Opinion

Superior Construction Company

Court
Armed Services Board of Contract Appeals
Filed
Jul 1, 2020
Status
Published
On the bench
Woodrow
Cited by
0 cases
Authority
More cited than 12.1%

The opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- )

)

Superior Construction Company ) ASBCA No. 61468

)

Under Contract No. H92237-11-C-0701 )

APPEARANCE FOR THE APPELLANT: Mr. Mahboobullah Atiqi

Vice President

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.

Air Force Deputy Chief Trial Attorney

Heather M. Mandelkehr, Esq.

Maj Ryan P. Payne, USAF

Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE WOODROW ON THE

GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT

This appeal involves a contractor’s demand for mobilization costs on a contract

in Afghanistan that was suspended and never reinitiated. The government contends

that appellant’s claim is untimely and has moved for summary judgment. We grant

the motion and deny the appeal.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On May 11, 2011, the Combined Joint Special Operations Task Force –

Afghanistan, now Special Operations Joint Task Force – Afghanistan (the

government) awarded Contract No. H92237-11-C-0701 to Superior Construction

Company SCC (SCC) 1 for the construction of a short take-off and landing zone

(STOLZ project) on Forward Base Darvishan, Afghanistan (R4, tab 5). On the same

day, the contracting officer (CO) provided a Notice to Proceed to SCC (R4, tabs 6-7).

2. SCC mobilized machinery and labor to begin the STOLZ project (R4, tab 8

at 2, tab 9 at 1-3). But upon arrival at the project site, a government representative

explained to SCC personnel that the project could not begin because ongoing

1 Appellant uses various names throughout its correspondence with the government:

Superior Construction Company; Women Superior Co.; Women Superior

Construction Company; and Superior Construction Supply and Service

Company. We will continue to use appellant’s name as captioned in this

appeal.

construction on a separate project prevented any work on the runway for the STOLZ

project (R4, tab 9 at 2). On June 11, 2011, that government representative advised

SCC by email that construction on the other project would likely not be complete until

late July or early August, and until then, work on the STOLZ project would have to be

suspended pending completion of the other (R4, tab 9 at 6; see tab 9 at 3-4). The

record does not indicate that a new start date was ever provided or that work was ever

done on the STOLZ project.

3. From July 18, 2011 until September 23, 2011, SCC and the government

exchanged numerous emails regarding compensation for mobilization costs and the

status of the new start date (R4, tabs 8-10). Throughout the email dialogue, SCC and

the government never reached an agreement concerning the amount of reasonable

compensation for costs expended by SCC for mobilization to the project site, with

appellant seeking amounts ranging from $22,500 to $36,000, and the government

proposing to pay amounts ranging from $3,000 to $5,000 (R4, tabs 8-10).

4. On August 8, 2017, SCC filed an appeal with the Board, which was

docketed as ASBCA No. 61272. On September 12, 2017, the Board requested that

SCC provide a copy of the claim it submitted to the CO prior to filing the appeal. In

response, SCC indicated that it had not submitted a claim to a CO for a decision. On

October 5, 2017, the Board dismissed ASBCA No. 61272 without prejudice to allow

SCC to submit a claim to a CO. Superior Constr. Co., ASBCA No. 61272, 2017

WL 4736788 (Oct. 5, 2017).

5. Prior to the October 5, 2017 dismissal, on September 20, 2017, SCC

submitted a claim to the CO for $40,900 in costs related to the STOLZ project (R4,

tabs 2-4). The claim describes costs for mobilization with escort charges, machinery

on-site, labor, and demobilization (R4, tab 4). The claim provides that machinery

remained on the project site from May 18, 2011 until July 17, 2011 (R4, tab 3).

6. After receiving the claim, the government requested that SCC submit all

related invoices (R4, tab 11 at 1). In response, SCC provided three invoices, which

included costs for mobilization, demobilization, and equipment leasing for the dates of

May 18, 2011 to July 17, 2011 (R4, tabs 11-14). Two of the invoices are dated

May 16, 2011, and the third invoice is dated July 18, 2011 (R4, tabs 12-14). The

invoices were later translated for accuracy by SOJTF-A linguists, which confirmed the

English text within each document (R4, tab 18 at 4). Upon further request by the

government for invoices submitted to the contracting officer’s representative in 2011,

SCC provided two more invoices both dated July 4, 2011 (R4, tabs 15-17). These two

invoices are entirely in English and also describe costs for mobilization,

demobilization, and machinery (R4, tabs 16-17).

2

7. The CO issued a final decision, dated December 28, 2017, denying the claim

based on the Contract Disputes Act’s (CDA’s) six-year statute of limitations for filing

a claim (R4, tab 18). On January 1, 2018, SCC filed a timely appeal with the Board,

which was docketed as ASBCA No. 61468 and is before us now.

8. On June 4, 2018, the government filed a motion for summary judgment

describing the “single controlling issue” as the “claim outside of the six-year period”

(gov’t mot. at 1). Attached as Exhibits G-1 and G-2 to the government’s motion are

SCC’s responses to discovery. SCC’s two admission responses are directly quoted

below:

Request for Admission No. 1. Admit that all costs related

to this appeal and its underlying claim were accrued by

17 July 2011.

Response: Superior Co. admits that all costs related to this

appeal were accrued by 17 July 2017

Request for Admission No. 2. Admit that the first and

only claim related to the costs incurred under the

Contract and are the subject of this appeal was filed on

20 September 2017.

Response: Superior co. Admits that the first and only

claim was filed on 20 September 2017. [B]ut we asked for

our expenditures through Email address to the contracting

officer back on 2011.

(Gov’t mot., ex. G-1 at 9) (syntax in original)

9. Following those responses, the government emailed SCC to clarify the date

on Admission No. 1 above. On May 31, 2018, SCC responded to the government’s

email saying, “I apologize for the inconvenience, it is 17 July 2011.” (Gov’t mot.,

ex. G-2 at 1) Accordingly we find that SCC’s claim accrued on July 17, 2011.

10. On October 10, 2018, SCC responded, via email to the Board, to the

government’s motion for summary judgment by submitting a self-described “Appeal

Statement” without specifically addressing the government’s contention. SCC also

attached three invoices “as an evidence to our Appeal.” (Bd. corr. ltr. dtd. October 10,

2018)

3

DECISION

Summary judgment is appropriate when there is no genuine issue of material

fact and the moving party is entitled to judgment as a matter of law. Anderson v.

Liberty Lobby, Inc., 477 U.S. 242, 247-48 (1986). When considering a motion for

summary judgment, the Board’s function is not “to weigh the evidence and determine

the truth of the matter but to determine whether there is a genuine issue for trial.”

Id. at 249. We are required to view the record in the light most favorable to the

nonmoving party, which in this case is SCC. Matsushita Elec. Indus. Co. v. Zenith

Radio Corp., 475 U.S. 574, 587-88 (1986) (citing United States v. Diebold, Inc., 369

U.S. 654, 655 (1962)).

The CDA provides that “[e]ach claim by a contractor against the Federal

Government relating to a contract . . . shall be submitted within 6 years after the

accrual of the claim.” 41 U.S.C. § 7103(a)(4)(A). A claim accrues, “when all events,

that fix the alleged liability of either the Government or the contractor and permit

assertion of the claim, were known or should have been known.” Federal Acquisition

Regulation (FAR) 33.201. The events fixing liability “should have been known” when

they occurred unless they were either concealed or inherently unknowable at the time.

Alion Sci. and Tech. Corp., ASBCA No. 58992, 15-1 BCA ¶ 36,168 at 176,489 (citing

Raytheon Missile Sys., ASBCA No. 58011, 13 BCA ¶ 35,241 at 173,017). “Once a

party is on notice that it has a potential claim, the statute of limitations can start to

run.” Kellogg Brown & Root Servs., Inc., ASBCA No. 58175, 15-1 BCA ¶ 35,988

at 175,824 (quoting Grey Personnel, ASBCA No. 54652, 06-2 BCA ¶ 33,378

at 165,476).

Failure to meet a statute of limitations is an affirmative defense, for which the

government, in this case, bears the burden of proof. Kellogg Brown & Root Servs., Inc.,

15-1 BCA ¶ 35,988 at 175,823 (citing FED. R. CIV. P. 8(c); Bridgestone/Firestone

Research, Inc. v. Automobile Club de L'Ouest de la France, 245 F.3d 1359, 1361

(Fed. Cir. 2001)).

The government contends it is entitled to summary judgment because SCC’s

claim accrued more than six years before the September 20, 2017 claim was submitted

to the CO for a final decision (SOF ¶ 5; gov’t mot. at 3). The government argues that

any costs related to this claim were able to be fully known by July 17, 2011 (gov’t

mot. at 1-2). Additionally, the government points to SCC’s responses to its request for

admissions and contends that by virtue of the admissions, there are no material facts in

dispute (id. at 2-3).

4

SCC responded to the motion by submitting a self-described “Appeal

Statement” without specifically addressing the government’s contention. SCC also

attached three invoices “as an evidence to our Appeal.” (SOF ¶ 10)

We found that the claim accrued on July 17, 2011 (SOF ¶ 9). The invoices

provided by SCC demonstrate that all of the costs related to SCC’s claim either had

been incurred or were known to SCC by this date. Specifically, SCC provided three

untranslated invoices, which included costs for mobilization, equipment rental, and

demobilization. Two of the invoices are dated May 16, 2011, while the final invoice is

dated July 18, 2011 (SOF ¶ 6). SCC subsequently submitted two more invoices, in

English, both dated July 4, 2011, which cover the same expenditures as the previous

native-language invoices. SCC confirmed, in its answers to government requests for

admission, that SCC did not incur any additional costs beyond those set forth in the

invoices. Indeed, SCC expressly stated that “all costs related to this appeal were

accrued by July 17, 201[1].” (SOF ¶ 8) Finally, SCC again confirmed that all of the

costs related to this appeal were accrued by July 17, 2011, when SCC responded to an

email inquiry from government counsel (SOF ¶ 9).

Based on the record before us, we conclude that all costs related to this appeal

were accrued by July 17, 2011, and SCC’s first and only claim was filed on

September 20, 2017 (SOF ¶¶ 5-6; see SOF ¶ 4). Together, these factual findings place

the September 20, 2017 claim six years, two months, and three days after July 17,

2011, the date it admits when all costs were accrued. Accordingly, as the claim

accrued more than six years prior to being filed with the CO, it is untimely.

Although we deem the claim untimely, our analysis does not end here. Because

even though SCC did not articulate the defense directly, we should determine if the

statute of limitations should be equitably tolled. Arctic Slope Native Ass’n, Ltd. v.

Sebelius, 583 F.3d 785, 798 (Fed. Cir. 2009). The CDA’s six-year limitation upon the

submittal of a claim may be equitably tolled when a litigant has (1) been pursuing his

rights diligently, and (2) some extraordinary external circumstance “stood in his way

and prevented timely filing.” Menominee Indian Tribe of Wisconsin v. United States,

136 S. Ct. 750, 755 (2016) (quoting Holland v. Florida, 560 U.S. 631 (2010)). The

burden of proof lies upon the part of the party seeking equitable tolling. See Levy v.

United States, 83 Fed. Cl. 67, 75 (2008) (citing Felder v. Johnson, 204 F. 3d 168,

170-71 (5th Cir. 2000)).

Here, the record shows that there was a flurry of activity between July and

September of 2011, and then nothing else until the August 2017 appeal to the Board

(SOF ¶¶ 3-4). Appellant offers no explanation as to what transpired between

September of 2011 and August of 2017. Because the August 2017 filing to the Board

was beyond the six-year limitation period, and because SCC has offered no evidence

5

of any extraordinary circumstance that prevented timely filing of the claim, we

conclude that SCC failed to diligently pursue its rights.

The CDA requires that a claim be submitted within six years after the accrual of

the claim. 41 U.S.C. § 7103(a)(4)(A). This claim was not.

CONCLUSION

The government’s motion for summary judgment is granted. SCC’s appeal is

denied.

Dated: July 1, 2020

KENNETH D. WOODROW

Administrative Judge

Armed Services Board

of Contract Appeals

I concur I concur

RICHARD SHACKLEFORD OWEN C. WILSON

Administrative Judge Administrative Judge

Acting Chairman Vice Chairman

Armed Services Board Armed Services Board

of Contract Appeals of Contract Appeals

I certify that the foregoing is a true copy of the Opinion and Decision of the

Armed Services Board of Contract Appeals in ASBCA No. 61468, Appeal of Superior

Construction Company, rendered in conformance with the Board’s Charter.

Dated: July 1, 2020

PAULLA K. GATES-LEWIS

Recorder, Armed Services

Board of Contract Appeals

6

This is a copy of a public record, reproduced as it was published. It is not legal advice, and it may not be the version a court would rely on. Check the official source before you cite it.

A word about cookies

We need a few to keep you signed in and the library working. The rest help us see which pages people use and where they get stuck. They stay off unless you say yes.