Opinion

Melwood Horticultural Training Center, Inc. v. United States

Court
United States Court of Federal Claims
Filed
Nov 30, 2020
Status
Published
On the bench
David A. Tapp
Cited by
0 cases
Authority
More cited than 14.5%

“The District Court’s holding of prematurity was influenced by the statutory scheme that requires several decisional steps before the final conveyance.”

How later courts described this case

  • “The District Court’s holding of prematurity was influenced by the statutory scheme that requires several decisional steps before the final conveyance.”
  • “subsequent to the District Court’s opinion, the Penn Central Reorganization Court determined that the Rail Act did not provide a process that would be fair and equitable to the estate[.]”
  • noting that section 1491(b) provides no jurisdiction for claims of wrongful termination or breach
  • “It is protestor’s burden to establish ripeness.”

Written by the judges who cited it.

The opinion

In the United States Court of Federal Claims

No. 20-758C

Filed: November 23, 2020

Reissued: November 30, 2020 1

MELWOOD HORTICULTURAL Keywords: Motion to

TRAINING CENTER, INC., Dismiss; RCFC 12(b)(1);

Ripeness; Pre-Award Bid

Plaintiff, Protest; AbilityOne; Section

898, National Defense

v. Authorization Act of Fiscal

Year 2017, Pub. L. No. 114-

THE UNITED STATES, 328, 130 Stat 2000; Javits-

Wagner O’Day Act, 41 U.S.C.

Defendant.

§§ 8501–06; 41 C.F.R. 51

Meghan A. Douris and Alix K. Town, Oles Morrison Rinker & Baker, LLP, Seattle, WA, for the

Plaintiff.

Steven C. Hough, Trial Attorney, with whom were Douglas K. Mickle, Assistant Director, Robert

E. Kirschman, Jr., Director, Commercial Litigation Branch, Jeffrey Bossert Clark, Acting

Assistant Attorney General, Civil Division, United States Department of Justice, Washington,

D.C., Robert B. Neill, Mark T. Robinson, United States Army, and Timi N. Kenealy, United

States AbilityOne Commission, Of Counsel, for the Defendant.

MEMORANDUM OPINION AND ORDER

TAPP, Judge.

This is an unconventional pre-award, pre-solicitation bid protest involving the second

iteration of a Pilot Program purportedly authorized by a panel established under Section 898 of

the 2017 National Defense Authorization Act. Plaintiff, Melwood Horticultural Training Center

(“Melwood”), challenges not only the United States’ intent to recompete a contract for base

operations support services provided to the U.S. Army, but also the selection of Fort Meade,

Maryland for the Pilot Program. The United States argues that this case is not yet ripe.

Melwood brought these challenges on June 23, 2020, before the United States solicited

bids for a new contract award. (Compl., ECF No. 1). That same day, Melwood filed a Motion for

1

This Opinion was originally issued under seal. On November 30, 2020, the parties notified the

Court that no redactions were necessary. (ECF No. 54). The Court therefore reissues this

Opinion without redactions but with two immaterial typo corrections.

Temporary Restraining Order, seeking an order enjoining the United States, acting through the

AbilityOne Commission (“AbilityOne” or “the Commission”), from issuing a request for

proposals. The Court denied that Motion on June 26, 2020. (Order Denying TRO, ECF No. 11).

On July 15, 2020, the United States issued an opportunity notice for a Base Operations

and Maintenance services contract at Fort Meade. (Administrative Record (“AR”) at 2, 1543,

ECF No. 22). The United States filed the administrative record for its decision on July 24, 2020.

Soon thereafter, the Court denied Melwood’s Motion to Supplement the Administrative Record.

(Order Denying Mot. to Suppl., ECF No. 33; Pl.’s Mot. to Suppl. AR, ECF No. 26). 2

On August 26, 2020, Melwood moved for judgment on the administrative record. (Pl.’s

MJAR, ECF No. 34). When the United States filed its Response and Cross-Motion for Judgment

on the Administrative Record (Def.’s Mot., ECF No. 42), the United States moved to dismiss

Melwood’s claims under RCFC 12(b)(1) and 12(b)(6). The parties each filed timely reply briefs.

This matter now stands submitted.

For the reasons set forth below, the Court GRANTS the United States’ Motion to

Dismiss, DENIES AS MOOT Melwood’s Motion for Judgment on the Administrative Record,

and DENIES AS MOOT the United States’ Cross-Motion for Judgment on the Administrative

Record.

I. Background

A. The AbilityOne Program

In 1971, Congress passed the Javits-Wagner O’Day Act (“JWOD”), which updated the

Wagner-O’Day Act of 1938. Pub. L. No. 92–28, § 1, 85 Stat. 77 (1971) (codified as amended at

41 U.S.C. §§ 46–48c (2006)). 3 JWOD established the “Committee for Purchase From People

Who Are Blind or Severely Disabled.” 41 U.S.C. § 8502. That Committee, colloquially known

as the AbilityOne Commission, exists to carry out the Federal Government’s policy of

“increas[ing] employment and training opportunities for persons who are blind or have other

severe disabilities through the purchase of commodities and services from qualified nonprofit

agencies employing persons who are blind or have other severe disabilities.” 41 C.F.R. § 51-1.1.

In order to implement these policy goals, procurements under the JWOD function

differently than traditional government procurements. For example, AbilityOne maintains a

Procurement List, which it publishes to the Federal Register, containing products and services

produced or provided by qualified nonprofit agencies (“NPA”) and available for purchase by the

2

Although Melwood moved to supplement the record, because it sought to fill “gaps in the

record” rather than add to it, the Court construed Melwood’s request as a motion to complete the

administrative record. Because Melwood “produced no ‘clear evidence of material that was

generated or considered by the agency but excluded from the record,’” the Court held that it was

“entitled to rely on the presumption that the record the United States has submitted is complete.”

(Order Denying Mot. to Suppl. at 2).

3

Congress amended JWOD in 2011 and recodified it at 41 U.S.C. §§ 8501–06.

2

Federal Government. 41 U.S.C. §§ 8503–8504. Qualified NPAs must employ “blind or other

severely disabled individuals for at least 75 percent of the hours of direct labor required for the

production or provision of the products or services.” § 8501. The Federal Government purchases

products and services from the Procurement List at Fair Market Prices that are determined by the

Commission. § 8503(b). The Commission may, “from time to time . . . revise its price

determinations . . . in accordance with changing market conditions.” § 8503(b).

AbilityOne also must designate central nonprofit agencies (“CNA”) to help “facilitate the

distribution” of government contracts among the qualified nonprofit agencies. § 8503(c).

SourceAmerica is the CNA applicable to this action. (Compl. at 3). The process for

“determin[ing] the fair market price of products and services contained on the procurement list”

involves the “contracting activity,” the qualified nonprofit agency, and the CNA (in this case,

SourceAmerica). 41 C.F.R. § 51-2.7(a). The “contracting activity” is “any element of an entity of

the Government that has responsibility for identifying and/or procuring Government

requirements for commodities or services.” 41 C.F.R. § 51-1.3. The “initial price is based on

Committee procedures, which permit negotiations between the contracting activity and the

nonprofit agency which will produce or provide the commodity or service to the Government,

assisted by the appropriate central nonprofit agency.” 41 C.F.R. § 51-2.7(a). “Recommendations

for initial fair market prices, or changes thereto, shall be submitted jointly by the contracting

activities and nonprofit agencies concerned to the appropriate central nonprofit agency.” 41

C.F.R. § 51-2.7(c). SourceAmerica will then submit the recommended price to AbilityOne. 41

C.F.R. § 51-2.7. Because the policy of the AbilityOne program is to “increase employment and

training opportunities for persons who are blind or have other severe disabilities,” procurements

under the program are designated as “other than competitive.” See 41 U.S.C § 3304(a)(5). The

effect of being designated “other than competitive” is that for procurements in the AbilityOne

program, “[f]ull and open competition need not be provided[.]” FAR 6.302-5(a)(2), (b)(2).

B. The 2017 National Defense Authorization Act (NDAA) and the Pilot Programs

On December 23, 2016, Congress passed the National Defense Authorization Act For

Fiscal Year 2017 (“NDAA”). NDAA For Fiscal Year 2017, Pub. L. No. 114-328, 130 Stat 2000

(2016). Section 898 of the NDAA stated that “[t]he Secretary of Defense shall establish a panel

to be known as the ‘Panel on Department of Defense and AbilityOne Contracting Oversight,

Accountability, and Integrity’” (the “898 Panel”). The 898 Panel was tasked to:

(4) recommend changes to law, regulations, and policy that the Panel

determines necessary to eliminate vulnerability to waste, fraud, and abuse

with respect to the performance of contracts of the Department of Defense;

...

(6) recommend ways the Department of Defense and the AbilityOne

Commission may explore opportunities for competition among qualified

nonprofit agencies or central nonprofit agencies and ensure an equitable

selection and allocation of work to qualified nonprofit agencies;

3

NDAA § 898(c)(4), (6). The 898 Panel was also directed to “consult[] with central nonprofit

agencies and qualified nonprofit agencies” and “suggest milestone dates for implementation of

the recommendations made under subsection (c)[.]” NDAA § 898(f)(1). These recommendations

would also be compiled in an annual report to Congress required by § 898(i). See also Pride

Indus., Inc. v. Comm. for Purchase From People Who Are Blind or Severely Disabled, 420 F.

Supp. 3d 1035, 1039 (E.D. Cal. 2019) (summarizing the required contents of the annual report).

The authority to implement these recommendations is somewhat ambiguous. Under

subsection (e), the 898 Panel has the “authority [to] request documentation or other information

needed from the AbilityOne Commission, central nonprofit agencies, and qualified nonprofit

agencies.” NDAA § 898(e). If AbilityOne fails to substantially implement the recommendations,

the Secretary of Defense, upon receiving notification, “may suspend compliance with the

requirement to procure a product or service [from the Procurement List] until the date on which

the Secretary notifies Congress, in writing, that the AbilityOne Commission is substantially

implementing the [898 Panel’s] recommendations[.]” NDAA § 898(g)(1)(A).

On July 18, 2018, the 898 Panel submitted its First Annual Report to Congress. (AR15–

84). In its First Annual Report, the 898 Panel stated that “CNA and NPA perception that a

designated NPA remains the provider of a product or service in perpetuity can erode

performance, escalate prices, and impact customer satisfaction, and the AbilityOne Program

Reputation and employment.” (AR44). Therefore, the 898 Panel recommended “changes to how

work is assigned or re-assigned, and also changes to Title 41 CFR 51.” (AR44). 4 The proposed

changes included “adding policy which would establish mandatory source selection procedures”

that “would require CNAs to use a specific list of measurable qualifications when choosing an

NPA for the project assignment, such as price, technical capability for the work, past

performance, and the percentage of disabled hours.” (AR44) (emphasis added). For

procurements, the 898 Panel proposed “[r]equir[ing] [a] best value trade-off analysis process that

considers price . . ..” (AR45).

In spring of 2019, the Army advised Pride Industries, Inc.—an AbilityOne NPA

contractor—that it would extend Pride’s Facilities Support Operations contract at Fort Bliss until

January 2020, after which “the contract would be performed by the party awarded the contract by

AbilityOne through a new, pilot procurement process.” Pride Indus., 420 F. Supp. 3d at 1040.

On June 10 and 11, 2019, AbilityOne announced two new policies which would comprise its

new Pilot Program for the AbilityOne procurement process. (AR85–87, 88–90). The first,

Interim Policy 51.301.1, announced “changes relevant to pilot test(s), in which a competitive

nonprofit agency (NPA) recommendation process will be conducted, considering technical

capability, past performance, and price.” (AR85) (emphasis added). The second policy, Interim

Policy 51.320.1, directed CNAs “not [to] provide technical and/or pricing assistance to any NPA

participating in the pilot test.” (AR89). Instead, NPAs were instructed to “provide their pricing

4

The regulations pertinent to the AbilityOne Program are contained in Title 41 C.F.R. Chapter

51.

4

information in accordance with the instructions included in the Opportunity Notice as well as

existing and interim Commission policy and procedures.” (AR89).

On July 31, 2019, the AbilityOne Commission initiated the first iteration of this Pilot

Program procurement at Fort Bliss. See Pride Indus., 420 F. Supp. 3d at 1041; (see also AR325,

1470). In that procurement, the incumbent, Pride Industries, was reselected to perform the

Facilities Support Contract and the Army recognized a 20 percent cost savings over the life of

the contract. (AR1470).

C. Melwood’s Base Operations Support Services Contract at Fort Meade

Melwood is a not-for-profit organization which employs persons who are blind or

otherwise severely disabled. (See Pl.’s MJAR at 4; Compl. at 1). In May 2011, Melwood was

added to the Procurement List as a qualified NPA contractor. (AR2). Melwood was enlisted to

provide Base Operation Support Services for multiple buildings at Fort Meade, an Army

installation in Maryland that is home to approximately 55,000 military and civilian personnel.

(See AR137). These support services include facilities maintenance, refuse removal,

groundskeeping, snow and ice removal, and other similar services. (AR91–108).

In recognition of saved costs and other benefits from the first Pilot Program procurement

at Fort Bliss, the Army requested that AbilityOne conduct a second iteration of its Pilot Program

for the Base Operations Support Services Contract (“BOSS Contract”) at Fort Meade. (AR1471).

Melwood’s Fort Meade contract was set to expire at the end of June 2020 but given several

options to extend the contract. (AR342, 354). The Army had undertaken an Independent

Estimate for pricing of the Fort Meade contract on December 11, 2019. (AR334). This estimate

showed a base year total cost of $26,062,290.04 and a five-year total cost of $136,521,931.90.

(AR334, 339). On December 19, 2019, AbilityOne responded to the Army’s interest via email,

stating that it would be “happy to work with” the Army on a second Pilot Program procurement.

(AR341).

On May 12, 2020, the Army published a press release announcing Fort Meade had been

selected for the second iteration of the Pilot Program. (AR347). Several days later, AbilityOne

notified Melwood of this press release by email. (AR347). On May 28, 2020, the Executive

Director of AbilityOne signed a Memorandum of Agreement formalizing the decision to initiate

the Pilot Program at Fort Meade. (AR358–61).

On June 23, 2020, Melwood filed a pre-solicitation, pre-award bid protest challenge,

seeking to “prevent the issuance of the Opportunity Notice and/or RFP” and to “challenge . . .

the Government’s intent to compete the Fort Meade Base Operations contract.” (Compl. at 1)

(emphasis added). Melwood also moved for a temporary restraining order, alleging it would

suffer irreparable reputational harm should the United States be permitted to proceed with the

solicitation. (See Order on TRO, ECF No. 11). On June 26, 2020, the Court denied Melwood’s

request. (Id.). On July 14, 2020, AbilityOne formally authorized the Pilot Program procurement

process for the BOSS Contract at Fort Meade and directed SourceAmerica to post the

opportunity notice. (AR1468–74). SourceAmerica then posted the opportunity notice on July 15,

2020. (See AR1543).

5

II. Analysis

Melwood’s Complaint challenges the procurement at Fort Meade on three grounds. First,

Melwood alleges that “the Commission has violated FAR 8.705-4 by improperly canceling the

Fort Meade [BOSS] contract with Melwood.” (Compl. at 9). Second, Melwood argues that

AbilityOne’s “source selection plan for the Fort Meade [BOSS] re-procurement violates 41

U.S.C. § 8503, FAR 8.707, FAR 6.302-5(b)(2), and 41 C.F.R. § 51-2.7 as [it] relinquishes

[AbilityOne’s] responsibility to establish a fair market price to a competition between the

nonprofit agencies, which is specifically prohibited.” (Compl. at 10). Third, Melwood alleges a

violation of the Administrative Procedures Act, 5 U.S.C. § 701–706, and seeks a declaratory

judgment that “the Section 898 Panel’s pilot program and the selection of the Fort Meade

[BOSS] contract’s participation in that program is arbitrary, capricious, an abuse of discretion,

and otherwise in violation of law.” (Compl. at 10–11).

Each party has moved for judgment on the administrative record with respect to these

challenges. The United States has also moved to dismiss Melwood’s Complaint on various

jurisdictional grounds. (See generally, Def.’s Mot.) (seeking dismissal for want of subject matter

jurisdiction, for being unripe, and for failure to state a claim). Because jurisdiction is a threshold

issue, see Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94–95 (1998), the Court will

address these arguments first before turning to the remaining challenges.

A. Legal Standards

i. Bid Protests

The Tucker Act grants the United States Court of Federal Claims jurisdiction over bid

protests brought by “an interested party objecting to a solicitation by a Federal agency for bids or

proposals for a proposed contract or to a proposed award or the award of a contract or any

alleged violation of statute or regulation in connection with a procurement or a proposed

procurement.” 28 U.S.C. § 1491(b)(1). In bid protest cases, this Court reviews agency actions

under the Administrative Procedure Act’s “arbitrary and capricious” standard. See 28 U.S.C. §

1491(b)(4). Under this standard, an “award may be set aside if either (1) the procurement

official’s decision lacked a rational basis; or (2) the procurement procedure involved a violation

of regulation or procedure.” Impresa Construzioni Geom. Domenico Garufi v. United States, 238

F.3d 1324, 1332 (Fed. Cir. 2001).

In this regard, the United States Court of Appeals for the Federal Circuit has explained

that: “when a challenge is brought on the first ground, the test is ‘whether the contracting agency

provided a coherent and reasonable explanation of its exercise of discretion, and the disappointed

bidder bears a “heavy burden” of showing that the award decision had no rational basis.’” Id. at

1332–33. “When a challenge is brought on the second ground, the disappointed bidder must

show a clear and prejudicial violation of applicable statutes or regulations.” Id. at 1333. In

addition, when reviewing an agency’s procurement decision, the Court should recognize that the

agency’s decision is entitled to a “presumption of regularity.” Citizens to Preserve Overton Park,

Inc. v. Volpe, 401 U.S. 402, 415 (1971), overruled on other grounds by Califano v. Sanders, 430

U.S. 99 (1977). “The [C]ourt should not substitute its judgment for that of a procuring agency.”

Cincom Sys., Inc. v. United States, 37 Fed. Cl. 663, 672 (1997). And so, “[t]he protestor must

6

show, by a preponderance of the evidence, that the agency’s actions were either without a

reasonable basis or in violation of applicable procurement law.” Info. Tech. & Applics. Corp. v.

United States, 51 Fed. Cl. 340, 346 (2001), aff’d, 316 F.3d 1312 (Fed. Cir. 2003) (citation

omitted).

The Court’s standard of review “is highly deferential.” Advanced Data Concepts, Inc. v.

United States, 216 F.3d 1054, 1058 (Fed. Cir. 2000). As long as there is “a reasonable basis for

the agency’s action, the court should stay its hand even though it might, as an original

proposition, have reached a different conclusion.” Honeywell, Inc. v. United States, 870 F.2d

644, 648 (Fed. Cir. 1989) (quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C.

Cir. 1971)). But, if “the agency ‘entirely fail[s] to consider an important aspect of the problem

[or] offer[s] an explanation for its decision that runs counter to the evidence before the agency,’”

then the resulting action lacks a rational basis and, therefore, is defined as “arbitrary and

capricious.” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375 (Fed.

Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co., 463 U.S. 29, 43

(1983)).

ii. Motion to Dismiss

To survive a Motion to Dismiss under RCFC 12(b)(1), the Complaint must “allege

sufficient facts to establish the court’s jurisdiction,” the basis of which must be “affirmatively

and distinctly set forth.” DaimlerChrysler Corp. v. United States, 442 F.3d 1313, 1318–19 (Fed.

Cir. 2006). The burden of establishing subject matter jurisdiction rests with the plaintiff, who

must do so by a preponderance of the evidence. Lujan v. Defenders of Wildlife, 504 U.S. 555,

561 (1992); Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988). This

Court’s jurisdiction to entertain claims and grant relief depends on the extent to which the United

States has waived sovereign immunity. United States v. Testan, 424 U.S. 392, 399 (1976). When

faced with a motion to dismiss for lack of subject matter jurisdiction pursuant to the RCFC Rule

12(b)(1), the Court must assume that all undisputed facts alleged in the complaint are true and

draw all reasonable inferences in the plaintiff’s favor. Scheuer v. Rhodes, 416 U.S. 232, 236

(1974); see also Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995). The movant,

however, may challenge the truth of any facts upon which jurisdiction depends. See Raymark

Indus. v. United States, 15 Cl. Ct. 334, 338 (1988). If it does, the plaintiff must come forward

with prima facie showing of jurisdiction. Id. The plaintiff cannot rely only on its allegations. See

Hornback v. United States, 52 Fed. Cl. 374, 377 (2002).

Moreover, the Court may look to evidence outside of the pleadings in order to ascertain

the propriety of its exercise of jurisdiction over a case. Rocovich v. United States, 933 F.2d 991,

994 (Fed. Cir. 1991), aff’d in relevant part, Martinez v. United States, 281 F.3d 1376 (Fed. Cir.

2002). In that vein, a Court may refrain from exercising its jurisdiction over a claim that is not

yet ripe. Suitum v. Tahoe Reg’l Planning Agency, 520 U.S. 725 (1997); Reno v. Catholic Soc.

Servs., Inc., 509 U.S. 43, 58 n.18 (1993) (“We have noted that ripeness doctrine is drawn both

from Article III limitations on judicial power and from prudential reasons for refusing to exercise

jurisdiction.”). Thus, dismissal of an unripe claim is most appropriate under RCFC 12(b)(1). If

the Court determines at any time that subject matter jurisdiction is lacking, it must dismiss the

complaint. See RCFC 12(h)(3).

7

B. Count I Must be Dismissed Under RCFC 12(b)(1) for Lack of Subject Matter

Jurisdiction

Count I of Melwood’s Complaint alleges that “the Commission has violated FAR 8.705-4

by improperly canceling the Fort Meade Base Operations Support Services contract with

Melwood.” (Compl. at 9). The United States’ Cross-Motion and Motion to Dismiss argues that

Count I “involves a dispute arising out of the contract between the parties, and therefore must be

brought under the Contract Disputes Act (CDA)—not under the Court’s bid protest jurisdiction.”

(Def.’s Mot. at 14) (internal citations and alterations omitted). Consequently, the United States

argues, Count I must be dismissed for either lack of subject matter jurisdiction under RCFC

12(b)(1) or for failure to state a claim under RCFC 12(b)(6). (Def.’s Mot. at 14). The Court

agrees that, under its bid protest jurisdiction, it lacks subject matter jurisdiction to adjudicate

what is essentially a wrongful termination of contract claim, and thus dismissal under RCFC

12(b)(1) is appropriate.

Melwood maintains that its claim “is a proper pre-award protest – not a [CDA] claim.”

(Pl.’s Opp. at 9). Melwood argues that “once a party objects to a procurement, [28 U.S.C.]

section 1491(b)(1) provides a broad grant of jurisdiction[.]” (Id. (citing 41 U.S.C. § 111, which

defines “procurement” as “all stages of the process of acquiring property or services, beginning

with the process for determining a need for property or services and ending with contract

completion and closeout.”)). Melwood has indeed brought its claims under 28 U.S.C. § 1491(b)

(bid protest jurisdiction) and 5 U.S.C. § 702 (judicial review under the APA). (See Compl. at 2).

However, Count I concerns the improper cancellation of a contract, which is inherently a

contract administration challenge that must be brought under the Contract Disputes Act.

Melwood cannot attempt to reframe this contract administration challenge as a bid protest

through its briefs.

“When a plaintiff’s claim involves a breach of a contract with the Government before the

expiration of the contract, the court cannot hear the claim as a bid protest because ‘28 U.S.C. §

1491(b) provides no jurisdiction for claims of wrongful termination or breach.’” Gonzalez-

McCaulley Inv. Grp., Inc. v. United States, 93 Fed. Cl. 710, 716 (2010) (quoting The Ravens

Group v. United States, 78 Fed. Cl. 390, 398 (2007)). “[C]laims related to the ongoing

administration and management of a government contract, including claims for breach of

contract or termination, must be pursued under the CDA, not under the court’s bid protest

jurisdiction.” Diversified Maint. Sys., Inc. v. United States, 103 Fed. Cl. 431, 436 (2012) (citing

Cecile Indus., Inc. v. Cheney, 995 F.2d 1052, 1055 (Fed. Cir. 1993) (“The CDA exclusively

governs Government contracts and Government contract disputes.”)) (citation omitted); Dalton

v. Sherwood Van Lines, 50 F.3d 1014, 1017 (Fed. Cir. 1995) (“When the Contract Disputes Act

applies, it provides the exclusive mechanism for dispute resolution”); see also Frazier v. United

States, 79 Fed. Cl. 148, 160 (2007) (“[P]ure contract claims are not appropriate in a bid protest,

even if clothed in the guise of a protest of an alleged statutory violation occurring in relation to a

procurement.”), aff’d, 301 Fed. Appx. 974 (Fed. Cir. 2008); Ravens Grp., Inc., 78 Fed. Cl. at 398

(noting that section 1491(b) provides no jurisdiction for claims of wrongful termination or

breach). Furthermore, the Court of Federal Claims’ CDA jurisdiction “requires both a valid

claim and a contracting officer’s final decision on that claim.” M. Maropakis Carpentry, Inc. v.

United States, 609 F.3d 1323, 1327 (Fed. Cir. 2010) (citing James M. Ellett Constr. Co. v.

United States, 93 F.3d 1537, 1541–42 (Fed. Cir. 1996)).

8

Melwood’s Complaint, on its face, alleges cancellation of a contract before its expiration,

thus it is a contract administration challenge that must be brought under the CDA, not the

Court’s bid protest jurisdiction. (See Compl. at 8, 9). Moreover, Melwood has not alleged its

claim satisfies the prerequisites for a CDA claim and concedes that “the grounds for a CDA

claim are not before the Court.” (Pl.’s Opp. at 9 n.2, ECF No. 44). Thus, dismissal of Count I

under RCFC 12(b)(1) for lack of subject matter jurisdiction is proper.

C. Count II Must Be Dismissed Under RCFC 12(b)(1) Because it Does Not

Challenge a “Final Agency Action” and is Therefore Unripe

The United States asserts that Melwood does not challenge a final agency action, but

rather an inchoate decision by AbilityOne—the “intent to [re]compete the Fort Meade” BOSS

Contract—therefore its entire Complaint is unripe and must be dismissed. (Def.’s Mot. at 8; see

also Compl. at ¶¶ 1, 6, 43, 49). Melwood responds that the May 2020 email from AbilityOne

stating the intent to recompete the BOSS Contract at Fort Meade evidences the consummation of

the agency decision-making process. (Pl.’s Opp. at 6). Additionally, Melwood argues that even if

its challenge was not ripe when the Complaint was filed, AbilityOne has now issued a formal

decision which constitutes final agency action, and thus the Court should find that its challenge

has ripened. (Id. at 8).

The Court agrees that Melwood brought this challenge too early, before a final agency

action was taken, and crucially, has not attempted to cure this defect with an amended

complaint. 5 However, because the Court finds Counts I and III are more appropriately dismissed

on other grounds, its holding that Melwood’s claim is unripe applies only to Count II.

For an action to be “ripe,” the protestor must establish “both the fitness of the issues for

judicial decision and the hardship to the parties of withholding court consideration.” Abbott

Labs. v. Gardner, 387 U.S. 136, 149 (1967); see also Caraco Pharm. Labs., Ltd. v. Forest Labs.,

Inc., 527 F.3d 1278, 1294–95 (Fed. Cir. 2008); Tex. v. United States, 134 Fed. Cl. 8, 17 (2017)

(“It is protestor’s burden to establish ripeness.”). “[A]n action is fit for judicial review where

further factual development would not ‘significantly advance [a court’s] ability to deal with the

legal issues presented.’” Caraco Pharm. Labs., 527 F.3d at 1295. (quoting Nat’l Park Hospitality

Ass’n v. Dep’t of Interior, 538 U.S. 803, 812 (2003)). Hardship to the parties may be present

where “the complained-of conduct has an ‘immediate and substantial impact’ on the plaintiff.”

Id. (quoting Gardner v. Toilet Goods Ass’n, 387 U.S. 167, 171 (1967)).

5

The Court passes no judgment on whether an amended complaint would have ripened this case.

Melwood has repeatedly maintained that this challenge is to the agency’s intent recompete the

Fort Meade BOSS Contract, not a challenge to the solicitation itself. During Oral Argument on

Melwood’s Motion to Supplement the Administrative Record, Melwood affirmed that only

“Count III of our complaint actually challenges the decision itself to include . . . Fort Meade as

part of the Pilot Program.” (Tr. of OA on Mot. to Suppl. at 12:1–8, ECF No. 39). In fact, the

Court specifically pointed out that this “seems to be . . . a challenge to the decision to

contemplate recompeting the Fort Meade contract rather than the actual decision to recompete

the contract.” (Id. at 8:7–12).

9

However, before examining whether Melwood’s claim satisfies both elements of being

“ripe,” the Court must first address the parties’ contradicting assertions about when ripeness

should be determined.

i. Ripeness is Evaluated at the Time the Complaint is Filed

Melwood argues that even if it was not ripe when filed, its claim is “unquestionably” ripe

now. (Pl.’s Opp. at 8). However, this argument misunderstands and misapplies the ripeness

doctrine. The Court agrees with the United States that accepting such an argument would defeat

the purpose of the doctrine, which is “to prevent the courts, through avoidance of premature

adjudication, from entangling themselves in abstract disagreements over administrative policies,

and also to protect the agencies from judicial interference until an administrative decision has

been formalized and its effects felt in a concrete way by the challenging parties.” Sys.

Application & Techs., Inc. v. United States, 691 F.3d 1374, 1383 (Fed. Cir. 2012) (internal

citations and quotations omitted).

Ripeness, for the purposes of a trial court’s jurisdiction, must be evaluated when the

Complaint is filed. Arrowhead Indus. Water, Inc. v. Ecolochem, Inc., 846 F.2d 731, 734 n.2 (Fed.

Cir. 1988). “The presence or absence of jurisdiction must be determined on the facts existing at

the time the complaint under consideration was filed.” Id. (citing Jervis B. Webb Co. v. Southern

Sys., Inc., 742 F.2d 1388, 1398 (Fed. Cir. 1984) (“[A] case or controversy must exist as of the

date of the filing of the declaratory judgment action”)). “[S]ubject matter jurisdictional facts

must be pleaded, and proved when challenged, and . . . later events may not create jurisdiction

where none existed at the time of filing.” Spectronics Corp. v. H.B. Fuller Co., 940 F.2d 631,

635 (Fed. Cir. 1991).

However, Melwood points to two cases in which the Supreme Court suggested that

ripeness may be evaluated on a “rolling basis.” (Pl.’s Opp. at 8). However, these decisions apply

to the prudentialism of appellate courts reviewing events that occurred after a lower court’s

decision. 6

In Blanchette v. Connecticut Gen. Ins. Corps., 419 U.S. 102, 137 (1974), the Supreme

Court considered the “conveyance taking” of land for rail use under the Rail Act and the Fifth

Amendment. 7 At the trial court below, the District Court determined that review of the issues

would be premature since the challenged conveyance decision required several further steps

6

Melwood relies on a third case, from another Judge on the Court of Federal Claims, in making

its argument. That case, CBY Design Builders v. United States, 105 Fed. Cl. 303, 329 n.20

(2012), stated in dicta that “jurisdictional questions of ripeness are not based on the state of

affairs at the time of filing, as subsequent events may make a matter ripe.” (citing Blanchette and

Buckley). However, that case had no need to grapple with the prudential concerns of the ripeness

doctrine as it primarily addressed mootness, but in any event, is not binding precedent on this

Court.

7

Blanchette is often alternatively cited as Regional Rail Reorganization Act Cases, 419 U.S. 102

(1974).

10

before it would constitute a “final” action. Id. at 138 (“The District Court’s holding of

prematurity was influenced by the statutory scheme that requires several decisional steps before

the final conveyance.”). However, soon after the District Court’s decision, those “decisional

steps” were completed. Id. at 139 (“subsequent to the District Court’s opinion, the Penn Central

Reorganization Court determined that the Rail Act did not provide a process that would be fair

and equitable to the estate[.]”). The Supreme Court decided that, for prudential reasons, even

though the issues may have been unripe for the district court, a remand would be wasteful and

unnecessary since the issues had since matured. Id. at 140 n.25 (“It might be appropriate under

different circumstances only to decide that the issues are ripe, and to remand to the District Court

for their determination on the merits. However, such a remand here would be both undesirable

and unnecessary.”).

In Buckley v. Valeo, 424 U.S. 1 (1976), the Supreme Court considered the

constitutionality of several provisions of the Federal Election Campaign Act of 1971, as well as

not-yet-final rulings and determinations by the Federal Election Commission. After the Court of

Appeals for the D.C. Circuit issued its decision, the Federal Election Commission promulgated

several rules and regulations under the authority of that Act. Id. at 115–16. Again, for prudential

reasons, the Supreme Court determined that it should consider these new regulations on appeal,

despite not being presented to the courts below. Id. at 117. (holding that the Supreme Court was

“warranted in considering all . . . aspects of the Commission’s authority which have been

presented by the certified questions.”).

Blanchette and Buckley are an exception, not the rule, to the ripeness doctrine. Nothing in

this case warrants a departure from the Federal Circuit’s ripeness jurisprudence which dictates

that “[t]he presence or absence of jurisdiction must be determined on the facts existing at the

time the complaint under consideration was filed.” Arrowhead Indus. Water, Inc., 846 F.2d at

734 n.2. Thus, the Court must assess the ripeness of Melwood’s claims from the time the

Complaint was filed on June 23, 2020, prior to AbilityOne’s formal authorization of the Pilot

Program.

ii. The Inchoate Procurement Decision Melwood Challenges Does Not

Satisfy the “Fitness” Prong

“When a party challenges government action, the [fitness] factor becomes a question of

whether the challenged conduct constitutes a final agency action.” Sys. Application & Techs.,

Inc., 691 F.3d 1374, 1384 (Fed. Cir. 2012) (citing Tokyo Kikai Seisakusho, Ltd. v. United States,

529 F.3d 1352, 1363 (Fed. Cir. 2008) and U.S. Ass’n of Imps. of Textiles & Apparel v. U.S. Dep’t

of Commerce, 413 F.3d 1344, 1349–50 (Fed. Cir. 2005)). “Final agency action hinges on two

points: ‘First, the action must mark the “consummation” of the agency’s decision-making

process—it must not be of a merely tentative or interlocutory nature. And second, the action

must be one by which “rights or obligations have been determined,” or from which “legal

consequences will flow.”’” Sys. Application & Techs., Inc., 691 F.3d at 1384 (quoting Bennett v.

Spear, 520 U.S. 154, 177–78 (1997) (citations omitted)).

The United States alleges that “final agency action” in this case occurred when the

AbilityOne Commission took a formal written vote on July 14, 2020, authorizing the

Commission to initiate the competitive process among qualified nonprofit agencies. (Def.’s Mot.

11

at 10; AR1469, 1473). Melwood alleges that final agency action was taken when AbilityOne

communicated the Army’s intent to select Fort Meade for the competition pilot. (Pl.’s Opp. at 6–

7). Melwood frames the final agency action as the informal decision not to continue the contract

with Melwood as the provider of Base Operations Support Services at Fort Meade. (Id.) (“No

further documentation was necessary to establish the agency’s final decision.”).

The Court agrees with the United States that “final agency action” occurred when the

formal written vote was taken and that Count II challenges agency action before a final agency

decision. At any point, up until AbilityOne took a formal vote to authorize the Pilot Program,

“[t]he Government could have changed its mind and decided not to proceed with the competition

pilot, and the Commission could have voted to deny authorization for it to move forward.” (See

Def.’s Mot. at 10). Only when the decision was final, and the parties were assured that the Pilot

Program would proceed, could “legal consequences flow.” As previously stated, Melwood filed

its Complaint on June 23, 2020, and a final vote did not occur until several weeks later. Melwood

has not sought leave to amend its Complaint to challenge this vote, which the United States has

conceded would constitute “final agency action.” (See id.). Therefore, Melwood fails to

challenge a “final agency action” necessary to satisfy the “fitness” prong of the ripeness inquiry.

iii. Melwood Has Not Asserted it Will Suffer “Hardship” Without Review

and Thus Has Conceded That Issue

To be “ripe,” a plaintiff’s claim must also satisfy the second prong by demonstrating a

“hardship” that would be presented if the Court withheld consideration of the issues. Thus,

Melwood must be able to show it has suffered an “immediate and substantial impact” stemming

from the Government’s conduct. Caraco Pharm. Labs., 527 F.3d at 1295 (quoting Gardner, 387

U.S. at 171). “A claim is not ripe for adjudication if it rests upon ‘contingent future events that

may not occur as anticipated, or indeed may not occur at all.’” Texas v. United States, 523 U.S.

296, 300 (1998) (quoting Thomas v. Union Carbide Agricultural Products Co., 473 U.S. 568,

580–581 (1985)).

Even if it could satisfy the “fitness” prong, Melwood has not demonstrated, or even

offered an argument, that it will suffer “hardship” in response to the United States’ Motion to

Dismiss. (See Pl.’s Opp. at 5–8 (discussing the point of litigation at which ripeness is

determined, and the fitness of the issues, but omitting discussion of hardship to Melwood)); see

also United States v. Dunkel, 927 F.2d 955, 956 (7th Cir. 1991) (“Judges are not like pigs,

hunting for truffles buried in briefs.”).

In any event, failure to respond to the United States’ ripeness arguments on the merits can

be construed as a concession of the issue. Cardiosom, LLC v. United States, 91 Fed. Cl. 659, 664

(2010), rev’d sub nom., Cardiosom, L.L.C. v. United States, 656 F.3d 1322 (Fed. Cir. 2011)

(“[B]y failing to respond to Defendant’s argument regarding the jurisdictional defect of the . . .

claim, Plaintiff has effectively conceded the issue.”); Philadelphia Auth. for Indus. Dev. v.

United States, 114 Fed. Cl. 519, 527 (2014) (Sweeney, J.) (construing plaintiff’s silence on the

merits of defendant’s arguments as waiver); Winnemucca Indian Colony v. United States, No.

13-874, 2014 WL 3107445, at *4 (Fed. Cl. July 8, 2014) (Firestone, J.) (“[P]laintiffs have not

responded to these arguments. As such, they are deemed conceded”).

12

Because Melwood has not identified any hardship it would suffer if the Court declines to

review this unconventional, pre-solicitation challenge, the Court construes that silence as a

concession that Melwood will suffer no hardship. Therefore, even if Melwood’s claims in Count

II were “fit” for judicial review, which they are not, Melwood cannot demonstrate a hardship

necessary to establish ripeness of the issues for judicial review. Because Count II is unripe, the

Court lacks jurisdiction to hear it. See Morris v. United States, 392 F.3d 1372 (Fed. Cir. 2004)

(explaining that a Court “does not have jurisdiction over claims that are not ripe”); RCFC 12(h)

(“If the court determines at any time that it lacks subject-matter jurisdiction, the court must

dismiss the action”). Consequently, the Court dismisses Count II without prejudice under RCFC

12(b)(1) for lack of jurisdiction. Shinnecock Indian Nation v. United States, 782 F.3d 1345, 1350

(Fed. Cir. 2015) (“If a claim is not yet ripe for judicial review, it should generally be dismissed

without prejudice.”).

D. The Court Lacks Subject Matter Jurisdiction Over the Administrative Procedures

Act, Thus Count III Should be Transferred to the U.S. District Court for the

District of Maryland

Count III of Melwood’s Complaint alleges a violation of the Administrative Procedures

Act (“APA”), 5 U.S.C. § 701–706, and seeks a declaratory judgment that “the Section 898

Panel’s pilot program and the selection of the Fort Meade BOS contract’s participation in that

program is arbitrary, capricious, an abuse of discretion, and otherwise in violation of law.”

(Compl. at 10–11).

The United States has moved for dismissal of this claim under RCFC 12(b)(1), asserting

that the Court of Federal Claims lacks subject matter jurisdiction to hear APA claims. (Def.’s

Mot. at 15 (citing Lion Raisins, Inc. v. United States, 416 F.3d 1356, 1370 n.11 (Fed. Cir. 2005)

(“Of course, no APA review is available in the Court of Federal Claims.”))). This is

unquestionably correct. See, e.g., Crocker v. United States, 125 F.3d 1475, 1476 (Fed. Cir. 1997)

(holding that the Court of Federal Claims lacked general federal question jurisdiction to review

the propriety of agency action under the Administrative Procedure Act, 5 U.S.C. §§ 701–706

(2000)).

Melwood, in its Reply brief, recognizes this defect and now seeks transfer to the U.S.

District Court for the District of Maryland. (Pl.’s Opp. at 11). Transfer may be effected under 28

U.S.C. § 1631 to cure a lack of jurisdiction if transfer “is in the interest of justice,” and the

destination court is one “in which the action . . . could have been brought at the time it was filed

or noticed[.]” Melwood argues that transfer is “in the interest of justice” because its “claims are

nonfrivolous and should be decided on the merits.” (Pl.’s Opp. at 12 (citing Galloway Farms,

Inc. v. United States, 834 F.2d 998 (Fed. Cir. 1987) (“The phrase ‘if it is in the interest of justice’

relates to claims which are nonfrivolous and as such should be decided on the merits.”))).

Melwood asserts that the District of Maryland is the proper venue under 28 U.S.C. § 1391(e)

because it is where “a substantial part of the events or omissions giving rise to the claim

occurred” or where “the plaintiff resides[.]” (See Pl.’s Opp. at 12). Of course, the BOSS Contract

was performed in Maryland, where Fort Meade is located, and alternatively, Melwood’s

principal place of business in Maryland. (Compl. at 2, 7). Therefore, the District of Maryland

would indeed be the proper venue.

13

The United States opposes transfer. (Def.’s Reply at 6, ECF No. 48). The basis of the

United States’ objection is that this claim is brought “in connection with a procurement or a

proposed procurement[.]” (Id. at 6–7 (citing § 1491(b)(1))). The United States argues that “the

Administrative Dispute Resolution Act of 1996 (ADRA) ‘terminated federal district court

jurisdiction over bid protests[.]’” (Id. at 7 (quoting Emery Worldwide Airlines, Inc. v. United

States, 264 F.3d 1071, 1079 (Fed. Cir. 2001))). “Congress intended the 1491(b)(1) jurisdiction to

be exclusive where 1491(b)(1) provided a remedy (in procurement cases).” Res. Conservation

Grp., LLC v. United States, 597 F.3d 1238, 1246 (Fed. Cir. 2010).

Although Count III invokes § 1491(b)(1), the thrust of Melwood’s challenge is that the

implementation of the Pilot Program as a whole is a violation of the Administrative Procedures

Act. (Compl. at 10). The U.S. District Court for the District of Maryland is better suited to

address whether this challenge was one which Congress intended to remove from the jurisdiction

of the federal district courts, and evaluate the claim’s merits. On its face, Count III is a

nonfrivolous claim that should be decided on the merits by a court with proper jurisdiction and

venue. Accordingly, the Court transfers Count III to the U.S. District Court for the District of

Maryland.

E. Melwood’s and the United States’ Motions for Judgment on the Administrative

Record are Denied as Moot

As explained above, this Court does not possess jurisdiction over Melwood’s claims for

various reasons. As such, this Court does not review the Administrative Record to determine

whether AbilityOne acted arbitrarily and capriciously, abused its discretion, or violated the law

with various aspects of the Pilot Program. However, like the District Court for the Eastern

District of California, which reviewed the first iteration of the 898 Panel’s Pilot Program, the

Court has grave concerns about the legality of the Pilot Program and AbilityOne’s execution of

it. See Pride Indus., 420 F. Supp. 3d at 1046 n.4 (noting that the Pilot Program “appears to

significantly modify if not abandon statutorily prescribed pricing and allocation processes.”).

The Court’s concerns are threefold.

First, Melwood raises a novel question of whether the program itself violates the JWOD

or is authorized by the NDAA. The JWOD establishes a “uniquely tailored statutory scheme for

providing government services contracts to the blind or severely disabled.” Id. The 898 Panel

and AbilityOne have, at best, ambiguous authority to implement new procurement procedures

that widely diverge from those explicitly outlined in JWOD. A plain reading of the NDAA

indicates that the 898 Panel is only authorized to provide recommendations, not implement new

procedures for AbilityOne procurements. NDAA § 898(c)(2)–(7). Subsection (e) circumscribes

the “authority” of the 898 Panel:

To carry out the duties described in subsection (c), the Panel may request

documentation or other information needed from the AbilityOne

Commission, central nonprofit agencies, and qualified nonprofit agencies.

NDAA § 898(e). All that is granted, under a plain reading of the text, is the power to collect

information in order to take the actions contemplated by subsection (c). Notably, seven of the

eight delineated “duties” of the 898 Panel, as defined in subsection (c), begin with “recommend

14

actions,” “recommend changes,” “recommend ways,” “recommend criteria,” or “review the

status” of the program. NDAA § 898(c)(1)–(7). The eighth duty would require a determination

by the Secretary of Defense, not simply the initiative of AbilityOne or a “contracting activity,”

such as the Army. The Court believes it is possible, or even likely, that the intended end goal of

the 898 Panel’s authority was to report to Congress and make recommendations on how to

change the governing statutes and regulations, rather than implement a Pilot Program that largely

disregards the procurement procedures of the JWOD and Title 41 C.F.R. Chapter 51.

Second, the Pilot Program seems to hinge on the addition of a price component, and the

two iterations so far have championed the Pilot Program’s cost-savings. The Court is skeptical of

whether the 898 Panel or AbilityOne may lawfully conduct a program that ignores, or runs

directly counter to, the policy goals outlined by JWOD, and the procurement procedures with

regard to price extensively detailed in 41 C.F.R. 51. While competition on price may not be

specifically prohibited, JWOD makes clear its preference for evaluation on other components of

a bid, and the detailed procurement scheme for arriving at an AbilityOne contract’s price

indicates bids should not contain a price component. There are specific policy reasons for these

procedures clearly delineated by the statute—providing employment for the blind and severely

disabled. It is unclear whether Congress intended to permit AbilityOne to drastically modify the

procurement procedures which encapsulate these policy prescriptions without a clear directive

that the addition of a price component is permissible.

Third, the Court is troubled by the Army’s ad hoc, back-of-the-napkin math relied upon

to determine that a resolicitation at Fort Meade could accomplish its legally dubious price-

slashing goals. With its Opposition to Melwood’s Motion for Temporary Restraining Order, the

United States attached a Declaration that estimated “that the fair market price for this acquisition

will be approximately 33% less than the current contract price. In monetary terms, the projected

savings [from implementing the Pilot Program at Fort Meade] will be approximately $2.6 - 3M

per year.” (J. Randall Robinson Decl. at ¶ 8, ECF No. 9-1). Later, the United States submitted a

Corrected Declaration, this time stating “We anticipate that the fair market price for this

acquisition will be approximately 11 % less than the current contract price. In monetary terms,

the projected savings will be approximately $2.2 - $2.9M per year.” (Corr. J. Randall Robinson

Decl. at ¶ 8). Melwood sought production of any other documents that would support a more

fulsome analysis of the cost-savings by the Army, but the United States assured the Court that

such analysis does not exist. (Tr. of OA on Mot. to Suppl. at 21:6–16 (stating that the cost-

savings analysis “was a pretty simple arithmetic calculation.”)). The Army apparently was not

prompted to conduct any detailed analysis as to the differences in sizes of the facility where the

contract would be performed, or the relative performance efficiency of the incumbent

contractors. In response to a question from the Court, the United States provided the following

summary of the Army’s comparative cost-savings analysis as it was listed in the first “erroneous”

declaration:

My understanding, Your Honor, is that the Army miscalculated – did the

wrong math as it were. That rather than looking at the cost savings and

applying that 11 percent figure, they took the estimated size of Fort Bliss

versus the estimated size of Fort Meade, the one fort being a smaller contract

than the other, and we’re essentially comparing apples to oranges and said,

15

geez, if the contract is a third the size, or a third less in size, the price should

be a third less in size as well.

(Id. at 22:20–25, 23:1–4). The Army apparently arrived at the 11 percent figure, the figure from

the “Corrected Declaration,” much the same way, without regard to disparities in efficiency of

the incumbent contractor’s performance:

In performing the estimate with the 11 percent cost savings, the Army looked

at what the price under the old contract at Fort Bliss was and the annual price

under the new contract at Fort Bliss and did simple arithmetic to realize an

11 percent cost savings. And that, in Mr. Robinson’s declaration, the 11

percent cost construction was applied to the new estimated value of the new

contract. Again, simple arithmetic yielded the cost range that was arrived at.

(Id. at 21:6–16). However, the Army’s own independent estimate contradicts whether it would

actually save costs from recompeting the BOSS Contract at Fort Meade. The Army’s

Independent Estimate for pricing of the Fort Meade contract showed a base year total cost of

$26,062,290.04 and a five-year total cost of $136,521,931.90. (AR334, 339). Melwood asserts

that it had performed the BOSS Contract at approximately $20.8 million in the previous contract

year (2019–2020). (Pl.’s MJAR at 5–6). By the Army’s own independent estimate, recompetition

of the BOSS Contract could actually lead to a contract price increase of $5.2 million in the base

year. This discrepancy highlights, and calls into question, the efficacy of the Army’s primary

stated goal for the Pilot Program: cost savings.

The United States argues that “no ‘statutory or regulatory provision . . . precludes’” the

Pilot Program’s inclusion of a price component. (Def.’s Reply at 12; see also Def.’s Mot. at 22–

23). In the alternative, the United States would place its reliance on a favorable standard of

review, arguing that even if the competition Pilot Program is contrary to the JWOD, it does not

present either a “clear” or “prejudicial” violation of the law and thus must be upheld. (See Def.’s

Mot. at 24). Perhaps the United States is correct, but this is no way to run a railroad. The Court

tends to agree with its peer, the District Court for Eastern District of California, in observing that

the United States’ arguments “appear to oversimplify and ignore the statutory scheme Congress

designed to distance price from the decision process to encourage government hiring of blind and

severely disabled people.” Pride Indus., 420 F. Supp. 3d at 1046 n.4 (citing 41 U.S.C. §

3304(a)(5) and F.A.R. 6.302-5(b)(2)).

Twice now courts have dismissed challenges to this Pilot Program as unripe. The APA

challenge from Pride Industries was unripe when brought prior to final contact award. Pride

Indus., 420 F. Supp. 3d at 1045. This Court has now found that Melwood’s challenge under 28

U.S.C. § 1491(b)(1) is unripe because it was brought prior to a formal vote to issue the

solicitation, and thus there is no final agency action to review. Despite the Court’s concerns, it

must reserve judgment for a claim that properly presents the issues for the Court’s review. In

light of its holding that the Court lacks jurisdiction, both Melwood’s and the United States’

Motions for Judgment on the Administrative Record are denied as moot.

III. Conclusion

16

The Court does not possess subject matter jurisdiction over Melwood’s Complaint.

Because it does not possess subject matter jurisdiction, it cannot issue a decision on the merits of

the parties’ motions for judgment on the administrative record. Accordingly, the Court orders the

following:

1. The United States’ Motion to Dismiss, (ECF No. 42) is GRANTED.

2. Melwood’s Motion for Judgment on the Administrative Record, (ECF No. 34), is

DENIED AS MOOT.

3. The United States’ Motion for Judgment on the Administrative Record, (ECF No.

42), is DENIED AS MOOT.

4. Count I of Melwood’s Complaint shall be DISMISSED without prejudice.

5. Count II of Melwood’s Complaint shall be DISMISSED without prejudice.

6. Count III of Melwood’s Complaint shall be TRANSFERRED to the United

States District Court for the District of Maryland.

7. No costs or fees shall be awarded.

8. The parties are DIRECTED to submit their proposed redactions no later than

December 7, 2020.

IT IS SO ORDERED.

s/ David A. Tapp

DAVID A. TAPP, Judge

17

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.