Opinion

Manela v. Stone

Court
California Court of Appeal
Filed
Jul 1, 2021
Status
Published
Cited by
0 cases
Authority
More cited than 15.8%

The opinion

Filed 7/1/21

CERTIFIED FOR PUBLICATION

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION ONE

YOSEF Y. MANELA, B302660

Plaintiff and Respondent, (Los Angeles County

Super. Ct. Nos. 19STCV18640

v. c/w 19STCV24162)

JOHN D.S. STONE et al.,

Defendants and Appellants.

APPEAL from orders of the Superior Court of Los Angeles

County, Daniel S. Murphy, Judge. Reversed.

Selvin & Weiner and Beryl Weiner for Defendants and

Appellants.

Buchalter, Robert M. Dato; and Gabriel G. Green for

Plaintiff and Respondent.

____________________________________

Defendants John D.S. Stone (Stone) and JDSS

Construction Company, Inc. (JDSS) (collectively, the Stone

parties) appeal from an order removing the Stone parties’

mechanic’s lien on a property owned by plaintiff Yosef Manela

(Manela) and his former wife Nomi Manela (the Manela

property). The Stone parties jointly filed the mechanic’s lien to

collect payment for work they performed on the Manela property

pursuant to a construction contract executed by the Manelas

and Stone (the Manela contract), the quality of which Manela

challenged in a separate lawsuit. After compelling the parties’

disputes to arbitration, the trial court granted Manela’s motion

to remove the mechanic’s lien based on the court’s conclusion that

Business and Professions Code section 7031, subdivision (a)1

likely required the Stone parties to forfeit compensation for any

work performed under the Manela contract.

Section 7031 generally prohibits a contractor from

collecting any compensation under a construction contract if the

contractor is not licensed at all times during performance of that

contract. (See § 7031, subd. (a).) After beginning work on the

Manela property, Stone formed a corporation, JDSS, of which

Stone is the sole shareholder, and assigned the Manela contract

to the new entity. The trial court concluded that, because Stone

assigned the contract to JDSS before Stone’s contracting license

had been transferred to JDSS, JDSS was unlicensed during a

portion of the time it was “performing work under the [c]ontract”

and could not recover compensation thereunder, including via the

mechanic’s lien.

1Unless otherwise specified, all statutory references are to

the Business and Professions Code.

2

On appeal, the Stone parties argue that the evidence

does not support that JDSS performed work under the Manela

contract before it became licensed, and in particular that the

trial court improperly relied on an assignment agreement as

conclusive evidence of such unlicensed performance. We hold

that the evidence in the record compels the conclusion that

section 7031 does not apply in the instant case. Accordingly,

we reverse.

FACTS AND PROCEEDINGS

A. The Manela Contract

From 1982 through 2015, Stone held a California general

contractor’s license (license No. 425872) and did business under

that license as Stone Construction Company, a fictitious business

name for his sole proprietorship.

In early 2014, Stone and Manela began discussing a major

home remodeling project on the Manela property. On January 4,

2015, Stone—as a sole proprietor doing business as Stone

Construction Company—and the Manelas signed the Manela

contract regarding the project. The contract provided that “SCC

[Stone Construction Company] will perform the work specified

herein at the [Manela] property on behalf of the owner[s] [the

Manelas]” and included a price and estimated completion date

of December 2015. (Capitalization omitted.) It further provided

that “extra work and change orders become part of the contract

once the order is prepared in writing and signed by the parties

prior to the commencement of any work covered by the new

change order.” (Capitalization omitted.)

3

B. The Incorporation of Stone’s Business As JDSS

On February 11, 2015, after work on the project had begun,

Stone formed JDSS, a corporation doing business under the same

fictitious business name as Stone’s sole proprietorship, Stone

Construction Company. Stone was the sole shareholder of the

corporation. Stone applied to the Contractors State License

Board (CSLB) to reissue his existing contractor’s license to JDSS.

While waiting for the CSLB to reissue the license, Stone

executed a March 15, 2015 agreement between himself and JDSS

(the assignment agreement) that purports to formally assign to

JDSS “all of [Stone’s] rights and obligations under the [Manela

contract]” “effective . . . March 15, 2015.”2 The agreement was

signed by Stone in his personal capacity, as well as by Stone on

behalf of JDSS in his capacity as its president. It was not signed

by either of the Manelas.

The CSLB ultimately reissued Stone’s license (license

No. 425872) to JDSS on June 22, 2015. Stone is listed as the

“qualifying individual” on the reissued license. (See § 7068,

subd. (b)(3) [“a corporation, or any other combination or

2 Although the assignment agreement purportedly

“assigns” Stone’s “rights and obligations” under the Manela

contract, it is properly understood as an assignment of Stone’s

rights under the Manela contract to JDSS, which JDSS accepted,

and an attempted delegation of Stone’s duties under that

contract. (See 29 Williston on Contracts (4th ed. 2021) § 74:27

[“One can assign rights and delegate duties; however, one cannot

assign duties”]; Recorded Picture Company [Productions] Ltd. v.

Nelson Entertainment, Inc. (1997) 53 Cal.App.4th 350, 362 [the

“ ‘assignment of rights under an executory contract does not

[necessarily] cast upon the assignee the obligations imposed by

the contract upon the assignor’ ”].)

4

organization, . . . shall qualify by the appearance of a responsible

managing officer or responsible managing employee who is

qualified for the same license classification as the classification

being applied for”].)

C. Activity During the Period When JDSS Was Not

Yet Licensed

Manela does not dispute that Stone was the person who

performed all contractor work on the project during the period

between March 15, 2015 (when Stone purported to assign the

Manela contract to JDSS) and June 22, 2015 (when the CSLB

reissued Stone’s license to JDSS). Whether Stone was doing so in

his personal capacity or as an agent of JDSS was the key subject

of disagreement in the proceedings below.

During this approximately three-month period,

Stone continued to send invoices to the Manelas as a sole

proprietorship, doing business as Stone Construction Company.

The first invoice reflected in the record from JDSS is dated

August 10, 2015 (i.e., after JDSS was licensed); all subsequent

invoices reflected in the record for work under the Manela

contract are from JDSS as well.

The record also contains an unsigned change order dated

during the three-month period when JDSS was not yet licensed.

This document, dated June 10, 2015, is on JDSS letterhead and

lists license number 425872 as the applicable contractor’s license

number. It provides that “[t]he contractor agrees to perform

and the owner agrees to pay for the following changes to this

contract,” then describes certain work and its pricing. There

are spaces on the form for both the “contractor” and “owner” to

sign and date under the word “approved,” but these spaces are

blank. (Capitalization omitted.) The document appears to bear

5

a “paid” stamp, which includes a text box that is likewise blank,

as well as a notation that the work was “invoiced on ynm-07.”

(Capitalization omitted.) The record does not indicate if or when

this work was performed and/or approved, or when the work

described in the change order was invoiced or paid for.

D. The Parties’ Dispute and Lawsuit

Throughout the course of the project, Manela requested

numerous change orders that expanded the scope of the project,

increased the cost, and delayed the estimated completion date,

although the extent to which they did so is a subject of debate

between the parties. In late 2018, the project still was not

completed, and the Manelas stopped paying JDSS’s invoices.

Manela filed this action against the Stone parties,3 whom the

complaint alleged were alter egos of each other, alleging they had

performed defective work and made material misrepresentations

in order to induce the Manelas to sign the Manela contract.

The Stone parties then jointly recorded a mechanic’s lien on

the Manela property for the amount of allegedly unpaid invoices

and filed a related action against the Manelas.4 Their verified

complaint included claims for breach of contract and foreclosure

on the mechanic’s lien. Paragraph 18 of the complaint

alleged that “[f]rom and after March 15, 2015, plaintiff JDSS

Construction Company, Inc., dba Stone Construction Company

continued work to provide the services required under the

3 Although the Manelas both signed the Manela contract,

Manela is the only plaintiff in the lead action against the Stone

parties, and Nomi Manela is not a party to either that action or

this appeal.

4 The two actions were assigned to the same trial judge.

6

contract.” (Capitalization omitted.) The assignment agreement

was attached as an exhibit to the verified complaint as well.

The Stone parties also filed a petition to compel arbitration

of Manela’s claims, pursuant to an arbitration clause in the

Manela contract.

E. Licensure Issue Raised in Manela’s Amended

Complaint and Motion to Remove Mechanic’s

Lien

Manela’s initial complaint did not include any allegations

about or causes of action based on lack of licensure. Based on

the Stone parties’ verified allegation in paragraph 18 of their

complaint, however, Manela amended his complaint to add

allegations that JDSS “and possibly Stone as well” had performed

work on the project without a contractor’s license, in violation of

section 7031. Section 7031, subdivision (a) prohibits, inter alia,

any “person engaged in the business or acting in the capacity

of a contractor” from “recover[ing] . . . compensation for the

performance of any act or contract where a license is required

by this chapter without alleging that they were a duly licensed

contractor at all times during the performance of that act or

contract.” Subdivision (b) of the section further provides

for disgorgement of compensation already paid under such

circumstances. (§ 7031, subd. (b) [“a person who utilizes the

services of an unlicensed contractor may bring an action . . .

to recover all compensation paid to the unlicensed contractor

for performance of any act or contract”].) Manela’s amended

complaint asserted new causes of action on this basis and sought,

in addition to damages based on Manela’s preexisting breach of

contract and negligence claims, return of all money the Manelas

7

had paid for work under the Manela contract, totaling over

$2 million.

Manela also filed a motion to remove the Stone parties’

jointly filed mechanic’s lien on several bases, including that the

lien was invalid under section 7031, subdivision (a), because

neither JDSS nor Stone was continuously licensed at all times

while performing work on the project.

F. The Parties’ Submissions Regarding the Motion

to Remove Mechanic’s Lien

The Stone parties opposed the motion to remove the

mechanic’s lien, claiming that there had been no gap in the

requisite licensure. Stone’s declaration submitted in support of

the Stone parties’ opposition contains several statements about

when Stone believed himself to be providing services as an agent

of JDSS. The declaration first provides that “[p]rior to June 22,

2015 [the date the license was transferred to JDSS], Stone

conducted his general contractor license business under the

dba Stone Construction Company.” Later, in paragraph 13, it

provides that “[f]rom and after February 11, 2015, all of Stone’s

general contracting business was conducted under the aegis of

JDSS.” (Italics added.) Finally, the declaration provides that

Manela “knew from and after the date of the [fifth] change order

dated June 10, 2015 that JDSS was providing all of the services

(labor and materials) under the contract” and that this was

“reflected on the change orders, the JDSS invoices, [and]

payments by [Manela] to JDSS.” (Capitalization omitted.)

In response, Manela argued that the assignment of the

construction contract prior to JDSS becoming licensed created

a gap in the requisite licensure even if Stone was always the

person performing the contracting services. Somewhat in tension

8

with this, however, in opposing the Stone parties’ concurrently

filed motion to compel arbitration, Manela also argued that

“Manela never consented to th[e] assignment, nor did he ratify

it.”5

The day before the hearing on the mechanic’s lien motion,

the Stone parties’ counsel filed an errata to the Stone declaration

previously filed in opposition to that motion. The errata

purported to alert the court to a “typographical error” and

omission—namely that the wrong date for when “all of Stone’s

general contracting business was conducted under the aegis of

JDSS” was inadvertently included in the Stone declaration. In

a supplemental declaration from Stone in support of the errata,

Stone explained that he had actually conducted business as JDSS

“ ‘[f]rom and after June 22, 2015,’ ” rather than from and after

February 11, 2015, as his earlier declaration had indicated.

G. Trial Court’s Decisions Regarding the

Mechanic’s Lien Motion and Related Motion

for Reconsideration

The court addressed Manela’s motion to remove the

mechanic’s lien and the Stone parties’ motion to compel

arbitration in the same tentative ruling, which the court

ultimately adopted in full. In that ruling, the trial court first

granted the arbitration motion. Manela had argued in opposition

to the motion that he could not be compelled to arbitrate with

JDSS because JDSS had not signed the arbitration agreement.

5 Likewise, in his opposition to the Stone parties’ petition

to compel arbitration, Manela argued he could not be compelled

to arbitrate his claims against JDSS because JDSS was not a

party to the home improvement contract.

9

The court rejected this argument based on the court’s conclusion

that the allegations in Manela’s complaint established “sufficient

identity of [the] parties between Stone . . . and JDSS” to enforce

the arbitration agreement against Manela.

In addressing the mechanic’s lien motion, the court

first rejected the Stone parties’ argument that the court lacked

jurisdiction to hear the motion because the matter was being

compelled to arbitration. The court emphasized that it had

limited jurisdiction to address the mechanic’s lien issue, and

would not be addressing the merits of the parties’ dispute.

The court granted the motion to remove the mechanic’s lien

on the basis that JDSS had performed work under the contract

without a license.6 The court explained that this conclusion

flowed solely from the assignment agreement; because “JDSS

assumed Stone’s rights and obligations under the [Manela]

[c]ontract” on March 15, 2015, “from March 15, 2015 to June 22,

2015, JDSS performed contractor services for which it was not

licensed.” The court further concluded that the assignment

distinguished the facts before it from a situation in which there

was a mere change in a contractor’s business form. (Cf. E. J.

Franks Construction, Inc. v. Sahota (2014) 226 Cal.App.4th 1123,

1129-1130 (Franks).)

The court declined to characterize anything in its order as

a finding of fact, emphasizing that it had “merely evaluat[ed] the

6The court did not find that Stone had performed under

the Manela contract without a license, nor did the ruling

otherwise address the argument made in Manela’s motion that

Stone had done so in violation of section 7031. Manela presented

two other bases on which he argued the court should remove the

mechanic’s lien, but the court rejected these.

10

probable validity of [d]efendants’ mechanic[’s] lien, not the merits

of this claim or claims that are compelled in arbitration.”7

The Stone parties filed an ex parte application and/or

motion seeking reconsideration of the trial court’s order removing

the mechanic’s lien, relief under Code of Civil Procedure

section 473, and/or leave to amend their complaint to correct

(primarily by deleting the complaint’s reference to the March 15,

2015 start date for when JDSS began providing services under

the contract). The Stone parties also requested an evidentiary

hearing on the issue of JDSS’s compliance with section 7031. In

connection with these requests, Stone filed another declaration,

in which he stated that the assignment “was not implemented

until such time as my contractor[’]s license number 425872 was

reissued on June 22, 2015 in the name of JDSS with myself

as the qualifying individual under the same license” and that

he “personally performed all contractor work on the Manela

parties[’] home improvement project from January 4, 2015 until

June 22, 2015.” (Capitalization omitted.)

At the ex parte hearing, the court explained that even

assuming the Stone parties’ most recent version of events were

true, “it wouldn’t . . . change[ ] my tentative [ruling] anyway . . .

because there’s no dispute there was a complete assignment in

March to that corporation [JDSS], which was not licensed.” The

7 We note, however, that Manela later filed a revised

statement of claims in the arbitration proceeding, relying in part

on the trial court’s order regarding the mechanic’s lien motion.

Among other things, Manela alleged that the trial court’s

“finding” on JDSS’s performance of services without a license

meant Manela may recoup the over $2 million in payments he

made to the Stone parties under the Manela contract.

11

court overruled Manela’s evidentiary objections to the most

recent Stone declaration, and noted—but did not make any

findings resolving—the conflicts between the various Stone

declarations.8

The court denied the Stone parties’ request for ex parte

relief, except for granting them leave to amend their complaint.

DISCUSSION

The Stone parties filed a petition for writ of mandate

in this court (case No. B302131) challenging the court’s order

removing the mechanic’s lien, as well as a notice of appeal (case

No. B302660) challenging both that order and the order denying

the Stone parties’ requested ex parte relief. This court initially

issued an order to show cause in the writ proceeding, then

discharged the order to show cause and informed the parties

that the writ petition would be considered with this appeal.

We conclude—and Manela does not contest—that the order

removing the mechanic’s lien is appealable. (See Howard S.

Wright Construction Co. v. Superior Court (2003) 106 Cal.App.4th

314, 318 [“the grant of a motion to remove a mechanic's lien is

essentially a judgment on the underlying foreclosure action that

no lien exists—a judgment that, upon recordation, removes the

lien from the public records . . . [a]nd . . . is a final, appealable

judgment for which writ relief would ordinarily be denied,”

8Specifically, the court commented, “The problem

I’m having is I have different declarations under penalty of

perjury. . . . Am I to basically accept one version and ignore the

other? Obviously if this was in trial, you would be able to—he

would be able to point out inconsistencies for the jury to decide

which is correct and which isn’t correct.”

12

fn. omitted].) We therefore consider the merits of the Stone

parties’ appeal from the order removing their mechanic’s lien.9

A motion to remove a mechanic’s lien should be granted

only when the lienholders (here, the Stone parties) fail to

make a threshold showing of the “probable validity of the lien.”

(Lambert v. Superior Court (1991) 228 Cal.App.3d 383, 387.)

Thus, by removing the mechanic’s lien in this case based on the

applicability of section 7031, the trial court concluded the Stone

parties had failed to show it was “probable” that section 7031

did not apply and/or did not require forfeiture of compensation

under the contract. On appeal, the Stone parties argue the

evidence does not support the court’s conclusion in this regard.

For reasons we discuss below, we agree.

A. Applicable Law Regarding Section 7031

Forfeiture

The Contractors State License Law (CSLL) (§ 7000 et seq.)

governs construction business in California in a manner intended

to “ ‘ ‘‘protect the public from incompetent or dishonest providers

of building and construction services. [Citation.]’’ [Citation.]’ ”

(Pacific Caisson & Shoring, Inc. v. Bernards Bros. Inc. (2011)

198 Cal.App.4th 681, 687.) The CSLL requires all contractors

“be licensed unless exempt.” (White v. Cridlebaugh (2009)

178 Cal.App.4th 506, 517.) Section 7031, subdivision (a) sets

forth the general rule that “no person engaged in the business

9Our disposition of the Stone parties’ appeal from this

order moots their appeal from the subsequent order seeking

reconsideration and related ex parte relief. It likewise moots

their writ petition (case No. B302131), which seeks relief also

sought in the appeal. We deny the writ petition on that basis

by separate order, concurrently filed with this opinion.

13

or acting in the capacity of a contractor, may bring or maintain

any action . . . for the collection of compensation for the

performance of any act or contract where a license is required

by this chapter without alleging that they were a duly licensed

contractor at all times during the performance of that act or

contract.” In M.W. Erectors, Inc. v. Niederhauser Ornamental

& Metal Works Co., Inc. (2005) 36 Cal.4th 412 (M.W. Erectors),

the California Supreme Court made clear the all-or-nothing

nature of section 7031’s forfeiture provisions, explaining that

a contractor “is ineligible to recover any compensation under

the terms of [section 7031], if, at any time during performance

of an agreement for contractor services, he or she was not duly

licensed.”10 (M.W. Erectors, supra, at p. 425, italics omitted;

id. at pp. 419 & 425−426.)

Importantly for purposes of this appeal, the time period

during which section 7031 requires a party to be licensed in order

to avoid forfeiture of compensation under a contract is not the

10 There is a singular, narrow “substantial compliance”

exception available under very specific circumstances set forth

in section 7031, subdivision (e). (§ 7031, subd. (e); see M.W.

Erectors, supra, 36 Cal.4th at pp. 418−419 & 433−434.) The

Stone parties do not argue that this exception applies. (See

§ 7031, subd. (e) [“the court may determine that there has been

substantial compliance with licensure requirements under this

section if it is shown at an evidentiary hearing that the person

who engaged in the business or acted in the capacity of a

contractor (1) had been duly licensed as a contractor in this

state prior to the performance of the act or contract, (2) acted

reasonably and in good faith to maintain proper licensure, and

(3) acted promptly and in good faith to remedy the failure to

comply with the licensure requirements upon learning of the

failure”].)

14

period during which the party is “engag[ed] in the business or

act[ing] in the capacity of a contractor,” but rather the period

when the contractor is performing under the contract.11 (See

M.W. Erectors, supra, 36 Cal.4th at p. 435, italics omitted;

ibid. [“the due licensure of which section 7031[, subdivision] (a)

speaks is due licensure while the contract itself is being

performed”].) For this reason, section 7031 does not require

forfeiture based on the contractor executing a construction

contract while unlicensed.12 (M.W. Erectors, supra, 36 Cal.4th

at pp. 435−437 & 440−441.) “[I]f fully licensed at all times

11 When no construction contract is in place, the time frame

during which section 7031 requires a party be licensed in order

to avoid forfeiture also is not determined by when the party is

engaged in the business or acting in the capacity of a contractor,

but rather by when the party is performing the acts for which the

CSLL requires a license and for which compensation is sought.

(See § 7031, subd. (a).)

12 Our Supreme Court more fully explains this point

as follows: “At the outset, we take note that allowing suit and

recovery under such circumstances [when the contractor is not

licensed at the time it executes the contract] violates no express

term of section 7031[, subdivision] (a). That statute prohibits a

contractor from suing ‘for the collection of compensation for the

performance of any act or contract where a license is required . . .

without alleging that he or she was a duly licensed contractor

at all times during the performance of that act or contract.’

[Citation.] The ‘act’ of executing an agreement is not one for

which a contractor seeks compensation; rather, he or she pursues

payment for carrying out the contract in a satisfactory manner.

[Citation.] Hence, we conclude, the due licensure of which

section 7031[, subdivision] (a) speaks is due licensure while

the contract itself is being performed.” (M.W. Erectors, supra,

36 Cal.4th at p. 435, italics omitted.)

15

during contractual performance, a contractor is not barred

from recovering compensation for the work solely because he

or she was unlicensed when the contract was executed.” (Id.

at p. 419, italics added & omitted.) M.W. Erectors explains

that this conclusion follows in part from the plain language of

section 7031, and in part from the CSLL more broadly treating

unlicensed acts “in the capacity of a contractor” differently than

unlicensed performance of a construction contract. (See M.W.

Erectors, supra, 36 Cal.4th at p. 437.) Namely, the CSLL

penalizes the broader general category of unlicensed acts in the

capacity of a contractor in section 7028, not section 7031, and

does so with civil and criminal penalties other than forfeiture.

(Id. at pp. 440−441; see § 7028, subd. (a) [it is a misdemeanor

“for a person to engage in the business of, or act in the capacity

of, a contractor within this state” without having a license].)

For the purposes of determining when a license is required

to avoid section 7031 forfeiture, “performance of . . . [the]

contract” refers to when the contractor is “carrying out” the

contract, and/or engaging in work for which the contractor will

seek compensation under the contract. (M.W. Erectors, supra,

36 Cal.4th at p. 435, italics omitted.) This does not mean that

the contractor is personally performing construction work.

Work by someone other than the contractor will often reflect a

contractor “carrying out” the contract and/or work for which the

contractor expects compensation under the contract, if the person

performing the work is doing so at the request of or otherwise

on behalf of the contractor. (See Judicial Council of California v.

Jacobs Facilities, Inc. (2015) 239 Cal.App.4th 882, 897 (Jacobs

Facilities) [contractor performed under contract when, as

contemplated by the contract, the contractor “deliver[ed] services”

16

performed by others and accepted compensation for them]; WSS

Industrial Construction, Inc. v. Great West Contractors, Inc.

(2008) 162 Cal.App.4th 581, 591−594 [subcontractor doing work

under a construction contract at contractor’s request while the

contractor was unlicensed triggered section 7031 forfeiture of

contractor’s compensation under the contract].)

The Stone parties primarily rely on Franks, supra,

226 Cal.App.4th 1123, a decision that draws heavily on the

reasoning of M.W. Erectors and is factually similar to the instant

appeal. In Franks, an individual contractor entered into a home

construction contract with the defendant homeowners. During

performance of the contract, he incorporated the plaintiff

corporation, of which he was the sole shareholder. The

contractor’s license that had been issued initially to him in

his personal capacity was reissued to his corporation, at which

point the corporation took over work under the contract. (Id. at

p. 1126.) The defendants argued that, because the corporation

had not been licensed at all times during the performance of

the contract, the plaintiff corporation had violated section 7031

and could not collect payment for any work under the contract.

(Franks, supra, p. 1126.) The Court of Appeal disagreed, holding

that these facts “involve[d] a licensed contractor and a change

in business entity status. Proper licensure was in place at all

times” (id. at p. 1129), in that a licensed individual was the

contractor on the project until he stopped doing business as a

sole proprietorship, incorporated his business, and transferred

his license to the resulting new corporate entity, at which point

that licensed corporate entity began acting as the contractor

on the project. (See id. at pp. 1129−1130.) Absent a gap in

the contractor’s licensure during contractual performance,

17

“section 7031 [did] not apply.” (Franks, supra, at p. 1128.)

Franks distinguished cases requiring section 7031 forfeiture as

“involv[ing] a period wherein the contractor was unlicensed or

where a license previously issued lapsed during the construction

project.” (Franks, supra, p. 1129.)

With this precedent regarding section 7031 in mind, we

turn to the Stone parties’ argument that the trial court erred in

its reliance on section 7031 to remove the mechanic’s lien in this

case.

B. Section 7031 Does Not Apply

The Stone parties argue that the evidence does not support

the trial court’s conclusion that they failed to show section 7031

probably does not require forfeiture. Specifically, the Stone

parties argue neither the assignment agreement, nor the record

as a whole, provides substantial evidence that JDSS performed

under the contract before it was licensed.

Although we ordinarily review evidentiary challenges

for substantial evidence, that standard “ ‘is typically implicated

when a defendant contends that the plaintiff succeeded at

trial in spite of insufficient evidence.’ ” (Sonic Manufacturing

Technologies, Inc. v. AAE Systems, Inc. (2011) 196 Cal.App.4th

456, 465; In re I.W. (2009) 180 Cal.App.4th 1517, 1528,

disapproved of on other grounds by Conservatorship of O.B.

(2020) 9 Cal.5th 989.) “ ‘In the case where the trier of fact has

expressly or implicitly concluded that the party with the burden

of proof did not carry the burden’ ”—here, the court’s implicit

finding that Stone parties failed to prove the probable validity of

the lien—and that party appeals, “ ‘the question for a reviewing

court becomes whether the evidence compels a finding in favor

of the appellant as a matter of law.’ ” (Dreyer’s Grand Ice Cream,

18

Inc. v. County of Kern (2013) 218 Cal.App.4th 828, 838.) We thus

consider whether the evidence compels the conclusion that JDSS

did not perform under the contract while unlicensed.

The parties identify the following evidence in this regard:

the assignment agreement; the June 10, 2015 change order; and

the conflicting statements by Stone regarding his work under the

Manela contract. We address each in turn below.

1. The assignment agreement

The trial court viewed the assignment agreement as

conclusive evidence that JDSS began performing under the

contract as of March 15, 2015 (the effective date listed in the

assignment). The Stone parties argue the assignment agreement

cannot serve as such evidence. We agree.

Under the assignment agreement, Stone assigned his

rights and purported to delegate the performance of his duties

under the Manela contract to JDSS, and JDSS accepted the

assignment of rights and assumed Stone’s duties. (See p. 4, fn. 2,

ante.) A third party’s agreement to assume a contractor’s duties

under a construction contract without a license is akin to the

execution of a construction contract without a license, something

the California Supreme Court has explained does not trigger

section 7031 forfeiture. (M.W. Erectors, supra, 36 Cal.4th at

pp. 419, 435−437 & 440−441.) Such an assumption is neither

an act for which the assignee may seek compensation under the

contract, nor an act that can be fairly characterized as “carrying

out the contract.” (Id. at p. 435, italics omitted.) It thus cannot

constitute “ ‘performance of that . . . contract.’ ” (Ibid., italics

omitted.) Moreover, as in the case of unlicensed contractual

execution discussed in M.W. Erectors, “[n]o compelling reason

exists to conclude that the public protective purposes of the CSLL

19

can only be served by deeming [a construction contract assigned

before the assignee is licensed] illegal, void, and unenforceable

on that basis alone.” (Id. at p. 441, italics added.)

Thus, for the purposes of applying section 7031, the

assignment agreement cannot establish that JDSS began

performing under the contract before it was licensed.

2. The June 10, 2015 change order

Manela argues that the June 10, 2015 change order on

JDSS letterhead reflects JDSS performing under the contract

as of that date. But the change order describes work to be

performed in the future; it does not indicate whether or when

the work was performed. Thus, a reasonable trier of fact could

not infer from this document that any work had been performed

at the request of or on behalf of JDSS before June 22, 2015.

Nor does JDSS’s mere issuance of a change order meet

the definition of performance of the contract set forth in

M.W. Erectors, because it is neither an act “for which [JDSS]

seeks compensation” nor an act “carrying out the contract.”

(M.W. Erectors, supra, 36 Cal.4th at p. 435, italics omitted.)

Rather, the Manela contract provides that work may be added

to the contract’s scope through a written change order signed

by both parties, meaning that executing a change order is an

act amending the original contract and, like entering into the

contract, does not constitute performance thereunder. Although

issuing a change order is certainly an “ ‘act[ ] in the capacity of

a contractor’ ” (id. at p. 437), M.W. Erectors distinguishes such

acts from the narrower category of performance under a specific

contract, and makes clear that the former does not trigger

20

section 7031 forfeiture.13 (See M.W. Erectors, supra, at

pp. 435-437 & 440−441.)

3. Stone’s statements regarding his work

under the Manela contract

Manela does not contend, and the record contains no

evidence, that any person other than Stone or subcontractors

hired by him performed any work under the Manela contract

before June 22, 2015. The Stone parties’ verified complaint

and Stone’s multiple declarations conflict regarding whether,

before that date, Stone performed that work and/or engaged

others to perform that work in his personal capacity or on behalf

of JDSS. Regardless, however, of what Stone declared or wrote in

his complaint, and notwithstanding the assignment agreement,

Stone remained personally liable for his promised performance

under the Manela contract in the absence of the Manelas’ consent

to the purported delegation. (See Civ. Code, § 1457; Jacobs

Facilities, supra, 239 Cal.App.4th at pp. 901−902 [“[w]ithout

the consent of the obligee, the delegation of a duty by an obligor

under a contract does not extinguish the obligor’s duty”]; see

also Wiseman v. Sklar (1930) 104 Cal.App. 369, 374-375 [“ ‘[t]he

obligations of an assignor of a contract continue to rest upon

him’ ” “irrespective of the legality or lack of legality of the

assignment, [the assignor] [is] at all times responsible to [the

13 To the extent Jacobs Facilities stands for the proposition

that a contractor executing contractual amendments or invoices

under a construction contract necessarily constitutes the

performance of that contract for the purposes of section 7031

(see, e.g., Jacobs, supra, 239 Cal.App.4th at pp. 897 & 905), we

view it as inconsistent with M.W. Erectors, and decline to follow

it.

21

other parties] under the contract”].) Yet, Manela does not

contend that the Manelas consented to the delegation before

June 22, 2015, nor does the record contain evidence supporting

any such approval.

The assignment agreement purports to assign Stone’s

rights and delegate his obligations under the Manela contract

to JDSS, effective March 15, 2015. Generally speaking, “[t]he

statutes in this state clearly manifest a policy in favor of the

free transferability of all types of property, including rights

under contracts” (Farmland Irrigation Co. v. Dopplmaier (1957)

48 Cal.2d 208, 222), but contractual “duties imposed upon one

party may be of such a personal nature that their performance

by someone else would in effect deprive the other party of that

for which he bargained. The duties in such a situation cannot

be delegated.” (Ibid.; see Superbrace, Inc. v. Tidwell (2004)

124 Cal.App.4th 388, 402 (Superbrace) [same].) For example,

duties “are not delegable in either of the following situations:

(1) where in the nature or circumstances of the case, the skill,

credit or other personal quality of the party was a distinctive

characteristic of the thing stipulated for, namely, the personal

nature of the contract itself, or (2) the personal quality of the

party was a material inducement to the other party entering

into the contract.” (Edgar Rice Burroughs, Inc. v. Commodore

Productions & Artists, Inc. (1959) 167 Cal.App.2d 463, 469.)

Here, the contractor services Stone agreed to provide to the

Manelas in the Manela contract are personal services to be

rendered by Stone. According to the allegations in Manela’s

complaint (which Manela reiterated in his brief to this court),

“Manela felt comfortable enough to agree to the terms and

execute a fixed price construction contract with Stone” and

22

“agreed to hire Stone notwithstanding Stone’s substantially

higher bid [for the project] because Stone represented that he

was the most qualified general contractor to handle the project,

he would provide the highest quality of service and oversight of

the project, [and] he would complete the project pursuant to a

clear, fixed price construction contract” within a certain amount

of time. Thus, that Stone would be the contractor on the project

was a “material inducement to the [Manelas] entering into

the contract.” (See id. at p. 469.) Under such circumstances,

one’s obligation to perform personal services under a contract

cannot be transferred “ ‘without the consent of the person entitled

to such performance.’ ” (Superbrace, supra, 124 Cal.App.4th at

p. 404.)

Manela does not argue that he consented to the assignment

agreement before June 22, 2015,14 nor does the record contain

any evidence that this occurred. The June 10, 2015 change order

on JDSS letterhead does not reflect the Manelas’ acquiescence

to JDSS stepping in for Stone before June 22, 2015, as it is not

signed as approved by either of the Manelas, nor does it indicate

if or when the Manelas paid for such proposed work15 or when

14 To the contrary, in his motion to remove the mechanic’s

lien, Manela claimed he “did not consent to any assignment

of the [Manela] contract from Stone to JDSS” at any point, a

claim he then reiterated in his reply supporting the motion.

(Capitalization omitted.)

15The document appears to bear a “paid” stamp with an

empty box below it. (Capitalization omitted.) Even if this stamp

is understood as indicating payment despite the lack of any

signature, initials, or date in that box, it still does not indicate

when such payment occurred. To the contrary, other notations on

23

the work was done. Rather, the earliest evidence in the record

that might constitute the Manelas’ acquiescence or consent to

the assignment agreement was their payment of JDSS invoices

for work performed under the Manela contract beginning in

August 2015. Absent any evidence of the Manelas’ consent to the

assignment agreement before June 22, 2015, Stone’s obligations

under the Manela contract still existed before June 22, 2015,

notwithstanding that the assignment agreement professes to be

effective as of March 15, 2015.16 As a result, regardless of how

Stone characterizes the work he performed before June 22, 2015,

he could not have been performing that work at the instruction

of or on behalf of JDSS, because he was already contractually

obligated to perform it in his personal capacity during that time

period. Put differently, until the Manelas consented to the

assignment agreement, “[t]he corporation [JDSS] was not the

contracting party,” and thus “did not act ‘as a contractor without

a license.’ ” (Franks, supra, 226 Cal.App.4th at p. 1130.)

The record thus compels the conclusion that Stone was not

performing under the contract on behalf of JDSS prior to JDSS

becoming duly licensed, that JDSS therefore was not performing

the document indicate the order was “invoiced” on an unspecified

date.

16 We need not and do not reach any conclusions as to if

or when the Manelas consented to the assignment, except to

note that there is no evidence in the record from which a

reasonable trier of fact could conclude that they consented to

it before June 22, 2015.

24

under the contract before it was licensed, and that section 7031

therefore does not apply.17

4. Franks

Our conclusion in this regard is consistent with the policy

rationale set forth in Franks, which we find persuasive. Here,

as in Franks, the same contractor’s license was in place at all

times during the performance of the contract, held at first by an

individual, then by that individual’s corporation. (See Franks,

supra, 226 Cal.App.4th at pp. 1128−1129; see also Jacobs

Facilities, supra, 239 Cal.App.4th at p. 899 [distinguishing

Franks because “[t]he continuity of license and business entity

that was central to the rationale of Franks was not present”].)

Franks concluded that, under these circumstances, allowing a

17 Manela does not argue that, if we conclude the trial court

erred in determining JDSS performed under the Manela contract

without a license, we should remand for the trial court to make

factual findings regarding whether Stone (as opposed to JDSS)

performed under the contract after his license was reissued to

JDSS on June 22, 2015, and whether the lien (held by both Stone

and JDSS) should be removed on this alternative basis. By

failing to raise this argument on appeal, Manela has forfeited it,

and we need not address it further. (See Tiernan v. Trustees of

Cal. State University & Colleges (1982) 33 Cal.3d 211, 216, fn. 4

[argument not raised on appeal is forfeited]; Boucher v. Alliance

Title Co., Inc. (2005) 127 Cal.App.4th 262, 267 [same].)

Similarly, we need not address arguments the trial

court rejected below as bases for removing the mechanic’s lien

(timeliness and a lien held by multiple parties), because Manela

does not argue on appeal that the court erred in rejecting these

arguments or that they provide alternative bases for affirming

the court’s order.

25

change in business form to create a gap in licensing “would lead

to absurd results” and would “effectively preclude licensed sole

proprietor contractors from lawfully incorporating and obtaining

a reissue of a general contracting license to the new business

entity at any time during the construction period.” (Franks,

supra, at p. 1129.)

Manela argues the trial court correctly concluded that the

instant case is distinguishable from Franks because it involves

the additional element of an assignment, rather than just

a change in business entity. But given that the assignment

agreement here could not unilaterally relieve Stone of his duties

to Manela under the original agreement (absent consent by

the Manelas), this is a distinction without a difference. Nor does

the additional element of the assignment agreement render any

less applicable Franks’ conclusion that forfeiture under such

circumstances would not serve “[t]he purpose of section 7031[,]

[which] is to deter unlicensed contractors from recovering

compensation for their work.” (Franks, supra, 226 Cal.App.4th at

p. 1129, italics omitted.) Just as the law “is not intended to deter

licensed contractors from changing a business entity’s status, and

obtaining a reissuance of the license to the new entity[,] during

a contract period” (ibid.), it is not intended to deter delegation

of contractual obligations based on such a “change in business

entity status” and concomitant reissuance of a license to that

new entity. (Ibid.)

Importantly, Franks did not treat the individual and the

corporation as interchangeable for the purposes of section 7031.

To the contrary, it recognized, as it must, that “a distinction

between a corporation and an individual [is] significant for

purposes of the CSLL” (Franks, supra, 226 Cal.App.4th at

26

pp. 1129−1130), a concept that played a prominent role in

Opp v. St. Paul Fire & Marine Ins. Co. (2007) 154 Cal.App.4th

71, 72–73 (Opp). The Court of Appeal in Opp required a

corporation to forfeit all payment for work under a construction

contract the corporation had signed because the corporation was

unlicensed during the performance of the contract, even though

the corporation’s president had a license during that time. (Id.

at pp. 74−76.) In executing the contract, the corporation had

represented that it held the license actually held by its president.

(Id. at pp. 72−73.) The Court of Appeal in Franks distinguished

Opp in part by noting that “[u]nlike Opp, Franks did not

misrepresent his contractor’s license by claiming it belonged to a

corporate entity. In fact, the corporate entity did not exist when

the contract . . . was executed.” (Franks, supra, at p. 1130.)

Opp is distinguishable from this case on this same basis. Franks

further distinguished Opp by noting that “recogniz[ing] the

individual as a contracting party in th[e] circumstances [present

in Opp] would, among other things, encourage fraud through

the misuse of another person’s contractor’s license and allow an

individual to enjoy the benefits of incorporation while avoiding

the burdens by effectively repudiating the existence of the

corporation when it was convenient to do so.” (Id. at p. 1130.)

This was not the case in Franks, nor is it the case here.

27

DISPOSITION

The order of the trial court removing the mechanic’s lien

is reversed. Upon remand, the trial court is instructed to enter

a new order confirming the validity of the mechanic’s lien

notwithstanding Manela’s motion to remove it.

The Stone parties are awarded their costs on appeal.

CERTIFIED FOR PUBLICATION.

ROTHSCHILD, P. J.

We concur:

CHANEY, J.

BENDIX, J.

28