Opinion

Stop Syar Expansion v. County of Napa

Court
California Court of Appeal
Filed
Apr 23, 2021
Status
Published
Cited by
0 cases
Authority
More cited than 15.4%

The opinion

Filed 3/25/21; modified and certified for partial publication 4/23/21 (order attached)

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION ONE

STOP SYAR EXPANSION,

Petitioner and Appellant, A158723

v.

(Napa County Super.

COUNTY OF NAPA, Ct. No. 16CV001070)

Defendant and Respondent;

SYAR INDUSTRIES, INC.,

Real Party in Interest and

Respondent.

INTRODUCTION

Stop Syar Expansion (SSE) has long opposed the expansion of Syar

Industries, Inc.’s (Syar) aggregate operation. Syar filed an application for

expansion in May 2008. After more than seven years of environmental

review and numerous hearings, the County Planning Commission, in October

2015, certified the final Environmental Impact Report (EIR) and approved a

modified project and a permit for an expansion half the size originally sought

and subject to more than 100 pages of conditions and mitigation measures.

SSE appealed both the EIR certification and the project and permit approvals

1

to the County Board of Supervisions, asserting in the respective appeals that

the EIR and the project and permit approvals were deficient in a multitude of

respects. After nearly a year of additional environmental review and

hearings, the Board, in a 109-page decision, rejected SSE’s appeals, certified

the EIR, and approved a further modified project and permit.

SSE filed the instant writ proceeding pursuant to Public Resources

Code, section 21168,1 challenging the certification of the EIR. It ultimately

winnowed down its claims with respect to the EIR to 16 asserted deficiencies.

After briefing by the parties and a hearing, the trial court, in a 42-page

ruling, denied the writ petition on a variety of grounds, reaching the merits

as to some issues and concluding SSE failed to exhaust administrative

remedies as to others.

SSE appeals and, at this juncture, contends the EIR is deficient in five

respects. We affirm.

DISCUSSION2

Basic CEQA Principles and Standard of Review

In South of Market Community Action Network v. City and County of

San Francisco (2019) 33 Cal.App.5th 321, 329–330 (South of Market), we

summarized the relevant CEQA principles and standard of review in a case

like this one, where the petitioner’s appeal “primarily challenges the content

and analysis of the EIR.” (Id. at p. 329.)

As we explained, the “ ‘basic purpose of an EIR is to “provide public

agencies and the public in general with detailed information about the effect

1 All further statutory references are to the Public Resources Code

unless otherwise indicated.

2 We discuss the pertinent facts and any relevant procedural history in

connection with our discussion of the issues raised on appeal.

2

[that] a proposed project is likely to have on the environment; to list ways in

which the significant effects of such a project might be minimized; and to

indicate alternatives to such a project.” ’ (Sierra Club v. County of Fresno

(2018) 6 Cal.5th 502, 511 . . . (Sierra Club).) ‘ “ ‘The EIR is the heart of CEQA’

and the integrity of the process is dependent on the adequacy of the EIR.” ’

(Rialto Citizens for Responsible Growth v. City of Rialto (2012)

208 Cal.App.4th 899, 924. . . .)” (South of Market, supra, 33 Cal.App.5th at

p. 329.)

“ ‘ “ ‘ “[A]n EIR is presumed adequate (Pub. Resources Code, § 21167.3),

and the plaintiff in a CEQA action has the burden of proving otherwise.” ’ ” ’

(Preserve Wild Santee v. City of Santee (2012) 210 Cal.App.4th 260, 275. . . .)”

(South of Market, supra, 33 Cal.App.5th at p. 329.)

“As our Supreme Court recently explained in Sierra Club: ‘The

standard of review in a CEQA case, as provided in sections 21168.5 and

21005, is abuse of discretion. Section 21168.5 states in part: “In any action

or proceeding . . . to attack, review, set aside, void or annul a determination,

finding, or decision of a public agency on the grounds of noncompliance with

this division, the inquiry shall extend only to whether there was a prejudicial

abuse of discretion.” [Citation.] Our decisions have thus articulated a

procedural issues/factual issues dichotomy. “[A]n agency may abuse its

discretion under CEQA either by failing to proceed in the manner CEQA

provides or by reaching factual conclusions unsupported by substantial

evidence. (§ 21168.5.) Judicial review of these two types of error differs

significantly: While we determine de novo whether the agency has employed

the correct procedures, ‘scrupulously enforc[ing] all legislatively mandated

CEQA requirements’ [citation], we accord greater deference to the agency’s

substantive factual conclusions. In reviewing for substantial evidence, the

3

reviewing court ‘may not set aside an agency’s approval of an EIR on the

ground that an opposite conclusion would have been equally or more

reasonable,’ for, on factual questions, our task ‘is not to weigh conflicting

evidence and determine who has the better argument.’ ” ’ (Sierra Club,

supra, 6 Cal.5th at p. 512.)” (South of Market, supra, 33 Cal.App.5th at

pp. 329–330.)

“The court explained that this ‘procedural issues/factual issues

dichotomy’ has worked well for courts reviewing agency determinations.

(Sierra Club, supra, 6 Cal.5th at p. 512.) Some procedural questions, such as

whether the agency has provided sufficient notice and opportunity to

comment on a [draft EIR], or whether it has entirely omitted a required

discussion, have clear answers. ‘But the question whether an agency has

followed proper procedures is not always so clear. This is especially so when

the issue is whether an EIR’s discussion of environmental impacts is

adequate, that is, whether the discussion sufficiently performs the function of

facilitating “informed agency decisionmaking and informed public

participation.” ’ (Id. at pp. 512–513.)” (South of Market, supra,

33 Cal.App.5th at p. 330.)

“After reviewing several of its own decisions and those of the Court of

Appeal, the court summarized three ‘basic principles’ regarding the standard

of review for adequacy of an EIR: ‘(1) An agency has considerable discretion

to decide the manner of the discussion of potentially significant effects in an

EIR. (2) However, a reviewing court must determine whether the discussion

of a potentially significant effect is sufficient or insufficient, i.e., whether the

EIR comports with its intended function of including “ ‘ “detail sufficient to

enable those who did not participate in its preparation to understand and to

consider meaningfully the issues raised by the proposed project.” ’ ”

4

[Citation.] (3) The determination whether a discussion is sufficient is not

solely a matter of discerning whether there is substantial evidence to support

the agency’s factual conclusions.’ (Sierra Club, supra, 6 Cal.5th at pp. 515–

516.)” (South of Market, supra, 33 Cal.App.5th at p. 330.)

“ ‘The ultimate inquiry, as case law and the CEQA guidelines make

clear, is whether the EIR includes enough detail “to enable those who did not

participate in its preparation to understand and to consider meaningfully the

issues raised by the proposed project.” ’ (Sierra Club, supra, 6 Cal.5th at

p. 516.) Generally, that inquiry is a mixed question of law and fact subject to

de novo review, but to the extent factual questions (such as the agency’s

decision which methodologies to employ for analyzing an environmental

effect) predominate, a substantial evidence standard of review will apply.

(Ibid.)” (South of Market, supra, 33 Cal.App.5th at pp. 330–331, fn. omitted.)

“Further, ‘ “[i]n determining the adequacy of an EIR, the CEQA

Guidelines look to whether the report provides decision makers with

sufficient analysis to intelligently consider the environmental consequences

of a project. ([Guidelines,] § 15151.) The CEQA Guidelines further provide

that ‘the sufficiency of an EIR is to be reviewed in the light of what is

reasonably feasible. . . . The courts have [therefore] looked not for perfection

but for adequacy, completeness, and a good faith effort at full disclosure.’

([Guidelines,] § 15151.)” [Citation.] The overriding issue on review is thus

“whether the [lead agency] reasonably and in good faith discussed [a project]

in detail sufficient [to enable] the public [to] discern from the [EIR] the

‘analytic route the . . . agency traveled from evidence to action.’ ” ’ (California

Oak Foundation v. Regents of University of California (2010) 188 Cal.App.4th

227, 262 . . . (California Oak Foundation); see Sierra Club, supra, 6 Cal.5th

at p. 515 [‘We also affirm that in reviewing an EIR’s discussion, we do not

5

require technical perfection or scientific certainty. . . .’].)” (South of Market,

supra, 33 Cal.App.5th at p. 331.)

“ ‘Although an agency’s failure to disclose information called for by

CEQA may be prejudicial “regardless of whether a different outcome would

have resulted if the public agency had complied” with the law (§ 21005, subd.

(a)), under CEQA, “there is no presumption that error is prejudicial” (§ 21005,

subd. (b)). Insubstantial or merely technical omissions are not grounds for

relief. [Citation.] “A prejudicial abuse of discretion occurs if the failure to

include relevant information precludes informed decisionmaking and

informed public participation, thereby thwarting the statutory goals of the

EIR process.” ’ (Neighbors for Smart Rail v. Exposition Metro Line

Construction Authority (2013) 57 Cal.4th 439, 463 . . .; see id. at pp. 464–465

[failure to comply with CEQA’s informational mandate ‘did not deprive

agency decision makers or the public of substantial information relevant to

approving the project, and is therefore not a ground for setting that decision

aside’].)” (South of Market, supra, 33 Cal.App.5th at p. 331.)

General CEQA Exhaustion Principles

The requirement that administrative remedies be exhausted “is

founded on the theory that the administrative tribunal is created by law to

adjudicate the issue sought to be presented to the court, and the issue is

within its special jurisdiction. If a court allows a suit to go forward prior to a

final administrative determination, it will be interfering with the subject

matter of another tribunal.” (Tahoe Vista Concerned Citizens v. County of

Placer (2000) 81 Cal.App.4th 577, 589 (Tahoe Vista).)

In the context of CEQA, specifically, “ ‘ “The essence of the exhaustion

doctrine is the public agency’s opportunity to receive and respond to

articulated factual issues and legal theories before its actions are subjected to

6

judicial review.” ’ [Citations.] Comments must express concerns so the lead

agency has ‘ “ ‘ “its opportunity to act and to render litigation

unnecessary.” ’ ” ’ [Citation.].” (North Coast Rivers Alliance v. Marin

Municipal Water Dist. Bd. of Directors (2013) 216 Cal.App.4th 614, 623

(North Coast Rivers).)

Thus, “the requirement of exhaustion is a jurisdictional prerequisite,

and not a matter of judicial discretion.” (Tahoe Vista, supra, 81 Cal.App.4th

at p. 589; accord, Clews Land & Livestock, LLC v. City of San Diego (2017)

19 Cal.App.5th 161, 184 (Clews Land); North Coast Rivers, supra,

216 Cal.App.4th at p. 624.)

“Inasmuch as the issue of exhaustion is a question of law, ‘[a]n

appellate court employs a de novo standard of review when determining

whether the exhaustion of administrative remedies doctrine applies.’ ” (North

Coast Rivers, supra, 216 Cal.App.4th at p. 624; accord, Clews Land, supra,

19 Cal.App.5th at p. 185.)

“ ‘The purposes of the doctrine are not satisfied if the objections are not

sufficiently specific so as to allow the Agency the opportunity to evaluate and

respond to them.’ [Citation.] ‘ “ ‘[Thus,] [r]elatively . . . bland and general

references to environmental matters’ . . . , or ‘isolated and unelaborated

comment[s]’ ” ’ do not satisfy the exhaustion requirement. [Citation.] Rather,

‘ “[t]he ‘exact issue’ must have been presented to the administrative

agency. . . .” ’ [Citation.] Requiring anything less ‘would enable litigants to

narrow, obscure, or even omit their arguments before the final administrative

authority because they could possibly obtain a more favorable decision from a

trial court.’ [Citation.].”3 (North Coast, supra, 216 Cal.App.4th at p. 623;

3This does not mean an objector must be as specific as an attorney

making an objection in a lawsuit. (California Native Plant Society v. City of

Rancho Cordova (2009) 172 Cal.App.4th 603, 629 [“To satisfy the exhaustion

7

accord, South of Market, supra, 33 Cal.App.5th at p. 347; Sierra Club v. City

of Orange (2008) 163 Cal.App.4th 523, 535 [“To advance the exhaustion

doctrine’s purpose ‘[t]he “exact issue” must have been presented to the

administrative agency. . . .’ ”].)

In the instant case, because the County, by ordinance (Napa County

Code, ch. 288), provides for an appeal of actions by the Planning Commission

to the County Board of Supervisors, the exhaustion analysis entails a dual

inquiry.

Tahoe Vista guides this analysis, as the court therein addressed what

was then an issue of first impression—“whether a party who raises an issue

in the first hearing provided on a project but fails to raise that same issue in

an administrative appeal remains free to raise that issue in a subsequent

court challenge under section 21177.”4 (Tahoe Vista, supra, 81 Cal.App.4th at

p. 589.) Following an extensive discussion of both section 21177 and the

exhaustion doctrine, the court concluded “section 21177 and the exhaustion

requirement, objections a party seeks to raise in a CEQA action must have

been made ‘known in some fashion, however unsophisticated[, in the

administrative proceeding].’ ”].) Nonetheless, the objection must fairly

apprise the agency of the substance of the objection so that it has an

opportunity to evaluate and respond to it. (Planning & Conservation League

v. Castaic Lake Water Agency (2009) 180 Cal.App.4th 210, 251 [“To satisfy the

exhaustion doctrine, the objections must ‘fairly apprise[]’ the agency of the

purported defect in the EIR.”].)

4 Section 21177 provides in pertinent part: “(a) An action or proceeding

shall not be brought . . . unless the alleged grounds for noncompliance with

this division were presented to the public agency orally or in writing by any

person during the public comment period provided by this division or before

the close of the public hearing on the project before the issuance of the notice

of determination. (b) A person shall not maintain an action or proceeding

unless that person objected to the approval of the project orally or in writing

during the public comment period . . . or before the close of the public hearing

on the project. . . .” (§ 21177, subds. (a)-(b).)

8

doctrine prevent such an issue from being raised in a court action.”5 (Tahoe

Vista, at pp. 589–592.)

In Tahoe Vista, it was undisputed that the “plaintiffs raised their

objection to the negative declaration ‘during the public comment period’ or

‘prior to the close of the [Planning Commission’s] public hearing on the

project before the issuance of the notice of determination.’ (§ 21177,

subd. (a).)” (Tahoe Vista, supra, 81 Cal.App.4th at p. 591.) “Plaintiffs thus

had standing to file their petition in the trial court and to prosecute their

claim under CEQA provided they otherwise exhausted all administrative

remedies available to them once the Planning Commission committed what

plaintiffs believed was a wrongful act.”6 (Tahoe Vista, at p. 591.)

5 The court pointed out, “[s]ection 14.5 of chapter 1514 of the Statutes

of 1984, the measure by which section 21177 was enacted, ‘states that the

“intent of the Legislature in adding Section 21177 . . . [is] to codify the

exhaustion of administrative remedies doctrine.” (Stats.1984, ch. 1514,

§ 14.5, p. 5345; italics added.) It further provides that “it is not the intent [of

the legislation] to limit or modify any exception to the doctrine of

administrative remedies contained in case law.” (Ibid., italics added.) “We

are thus directed to read [section 21177] with reference to a specific common

law rule.” (Cantor v. Anderson (1981) 126 Cal.App.3d 124, 129 . . . , citations

omitted.) That rule has to do with the law of administrative remedies as it

preceded the enactment of section 21177.’ (California Aviation Council [v.

County of Amador (1988)] 200 Cal.App.3d [337, 346] (conc. opn. of Blease,

J.).)” (Tahoe Vista, supra, 81 Cal.App.4th at pp. 589–590.)

6 The court also explained why the dual requirements of section

21177—that (a) the plaintiff have participated in the administrative

proceedings prior to the issuance of a notice of determination and (b) the

specific issue the plaintiff later raises in a court challenge was raised by

someone during those proceedings—are more accurately characterized as

establishing “standing” to sue, rather than requiring exhaustion of

administrative remedies. (Tahoe Vista, supra, 81 Cal.App.4th at pp. 589–

590; see Clews Land, supra, 19 Cal.App.5th at p. 184, fn. 3 [also stating dual

requirements of § 21177 are “separate from” the operation of the exhaustion

doctrine where there are “available administrative procedures to challenge”

9

The appellate court then turned to the principal issue—whether the

plaintiffs had exhausted their administrative remedies with respect to the

issues they sought to raise in their court action. The court explained that

“ ‘[c]onsideration of whether such exhaustion has occurred in a given case will

depend upon the procedures applicable to the public agency in question.’

(City of Sacramento v. State Water Resources Control Bd. (1992)

2 Cal.App.4th 960, 969 . . . ; see also Park Area Neighbors v. Town of Fairfax

(1994) 29 Cal.App.4th 1442, 1450 . . . [failure to appeal planning

commission’s actions ‘in the manner prescribed by the town code’ constituted

failure to exhaust administrative remedies]; Browning–Ferris Industries v.

City Council (1986) 181 Cal.App.3d 852, 860. . . .)” (Tahoe Vista, supra,

81 Cal.App.4th at pp. 591–592.)

In Tahoe Vista, those procedures were provided by section 25.140 of the

Placer County Code, which “allows persons who appear at a Planning

Commission hearing to appeal the Planning Commission’s decision to the

Board of Supervisors. The County Code describes the scope of the appeal

hearing as follows: ‘At the hearing (a hearing conducted “over again”), the

appellate body shall initiate a discussion limited to only those issues that are

the specific subject of the appeal, and, in addition, the specific grounds for the

appeal. [For example, if the permit for a project approval or denial has been

appealed, the entire project will be the subject of the appeal hearing;

however, if a condition of approval has been appealed, then only the condition

and issues directly related to the subject of that condition will be allowed as

part of the discussion by the appellate body.]’ (Placer County Code, § 25.140,

the public agency’s decision concerning an EIR; the “exhaustion doctrine is

separate from, and in addition to, the [statutory] requirements under

CEQA”].)

10

subd. D.4.a., italics in original.)” (Tahoe Vista, supra, 81 Cal.App.4th at

p. 592, first italics added.)

“These procedures thus provided plaintiffs with an appeal from the

Planning Commission’s decision, but required plaintiffs to specify the

particular subject or grounds of the appeal. Although the Board of

Supervisors would consider the matter ‘over again,’ or in legal parlance, de

novo, its review was limited solely to those issues the plaintiffs placed before

it.” (Tahoe Vista, supra, 81 Cal.App.4th at p. 592.) The plaintiffs’ appeal,

however, had placed “only the conditional use permit before the Board of

Supervisors and only with regard to parking.” (Ibid.) The court pointed out

the appeal form had “provided a specific notation by which [the] plaintiffs

could have appealed the Planning Commission’s approval of the negative

declaration,” but they “did not specify they were appealing the Planning

Commission’s decision on that point.” (Ibid.) Such failure “to raise an issue

in an administrative appeal after raising the issue in the first public or

administrative hearing,” said the court, constituted “a failure to exhaust

administrative remedies and prevent[ed] the issue from being raised in a

subsequent judicial action.” (Ibid.; see Clews Land, supra, 19 Cal.App.5th at

pp. 185–187 [where municipal code provided a bifurcated appeals procedure,

one applicable to environmental determinations and the other to other kinds

of land use decisions, and petitioner did not comply with the former, it “did

not exhaust its administrative remedies regarding the [mitigated negative

declaration], and it may not now bring a judicial action challenging it”].)

Thus, as Tahoe Vista and other cases explain, SSE must first

demonstrate that it meets the requirements of section 21177—that is, that it

participated in the Planning Commission hearings “ ‘before the issuance of

the notice of determination’ ” and that either it, or another objector appearing

11

during those proceedings, raised the issues SSE has raised in this court

action. (Tahoe Vista, supra, 81 Cal.App.4th at p. 591; Clews Land, supra,

19 Cal.App.5th at p. 184, fn. 3.)

Because the County provides for an appeal of actions by the Planning

Commission to the Board of Supervisors, SSE must secondly demonstrate

that it exhausted this administrative remedy. (Clews Land, supra,

19 Cal.App.5th at pp. 184–187; Tahoe Vista, supra, 81 Cal.App.4th at

pp. 591–592.) And to determine whether SSE did so, we must look to the

County’s appeal procedures. (Clews Land, at p. 185; Tahoe Vista, at pp. 591–

592.)

These procedures are set forth in chapter 2.88 of the Napa County Code

of Ordinances. An appeal is commenced by filing a “notice of intent to

appeal” and paying the required fees “within ten working days of the decision

of the approving authority.” (Napa County Code. § 2.88.040, subd. (A).)

Within “ten working days following the submittal of a notice of intent to

appeal,” the appellant must submit an “appeal packet.” (Id., § 2.88.050, subd.

(A).) This packet must, among other things, include “[i]dentification of the

specific factual or legal determination of the approving authority which is

being appealed, and the basis for such appeal.” (Id., § 2.88.050, subd. (A)(4).)

“Any issue not raised by the appellant in the appeal packet shall be deemed

waived.” (Ibid.) “If the basis of the appeal is, in whole or in part, an

allegation of prejudicial abuse of discretion on the part of the approving

authority, that there was a lack of a fair and impartial hearing, or that there

were no facts presented to the approving authority to support the decision,

such grounds of appeal and the factual or legal basis for such grounds must

be expressly stated or the board shall deem such bases and grounds for

appeal waived by the appellant.” (Id., § 2.88.050, subd. (A)(5).)

12

In accordance with these provisions, the Board of Supervisor’s 109-page

decision separately identified and addressed each “ground” SSE listed in its

“Grounds of Appeal” set forth in its appeals packets; indeed, in many

instances the Board extensively quoted from SSE’s stated grounds to set forth

the ground raised, which the Board then addressed. In fact, the Board’s

decision separately identified and addressed the grounds SSE raised in its

first appeal from the Planning Commission’s certification of the EIR, and

those it raised in its second appeal from the Commission’s approval of the

project and permit. The Board addressed no other grounds.

Thus, like the appeal process at issue in Tahoe Vista, the County’s

procedures provided SSE “with an appeal from the Planning Commission’s

decision, but required [that SSE] to specify the particular subject or grounds

of the appeal.” (Tahoe Vista, supra, 81 Cal.App.4th at p. 592.) And while the

Board of Supervisors will “exercise its independent judgment in determining

whether the decision appealed was correct” (Napa County Code, § 2.88.090,

subd. (A)), an appeal is bounded by the grounds of appeal set forth in the

appeal packet (id., § 2.88.050(A)(4), (5)). (See Tahoe Vista, supra,

81 Cal.App.4th at pp. 592–593.)

Accordingly, to demonstrate that it exhausted its administrative

remedies, SSE must show that it timely filed a notice of intent to appeal and

timely submitted an appeal packet which specifically identified the grounds it

raises in this court action.

Citing to Citizens for Open Government v. City of Lodi (2006)

144 Cal.App.4th 865 (Citizens), SSE maintains Tahoe Vista is not controlling

and it was not required to exhaust the administrative remedy set forth in the

County’s appeal ordinance. Citizens was decided by the same court that

13

decided Tahoe Vista. The court did not repudiate its prior decision, but

rather, distinguished it.

In Citizens, the city issued a notice of preparation of a draft EIR and

the objecting group appeared at the planning commission meeting and

asserted the draft was deficient in a number of respects. (Citizens, supra,

144 Cal.App.4th at p. 869.) A second objecting group raised similar, but not

identical issues. (Ibid.) The commission subsequently certified the EIR and

approved a permit and tentative map. (Id. at p. 870.) The city code provided

for an appeal to the city council, which had to be filed within five days of the

commission’s decision. (Ibid.) There was no requirement that issues be

specified; rather, the city gave notice that any person could appear and “

‘present their views and comments’ ” on the development project. (Id. at

p. 871.) The city further advised that any challenge in court, might be “

‘limited to raising only those issues you or someone else raised’ ” at the city

council hearing or in correspondence delivered to the city clerk before the

council meeting. (Ibid.) Only the second objecting group filed an appeal from

the commission to the city council. But both groups appeared at the city

council meeting, and the first objecting group raised the mitigation issue it

subsequently raised in its writ proceeding. (Id. at pp. 870–871.) The trial

court dismissed the writ petition for failure to exhaust administrative

remedies on the ground the first objecting group had not filed its own appeal

to the city council. The Court of Appeal reversed. (Id. at p. 872.)

Observing that the only issue before it was whether the first objecting

group had exhausted its administrative remedies, the appellate court, as it

had in Tahoe Vista, examined “the procedures applicable to the public agency

in question.” (Citizens, supra, 144 Cal.App.4th at p. 876.) The court pointed

out the city’s appeal procedure differed from that at issue in Tahoe Vista in

14

several significant respects. The city did not require a specification of issues,

nor did it require each objector to file its own appeal. On the contrary, the

city council treated the second objectors’ appeal as opening the entire

environmental review process to anyone who wanted to voice any concern.

(Id. at p. 877.) Indeed, the city essentially advised “that any person

participating in the [council] hearing could subsequently challenge the

matter in court limited only by the issues raised at the hearing.” (Ibid.)

Thus, rather than being a true “ ‘appeal,’ ” the city’s procedures “in reality”

simply “transfer[red] . . . the final decision-making authority from the

planning commission to the city council.”7 (Ibid.)

7 SSE points out the Citizens court first “note[s]” that if a nonelected

body certifies an EIR, the public entity must, pursuant to section 21151,

provide for an appeal to the elected decision making body, and under CEQA

Guidelines, a final EIR must reflect the “ ‘lead agency’s [i.e., the final decision

making body’s] independent judgment and analysis.’ ” (Citizens, supra,

144 Cal.App.5th at p. 876, italics omitted.) In Citizens then, the city council

was the “ ‘final decision-making body’ ” that exercised the “ ‘lead agency’s

independent judgment and analysis.’ ” (Italics omitted.) Thus, the city

council was not acting in a “traditional” appellate sense. (Ibid.) The court

did not suggest, however, as SSE implies, that this was determinative of

exhaustion. On the contrary, it was against this statutory backdrop, that the

court went on to discuss the city’s appeal procedures and to conclude they

were, in significant respects, unlike those in Tahoe Vista. (Id. at pp. 876–

877.) Indeed, in Tahoe Vista, the court had pointed out that while the board

of supervisors heard issues on appeal de novo and was also required to adopt

all findings necessary to implement approval of the project, including re-

adopting a negative declaration, this did not mean the challengers did not

have to follow the county’s appellate procedures. (Tahoe Vista, supra,

81 Cal.App.4th at p. 593; see Clews Land, supra, 19 Cal.App.5th at pp. 187–

188 [where environmental decision is delegated to nonelected body, which

CEQA allows, agency must provide appeal process and challenger must

comply with that process to pursue judicial challenge].)

15

Nor does California Clean Energy Committee v. City of San Jose (2013)

220 Cal.App.4th 1325 (Clean Energy), assist SSE. In that case, the court

concluded the city had improperly divided CEQA duties between the

planning commission and the city council and, thus, the purported

“delegation” to the commission was invalid. The action by the city council as

the final decision maker, however, was valid. (Id. at pp. 1338, 1342.) As a

consequence, there was no valid appeal to be taken from the decision by the

commission under the municipal code “appeal” provisions. (Id. at pp. 1345–

1346.) Nor did the code provide for any appeal from the city council’s action.

(Id. at p. 1346.) Moreover, in that venue, the objector had preserved issues

for judicial challenge by submitting comment letters before the city council

acted. (Id. at pp. 1346–1348.) The Clean Energy court not only did not take

issue with Tahoe Vista, but it reaffirmed the exhaustion principles

established by that case (Clean Energy, at pp. 1342–1344), concluding only

that the circumstances in the case before it differed and the objectors

complied with the dual requirements of section 21177 in the one forum that

had validly acted, namely the city council. (Clean Energy, at p. 1348; ibid.

[“The situation presented to us is dissimilar to the situation addressed in

Tahoe Vista, where the ultimate decisionmaking authority’s review was

specifically confined to issues raised in the administrative process.”])

Here, the County’s appeal procedure is akin to that in Tahoe Vista.

(See Clews Land, supra, 19 Cal.App.5th at pp. 185–187.) Accordingly, SSE

was required to comply with that procedure.

We close with one final point as to exhaustion—that the petitioner

challenging a CEQA determination “has the burden of proof to show

exhaustion occurred.” (North Coast, supra, 216 Cal.App.4th at p. 624; accord,

Sierra Club, supra, 163 Cal.App.4th at p. 536.) And in this regard, a list of

16

string-cites to the administrative record without explanation as to “how each

citation supports the assertion [the public agency] was ‘fairly appri[s]ed’ ” of

the asserted noncompliance with CEQA, is not sufficient. (See Sierra Club,

at p. 536.)

With this overview of CEQA principles and the exhaustion requirement

in mind, we turn to the five issues SSE raises on appeal.

Daily Particulate Emissions

SSE maintains the EIR’s emissions analysis is deficient because it

assesses impacts on only an annualized basis and does not also include an

assessment on a daily basis. SSE relies on comments by its expert, who

opined the County’s methodology of “[d]ividing the annual emissions across

365 days improperly dilutes the daily emissions because the Quarry only

operates 250 days per year.” 8

The quarry is under the regulatory jurisdiction of the Bay Area Air

Quality Management District (District), which is “a regional agency

authorized to adopt and enforce regulations governing air pollutants from

stationary sources such as factories, refineries, power plants, and gas stations

in the San Francisco Bay Area. . . . (Health & Saf. Code, §§ 39002, 40000,

40001, subd. (a), 40200.) . . . [T]he District monitors air quality, issues

permits to certain emitters of air pollution, and promulgates rules to control

8 There is no exhaustion issue as to this issue. In what it identified as

SSE’s “Eighteenth Ground for Appeal” from the certification of the EIR , the

Board of Supervisors addressed a claim that “annualized emissions were not

properly analyzed” and, specifically, that it was not proper to determine “the

total quantity of annual emissions” by “divid[ing] by 365 days/year to

determine the average daily quantity of emissions released by the Quarry”

because (a) the operational season was only 250 days and (b) “[d]aily

emissions must be associated with daily production to arrive at an actual

daily emissions exposure.”

17

emissions. (Id., §§ 40001, 42300, 42301.5, 42315.)” (California Building

Industry Assn. v. Bay Area Air Quality Management Dist. (2015) 62 Cal.4th

369, 378, fn. omitted (California Building).)

To implement its charge, the District develops “ ‘thresholds of

significance’ for determining ‘the significance of environmental effects.’ ”

(California Building, supra, 62 Cal.4th at p. 378.) These thresholds set levels

at which toxic air contaminants and certain types of particulate matter,

including PM2.5—particulate matter with a diameter of 2.5 microns or less—

would be deemed environmentally significant. (Id. at p. 379.) The District’s

CEQA guidelines are “advisory” and provide methodologies “for analyzing air

quality impacts based on evidence and technical studies supporting” the

guidelines.

The Air Quality and Health Impact Risk Assessment (AQ Assessment)

prepared by County consultants serves as the “evidentiary and analytical

basis of the air quality sections of the EIR.”9

The AQ Assessment explains that the air quality analysis utilizes “the

impact assessment methodologies presented in the [District’s] CEQA Air

Quality Guidelines (BAAQMD 2010) and the [District’s] Revised Draft

Options and Justification Report CEQA Thresholds of Significance

(BAAQMD 2009).” The AQ Assessment further explains “[o]perational

emissions are evaluated using only the maximum annual thresholds because

the average daily thresholds are equivalent (i.e. 10 tons divided by 365 days

per year=54.8 lb/day which BAAQMD rounded down to 54 lb/day threshold).”

The EIR thus concludes that, “after mitigations,” there is “less than

significant” impact from PM 2.5 emissions based on use of a 365-day average

annual threshold for that pollutant.

9 The AQ Assessment is attached to the draft EIR as Appendix I.

18

Agencies have “substantial discretion in determining the appropriate

threshold of significance to evaluate the severity of a particular impact.”

(Mission Bay Alliance v. Office of Community Investment & Infrastructure

(2016) 6 Cal.App.5th 160, 192.) “Similarly, our Supreme Court stated: ‘A

lead agency enjoys substantial discretion in its choice of methodology’ for

evaluation of the significance of an impact. (Center for Biological Diversity [v.

Department of Fish & Wildlife (2015)] 62 Cal.4th [204,] 228 [(Center for

Biological Diversity)].)” (King & Gardiner Farms, LLC v. County of Kern

(2020) 45 Cal.App.5th 814, 884 (King & Gardiner).)

However, “when the agency chooses to rely completely on a single

quantitative method to justify a no-significance finding, CEQA demands the

agency research and document the quantitative parameters essential to that

method. Otherwise, decision makers and the public are left with only an

unsubstantiated assertion that the impacts . . . will not be significant. (See

Guidelines, § 15064, subd. (f)(5) [substantial evidence to support a finding on

significance includes ‘facts, reasonable assumptions predicated upon facts,

and expert opinion supported by facts,’ but not ‘[a]rgument, speculation, [or]

unsubstantiated opinion’].)” (Center for Biological Diversity, supra,

62 Cal.4th at p. 228.)

With respect to SSE’s assertion that the District’s guidelines mandate

an analysis of both annual and daily emissions, we first observe the District’s

guidelines are not legally binding directives to a lead agency conducting an

environmental review under CEQA. (See Bay Area Air Quality Management

District CEQA Guidelines, May 2011, p. 1-1 [“The purpose of the [District] . .

. Guidelines is to assist lead agencies in evaluating air quality impacts of

projects and plans proposed in the San Francisco Bay Area Basin. . . . The

Guidelines provides [District]-recommended procedures for evaluating

19

potential air quality impacts during the environmental review process

consistent with CEQA requirements.”]; id. at p. 2-5 [“A lead agency should

rely on substantial evidence most appropriate for the project being studied.”];

id. at pp. C-20-C-21 [“This is an advisory document that provides the lead

agency, consultants, and project applicants with uniform procedure for

addressing air quality in environmental documents.”]; see also Robie et al.,

Cal. Civil Practice: Environmental Litigation (2020) § 8.4 [“The Guidelines

set forth indications or outlines to be followed, allowing for flexibility in the

action and conduct of governmental agencies. . . . The Guidelines are subject

to a construction of reasonableness and courts will not seek to impose

unreasonable extremes or inject themselves within an agency’s area of

discretion as to the choice of action to be taken.”].)10

As pertinent here, the District’s guidelines set forth a multi-step

procedure for making a “[s]ignificance [d]etermination.” Step 2 of this

procedure involves “Comparison of Unmitigated Emissions with Thresholds

of Significance,” and is explained as follows: “Sum the estimated emissions

10

In its appellant’s closing brief, SSE asserts the County “adopted” the

District’s guidelines as evidenced by “the EIR’s explicit language that it

‘utilize[d] the impact assessment methodologies’ presented in the [District]

Guidelines [citation] and the fact that Appendix G of the CEQA Guidelines

states that a proposed project would have a significant impact if it violates an

air quality standard.” However, being guided by a District guideline is not

tantamount to “adopting” the guideline as its own mandatory regulatory law.

The draft EIR expressly states the District’s guidelines are advisory.

Moreover, the District’s guidelines, themselves, contemplate adjustments as

a particular situation warrants. (See District Guidelines, at p. 1-3 [“The

recommendations in the CEQA Guidelines should be viewed as minimum

considerations for analyzing air quality impacts. Lead agencies are

encouraged to tailor the air quality impact analysis to meet the needs of the

local community and may conduct refined analysis that utilize more

sophisticated models, more precise input data, innovate mitigation measures,

and/or other features.”])

20

for area, mobile, and stationary sources (if any) for each pollutant as

explained above and compare the total average daily and annual emissions of

each criteria pollutant and their precursors with the thresholds of

significance determined by the lead agency. If daily average or annual

emissions of operational-related criteria air pollutants or precursors do not

exceed the thresholds, the project would result in a less than significant

impact to air quality. . . .”

SSE raised the annual/daily issue before the Planning Commission in

comments on the draft EIR, and the issue was addressed in the response to

comments attached to the final EIR.11

The response points out that “at the time that the [AQ Assessment]

was prepared it was standard practice to use 365 days to determine the

average daily emissions,” and the AQ Assessment “used the CalEEMod model

[California Emissions Estimator Model12] methods in place at the time.”

Therefore, the AQ Assessment was “prepared in a manner consistent with

the default method for analyzing development project air quality impacts.”

11 The final EIR includes the draft EIR, comments and

recommendations received on the draft; a list of persons, organizations and

agencies commenting on the draft EIR, responses of the lead agency to

significant environmental points, and any other information added by the

agency. (Cal. Code Regs., tit. 14, § 15132; 14 Cal. Legal Forms: Transaction

Guide (2020) § 30.B.210 Flowchart Describing Environmental Impact

Evaluation Process.)

12 The California Emissions Estimator Model “is a statewide land use

emissions computer model designed to provide a uniform platform for

government agencies, land use planners, and environmental professionals to

quantify potential criteria pollutant and greenhouse gas . . . emissions

associated with both construction and operations from a variety of land use

projects.” (CalEEMod, California Emissions Estimator Model®,

<http://www.caleemod.com/> [as of March 25, 2021].)

21

The response additionally points out that the District was served with

the Notice of Preparation of the draft EIR and a copy thereof, including all

related technical studies—which discussed “how the Project emissions were

evaluated in relation to their CEQA thresholds of significance.” Had the

District had concerns about the emissions analysis, it could have submitted

comments on the draft. It did not, and thus “did not take issue” with the

County’s methodology.13

The response to comments further explains, “the [2009] baseline

annual production level . . . and corresponding baseline emissions levels

reported in the DEIR are the average over five years [2004-2008]. The

Project daily average emissions, as calculated using annual emissions in the

DEIR, would not be reflective of the daily average in the maximum year

which would be the proper comparison to make. Thus, comparing the

average day in the baseline period, the maximum calendar year production

was 17% higher than the average production over the five years. If daily or

monthly production data were available to calculate annual production on a

rolling basis, then a greater annual production could be substantiated.

Nevertheless, this increase in the baseline average day would decrease the

Project average day by a corresponding amount.” Accordingly, the response

13 SSE’s assertion in its appellant’s closing brief that its “expert raised

the omission of daily emissions analysis to the BAAQMD CEQA division

planning manager, who expressed concern with the County’s interpretation of

the BAAQMD thresholds,” thus, goes nowhere. Even assuming its expert

told the Planning Commission prior to its certification of the EIR that in

June 2015 he had called the District and his conversation “elicited concerns”

by the planning manager, this assertion is hopelessly vague. Moreover, it

does not detract from the fact the District was thereafter served with a copy

of the draft EIR and technical attachments and voiced no criticism of the

County’s methodology as fully developed and set forth in the draft EIR and

supporting attachments.

22

concluded, “using [an] annual emissions significance determination . . . as a

surrogate for the average daily emissions significance determination is

appropriate and reflective of the potential Project air quality impacts.”

At the hearing before the Board of Supervisors, the County’s consulting

expert further discussed air quality particulates as follows: “The comment

[critical of the particulate analysis] was, ‘Well, on average, they are only

going to work 350 [sic] days a year.’ And so, obviously, if you divide it by 250

instead of 365, you get a higher number of pounds per day because there’s

fewer days in which to produce the ten tons. So the facility can operate 24/7,

365, but normal operation, like I said, is planned for 250 days per year. [¶]

Using 365 days is appropriate, and here’s why: The baseline annual

production is averaged over five years and doesn’t reflect the daily average.

It reflects a multiple-year annual average, in fact. And so if we were to look

at a daily average of what’s actually daily going on, you would find that you

had some very busy days, and you would find that you had less busy days.”

So, “from my perspective, we did include the daily threshold because it’s the

same as the annual threshold when you look at it the way we looked at it.”

Following the close of the hearing, the Board of Supervisors found that,

“As modeled for the [AQ Assessment] and described in the EIR, criteria air

pollutant emissions (i.e., ROG, NOx, and exhaust PM10 and PM2.5) were

average[d] over the year (i.e. 365 days), however, because the facility

typically operates approximately 250 days/year which is the normal operating

schedule (Draft EIR page 3-14), dividing by fewer operational days would

increase the daily average emissions by 46% (i.e., 365 ÷ 250=1.46) resulting

in emissions of approximately 80 lb/day. The baseline annual production

level (i.e. 810,363 tons/year) and baseline emissions levels identified in the

Draft EIR are averaged over a five year period, therefore, comparing the

23

average day in the five year period with a 365 day maximum per year is a

reasonable approach. (See response to comment in Final EIR, Appendix C,

Air Quality and Greenhouse Gas Emissions for a full discussion on this

issue.) [¶] When the [AQ Assessment] was prepared it was standard practice

to use 365 days to determine the average daily emissions. The project [AQ

Assessment] used the CalEEMod model methods in place at the time (i.e.,

Version 1.x). Furthermore[,] the average annual daily trips . . . used in

CalEEMod are by definition the annual trips divided by 365. Thus, the air

quality impact analysis was prepared in a manner consistent with the default

method for analyzing project air quality impacts. [¶] The [District] provided

comments on the [notice of preparation] in a letter dated July 30, 2009 and

received the Draft EIR in 2013 including the related technical studies. [The

District] did not identify any issues of project emissions evaluation in relation

to CEQA thresholds of significance. [¶] Therefore, using annual emissions

significance determination in the Draft EIR as a surrogate for the average

daily emissions significance determination is appropriate and reflective of the

potential project air quality impacts.”

Thus, at bottom, SSE’s issue as to the truck emissions analysis is that

it is tied to the County’s use of a five-year average annualized approach,

rather than a one-year 250-day approach. This is a disagreement among

experts, which is not a sufficient basis to conclude an EIR is inadequate.

(Town of Atherton v. California High-Speed Rail Authority (2014)

228 Cal.App.4th 314, 349 (Atherton) [“ ‘Disagreement among experts does not

make an EIR inadequate. . . .’ ”].) “ ‘Although others might well assess the

significance of [a] risk . . . differently, it [is] error for the court to substitute

its judgment for that of the Agency.’ ” (North Coast, supra, 216 Cal.App.4th

at p. 640.) “The issue is not whether other methods might have been used,

24

but whether the agency relied on evidence that a ‘ “reasonable mind might

accept as sufficient to support the conclusion reached” ’ in the EIR.” (Id. at

p. 642.) We cannot say that the five-year average annualized approach the

County chose to use was bereft of explanation or not one a reasonable mind

could accept.14

Baseline for Truck Traffic Emissions

SSE also contends the EIR improperly assesses truck emission impacts

by using a baseline production number based on a five-year average (2004-

2008) annual production figure, rather than on 2009 production levels.

Specifically, SSE asserts (1) the “EIR does not make the required showing

that 2009 production levels would be misleading”; (2) the EIR does not

address why use of a five-year average production figure was “required to

provide the most accurate picture practically possible of [the] Project

impacts”; and (3) does not address “why 2009 production levels were not

included” in the five-year average production figure.

Exhaustion

The trial court ruled SSE failed to exhaust its administrative remedies

with respect to these claims.

SSE claims it did exhaust its administrative remedies, pointing to the

following language (which we have italicized) in its Grounds of Appeal in its

appeal packet supporting its appeal of the certification of the EIR (we have

quoted the entirety of the passages from which SSE has selectively quoted):

“A. Ad hoc changes to the EIR document have created a lot of

confusion among staff, commissioners and the public regarding

foundational elements of the Project including:

[¶] . . . [¶]

14Given our conclusion in this regard we need not, and do not, reach

the County’s and Syar’s alternative arguments in defense of the truck

emission analysis.

25

“6. Interchangeable use of ‘total production’ and ‘annual permitted

saleable quantity’ throughout by County staff, consultants and staff

obfuscate actual production for which EIR is performed. [¶] The terms

‘total production’ and ‘annual permitted saleable quantity’ are used

interchangeably throughout the EIR and the EIR process even though

these terms describe different production totals. As a result, the EIR

underestimates the environmental impacts by approximately 50%

because the amount of production required to produce annual

permitted saleable quantities exceeds that amount by approximately

50%. Environmental impacts, including but not limited to air quality,

hydrology and water quality, noise and vibration and greenhouse gases,

determined by the amount of actual production is affected by this

obfuscation such that those environmental impacts are as yet

unknown.” (Underscoring omitted, italics added.)

“C. Baseline conditions are not adequately described.

“The EIR fails to describe baseline conditions with reference to actually

existing physical conditions. Instead, the EIR relies on models

conducted at other sites to analyze the baseline air quality impacts. It

used the standard trip from the County’s traffic model to analyze

baseline traffic conditions. It fails to disclose existing water usage,

relying instead on data for water usage and groundwater levels to be

collected after the expansion is approved. Air quality studies in the

EIR are based on mining industry sponsored tests and models

conducted at other sites and are calculated with controlled conditions

not representative of the Project’s actual conditions. The EIR provides

no basis for relying on modeled conditions instead of measuring the

actually existing physical conditions.” (Italics added.)

“V. DEIR. Misrepresentation of Annual Product Sales.

“1. Throughout the Syar EIR and Lead Agency documents, annual

quarry production is confused with annual quarry sales that in turn

misleads and confused governmental decision makers and the public.

[¶] 2. For instance, in the draft EIR Vol. 1, August 2013, Table 3-3, pg.

3-13, Product Sales (tons) are equated to existing total annual Quarry

production. In the footnotes it is stated: 1 810,364 Tons/Year Sold

(total of Haul Trips and Rail Trips.) This is the total processed not the

total sold. This misleads governmental decision makers and the public.

Also, any permitting, production, or planning decisions are made using

26

this false basis will be also be inaccurate and false. [¶] 3. Another

example: Draft EIR Vol. II, August 2013, 3.1.1, pg. 11: ‘Between 2004

(period of record) the Quarry’s annual average sales was approximately

810,000 tons, or 81 percent of the current permitted maximum.’ ”

(Original italics omitted, italics added.)

SSE also points to the following language (which we again have

italicized) in its Grounds of Appeal in its second appeals packet in support of

its appeal of the project and permit approvals (and we have again quoted the

entirety of the passages from which SSE has selectively quoted):

“XI. The Findings for Approval of Surface Mining Permit fail to comply

with the requirements of Napa county Code chapter 16.12 for issuance

of surface mining permit, are in error, inadequate and incomplete.

“A. Plans and reports submitted with the application do not adequately

describe the proposed operation. Inadequate and shifting description of

project and its environmental impacts. Baseline production, reserves,

greenhouse gas emissions, truck trips, groundwater usage are

inaccurately and incompletely described. For example, the map

attached as Exhibit 4 depicts an off-site groundwater well to which

Syar has access but was never disclosed or analyzed. Nor does the

permit resolution require any monitoring or other condition related to

this off-site well. Exhibit 5, a page from the 1973 EIR conducted for the

original permit shows groundwater at that time far exceeding that

estimated today—1120.14 acre feet per year historically vs 140.6 acre

feet per year. There is no accurate estimate of groundwater use either

in the EIR or in the permit approval such that the project’s

groundwater use may imperil surrounding properties’ dependence on

groundwater.” (Italics added.)

None of these grounds of appeal comes close to apprising the Board of

Supervisors of the five-year average/2009 actual production issue SSE has

raised in this court action.15 Accordingly, as the trial court concluded, SSE

15 SSE also points to pages in the record wherein its members or other

persons sought information about and made comments pertaining to the

“lack of support for the baseline production level.” None of this, however,

27

failed to exhaust its administrative remedies as to this issue and is barred

from raising it in this court action.

Merits

Even if SSE had exhausted its administrative remedies, its complaint

about the production baseline used to assess truck emissions lacks merit.

“CEQA requires an EIR to ‘focus on impacts to existing environment,

not hypothetical situations.’ [Citation.] ‘[T]he impacts of a proposed project

are ordinarily to be compared to the actual environmental conditions existing

at the time of CEQA analysis. . . .’ [Citation.] [¶] To accomplish this, CEQA

directs an EIR to include what is called an environmental baseline, a

description of the project site’s physical and environmental conditions at the

time the EIR is prepared. ‘An EIR must include a description of the physical

environmental conditions in the vicinity of the project, as they exist at the

time the preparation is published . . . from both a local and regional

perspective. This environmental setting will normally constitute the baseline

physical conditions by which a lead agency determines whether an impact is

significant.’ (CEQA Guidelines, § 15125, subd. (a).) [¶] ‘An inappropriate

baseline may skew the environmental analysis flowing from it, resulting in

establishes that SSE exhausted its administrative remedies pursuant to the

County appeals ordinance. As the ordinance specifies, and the Board of

Supervisors’ decision reflects, the only grounds considered and addressed on

appeal by the Board are those identified in an appeal packet, and in neither

of SSE’s appeal packets did it identify as a ground for appeal the issue it has

raised in this court action. Nor did the Board, in turn, address such ground

in its decisions rejecting SSE’s appeals. While SSE claims it did not have

sufficient information to raise as a ground for appeal the five-year

average/2009 actual production issue it is now pursuing, that is not so. It

was clear the County was utilizing a five-year average methodology to assess

impacts, and the legal challenge SSE is now making could have been

advanced before the Board.

28

an EIR that fails to comply with CEQA.’ [Citations.] The ‘normal[]’ rule is

that the baseline must reflect the ‘physical conditions existing at the time

[the] environmental analysis’ begins. [Citation.] [¶] However, ‘ “the date for

establishing [the] baseline cannot be a rigid one. Environmental conditions

may vary from year to year and in some cases it is necessary to consider

conditions over a range of time periods.” [Citation.]’ (Communities, supra,

48 Cal.4th at pp. 327-328; see also San Francisco Baykeeper, Inc. v. State

Lands Com. (2015) 242 Cal.App.4th 202, 218-219 . . . [(Baykeeper)] [five-year

average of mining volumes was appropriate baseline].) Thus, ‘despite the

CEQA Guidelines’ reference to ‘. . . the time environmental analysis is

commenced’ [citation], ‘[n]either CEQA nor the CEQA Guidelines mandates a

uniform, inflexible rule for determination of the existing conditions baseline.

Rather, an agency enjoys the discretion to decide, in the first instance,

exactly how the existing physical conditions without the project can most

realistically be measured, subject to review, as with all CEQA factual

determinations, for support by substantial evidence.” [Citation.]’ (Neighbors

for Smart Rail v. Exposition Metro Line Construction Authority[, supra,]

57 Cal.4th 439, 449 . . . (Neighbors for Smart Rail).)” (San Franciscans for

Livable Neighborhoods v. City and County of San Francisco (2018)

26 Cal.App.5th 596, 614-615.)

Here, recognizing that “levels of operations vary . . . seasonally and

with economic conditions,” the County chose to use the “recent 5-year average

annual rate” of production (2004 to 2008) instead of using only 2009

production data to calculate the production baseline. In short, in its AQ

Assessment, the County both explained the methodology by which it

established the production baseline, and provided a reasonable explanation

for that choice. That SSE and its expert would use a different methodology is

29

not a basis for finding the EIR inadequate. (See Atherton, supra, 228

Cal.App.4th at p. 349; North Coast, supra, 216 Cal.App.4th at pp. 640, 642.)

Citing Neighbors for Smart Rail, supra, 57 Cal.4th 439, SSE asserts

the County relied on a hypothetical and unsupported baseline without

showing an existing conditions analysis would be misleading. SSE’s reliance

on Neighbors is misplaced. There, the lead agency used an exclusively

“future conditions baseline for assessment of the project impacts on traffic

and air quality.” (Id. at p. 446.) “[W]hile an agency preparing an EIR does

have discretion to omit an analysis of the project’s significant impacts on

existing environmental conditions and substitute a baseline consisting of

environmental conditions projected to exist in the future,” said the court, the

agency also “must justify its decision by showing an existing conditions

analysis would be misleading or without environmental value.” (Id. at p. 457,

italics added.)

Here, as we have discussed, the County did not use a future projected

baseline analysis, rather it based the production baseline on production

during the immediately preceding five years in order to account for variations

in production caused by multiple factors.

What SSE is actually arguing is that any deviation “from CEQA’s

normal baseline”—i.e., existing conditions at the time of the notice of

preparation is published—“must be supported by a demonstration in the EIR

that analyzing project impacts under the normal baseline would be

‘misleading or without informational value’ ” (Association of Irritated

Residents v. Kern County Bd. Of Supervisors (2017) 17 Cal.App.5th 708, 730

(Kern County)) and that a reasoned explanation of how and why the agency

has used historic data to determine the baseline is insufficient.

30

However, cases have rejected the assertion that the standard for a

future conditions based baseline established in Neighbors for Smart Rail

applies to every situation where a lead agency determines it is more

reasonable to determine the baseline by considering data from a time period

other than the date of publication of the notice of preparation. (See Kern

County, supra, 17 Cal.App.5th at pp. 730-731 [determining test for future

conditions baselines applies only “to baselines that use hypothetical future

conditions” and not to “an agency’s decision about how to measure existing

conditions when the activity creating those conditions has fluctuated,” italics

omitted]; see also, e.g., Baykeeper, supra, 242 Cal.App.4th at pp. 218-219

[lead agency did not abuse its discretion in determining baseline for

measuring project impacts by using a five-year average of annual mining

volumes was a better indicator of existing conditions; the agency’s

determination was supported by “meaningful analysis”].)

Baykeeper is closely analogous to the case at hand. In that case, the

Lands Commission granted real parties a 10-year extension of a 10-year

mineral extraction lease authorizing them to continue dredging sand from

certain lands. (Baykeeper, supra, 242 Cal.App.4th at pp. 210-211.) The

Commission published the notice of preparation of the EIR in 2007. In the

EIR, the lead agency explained that rather than using 2007 data to fix

baseline conditions, it determined “a five-year average of annual mining

volumes was a better indicator of existing mining conditions.” (Id. at p. 216.)

The EIR explained that “the volume of sand mined from the leased areas

during 2007 was not an accurate reflection of existing baseline conditions

because (1) limiting the baseline to any single calendar year would fail to

account for the fact that the ‘annual quantity of sand mined fluctuates

substantially due to changes in demand, economic conditions, capacity, and

31

other facts,’ and (2) the volume of sand that was mined in 2007 was in the

‘low range compared with previous years.’ ” (Id. at p. 217.) These points

were reinforced in the response to comments to the draft EIR, wherein staff

acknowledged the notice of preparation date normally fixes the baseline, but

explained that using the average volume of sand mined per year from 2002 to

2007 “ ‘recognizes that sand mining activity levels can fluctuate substantially

from year to year. ’ ” (Ibid.) In the court action, the challenger contended the

EIR was “deficient because the baseline conditions were artificially inflated

and not reflective of current mining conditions in the projected area.” (Ibid.)

The Court of Appeal upheld the commission’s determination,

concluding substantial evidence supported its utilization of “a five-year

average of annual mining volumes was a better indicator of existing mining

conditions than the 2007 rate in light of the financial crisis of 2007, and the

general nature of the mining industry.” (Baykeeper, supra, 242 Cal.App.4th

at p. 218.) This evidence included data from the California Geological Survey

which showed “ ‘California’s residential construction slowdown during [2007]

contributed to a significant decrease in both production and value of

construction aggregate’ ” and statistics “regarding the permitted and actual

sand mining volumes from the lease areas during the previous [ten year]

lease period” which supported the commission’s conclusions about the “fluid

nature of mining activities in general.” (Ibid.)

SSE maintains Baykeeper is distinguishable and the County failed to

provide any “meaningful analysis . . . and supportive evidence” to support its

use of a five-year average baseline. Specifically, SSE complains that unlike

the Lands Commission in Baykeeper, the County did not “provide a 10-year

average of production for comparison” nor the “annual statistics” for 2004 to

2008. Cases will, of course, differ, and there is no rule that only data

32

identical to that in Baykeeper can support a baseline based on historic data.

Further, the County referenced the California Geological Survey (2013),

which noted that many factors including population, “major public

construction projects,” and the economy can impact the demand for aggregate

production.16 The survey states, “Should unforeseen events occur, such as

massive urban renewal, infrastructure projects, reconstruction in the wake of

disaster, or major economic recession,” the demand for aggregate could

“change considerably.” This fluctuation in demand can be seen in the

provided data on the “recorded aggregate production” at the Syar quarry for

the years 1960 through 2010. The data shows a varied course of production

over this 50-year span, including during the baseline production years at

issue here. The average production levels were 7,500,000 (2004), 7,943,000

(2005), 6,413,000 (2006), 6,778,000 (2007), and 4,753,000 (2008). (The

average production for 2009 was 4,190,000 tons.)

The County and Syar maintain the production differential in 2009

reflects “a year of substantial economic downt[urn].” SSE maintains, in turn,

that respondents “do not provide evidence for that statement or that the

economic conditions impacted aggregate production levels in 2009.” While we

think it may be a matter of judicial notice that our state’s economy was in

serious distress during that time frame, the precise cause for the lower

production level is immaterial. What the historic production numbers show

is that aggregate production can vary considerably, supporting the County’s

16 Contrary to SSE’s claim that the County referenced this document in

the final EIR only “to demonstrate the Project site is classified as containing

mineral deposits, not to support the claimed baseline conditions,” the County

actually referenced the document several times in its response to comments,

including in response to a comment discussing the average truck trip

distance, on-road emissions, aggregate consumption, and the production

baseline of 810,363 tons per year.

33

determination that a five-year average is a reasonable means by which to

assess the impacts of an expanded operation.

In sum, that SSE disagrees with the County’s chosen methodology for

determining the production baseline is insufficient to show an abuse of

discretion. (See Baykeeper, supra, 242 Cal.App.4th at p. 219.)17

Insufficient Mitigation for Loss of Carbon Sequestration Capacity

Due to Loss of Oak Woodlands

SSE maintains the EIR also insufficiently addresses greenhouse gas

emission impacts caused by the loss of oak woodland. Specifically, SSE

claims Mitigation Measure 4.4-9 relies on “illusory oak tree preservation”

(through conservation easements on existing woodlands) to mitigate the loss

of carbon sequestration capacity provided by living trees, since the approved

project would “deforest 121 acres of California oak woodland,” but the

mitigation measure requires that replacement trees be planted on only 12

acres.

Exhaustion

The County and Syar maintain SSE failed to exhaust its administrative

remedies because it did not identify in either appeal packet the greenhouse

gas/loss of oak woodlands issue it raises in this court action.

SSE first responds that the County and Syar forfeited exhaustion, as it

was not raised as an affirmative defense in the trial court. As we have

recited, however, the courts have repeatedly stated that exhaustion,

particularly in CEQA cases, is a jurisdictional prerequisite and not a matter

of judicial discretion. (E.g., Clews, supra, 19 Cal.App.5th at p. 184.)

Furthermore, the exhaustion requirement is based on important public

We need not, and do not, address the alternative arguments the

17

County and Syar make to support the production baseline.

34

policies, including that the public agency has had a fair opportunity during

the environmental review process to address and, if necessary, to correct,

asserted deficiencies in its environmental review. (E.g., North Coast, supra,

216 Cal.App.4th at p. 623.) Failure to exhaust administrative remedies can

also preclude the development of a full administrative record as to an issue

subsequently challenged in a court action. This not only prejudices the public

agency, but also impedes the court’s ability to review the agency’s action.

Finally, whether an objector exhausted its administrative remedies is a legal

question that can be as readily decided on appeal as in the trial court. (Id. at

p. 624.)

We therefore need not automatically dispense with the exhaustion

requirement solely because it was not raised in the trial court. (See Sea &

Sage Audubon Society, Inc. v. Planning Com. (1983) 34 Cal.3d 412, 417

[“appellate courts have . . . permitted a party to raise belatedly ‘a pure

question of law which is presented on undisputed facts’ ”].) Given that nearly

eight years of environmental review before the Planning Commission and the

Board of Supervisors was devoted to the project at issue, resulting in an

administrative record exceeding 29,000 pages in length, we decline to

dispense with this jurisdictional prerequisite here.18

18 SSE cites to Golden Door Properties, LLC v. Superior Court (2020)

53 Cal.App.5th 733 (Golden Door III), as though it holds exhaustion must

first be raised in the trial court and if not, this prerequisite is forfeited. The

case holds no such thing. Golden Door III involved an original writ

proceeding challenging an order on a motion to augment the administrative

record. (Id. at p. 50.) Specifically, the appellate court addressed whether a

lead agency must retain documents, including e-mails, regardless of any

automatic document destruction protocols. The court answered in the

affirmative. (Id. at pp. 42-43.) It’s only mention of exhaustion was in

explaining why the discovery referee had erred in refusing to consider the

showing the petitioner made in its reply memorandum, responding to an

exhaustion argument the respondent made in its opposing discovery

35

SSE secondly responds that it did exhaust its administrative remedies

as to the greenhouse gas/loss of oak woodlands issue it has raised in this

court action.

We have reviewed the entirety of SSE’s grounds of appeal in both

appeal packets. While there are a number of generic assertions of inadequate

analysis of greenhouse gases, nowhere in SSE’s grounds of appeal pertaining

to greenhouse gases is there any reference to trees at all, let alone an

assertion the greenhouse gas analysis is deficient due to failure to adequately

account for and mitigate loss of carbon sequestration capacity.

For example, on the pages of its appeals packets to which SSE cites, we

find the following language, which we presume is the language to which SSE

must be referring, since each page has extensive, single-spaced text and SSE

provides no further assistance as to what language it believes is relevant to

exhaustion:

“The EIR’s greenhouse gas emissions calculations and the air quality

assessment are calculated on the basis of the number of truck and

vehicle trips associated with the quarry operation. However, the EIR

does not identify the length of the truck or vehicle trips. This

information is essential for determination of the emissions associated

with each and cumulative trips. A California Public Records Act

request was made for the weigh tags, which identify the actual

destination of each truck trip, thereby allowing calculation of the

emissions associated with it. The County refused to provide the weigh

tags and acknowledged that it does not have the information requested.

After the lengthy EIR process, the administrative record still does not

contain evidence of the amount of aggregate used locally or the future

local need for aggregate or the reserves present in the unexpanded

quarry. Failure to evaluate the emissions associated with the actual

memorandum. The appellate court stated the petitioner had no obligation in

its discovery moving papers to anticipate the respondent’s exhaustion

argument and properly countered the argument in its reply. (Id. at pp. 63-

64.)

36

trips renders the EIR’s greenhouse gas emissions calculations and air

quality assessment invalid. The Planning Commission’s conclusion

that the environmental impacts of the project on greenhouse gas

emissions and air quality are ‘less than significant’ is not supported by

substantial evidence.”

“The EIR finds the proposed expansion would have significant air

quality and greenhouse gas emission impacts yet fails to require

feasible mitigation that would eliminate or substantially lessen these

impacts. The EIR does not include a greenhouse gas mitigation plan.

Quantification of Syar’s greenhouse gas emissions data is unverified.

The EIR does not identify or analyze the cumulative environmental

impacts of the Project’s contribution to greenhouse gases. . . . [T]he EIR

was certified without an accurate inventory of existing emissions so the

impact of the Project’s current operations or proposed expansion cannot

be comprehensively analyzed.”

“Mitigation measures are inadequate to address environmental effects

of project.” “[G]reenhouse gas emissions . . . are inaccurately,

inadequately and incompletely described.”

Rather, the only mention of trees in SSE’s stated grounds of appeal in

either appeal packet is in section XVI of its grounds of appeal of the project

and permit approvals, wherein SSE stated in pertinent part:

“XVI. The Conditions of Approval (COA) are flawed because they are

based on flawed/inadequate mitigation measures. In addition, the

following are examples of other issues with the COA. Again, due to the

time allowed to file the appeal, an exhaustive list of flaws in the COA

cannot be provided at this time. [¶] . . . [¶]

“7. COA—PROJECT SPECIFICATION CONDITIONS, ITEM N:

requires replacement of oak woodlands at a ratio of 2:1, but a tree count

was not included in the EIR or in the Conditions of Approval from

which the number of replacement trees can be determined.

“8. COA—PROJECT SPECIFICATION CONDITIONS, ITEM O: does

not address inadvertent removal of trees.”

37

Again, this ground did not begin to fairly apprise the Board of

Supervisors of the greenhouse gas/loss of oak woodlands carbon sequestration

issue SSE has raised in this action. The Board, in turn, understandably, did

not perceive SSE to be raising any such issue by virtue of this stated ground,

as evidenced by its decision rejecting SSE’s appeals and specifically

addressing this ground as follows:

“Appellant’s Position:

Appellant SSE alleges that the conditions of approval are flawed

because they are based on flawed/inadequate mitigation measures.

Appellant SSE includes the following examples of other issues with the

COA and contends that due to the time allowed to file the appeal, an

exhaustive list cannot be provided in time. [¶] . . . [¶]

“7. COA—PROJECT SPECIFICATION CONDITIONS, ITEM N:

requires replacement of oak woodlands at a ratio of 2:1, but a tree count

was not included in the EIR or in the Conditions of Approval from

which the number of replacement trees can be determined.

“8. COA—PROJECT SPECIFICATION CONDITIONS, ITEM O: does

not address inadvertent removal of trees. [¶] . . . [¶]

“Findings and Decision. [¶] . . . [¶]

“The Conditions of Approval are detailed, voluminous, enforceable, and

subject to review every five years at a noticed public hearing before the

Planning Commission. (See COA No. 1(F).) This review is in addition

to the Annual Compliance and Assurance Update Report submitted to

the Planning, Building and environmental Services Department per

COA NO. 2(L). [¶] . . . [¶]

“Regarding COA Nos. N and O, the project replaces oak woodlands at

this scale on an acreage basis, not on an individual tree basis.

Mitigation includes the appropriate acreage of replacement oak

woodland to satisfy the 2:1 replacement ratio.”

38

SSE additionally cites to two other pages of the record—which are not

part of its stated grounds of appeal but are attachments to its second appeal

packet. However, as the County’s appeal ordinance makes explicit, and the

Board of Supervisor’s decision makes clear, only specified grounds are

addressed on appeal. For the same reason, SSE cannot rely on written

comments submitted to the planning department by the Quercus Group three

months after SSE filed its second appeal packet identifying its “Grounds of

Appeal” of the project and permit approvals. These comments discussed

“direct and indirect biogenic GHG emissions [that] occur when native forest

resources are harvested” and referenced “Mitigation Measure 4.4-9.”19 ( SSE

has not directed our attention, however, to any action by it to augment its

stated grounds of appeal either as to the certification of the EIR or approvals

of the project and permit. Accordingly, as we have recited, the Board of

Supervisors, in accordance with the County’s appeal ordinance, addressed

and made findings only as to the stated grounds before it.

In short, SSE did not raise as a Ground of Appeal to the Board of

Supervisors the greenhouse gas/loss of oak woodlands issue it raises in this

court action. Thus, SSE did not exhaust its administrative remedies as to

this issue.

Merits

Indeed, as to this issue, SSE’s failure to exhaust its administrative

remedies—and thus its failure to afford the County the opportunity to

19During one of the hearings before the Board, an individual, not from

SSE, but an organization called Bay Area 350, spoke about biogenic

greenhouse gases, Mitigation Measure 4.4-9, and also read parts of the

Quercus Group report into the record.

39

address this ground during the environmental review process—creates an

impediment to full judicial review.

As we have recited, the Board had no cause to understand SSE was

attacking either the certification of the EIR or the approvals of the project

and permit on the ground the greenhouse gas analysis was deficient due to

failure to sufficiently mitigate loss of carbon sequestration capacity provided

by existing oak trees, and the Board therefore did not address this issue.

Rather, the Board addressed the only ground pertaining to trees SSE

identified—that the conditions of approval of the project and permit were

“flawed” because condition N requiring tree replacement at a 2:1 ratio did not

include a “tree count” and condition O did not address the “inadvertent

removal of trees.” And as to that ground, there is no dispute that the Board

provided a reasonable explanation as to why it rejected SSE’s assertions as to

conditions N and O.

The EIR explains that Mitigation Measure 4.4-9 specifies that “[d]irect

and indirect impacts to approximately 130 acres of native oak woodlands

shall be compensated at a total mitigation ratio of 2:1, including [a]

combination of onsite avoidance and preservation . . . , onsite replacement . . .

and offsite.” (Boldface and italics added.) More specifically, “mitigation may

be accomplished through a combination of onsite avoidance/preservation,

partial onsite replacement/preservation, and additional preservation in

accordance with a plan prepared by a qualified biologist. The additional

preservation will be achieved through onsite or offsite mitigation, in-lieu fee

payment to the Oak Woodlands Conservation Fund or through other

mitigation activities. . . .”

As to tree replacement, the EIR states “[a] site evaluation of oak

woodlands on the project site by an ecologist mapped out areas that appeared

40

suitable for initiating oak replacement plantings. . . . These areas amount to

approximately 12 acres of suitable area for potential onsite replacement for

partial mitigation of impacts to oaks. . . .”

The EIR goes on to state that, under the mitigation measure, “[t]he

proposed project would avoid [any future disturbance of] 136 acres of on-site

oak woodlands. . . . These areas shall be protected via deed restriction in a

form acceptable to the County and shall be recorded prior to any new

vegetation removal activities.” A further provision of the mitigation measure

provides that “[a]n additional 111 acres off-site shall be permanently

preserved via easement or deed restriction or in-lieu fee payment to the Oak

Woodlands Conservation Fund consistent with Public Resources Code section

21083.4. . . . Offsite location(s) shall be located within Napa County and be of

like quality and habitat value as those being removed. . . .”

The combination of mitigation measures required by Mitigation

Measure 4.4-9 is consistent with the Oak Woodlands Preservation Act

(§ 21083.4), which provides in part: “As part of the determination made

pursuant to Section 21080.1,[20] a county shall determine whether a project

within its jurisdiction may result in a conversion of oak woodlands that will

have a significant effect on the environment. If a county determines that

there may be a significant effect to oak woodlands, the county shall require

one or more of the following oak woodlands mitigation alternatives to

mitigate the significant effect of the conversion of oak woodlands: [¶] (1)

Conserve oak woodlands, through the use of conservation easements. [¶]

(2)(A) Plant an appropriate number of trees, including maintaining plantings

20 Section 21080.1 provides in part: “The lead agency shall be

responsible for determining whether an environmental impact report, a

negative declaration, or a mitigated negative declaration shall be required for

any project which is subject to this division.” (§ 21080.1, subd. (a).)

41

and replacing dead or diseased trees. [¶] (B) The requirement to maintain

trees pursuant to this paragraph terminates seven years after the trees are

planted. [¶] (C) Mitigation pursuant to this paragraph shall not fulfill more

than one-half of the mitigation requirement for the project. [¶] (D) The

requirements imposed pursuant to this paragraph also may be used to

restore former oak woodlands. [¶] (3) Contribute funds to the Oak Woodlands

Conservation Fund, as established under subdivision (a) of Section 1363 of

the Fish and Game Code, for the purpose of purchasing oak woodlands

conservation easements, as specified under paragraph (1) of subdivision (d) of

that section and the guidelines and criteria of the Wildlife Conservation

Board. A project applicant that contributes funds under this paragraph shall

not receive a grant from the Oak Woodlands Conservation Fund as part of

the mitigation for the project. [¶] (4) Other mitigation measures developed by

the county.” (§ 21083.4, subd. (b)(1)-(4).)

The combination of mitigation measures required by Mitigation

Measure 4.4-9 is also consistent with the oak woodlands provisions of the

County’s general plan. It provides, as to oak woodland habitat, that the

County shall “[m]aintain and improve oak woodland habitat to provide for

slope stabilization, soil protection, species diversity, and wildlife habitat

through appropriate measures including” compliance with section 21083.4

and providing “replacement of lost oak woodlands or preservation of like

habitat at a 2:1 ratio when retention of existing vegetation is found to be

infeasible.”

In sum, through the combination of mitigation measures required by

Mitigation Measure 4.4-9, the impact on 121 acres of oak woodlands is being

mitigated by way of planting and preserving a collective total of 242 acres of

such woodlands, and the EIR, thus, concludes the mitigation measure “would

42

reduce the potential impacts on coast live oak and habitat to a less-than-

significant level by implementation of avoidance, restoration and/or

replacement.” (Boldface & italics added.)

However, SSE is not, at this juncture, complaining about the

sufficiency of the mitigation measures to address the impact on the native

oak woodlands, but rather about its sufficiency to mitigate greenhouse affects

and, specifically, loss of carbon sequestration capacity.

The EIR separately analyzes greenhouse gas emissions, including

changes to carbon sequestration capacity resulting from the clearing of the

trees. Specifically, section 4.17 of the EIR, entitled “Greenhouse Gases,”

explains “[w]hen land is cleared, some percentage of the carbon stored is

released back to the atmosphere as CO2. Land clearing or the loss of carbon

stock is thus a type of [greenhouse gas] emission.” The EIR concludes the

proposed project “would have a potentially negative effect on the County’s

current level of carbon sequestration functions. . . . This impact is considered

potentially significant.”

The EIR then discusses the mitigation measure “requir[ing]

compensation for loss of oak woodland” (i.e., Mitigation Measure 4.4-921), and

also Mitigation Measure 4.17-2. It explains that “Mitigation Measure 4.4-[9]

would require compensation for loss of oak woodland. Compensation would

include a mix of preservation (either on or off-site), onsite replacement, and

contribution to an in-lieu fee program. . . . Mitigation Measure 4.17-2 would

monitor [greenhouse gas] emissions as the project is implemented and

identify measurable reduction strategies to reduce emissions when emissions

21 The EIR refers to the mitigation measure regarding compensation

for loss of oak woodland as 4.4-8, but this appears to be a typographical error

as 4.4-8 addresses impacts to purple needlegrass, whereas 4.4-9 addresses

loss of oak woodland.

43

exceed the established baseline. . . . As mitigated, the proposed project would

be consistent with the Napa County General Plan, and [the impact] would be

considered less than significant.”

SSE complains that the “ ‘EIR hasn’t provided any mathematical

calculations that demonstrate the proposed mitigation will in fact reduce

direct and indirect biogenic emissions to less than significant’ ” and that the

EIR fails to demonstrate how Mitigation Measure 4.4-9 “would ‘actually

mitigate the [121] acres of lost forest carbon sequestration capacity.’ ”

But because SSE did not identify these complaints as a Ground of

Appeal, they were never addressed during the administrative proceedings.

We are therefore left to observe that SSE cites no authority requiring

mathematical calculations concerning carbon sequestration mitigation. In

fact, the Bay Area Air Quality Management District’s CEQA Air Quality

Guidelines specifically provide: “Biogenic CO2 emissions should not be

included in the quantification of [greenhouse gas] emissions for a project. In

its reply brief, SSE asserts, as we understand it, that it is not claiming

“biogenic” greenhouse gases must be included in the “quantification” of total

green gas emissions, but rather, that the effectiveness of mitigation measures

for loss of carbon sequestration capacity must be demonstrated by

mathematical computation. SSE does not, however, cite to any District

guideline that imposes such a requirement.

SSE also cites to King & Gardiner Farms, LLC v. County of Kern (2020)

45 Cal.App.5th 814 (King), as compelling the conclusion Mitigation Measure

4.4-9’s authorization of conservation easements on other woodlands is, per se,

inadequate mitigation of loss of carbon sequestration capacity. In King, the

project at issue was a Kern County “ordinance to streamline the permitting

process for new oil and gas wells” for which an EIR had been prepared. (Id.

44

at p. 829.) “An important purpose of the proposed amendment was to

eliminate time-consuming and costly review of individual well and field

development activities by establishing a ministerial permit review process

that incorporates mitigation measures identified in the project’s EIR. If the

County correctly determined the permit review process was ministerial—that

is, did not involve the exercise of discretion—the processing of future permit

applications by the County [would] not be subject to additional environmental

review under CEQA.” (Id. at p. 832, fn. omitted.)

One of the issues addressed by the EIR was conversion of agricultural

lands in Kern County. The EIR “estimated annual land disturbances

associated with future oil and gas exploration and production activities would

result in the conversion of 298 acres of agricultural land annually.” (King,

supra, 45 Cal.App.5th at p. 870.) A mitigation measure required loss of

agricultural land to be addressed in a “ ‘1:1 mitigation ratio’ ” via four

different methods, one of which was funding agricultural conservation

easements. (Id. at p. 871.) The court concluded “agricultural conservation

easements . . . do not actually offset the conversion of farmland.” (Id. at

pp. 829-830.) It explained “Entering into a binding agricultural conservation

easement does not create new agricultural land to replace the agricultural

land being converted to other uses. Instead, an agricultural conservation

easement merely prevents the future conversion of the agricultural land

subject to the easement. Because the easement does not offset the loss of

agricultural land (in whole or in part), the easement does not reduce a

project’s impact on agricultural land. The absence of any offset means a

project’s significant impact on agricultural land would remain significant

after the implementation of the agricultural conservation element. . . . At the

end of each year, there would be 289 fewer acres of agricultural land in Kern

45

County. Accordingly, under the thresholds of significance listed in the EIR,

this yearly impact would qualify as a significant environmental effect.

Therefore, we agree with KG Farms’ contention that MM 4.2-1.a does not

provide effective mitigation for the conversion of agricultural land.” (Id. at

pp. 875-876.)

Here, SSE is not challenging the adequacy of Mitigation Measure 4.4-9

to mitigate the impact on (and namely, the loss of) oak woodlands, which

would be the analog of the loss of farmland in King. Rather, SSE has

expressly limited its claim to “the failure of the EIR to formulate effective

mitigation for the Project’s GHG impacts due to carbon sequestration and

storage losses.”

SSE’s reliance on Golden Door Properties, LLC v. County of San Diego

(2020) 50 Cal.App.5th 467 (Golden Door II) is also misplaced. That case

concerned the county’s ongoing efforts to adopt a climate action plan,

guidelines for determining significance of climate change, and a supporting

EIR. (Id. at p. 482.) At the outset of its opinion, the court stated: “To be

abundantly clear, our holdings are necessarily limited to the facts of this

case, and in particular [mitigation measure] M-GHG-1. Our decision is not

intended to be, and should not be construed as, [a] blanket prohibition on

using carbon offsets—even those originating outside of California—to

mitigate GHG emissions under CEQA.” (Id. at p. 483.) In concluding that M-

GHG-1 violated CEQA because its performance standard was unenforceable,

the court rejected the County’s assertion M-GHG-1 was the “equivalent” of a

“cap-and-trade offset[]” program. The court explained M-GHG-1 was

“materially different from Assembly Bill No. 32 compliant cap-and-trade

offsets.” (Id. at p. 511.) For one thing, M-GHG-1 did not require offset

protocols “to be consistent with CARB requirements under title 17, section

46

95972, subdivision (a)(1)-(9) of the California Code of Regulations.” (Id. at

p. 512.) There also were no limits of use of credits, from any place in the

world, to meet greenhouse gas reduction standards. “In sharp contrast, cap-

and-trade offsets cannot[, under the state’s regulatory scheme,] exceed 8

percent of an entity’s entire compliance obligation.” (Id. at p. 513.) In

addition, under the state’s cap-and-trade scheme, “GHG emission reductions

must be additional ‘to any greenhouse gas emission reduction otherwise

required by law or regulation, and any other greenhouse gas emission

reduction that otherwise would occur.’ ” (Id. at pp. 513-514.) “For example,

CARB will not approve a protocol that ‘includes technology or GHG

abatement practices that are already widely used.’ ” (Id. at p. 514.)

Suffice it to say, the court’s discussion in Golden Door II of a

greenhouse mitigation measure enacted in conjunction with the development

of the county’s climate action plan, and specifically in the context of rejecting

the county’s assertion the measure was the equivalent of a statutorily

compliant cap-and-trade program, is not the context with which we are

concerned here. Furthermore, SSE’s reliance on the cap-and-trade discussion

in Golden Door II to bolster its claim that the EIR in this case insufficiently

mitigates greenhouse gas impacts caused by loss of oak woodlands only

magnifies the consequences of its failure to exhaust its administrative

remedies as to this issue—the County had no opportunity to address any

comparative cap-and-trade issue, and the record, in turn, is not developed in

this respect.

Finally, the EIR identifies not only Mitigation Measure 4.4-9, but also

Mitigation Measure 4.17-2. This mitigation measure provides in pertinent

part:

“The Applicant shall prepare a Greenhouse Gas Reduction Plan (GHG

Reduction Plan). The GHG Reduction Plan shall identify the measures

47

to be used to reduce the GHG emissions associated with the proposed

project below the 1,100 MT CO2e annual land use threshold (or

increase of 1,100 MT CO2e over baseline conditions). The effectiveness

of each measure in the GHG Reduction Plan shall be quantified,

indicating its contribution to the reduction of GHG emissions. The

Applicant shall choose from, but not be limited to, the following

measures to incorporate into the GHG Reduction Plan: [¶] Fuel on-road

and off-road vehicles with alternative fuels (such as hybrid, biodiesel,

and electric); [¶] Plant native trees and vegetation that have low

emissions of volatile organic compounds species for carbon

sequestration in locations at the project site not to be disturbed by

quarrying activities; [¶] Replace diesel-powered vehicles with newer

model, low-emission vehicles or replace diesel engines with higher fuel

efficiency engines or use retrofit emission control devices, such as diesel

oxidation catalyst, verified by the California Air Resources Board as old

vehicles or engines no longer become operable; [¶] Develop a monitoring

program that reduces diesel-fueled idling times beyond that required

under the California Air Resources Board Heavy-Duty Vehicle Idling

Emission Reduction Program; [¶] Require that on-road haul trucks that

are under contract with the quarry operator use 2003 model or newer

trucks; [¶] Establish an on-site renewable energy system (such as

solar); [¶] Install an automated load out system; [¶] Contribute to a

State or County offset mitigation program. [¶] The GHG Reduction

Plan shall be reviewed and approved by Napa County and shall be

updated as necessary to address changing conditions and regulations.

[¶] Prior to implementing the GHG Reduction Plan, the Applicant shall

monitor GHG emissions biannually in a GHG inventory submitted to

the County for review. The first inventory shall be calculated as a

three-year average after issuance of the use permit (for example, if the

use permit is issued in 2014, then the first inventory shall be performed

in 2018 for years 2015 through 2017). A three-year average would

accommodate the variability in aggregate sales from year to year. The

inventory shall follow the most recent version of the General Reporting

Protocol of the California Climate Action Registry or other protocol as

appropriate and approved by the County (CCAR 2007). . . . The

purpose of the inventory is to compare emissions from project

operations to the baseline emissions established in this EIR, which is

approximately 7,200 MT CO2e per year (if new baseline emissions are

established as a result of refined reporting methods, the use of a

different baseline is acceptable with approval by the County). At such

time as the inventory indicates GHG emissions are at or over baseline

48

conditions (7,200 MT CO2e per year), then the Applicant shall

implement measures in the GHG Reduction Plan as necessary to avoid

emissions above the 1,100 metric ton threshold (i.e.: 8,300 MT CO2e per

year–baseline plus threshold).”

The Board of Supervisors addressed and rejected SSE’s complaints that

the “EIR does not include a greenhouse gas mitigation plan,” “[q]uantification

of Syar’s greenhouse gas emissions is unverified,” and the “EIR’s air quality

mitigation measure (Mitigation Measure 4.3) consists essentially of keeping

logs and providing the logs to the County twice a year if the County asks for

it.” (Italics & underscoring omitted.) The Board pointed out that “the Final

Draft Climate Action Plan was publicly available and referenced in Section

4.17 of the Draft EIR. . . . [¶] . . . The [Greenhouse Gas Reduction Plan] will

incorporate one or more of the measures listed in Mitigation Measure 4.17-2,

which would reduce GHG impact to less than significant levels. . . . [¶] . . .

Mitigation Measure 4.17-2 will monitor and begin mitigating emissions as

they approach or exceed the threshold. The project will mitigate any

emissions over the threshold, even if the emissions had already occurred and

the project implements mitigation retroactively. . . . [¶] . . . The mitigation

measures contain performance standards and provides a range of options for

demonstrating compliance. Syar has not asserted that it is infeasible and has

agreed to comply.”

In sum, as to the greenhouse gas issues SSE actually raised in its

appeal to the Board of Supervisors, there is ample discussion in the EIR and

appropriate mitigation measures have been required.

Water Usage Baseline

SSE maintains the water use baseline is “unsupported” and “relies on

layers of uncertainty,” thereby resulting in an “artificially high baseline”

which has resulted in “underreport[ing] the Project’s potential impacts.” As

49

we understand its claims, SSE contends the baseline is inaccurate for two

reasons. One, “there are conflicting amounts” stated “throughout the EIR” as

to annual sand production during 2004-2008 (these five years of production

were averaged to provide the production baseline figure) and the EIR “relies

on the highest estimate.” Two, the baseline determination incorrectly

“assume[d] that the sand production water use” during 2009-2011 which was

determined to be 2.7 percent of the total water usage during those years, was

also 2.7 percent of the total water usage during the preceding five years.

These asserted shortcomings resulted, with no “factual support,” in a

“significant scale-up of the water usage for dust control.”

Exhaustion

Syar and the County maintain SSE failed to exhaust its administrative

remedies in regard to the complaints about the water usage baseline they

have pursued in this court action. They assert SSE’s appeal packets raised

only “the general and nebulous issue that the EIR contains an ‘[i]naccurate

description of current groundwater use.’ ”

SSE maintains it exhausted its administrative remedies, citing to the

following language (which we have italicized) in its grounds of appeal in its

first appeal packet, in support of its appeal of the EIR certification (we again

set forth the entirety of the passages in which the language cited by SSE

appears):

“C. Baseline conditions are not adequately described.

“The EIR fails to describe baseline conditions with reference to actually

existing physical conditions. Instead, the EIR relies on models

conducted at other sites to analyze the baseline air quality impacts. It

used the standard trip length from the County’s traffic model to

analyze baseline traffic conditions. It fails to disclose existing water

usage, relying instead on data for water usage and groundwater levels

to be collected after the expansion is approved. Air quality studies in

50

the EIR are based on mining industry sponsored tests and models

conducted at other sites and calculated with controlled conditions not

representative of the Project’s actual conditions. The EIR provides no

basis for relying on modeled conditions instead of measuring the

actually existing physical conditions.” (Italics added.)

“M. Mitigation deferred and/or inadequate.

“1. 35-year permit period precludes adequate mitigation measures.

“The County admits that ‘pre-design of the mine at each stage of

development is difficult and prone to inaccuracies because the

economics and technology available for material recovery cannot be

accurately evaluated based on what is known today. Mining operations

are inherently market sensitive and market value and need for specific

types of material vary greatly over time.’ The County further admits

that ‘(u)ntil the economic value and market demand for material is

known with precision the cost/benefit of mining and implementing all of

the mitigation measures cannot be evaluated.’ [Citation.]

“Even assuming that the impact analysis is correctly done, which it

clearly was not, mitigation is inadequate. The document relies on

infeasible mitigation measures in several major resource areas which

are insufficient to reduce potential impacts to a less than significant

level for other impacts and other resource areas. Some examples

include:

“a. Groundwater

Assessment of existing water usage and groundwater levels will

not occur until after Project approval. This constitutes

impermissible deferred mitigation.

“Given the fractured bedrock nature of the aquifer, the mitigation

measure meant to prevent excess loss of groundwater through

seepage (Mitigation Measure 4.8-2) is infeasible. The mitigation

measure relies on borings to determine whether mining may be

planned close to the groundwater table; in fractured bedrock,

where groundwater flow occurs primarily through fractures,

borings will not be able to correctly predict the location of the

groundwater table. The County’s experience with the MST

amply demonstrates that groundwater elevations, groundwater

51

quality, and groundwater flowrates can vary tremendously

between wells located in close proximity.

“The mitigation measure (Mitigation Measure 4.8-3) intended to

ensure that groundwater consumption does not exceed the

currently stated level of 140 acre feet per annum (afa) is

inadequate because it fails to account for new consumptive uses

associated with increased loss to evaporation from new/larger

ponds, and the greatly increased surface area of the rock face. No

effort was made to assess the potential extent of seepage

(although Syar should have been able to provide some

characterization of current seepage levels.) See Parker

Groundwater Report in the administrative record.”22

SSE’s also cites to the following language (which we have italicized) in

its “Grounds of Appeal” in its second appeal packet in support of its appeal of

the project and permit approvals (we again set forth the entirety of the

passage in which the language cited by SSE appears):

“XI. The findings for Approval of Surface Mining Permit fail to comply

with the requirements of Napa County Code Chapter 16.12 for issuance

of surface mining permit, are in error, inadequate and incomplete.

“A. Plans and reports submitted with the application do not adequately

describe the proposed operation. Inadequate and shifting description of

project and its environmental impacts. Baseline production, reserves,

greenhouse gas emissions, truck trips, groundwater usage are

inaccurately, inadequately and incompletely described. For example,

the map attached as Exhibit 4 depicts an off-site groundwater well to

which Syar has access but was never disclosed or analyzed. Nor does

the permit resolution require any monitoring or other condition related

to this off-site well. Exhibit 5, a page from the 1973 EIR conducted for

the original permit shows groundwater at that time far exceeding that

estimated today-1120.14 acre feet per year historically vs. 140.6 acre

22 The Parker Groundwater Report was attached to a June 2, 2015

letter to the Planning Department from Kathy Felch, “on behalf of” Syar.

Contrary to SSE’s claim, the appeal packet did not “incorporate” this report

by this reference, nor did the packet identify where, in the massive

administrative record, the report was to be found.

52

feet per year. There is no accurate estimate of groundwater use either in

the EIR or in the permit approval such that the project’s groundwater

use may imperil surrounding properties’ dependence on groundwater.”

(Italics added.)

The excerpts on which SSE relies, particularly when read in context,

can only be described as “ ‘[r]elatively . . . bland and general references to

environmental matters,’ ’’ “ ‘unelaborated comment[s].’ ” (North Coast Rivers,

supra, 216 Cal.App.4th at p. 623.) Such generic objections do not satisfy the

exhaustion requirement. (Ibid.)

Moreover, SSE’s statements certainly did not apprise the Board of

Supervisors of the sand production related issues SSE has pursued in this

court action, as the Board’s decision reflects.

The Board summarized SSE’s “baseline” ground of appeal as follows:

“Baseline conditions are not adequately described. The EIR fails to

describe baseline conditions with reference to actually existing physical

conditions. Instead, the EIR relies on models conducted at other sites

to analyze the baseline air quality impacts. It used the standard trip

length from the County’s traffic model to analyze baseline traffic

conditions. It fails to disclose existing water usage, relying instead on

data for water usage and groundwater levels to be collected after the

expansion is approved. Air quality studies in the EIR are based on

mining industry sponsored tests and models conducted at other sites

and are calculated with controlled conditions not representative of the

Project’s actual conditions. The EIR provides no basis for relying on

modeled conditions instead of measuring the actually existing physical

conditions.”

As to this ground, the Board concluded in relevant part:

“Substantial evidence supports the EIR’s determination of baseline

conditions for groundwater. There is no historical metering of

groundwater use at Syar Napa Quarry because groundwater use

metering has not been a County requirement of pre-existing

groundwater wells in the MST. The lack of groundwater extraction

data is not unique in Napa County or the State of California. Due to

53

the unavailability of groundwater metering data in 2009 (when the

County published the NOP), metering was conducted as part of the

baseline studies for the project during 2011. The EIR used this data to

calculate the groundwater used during the baseline year of 2009 by

adjusting for differing production volumes between 2009 and 2011, as

recorded in the Syar Napa Quarry Water Supply Assessment found in

the Draft EIR, Appendix K.”

The Board summarized SSE’s mitigation deferred/inadequate ground of

appeal in pertinent part as follows:

“35-year permit period precludes adequate mitigation measures. [¶]

The County admits that ‘pre-design of the mine at each stage of

development is difficult and prone to inaccuracies because the

economics and technology available for material recovery cannot be

accurately evaluated based on what is known today. Mining operations

are inherently market sensitive and market value and need for specific

types of material vary greatly over time.’ The County further admits

that ‘(u)ntil the economic value and market demand for material is

known with precision the cost/benefit of mining and implementing all of

the mitigation measures cannot be evaluated. [¶] Even assuming that

the impact analysis is correctly done, which it clearly was not,

mitigation is inadequate. The document relies on infeasible mitigation

measures in several major resource areas which are insufficient to

reduce potential impacts to a less than significant level for other

impacts and other resource areas. Some examples include: [¶] a.

Groundwater. [¶] Assessment of existing water usage and groundwater

levels will not occur until after Project approval. This constitutes

impermissible deferred mitigation. [¶] Given the fractured bedrock

nature of the aquifer, the mitigation measure meant to prevent excess

loss of groundwater through seepage (Mitigation Measure 4.8-2) is

infeasible. The mitigation measure relies on borings to determine

whether mining may be planned close to the groundwater table; in

fractured bedrock, where groundwater flow occurs primarily through

fractures, borings will not be able to correctly predict the location of the

groundwater table. The County’s experience with the MST amply

demonstrates that groundwater elevations, quality, and flowrates can

vary tremendously between wells located in close proximity. [¶] The

mitigation measure (Mitigation Measure 4.8-3) intended to ensure that

groundwater consumption does not exceed the currently stated level of

54

140 acre-feet per year is inadequate because it fails to account for new

consumptive uses associated with increased loss to evaporation from

new/larger ponds, and the greatly increased surface area of the rock

face. No effort was made to assess the potential extent of seepage

(although Syar should have been able to provide some characterization

of current seepage levels.) (See Parker Groundwater Report in the

administrative record.)”

As to this ground, the Board concluded in relevant part:

“Groundwater Mitigation: [¶] A licensed hydrologist prepared a

comprehensive groundwater analysis and recommended appropriate

mitigation measures to reduce impacts as set forth in the EIR. For

projects for which an EIR has been prepared, where substantial

evidence supports the approving agency’s conclusion that mitigation

measures will be effective, courts will uphold such measures against

attacks based on their alleged inadequacy. (Laurel Heights,

supra,47 Cal.3d at p. 407; Sacramento Old City Assn. v. City Council

(1991) 229 CaI.App.3d 1011, 1027.) Similarly, substantial evidence

shows the mitigation measures were adequate. (See Mira Mar Mobile

Community v. City of Oceanside (2004) 119 Cal.App.4th 477, 495 . . .

[mitigation may include ‘minimizing impacts by limiting the degree or

magnitude of the action’ and ‘compensating for the impact by replacing

or providing substitute resources or environments’].) The Board has

considerable discretion in determining the effectiveness of mitigation

measures. (Vineyard Area Citizens for Responsible Growth, Inc. v. City

of Rancho Cordova (2007) 40 Cal.4th 412, 435 . . . [‘the reviewing court

“may not set aside an agency’s approval of an EIR on the ground that

an opposite conclusion would have been equally or more reasonable” ’;

court cannot ‘ “determine who has the better argument’ ”]; see also

Banning Ranch Conservancy v. City of Newport Beach (2012)

211 CaI.App.4th 1209, 1233.)

“With respect to evaporative losses, they were addressed by Mitigation

Measure 4.8-2, which protects against potential persistent open water

bodies created when mining intersects the groundwater elevation,

substantially increasing evaporation losses. Evaporative loss can also

occur when the groundwater recharge mechanisms are interfered with,

such as when subsurface flow in fractures or soil is exposed or

intercepted by mining. However, Mitigation Measure 4.8-2 requires

that any subsurface flow in fractures or soil that is exposed or

55

intercepted by the excavation be re-infiltrated within the same

watershed boundaries. This mitigation also includes spring season

monitoring concurrent with the SWPPP monitoring (required by

Mitigation Measure 4.8-1) to verify that springs and subsurface flow

exposed as a result of mining activities are infiltrated back into the

subsurface before reaching the surface flow channels.”

As to SSE’s claim of inadequate “plans and reports” to support approval

of the mining permit ground, the Board quoted the ground verbatim. And as

to “Wells and Water Use,” the Board concluded:

“The Draft EIR accurately describes baseline water use of the project

and future project demand in Appendix K. Appellant SSE’s reference

to one page from a 1973 EIR does not reflect the current water use at

the quarry and in fact the reference to one million gallons a day

appears to be a description of the wells daily production, not the water

use occurring at the quarry. As discussed in the Draft EIR, Final EIR,

the Appendices, and other responses to comments, the majority of

water use at the quarry is associated with the application of water for

dust control purposes, which in the 1973 EIR is stated as 80,000

gallons per day, therefore, to assume that the quarry utilized an

additional 920,000 gallons a day is mere speculation. Most importantly

even assuming for argument sake that the quarry prior to Syar

Industries purchase of the site utilized 1,000,000 gallons of water a

day, the evidence in the record establishes that it no longer does so.

The Draft EIR accurately measure baseline water use and requires

ongoing monitoring and reporting to [e]nsure that the baseline water

use of 140.6 acre-feet per year is not exceeded. The Draft EIR

evaluated the two wells utilized by the project for water supply, the

Quarry Well and Latour Court Well. No other wells are currently being

utilized. Mitigation Measure 4.8-4 requires monitoring and restricts

groundwater use to a maximum of 140.6 acre-feet per year.” 23

23 SSE also points to what appears to be a PowerPoint document

prepared for a hearing on March 22, 2016. That document lists, under the

heading “Stop Syar Expansion Appeal Grounds,” the ground of “Inadequate

impact and mitigation assessment due to incorrect baseline and modeling

techniques primarily associated with [¶] Air Quality and Health Risk [,]

Noise[,] Groundwater Hydrology and use[,] Aesthetics.” This, however, was

simply another articulation of SSE’s generic complaints about the baselines

56

In short, the Board of Supervisors, in accordance with the County’s

appeal ordinance, addressed and made findings only as to the stated grounds

before it, none of which fairly raised the sand production-related issues SSE

has pursued here.

The trial court nevertheless concluded SSE had exhausted its

administrative remedies, stating: “[T]he Court interprets Petitioner’s

arguments relating to the EIR’s water supply analysis more broadly, as an

assertion that the EIR fails to adequately analyze the existing water supply,

and the water supply planning for the Project. The court finds that

Petitioner did raise these issues in its appellate packet [citation] in a manner

sufficient to give the County ‘the opportunity to evaluate and respond to

them.’ ”

We agree that SSE “broadly” raised the issue of the water usage

baseline, but that is not the standard for exhaustion. Rather, “ ‘ “ ‘the exact

issue’ ” ’ must have been presented to the administrative agency.” (South of

Market, supra, 33 Cal.App.5th at p. 347; North Coast Rivers, supra,

216 Cal.App.4th at p. 623.) Objections must be “ ‘sufficiently specific’ ” to

apprise the agency of the asserted deficiency, so it can “ ‘evaluate and

respond’ ” and have an “ ‘ “ ‘ “opportunity to act and to render litigation

unnecessary.” ’ ” ’ ” (North Coast Rivers, at p. 623.) The Board of Supervisors

was not so apprised as to the sand production related issues about the water

usage baseline SSE has pursued here. Thus, SSE did not exhaust its

administrative remedies in this regard.

and did not apprise the Board of the water usage baseline complaints related

to sand production it has raised in this court action.

57

Merits

Even assuming SSE exhausted its administrative remedies, there is no

merit to its challenge to the water usage baseline.

The water usage baseline and the EIR’s water impact analysis is based

on the “Syar Napa Quarry Water Supply Assessment” (Water Supply

Assessment) prepared by County consultants during the environmental

review process.24 The assessment explains how the usage baseline was

determined as follows:

Syar operates two water supply systems associated with the quarry.

The systems are supplied by two wells, the Latour Court Well and the Quarry

Well, and by surface water detention ponds.

Water is used at the quarry for dust suppression, sand and gravel

washing, bathrooms at the Syar site offices, and irrigation of “reclamation re-

vegetation.” The Latour Court Well supplies potable water to the Syar

offices, as well as to the offices of other companies. The Quarry Well supplies

“non-potable water for quarry operations.” The surface water detention

ponds supply water for dust suppression and for “washing sand and

aggregate materials.”

The quarry facilities are not connected to a municipal water source.

During the years the quarry has been in existence, “there has not been a need

to account for the amount of water required [because]. . . [w]ater has always

been available in abundance by way of a water well field that was developed

by the C&H Sugar Company many years ago. . . .”

The Water Supply Assessment relied in part on the production

baseline, which was determined, as we have discussed, by averaging annual

quarry production for the preceding five years.

24 This assessment is attached to the EIR as Appendix K.

58

Because water usage had, historically, not been measured and was not

measured during that five-year period, the assessment next examined three

sources of data to arrive at a baseline water usage number.

First, the assessment looked at the extraction rates from the Latour

Court Well, which was metered starting in 2011. Second, as to the Quarry

Well, the assessment looked at a combination of metered flow for a six-month

period in 2009 and actual truck counts filling from the well. It then

approximated extraction for the remaining months of 2009 “by scaling the

pumping rates [from the six-month period] to match the percent

increase/decrease observed in the Latour Court Well.” Third, to estimate

water use from the surface-water detention ponds, the assessment used the

number of water truck fillings during a 20-day period in May 2009, and based

on this, arrived at “a typical monthly pond extraction rate.”

Based on this data, the Water Supply Assessment estimated the

annual total water usage for 2009 to 2011 from the Latour Court Well as

17,974,900 gallons, from the Quarry Well as 13,515,00 gallons, and from the

surface ponds as 9,714,000 gallons (which assumed pumping occurred only

from May through September25). Thus, the assessment concluded the

average total annual water usage for the years 2009-2011 was 41,203,900

gallons

The Water Supply Assessment then compared average annual sand

production for this same time period, 44,329 tons, and factored in that it

takes 25 gallons of water to produce one ton. The assessment thus calculated

the amount of water used for sand production for 2009-2011 as 1,108,225

25The assessment pointed out water usage from the ponds for dust

suppression occurs only from May through September.

59

gallons. This, in turn, was 2.7 percent of the total annual water usage for

those years.

The assessment then returned to the baseline sand production—49,474

tons (an average of the “known sand production” for the preceding five years).

Multiplied by the sand production water usage figure of 25 gallons per ton,

this resulted in a baseline water usage of 1,236,850 gallons for sand

production. The assessment then factored in that water usage for sand

production during the 2009-2011 period accounted for only 2.7 percent of

total usage, and using this same percentage, calculated the baseline total

water usage as about 45.8 million gallons.26

SSE complains the EIR water usage baseline “scrapes together an

assortment of information regarding water use” from 2009-2011, resulting in

an “unsupported estimate” of quarry water usage, which is then “significantly

scaled-up to form the baseline water usage” and “fails to provide the most

accurate picture.”

As detailed above, the EIR does, indeed, rely on “an assortment of

information regarding water usage.” Neither the data on which it relies, nor

the methodology used to estimate baseline water usage, however, are

“unsupported.” Rather, because there had always been ample water for the

aggregate operation and because metering was not required as of the baseline

date, the water supply assessment had to devise a reasonable methodology

for estimating the baseline water usage.

26 The County commissioned a second water assessment that used an

entirely different methodology. It calculated baseline water usage “by

combining the site description and geological setting information with

monitoring data from: rainfall, evaporation/evapotranspiration, stream

gages, pond gages, groundwater elevation piezometers, and field

observation.” The study concluded the estimated baseline annual quarry

water usage was about 48.8 million gallons.

60

As we have recited, SSE maintains the Water Supply Assessment used

by the County is deficient in two respects.

First, it takes issue with the baseline sand production number of

49,474 tons (the average annual production during the five-year baseline

period).27 SSE claims “[t]here are conflicting amounts used throughout the

EIR” regarding the amount of sand production during that time period and

the EIR “relies on the highest estimate.” Specifically, SSE points to a lower

annual sand production number of 37,688 tons, found in the “Air Quality and

Health Risk Impact Assessment” (AQ Assessment) prepared by another

consultant and attached as Appendix I to the Draft EIR. That lower number,

however, is in a chart covering that same five-year timeframe titled “Total

Quarry Production Shipped by Truck.” (Italics added.) The AQ Assessment,

of course, was concerned with emissions from truck traffic, so focused on

truck records and not the actual “known” sand production amounts used in

the Water Supply Assessment.

SSE also claims the Water Supply Assessment incorrectly “assumes

that sand production water use would also be 2.7 percent of the total water

usage in 2004-2008.” SSE does not explain, however, why it was not

reasonable for the County to make the assumption that the percent of the

total water usage used for sand production during the 2009 to 2011

timeframe would be similar to that during the preceding five year timeframe.

27 The Water Assessment states it is based on “the five-year average

production rates from 2004 through 2009.” As the trial court noted, a five-

year period includes 2004, 2005, 2006, 2007 and 2008, but does not include

2009. It also appears to have been assumed that the five-years of production

figures that were averaged to provide the production baseline figure were the

five years preceding the 2009 date of publication of the notice of preparation.

61

In sum, the Water Supply Assessment and EIR explain in considerable

detail the methodology the County chose to use to determine the water usage

baseline and the reasons for that choice. This discussion adequately allowed

for public discussion and informed decision-making. (See South of Market,

supra, 33 Cal.App.5th at p. 354 [“ ‘ “CEQA requires an EIR to reflect a good

faith effort at full disclosure; it does not mandate perfection, nor does it

require an analysis to be exhaustive.” ’ ” Quoting Chaparral Greens v. City of

Chula Vista (1996) 50 Cal.App.4th 1134, 1145].)

SSE claims water usage for dust control does not increase

proportionally with increased production and therefore there is “no

evidentiary support for the scaling-up of water usage during the baseline

years beyond the approximately 2.7 percent of the water used for sand

washing.” “There is,” according to SSE, no “factual support for the

[assessment’s] significant scale-up of the water usage for dust control.” We

are at a loss as to SSE’s point. As we have discussed, the Water Supply

Assessment determined that 2.7 percent of the total water usage during the

2009-2011 timeframe was for sand processing and the remaining 97.3 percent

was used for other purposes. It then applied that same correlation to the

preceding five-year time period, and based on known sand production for that

period, arrived at a total water usage number for both sand production and

for other uses during that prior time period. We fail to see how this

“significantly scaled up” the water usage for dust control during the

preceding five-year timeframe and, in turn, the baseline.

In fact, the Water Supply Assessment recognized there is not

necessarily a proportional increase in both quarry production and water

usage for dust control, stating: “The proposed increase in mining production

does not necessarily relate to a proportional increase in water consumption,

62

because the same number of roads and stockpiles will require dust

suppression regardless of the total production amounts.” (Italics added.) But

as between the preceding five-years and the 2009-2011 time periods, there

was no increase in the size of the quarry operation, suggesting the water

required for dust control would likely be reasonably equivalent during both

time periods.

SSE cites to Save Our Peninsula Committee v. Monterey County Bd. of

Supervisors (2001) 87 Cal.App.4th 99 (Monterey). In that case, the draft EIR

established a “baseline of 45 acre-feet per year, based on the representation

by the owners that 21 acres were irrigated.” (Id. at p. 120.) It acknowledged,

however, there was “ ‘no documentation’ ” of “any substantial irrigation prior

to 1997,” the year of the draft EIR, and no well reports regarding the

property. (Id. at pp. 109, 120-121.) “[S]parse” records of water use on the

property existed for five years. (Id. at p. 121.) There was also “a temporary

aquifer test conducted in 1991 [which] produced 1.20 acre-feet,” and aquifer

testing in 1992 which produced “40.68 acre-feet.” (Ibid.) In the three years

before the development application, “water production totals were 11.58 acre-

feet, 0.40 acre-feet, and 1.08 acre-feet.” (Ibid.) After the development

application was submitted, water production was measured at 78.34 acre-

feet, 34.04 acre-feet in 1998, and 41.14 acre-feet for a portion of 1999. (Id. at

p. 123.)

In the “Supplemental Information and Errata” to the EIR, “several

possible combinations and averages of these production numbers” were

suggested. (Monterey, supra, 87 Cal.App.4th at p. 123.) The baseline figure

adopted by the Board, 51 acre-feet per year, was “an average of the water

meter readings in the past three years.” (Ibid.)

63

The Monterey court had “no objection to the EIR’s methodology of

estimating historical water use on property where no documentation is

available to verify actual use.” (Monterey, supra, 87 Cal.App.4th at p. 121.)

Indeed, the court explained “If the determination of a baseline condition

requires choosing between conflicting expert opinions or differing

methodologies, it is the function of the agency to make those choices based on

all of the evidence.” (Id. at p. 120.)

The court noted, however, that the data on which the calculation was

based was “clearly faulty” because “several of the figures on the water

production chart do not represent water actually used for irrigating the

property.” (Monterey, supra, 87 Cal.App.4th at p. 123, italics omitted.) It

noted, as an example, that the 78.34 acre-feet figure for 1997 included 52-

acre-feet produced during aquifer testing. (Id. at p. 123.) “A baseline figure,”

said the court, “must represent an environmental condition existing on the

property prior to the project. There is simply no justification for using a total

of 78.34 acre-feet of water as part of a baseline calculation for this property,

when the evidence was that 52 acre-feet of this amount was pumped for the

purpose of aquifer testing and was discharged into the Carmel River.” (Ibid.)

“[E]stimating water used for irrigation where there was no substantial

evidence to show that the property was in fact irrigated does not accurately

reflect existing conditions.” (Id. at p. 121.)

The baseline calculation here has no comparable “clearly faulty” figure.

The water usage baseline was estimated by using “known” sand production

amounts during all referenced time periods, using an undisputed gallon

figure required for sand production, and using water use data for time

periods for which there were records. None of this information was plainly

erroneous, unlike in Monterey.

64

At bottom, SSE disagrees with the County’s chosen methodology for

determining the baseline given the lack of complete water usage records for

2009 and no records for the preceding five years on which the baseline was

based. However, as Monterey, itself, confirms, where “the determination of a

baseline condition requires choosing between conflicting expert opinions or

differing methodologies, it is the function of the agency to make those choices

based on all of the evidence.” (Monterey, supra, 87 Cal.App.4th at p. 120.)

The EIR, which incorporates the Water Supply Assessment, explains the

County’s choice of methodology and reasons for it, and it cannot be said that

the County’s approach is marred by plainly faulty data or is unreasonable.

(See South of Market, supra, 33 Cal.App.5th at p. 334 [“when assessing the

legal sufficiency of an EIR, we do not look for perfection, but ‘adequacy,

completeness, and a good faith effort at full disclosure’ ”].)

Water Use Mitigation Measure

In a related vein, SSE maintains Mitigation Measure 4.8-4 is

inadequate because it sets a cap on quarry groundwater usage based on the

asserted “hypothetical” water usage baseline. SSE additionally claims an

“enforcement mechanism” for the usage cap is “lacking.”

Again, even assuming SSE exhausted its administrative remedies as to

these complaints (we note none of its grounds of appeal mention Mitigation

Measure 4.8-4), they are without merit.

We have already determined SSE’s challenge to the supposedly

“hypothetical” water usage baseline lacks merit. We therefore consider here

only SSE’s complaint that there is no “enforcement” of Mitigation Measure

4.8-4’s usage “cap.”

As we have discussed, the Water Supply Assessment explained that

water usage was not metered during the five-year baseline period because

65

water was drawn from private sources and there was always ample water for

quarry production. The assessment further discussed that it was anticipated

that the project would continue to use extracted water at the baseline rate,

and if additional water is needed, it will be procured from other sources,

including the Napa Sanitation District’s recycled waste water program. The

assessment went on to estimate that some 16 million additional gallons of

water might be needed for the projected increased production. This would be

met through several means, including: “recycled water from the City of

Napa,” “water recovery system at its sand plant to recycle the water that is

used in washing the sand,” and/or reduced water demands by alternative

dust suppression methods, such as gravel application to roads and spray

surfactants.

As set forth in the draft EIR, Mitigation Measure 4.8-4 provided:

“Avoid depleting groundwater supplies by water reuse and obtaining new

supplies of additional water for operations.” The explanation of the

mitigation measure provided: “If additional [water] is required for the

proposed project, this additional water will be obtained from off-site

sources. . . . Off-site sources of recycled water are available and water can be

purchased from public or private sources. If additional water sources are not

available then production volume will be reduced to the extent that the water

use does not exceed the maximum allowable annual usage [of] 45.8 million

gallons (140.6 acre-ft) per year.” The draft further explained, “[n]o additional

water from on-site resources is available to accommodate the additional

water demand of the proposed project. The maximum allowable annual

usage is 45.8 million gallons. . . . This mitigation measure includes metering

to verify that demands upon on-site water are not exceeded.” “In order to

monitor the use of the existing on-site sources, metering and record keeping

66

are required. Mitigation would include metering of all water use at the

site. . . . [¶] . . . [¶] . . .The total of groundwater/surface water used for quarry

operations would be totaled and reported annually. The annual usage would

be compared against the baseline usage on an annual basis.”

During the review process, Mitigation Measure 4.8-4 was augmented

with the following language: “Any new or additional water sources for

Quarry operations shall [be] subject to additional environmental review

pursuant to CEQA and modification of this surface mining permit. The

County Engineering and Conservation Division shall monitor this

requirement. Compliance [with] this measure shall be subject to Article VI

(Enforcement) of Napa County Code Chapter 16.12 (Surface Mining and

Reclamation).”

Thus, the “cap” imposed by the Mitigation Measure is enforceable, both

through metering and the enforcement provisions of the County Code. (See

Napa County Code, §16.12.660, subd. (a) [“Any person who operates,

maintains or causes to be operated or maintained any surface mining

operation which is not in conformance with the provisions of this chapter, the

exploration or surface mining permit issued, or any requirement, term or

condition of a master mining plan approved for the site being mined is guilty

of a misdemeanor.”])

Water Quality Impacts

As to water quality, SSE asserts the EIR (1) failed to disclose baseline

water quality conditions, and (2) failed to analyze water quality impacts of

using a surfactant, a substance added to water to enhance effectiveness for

dust control.

67

Exhaustion

The trial court ruled SSE failed to exhaust its administrative remedies

as to these water quality issues.

SSE claims it did so, citing to the following language (which we have

italicized) in its first appeal packet supporting its appeal of the EIR

certification (again, we quote the entirety of ground):

“f. Groundwater depletion and increased sediment effect on steelhead

trout and Western Pond Turtles.

“Both steelhead trout, on the Endangered Specie[s] List as threatened

status, and Western Pond Turtles, a specie of concern warranting full

protection of their habitat, are found in Project’s expansion area.

Neither the EIR nor the responses to public comments adequately

address the Project’s exacerbation of groundwater depletion in the MST

Groundwater Deficient Area and its destruction of the Cayetano and

Marie creeks and their watersheds. There is no adequate discussion of

the biological/aquatic resource impacts from the Project’s increase in

toxic sediment discharges to the Cayetano/Marie watersheds. There is

no analysis or mitigation proposed for the destruction of habitat for the

steelhead and the turtles. See comment letter from Living Rivers

Council in administrative record.” (Second italics added.)

SSE also points to the following language (which we have italicized) in

its second appeal packet supporting its appeal of the project and permit

approvals (again, we quote the language in context):

“IX. PERMIT APPROVAL DOES NOT COMPLY WITH SMARA

“SMARA requires, inter alia, that a reclamation plan contain a

description of the manner in which contaminants will be controlled.

See Public Resources Code section 2772. There is no evidence in the

record of a description of how contaminants will be controlled.”

68

Neither of these stated grounds of appeal comes close to advising the

Board of Supervisors as to the water quality issues SSE has advanced in this

court action.

SSE also cites to another ground set forth in its second appeal packet,

entitled: “XIX. POPE CREEK QUARRY SHUT DOWN DURING

PENDENCY OF SYAR APPICATION.” However, this ground concerned a

different, “much smaller” quarry that was shut down in 2011, and as to which

the County had some difficulty in enforcing waste and debris mitigation.

Again, there is no way the Board of Supervisors would have divined from this

ground, that SSE was complaining about the lack of a water quality baseline

and the use of surfactant to enhance dust control.

SSE also maintains its explicit “incorporation” of the Parker

Groundwater Report in its first appeal packet sufficed to raise the water

quality issues it raises here. But SSE did not “incorporate” that report and

instead merely referenced it—“See Parker Groundwater Report in the

administrative record” (at a location it did not mention)—as support for a

different ground of appeal. Indeed, this reference was in support of a claim

there were no sufficient mitigation measures “to prevent excess loss of

groundwater through seepage,” as “[n]o effort was made to assess the

potential extent of seepage.” SSE is not, in this appeal, complaining about

groundwater loss through seepage.

SSE’s claim that the “County’s response to the appeal understood this

comment to address inadequacies of the SWPPP and water quality

mitigation” is likewise meritless. SSE cites to a page in a “Staff Report for

Napa County Board of Supervisors Syar Appeal Hearing,” without identifying

any specific language. That page discusses “Contaminant Control” in the

context of hazardous waste removal and identifies licensed waste transport

69

contractors. It mentions “control of contaminants also extends to air quality,”

but makes no mention of water quality.

Not surprisingly, the Board of Supervisors decision reflects it did not

understand SSE to be claiming the EIR was deficient because it failed to

establish a water quality baseline and failed to assess the impact of

surfactant use. Rather, as the Board’s decision shows, the Board addressed

only the grounds that were fairly before it—namely the adequacy of analysis

of impacts on steelhead and turtles, and compliance with Surface Mining Act

requirements pertaining to reclamation of mined areas.

As to the surfactant issue only, SSE additionally points out the Board

of Supervisors addressed the issue in its 37-page decision addressing the

appeal of another objector, Skyline Park Citizens Association (Skyline Park).

Among its stated grounds of appeal, Skyline Park included, as issue #4, the

following: “The EIR fails to identify an adequate supply of water to serve the

Project at the approved production levels, fails to evaluate the environmental

impacts of reasonably foreseeable means whereby the Project’s existing water

supply can and will need to be supplemented to sustain those production

levels, and fails to adequately protect groundwater resources in the MST

groundwater deficient area.” As we discuss below, the Board recounted how

this ground embraced the use of surfactant, and addressed Skyline’s concern

at length.

We have considerable doubt that SSE can point to the efforts of another

objector to establish that SSE exhausted its administrative remedies. The

Napa County appeals ordinance requires an appellant to state its grounds of

appeal and expressly states grounds not raised are waived. (Napa County

Code, § 2.88.050(C)(4)-(6).) And in accordance with the dictates of the

ordinance, the Board of Supervisors rendered separate decisions as to each

70

appellant and, as to each, addressed only the grounds raised by that

appellant.

Furthermore, Skyline Park filed its own court action challenging the

Board’s decision denying its administrative appeal. And in that court action,

Skyline raised the issue of surfactant use, alleging “The EIR fails to analyze

the environmental impacts of Syar’s use of chemical dust suppressants to

achieve its water conservation goal.” Skyline eventually reached a

settlement with the County, and its action was then dismissed with

prejudice. Given that this dismissal constituted a final judgment on the

merits, it had preclusive effect not only as to the claims Skyline raised, like

the use of surfactants, but also as to claims it could have raised. (See

Mycogen Corp. v. Monsanto Co. (2002) 28 Cal.4th 888, 896–897.)

SSE points out it was not a party to Skyline Park’s court action.

However, it is now well-established that an objector will be precluded from

relitigating CEQA issues where a final judgment has been entered in a court

action brought by another objector and there is a community of interest—or,

privity—between the two objectors. (See Inland Oversight Committee v. City

of San Bernardino (2018) 27 Cal.App.5th 771, 781–782; Atwell v. City of

Rohnert Park (2018) 27 Cal.App.5th 692, 699; Citizens for Open Access ect.

Tide, Inc. v. Seadrift Assn. (1998) 60 Cal.App.4th 1053, 1071–1072.) We have

no difficulty concluding there was such privity between SSE and Skyline

Park. After all, SSE is relying on Skyline Park’s administrative appeal

efforts to establish that it exhausted its administrative remedies. We fail to

see how SSE can align itself with Skyline Park for purposes of exhausting

administrative remedies, but then disclaim any community of interest for

purposes of the preclusive effect of Skyline Park’s litigation efforts.

71

Merits

In any case, even assuming SSE exhausted its administrative

remedies, neither of its complaints about water quality have merit.

As we have recited, the first of SSE’s water quality complaints is that

the EIR fails to disclose baseline water quality conditions. Specifically, SSE

complains the EIR “fails to disclose that the Quarry’s water quality baseline

is one of recurrent pollution.”

However, the EIR discloses exactly that, stating as follows: “The

project could result in a violation of water quality standards or waste

discharge requirement by employing quarry practices that would cause

substantial erosion or sedimentation on- or off-site. . . . The Syar Napa

Quarry currently has a SWPPP [Stormwater Pollution Prevention Plan] as

part of Syar NPDES Permit for Industrial Activities and would continue to do

so under the project. The SWPPP describes and dictates management

practices to prevent contaminants from entering storm water discharge and

prevent unauthorized non-storm water discharges. . . . Compliance with

sediment discharge limits is monitored by comparing the discharge from the

site to EPA suggested benchmarks. Monitoring of storm water discharges

from the Syar Napa Quarry has indicated that EPA suggested benchmark

standards have been exceeded. A tabulation of surface water sampling

results is provided in Appendix D of the Winzler & Kelly 2012 report,”

attached to the DEIR.

SSE maintains this discussion is inadequate due to its reference to

Appendix D, a disclosure which, according to SSE, must be “made in the EIR

itself and not buried as an afterthought, tacked onto an appendix.” SSE cites

to Banning Ranch Conservancy v. City of Newport Beach (2017) 2 Cal.5th 918

(Banning) and Vineyard Area Citizens for Responsible Growth Inc. v. City of

72

Rancho Cordova (2007) 40 Cal.4th 412 (Vineyard). These cases stated, “[t]he

data in an EIR must not only be sufficient in quantity, it must be presented

in a manner calculated to adequately inform the public and decision makers,

who may not be previously familiar with the details of the project.

‘[I]nformation “scattered here and there in EIR appendices” or a report

“buried in an appendix,” is not a substitute for “a good faith reasoned

analysis.” ’ ” (Vineyard, at p. 442; see Banning, at pp. 940–941.)

In Vineyard, the court observed, “A reader of the FEIR could not

reasonably be expected to ferret out an unreferenced discussion in the earlier

Water Forum Proposal, interpret that discussion’s unexplained figures

without assistance, and spontaneously incorporate them into the FEIR’s own

discussion of total projected supply and demand.” (Vineyard, supra,

40 Cal.4th at p. 442, italics & bold added.) Thus, “[t]o the extent the County,

in certifying the FEIR as complete, relied on information not actually

incorporated or described and referenced in the FEIR, it failed to proceed in

the manner provided in CEQA.” (Ibid., italics added; see Banning, supra,

2 Cal.5th at pp. 940–941.)

Here, in contrast, discharge containment was both generally discussed

in the EIR and the detailed analytical data was expressly referenced in an

identified appendix. Thus, the information was “presented in a manner

calculated to adequately inform the public and decision makers.” (Vineyard,

supra, 40 Cal.4th at p. 442.)

SSE’s second water quality complaint is that the EIR failed to analyze

the potential impact of using surfactants.

The draft EIR noted that “[n]o additional water from on-site resources

is available to accommodate the additional water demand of the project.”

Accordingly, Mitigation Measure 4.8-4 stated in pertinent part: “Mitigation

73

also will be applied by off-setting the need for additional water by reuse of the

water and gains in process efficiency. This could include gravel application

for roadways and production areas to reduce dust generation and the need for

dust suppression by water application.” The draft EIR also discussed

“fugitive dust,” and in that regard referenced Mitigation Measure 4.3-2B

which provided in pertinent part: “Maintain chemical dust suppressant,

equivalent dust suppressant that achieves similar control, on the unpaved

road surfaces as described in the manufacturer’s specifications. Material

used for chemical dust suppressant shall not violate State Water Quality

Control Board standards. Materials accepted by the California Air Resources

Board and the US EPA, and which meet State water quality standards shall

be considered acceptable.”

As we have discussed, Skyline Park raised the issue of sufficient water

for mining operations, and Board of Supervisors addressed the issue,

including the use of surfactants to enhance existing water resources, in its

decision on Skyline’s appeal. The Board first discussed the background of the

issue, explaining that during the environmental review process, and in

response to Skyline’s concern about the use of alternative water resources,

Syar had “determined it could feasibly achieve the reduced maximum annual

production rate of 1.3 million tons without exceeding baseline water use via

water conservation technologies, as discussed in the Draft EIR mitigation

measures, Water Availability Analysis, and Air Quality Analysis. The water

conservation technologies include graveling or paving roads, using

surfactants, reusing wash water, and other methods that reduce the use of

water for dust suppression.” Syar and the County’s EIR consultant then

“provided evidence regarding the feasibility of achieving full production

within the maximum water use limitations. [Syar’s] evidence of feasibility

74

was focused on the use of surfactants on heavy traffic areas due to the readily

available information regarding its effectiveness in reducing water demand.

In practice, [Syar] would use numerous technologies to increase water use

efficiency and make adjustments based on monitoring data to achieve

compliance with the maximum allowable groundwater use of 140.6 acre-feet

per year.”

The Board then turned to Skyline Park’s concern that Syar’s “agreeing

not to exceed its baseline water use via increased efficiencies and water

conservation” raised, in turn, concern “that the use of such technologies, like

surfactants on road surfaces was a change in the mitigation measure or new

information that would require additional environmental review.” The Board

stated it had “received evidence from both the Applicant and Appellants and

heard testimony from the County EIR Consultant.” The consultant “stated

that the EIR already considered the use of surfactants and other technologies

in the project’s Water Availability Analysis and Air Quality Modeling and

that such use was consistent with the proposed mitigation measures.

Notably, under Mitigation Measure 4.3-2B, the Applicant may only use dust

suppressants that the California Water Quality Control Board, the California

Air Resources Board and the United States Environmental Protection Agency

has approved. While some types of surfactants could have environmental

impacts, the EIR Consultant stated that many surfactants were composed of

nontoxic plant material and do not result in any impacts. The Board also

head from County staff that environmentally friendly surfactants were in

common use throughout the Napa Valley in agricultural areas. Further, the

Project’s Industrial Storm Water Permit monitors water quality impacts and

would effectively address any possible impacts. The EIR consultant also

clarified that the use of surfactants was not new information since the use of

75

surfactants was expressly provided for in air quality mitigation and discussed

in the Draft EIR and its appendices.”

The Board went on to explain that “[i]n response,” it had “directed staff

to clarify in the mitigation measures, consistent with the Draft EIR, that only

non-toxic surfactants would be allowed. . . .”

The Board then set forth the entirety of the three pertinent and lengthy

mitigation measures, indicating the modifications. For example, Mitigation

Measure 4.8-4 was augmented with language stating, inter alia, “The

Permittee shall review the monitoring data on a monthly basis to confirm the

status of its annual water use. The total of groundwater/surface water used

for quarry operations shall be totaled and reported monthly to the County.”

Mitigation Measure 4.8-4 was also modified to eliminate any reliance on new

water sources to meet quarry demand. Instead, “[t]he Permittee shall also

off-set additional water demands by reusing water and increasing processing

efficiencies. This could include gravel, pavement, and surfactant application

to roadways and production areas to reduce dust generation and the need for

dust suppression by water application, as discussed in Mitigation Measure

4.3-2b and Draft EIR, Appendix J.” As modified, the measure further

specified, “[t]his permit does not authorize the consumptive use of water for

any source in excess of 140.6 acre-ft per year, regardless if obtained outside

the MST.”

Mitigation Measure 4.3-2b was also augmented with the following

language: “Materials used for chemical dust suppressant shall include any

non-toxic chemical or organic dust suppressant or stabilizer and shall not

violate State Water Quality Control Board standards. Materials accepted by

the California Air Resources Board and the U.S. EPA, and which meet state

water quality standards shall be considered acceptable. The permittee shall

76

maintain records on dust suppressant use and any other supporting

documentation to verify compliance with the conditions above. Such records

shall include type of control measure(s) used, location and extent of coverage,

date of use, amount, and frequency of application, including product

information sheets that identify the name of the dust suppressant(s) and

application instructions. Records shall be maintained for five (5) years, and

shall be submitted to the PBES Department annually, as required by COA

No. 2 (L).”

In sum, as the Board of Supervisors recognized, the Draft EIR did

analyze the use of surfactants and did so specifically in the context of their

use—to control dust. Moreover, the issue was adequately examined during

the administrative appeal process. And while SSE suggests it was improper

to modify and enhance the pertinent mitigation measures during that

process, that is incorrect. One of the important purposes of the exhaustion

doctrine is to allow agencies the opportunity to review, and to address,

asserted deficiencies in the environmental review. (See State Water

Resources Control Bd. Cases (2006) 136 Cal.App.4th 674, 794; quoting Napa

Citizens for Honest Government v. Napa County Bd. of Supervisors (2001)

91 Cal.App.4th 342, 384.) Indeed, “[a]fter a project has been approved and

while it is still being developed a mitigation measure or condition of approval

may be changed or deleted if the measure has been found to be impractical or

unworkable.” (Lincoln Place Tenants Assn. v. City of Los Angeles (2005)

130 Cal.App.4th 1491, 1508–1509.)

Consistency with General Plan

SSE lastly contends the EIR failed to address the project’s asserted

inconsistencies with the County’s general plan.

77

Not A CEQA Issue

In the trial court, the County and Syar pointed out an EIR must

address only inconsistencies with a general plan. Because the County

determined the project is consistent with its general plan, they maintained

the EIR is not deficient in this regard. Further, to challenge the County’s

consistency determination, the County and Syar maintained SSE was

required to proceed by way of a separate cause of action under Code of Civil

Procedure section 1085 for ordinary mandamus, or a separate proceeding for

such—neither of which SSE pursued. The trial court agreed and therefore

did not consider the merits of SSE’s general plan consistency argument.

In The Highway 68 Coalition v. County of Monterey (2017)

14 Cal.App.5th 883, 893–894 (Highway 68), the Court of Appeal explained,

“the issue of whether a proposed project is consistent with a county’s general

plan is not a CEQA issue, and therefore the mandate procedures provided for

CEQA violations at section 21168.9 do not apply. The CEQA Guidelines

provide: ‘The EIR shall discuss any inconsistencies between the proposed

project and applicable general plans, specific plans and regional plans.’

(Guidelines, § 15125, subd. (d).) Thus, as this court has stated, ‘ “ ‘[w]hile

there is no requirement that an EIR itself be consistent with the relevant

general plan, it must identify and discuss any inconsistencies between a

proposed project and the governing general plan. [Citation.]’ [Citation.]

‘Because EIRs are required only to evaluate “any inconsistencies” with plans,

no analysis should be required if the project is consistent with the relevant

plans. [Citation.]’ [Citation.]” [Citation.]’ (Pfeiffer, supra, 200 Cal.App.4th

at p. 1566.)”

Rather, an “ ‘agency’s decisions regarding project consistency with a

general plan are reviewed by ordinary mandamus.’ (San Francisco

78

Tomorrow v. City and County of San Francisco (2014) 229 Cal.App.4th 498,

515. . . .)” (Highway 68, supra, 14 Cal.App.5th at p. 894.)

The Highway 68 court went on to explain, “[u]nder the Government

Code, every county and ci

This text is long and has been trimmed here. Open the source document for the complete record.

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.