing wage law includes no such

geographical limitation on coverage. They argue that even if

there was a valid reason for applying principles derived from

federal law to hauling and offsite fabrication, those principles

should not be used more generally to define the scope of section

1772.

It is unnecessary to consider the geographical scope of the

prevailing wage law to assess the validity of the approach taken

in Sansone, Williams, and Sheet Metal.19 Those cases primarily

involved whether a company is a subcontractor within the

meaning of the prevailing wage law. While the factors they

employed may be valid to resolve that narrow question, they are

not necessarily useful to resolve whether an activity is

performed “in the execution” of a public works contract under

section 1772. The reliance on their approach for this different

purpose has led to an interpretation of section 1772 that

expands its application to tasks that might not otherwise qualify

as public works, simply because they have some functional

relationship or integration with public work. That expansion is

not supported by the language or legislative history of section

18

Aside from federal authority, Sansone also relied upon the

Wisconsin Supreme Court decision in Green, supra, 128

N.W.2d 1. (Sansone, supra, 55 Cal.App.3d at pp. 443–444.) Like

the federal Davis-Bacon Act, Wisconsin limited its coverage to

“ ‘work on the site.’ ” (Green, at p. 6.)

19

We express no view concerning whether California’s

prevailing wage law places a geographic limitation on coverage

in relation to the public works site.

28

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

1772. It instead originates from the federal Davis-Bacon Act,

which contains no statutory language analogous to section 1772.

Further, the approach in Sansone, Williams, and Sheet

Metal causes coverage to turn on factors other than an activity’s

definition as a public work. To the extent coverage is premised

upon whether an activity is integrated into the flow process of

construction, the approach ignores the carefully crafted

definitions of public work contained in the prevailing wage law.

Moreover, it is not entirely clear what it means for an activity to

be “integrated” into construction or other defined public work.

To the extent it might be argued the Legislature has

acquiesced in the existing construction of section 1772 by failing

to amend or clarify its provisions, the argument is not

persuasive. “In the area of statutory construction, an

examination of what the Legislature has done (as opposed to

what it has left undone) is generally the more fruitful inquiry.

‘[L]egislative inaction is “ ‘a weak reed upon which to

lean’ ” . . . .’ ” (Harris v. Capital Growth Investors XIV (1991) 52

Cal.3d 1142, 1156; accord, Saint Francis Memorial Hospital v.

State Dept. of Public Health (2020) 9 Cal.5th 710, 723.) Since

Sansone was decided, the Legislature has actively defined and

modified the definitions of “public works.” (See, e.g., Stats. 2000,

ch. 881, § 1, p. 6517; Stats. 2001, ch. 938, § 2, p. 7509; Stats.

2012, ch. 810, § 1; Stats. 2015, ch. 739, § 1.) These actions are

not consistent with an interpretation of section 1772 that would

expand the scope of the prevailing wage law as plaintiffs urge.

The prevailing wage law as written and amended does not

support an interpretation of section 1772 that expands the law’s

scope beyond defined “public works.” To the extent O.G.

Sansone Co. v. Department of Transportation, supra, 55

29

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

Cal.App.3d 434, Williams v. SnSands Corp., supra, 156

Cal.App.4th 742, and Sheet Metal Workers’ Internat. Assn.,

Local 104 v. Duncan, supra, 229 Cal.App.4th 192, suggest to the

contrary or are otherwise inconsistent with this opinion, they

are disapproved.20

In his dissent in Busker v. Wabtec Corp. (Aug. 16, 2021,

S251135) ___ Cal.5th ___ (dis. opn. of Cuéllar, J.) (Busker),

Justice Cuéllar argues that the majority “overturns decades of

legal decisions that had established a persuasive, workable

framework for interpreting and applying” section 1772. 21

(Busker, at ___ [p. 3] (dis. opn. of Cuéllar, J.).) However, it is

precisely because the existing “framework” is so unclear that the

Ninth Circuit asked this court to address the application of

section 1772 in two separate cases. (See ante, at p. 3; Busker, at

___ [p. 26].) The interpretation we adopt turns on careful

consideration of the text of section 1772 and its history, not upon

concerns about whether the current interpretation is difficult to

administer. In any event, the existing framework could hardly

be described as workable.

20

We express no view as to whether Sansone and its progeny

have continued vitality in assessing whether an employer is a

subcontractor (as opposed to bona fide material supplier) within

the meaning of the prevailing wage law.

21

The dissent has chosen to set forth the bulk of its section 1772

analysis and critique of the majority’s approach in a separate

opinion filed in Busker, a decision filed concurrently with this

opinion. (See dis. opn. of Cuéllar, J., post, at p. 2; Busker, supra,

___ Cal.5th at ___ [p. 27, fn. 17].) The reader is directed to

Justice Cuéllar’s dissent in Busker for a more complete

explanation of the dissent’s approach to interpreting section

1772 and its response to the majority’s analysis here. (Busker,

at ___ [pp. 1–24] (dis. opn. of Cuéllar, J.).)

30

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

The difficulty in applying the approach taken in Sansone

and its progeny is exemplified by the three “factors” the dissent

identifies as relevant to assessing “whether labor is done in ‘the

execution of [a] contract for public work’ under section

1772 . . . .” (Dis. opn. of Cuéllar, J., post, at p. 2.) The factors

include “whether the labor is (1) functionally related to the

construction process; (2) integrated into that process; and (3)

done to fulfill the prime contractor’s obligation to complete a

public works aspect of the project.” (Id. at pp. 2–3, fn. omitted.)

These factors are not “longstanding,” as Justice Cuéllar’s Busker

dissent suggests (Busker, supra, ___ Cal.5th at ___ [p. 12] (dis.

opn. of Cuéllar, J.)), but instead are derived from a hodgepodge

of considerations found in Sansone, Williams, and Sheet Metal.

Moreover, despite the emphasis in Justice Cuéllar’s Busker

dissent on the importance of the terms “execution” and “deemed”

in section 1772 (see Busker, at ___ [pp. 3–4] (dis. opn. of Cuéllar,

J.)), the three-part test does not even mention them. Instead,

the test relies on broad and undefined terms not found in the

statute: “functionally related,” “construction process,”

“integrated,” and “public works aspect of the project.” (Id. at ___

[pp. 10–11] (dis. opn. of Cuéllar, J.).)

Justice Cuéllar’s Busker dissent acknowledges that some

“judgment” will be required “to discern whether a particular

type of labor has a functional or integrated relationship with

contracted-for public work.” (Busker, supra, ___ Cal.5th at ___

[p. 14] (dis. opn. of Cuéllar, J.).) However, the shifting

characterization of how section 1772 is to be applied points to

the extreme difficulty in exercising that judgment. At one point,

Justice Cuéllar’s Busker dissent refers to “[w]ork critically

related” to the execution of a public works contract. (Busker, at

___ [p. 2] (dis. opn. of Cuéllar, J.), italics added.) Elsewhere, it

31

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

refers to “labor that is not unduly attenuated from the actual

construction work or other defined public work, and instead

bears a logical connection to the preconstruction, construction,

or postconstruction process.” (Id. at ___ [p. 11] (dis. opn. of

Cuéllar, J.), italics added.) At another point, it describes “tasks

vital to the performance and completion of covered ‘public work’

. . . .” (Id. at ___ [p. 24] (dis. opn. of Cuéllar, J.), italics added.)

Finally, it describes section 1772 as covering “labor performed

in preparation for, in furtherance of, or otherwise bearing a

critical relationship to defined public work and the public works

project as a whole . . . .” (Id. at ___ [p. 24] (dis. opn. of Cuéllar,

J.), italics added.) The differing and expansive terms used to

describe the application of section 1772 illustrate the inherent

difficulty in applying the test laid out in the dissent. It is simply

not the case that the majority approach rejects a persuasive or

workable framework for interpreting and applying section 1772.

2. Administrative Decisions

In addition to case law interpreting section 1772,

administrative decisions of the Department of Industrial

Relations (Department) have also applied the statute. Amicus

curiae Division of Labor Standards Enforcement cites several

coverage decisions from the 1980’s and 1990’s interpreting

section 1772 to apply to mobilization. These decisions do not

have a precedential effect. (See Kaanaana, supra, 11 Cal.5th at

p. 179.) Further, the Department has no comparative

advantage over the courts in deciding an issue of pure statutory

interpretation. (Kaanaana, at p. 179; Center for Biological

Diversity v. Department of Fish & Wildlife (2015) 62 Cal.4th 204,

236.) Nevertheless, while “ultimate responsibility for statutory

interpretation rests with the courts, an agency’s interpretation

32

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

‘is “one among several tools available to the court” when judging

the [statute’s] meaning and legal effect.’ ” (Id. at p. 178.)

In his Busker dissent, Justice Cuéllar argues that the

Department’s decisions deserve “serious consideration and offer

further insight into what the statute means.” (Busker, supra,

___ Cal.5th at ___ [p. 7] (dis. opn. of Cuéllar, J.).) He

acknowledges the decisions have “dutifully applied the approach

in Sansone, Williams, and Sheet Metal for effectuating section

1772.” (Busker, at ___ [p. 13] (dis. opn. of Cuéllar, J.).) But that

is precisely why they add nothing to the analysis. An

administrative interpretation that is clearly erroneous, even if

long-standing and consistent, is entitled to no deference. (See

Sara M. v. Superior Court (2005) 36 Cal.4th 998, 1012.) Because

the decisions apply the same approach to section 1772 as

Sansone and its progeny, they offer no valid reason to extend

coverage to mobilization under that statute.

F. Application to Mobilization

In light of our interpretation of section 1772, the answer

to the Ninth Circuit’s certified question is simple. That statute

does not expand coverage to labor not otherwise defined as

public work. Unless mobilization qualifies as public work, an

employer has no obligation to pay the prevailing wage to those

who perform it. Section 1772 cannot independently serve as the

basis for concluding that the prevailing wage must be paid for

mobilization.

This conclusion does not rule out the possibility that

prevailing wages must be paid for mobilization work under some

33

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

other theory.22 But that issue is not before us. The Ninth

Circuit’s question is limited to whether mobilization is covered

under section 1772.

While this court may restate the certified question (Cal.

Rules of Court, rule 8.548(f)(5)), we lack the power to reshape

the federal litigation that gave rise to the question in the first

instance. When we decide a question of California law posed by

another court, we are limited to an issue that “could determine

the outcome of a matter pending in the requesting court.” (Cal.

Rules of Court, rule 8.548(a)(1).) The broader issue of whether

plaintiffs are entitled to be paid the prevailing wage under any

conceivable theory is beyond the scope of the pending federal

litigation. The sole issue presented on appeal to the Ninth

Circuit was whether section 1772 afforded coverage for

mobilization. A decision concerning whether mobilization

qualifies as “construction” or other defined “public work” would

not only consider a defense to the partial summary judgment

motion not raised by the plaintiffs, but it would also not address

the narrow legal issue before the Ninth Circuit.

Plaintiffs did raise the issue of whether transportation of

equipment to the work site should be treated as “travel time,”

which, they claim, must be compensated at the prevailing wage.

22

As used in the prevailing wage law, for example, the term

“ ‘construction’ ” includes “preconstruction” and

“postconstruction” phases of construction work. (§ 1720(a)(1); cf.

Priest v Housing Authority of City of Oxnard (1969) 275

Cal.App.2d 751, 756.) In addition, section 1720, subdivision

(a)(3) defines “ ‘public works’ ” to include “[s]treet . . .

improvement work.” We express no view as to whether

mobilization qualifies as construction, street improvement

work, or any other category of “ ‘public works’ ” defined in

section 1720 et seq.

34

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

To the extent their contention is premised upon the application

of section 1772, the argument fails for the reasons articulated

above. If travel time does not fall under a definition of public

work, section 1772 does not independently provide a basis for

coverage. Insofar as there may be some other statutory basis for

compensating travel time at the prevailing rate, that issue is

beyond the scope of the question certified by the Ninth Circuit.

Justice Cuéllar’s dissents here and in Busker argue in

quite forceful terms that a different approach to the

understanding of “public works” is called for. They set out what

our colleagues urge would be a better interpretation of the

statutory language, and they reject the notion that coverage is

limited to defined “public works.” They fail to acknowledge,

however, that this is a legislative function. The Legislature may

of course choose, or decline, to modify the definitions of “public

works” it has chosen over the decades. That is a policy choice to

be considered by the Legislature after input from all interested

parties and the exercise of its own judgment as to how best serve

the sometimes competing goals it seeks to achieve.

In our view, it is not the role of the judiciary to usurp that

legislative prerogative. Reading existing legislative enactments

with care is not “pernicious” or merely an exercise in “judicial

modesty.” (Busker, supra, ___ Cal.5th at ___ [pp. 2, 3] (dis. opn.

of Cuéllar, J.).) Instead, it is an approach, firmly established in

our jurisprudence, that honors the important safeguards served

by the separation of powers. “[C]onstru[ing] the law liberally”

is a different enterprise from rewriting the law to have it read

as we think best. (Busker, at ___ [p. 2] (dis. opn. of Cuéllar, J.).)

We emphasize two points, lest there be any confusion.

First, the prevailing wage law covers what the Legislature says

35

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Opinion of the Court by Corrigan, J.

it covers. Second, our holding is narrow. We merely address the

question posed by the parties and the Ninth Circuit: whether

section 1772, standing alone, expands the scope of the term

“public works” to embrace labor that is not covered by the

definitions enacted as part of section 1720 et seq. Nothing we

say here should be read to condone any attempt to ignore the

protections or obligations of the prevailing wage law.

III. CONCLUSION

We answer the Ninth Circuit’s question as follows.

Section 1772 does not expand the categories of public work that

trigger the obligation to pay at least the prevailing wage under

section 1771. Here there is no contention that mobilization

qualifies as defined “public work.” Under the circumstances,

section 1772 does not provide a basis for requiring plaintiffs to

be paid the prevailing wage for that work.

CORRIGAN, J.

We Concur:

CANTIL-SAKAUYE, C. J.

KRUGER, J.

GROBAN, J.

JENKINS, J.

36

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

S253574

Dissenting Opinion by Justice Cuéllar

Plaintiffs (Leopoldo Pena Mendoza, Elviz Sanchez, and

Jose Armando Cortes) worked as engineers for a public works

roadway construction project. They operated heavy milling

machines to break up the existing roadbeds so that new roads

could be built. (Maj. opn., ante, at p. 2.) This was

unquestionably “ ‘public works’ ” labor under Labor Code section

1720, subdivision (a)(1),1 as it clearly involved “[c]onstruction,

alteration, demolition, installation, or repair work . . . .”

(§ 1720, subd. (a)(1).) The majority agrees. (Maj. opn., ante, at

p. 6.)

Plaintiffs also had to engage in “mobilization”

work: transporting the milling machinery to and from offsite

storage locations and preparing it for use. (Maj. opn., ante, at p.

2 & fn. 3.) There was little prospect that plaintiffs could

complete the construction work they were hired to do without

mobilizing the machines used to repave the roadways. The

majority nonetheless rejects plaintiffs’ argument that

mobilization labor qualifies for prevailing wage coverage under

section 1772, which provides that “[w]orkers employed by

contractors or subcontractors in the execution of any contract for

public work are deemed to be employed upon public work.”

(§ 1772.) By its account, section 1772 in no way relates to the

1

Further unspecified section references are to the Labor

Code.

1

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Cuéllar, J., dissenting

scope of work covered, and instead simply ensures coverage for

contract workers engaged in defined public works activities.

(See, e.g., maj. opn., ante, at pp. 1–2, 8–10, 14, 21–22.)

That’s a conclusion I cannot embrace. I respectfully

dissent for the same reasons explained more fully in my

separate dissenting opinion in the other prevailing wage case we

also decide today, Busker v. Wabtec Corp. (Aug. 16, 2021,

S251135) __ Cal.5th __ (Busker).

Because of the prevailing wage law’s critical function in

protecting workers employed on public works, we must interpret

the law liberally. (City of Long Beach v. Department of

Industrial Relations (2004) 34 Cal.4th 942, 949–950.) For

several decades, the Courts of Appeal and Department of

Industrial Relations (DIR) have fulfilled their obligation in

construing section 1772 by interpreting it to cover certain work

critically related to the “execution of” (ibid.) a public works

contract. (See, e.g., O.G. Sansone Co. v. Department of

Transportation (1976) 55 Cal.App.3d 434, 443–444 (Sansone);

Williams v. SnSands Corp. (2007) 156 Cal.App.4th 742, 752–

753; Sheet Metal Workers’ Internat. Assn., Local 104 v. Duncan

(2014) 229 Cal.App.4th 192, 205–206, 211–214 (Sheet Metal).)

These cases provide us with three factors that help determine

whether labor is done in “the execution of [a] contract for public

work” under section 1772: whether the labor is (1) functionally

related to the construction process; (2) integrated into that

2

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Cuéllar, J., dissenting

process; and (3) done to fulfill the prime contractor’s obligation

to complete a public works aspect of the project.2

The majority nonetheless breaks with this established

authority without justification. It glosses over section 1772’s

language deeming workers engaged in the “execution of” a public

works contract — i.e., working to carry out and complete the

construction or other related tasks for the project — to be

employed on “public work.” (§ 1772.) It papers over this

language, and in the process disapproves of long-standing

authority providing a workable framework for applying it, on

the basis of an implausible reading of the section’s exceedingly

spare legislative history. And its interpretation undermines the

prevailing wage law’s purposes; among other things, it

encourages public works employers to segment out labor not

defined as “public works,” but nonetheless constituting labor as

crucial as it is integral to public works projects, so that they can

pay lesser wages.

I add two brief observations to my Busker dissent (Busker,

supra, __ Cal.5th at p. __ [pp. 1–24] (dis. opn. of Cuéllar, J.)),

underscoring how the majority’s interpretation errs as it

specifically relates to mobilization work. First, mobilization

naturally merits prevailing wage coverage based on its critical

relationship with covered public work. The three factors from

the Sansone line of cases reinforce this conclusion. The

mobilization at issue here was functionally related to and

2

Although the Sansone line of cases refers to the

“construction” process (see, e.g., Sansone, supra, 55 Cal.App.3d

at p. 444), its principles would apply to any other type of activity

that qualifies as “public work.” I therefore use “construction”

here as an umbrella term for all the kinds of labor defined by

the statute as public work.

3

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Cuéllar, J., dissenting

integrated into the covered milling work and the project as a

whole because the road construction as contracted for could not

occur unless the machines arrived promptly, worked properly,

and were removed when they served their purpose. Moreover,

plaintiffs had to engage in mobilization to fulfill the prime

contractor’s contractual obligation to build new roads. The

contractor owned the milling machines and elected to store them

offsite. It directed its own employees to prepare and transport

them so those employees could then use the machines as part of

the road construction called for by the contract.

In other words, the mobilization of specialized

construction equipment by the skilled workers who would use

them at the jobsite was sufficiently connected with the execution

of a public construction project to be deemed public work under

section 1772. (Cf. Allied Concrete & Supply Co. v. Baker (9th

Cir. 2018) 904 F.3d 1053, 1061 [explaining how prevailing wage

coverage for ready-mix concrete drivers, as opposed to drivers

supplying standard building materials, makes sense because

the former “are more integrated into the construction process”

and “are more skilled than other drivers and provide a material

that is more important to public works projects than other

materials such that paying the prevailing wage will attract

superior drivers and improve public works”].) Excluding this

labor from coverage under section 1772 despite its critical role

makes no sense.

Also calling into question the majority’s interpretation: It

flies in the face of the DIR’s consistent position covering

mobilization work under section 1772. As the DIR’s Division of

Labor Standards and Enforcement argues in its amicus curiae

brief and illustrates in the past coverage determinations that it

provides in its request for judicial notice, the agency has for

4

MENDOZA v. FONSECA MCELROY GRINDING CO., INC.

Cuéllar, J., dissenting

decades followed Sansone and interpreted the section as

covering mobilization labor based on the labor’s critical

relationship to covered work. Neither defendants (Fonseca

McElroy Grinding Co. Inc. and Granite Rock Company) nor the

majority identify any circumstance where the DIR has

determined that mobilization is not covered.

Because plaintiffs’ mobilization work critically facilitated

the public works roadway construction project, section 1772

entitled them to prevailing wages for this labor. They performed

this labor “in the execution of” the contract for the roadway

project, and section 1772’s language therefore “deemed” them

“to be employed upon public work.” (§ 1772.) But the majority

narrows this statutory language beyond recognition. So with

respect, I dissent.

CUÉLLAR, J.

I Concur:

LIU, J.

5

See next page for addresses and telephone numbers for counsel who

argued in Supreme Court.

Name of Opinion Mendoza v. Fonseca McElroy Grinding Co., Inc.

__________________________________________________________

Procedural Posture (see XX below)

Original Appeal

Original Proceeding XX on request by 9th Circuit (Cal. Rules of

Court, rule 8.548)

Review Granted (published)

Review Granted (unpublished)

Rehearing Granted

__________________________________________________________

Opinion No. S253574

Date Filed: August 16, 2021

__________________________________________________________

Court:

County:

Judge:

__________________________________________________________

Counsel:

Justice At Work Law Group, Tomas E. Margain; Esner, Chang &

Boyer, Stuart B. Esner and Holly N. Boyer for Plaintiffs and

Appellants.

Altshuler Berzon, Eileen Goldsmith and Zoe Palitz for International

Association of Sheet Metal, Air, Rail & Transportation Workers, Sheet

Metal Workers’ Local Union No. 104 as Amicus Curiae on behalf of

Plaintiffs and Appellants.

David Balter, Kristin García, Luong Chau and Lance Grucela for

Department of Industrial Relations, Division of Labor Standards

Enforcement as Amicus Curiae on behalf of Plaintiffs and Appellants.

Simpson, Garrity, Innes & Jacuzzi, Paul V. Simpson and Sarah E.

Lucas for Defendants and Respondents.

Rutan & Tucker, Paul Aherne and Alyssa Roy for Construction

Employers’ Association as Amicus Curiae on behalf of Defendants and

Respondents.

Cook Brown, Dennis B. Cook and Stephen McCutcheon for Modular

Building Institute, Northern Alliance of Engineering Contractors and

Western Electrical Contractors Association, Inc., as Amici Curiae on

behalf of Defendants and Respondents.

Sweeny, Mason, Wilson & Bosomworth and Roger M. Mason for United

Contractors as Amicus Curiae on behalf of Defendants and

Respondents.

Jeffer Mangels Butler & Mitchell, Kerry Shapiro, Matthew D. Hinks

and Martin P. Stratte for California Construction and Industrial

Materials Association as Amicus Curiae on behalf of Defendants and

Respondents.

Ogletree, Deakins, Nash, Smoak & Stewart, Robert R. Roginson and

Ryan H. Crosner for Associated General Contractors of California as

Amicus Curiae on behalf of Defendants and Respondents.

Atkinson, Andelson, Loya, Ruud & Romo, Robert Fried, Thomas A.

Lenz and Elizabeth P. Lind for Associated Builders and Contractors of

California as Amicus Curiae on behalf of Defendants and Respondents.

Counsel who argued in Supreme Court (not intended for

publication with opinion):

Stuart B. Esner

Esner, Chang & Boyer

234 East Colorado Boulevard, Suite 975

Pasadena, CA 91101

(626) 535-9860

Tomas E. Margain

Justice At Work Law Group

84 West Santa Clara Street, Suite 790

San Jose, CA 95113

(408) 317-1100

Paul V. Simpson

Simpson, Garrity, Innes & Jacuzzi, P.C.

601 Gateway Boulevard, Suite 950

South San Francisco, CA 94080

(650) 615-4860

Robert R. Roginson

Ogletree, Deakins, Nash, Smoak & Stewart, P.C.

400 South Hope Street, Suite 1200

Los Angeles, CA 90071

(213) 457-5873

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.