In the United States Court of Federal Claims

No. 17-464C

(Filed: January 28, 2020)

**************************

VIRGINIA ELECTRIC AND POWER

COMPANY d/b/a DOMINION Contracts; termination for

ENERGY VIRGINIA, convenience; allowable

costs; FAR 52.249-2

Plaintiff, (1996); FAR 31.205-42(b)

(2018); summary

v. judgment; upgrade costs;

utilities.

THE UNITED STATES,

Defendant.

**************************

Alan M. Freeman, Washington, DC, for plaintiff. Albert B. Krachman

and Jaret N. Gronczewski, of counsel.

Barbara E. Thomas, Senior Trial Counsel, United States Department

of Justice, Civil Division, Commercial Litigation Branch, Washington, DC,

with whom were Joseph H. Hunt, Assistant Attorney General, Robert E.

Kirschman, Jr., Director, Patricia M. McCarthy, Assistant Director, for

defendant. Erika L. Whelan Retta, Trial Attorney, Air Force Legal

Operations Agency, of counsel.

OPINION

BRUGGINK, Judge.

Plaintiff claims that the United States owes Virginia Electric and

Power Company, doing business as Dominion Energy Virginia

(“Dominion”), the cost of upgrading the metering, lighting, and distribution

of the electrical system at Fort Monroe, a military base in the Commonwealth

of Virginia. The United States, acting through the Defense Energy Support

Center, entered into a 50-year contract with Dominion in 2004 for utility

services (“the Utility Services Contract”) and contemporaneously, but

separately, sold Dominion the electrical system at Fort Monroe. On

September 15, 2011, the Army terminated for convenience the Utility

Services Contract. Subsequently, the United States and Dominion settled

certain cost claims relating to the termination and entered into a separate

contract for Dominion to supply electricity and certain utility services at Fort

Monroe. The only outstanding question is whether the United States is liable,

under the terminated line item of the Utility Services Contract, for potential

future upgrade costs, i.e., costs not incurred prior to termination.

Plaintiff asserts that the United States terminating the Utility Services

Contract unavoidably triggered an obligation for plaintiff, which continues

to own the electrical system, to bring the system up to higher standards than

those that would have applied if the Utility Services Contract had continued.

It points to its obligations under state law and corporate policies.

Pending are the parties’ cross-motions for summary judgment.

Plaintiff moved for summary judgment as to liability on its Counts I, II, and

IV; its motion is silent on Count III. Defendant cross-moved for summary

judgment on Counts I, II, and IV and moved for summary judgment on Count

III. Plaintiff requested summary judgment on Count III in a footnote of its

response brief. Defendant also moved for summary judgment on an equitable

adjustment theory raised for the first time in plaintiff’s motion. The motions

are fully briefed. The Fort Monroe Authority, represented by Virginia’s

Office of the Attorney General, submitted an amicus brief in support of

plaintiff’s position. The court held oral argument on December 11, 2019. For

the reasons set out herein, we deny plaintiff’s motion for summary judgment

and grant the government’s motion.

BACKGROUND

In the late 1990s, Congress authorized the Secretaries of the Military

Departments to privatize utility systems on military bases as a cost-saving

mechanism. The statute authorized the departments to “convey a utility

system, or part of a utility system, under the jurisdiction of the Secretary to

a municipal, private, regional, district, or cooperative utility company or

other entity.” 10 U.S.C. § 2688(a) (2018).

The Secretary of Defense later issued a directive to the Military

Departments “to privatize all utility systems, except where needed for unique

security reasons or when privatization is uneconomical.” Def.’s App. 7.

Privatization meant “the total divestiture of a utility system through the

transfer and conveyance of the installation’s utility infrastructure assets in

conjunction with and for the purpose of the conveyee providing utility

2

distribution services on a long-term basis.” Id. The directive thus outlined

two goals: (1) divest the United States of utility systems and (2) secure utility

services. 1

To implement this directive, in 2001, the Defense Energy Support

Center issued a solicitation seeking “offerors to assume ownership, operation

and maintenance of the utility infrastructures” at four Army bases: Fort

Monroe, Fort Eustis, Fort Story, and Fort Lee. 2 Id. at 11. Fort Monroe, which

is in Hampton, Virginia, and at the time encompassed 568 acres, is the base

at issue here. The available utility infrastructures at Fort Monroe were

electric, natural gas, water, and wastewater. 3 The solicitation outlined two

different transactions: (1) purchase of utility systems and (2) a 50-year Utility

Services Contract.

Dominion offered to buy the electrical systems and supply utility

services at Fort Monroe, Fort Eustis, and Fort Story. Dominion offered two

alternatives for its provision of service. First, it offered a “regulated

proposal” under which the United States would pay for bringing the electrical

system up to certain modern standards imposed on Dominion’s other

customers. Alternatively, it offered an “unregulated proposal” under which

“[t]he electric system components were not required to meet – and they did

not meet – the same regulated standards applicable to comparable systems

serving regulated customers in other parts of Dominion’s Virginia service

territory.” Pl.’s Mot. Summ. J. 1; Am. Compl. ¶ 15 (“In a nutshell, before the

contract termination, the Fort Monroe utility system was exempt from

meeting regulated standard.”).

The Defense Energy Support Center awarded Dominion a contract for

utility services on the electrical systems at those three bases on June 24, 2004.

The Preamble summarized the Utility Services Contract as follows:

[Dominion] shall assume ownership, operation and

maintenance of the electric distribution systems at Fort Eustis,

1

Utility services meant operation and maintenance of the system rather than

supplying the commodity, such as electricity.

2

The solicitation did not seek proposals for the sale of electricity.

3

The Army owned and operated the electrical system at Fort Monroe, while

Dominion supplied electricity under a separate, unrelated contract. Dominion

supplied electricity to “[a] single 13.2-kV Virginia Power delivery point . . .

near the center of the installation,” which the Army’s electrical system then

distributed throughout the base. Def.’s App. 136.

3

Fort Story, and Fort Monroe, Virginia. [Dominion] shall

furnish all necessary labor, management, supervision, permits,

equipment, supplies, materials, transportation, and any other

incidental services required for the complete ownership,

operation, maintenance, repair, upgrade, and improvement of

the utility system. These services shall be provided in

accordance with all terms, conditions, and special contract

requirements, specifications, attachments, and drawings

contained explicitly in this contract or incorporated by

reference.

Def.’s App. 99. The Preamble incorporated a version of Dominion’s proposal

into the Utility Services Contract. Of importance here, the incorporated

proposal was the “unregulated” proposal, which meant that the United States

accepted the proposal that did not require Dominion to upgrade the system

to modern standards for its metering, lighting, or distribution, among other

things.

The Utility Services Contract did not convey the electrical system to

Dominion. Rather, the Utility Services Contract provided at section C.2.2:

“The conveyance of the utility system is authorized by and conducted under

10 USC § 2688. The conveyance of the utility system is not an acquisition

and therefore is not subject to the FAR and its supplements.” Id. at 20.

Section C.5.1 explained:

Prior to the transfer of title, such facilities shall continue to be

owned by the Government. Transfer of title shall be

accomplished by Easement. The Easement shall provide the

complete list of all assets to be sold. . . . The parties shall

prepare and execute such additional documents as may be

necessary to implement the ownership transfer.

Id. at 25. In other words, transfer of ownership of the infrastructure, although

related to the Utility Services Contract, was accomplished separately.

After entering the Utility Services Contract, the parties executed the

Bill of Sale, Easement, and Promissory Note. The Bill of Sale, executed on

February 16, 2005, stated:

The United States of America . . . sells, transfers and

conveys to the Virginia Electric and Power Company dba

Dominion Virginia Power, . . . the property described below:

4

All those certain facilities and equipment, including, but

not limited to, substations, switching stations, transformers,

exterior lighting, overhead electrical lines, and underground

electrical lines, comprising the Fort Monroe, Virginia electrical

system, all or part of which is more particularly described on

Exhibit “A”, attached hereto and made a part of this Bill of

Sale.

This sale is subject to the following provisions:

1. The terms and conditions found in the Utility Distribution

Contract No. SP0600-04-C-8253 and Department of the Army

Easement No. DACA65-2-05-34 being agreements between

the Government and the Grantee;

2. The Government covenants that it has good and valid title to

the facilities and equipment being conveyed by this Bill of

Sale, . . . and

3. The Government makes no warranty with regards to the

condition of the facilities and equipment.

Id. at 149 (emphasis omitted).

The Easement, also executed on February 16, 2005, provided in

pertinent part:

The Secretary of the Army, under and by virtue of the

authority vested in the Secretary by Title 10, United States

Code, Section 2688 and Title 10, United States Code, Section

2668, having found that the granting of this easement is not

incompatible with the public interest, hereby grants to:

Virginia Electric and Power Company dba Dominion Virginia

Power, hereinafter referred to as the Grantee, an easement for

construction, operation, maintenance, repair and replacement

of electric utility system, including all right, title and interest

in and to all appurtenances located thereon, hereinafter referred

to as the facilities, over, across, in and upon lands of the United

States as identified in Exhibit(s) “A” and “B”, hereinafter

referred to as the premises, and which are attached hereto and

made a part hereof. This easement is issued in conjunction with

Utility Distribution Contract No. SP0600-04-C-82S3

5

hereinafter referred to as the contract, between the Government

and the Grantee.

This easement is granted subject to the following

conditions.

1. Term[:] This easement is hereby granted for a term of fifty

(50) years, beginning December 1, 2004, and ending

November 30, 2054.

2. Contract-Easement Relationship[:] This easement and the

contract shall not merge, but the terms and conditions of each

shall survive the execution and delivery of this easement and

any subsequent recordation thereof. In the event the terms and

conditions of this easement conflict with the terms and

conditions of the contract, the terms and conditions of the

contract shall prevail. . . .

3. Transfer of Ownership

a. The Fort Monroe Military Installation’s Electrical

System consists of, but is not limited to:

1. Approximately 586 street lights/poles

2. Approximately 106,428 linear feet of under-

ground electric lines

3. Approximately 2,227 kilo volts transformers

(including 139 underground structures/man-

holes, 20 miles of underground lines and 107

underground transformers

4. One-(1) 300 KV Sub/Switch Station Building

which includes 9 switching cabinets

b. The ownership of the Fort Monroe Military

Installation’s electrical system is hereby transferred by

the Government and accepted by the Grantee.

Id. at 150-65 (emphasis omitted). The practical effect of these documents

was to convey the electrical system to Dominion and grant Dominion a 50-

year right of access to the Fort Monroe property.

6

In the third element of the transaction, Dominion executed a

Promissory Note on February 28, 2005, promising to pay the Army

$2,133,075.93 for the Fort Monroe electrical system. The parties

incorporated the Bill of Sale, the Easement, and the Promissory Note into the

Utility Services Contract through Modification 4 dated April 20, 2005.

Finally, regarding ownership of the electrical system itself, the Utility

Services Contract provided in paragraph 4 of the Preamble:

[A]t the end of the contract term [Dominion] may

submit a claim for unrecovered investments. . . . The parties

anticipate that at its expiration this contract may be renewed at

mutually satisfactory terms. If the contract is renewed, no

claim for unrecovered investments shall be allowed. If the

contract is not renewed and [Dominion’s] claim for

unrecovered investments is allowed, the Government may, at

its sole option, reacquire the electric distribution system in its

entirety for the amount of the unrecovered investment claim

settlement without additional compensation. The reacquisition

shall be effective upon payment of the unrecovered investment

claim settlement. In the event the Government exercises its

reacquisition option the electric system shall be tendered to the

Government free of liens or encumbrances of any kind.

Id. at 99.

The Utility Services Contract had three line items, one for each

military base: CLIN 1 Fort Eustis, CLIN 7 Fort Monroe, and CLIN 11 Fort

Story. Each contract line item had two components: (1) the Fixed Monthly

Charge for utility services and (2) the Monthly Credit as Payment for

Purchase Price. The Fixed Monthly Charge represented what the United

States would pay Dominion for two sub-components of utility services: (a)

operations and maintenance and (b) renewals and replacements. The parties

set the Fixed Monthly Charge for the first two years of the contract term,

with later years subject to price redetermination. The parties could adjust the

Fixed Monthly Charge for Capital Upgrades as set out in the contract. The

Monthly Credit represented the monthly part of the $2 million purchase price

that the United States would subtract from the Fixed Monthly Charge. CLIN

7 set out the two components as follows:

7

Id. at 103.

Although the parties chose the “unregulated” option, the Utility

Services Contract nevertheless provided in section C.11.1 that Dominion was

“responsible for accomplishing all required upgrades and renewals and

replacements to maintain and operate the utility system(s) in a safe, reliable

condition, and to meet the requirements of this contract.” Id. at 118. Plaintiff

specifically proposed a list of Initial Capital Upgrades in its Schedule B-2,

which were “those repair, replacement, and improvement activities” that

Dominion would complete to bring the system as purchased up to applicable

regulatory and corporate standards; the Initial Capital Upgrade did not

include the metering, lighting, and distribution at issue in this case. Id.

Upgrades also included Future Capital Upgrades, namely “investments in the

utility system resulting from changes in the requirements, laws or

regulations.” Id. The contract defined renewals and replacements as

“investments in the utility system to renew or replace system components

that fail or reach the end of their useful life.” Id.

The parties anticipated that Dominion would submit “an Annual

Capital Upgrades and Renewals and Replacements Plan that identifies capital

upgrades and major renewals and replacements the Contractor intends to

accomplish.” Id. The Utility Services Contract further explained that the

government reserved “the right to determine at its discretion, whether it will

pay for any portion of proposed upgrades.” Id. at 118-19. The government

would pay for approved upgrades when accomplished. The contract stated

8

that the government would pay for the renewals and replacements named in

Schedule B-2 and set out a process for approving future capital upgrades.

Not included in the upgrades and renewals proposed initially, plaintiff

concedes, were the upgrade costs sought here. The claimed upgrade costs do

not fall within the upgrade categories, plaintiff explained, because the

government chose the “unregulated” contract approach when it entered into

the Utility Services Contract. Moreover, even if the “unregulated” contract

would have covered the anticipated work, the United States did not order the

upgrades Dominion now claims under the contract and Dominion did not

begin the disputed upgrade work during the contract performance period.

Section I.2 incorporated “FAR 52.249-2 Termination for

Convenience of the Government (Fixed Price) Sep 1996” into the Utility

Services Contract. Id. at 47. That clause stated:

(a) The Government may terminate performance of work

under this contract in whole or, from time to time, in part if the

Contracting Officer determines that a termination is in the

Government’s interest. The Contracting Officer shall terminate

by delivering to the Contractor a Notice of Termination

specifying the extent of termination and the effective date. . . .

(e) After termination, the Contractor shall submit a final

termination settlement proposal to the Contracting Officer . . .

(f) Subject to paragraph (e) of this clause, the Contractor and

the Contracting Officer may agree upon the whole or any part

of the amount to be paid or remaining to be paid . . .

(g) If the Contractor and the Contracting Officer fail to agree

on the whole amount to be paid because of the termination of

work, the Contracting Officer shall pay the Contractor the

amounts determined by the Contracting Officer as follows . . .:

(1) The contract price for completed supplies or services

accepted by the Government . . . not previously paid for,

adjusted for any saving of freight and other charges.

(2) The total of—

(i) The costs incurred in the performance of the work

terminated, including initial costs and preparatory expense

9

allocable thereto, but excluding any costs attributable to

supplies or services paid or to be paid under subparagraph

(g)(1) of this clause;

(ii) The cost of settling and paying termination settlement

proposals under terminated subcontracts that are properly

chargeable to the terminated portion of the contract if not

included in subdivision (g)(2)(i) of this clause; and

(iii) A sum, as profit on subdivision (g)(2)(i) of this clause . . .

(3) The reasonable costs of settlement of the work terminated,

including— (i) Accounting, legal, clerical, and other expenses

reasonably necessary for the preparation of termination

settlement proposals and supporting data; (ii) The termination

and settlement of subcontracts (excluding the amounts of such

settlements); and (iii) Storage, transportation, and other costs

incurred, reasonably necessary for the preservation, protection,

or disposition of the termination inventory. . . .

(i) The cost principles and procedures of Part 31 of the Federal

Acquisition Regulation . . . shall govern all costs claimed,

agreed to, or determined under this clause. . . .

(l) If the termination is partial, the Contractor may file a

proposal with the Contracting Officer for an equitable

adjustment of the price(s) of the continued portion of the

contract. . . . Any proposal by the Contractor for an equitable

adjustment under this clause shall be requested within 90 days

from the effective date of termination unless extended in

writing by the Contracting Officer. . . .

FAR 52.249-2.

The United States did not give Dominion the opportunity to perform

under the Utility Services Contract for fifty years. Instead, in 2005, Congress

selected Fort Monroe for closure under the Defense Base Closure and

Realignment Act of 1990, Pub. L. No. 101-510, as amended by later statutes.

Am. Compl. ¶ 12. From 2005 to 2011, the United States and the

Commonwealth of Virginia laid the groundwork for what would happen to

the Fort Monroe property once it was no longer a United States military base.

10

Virginia is a player here, because the Commonwealth, in two deeds

dated 1838 and 1936, conveyed about 285 acres of the property occupied by

Fort Monroe to the United States. The deeds stated that title to the property

would revert to Virginia if the United States ceased using the property for

“fortification or national defense.” Def.’s App. 483. Virginia had also

conveyed another part of the Fort Monroe property to the United States, and

although Virginia did not hold the same reversionary interest in that property,

the United States and Virginia negotiated a transfer of that property back to

the Commonwealth as well. The United States and Virginia negotiated these

transfers of property after Congress selected Fort Monroe for closure. Over

time, Virginia created an entity responsible for Virginia’s portion of the Fort

Monroe property: The Fort Monroe Authority.

On January 27, 2011, the contracting officer sent Dominion a

memorandum titled “Operation and Maintenance Contract SP0600-04-C-

8253 Partial Termination for Convenience of the Government.” Id. at 259.

The memorandum stated:

1. The Army, in compliance with Base Realignment and

Closure [] Public Law, will close Fort Monroe on 15

September 2011. By this date, Army missions will be

relocated and property will transition to the Commonwealth

of Virginia. In accordance with Federal Acquisition

Regulation clause 52.249-2— Termination for

Convenience of the Government (Fixed-Price), contract

line item number 0007 for Privatization of Fort Monroe,

Virginia Electric Distribution System is hereby terminated

for convenience effective 15 September 2011.

2. It is requested that you submit a termination settlement

proposal no later than 28 March 2011. If you have any

questions, please contact the undersigned at [contact

information].

Id.

Dominion informed the contracting officer that, in Dominion’s view,

the partial termination for convenience notice was insufficient because “it

did not clearly state the Government’s desire upon termination,” specifically

whether the United States would exercise its option to reacquire the electrical

system. Id. at 260. Following discussions with Dominion, on June 3, 2011,

the Director of Business Operations, 633d Contracting Squadron,

11

Department of the Air Force, sent Dominion a revised memorandum

regarding the termination of Utility Services Contract CLIN 7. The first

paragraph replicated the first paragraph of the original memorandum. The

final paragraph again requested a termination settlement proposal, now by

August 2, 2011. New paragraph two stated,

The Army desires [Dominion] to continue ownership of the

electrical distribution system at Fort Monroe after termination

effective date. While the Army continues to own the

property[,] it will continue to provide [Dominion] with a

standard utility easement for future access to the distribution

system. The Army believes these easements will be conveyed

with the land and be further granted by the Fort Monroe

Authority or any other future property owner as a requirement

in the terms of the conveyance from the Army.

Id. at 266. Dominion submitted its settlement proposal on August 2, 2011.

On September 15, 2011, the Utility Services Contract CLIN 7

terminated. As of September 15, 2011, Dominion owned the Fort Monroe

electrical system, but Dominion no longer sold the United States utility

services. The United States owned the real property at Fort Monroe.

On October 24, 2011, Dominion and the Army Contracting Command

at Rock Island executed an “Authorization for Electric Service” under a

preexisting Contract No. GS-00P-08-BSD-0560. That contract is an

areawide public utility contract between the General Services Administration

and Dominion, executed in 2008, which we will refer to as the Areawide

Contract. Id. at 239-56, 274. The Areawide Contract is a “master contract”

issued “to cover the utility service acquisitions of all Federal agencies in the

franchised certificated service territory from [Dominion] for a period not to

exceed ten (10) years.” Id. at 241. The Authorization stated that Dominion

would provide “Continue[d] Service” and “Special Facilities” to Fort

Monroe, effective September 15, 2011, and continuing “until notified by

Customer.” Id. at 274.

The Authorization stated that Dominion would provide electric

“[s]ervice through one 7.5 mVA transformer to multiple delivery points with

primary metering at 13.2 kV[] [i]nstead of[] [s]ervice through two 2800 kVa

transformers . . . with totalized secondary metering.” Id. at 276-77. The

Authorization also stated that the United States would pay Dominion a

12

“monthly facilities charge” of $54,655.77 for providing those “facilities” and

the government would pay Dominion an added amount each month for the

electricity supplied and delivered to Fort Monroe. Id. at 279. This

Authorization under the Areawide Contract filled the gap left by the

terminated CLIN 7 of the Utility Services Contract by compensating

Dominion for electricity plus certain utility services. The United States

remained Dominion’s customer.

After the Utility Services Contract termination, Dominion and the

government negotiated Dominion’s compensation for the termination

through a series of amended termination settlement proposals, two certified

claims, and an appeal to the Armed Services Board of Contract Appeals. The

United States and Dominion settled Dominion’s claims for net unrecovered

investments and settlement costs. The outstanding dispute between the

parties relates solely to the cost for future upgrades to metering, lighting, and

distribution on the Fort Monroe electrical system that Dominion believes it

must complete due to the termination of the “unregulated” contract.

The first transfer of real property from the United States back to

Virginia did not occur until 2013. By a quitclaim deed transferring a part of

the real property at Fort Monroe, the United States split ownership of the real

property at Fort Monroe between the United States and Virginia. Since that

time, the United States has transferred more Fort Monroe property to

Virginia. Virginia has also conveyed some of the property back to the United

States for use as a national monument. The United States and Virginia still

split ownership of the property as of the date of oral argument. Dominion

continues to own the Fort Monroe electrical system, and the United States

remains the customer of record for Dominion’s purposes.

Dominion takes the position that each of the foregoing events—the

termination of CLIN 7, the United States’ failure to reacquire the electrical

system, the United States exchanging property at Fort Monroe with Virginia,

and the possibility of multiple future customers at Fort Monroe

(governmental and non-governmental)—“caused Dominion to incur an

obligation under its Tariff (and per its T&Cs) to modify the [metering,

lighting, and distribution] to meet the same regulated standards applicable to

comparable systems serving Dominion’s regulated rate base.” Pl.’s Mot.

Summ. J. 9. To support this belief, plaintiff cites its obligation under Virginia

state law to provide reasonably adequate services and just rates to its

regulated rate base without preferential treatment as well as its internal

13

corporate policies and broader industry standards. See, e.g., id. at 9, 12, 23,

24. Notably, the United States, which remains Dominion’s customer at Fort

Monroe, has not ordered such work under the existing federal Areawide

Contract. Neither the parties’ briefing nor that of the amicus state that the

Fort Monroe Authority or other Virginia authority has ordered this work.

Dominion’s belief is that the upgrade work is an independent legal obligation

arising out of its status as a regulated utility company in Virginia and out of

its corporate policies.

Dominion and the Fort Monroe Authority have discussed a contract

between Dominion and the Fort Monroe Authority for utility services and

electricity at the Fort Monroe property; the goal is for the Fort Monroe

Authority to replace the United States as Dominion’s contracting partner.

Plaintiff is concerned, however, that any such future contract would not

compensate Dominion for its perceived obligation to upgrade facilities. The

Fort Monroe Authority is similarly concerned that Dominion will pass on the

cost of any upgrade work to Virginia. Dominion and the Fort Monroe

Authority’s negotiations have failed due to their belief that someone else,

preferably the United States, must first commit to pay for upgraded metering,

lighting, and distribution.

Defendant acknowledges that Dominion has chosen to spend

$240,000 to begin upgrades. The parties agree that the government did not

order the work nor did Dominion begin the work during performance of the

contract at bar. Dominion concedes that it has not completed its projected

upgrades. It estimates that the total cost of the upgrades, including the

amount already spent, will be approximately $13 million. Dominion filed suit

in this court in 2017 seeking payment for the cost of upgrading the metering,

lighting, and distribution at Fort Monroe.

DISCUSSION

To be clear at the outset, plaintiff is not making a claim for costs

incurred during the performance of the Utility Services Contract or for costs

already spent as part of the termination for convenience. Instead, plaintiff’s

various arguments flow from two assumptions: (1) Had the United States

allowed the Utility Services Contract to continue, plaintiff would not be

obligated to upgrade the metering, lighting, and distribution, because the

contract did not require those upgrades; alternatively, if those upgrades

became necessary during the life of the contract, the contract set out a process

for recouping that cost from the United States, a process no longer available

14

to plaintiff. And (2) the United States, by terminating CLIN 7 of the Utility

Services Contract, triggered an obligation—external to the Utility Services

Contract, found in Virginia state law and plaintiff’s corporate policies—for

Dominion to upgrade the metering, lighting, and distribution at Fort Monroe,

foisting onto plaintiff costs that it had not planned to expend at Fort Monroe.

Plaintiff advances five theories of liability under which the United

States must pay for the upgrades: (1) The upgrades are an allowable cost

under FAR 31.205-42(b) caused by the termination for convenience of the

Utility Services Contract. (2) The upgrade costs are fair compensation after

a termination for convenience under FAR 49.201. (3) The termination for

convenience of the Utility Services Contract was defective without such

payment. (4) Failing to pay for the upgrade costs constitutes a breach of the

Utility Services Contract. Plaintiff’s motion for summary judgment also

introduced a new theory that, (5) because the termination of the Utility

Services Contract was partial, plaintiff is entitled to an equitable adjustment

for its increased cost of performance under the other two contract line items.

In Count I, plaintiff argues that the cost to upgrade the metering,

lighting, and distribution will be attributable to the contract as unavoidably

continuing after termination. It estimates the cost to be $13 million. Plaintiff

relies on FAR 31.205-42(b) Costs Continuing After Termination:

Contract terminations generally give rise to the incurrence of

costs or the need for special treatment of costs that would not

have arisen had the contract not been terminated. The

following cost principles peculiar to termination situations are

to be used in conjunction with the other cost principles in

subpart 31.2: . . .

(b) Costs continuing after termination. Despite all reasonable

efforts by the contractor, costs which cannot be discontinued

immediately after the effective date of termination are

generally allowable. . . .

Despite citing subsection -42(b), plaintiff does not argue that

Dominion could not discontinue the upgrade work immediately after

termination. In fact, plaintiff insists that, under the Utility Services Contract,

this specific upgrade work was not required, and it concedes that the work

was not underway during the pre-termination period. Instead, plaintiff relies

on the introductory language: “costs that would not have arisen had the

15

contract not been terminated.” Id. Plaintiff contends that, had the United

States not ended the contract some forty-three years early or had the United

States reacquired the electrical system from plaintiff, Dominion would not

face an obligation to upgrade the metering, lighting, and distribution. When

the government terminated early, plaintiff argues, the termination subjected

Dominion to the broader requirements of state law and Dominion’s policies

to upgrade the system. Therefore, “but for” the termination, the upgrade costs

would not have arisen.

We address below the question whether plaintiff has established its

critical assumption that termination altered its legal obligation to upgrade the

Fort Monroe electrical system. For the moment, we will accept that

assumption. Even accepting plaintiff’s “but for” argument, however, the

fundamental problem is that these upgrade costs are unconnected to the work

Dominion performed under the Utility Services Contract. They are not

contract costs continuing after termination. They are costs that Dominion will

incur, if at all, because of separate contracts or obligations. They have not

been nor will they be performed in satisfaction of the terminated work.

Plaintiff bought an outdated electrical system. The parties agreed at

oral argument that plaintiff has owned the system since 2005 and that the

termination did not interrupt that ownership. Dominion knew prior to

purchase that the system did not meet Dominion’s “regulated standard”—

whether internally imposed or imposed by law—for a modern electrical

system as far as metering, lighting, and distribution are concerned. Plaintiff

paired that risky purchase with a services contract that it believed would last

at least fifty years, hoping to spread out the cost of repairs over many

decades. Yet the services contract that plaintiff agreed to did not provide

Dominion with any guarantee that the United States would reacquire the

system at the end of the contract term or upon termination and, critically,

allowed the United States to end the utility services part of the bargain at its

own convenience. Moreover, the Utility Services Contract did not bargain

for, much less guarantee, that the United States would pay for such an

upgrade prior to or after termination.

The cases Dominion relies on highlight the difference between the

costs arising after termination that are attributable to the contract and the

costs Dominion seeks in this case. In Nolan Bros., Inc., v. United States, for

instance, the contractor wore out the tires on its equipment performing an

excavation contract. 194 Ct. Cl. 1, 22 (1971). The contractor claimed the

16

price of new tires following the termination. The Court of Claims held, “The

expense involved in replacing tires worn out as a result of [operating

plaintiff’s equipment] on the job during the pre-termination period was

[recoverable], irrespective of whether the actual replacement of such tires

occurred during the pre-termination period or after the work under the

contract was terminated.” Id. Dominion points to Nolan Brothers as an

example of a recoverable cost that arose after termination. The difference

between Nolan Brothers and Dominion’s claim, however, is that the Nolan

Brothers contractor wore out its tires while performing the contract. The

Utility Services Contract did not include the costs that Dominion claims here,

because, with the United States as its contracting partner on the

“unregulated” contract, Dominion did not have its alleged legal obligation to

upgrade the metering, lighting, and distribution. Plaintiff did not perform any

of the upgrade work, what little it has done so far, during contract

performance. Dominion is thus not looking to replace something worn out in

the performance of the contract but instead is looking to have a former

customer pay for an upgrade that a later customer might demand.

Plaintiff also cites White Buffalo Construction, Inc. v. United States,

in which this court held that the United States must pay the contractor “fair

compensation for any additional repairs occurring after termination that were

necessitated by the contract work.” 52 Fed. Cl. 1, 11 (2002). In that case, the

contractor used its equipment during performance of the contract. Here,

Dominion concedes that the Utility Services Contract did not require

upgrading the metering, lighting, and distribution system and that it did not

undertake the work during the performance period.

Plaintiff’s focus on a single line in FAR 31.205-42, “costs that would

not have arisen had the contract not been terminated,” is unpersuasive

because section -42(b) clearly assumes a connection between the substance

of the contract and the claimed cost. Furthermore, the termination clause,

FAR 52.249-2, lists categories of costs predicated on some connection

between the performance of the contract and the cost arising or continuing

after termination. For instance, the termination clause particularly lists “costs

incurred in the performance of the work terminated” and “the reasonable

costs of settlement of the work terminated,” such as costs necessary to

preserve or dispose of termination inventory. FAR 52.249-2(g)(2)-(3).

Plaintiff does not cite these categories or any other in the termination clause

in its complaint or briefing, perhaps because these categories also require

some nexus between the work anticipated under the contract and the costs

17

plaintiff claims. The costs claimed here instead relate to work that Dominion

may complete, on a system that Dominion owns, in performance of a future

contract.

Our foregoing assumption that the termination of CLIN 7 triggered a

legal obligation for plaintiff to upgrade the metering, lighting, and

distribution at Fort Monroe is, in any event, not established. Plaintiff

contends that by terminating CLIN 7 without reacquiring the system, the

United States ended the “unregulated” status of the Fort Monroe electrical

system and thrust the system into Dominion’s regulated rate base. Plaintiff’s

citations to state law and its corporate policies only generally discuss

Dominion providing reasonably adequate service to similarly situated

customers, however. As of September 15, 2011, and for at least two years

thereafter, Fort Monroe remained federal property. The United States has at

all points remained Dominion’s customer regarding electricity and utility

services at Fort Monroe, first under the Utility Services Contract and now

under the Areawide Contract. It is unclear how the services Dominion

provides to the United States became automatically subject to the regulations

governing Dominion’s broader rate base upon termination of CLIN 7.

Plaintiff has not established a cause-and-effect relationship between the

termination and plaintiff’s perceived obligation to perform upgrade work.

In addition to the termination itself, plaintiff argues that splitting the

real property ownership triggered a requirement found in its tariff (or

elsewhere in state law or its corporate policies) to upgrade metering, lighting,

and distribution. Splitting the property did not occur until at least two years

after the termination, however. The termination of CLIN 7 and the transfer

of property between the United States and Virginia were unrelated

transactions. Plaintiff also argues that the change from a single-customer,

contiguous federal property to a multi-customer property triggered its

obligation to upgrade, even though plaintiff’s customer has remained the

United States under the Areawide Contract. Its multi-customer problem is

largely conjectural at this point. Moreover, as discussed at oral argument, the

United States, as the customer under the Areawide Contract, has not ordered

this upgrade work. Any future upgrade work would be requested by the Fort

Monroe Authority, a separate state government entity with which plaintiff

may negotiate a contract in the future.

None of plaintiff’s theories, taken together or separately, establish that

plaintiff has an existing legal obligation to upgrade the metering, lighting,

18

and distribution on the Fort Monroe electrical system. More importantly,

even if such a requirement exists, plaintiff’s arguments do not tie that

obligation to what the United States bargained for under Utility Services

Contract CLIN 7 or to the termination itself. Because plaintiff cannot connect

its anticipated upgrade work to the Utility Services Contract, the court denies

plaintiff’s motion for summary judgment on Count I and grants the

government’s cross-motion on that count.

Plaintiff also argues, in Count II, that it is only fair that defendant pay

for the estimated cost to upgrade the metering, lighting, and distribution.

Plaintiff relies on FAR 49.201(a), which states, “A settlement should

compensate the contractor fairly for the work done and the preparations made

for the terminated portions of the contract, including a reasonable allowance

for profit.” Of course, the aim of a termination settlement is to compensate

the contractor fairly, but FAR Part 49 does not offer a standalone category

for the upgrade costs. As FAR 49.201(a) points out, the termination

settlement connects to the work contemplated under the original contract or

to work triggered by termination. To the extent that plaintiff argues that it

was unfair to terminate a contract that called for 50 years of performance,

plaintiff has shown no basis in the contract for that argument, particularly in

view of the termination for convenience clause. Plaintiff cannot shoehorn

entitlement to costs for upgrading metering, lighting, and distribution that are

disconnected from its work under the Utility Service Contract into this

general FAR provision. We thus deny plaintiff’s motion for summary

judgment on Count II and grant the government’s cross-motion.

In Count III, plaintiff alternatively seeks $13 million for upgrading

the Fort Monroe electrical system on a theory of “Defective Termination.”

Plaintiff theorizes that terminating the Utility Services Contract also

terminated the Bill of Sale and that the United States unilaterally forced the

electrical system on Dominion in the termination process. Dominion’s

argument has no basis in fact or law. The termination notices were legally

sufficient. Plaintiff conceded at oral argument that it has, at all relevant times,

owned the electrical system, and it did not distinguish between pre-

termination and post-termination ownership.

Even if plaintiff had not made this concession, nothing in the Utility

Services Contract, the Bill of Sale, or the Easement suggest that a termination

of the Utility Services Contract CLIN 7 also revoked or voided the property

transfer from the United States to plaintiff. The contract explains that the

19

electrical system sale is not an acquisition and is not subject to the FAR. The

contract establishes that the United States owned the system until the parties

executed the Easement, at which point plaintiff owned the system. Both the

Bill of Sale and the Easement confirm that, upon execution of those

documents, ownership of the system transferred to plaintiff. The fact that the

Bill of Sale was “subject to” the contract does not suggest that termination

of CLIN 7 unwound the sale of the electrical system to defendant; the

contract provided an option for reacquisition that the government declined to

exercise. Nothing in the Easement suggests that the termination of CLIN 7

automatically revoked the conveyance or the access rights granted in that

document either. The parties’ behavior in the termination settlement process

reflected this reality: they decreased any settlement amount by the remaining

purchase price. Dominion’s theory does not reflect the undisputed facts of its

transaction with the government nor does it seek relief consistent with its

own theory. We therefore grant the government’s motion on Count III and

deny plaintiff’s cross-motion.

In Count IV, plaintiff alternatively seeks $13 million for upgrading

the Fort Monroe electrical system because defendant breached the contract

by refusing to pay for the metering, lighting, and distribution costs during the

termination settlement process. The contract allowed the government to

terminate the contract for convenience. The termination clause set out the

procedure for determining a settlement and incorporated the cost principles

in FAR Part 31 to aid in determining the settlement amount. After the

government notified Dominion of the upcoming termination through two

termination notices, the government went through the termination settlement

proposal process outlined in the termination clause. The government thus

fulfilled its duties under the termination for convenience clause. The fact that

the government disagreed with Dominion on what the government owes

Dominion under that clause is not a breach of the Utility Services Contract.

Because plaintiff has not identified a duty set out in the Utility Services

Contract that the government breached, we deny plaintiff’s motion and grant

the government’s cross-motion.

Finally, in its motion for summary judgment, plaintiff raised a novel

theory of recovery, not found in its complaint (original or amended) or its

claims presented to the contracting officer, that Dominion was entitled to an

equitable adjustment for increased costs of performance based on the partial

termination of the Utility Services Contract, specifically CLIN 7 Fort

Monroe. See FAR 52.249-2(l). Plaintiff claims $13 million for metering,

20

lighting, and distribution costs, this time as relief for increased costs of

performance. In its cross-motion and response, defendant moved for the

court to dismiss this claim, because plaintiff did not raise a claim for

equitable adjustment before the contracting officer nor in its complaints.

As an initial matter, plaintiff did not move to amend its complaint to

raise this distinct claim prior to summary judgment. The court will not

consider a claimed raised after ample time to amend the complaint and when

defendant did not have an opportunity to prepare for the claim during

discovery. Moreover, plaintiff did not submit a claim to the contracting

officer for an equitable adjustment for increased costs of performance due to

a partial termination under FAR 52.249-2(l). The court lacks jurisdiction to

entertain a claim for costs that plaintiff did not raise to the contracting officer.

41 U.S.C. §§ 7101-09, 7103 (2018). Plaintiff’s theory is new, as is the

category of relief it seeks and the operative facts relating to costs increasing

under the other two contract line items. See K-Con Bldg. Sys., Inc. v. United

States, 778 F.3d 1000, 1005 (Fed. Cir. 2015). Thus, plaintiff’s new claim

must be dismissed for lack of jurisdiction.

CONCLUSION

In sum, we deny plaintiff’s motion for summary judgment on Counts

I, II, and IV. We grant the government’s cross-motion for summary judgment

on Counts I, II, and IV. We also grant the government’s motion for summary

judgment on Count III and deny plaintiff’s untimely request for summary

judgment on that count. We dismiss the equitable adjustment claim, to the

extent it can be characterized as such, raised in plaintiff’s motion for

summary judgment. The Clerk is directed to enter judgment for defendant.

No costs.

s/Eric G. Bruggink

ERIC G. BRUGGINK

Senior Judge

21